Site Preparation for ClearCube Installation. Rev. F

Size: px
Start display at page:

Download "Site Preparation for ClearCube Installation. Rev. F"

Transcription

1 Site Preparation for ClearCube Installation Rev. F

2 EXECUTIVE SUMMARY Because of the centralized nature of the ClearCube architecture, installation of the system requires a certain degree of site preparation. Proper preparation will result in a rapid installation and long-term trouble-free operation. In some cases, such as installation in pre-existing data centers and/or network closets, this preparation will not require many modifications to the site. In other cases, it may be necessary to convert closets or backrooms to accommodate chassis and blades. This paper will describe the steps required for ensuring all pre-installation activities and site preparation steps are identified. The paper details what environmental conditions need to exist (cooling, power, architectural supports, etc.) for successful installation and why they are necessary. In addition, observations from the field are documented to illustrate areas requiring particular attention during your installation. This paper is a companion document to the ClearCube Site Prep Checklist (found on the ClearCube Support website), which must be completed and signed by the customer s Project Manager and the ClearCube (or Partner) Account Executive to verify that the customer site is ready for installation. The CompleteStart Professional Services Program is available to help customers resolve issues at any time during pre-installation preparation as well as during the installation itself. This service will ensure that installation of the ClearCube Solution is as smooth as possible for the IT staff and transparent to the user. CompleteStart is a comprehensive program covering three vital areas: Pre-installation Readiness, Training and Installation. 2

3 INTRODUCTION The ClearCube solution removes box PCs from the desktop and delivers true centralization of your company s computing assets. Aided by the PC small form factor and the exclusive distance capability, a company can centralize the computers of several hundred users within the secure confines of a data center or other IT space. Alternatively, PC blades can be stored in local communications closets closer to the end users. In any of these scenarios, the site must meet certain minimum requirements prior to installation of ClearCube chassis and blades. These requirements fall under the categories of clearance, load bearing capacity, power delivery and cooling capability. Site preparation is a critical part of the ClearCube installation process. The site must provide adequate clearance for maintenance purposes in the event a blade needs to be changed out or if cabling at the rear of the chassis needs adjustment. Proper cooling and ventilation is required to prevent thermal overload of the blade and chassis electronics. Finally, the site must provide sufficient electrical power for operation of the blades and chassis. The power draw and heat output is highly concentrated and can require expansion of the electrical infrastructure as well as added cooling capacity and/or air flow for smaller data centers. In addition, the ClearCube solution includes enterprise-level management software that unleashes the full potential of the R Series blade architecture. The software requires proper setup and installation, and the customer s Network Administrator must work with ClearCube to determine any conflicts that the software might have with site-specific server or web policies. User Port Chassis with Blades Administrator User Data Center Rack 3

4 SPACE AND CLEARANCE REQUIREMENTS The dense form-factor of ClearCube PC blades allows a high concentration of computing power in a relatively small space, resulting in improved hardware security and manageability than a distributed PC architecture. This concentration of blades and chassis will have an impact on your data center and/or network closet. ClearCube chassis fit into standard 19 racks and/or cabinets and are 29.8 inches deep and 3U in height. ClearCube recommends that the racks (or cabinets) that you choose incorporate cable guides (horizontal or vertical) to organize the power, network, User Port connection and management cables. A full rack of blades ( for dual slot blades) will have the following cable counts (it is important to note that the information below is a guide, as each installation may be different): Chassis Type Power Cables Direct Connect BackPack Blade Switching BackPack R4300 chassis with Administrator Connect Modules R4300 chassis with User Connect Modules R4300 chassis with 8x8 Connect Modules C/Port Cables Single slot blades Dual slot blades Ethernet Cables 1 Single slot blades Dual slot blades Management Cables Management Administration Sparing R1300, R2100 and R2200 blade models contain dual NICs. If both NICs are utilized, the number of Ethernet cables required is doubled. Table 1: Chassis Cabling Requirements In addition, each chassis requires proper airflow to keep the blades cool. At least five inches of space should be maintained behind the rack at all times to ensure adequate ventilation. However, ClearCube recommends maintaining eight inches at all times, giving IT staff members space for cable management and administration. The minimum physical footprint for a rack of ClearCube blades is two feet wide and three feet deep. If you are using a cabinet, the footprint will be dependent on the size of the cabinet (please refer to the cabinet manufacturers specifications for this information). 4

5 During the operational life of the chassis, it will need to be accessed for maintenance purposes from time to time. This may entail opening a cabinet door or other access point, and therefore more space than the minimum footprint is recommended. In any case, personnel must be able to access the rear of the chassis to change cable connections or replace chassis modules this will require at least eight inches of clearance behind the chassis. From the front of the chassis, a technician must be able to open the front bezel and pull out all of the blades this requires two feet of clearance (the length of each blade). You will also need access to the network switch that is connected to each chassis in the event the port settings must be manually adjusted. LOAD BEARING (WEIGHT) REQUIREMENTS Made with strong sheet metal to protect the Blades and modules, one fully loaded chassis weighs approximately 80 pounds. A fully loaded rack of chassis and Blades will weigh approximately 0 lbs, not including the weight of the rack itself. The loading on the floor will be greater than 187 lbs. per square foot. Prior to installation, the customer must verify that the floor will hold this considerable weight raised floors may need additional support under the racks. Customers with smaller installations also must make sure that their floor, table, or other furniture can handle the weight of multiple chassis. In addition to weight concerns, racks and chassis must be in stable positions for proper installation. If the installation site uses a 2-post rack, the chassis must be mounted on the rack at each chassis center of gravity. ClearCube recommends using a 4-post rack or a cabinet with adjustable middle rails, which will add stability by providing support at both ends of the chassis. ClearCube offers a Chassis Rapid Mounting Kit for use with 4-post racks that can improve installations times by a factor of five. Prior to chassis installation, the rack should be secured to both the ceiling and floor to prevent tipping. 5

6 COOLING AND ENVIRONMENTAL REQUIREMENTS Each ClearCube R Series chassis holds up to eight single processor blades or four dual processor workstation blades and their associated hard drives, memory and power supplies. This concentration of electronics generates a significant amount of heat, even when the equipment is not operating at full capacity. While the chassis can exceed 5100 BTU/Hr with all Blades operating at peak power, nominal usage will result in heat rates between 3100 and 3850 BTU/Hr. ClearCube recommends a cooling system designed to remove 3850 BTU/hr of heat. In terms of cooling capacity, every three chassis will require approximately 1.3 tons of additional cooling at the location where they are installed. The acceptable thermal range for operating blades and chassis is from 0 to 35 C (32-95 F). Temperatures outside this range will damage the internal electronic components, regardless of whether the event is a brief spike or a sustained condition. If blade temperatures exceed the acceptable range and components fail, this will void the product warranty. Installation Experiences: While data centers are often well equipped to handle the heat load, other rooms such as telecommunications closets and spare backrooms may need duct work to bring in more ventilation from the central cooling system. Lacking this ventilation, temperatures above 100 F are easily reached, which can cause blades and chassis to prematurely fail. In order to prevent this, a ClearCubecertified Systems Engineer should verify that the installation site has been properly prepared to provide sufficient cooling. Cooling capabilities of the HVAC system will be severely reduced without proper ventilation and airflow through the chassis. In an open rack, chassis require five inches of clearance at the rear of the fans to allow airflow. Care must be taken in organizing cable bundles to not disrupt this airflow, which will necessitate the use of cable ties and guides. For chassis held in cabinets or other enclosures, a fan at the top of the cabinet will be required to ensure hot air does not stagnate in the enclosure. Proper room ventilation ducting is vital to ensuring that air heated by the blades doesn t continuously circulate in the room. Regardless of the cooling system capacity installed, waste heat from the blades should be directly vented to the environment. If waste heat from the blades isn t properly vented, a closed loop circulation system could form leading to excessive room temperatures. This is true even if the installed cooling system has excess cooling capacity because heated, re-circulated air can enter the chassis intakes. In addition to thermal considerations, the blades must be kept in a relatively clean environment. The electronic circuitry on the blades and chassis modules is not protected from airborne contamination by dust or chemicals. Therefore, the chassis must be kept away from areas with high concentrations of contaminants. 6

7 POWER REQUIREMENTS The power draw of a fully populated rack is highly concentrated, making adequate power circuitry vital for proper operation. Each chassis, operating at full power, will draw a maximum current of 12 amps at 120 VAC (6A at 240 VAC) or 1.44 kva. This power draw can be seen during blade boot-up and imaging, when the processors and hard drives are running at full speed. Normal blade operation will result in a current draw in the range of 7-9 amps per chassis at 120 VAC. The chassis power supply is designed to accept A/C voltages between 100 and 240 VAC. Note: there is an inverse relationship between voltage and current. Therefore, if the power system voltage is doubled from 120 VAC to 240 VAC, the current required is halved. For detailed power requirements on various circuit voltages (100V, 120V, 208V and 240V), please refer to the Site Preparation Checklist spreadsheet available at Installation Experiences: Sites other than Data Centers may not have adequate preinstalled power. Customers who intend to place several chassis in telecom closets or other backrooms may need to expand the site power system so that adequate power will be delivered to the chassis. Surge suppression at the desktop is vitally important, as C/Ports can be damaged when an electrical storm disrupts the site s power distribution system. Consult a professional electrician before attempting ANY electrical system modifications! After ensuring that adequate power can be supplied to the chassis, the next site concern is power protection. ClearCube recommends one 15 A (at 120 VAC) circuit breaker to be allocated for each chassis, with another appropriately sized circuit breaker protecting each rack. If a customer uses uninterruptible power supplies, sizing should be based on the requirement to supply 9 A (at 120 VAC) to each chassis for the desired duration. Customers should also make sure that the UPS will pass through enough current to the chassis even while charging. A 3 kva UPS will, at most, support two chassis. Refer to Table 1 below for additional information for minimum UPS sizing. Finally, installation sites will require surge protection for both the chassis in the Data Center as well as the C/Ports at the desktop. Although the C/Ports do not require much power, they can sustain damage from power surges in the electrical system. Table 2: Minimum UPS sizing required for Chassis # of Chassis UPS Size 2 3 kva 3 5 kva 5 8 kva Cabling Infrastructure Each fully loaded chassis will require eight Category 5 cables with RJ-45 connectors for connecting the PC blades to the C/Ports at user s desktops and eight network cables for connecting the PC blades to the Ethernet network switch. These cables are not included with the ClearCube equipment. Short, color-coded Category 5 cables ARE provided with each chassis for sparing, administration and management daisy-chain connections. 7

8 NOTE: the ClearCube Architecture uses all four copper wire pairs for the cable connection between the PC blade and each C/Port. If your installation currently splits out wire pairs for multiple uses, you will need to ensure that a separate, full Category 5 connection is available for each PC blade to C/Port connection. Fiber optic installations require two 62.5 micron, multi-mode fibers connected in a straight-through manner. NETWORK CONSIDERATIONS FOR I/PORT ENVIRONMENTS Customers deploying I/Ports need to ensure their Ethernet infrastructure can support the added network demands imposed by these products. Each I/Port requires a dedicated network switch port for connectivity. This is in addition to the network switch port required for each blade. I/Ports also require sufficient network bandwidth for adequate performance. Depending upon the user s applications this can range from 50 kbps for text-based applications to 1 Mbps for graphically intensive programs. The chart below can help you determine necessary bandwidth that will be required by the users in your organization. Application Typical Sustained Bandwidth Example Applications Environment Required While a User is Active Basic, text-based , notepad 15 Kbits/sec Typical Office Word, Excel, basic web browsing 35 Kbits/sec Graphically intensive Flash animation, PowerPoint 70 Kbits/sec Table 3: I/Port Bandwidth Guidelines Note: Every network environment is unique, so these bandwidth amounts should be used as a guideline, not absolute measures. Certain network conditions may dictate higher bandwidth requirements than those listed above. SOFTWARE PREPARATION AND IT PERSONNEL REQUIREMENTS The ClearCube Management Suite (CMS) is enterprise software that enables customers to realize the full potential of ClearCube s centralized PC blade architecture. The components of CMS require various TCP and UDP ports to be open for reliable communication. Please call ClearCube Technical Support or visit support.clearcube.com to obtain the most current list of network ports used by CMS. These ports cannot be blocked by firewalls or access lists when customers are deploying CMS. In some customer environments, this may require assistance from a group other than the team deploying ClearCube hardware and CMS. Arrangements should be made with the required personnel to complete this work before deploying the ClearCube software. ClearCube Professional Services can assist in customizing the software installation process to help meet customer security requirements and resolve other issues. The ClearCube Management Suite components rely on Java, Perl and Apache Tomcat technologies as prerequisites. Some customer environments include other applications that rely on Java or Tomcat. Administrators should ensure that CMS prerequisite requirement versions do not conflict with prerequisite versions for other applications in the environment. In addition to management software, each managed group of ClearCube chassis must have one chassis with a Remote Management Module (RMM) connected to the network. The RMM is a controller that links a chassis systems management bus to the ClearCube management software via Ethernet. The RMM enables switching functions, logging of chassis events, and permits remote control of an entire rack of chassis, allowing any administrator with Internet access to manage the client blades and chassis remotely. Depending on the RMM version, some will 8

9 require static IP addresses and some can be configured in static or DHCP mode. During installation, the network administrator must assign static IP addresses to the RMMs or ensure that a DHCP server is available for models that support DHCP. This also means each RMM will require a physical network connection. CONCLUSION The ClearCube solution represents a revolutionary step forward in efficient and cost-effective business computing. However, because it does reverse the trend of distributed computational power, installation can present unique challenges. Adherence to the guidelines set out in this paper and summarized in the ClearCube Site Preparation Checklist will ensure a trouble-free installation and subsequent usage. This will result in a positive experience for both the customer s IT department and end-users. ClearCube Professional Services ClearCube has a Professional Services group to assist customers with installation of its equipment, including pre-installation site surveys. ClearCube Professional Services will work with clients to resolve any site or software issues and ensure compliance with installation guidelines. Please contact your ClearCube Account Executive or visit the ClearCube Professional Services home page at for more information. 9

Compaq Ultra-Dense Server Deployment in Telecommunications (Telco) Racks

Compaq Ultra-Dense Server Deployment in Telecommunications (Telco) Racks Guidelines June 2000 Prepared by: Storage Products Group Compaq Computer Corporation Contents Introduction...3 Rack Warnings...4 Telco Rack Option Kit for Compaq ProLiant DL360 Server Installation...5

More information

E-Series Site Preparation Guide

E-Series Site Preparation Guide E-Series Site Preparation Guide September 2017 215-11797_A0 doccomments@netapp.com Table of Contents 3 Contents Deciding whether to use this guide... 10 Specifications of the model 3040 40U cabinet...

More information

Junos WebApp Secure 5.0 Hardware Guide

Junos WebApp Secure 5.0 Hardware Guide Junos WebApp Secure 5.0 Hardware Guide Junos WebApp Secure 5.0 Hardware Guide This document contains a specification for the MWS1000 hardware appliance, as well as instructions for installation into a

More information

APC APPLICATION NOTE #74

APC APPLICATION NOTE #74 #74 Configuration of InfraStruXure for Data Centers to Support Dell PowerEdge 1855 Abstract Many companies are making plans to incorporate Dell PowerEdge Blade Servers into their data center applications.

More information

Installation Job Aid for VSP 4450GTX-HT- PWR+

Installation Job Aid for VSP 4450GTX-HT- PWR+ Installation Job Aid for VSP 4450GTX-HT- PWR+ Notices Release 6.1.0.0 NN46251-305 Issue 02.01 November 2017 Notice paragraphs alert you about issues that require your attention. The following paragraphs

More information

Quick Start. This document describes how to install the Juniper Networks PTX5000 Packet Transport

Quick Start. This document describes how to install the Juniper Networks PTX5000 Packet Transport PTX5000 Packet Transport Router Quick Start September 2017 Part Number: 530-066788 Revision 01 This document describes how to install the Juniper Networks PTX5000 Packet Transport Router. Contents Quick

More information

Installation Job Aid for VSP 4850GTS

Installation Job Aid for VSP 4850GTS Installation Job Aid for VSP 4850GTS Notices Release 6.1.0.0 NN46251-308 Issue 02.01 November 2017 Notice paragraphs alert you about issues that require your attention. The following paragraphs describe

More information

IBM BladeCenter HT ac and dc model chassis accommodates BladeCenter blade servers for telecommunications environments and new options

IBM BladeCenter HT ac and dc model chassis accommodates BladeCenter blade servers for telecommunications environments and new options IBM Europe Announcement ZG07-0187, dated February 13, 2007 IBM BladeCenter HT ac and dc model chassis accommodates BladeCenter blade servers for telecommunications environments and new options Key prerequisites...2

More information

Installing the Cisco MDS 9020 Fabric Switch

Installing the Cisco MDS 9020 Fabric Switch CHAPTER 2 This chapter describes how to install the Cisco MDS 9020 Fabric Switch and its components, and it includes the following information: Pre-Installation, page 2-2 Installing the Switch in a Cabinet

More information

Dell SC7020 Storage Controller Getting Started Guide

Dell SC7020 Storage Controller Getting Started Guide Dell SC7020 Storage Controller Getting Started Guide Regulatory Model: E03T Regulatory Type: E03T001 Notes, Cautions, and Warnings NOTE: A NOTE indicates important information that helps you make better

More information

Installing the ASA 5550

Installing the ASA 5550 CHAPTER 3 Installing the ASA 5550 Caution Read the safety warnings in the Regulatory Compliance and Safety Information for the Cisco ASA 5500 Series and follow proper safety procedures when performing

More information

Installing the IPS 4345 and IPS 4360

Installing the IPS 4345 and IPS 4360 CHAPTER 4 Installing the IPS 4345 and IPS 4360 Contents This chapter describes the Cisco IPS 4345 and the IPS 4360, and includes the following sections: Installation Notes and Caveats, page 4-1 Product

More information

Preparing to Install the VG248

Preparing to Install the VG248 CHAPTER 2 To ensure normal system operation, plan your site configuration and prepare your site before installation. Before installing the VG248, review these sections: Preparing the Installation Site,

More information

Installation Job Aid for Ethernet Routing Switch 3600 Series

Installation Job Aid for Ethernet Routing Switch 3600 Series Installation Job Aid for Ethernet Routing Switch 3600 Series Notices NN47213-303 Issue 03.01 November 2017 Notice paragraphs alert you about issues that require your attention. Following are descriptions

More information

Dell MD1280 Storage Enclosure Getting Started Guide

Dell MD1280 Storage Enclosure Getting Started Guide Dell MD1280 Storage Enclosure Getting Started Guide Regulatory Model: SP-2584, E11J Notes, Cautions, and Warnings NOTE: A NOTE indicates important information that helps you make better use of your computer.

More information

NOTE: All facility requirements must be met before 3D Systems Customer Support can schedule a trip to your facility to install the printer.

NOTE: All facility requirements must be met before 3D Systems Customer Support can schedule a trip to your facility to install the printer. Facility Guidelines This section provides details relating to site selection, site preparation and readiness of the facility to accept and install the ProJet Professional Printing System. Discuss appropriate

More information

Server Rack Cabinet Compatibility Guide

Server Rack Cabinet Compatibility Guide Server Rack Cabinet Compatibility Guide Revision 2.4 September 2005 A Guide to the Selection and Evaluation of Server Rack Cabinets for Compatibility and Use with Intel Server Chassis Disclaimer THE INFORMATION

More information

PACSystems RX7i IC698CHS009/119

PACSystems RX7i IC698CHS009/119 January 2010 The RX7i rack can be used for all RX7i CPU and I/O configurations, Series 90-70 I/O, and VME modules. Backplane connectors are spaced on 0.8" (20.3mm) centers to accommodate single-width RX7i

More information

This manual describes how to prepare a site for the CTL 9712 DPS 7000 Integrated Library Unit (ILU).

This manual describes how to prepare a site for the CTL 9712 DPS 7000 Integrated Library Unit (ILU). January 1997 7 Preface PURPOSE OF THIS MANUAL This manual describes how to prepare a site for the CTL 9712 DPS 7000 Integrated Library Unit (ILU). It gives the specific site requirements for the following

More information

3 Uninterruptible Power Systems

3 Uninterruptible Power Systems S5K Modular Series Uninterruptible Power Systems (UPS) This easily upgraded and flexible UPS provides the protection you want, when you need it. The 5K Modular is scalable from 4 to 20 kva, offering many

More information

Prisma II Platform. Optoelectronics

Prisma II Platform. Optoelectronics Optoelectronics Prisma II Platform Description In optical transmission systems, the network platform forms the foundation of the product family. The Prisma II platform provides network operators with the

More information

Uninterruptible Power Systems

Uninterruptible Power Systems Uninterruptible Power s 2 S5K Modular Series On-Line Uninterruptible Power s (UPS) The 5K Modular is scalable from 4 to 20 kva, offering many flexible options by adding a few standard modules. Designed

More information

Z8 G4 Site Prep Guide Table of contents

Z8 G4 Site Prep Guide Table of contents Z8 G4 Site Prep Guide Table of contents Introduction... 2 Power consumption and cooling considerations... 2 Power consumption limitations... 2 Uninterruptible power supply (UPS)... 3 Power consumption

More information

Installing the Cisco AS5400XM Universal Gateway

Installing the Cisco AS5400XM Universal Gateway CHAPTER 3 Installing the Cisco AS5400XM Universal Gateway This chapter guides you through the installation of the Cisco AS5400XM universal gateway and includes the following sections: Setting Up the Chassis,

More information

Power and Cooling for Ultra-High Density Racks and Blade Servers

Power and Cooling for Ultra-High Density Racks and Blade Servers Power and Cooling for Ultra-High Density Racks and Blade Servers APC White Paper #46 Richard L. Sawyer Director of Data Center Technology American Power Conversion Company 2005 APC corporation What has

More information

350 East Plumeria Drive San Jose, CA USA May

350 East Plumeria Drive San Jose, CA USA May Installation Guide 350 East Plumeria Drive San Jose, CA 95134 USA May 2012 201-15135-02 NETGEAR, Inc. All rights reserved. No part of this publication may be reproduced, transmitted, transcribed, stored

More information

APC by Schneider Electric Solutions for Cisco Unified Computing System (UCS) Blade Applications

APC by Schneider Electric Solutions for Cisco Unified Computing System (UCS) Blade Applications APC by Schneider Electric Solutions for Cisco Unified Computing System (UCS) Blade Applications The Cisco Unified Computing System is a next-generation data center platform that unites compute, network,

More information

SPOS (Station Point of Sale) 200. SFTP (Station Fare Transaction Processor) 35. CQD (Card Query Device) 35. HCR (Handheld Card Reader) Cradles 120

SPOS (Station Point of Sale) 200. SFTP (Station Fare Transaction Processor) 35. CQD (Card Query Device) 35. HCR (Handheld Card Reader) Cradles 120 DESIGN GUIDELINES PRESTO INSTALLATION & CONNECTIVITY PAGE 1 of 4 ELECTRICAL CONNECTIVITY AND WIRING Communications Conduits Conduits designated for Presto equipment data wiring shall be clearly identified

More information

RFP Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service

RFP Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service RFP 2017 845 Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service Version 1 Contents Project objectives... 1 Background... 1 Scope... 1 Timeframe and Cost... 4 Stakeholders, roles and responsibilities...

More information

350 East Plumeria Drive San Jose, CA USA February

350 East Plumeria Drive San Jose, CA USA February Installation Guide 350 East Plumeria Drive San Jose, CA 95134 USA February 2013 201-15135-03 Support Thank you for selecting NETGEAR products. After installing your device, locate the serial number on

More information

Liebert XDA Air Flow Enhancer. User Manual

Liebert XDA Air Flow Enhancer. User Manual Liebert XDA Air Flow Enhancer User Manual Technical Support Site If you encounter any installation or operational issues with your product, check the pertinent section of this manual to see if the issue

More information

Cisco MCS 7815-I1 Unified CallManager Appliance

Cisco MCS 7815-I1 Unified CallManager Appliance Data Sheet Cisco MCS 7815-I1 Unified CallManager Appliance THIS PRODUCT IS NO LONGER BEING SOLD AND MIGHT NOT BE SUPPORTED. READ THE END-OF-LIFE NOTICE TO LEARN ABOUT POTENTIAL REPLACEMENT PRODUCTS AND

More information

System Storage DS3950 Quick Start Guide

System Storage DS3950 Quick Start Guide System Storage DS3950 Quick Start Guide This Quick Start Guide describes the basic procedure for installing, cabling, and configuring the IBM System Storage DS3950 storage subsystem (Machine Types 1814-94H

More information

Checklist for building an edge data center

Checklist for building an edge data center Checklist for building an edge data center Building an edge data center to provide a cloud computing environment within a service provider central office can be a complex endeavor. It requires lots of

More information

Dell SC5020 and SC5020F Storage Systems Getting Started Guide

Dell SC5020 and SC5020F Storage Systems Getting Started Guide Dell SC5020 and SC5020F Storage Systems Getting Started Guide Regulatory Model: E03T Regulatory Type: E03T001 Notes, Cautions, and Warnings NOTE: A NOTE indicates important information that helps you make

More information

3 Uninterruptible Power Systems

3 Uninterruptible Power Systems S5K Modular Series On-Line Uninterruptible Power s (UPS) This easily upgraded and flexible UPS provides the protection you want, when you need it. The 5K Modular is scalable from 4 to 20 kva, offering

More information

PowerLogic Circuit Monitor Series 4000T Reference Manual Addendum

PowerLogic Circuit Monitor Series 4000T Reference Manual Addendum PowerLogic Circuit Monitor Series 4000T Reference Manual Addendum Contents POWERLOGIC Circuit Monitor Series 4000T Reference Manual Addendum CONTENTS CONTENTS................................................

More information

Dell SCv3000 and SCv3020 Storage System Getting Started Guide

Dell SCv3000 and SCv3020 Storage System Getting Started Guide Dell SCv3000 and SCv3020 Storage System Getting Started Guide Regulatory Model: E03T Regulatory Type: E03T001 Notes, Cautions, and Warnings NOTE: A NOTE indicates important information that helps you make

More information

Cisco Prisma II Platform

Cisco Prisma II Platform Cisco Prisma II Platform In optical transmission systems, the network platform forms the foundation of the product family. The Cisco Prisma II platform provides network operators with the unique features

More information

Summit Virtual Chassis Design and Installation Guide

Summit Virtual Chassis Design and Installation Guide Summit Virtual Chassis Design and Installation Guide Extreme Networks, Inc. 10460 Bandley Drive Cupertino, California 95014 (888) 257-3000 http://www.extremenetworks.com Published: June 1998 Part No: 120031-00

More information

Where s the Heat Coming From. Leland Sparks Global Account Technical Consultant Belden

Where s the Heat Coming From. Leland Sparks Global Account Technical Consultant Belden Where s the Heat Coming From Leland Sparks Global Account Technical Consultant Belden What is the greatest DC challenge you face? Air Flow to Heat Load Relation Server Inlet Fans Chips Outlet LOAD Dell

More information

Dell Networking S4810 Open Networking (ON) Getting Started Guide

Dell Networking S4810 Open Networking (ON) Getting Started Guide Dell Networking S4810 Open Networking (ON) Getting Started Guide Regulatory Model: S4810 Notes, Cautions, and Warnings NOTE: A NOTE indicates important information that helps you make better use of your

More information

A) Differences between Precision and Comfort Cooling Here are the major differences exist between precision air conditioning and comfort systems.

A) Differences between Precision and Comfort Cooling Here are the major differences exist between precision air conditioning and comfort systems. DATA CENTRE COOLING SYSTEM A) Differences between Precision and Comfort Cooling Here are the major differences exist between precision air conditioning and comfort systems. 1. Cooling Optimized to Electronic

More information

Cisco CRS 3-Phase AC Power Distribution Unit Installation Guide 2. Cisco CRS 3-Phase AC Power Distribution Unit 2

Cisco CRS 3-Phase AC Power Distribution Unit Installation Guide 2. Cisco CRS 3-Phase AC Power Distribution Unit 2 Cisco CRS 3-Phase AC Power Distribution Unit Installation Guide Cisco CRS 3-Phase AC Power Distribution Unit Installation Guide 2 Cisco CRS 3-Phase AC Power Distribution Unit 2 Revised: November 18, 2016,

More information

HP UPS R/T3000 G2. Overview. Precautions. Kit contents. Installation Instructions

HP UPS R/T3000 G2. Overview. Precautions. Kit contents. Installation Instructions HP UPS R/T3000 G2 Installation Instructions Overview The HP UPS R/T3000 G2 features a 2U rack-mount with convertible tower design and offers power protection for loads up to a maximum of 3300 VA/3000 W

More information

Installing the HP ProLiant DL380p G8 Server for Avaya one-x Speech

Installing the HP ProLiant DL380p G8 Server for Avaya one-x Speech Installing the HP ProLiant DL380p G8 Server for Avaya one-x Speech Release 6.3 Issue 1 March 2014 Contents Chapter 1: Installing the HP DL380p G8 Server... 5 HP ProLiant DL380p G8 Server overview... 5

More information

Obtaining Documentation and Submitting a Service Request, page xvii Safety Warnings, page xvii Safety Guidelines, page xx

Obtaining Documentation and Submitting a Service Request, page xvii Safety Warnings, page xvii Safety Guidelines, page xx Preface Obtaining Documentation and Submitting a Service Request, page xvii Safety s, page xvii Safety Guidelines, page xx Obtaining Documentation and Submitting a Service Request For information on obtaining

More information

Introduction to NetApp E-Series E2700 with SANtricity 11.10

Introduction to NetApp E-Series E2700 with SANtricity 11.10 d Technical Report Introduction to NetApp E-Series E2700 with SANtricity 11.10 Todd Edwards, NetApp March 2014 TR-4275 1 Introduction to NetApp E-Series E2700 with SANtricity 11.10 TABLE OF CONTENTS 1

More information

Cisco MCS 7845-H1 Unified CallManager Appliance

Cisco MCS 7845-H1 Unified CallManager Appliance Data Sheet Cisco MCS 7845-H1 Unified CallManager Appliance THIS PRODUCT IS NO LONGER BEING SOLD AND MIGHT NOT BE SUPPORTED. READ THE END-OF-LIFE NOTICE TO LEARN ABOUT POTENTIAL REPLACEMENT PRODUCTS AND

More information

CCBC is equipped with 3 computer rooms, one at each main campus location:

CCBC is equipped with 3 computer rooms, one at each main campus location: Policy: Computer Room Procedures Policy: Draft 12/14/2009 1.0 Purpose The purpose of this document is to establish procedures for the Community College of Baltimore County (CCBC) Information Technology

More information

GSW-2453 Gigabit Chassis switch. User Guide

GSW-2453 Gigabit Chassis switch. User Guide GSW-2453 Gigabit Chassis switch User Guide Contents 1. INTRODUCTION... 1 Features... 1 Package Contents... 2 Ethernet Switching Technology... 2 2. HARDWARE DESCRIPTION... 4 Physical Dimension... 4 Front

More information

Start Here. Features. Model DS108 Dual Speed Hub Installation Giude

Start Here. Features. Model DS108 Dual Speed Hub Installation Giude Start Here The NETGEAR Model DS108 Dual Speed Hub is a network hub that enables users to mix and match 10 and 100 megabits per second (Mbps) devices on the same network. This capability eliminates the

More information

1.0 Executive Summary. 2.0 Features and Benefits

1.0 Executive Summary. 2.0 Features and Benefits Table of Contents 1.0 EXECUTIVE SUMMARY 2.0 FEATURES AND BENEFITS 3.0 DETAILS OF SERVICE 4.0 Deliverable 5.0 Exclusions 6.0 SCOPE OF RESPONSIBILITY 7.0 PROJECT WORK DETAILS 8.0 ORDERING INFORMATION 9.0

More information

InstaPATCH Cu Cabling Solutions for Data Centers

InstaPATCH Cu Cabling Solutions for Data Centers SYSTIMAX Solutions InstaPATCH Cu Cabling Solutions for Data Centers Design Guidelines August 2008 www.commscope.com Contents Overview 1 InstaPATCH Cu Solution Specification 2 Harness Assembly Design 3

More information

Unpacking an Epica Distribution Matrix

Unpacking an Epica Distribution Matrix an Epica Distribution Matrix An Epica Distribution Matrix is shipped with one enclosure in each palleted box. Each box contains one of each of the following items (invoices are sent separately): Power

More information

LVN5200A-R2, rev. 1, Hardware Installation Guide

LVN5200A-R2, rev. 1, Hardware Installation Guide LVN5200A-R2 LVN5250A-R2 LVN5200A-R2, rev. 1, Hardware Installation Guide Customer Support Information Order toll-free in the U.S.: Call 877-877-BBOX (outside U.S. call 724-746-5500) FREE technical support

More information

SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS

SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS CONTENTS PAGE 1. GENERAL... 5-1 1.1. Introduction... 5-1 1.2. Equipment Layout Requirements... 5-1 2. EQUIPMENT FRAMES... 5-2 2.1. Introduction...

More information

MSYS 4480 AC Systems Winter 2015

MSYS 4480 AC Systems Winter 2015 MSYS 4480 AC Systems Winter 2015 Module 12: DATA CENTERS By Satwinder Singh 14/05/2015 1 Data Centers Data Centers are specialized environments that safeguard your company's most valuable equipment and

More information

Installation and Maintenance

Installation and Maintenance CHAPTER 4 Installation and Maintenance Revised: April 19, 2010, Introduction This chapter explains how to install a SCE 1000 platform in a rack or in a general tabletop or workbench installation. Additionally,

More information

Dim levels for each system output may be controlled by any of the following methods:

Dim levels for each system output may be controlled by any of the following methods: Applied Electronics Bravo Series Dimming System Rack-Mount Architectural l SA12/2400A and l SA12/2400E Setup and Operation Instructions 1.0 Scope This document details the setup and operation requirements

More information

Chapter 2 BladeStation Enclosure

Chapter 2 BladeStation Enclosure Chapter 2 BladeStation Enclosure Cubix BladeStation is an enclosure that provides power and cooling to multiple Cubix Blade Servers. It consists of a steel case, a mid-plane, an Input / Output (I / O)

More information

Cooling System. Cooling System Overview. 16-Slot Line Card Chassis Airflow

Cooling System. Cooling System Overview. 16-Slot Line Card Chassis Airflow This chapter describes the components that make up the cooling system of the Cisco CRS Series Carrier Routing System 16-Slot Line Card Chassis. It contains the following sections: 16-Slot Line Card Chassis

More information

Cisco MCS 7825-I1 Unified CallManager Appliance

Cisco MCS 7825-I1 Unified CallManager Appliance Data Sheet Cisco MCS 7825-I1 Unified CallManager Appliance THIS PRODUCT IS NO LONGER BEING SOLD AND MIGHT NOT BE SUPPORTED. READ THE END-OF-LIFE NOTICE TO LEARN ABOUT POTENTIAL REPLACEMENT PRODUCTS AND

More information

LifeSize ClearSea Installation Guide August 2012

LifeSize ClearSea Installation Guide August 2012 LifeSize ClearSea Installation Guide August 2012 LifeSize ClearSea LifeSize ClearSea Virtual Machine LifeSize ClearSea Installation Guide 2 LifeSize ClearSea This guide describes how to install and configure

More information

QuickSpecs. HP Rack Series. Overview. HP Rack Series - 36U

QuickSpecs. HP Rack Series. Overview. HP Rack Series - 36U Overview - 42U - 36U - 22U DIM "A" 78.838 [2002.50] DIM "A" 68.338 [1735.78] DIM "A" 43.838 [1113.48] DIM "B" 24.125 [612.77] DIM "B" 24.125 [612.77] DIM "B" 24.125 [612.77] DA - 10995 Worldwide Version

More information

Dell Storage Center. Getting Started Guide. SCv2000 and SCv2020 Storage System. Regulatory Model: E09J, E10J Regulatory Type: E09J001, E10J001

Dell Storage Center. Getting Started Guide. SCv2000 and SCv2020 Storage System. Regulatory Model: E09J, E10J Regulatory Type: E09J001, E10J001 Dell Storage Center SCv2000 and SCv2020 Storage System Getting Started Guide Regulatory Model: E09J, E10J Regulatory Type: E09J001, E10J001 Notes, Cautions, and Warnings NOTE: A NOTE indicates important

More information

INSTRUCTION MANUAL RA 55 RACK ADAPTER RACK ADAPTER FOR MST SERIES POWER MODULES

INSTRUCTION MANUAL RA 55 RACK ADAPTER RACK ADAPTER FOR MST SERIES POWER MODULES INSTRUCTION MANUAL RA 55 RACK ADAPTER RACK ADAPTER FOR MST SERIES POWER MODULES KEPCO INC. An ISO 9001 Company. MODEL RA 55 RACK ADAPTER ORDER NO. REV. NO. IMPORTANT NOTES: 1) This manual is valid for

More information

02 Why Does My IT Infrastructure Need a UPS?

02 Why Does My IT Infrastructure Need a UPS? UPS Buyer s Guide TABLE OF CONTENTS 01 What is a UPS? 02 Why Does My IT Infrastructure Need a UPS? 03 Common Features of UPS Systems ENERGY STORAGE SYSTEMS BATTERIES POWER PROTECTION MONITORING SOLUTIONS

More information

Aruba JL311A Cable Guard Installation Instructions

Aruba JL311A Cable Guard Installation Instructions Aruba JL3A Cable Guard Installation Instructions Abstract Use this guide to assist in the basic installation of the Aruba JL3A Cable Guard on select Aruba 8 port switches. *500-97* Part Number: 500-97

More information

Chapter 1 Product Introduction

Chapter 1 Product Introduction Chapter 1 Product Introduction Congratulations for purchasing of the Gigabit Ethernet Switch. Before you install and use this product, please read this manual carefully for full exploiting the functions

More information

Dell Networking S4100-ON Series. Set-Up Guide

Dell Networking S4100-ON Series. Set-Up Guide Dell Networking S4100-ON Series Set-Up Guide Notes, cautions, and warnings NOTE: A NOTE indicates important information that helps you make better use of your product. CAUTION: A CAUTION indicates either

More information

PLC Racks IC697CHS782/783

PLC Racks IC697CHS782/783 5 1 PLC Racks IC697CHS782/783 (IC697CHS782/783) datasheet Features Accepts 3rd Party VME modules which require 0.8 spacing. Accepts all IC697 PLC module types. Rear mount rack mounts in a 10 (254 mm) deep

More information

Installation Manual. Mounting Instructions Mechanical Mounting. Luminato. Teleste Corporation

Installation Manual. Mounting Instructions Mechanical Mounting. Luminato. Teleste Corporation Luminato Installation Manual Teleste Corporation Mounting Instructions Mechanical Mounting Luminato Mechanical Installation, agile_59300316, rev0044 Introduction 1 Contents Introduction 4 General... 4

More information

Specification Sheet: HT SERIES

Specification Sheet: HT SERIES Specification Sheet: HT SERIES HT Series: High Specification 19 Enclosures Hi-tech Series of 19 enclosures, supplied in self assembly (flat pack) format for ease of transportation and storage. Manufactured

More information

VEP4600. Setup Guide

VEP4600. Setup Guide VEP4600 Setup Guide Notes, cautions, and warnings NOTE: A NOTE indicates important information that helps you make better use of your product. CAUTION: A CAUTION indicates either potential damage to hardware

More information

USP-070-B08 USP-104-B10, USP-104-M10 USP-156-B10

USP-070-B08 USP-104-B10, USP-104-M10 USP-156-B10 UniStream HMI Panel Installation Guide USP-070-B10, USP-070-B08 USP-104-B10, USP-104-M10 USP-156-B10 Unitronics UniStream platform comprises control devices that provide robust, flexible solutions for

More information

iconverter 2-Module Power Chassis

iconverter 2-Module Power Chassis iconverter 2-Module Power Chassis User Manual 38 Tesla, Irvine, CA 92618 USA Phone: (949) 250-6510; Fax: (949) 250-6514 Page 1 Warning The operating description in this Instruction Manual is for use by

More information

Office of the Chief Information Officer Technical Note: IT-960-TN14 Effective: 05/25/2006 Last Revised: 02/17/2012 Issuing Office: OCIO

Office of the Chief Information Officer Technical Note: IT-960-TN14 Effective: 05/25/2006 Last Revised: 02/17/2012 Issuing Office: OCIO Cabling Standards Office of the Chief Information Officer Technical Note: IT-960-TN14 Effective: 05/25/2006 Last Revised: 02/17/2012 Issuing Office: OCIO 1. Purpose CABLING STANDARDS This technical note

More information

CTO Server and Network Cabinets

CTO Server and Network Cabinets DeltaV Distributed Control System Product Data Sheet January 2018 CTO Server and Network Cabinets CTO Server and Network Cabinet. Delivers standard cabinet with 19 frame construction for your DeltaV networking

More information

Network+ Guide to Networks 7 th Edition

Network+ Guide to Networks 7 th Edition Network+ Guide to Networks 7 th Edition Chapter 4 Structured Cabling and Networking Elements 2016 Cengage Learning. May not be scanned, copied or duplicated, or posted to a publicly accessible website,

More information

StorNext M440 Site Planning Guide

StorNext M440 Site Planning Guide StorNext M440 Contents StorNext M440 Site Planning Guide Included with Your StorNext M440... 1 Professional Installation Requirements. 2 Site Requirements... 2 Shipping Information... 3 StorNext M440 System

More information

Cisco MCS 7815-I2. Serviceable SATA Disk Drives

Cisco MCS 7815-I2. Serviceable SATA Disk Drives Data Sheet Cisco MCS 7815-I2 THIS PRODUCT IS NO LONGER BEING SOLD AND MIGHT NOT BE SUPPORTED. READ THE END-OF-LIFE NOTICE TO LEARN ABOUT POTENTIAL REPLACEMENT PRODUCTS AND INFORMATION ABOUT PRODUCT SUPPORT.

More information

HP Modular Cooling System: water cooling technology for high-density server installations

HP Modular Cooling System: water cooling technology for high-density server installations HP Modular Cooling System: water cooling technology for high-density server installations technical brief Abstract... 2 Introduction... 2 Data center trends... 2 Increased power demands... 3 Increased

More information

SW-UNM-24FE2GC-24POE 24 Fast Ethernet Ports PoE + 2 Giga Combo User Manual Ver 1.1

SW-UNM-24FE2GC-24POE 24 Fast Ethernet Ports PoE + 2 Giga Combo User Manual Ver 1.1 SW-UNM-24FE2GC-24POE 24 Fast Ethernet Ports PoE + 2 Giga Combo User Manual Ver 1.1 Chapter 1 Product Introduction Congratulations on your purchasing of the PoE Ethernet Switch. Before you install and use

More information

Cisco MCS 7815-I2 Unified CallManager Appliance

Cisco MCS 7815-I2 Unified CallManager Appliance Data Sheet Cisco MCS 7815-I2 Unified CallManager Appliance THIS PRODUCT IS NO LONGER BEING SOLD AND MIGHT NOT BE SUPPORTED. READ THE END-OF-LIFE NOTICE TO LEARN ABOUT POTENTIAL REPLACEMENT PRODUCTS AND

More information

R E C T I F I E R I N V E R T E R C O N V E R T E R MP7

R E C T I F I E R I N V E R T E R C O N V E R T E R MP7 Uninterruptible Power Supply Product Specifications Description The industrial UPS provides your critical equipment with uninterruptible 3 phase AC power. Using high frequency dual conversion technology,

More information

This Datasheet for the IC697CHS790. Rack, 9 Slots, Rear Mount.

This Datasheet for the IC697CHS790. Rack, 9 Slots, Rear Mount. This Datasheet for the IC697CHS790 Rack, 9 Slots, Rear Mount. http://www.cimtecautomation.com/parts/p-14771-ic697chs790.aspx Provides the wiring diagrams and installation guidelines for this GE Series

More information

Rugged MediaConverter

Rugged MediaConverter Rugged MediaConverter Installation Guide RuggedCom Inc. 30 Whitmore Road, Woodbridge, Ontario Canada L4L 7Z4 Web: http://www.ruggedcom.com/ Tel: (905) 856-5288 Fax: (905) 856-1995 Toll Free: (888) 264-0006

More information

PS8 - II. Professional Power Sequencer. User s Manual

PS8 - II. Professional Power Sequencer. User s Manual PS8 - II Professional Power Sequencer User s Manual IMPORTANT SAFETY INSTRUCTIONS READ FIRST This symbol, whenever it appears, alerts you to the presence of uninsulated dangerous voltage inside the enclosure.

More information

HP R/T2200 UPS. Overview. Precautions. Installation Instructions. The HP UPS R/T2200 features power protection for loads up to 2200 VA/1600 W.

HP R/T2200 UPS. Overview. Precautions. Installation Instructions. The HP UPS R/T2200 features power protection for loads up to 2200 VA/1600 W. HP R/T2200 UPS Installation Instructions Overview The HP UPS R/T2200 features power protection for loads up to 2200 VA/1600 W. For more information about any of the topics covered in this document, see

More information

RT12-240V/2.4kW Rectifier Specification

RT12-240V/2.4kW Rectifier Specification The RT12-240V/2.4kW is a switched mode rectifier (SMR) module that delivers up to 2.4kW of output power (and up to 11A output current) into a 240V nominal DC system. The RT12 suits AC supply voltages between

More information

V800 Cabinet Solution

V800 Cabinet Solution WWW.SIEMON.COM V800 Cabinet Solution 8 V800 Cabinet Lightweight Stability Design provides an extremely stable, high-capacity cabinet without excessive weight Integrated Side Panel Grounding Spring loaded

More information

Data Center Enclosures Best Practices. Maximize the Efficiency of the Enclosure within a Data Center

Data Center Enclosures Best Practices. Maximize the Efficiency of the Enclosure within a Data Center Data Center Enclosures Best Practices Maximize the Efficiency of the Enclosure within a Data Center Things to ask before selecting Enclosures: Primary Use Severs or Patching, or both determines size. RMU

More information

Tel: AC Power for Business-Critical Continuity TM

Tel: AC Power for Business-Critical Continuity TM Tel: +852-2690-4118 AC Power for Business-Critical Continuity TM Anticipating Technology Changes Through Adaptive Architecture Today, you need a power infrastructure that can work across your enterprise

More information

TECHNICAL SPECIFICATIONS + TECHNICAL OFFER

TECHNICAL SPECIFICATIONS + TECHNICAL OFFER ANNEX II + III : TECHNICAL SPECIFICATIONS + TECHNICAL OFFER Contract title : Supply of Information & Communication Technology Hardware Publication reference: 2017/386304 10/1/1.1/1.2.2a p 1 / Columns 1-2

More information

HP UPS R/T3000 ERM. Overview. Precautions. Installation Instructions

HP UPS R/T3000 ERM. Overview. Precautions. Installation Instructions HP UPS R/T3000 ERM Installation Instructions Overview The ERM consists of two battery packs in a 2U chassis. The ERM connects directly to a UPS R/T3000 or to another ERM. Up to two ERM units can be connected.

More information

REDUNDANT POWER SUPPLY SYSTEM FOR NETGEAR RPS CAPABLE ETHERNET SWITCHES

REDUNDANT POWER SUPPLY SYSTEM FOR NETGEAR RPS CAPABLE ETHERNET SWITCHES REDUNDANT POWER SUPPLY SYSTEM FOR NETGEAR RPS CAPABLE ETHERNET SWITCHES MODEL NO. OPN300-48SN Single-Port 48V DC Output RPS System Manual Revision E May 2009 Optimal Power Supplies LLC www.optimal-power.com

More information

Site Preparation CHAPTER

Site Preparation CHAPTER CHAPTER 3 Site Preparation This chapter describes the steps to take and the considerations you should keep in mind prior to installing the modules in an open rack. It also contains information that applies

More information

MAINTENANCE MANUAL. EDACS REDUNDANT POWER SUPPLY SYSTEM 350A1441P1 and P2 POWER MODULE CHASSIS 350A1441P3, P4, AND P5 POWER MODULES TABLE OF CONTENTS

MAINTENANCE MANUAL. EDACS REDUNDANT POWER SUPPLY SYSTEM 350A1441P1 and P2 POWER MODULE CHASSIS 350A1441P3, P4, AND P5 POWER MODULES TABLE OF CONTENTS MAINTENANCE MANUAL EDACS REDUNDANT POWER SUPPLY SYSTEM 350A1441P1 and P2 POWER MODULE CHASSIS 350A1441P3, P4, AND P5 POWER MODULES TABLE OF CONTENTS SPECIFICATIONS*... 2 INTRODUCTION... 3 DESCRIPTION...

More information

Cisco Nexus 7000 Series.

Cisco Nexus 7000 Series. Data Sheet Cisco Nexus 7000 Series Chassis Product Overview The Cisco Nexus 7000 Series Switches combine the highest levels of scalability with operational flexibility. The Cisco Nexus 7000 Series Switches

More information