Girard Siding Environmental Assessment (EA) Public Meeting. May 23, 2013

Similar documents
Girard Siding Environmental Assessment (EA) Public Meeting. May 23, 2013

Road Intersections Near Level Crossings: Intersection Awareness in Illinois. Brian Vercruysse Illinois Commerce Commission

Fox River Grove, 20 Years Later. Brian Vercruysse, PE November 3, 2015 Arlington, TX

A. INTRODUCTION B. PRINCIPAL CONCLUSIONS AND IMPACTS C. METHODOLOGY

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

The Piedmont Corridor

Rail Division Update. Presented to Joint Appropriations Subcommittee on Transportation. Paul C. Worley, CPM Rail Division Director February 28, 2013

The Blue Line Extension

Electrification - Infrastructure Construction activities in Segment 2:

Midwest Interstate Passenger Rail Commission Briefing: Development of the Midwest s Regional Intercity Passenger Rail Network

North Metro Corridor Draft Environmental Impact Statement (DEIS) Public Hearings. December 9 & 10, 2009

Positive Train Control (PTC) Implementation on A-train Commuter Rail. Updated July 31, 2018

Meeting attendees are now required to go through security screenings upon entering the building. Please allow for extra time.

Feasibility Study Downtown Moorhead Railroad Grade Separation Moorhead, Minnesota July 2008

U.S. System Summary: OHIO HUB

S-03-SegB: South Federal Way to Fife LRT

OVERVIEW: POSITIVE TRAIN CONTROL (PTC) December 2017

Project Overview/Update: Advanced Signal System CBOSS PTC

# 7. Date of Meeting: March 13, 2018 BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM SUBJECT:

GDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010

Subject YRRTC Accomplishments and Highlights

Mountain Corridor Incident Management Program

Appendix D Supportive Transportation Materials

OVERVIEW: POSITIVE TRAIN CONTROL (PTC) June 2018

Managing DC Work Zones: DDOT s Citywide Transportation Management Plan

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

THE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9

The Maryland Transit Administration. A Plan to Connect Baltimore

Click to edit Master title style Click to edit Master title style

DOWNTOWN TUNNEL / MIDTOWN TUNNEL / MLK EXTENSION PROJECT PROCUREMENT PROCESS

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

Provo-Orem Bus Rapid Transit

Northern Virginia Transportation Authority

Railroad-DOT Mitigation Strategies (R16) An Overview. March 2016

Community Advisory Committee. June 5, 2017

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

TRANSPORTATION DEPARTMENT Business Plan

Master Plan for the Port of New York and New Jersey: A Road Map for the Next 30 Years

Dulles Area Transportation Association

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS

Illinois Tollway Diversity Advisory Council. Gustavo Giraldo, Chief of the Department of Diversity and Strategic Development April 12, 2017

South Central ROP Projects

Report to the HDC JPA

PUBLIC WORKS ORGANIZATIONAL CHART

Corridor Management Committee. December 17, 2014

Corridor Management Committee. January 12, 2017

CONNECTING AND TRANSFORMING CALIFORNIA. Frank Vacca, Chief of Rail Operations UNLV Symposium October 17, 2018 Las Vegas, Nevada

Infrastructure Investment, Land Use and Economic Development in the Southern Suburbs

MOTION NO. M Agreement with the Microsoft Corporation and the City of Redmond for the Overlake Transit Center within the East Link Extension

GSA Renewable Energy Purchasing Update

Oregon House Transportation & Economic Development Committee

BOARD OF SUPERVISORS 2017 TRANSPORTATION SUMMIT INFORMATION ITEM

MARTA BOARD OF DIRECTORS OCTOBER 4, 2018

Community Update. May 31, 2011

C Line Rapid Bus 90% Design

Transportation Demand Management: The Mississauga Experience Lorenzo Mele TDM Coordinator

our vision our mission BE A SOLUTION-DRIVEN ADVISOR WITH OUTSTANDING EXPERTISE. ALWAYS BE THE FIRST CHOICE FOR CLIENTS, PARTNERS AND EMPLOYEES.

Downtown Boise Multimodal Center

SECTION 106 ACTIVITIES ANNUAL REPORT

USA: INFRASTRUCTURES DAY

High Speed Rail Update

South Central Pennsylvania Regional Operations Plan Candidate Project Listing (DRAFT)

ROADWAY LIGHTING CURFEW

Corridor Management Committee. January 14, 2016

CHAPTER 6 REFERENCES

2018 State and Federal Legislative Program

Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Inside Southern part of 3rd Street Tunnel

Connecticut Department of Department of Administrative Services and the Broadband Technology Opportunity Program (BTOP) 8/20/2012 1

Station Location Feasibility Study

PREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT

Rural Intersection Collision Avoidance System (RICAS)

The Final Rule on Work Zone Safety and Mobility

STUDY REPORT #1 ADDENDUM

Connected & Automated Vehicle Activities

MEP: A National Resource for Connecting & Assisting Small U.S. Manufacturers with Viable Business Opportunities

Federal Government. Each fiscal year the Federal Government is challenged CATEGORY MANAGEMENT IN THE WHAT IS CATEGORY MANAGEMENT?

Stakeholder Engagement Summary Report

Canada s Atlantic Gateway and Trade Corridor

Johnson City Regional ITS Architecture Update Review Workshop. March 12, 2015

Distracted Work. Kentucky Crushed Stone Association - Annual Safety & Education Seminar February Robert Jameson, Central Mine Services, Inc.

10.1 BIBLIOGRAPHY Noise and Vibration Study Yard and

EXTENDING RED/PURPLE LINE REVENUE SERVICE TO EAST SIDE OF DOWNTOWN LOS ANGELES/ARTS DISTRICT

Work Type Definition

Upgrading Traffic Signals to Enable a Connected Vehicle Test Bed Somerville, Massachusetts

NCTCOG MTP Policy Bundle Application for TXDOT

NOVEMBER department of transportation CONNECTICUT DEPARTMENT OF TRANSPORTATION. Statewide Computerized Traffic Signal Systems Needs Assessment

DESIGN CRITERIA MEMORANDUM

Where are we with C-ITS today? Joint CIMEC/CODECS City Pool workshop Barcelona, 14 November 2016

Community Update. June 8, 2011

Dedicated Short Range Communication: What, Why and How?

GATEWAY PROGRAM OVERVIEW AND UPDATE

Next Steps. Investing in the Future of. MASTER DEVELOPER PROCUREMENT OVERVIEW October 2016 July Chicago Union Station Chicago Union Station

GTA West Corridor Review

Opportunity Corridor-Section 3 Stakeholders Meeting. The Kokosing DBT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

Addison, Irving Park, Montrose, and Damen Stations Community Meeting

Community Update. June 21, 2011

Model State Driver Distraction Plan. Ford Motor Company

The Missouri Department of Transportation, in cooperation with its regional partners Illinois Department of Transportation, Metro and East West

Transcription:

Girard Siding Environmental Assessment (EA) Public Meeting May 23, 2013 1

Agenda» Program Overview» Girard Siding Project EA» Auburn to Shipman Track Improvement Project» Public Involvement Opportunities 2

Illinois High-Speed Rail Chicago to St. Louis: Program Overview 3

Program Objectives The overall purpose of this project is to enhance the passenger transportation network within the Chicago to St. Louis corridor, resulting in a more balanced use of the modal components, reduced travel time, increased service reliability, and enhanced safety. 4

Project Location 5

Who s Involved? Elected Officials Regional Agencies Transportation Providers Business Community General Public & Interest Groups City/County Technical Staff Project Partners Illinois Department of Transportation (IDOT) Federal Railroad Administration (FRA) Union Pacific Railroad (UPRR) Amtrak Illinois Commerce Commission (ICC) Others Support Parsons Brinckerhoff - Program Manager IDOT Consultants (PTB Advertisements) including Parsons Corp. for Tier 2 EIS UPRR Contractors/Consultants 6

Overall Project Tasks» Design and construction of main track, including concrete ties, welded rail, etc.» Realignment of curves» New second tracks and sidings» Grade crossing warning devices» Construction of non-complex grade crossings» Train control signaling (PTC)» Turnouts, culverts, bridges, fencing, etc. 7

Construction Accomplishments» Since 2010, activities have included the: o Installation of 237 track miles of new rail o Installation of 619,813 new concrete ties o Spreading of 1,252,129 tons of stone ballast o Initial renewal of 235 crossing surfaces and approaches 8

Construction Accomplishments» Significant Grade Crossing Upgrades: o Completed diagnostics at 270 locations o Extensive liaison with IDOT Highways, locals, ICC, FRA, others o Extensive safety features and physical upgrades 9

Benefits» Safety» New Passenger Cars and Locomotives» New Stations» Environmental» Service and Reliability 10

Safety Improvements» Four-quad vehicle gates» Pedestrian gate crossings» Improved road crossings» Signage» Fencing 11

Project Schedule 12

Current Program Budget: $1.45 Billion» Track & Structures $726.3 million» Real Estate $ 16.3 million» Stations $ 40.0 million» Rolling Stock / Equipment $211.0 million» Signaling & Communications $183.9 million» Miscellaneous $ 61.6 million (Grade Crossing Approaches, Overhead Bridges, Fencing, etc)» Professional Services $211.4 million (Program Management, Environmental / Design, Construction Oversight) Total: $1.45 billion Note: This summary does not include the Tier 1 Environmental Impact Statement (EIS), Joliet Multi-modal Station, or other individual projects 13

110 MPH Service» October 19 th High Speed Demonstration Run» Public Operation of Higher-Speed Service between Dwight and Pontiac o Began November 22, 2012 o Three northbound (300, 302, and 304) and three southbound (301, 305, and 307) trains 14

Rail Car Procurement» Rail Car Procurement o Joint effort between California, Illinois, Michigan, and Missouri Led by Caltrans Competitive bid for 130 cars o Awarded in November 2012 to Nippon Sharyo, USA Facilities located in Rochelle, IL Will utilize Buy American Program 15

Girard Siding Project Environmental Assessment 16

Project Location» Girard Siding Project area follows the existing UPRR corridor o Begins in Virden, IL and ends in Nilwood, IL 17

Alternatives Evaluated» The Environmental Assessment evaluates both a No-Build and a Build Alternative.» The No-Build Alternative: o Includes a continuation of existing single track between Virden and Nilwood o Unable to accommodate high-speed rail traveling at 110 mph o Unable to provide operating flexibility for the growing rail freight traffic 18

Alternatives Evaluated» The Build Alterative: o Constructs a new 8.7 mile long siding track o Installs new signal equipment and switches o Installs new crossing gates o Allows for high-speed rail service» The Build Alternative is integral element of the overall upgrades between Chicago and St. Louis 19

Auburn to Shipman Track Improvement Project 20

Auburn to Shipman Track Improvements» Provide 27 miles of track upgrades» Install new turnouts» Reconstruct the Carlinville siding» Install new signals, rail and concrete ties 21

Additional Nearby Improvements 22

Proposed Station Improvements» Carlinville Station o Proposed site near the current facility o Plans in the conceptual design phase» Environmental Documentation o Categorical Exclusion (CE) Reevaluation of 2004 Record of Decision (ROD) Study began in March 2013 Anticipated Completion Fall 2013 23

Fencing» Railroad right-of-way (ROW) fencing: o Will be added within urban areas, select rural areas, and within 150 feet of all pedestrian crossing gate locations o Will serve as an added safety measure o Will be placed within one foot inside the Union Pacific Railroad ROW o Will be maintained by UPRR 24

Fencing» Fencing material types will be previewed with the local communities along the corridor. o Ornamental fencing will be used within urban areas. o Chain-link fencing will be used in locations adjacent to the railroad outside of an urban area. 25

ICC Safety Briefing 26

Public Safety in High Speed Rail Corridors CHICAGO-ST. LOUIS HSR CORRIDOR Michael E. Stead Rail Safety Section Illinois Commerce Commission

Public Safety Must Be the #1 Priority

Public Safety in High Speed Rail Corridors Train Speeds will Increase Current Max. Train Speed = 79 mph Proposed Max. Train Speed = 110 mph Crossing Warning Times will Increase Current warning times = 35 seconds Warning times for max. speed trains: 80 seconds min. Train Volumes Projected To Increase Passenger Freight More Trains = Greater Exposure

Longer Warning Times NOT Longer Delays

Any time is Train Time..

94% of All Crashes are Driver Error

25% of Crashes Involve Driving into the Side of a Train

75% of Those Crashes Occur During Daylight Hours

Speed of an Approaching Train (Optical Illusion) Slow moving Freight Train at 10 MPH Amtrak Train traveling at up to 110 MPH

Flashing Red Lights Mean Stop (You may not see an approaching train)

Public Safety in High Speed Rail Corridors Considerations Public Crossings Private Crossings Field Crossings Pedestrian Crossings Trespassers

Public Safety in High Speed Rail Corridors Proposed Safety Improvements Four Quadrant Roadway Gates Pedestrian Gates Right-of-Way Fencing Automatic Warning Devices - Private Xings User-Activated Devices - Farm Xing

Four Quadrant Gates

Pedestrian Crossings

Pedestrian Crossings (Safe Access) Pedestrian Xing with R.O.W. Access Pedestrian Xing with Restricted R.O.W. Access

Trespassers (Restrict Access to RR R.O.W.)

Trespassers (Worn paths indicate dangerous and illegal access to crossing or walking along RR tracks)

Trespassing is the #1 reason for railrelated fatalities or injuries

Trespassers It is illegal for any person to walk across or along railroad tracks at any place other than an authorized crossing.

Field Crossings (Safe Access) Field Crossing w/o Active Warning Devices Field Crossing with User Activated Devices

Farm Equipment

Railroad Safety Outreach & Education Chip Pew Railroad Safety Specialist Illinois Commerce Commission

Public Safety Outreach

Public Safety Outreach

Chip Pew (312) 636 3034 cpew@icc.illinois.gov

Public Involvement Opportunities 53

Public Involvement Opportunities Stakeholder Outreach Public Meetings & Hearings Stakeholder Meetings/Briefings Small Group Meetings Media Outreach Fact Sheets/Newsletters Project Website: www.idothsr.org Project Hotline: 1-855-IDOT-HSR 54

Business Opportunities» Visit the Doing Business section of www.idothsr.org. o Find details about the bidding process and current business opportunities o Find related links for detailed procedures 55

Additional High-Speed Rail Information» Visit www.idothsr.org for project specific information, business opportunities, and to comment on the Illinois High-Speed Rail Project» Visit the Facebook Page: www.facebook.com/illinoishighspeedrail» Call the Project Hotline: 1-855-IDOT-HSR (436-8477) 56

Illinois Commerce Commission Michael E. Stead Rail Safety Program Administrator Illinois Commerce Commission 527 E. Capitol Avenue Springfield, IL 62701 (217) 557-1285 mstead@icc.illinois.gov 57

QUESTIONS 58

THANK YOU 59