1 Transmission Relay Loadability FERC Order 733 Project NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

2 Project Overview 2 Standards Involved PRC Transmission Relay Loadability Applicable Entities Affected Functional Entities with Load-Responsive Phase Protection ti Systems: Transmission Owners Generator Owners Distribution Providers Planning Coordinators

3 Project Overview 3 Applicable Facilities Affected Transmission lines operated at 200 kv and above Transmission lines operated at 100 kv to 200 kv as determined by the Planning Coordinator Transmission lines operated below 100 kv identified as critical facilities by the Regional Entity and as determined by the Planning Coordinator

4 Project Overview 4 Applicable Facilities Affected (cont d) Transformers with low voltage terminals connected at 200 kv and above Transformers with low voltage terminals connected at 100 kv to 200 kv as determined by the Planning Coordinator Transformers with low voltage terminals identified as critical i facilities i by the Regional Entity and as determined by the Planning Coordinator

5 Project Overview 5 Scope On March 18, 2010, FERC issued Order No. 733 which approved Reliability Standard PRC Transmission Relay Loadability, and also directed NERC to develop certain modifications to the PRC standard through its Reliability Standards development process. PRC is the first step toward satisfying Order 733.

6 Project Schedule to Completion 6 Second draft of PRC standard posted on November 1, 2010 for a 45-day formal comment period with concurrent ballot during the last 10 days of the comment period Comments and Ballot Results Close on December 16, 2010 Respond to Comments and Post Third Draft for Comment in January 2011 Conduct Recirculation Ballot in February 2011 Ballot Completion Anticipated in February 2011 Expected NERC Board of Trustees Approval in February 2011 Submit to FERC for Approval in March 2011

7 PRC Summary Key Changes to Requirements 7 R1 Modified criterion 10 (transformer loadability) to address paragraph 203 of Order 733 New R2 to address out-of-step blocking issues from paragraph 244 New R4 to require that entities provide a list of facilities using 15- minute ratings to PC, TOP, and RC per paragraph 186. New R5 to require that entities using criterion 12 (set relays to protect lines and determine loadability from settings) provide a list of such facilities to Regional Entity per paragraph 224. Modified old R3 (now R6) to use Attachment B criteria New R7 to provide for systemic implementation of standard for facilities determined per R6

8 PRC Change to R1, Criterion 10 8 Relay Loadability for Transformers Previously required load responsive relays to generally meet R1 Order 733, paragraph 203 directed modification to verify the equipment is capable of sustaining the overload Two components to transformer withstand capability (IEEE C37.91 and IEEE C57.102) Thermal defined for currents over 2 x rating, times up to 30 minutes Mechanical based only on impedance times from 2 seconds to eight seconds Requirement modified to require that the transformer fault protection address the mechanical withstand characteristic

9 PRC R1 Criterion 10 Change 9 Transformer withstand per IEEE C37.91 and C Thermal withstand curve Provide for operator response If protection is desired, apply devices designed for that purpose, with appropriate timing response Mechanical Withstand curve Addressed within standard

10 PRC New R2 (Out-of-Step Blocking -OSB) 10 Attachment A previously specified that OSB needed to be considered If OSB is asserted by load conditions when a fault occurs, it will prevent fault protection from operating Order 733, paragraph 244 directed that OSB be added as an additional requirement shall verify that its out-of-step of blocking elements allow tripping for faults that occur during the loading conditions used per R1.

11 PRC New R4 List of Facilities Using 15-Minute Rating 11 R1, criterion 2 provides a smaller margin if entities are using a 15-minute rating Clarified in footnote 2 to address 15-minute ratings used for system operations Commits entities to 15-minute response to impending ratings violations Order 733, paragraph 186 directed that entities by required to provide a list of such facilities to TOPs. R4 requires that the list be provided annually to the TOPs, and adds Planning Coordinator and Reliability Coordinator to list

12 PRC New R5 List of Facilities using R1 Criterion R1 criterion 12 provides that entities shall set their relays to protect their facilities and develop an associated rating if they are unable to apply any other criteria Order 733,,paragraph p 244 directs that the list of facilities using criterion 12 be available to users, owners, and operators of the BPS R5 requires that the list be provided annually to the Regional Entity

13 PRC R6 Use Attachment B Criteria 13 Previous R3 required that Planning Coordinators have a process to determine facilities critical to the reliability of BES, maintain a list of such facilities, and provide the list Order 733 directs that NERC develop the criteria R6 now requires that the Planning Coordinators apply ppy the criteria annually to kv facilities and to sub- 100 kv facilities identified as critical facilities in the Regional Entity Compliance Registry If Attachment B Criterion B4 is used, include the year studied Provide the list of identified facilities to all RE, RC, TO, GO, and DP within ihi its Planning Coordinator area within ihi 30d days

14 PRC New R7 Systemic Implementation for sub-200 kv Facilities 14 PRC provided for ongoing implementation for sub-200 kv facilities (per old R3) within Implementation Plan Not an effective approach Implementation Plan is only for initial implementation of new Standard, not for ongoing compliance New R7 to require that TO, GO, and DP implement R1, R2, R3, R4, and R5 for facilities identified per R6 within 24 months

15 Modifications to Attachment A 15 Order No directed modifications to Attachment t A to include supervising i relay elements The Order specifically discussed concerns with pilot wire and current differential protection systems supervised by fault detector relays A new Section 1.6 in Appendix A was added to address this concern The proposed revision makes PRC applicable to the following protective functions: Supervisory elements associated with current-based, communication-assisted schemes where the scheme is capable of tripping for loss of communications

16 Addition of a New Attachment B 16 Order No directed inclusion of a test that Planning Coordinators must use to determine whether a sub-200 kv facility is critical to reliability of the Bulk- Power System The Applicability Test contained in Attachment B will be used by Planning Coordinators to determine which sub- 200 kv transmission Elements must comply with this standard The test will be applied to: All facilities 100 kv to 200 kv Facilities below 100 kv identified by the Regional Entity as y g y critical facilities for the purposes of the Compliance Registry

17 Circuit must comply with the standard if any of the following criteria apply: ppy 17 Monitored Elements of: A flowgate in the Eastern Interconnection, A major transfer path within the Western Interconnection as defined by the Regional Entity, or A comparable monitored Element in the Texas Interconnection or Québec Interconnection, that have been included to address long-term reliability concerns, as confirmed by the applicable Planning Coordinator. Monitored Elements of an IROL where the IROL was determined in the long-term planning horizon Circuits that form a path (as agreed to by the plant owner and the Transmission Entity) to supply off-site power to nuclear plants

18 Circuit must comply with the standard if any of the following criteria apply: ppy (cont.) 18 Circuits identified through defined power flow analysis: Simulation of double contingency combinations selected by engineering judgment in TPL-003 Category C3, but without manual system adjustments between contingencies Evaluation of the post-contingency loading of 100 kv to 200 kv circuits to identify circuits loaded greater than a specified percentage above the Facility Rating nearest a four-hour duration 115% of the Facility Rating, if based on a loading duration of up to and including four hours 120 % of the Facility Rating, if based on a loading duration greater than four and up to and including eight hours 130% of the Facility Rating, if based on a loading duration of greater than eight hours Radial circuits serving only load are excluded. Circuits that the Planning Coordinator may include based on Circuits that the Planning Coordinator may include based on other technical studies or assessments

19 Implementation Plan 19 The Implementation Plan for the revised standard provides varying amounts of time based on the nature of each Requirement Footnote 1 pertaining to Temporary Exceptions approved prior to approval of PRC has been removed as directed in 284 This has no impact on applicable entities because the Temporary Exceptions have expired The latest due date for mitigation of temporary exceptions under the Beyond Zone 3 review was December 31, 2008

20 Implementation Plan (cont.) 20 Facility owners 1 must comply with existing criteria in R1 upon approval, 2 and Must comply with the addition to criterion 10 pertaining to transformer fault protection within 12 months, 2 and Protective ti functions described d in the new section 1.6 of Attachment A must comply with R1 within 24 months 2 Facility owners 1 must comply with R2 and R3 upon approval 2 R2 already is enforceable as section 2 of Attachment A in PRC R3 already is enforceable as R2 in PRC Transmission Owners, Generator Owners, and Distribution Providers as described in the Applicability section of PRC Measured from the first day of the first calendar quarter after applicable regulatory approvals or in those jurisdictions where regulatory approval is not required, the first day of the first calendar quarter after Board of Trustees adoption

21 Implementation Plan (cont.) 21 Facility owners 1 must comply with R4 and R5 within 6 months 2 Planning Coordinators comply with R6 (apply the criteria in Attachment B) within 18 months 2 Requirement R7 is effective upon approval; 2 however, R7 provides facility owners 1 at least 24 months to meet R1 R5 following notification by the Planning Coordinator that a sub-200 kv Facility must comply with this standard 1 Transmission Owners, Generator Owners, and Distribution Providers as described in the Applicability section of PRC Measured from the first day of the first calendar quarter after applicable regulatory 2 Measured from the first day of the first calendar quarter after applicable regulatory approvals or in those jurisdictions where regulatory approval is not required, the first day of the first calendar quarter after Board of Trustees adoption

22 Summary 22 Overview of Key Changes to PRC to Satisfy Directives in FERC Order 733 PRC Posted for Formal Comment with Concurrent Ballot Close on December 16, 2010 Webinar Provided as Outreach to Industry Target Submittal to NERC BOT in February 2011 Submit to FERC for Approval in March 2011 Implementation Plan provides varying amounts of ftime based on the nature of each hrequirement

23 Information Link Transmission Relay Loadability, Project Information Link to NERC Website Charles Rogers, SDT Chair, Affiliation Phil Tatro, SME & Advisor, NERC Staff Joe Bucciero, NERC Project Coordinator com 13 23

24 24? Questions and Answers

25 Closing and Adjourn 25 Register for the Ballot Pool Provide Constructive Comments Offer alternative language where possible Thank you.

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ]

136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ] 136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Parts 39.10 and 40 [Docket No. RM11-16-000] Transmission Relay Loadability Reliability Standard (September 15, 2011)

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project ) Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval. Introduction 1. Title: IROL and SOL Mitigation in the ERCOT Region 2. Number: IRO-006-TRE-1 3. Purpose: To provide and execute transmission loading relief procedures that can be used to mitigate SOL or

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

CIP Standards Development Overview

CIP Standards Development Overview CIP Standards Development Overview CSSDTO706 Meeting with FERC Technical Staff July 28, 2011 Objectives Historical Timeline CIP-002-4 CIP-005-4 CIP Version 5 2 Project 2008-06 Overview FERC Order 706 SDT

More information

CIP Cyber Security Configuration Change Management and Vulnerability Assessments

CIP Cyber Security Configuration Change Management and Vulnerability Assessments Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standards Development Update

Standards Development Update Standards Development Update Steven Noess, Director of Standards Development FRCC Reliability Performance Industry Outreach Workshop September 20, 2017 Supply Chain Risk Management 1 Cyber Security Supply

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

ERO Enterprise Strategic Planning Redesign

ERO Enterprise Strategic Planning Redesign ERO Enterprise Strategic Planning Redesign Mark Lauby, Senior Vice President and Chief Reliability Officer Member Representatives Committee Meeting February 10, 2016 Strategic Planning Redesign Current

More information

Standard COM Communication and Coordination

Standard COM Communication and Coordination A. Introduction 1. Title: Communication and Coordination 2. Number: COM-002-3 3. Purpose: To ensure Emergency communications between operating personnel are effective. 4. Applicability 4.1. Reliability

More information

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia Page 1 of 15 British Columbia Utilities Reliability Standards with s adopted in British Columbia BAL-001-2 Standard Real Power Balancing Control Performance R-14-16 July 1, 2016 BAL-002-1 1 Disturbance

More information

Implementation Plan for COM-001-2

Implementation Plan for COM-001-2 Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.

More information

Standard CIP 007 3a Cyber Security Systems Security Management

Standard CIP 007 3a Cyber Security Systems Security Management A. Introduction 1. Title: Cyber Security Systems Security Management 2. Number: CIP-007-3a 3. Purpose: Standard CIP-007-3 requires Responsible Entities to define methods, processes, and procedures for

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

This draft standard is being posted for an initial comment and ballot. The draft includes modifications to meet the directives of FERC Order No. 791.

This draft standard is being posted for an initial comment and ballot. The draft includes modifications to meet the directives of FERC Order No. 791. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standard CIP 005 4a Cyber Security Electronic Security Perimeter(s)

Standard CIP 005 4a Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-4a 3. Purpose: Standard CIP-005-4a requires the identification and protection of the Electronic Security Perimeter(s)

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Standard CIP Cyber Security Security Management Controls

Standard CIP Cyber Security Security Management Controls A. Introduction 1. Title: Cyber Security Security Management Controls 2. Number: CIP-003-4 3. Purpose: Standard CIP-003-4 requires that Responsible Entities have minimum security management controls in

More information

Draft CIP Standards Version 5

Draft CIP Standards Version 5 Draft CIP Standards Version 5 Technical Webinar Part 1 Project 2008-06 Cyber Security Order 706 Standards Drafting Team November 15, 2011 Agenda Opening Remarks John Lim, Consolidated Edison, Chair V5

More information

Standard CIP 007 4a Cyber Security Systems Security Management

Standard CIP 007 4a Cyber Security Systems Security Management A. Introduction 1. Title: Cyber Security Systems Security Management 2. Number: CIP-007-4a 3. Purpose: Standard CIP-007-4 requires Responsible Entities to define methods, processes, and procedures for

More information

primary Control Center, for the exchange of Real-time data with its Balancing

primary Control Center, for the exchange of Real-time data with its Balancing A. Introduction 1. Title: Reliability Coordination Monitoring and Analysis 2. Number: IRO-002-5 3. Purpose: To provide System Operators with the capabilities necessary to monitor and analyze data needed

More information

Proposed Clean and Redline for Version 2 Implementation Plan

Proposed Clean and Redline for Version 2 Implementation Plan Exhibit A Implementation Plans for CIP-002-2 through CIP-009-2 and CIP-002-3 and CIP-009-3 For Generator Owners and Generator Operators of U.S. Nuclear Power Plants Proposed Clean and Redline for Version

More information

DRAFT Reliability Standard Audit Worksheet 1

DRAFT Reliability Standard Audit Worksheet 1 DRAFT Reliability Standard Audit Worksheet 1 PRC-025-2 Generator Relay Loadability This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR Number: Compliance

More information

CIP Cyber Security Configuration Management and Vulnerability Assessments

CIP Cyber Security Configuration Management and Vulnerability Assessments Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Standard CIP 005 2a Cyber Security Electronic Security Perimeter(s)

Standard CIP 005 2a Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-2a 3. Purpose: Standard CIP-005-2 requires the identification and protection of the Electronic Security Perimeter(s)

More information

A. Introduction. B. Requirements and Measures

A. Introduction. B. Requirements and Measures A. Introduction 1. Title: Communications 2. Number: COM-001-3 3. Purpose: To establish Communication capabilities necessary to maintain reliability. 4. Applicability: 4.1. Functional Entities: 4.1.1. Transmission

More information

CIP Cyber Security Security Management Controls. Standard Development Timeline

CIP Cyber Security Security Management Controls. Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Standard COM-002-2a Communications and Coordination

Standard COM-002-2a Communications and Coordination A. Introduction 1. Title: Communication and Coordination 2. Number: COM-002-2a 3. Purpose: To ensure Balancing Authorities, Transmission Operators, and Generator Operators have adequate communications

More information

Standard CIP-006-3c Cyber Security Physical Security

Standard CIP-006-3c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-3c 3. Purpose: Standard CIP-006-3 is intended to ensure the implementation of a physical security

More information

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities A. Introduction 1. Title: Real-time Reliability Monitoring and Analysis Capabilities 2. Number: TOP-010-1(i) 3. Purpose: Establish requirements for Real-time monitoring and analysis capabilities to support

More information

CIP Cyber Security Incident Reporting and Response Planning

CIP Cyber Security Incident Reporting and Response Planning Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

The North American Electric Reliability Corporation ( NERC ) hereby submits

The North American Electric Reliability Corporation ( NERC ) hereby submits March 3, 2011 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 Re: North American Electric

More information

Project Posting 8 Frequently Asked Questions Guide

Project Posting 8 Frequently Asked Questions Guide Project 2007-02 Posting 8 Frequently Asked Questions Guide General Questions 1. What were the inputs that drove the development of posting 8 of Project 2007-02? The NERC Board of Trustees November 7 th,

More information

Standard Development Timeline

Standard Development Timeline CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

Standard CIP Cyber Security Systems Security Management

Standard CIP Cyber Security Systems Security Management A. Introduction 1. Title: Cyber Security Systems Security Management 2. Number: CIP-007-4 3. Purpose: Standard CIP-007-4 requires Responsible Entities to define methods, processes, and procedures for securing

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

Industry Webinar. Project Single Points of Failure. August 23, 2018

Industry Webinar. Project Single Points of Failure. August 23, 2018 Industry Webinar Project 2015-10 Single Points of Failure August 23, 2018 Agenda Presenters Standard Drafting Team o Chair, Jonathan Hayes, SPP o Vice Chair, Delyn Kilpack, LGE-KU NERC Staff o Latrice

More information

CIP Cyber Security Recovery Plans for BES Cyber Systems

CIP Cyber Security Recovery Plans for BES Cyber Systems Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standard CIP-006-4c Cyber Security Physical Security

Standard CIP-006-4c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-4c 3. Purpose: Standard CIP-006-4c is intended to ensure the implementation of a physical security

More information

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014 Request for Data or Information Protection System Misoperation Data Collection August 14, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 15 Table of

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard CIP Cyber Security Electronic Security Perimeter(s)

Standard CIP Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-2 3. Purpose: Standard CIP-005-2 requires the identification and protection of the Electronic Security Perimeter(s)

More information

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table

More information

Project Retirement of Reliability Standard Requirements

Project Retirement of Reliability Standard Requirements Project 2013-02 Retirement of Reliability Standard Requirements Unofficial Comment Form for Paragraph 81 (P81) Project Retirement of Reliability Standard Requirements This form is provided in a Word format

More information

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1 DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...

More information

Standard CIP 004 3a Cyber Security Personnel and Training

Standard CIP 004 3a Cyber Security Personnel and Training A. Introduction 1. Title: Cyber Security Personnel & Training 2. Number: CIP-004-3a 3. Purpose: Standard CIP-004-3 requires that personnel having authorized cyber or authorized unescorted physical access

More information

CIP Cyber Security Personnel & Training

CIP Cyber Security Personnel & Training A. Introduction 1. Title: Cyber Security Personnel & Training 2. Number: CIP-004-6 3. Purpose: To minimize the risk against compromise that could lead to misoperation or instability in the Bulk Electric

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures.

More information

Standard CIP Cyber Security Incident Reporting and Response Planning

Standard CIP Cyber Security Incident Reporting and Response Planning A. Introduction 1. Title: Cyber Security Incident Reporting and Response Planning 2. Number: CIP-008-4 3. Purpose: Standard CIP-008-4 ensures the identification, classification, response, and reporting

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered

More information

Standard TOP Transmission Operations

Standard TOP Transmission Operations A. Introduction 1. Title: Transmission Operations 2. Number: TOP-001-34 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection

More information

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides

More information

Cyber Security Standards Drafting Team Update

Cyber Security Standards Drafting Team Update Cyber Security Standards Drafting Team Update Michael Assante, VP & Chief Security Officer North American Electric Reliability Corp. February 3, 2008 Overview About NERC Project Background Proposed Modifications

More information

Critical Cyber Asset Identification Security Management Controls

Critical Cyber Asset Identification Security Management Controls Implementation Plan Purpose On January 18, 2008, FERC (or Commission ) issued Order. 706 that approved Version 1 of the Critical Infrastructure Protection Reliability Standards, CIP-002-1 through CIP-009-1.

More information

Standard Development Timeline

Standard Development Timeline CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

Project Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018

Project Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018 Project 2017-01 Modifications to BAL-003-1.1 Frequency Response and Frequency Bias Setting Industry Webinar December 18, 2018 Administrative Items North American Electric Reliability Corporation (NERC)

More information

# Name Duration

# Name Duration 1 Project 2010-07 GOTO 712 days 2 SAR Development and Finalization 243 days 3 Standards Committee Accepts SAR for Posting 17 days 4 Post SAR for Comment 30 edays 5 Post Request for SAR Drafting Team Nominations

More information

Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities

Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities NRECA TechAdvantage March 2014 Patti Metro Manager, Transmission & Reliability Standards NRECA

More information

Summary of FERC Order No. 791

Summary of FERC Order No. 791 Summary of FERC Order No. 791 On November 22, 2013, the Federal Energy Regulatory Commission ( FERC or Commission ) issued Order No. 791 adopting a rule that approved Version 5 of the Critical Infrastructure

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

Standard Development Timeline

Standard Development Timeline CIP-003-67(i) - Cyber Security Security Management Controls Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when

More information

Unofficial Comment Form Project Operating Personnel Communications Protocols COM-002-4

Unofficial Comment Form Project Operating Personnel Communications Protocols COM-002-4 Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Please DO NOT use this form. Please use the electronic comment form to submit comments on the proposed draft COM 002 4 (Operating

More information

CIP Cyber Security Physical Security of BES Cyber Systems

CIP Cyber Security Physical Security of BES Cyber Systems A. Introduction 1. Title: Cyber Security Physical Security of BES Cyber Systems 2. Number: CIP-006-5 3. Purpose: To manage physical access to BES Cyber Systems by specifying a physical security plan in

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-012-1 Cyber Security Communications between Control Centers This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity:

More information

Québec Interconnection Approach to BES

Québec Interconnection Approach to BES Québec Interconnection Approach to BES Placer une photo ici s il y a lieu NPCC Governmental/Regulatory Affairs Advisory Group Sylvain Clermont November 27, 2012 Introduction: HQT Our mission HQT operates

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

1. Post for 45-day comment period and pre-ballot review. 7/26/ Conduct initial ballot. 8/30/2010

1. Post for 45-day comment period and pre-ballot review. 7/26/ Conduct initial ballot. 8/30/2010 Standard CIP 011 1 Cyber Security Protection Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 FAC-003-4 Transmission Vegetation Management. Registered Entity Name: Applicable Function(s): Applicable only for TO and GO Compliance Monitoring Method: RSAW Version:

More information

A. Introduction 1. Title: 2. Number: 3. Purpose: 4. Applicability: 4.1. Functional Entities: Balancing Authority Distribution Provider

A. Introduction 1. Title: 2. Number: 3. Purpose: 4. Applicability: 4.1. Functional Entities: Balancing Authority Distribution Provider The Background, VRF/VSLs, and Guidelines and Technical Basis Sections have been removed for this informal posting. The Project 2016-02 is seeking comments around the concept of the Requirement/Measure

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Cyber Security Supply Chain Risk Management

Cyber Security Supply Chain Risk Management Cyber Security Supply Chain Risk Management JoAnn Murphy, SDT Vice Chair, PJM Interconnection May 31, 2017 FERC Order No. 829 [the Commission directs] that NERC, pursuant to section 215(d)(5) of the FPA,

More information

Unofficial Comment Form Project Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays)

Unofficial Comment Form Project Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays) Project 2007-17.3 Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays) Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the

More information

Unofficial Comment Form

Unofficial Comment Form Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting

More information

CIP Cyber Security Recovery Plans for BES Cyber Systems

CIP Cyber Security Recovery Plans for BES Cyber Systems A. Introduction 1. Title: Cyber Security Recovery Plans for BES Cyber Systems 2. Number: CIP-009-5 3. Purpose: To recover reliability functions performed by BES Cyber Systems by specifying recovery plan

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

NERC and Regional Coordination Update. Operating Committee Preston Walker January 9, 2018

NERC and Regional Coordination Update. Operating Committee Preston Walker January 9, 2018 NERC and Regional Coordination Update Operating Committee Preston Walker January 9, 2018 Standards Project Action End Date Project 2017-07 Standards Alignment with Registration NERC Standards Under Development

More information

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting

More information

Standard Development Timeline

Standard Development Timeline CIP-008-6 Incident Reporting and Response Planning Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

Bulk Electric System Definition Changes and Reporting

Bulk Electric System Definition Changes and Reporting Bulk Electric System Definition Changes and Reporting June 12, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Overview BES Definition Change BES Definition Reference

More information

Consideration of Issues and Directives Federal Energy Regulatory Commission Order No. 791 June 2, 2014

Consideration of Issues and Directives Federal Energy Regulatory Commission Order No. 791 June 2, 2014 Federal Energy Regulatory Commission Order No. 791 June 2, 2014 67 and 76 67. For the reasons discussed below, the Commission concludes that the identify, assess, and correct language, as currently proposed

More information

Misoperations Information Data Analysis System (MIDAS)

Misoperations Information Data Analysis System (MIDAS) Misoperations Information Data Analysis System (MIDAS) End User Guide June 2016 NERC Report Title Report Date I Table of Contents Preface... iii Chapter 1 Reporting Obligations...1 Entities Obligated to

More information

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015 Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered

More information

Standard CIP Cyber Security Physical Security

Standard CIP Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-3 3. Purpose: Standard CIP-006-3 is intended to ensure the implementation of a physical security program

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Meeting Notes Project Modifications to CIP Standards Drafting Team June 28-30, 2016

Meeting Notes Project Modifications to CIP Standards Drafting Team June 28-30, 2016 Meeting Notes Project 2016-02 Modifications to CIP Standards Drafting Team June 28-30, 2016 Exelon Chicago, IL Administrative 1. Introductions / Chair s Remarks The meeting was brought to order by S. Crutchfield

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information