Kent Wind Energy Networking Event. Wednesday 26 th September
|
|
- Francine Lauren Sparks
- 5 years ago
- Views:
Transcription
1 Kent Wind Energy Networking Event Wednesday 26 th September
2 Consortium partners Dong Energy is a leading offshore wind developer, having built around half of all offshore wind farms globally. (50%) E.ON is one of the world s leading power and gas companies. It s renewable division (E.ON Climate and Renewables) is one of the largest renewable energy companies in the world. (30%) The Masdar Initiative is Abu Dhabi s multi-faceted, multi-billion dollar investment in the development and commercialisation of innovative technologies in renewables, alternative and sustainable energies as well as sustainable design. (20%) 2
3 London Array phase one Phase One 630MW Green light given to Phase One in May 2009 by consortium partners. ( 2.2 billion investment) 175 SWP 3.6MW 120m turbines Two 33kV/150kV offshore substations 200km 33kV inter array cables 210km 150kV export cables One onshore 150kV/400kV substation One Operations & Maintenance base 3
4 Project gestation Apr 01 First Project Heads of Terms Dec 03 Crown Estate agreement for Round 2 lease Jun 05 Consent applications submitted Jun 06 Swale BC rejected application for substation Dec 06 Offshore consents granted Mar 07 Substation public inquiry - decision Aug 07 Jul 08 Shell sold its share to DONG (50%) and E.ON (50%) Oct 08 E.ON sold 40% of its share to Masdar Apr 09 Budget assistance for Round 2 projects May 09 Investment decision & turbine contract Jul 09 - Construction of onshore substation started Mar 11 - Offshore construction started Dec 12 Construction due to be completed 4
5 Construction update 133 turbines 175 monopiles 165 transition pieces 2 offshore substations and associated foundations 3 export cables installed with fourth cable currently being installed 166 array cables installed 5
6 Procurement approach Multi-contract approach adopted by the Participants 12 Contract Packages, including installation vessels and O&M facilities JV Project Team managing ITT, tender negotiations and contracting Legal advice on contracts provided by Pinsent Masons Interfaces between packages managed by Project Team Participant Procurement Compliance Panel (PPCP) ensures compliance with the contracting and procurement policy Contract strategy changed as result of the tender process: Turbine supplier declined to install turbines Foundation contractor agreed to install turbines and foundations but did not have the right vessels London Array to free issue installation vessels 6
7 The procurement process Stage 1: Prequalification Stage 2: Invitation to tender Stage 4: contract award Stage 3: Tender assessment 7
8 London Array main contract suppliers (Phase one) Wind turbines Siemens Wind Power are supplying MW turbines, fitted with new 120m rotor. Contract executed: May 2009 Siemens Wind Power has over 20 years experience. Foundations Supplied by a JV between Par Aarsleff A/S and Bilfinger Berger GmBH Contract executed: November 2009 WT and foundation installation Being installed by Aarsleff A/S and Bilfinger Berger Ingeniuerbeau GmBH. Contract executed: November 2009 Offshore substation Design, fabrication and installation awarded to Future Energy a JV between Fabricom, lemants and Geosea. Contract executed: September 2009 Supplied the offshore substation for the Belwind Offshore Wind Farm Export cable supply Nexans Norway are supplying the 220km of 150kV export cable. Contract executed: September 2009 Over 20 years experience 8
9 London Array main contract suppliers (Phase one) Array cable supply JDR Cable Systems are supplying the 210km of 33kV array cables. Contract executed: November 2009 Experience on five offshore power cable projects. Export and array cable installation Being installed by Visser and Smit Marine Contracting Contract executed: February 2010 Onshore substation Awarded to Siemens Transmission and Distribution Ltd. Contract executed: September 2009 Have constructed four onshore NGET substations and two offshore substations. Offshore installation vessels MPI Adventure and Discovery and A2 SEA s Sea Worker. Ballast Nedam s HLV Svanen also used to install 11 foundations. A2 Sea s Sea Jack will also be used for installation activities. Contract executed: A2SEA October 2009, MPI February 2010 MPI owns the Resolution and A2SEA has over five years experience O&M base design and construction Designed by BBLB Architects. Constructed by Mansell, managed from their Maidstone office. 9
10 Local supply chain initiatives Meet the Buyer, Westgate-on-Sea 9 June 2010 Objective: local businesses could find out how they could benefit from the wind farm s construction and maintenance activities Attended by more than 150 local businesses from across Kent Opportunity to meet the London Array team and some of our main contractors Database Contact via London Array website Used within the London Array team and shared with main suppliers Kent Wind Energy 10
11 Kent Wind Energy Networking Event The future of offshore wind Wednesday 26 th September
12 The Crown Estate Round 1 and 2 As the owner of the seabed the Crown Estate has a central role in the delivery of UK offshore wind Round 1 Demonstration Projects 18 Projects, 13 locations 30 turbines maximum 20MW minimum installed 10 km2 maximum area 22 year leases Round 2 Fully Commercial 15 Sites Agreements for lease in territorial waters and UKCS 40/50 year leases depending on site capacity Option fees according to size 12
13 Offshore wind and the Thames Estuary Greater Gabbard Gunfleet Sands I and II Kentish Flats London Array Thanet DATE 13
14 Round 3 Rapid development of offshore wind capacity is key to the delivery of the UK's share of the EU target of 20 per cent renewable energy by Round 3 leasing programme anticipates the delivery of up to 25 GW (gigawatts) of new offshore wind farm sites by The Crown Estate has allocated the 9 zones to development consortia, who have exclusive rights to develop wind farms in their allocated zones. The successful development consortia will remain wholly responsible for construction and operation of wind farm sites. The grid connection will be owned & operated and may be constructed by an Offshore Transmission Owner (OFTO) 14
15 Crown Estate Rounds 1&2 and Round 3
16 France July 2011: International call for bids for the installation of 3GW of offshore capacity April 2012: Winning bids announced four out of five locations awarded. Two consortiums led by EDF and Iberdrola. Fifth location on tender until 16 Sept End 2012: French Government about to launch second round of offshore wind tenders for two more locations (750MW Le Trepot in northern France and up to 600MW off the island of Noirmoutier) 2013: Hints of an even bigger tender to follow to propel France towards meetings its target of 6GW of offshore capacity by : Target for start up of first wind farms 16
London Array signs contracts worth almost 2bn for work on world s largest offshore wind farm
Press Release London Array signs contracts worth almost 2bn for work on world s largest offshore wind farm Supply and installation contracts finalised for first phase of offshore wind farm Six contractors
More informationArkona Offshore Wind Project
Holger Matthiesen 04.12.2017 Arkona Offshore Wind Project Norwegian offshore wind delegation E.ON strategy Global trends like sustainability and climate protection, digitalization and technological innovation
More informationWIND POWER EPC. Anders Lindberg, Head of EPC. Meet the Management, 2 February 2017
WIND POWER EPC Anders Lindberg, Head of EPC Meet the Management, 2 February 2017 83 Anders Lindberg Senior Vice President, Head of EPC Born: 1965 Education: EMBA in Business Administration (SSE) & MSc.
More informationWind Power Systems - Project Rödsand 2
Wind Power Systems - Project Rödsand 2 Nysted & Rödsand 2 Jörgen Svensson Industrial Electrical Engineering and Automation Outline - Rödsand 2 Background The task Project phases Design inputs Project management
More informationCost of Electricity (CoE)
Cost of Electricity (CoE) Cost reduction Road to 40% reduction in CoE 2 June 2014 Christian Juul For External usage Reduction in cost is essential to make offshore wind competitive and reduce dependency
More informationTaiwan Offshore Wind Policy and Regulation
Taiwan Offshore Wind Policy and Regulation Prepared by: Emilie Reeve 2 nd May 2018, Glasgow 0 Taiwan offshore wind development target timeline Government set timeframe for offshore wind growth Current
More informationOpportunities in the journey to subsidy free Bruce Valpy Glasgow 4 May 2016
Opportunities in the journey to subsidy free Bruce Valpy Glasgow 4 May 2016 1/13 Agenda UK opportunities in the journey to subsidy free Contents Selected clients 1. Journey to subsidy free 2. And beyond
More informationGOW Special Edition June 2016
GOW Special Edition June 2016 Welcome RenewableUK is pleased to bring you a special conference edition of our Offshore Wind Project Intelligence. This product is exclusively offered to all members and
More informationDue Diligence Services for Global Investment Agency to Assess the Business Case of Offshore Wind Plant Installations in India
Due Diligence Services for Global Investment Agency to Assess the Business Case of Offshore Wind Plant s in India join the Future now Copyright 2016 ENINCON LLP, All rights reserved Opportunity Assessment
More informationMODULAR HUB AND SPOKE 17 NOVEMBER 2017
MODULAR HUB AND SPOKE 17 NOVEMBER 2017 Executive Summary Future North Sea offshore wind farms will increasingly be located further from shore. The longer distances to shore and generally deeper waters
More informationConnecting and Managing Offshore Wind Danish Embassy - 4 th December 2012
Connecting and Managing Offshore Wind Danish Embassy - 4 th December 2012 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same
More information12 Approval of a New PRESTO Agreement Between York Region and Metrolinx
Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO
More informationDriving innova*on and knowledge
Driving innova*on and knowledge Presentation to Mer-Innovate SPARTA Paul Ellsmore Academic and Cross-Catapult Engagement Manager 29 th October 2014 Catapults: A long-term vision for innovation & growth
More informationSmart Systems and Heat
Smart Systems and Heat 02 03 Energy Technologies Institute www.eti.co.uk Why? Our Smart Systems and Heat programme is focused on creating future-proof and economic local heating solutions for the UK Heat
More informationSmart Systems and Heat
Smart Systems and Heat 02 03 Why? Our Smart Systems and Heat programme is focused on creating future-proof and economic local heating solutions for the UK Heat accounts for over 40% of the UK s demand
More informationSUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17
Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11
More informationBudget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017
2017-18 Budget Review Process (BRP) Preliminary List of Business Initiatives Stakeholder Meeting April 10, 2017 Purpose / Agenda The purpose of this presentation is to: Provide stakeholders with a BRP
More informationVirginia offshore wind port readiness
Virginia offshore wind port readiness A presentation to the Virginia Offshore Wind Development Authority 7 October 2015 Richmond, VA Contact: Charles Nordstrom, PE Project manager cjn@bvgassociates.com
More informationAn Introduction to Network Codes & The Links Between Codes
An Introduction to Network Codes & The Links Between Codes April 2014 About ENTSO-E 41 TSOs from 34 countries 532 million citizens served 828 GW generation 305 Thousand Km of transmission lines Ten-Year
More informationADB s Energy Program in Myanmar
ADB s Energy Program in Myanmar March 2014 Chong Chi Nai Director, Energy Division Southeast Asia Regional Department 1 Current Sector Context Low electrification ratio Need to develop cost effective way
More informationI E C E N G I N E E R I N G P R O C E S S I N O F F S H O R E W I N D F A R M S
IEC 61850 ENGINEERING PROCESS IN OFFSHORE WIND FARMS Saeed Nemati 27 September 2017 IEC 61850 2 IEC 61850 in Offshore Wind Farms About Dong Energy Main Business Units Bioenergy & Thermal Power Distribution
More information6 Version 1.0 (September 20, 2002) 0 days $0 0 days 01 Oct '02 01 Oct ' days $
1 Windstorm Power Ltd. 0 days $0 0 days 01 Oct '02 01 Oct '02 984 days $0 1 2 Canadian Wind Park 0 days $0 0 days 01 Oct '02 01 Oct '02 984 days $0 2 3 (40 Nordex N80 2.5 MW turbines) 0 days $0 0 days
More informationThe Efficient Way. SVC PLUS Innovation meets experience. Answers for energy.
The Efficient Way SVC PLUS Innovation meets experience Answers for energy. Enhancement of Grid Efficiency Improved dynamic stability and power quality of power systems in a new, highly economical manner
More informationFreedom of Information Act 2000 reference number RFI
P. Norris By email to: xxxxxxxxxxxxxxxxxxxxxx@xxxxxxxxxxxxxx.xxm 02 November 2011 Dear P. Norris Freedom of Information Act 2000 reference number RFI20111218 Thank you for your request under the Freedom
More informationFor personal use only
FY 2014 Half-Year Results 27 February 2014 NEXTDC LIMITED ACN 143 582 521 H1 FY14 highlights for the half-year ended 31 December 2013 National network nearing completion Strong functional sales channel
More informationThe GCC Interconnection Grid
GCC Interconnection Authority The GCC Interconnection Grid ME Power & Water Conference Abu Dhabi, UAE Nabeel H. Al-Maskati, PhD Hassan K. Al-Asaad, Asaad, MBA March 2007 Background Gulf Cooperation Council
More informationFigure 9.1: The ITER construction site in October UK firm Atkins, as part of Engage
9.1 OVERVIEW CCFE s industry programme, now operating under the auspices of the UK Atomic Energy Authority, has continued to play a very active role in involving British companies in fusion during the
More informationFor personal use only
2011 Annual General Meeting October 21, 2011 AUSTRALIA S PRIME DEFENCE CONTRACTOR SHIPS SYSTEMS SUPPORT Agenda Results highlights and key events Group financial summary Current order backlog U.S. Navy
More informationElia Grid International Your expert in power system solutions
Elia Grid International Your expert in power system solutions 2 ELIA GRID INTERNATIONAL Your expert in power system solutions Backed by major grid operators Elia Grid International combines the best of
More informationGovernment of Canada IPv6 Adoption Strategy. IEEE International Conference on Communications (ICC 12) June 14 th, 2012
Government of Canada IPv6 Adoption Strategy IEEE International Conference on Communications (ICC 12) June 14 th, 2012 IPv6 Context The internet is running out of IPv4 addresses now IPv6 is here RIPE NCC
More informationCompany Presentation. Charles F. Dunleavy, Chief Executive Officer Brian M. Posner, Chief Financial Officer
Company Presentation Charles F. Dunleavy, Chief Executive Officer Brian M. Posner, Chief Financial Officer November 16, 2010 Forward-Looking Statements In addition to historical information, this presentation
More informationContractor Alliancing Sean Mooney Programme Manager
1 Contractor Alliancing Sean Mooney Programme Manager Today s Agenda Introduction Background Contractor Alliancing The Process Alliance Electricity Alliance North (EAN) Optimise Water (LLP) JV Benefits
More informationCost efficient procurement of solar PV assets
Cost efficient procurement of solar PV assets Transnet - CSIR Solar PV Workshop CSIR Energy Centre Energy Autonomous Campus with Energy Markets & Policy Pretoria Campus: Knowledge Commons, Ulwazi 19 May
More informationForeign Direct Investment (FDI) and Renewable Energy. Donal Flavin, Strategic Policy Manager, IDA Ireland
Foreign Direct Investment (FDI) and Renewable Energy Donal Flavin, Strategic Policy Manager, IDA Ireland October 11, 2018 Presentation Outline IDA Ireland. Ireland s FDI (Foreign Direct Investment) Sector.
More informationResults for the year ending 31 March 2010.
Induction MITIE at a glance We re the strategic outsourcing and asset management company; FTSE 250 listed support services business with a track record of more than 20 years of growth; Revenues in excess
More informationInvestment in offshore wind - utility s perspective Marek Dziewior
European Summer School 2015 Economic and Legal Aspects of the Electricity, Gas and Heat Market Investment in offshore wind - utility s perspective Marek Dziewior European Summer School 2015 1 Agenda E.ON
More informationFigure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended
Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public
More informationOptimizing wind farms
Optimizing wind farms We are Uniper Your benefits We are a leading international energy company with operations in more than 40 countries and around 13,000 employees. We combine a balanced portfolio of
More informationNational Nuclear Laboratory Overview
National Nuclear Laboratory Overview BECBC 06/09/17 Dr Lindsay Edmiston; Acting Business Leader Waste Management and Technology NNL at a Glance NNL: The principal R&D organisation to underpin UK s national
More informationElectricity Market Reform
Electricity Market Reform Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. John Perkins, Feed
More informationPLUS Technology for Large Scale Renewable Energy Integration
PLUS Technology for Large Scale Renewable Energy Integration ASIA CLEAN ENERGY FORUM 2015 Manila 15-19 June, 2015 P. Thepparat*, M. Haeusler, V. Hild, B. Rutrecht, K. Uecker Vers. 8-4-00 Energy Management
More informationGigabit West Sussex. Report to Cabinet. Executive Summary. Recommendations. Reasons for Recommendations. Background Papers
Report to Cabinet 21 st September 2017 By the Cabinet Member for Finance & Assets DECISION REQUIRED Not Exempt Gigabit West Sussex Executive Summary This report explains the reasons why the Council should
More informationCloud. Cloud Innovation World Cup 2013/14 15 OCT - 15 MAR. Special Prize Evolve Insurance Award. Participant Information INDUSTRY 4.
Innovation World Cup 2013/14 15 OCT - 15 MAR Participant Information ICT BUSINESS SERVICES Urban Infrastructures SMART LIVING INDUSTRY 4.0 MOBILITY Evolve Insurance Award THE CATEGORIES CLOUD INNOVATION
More informationSTATE OF MINNESOTA PUBLIC UTILITIES COMMISSION
STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION In the Matter of the Application of Getty Wind Company, LLC for a Site Permit for a Large Wind Energy Conversion System in Stearns County, Minnesota In the
More informationTransWest Express Transmission Project Interregional Transmission Project Submittal
TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March
More informationSiemens HVDC & FACTS Innovations and Projects
Siemens HVDC & FACTS Innovations and Projects EPRI Conference, October 2010 in Palo Alto Volker Hild, Jeff Vivian Bulk Power Transmission in China Selected HVDC Applications Page 2 Oct - 2010 Ultra HVDC
More informationOceansgate Plymouth University
Oceansgate Plymouth University Feb 2018 Patrick Hartop Head of City Deal patrick.hartop@plymouth.gov.uk Gareth Simmons Strategic Projects Director gareth.simmons@plymouth.gov.uk Why is this so important
More informationImplementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899)
Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899) Operation Name: Energy Community
More informationRocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH
Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation
More informationYour experts for coal assets
Your experts for coal assets We are Uniper Your benefits We are a leading international energy company with operations in more than 40 countries and around 13,000 employees. We combine a balanced portfolio
More informationNortheast Coordinated System Plan and Other Interregional Activities
Northeast Coordinated System Plan and Other Interregional Activities IPSAC10 November 6, 2009 Michael I. Henderson and John Buechler Background on Interregional Planning Order 890 requires regional coordination
More informationEnergy Step Code Implementation Strategy. March 26, 2018
Energy Step Code Implementation Strategy March 26, 2018 About the BC Energy Step Code Climate Leadership Plan call for: Net zero energy ready buildings by 2032; Development of the Energy Step Code to get
More informationThe Power Skills Centre Training Courses
The Power Skills Centre Training Courses 2018-2019 Substations Courses Specialist Courses Cables Courses Power Networks Courses Protection Courses Tailored Programmes www.eatechnology.com Safer, Stronger,
More informationProgress Report on the GCC Electricity Grid Interconnection in the Middle East
GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Progress Report on the GCC Electricity Grid Interconnection in the Middle East by: Adnan Al-Mohaisen, GM, GCCIA Luc Chausse, Project Director, SNC-Lavalin
More informationAORC Technical meeting 2014
http : //www.cigre.org B1-1090 AORC Technical meeting 2014 Dynamic Installation for Fukushima Floating Offshore Wind Farm Demonstration Project Yasuhiro Tominaga, Hiroshi Nakano, Koji Tomikuda, Masayoshi
More informationPROJECT REPORT RCMP E DIVISION HEADQUARTERS RELOCATION PROJECT
PROJECT REPORT RCMP E DIVISION HEADQUARTERS RELOCATION PROJECT TABLE OF CONTENTS PROJECT DESCRIPTION 01 07 WHY A PUBLIC-PRIVATE 03 08 05 Overview of the RCMP E Division Headquarters Relocation Project.
More informationNew Concept for Article 36 Networking and Management of the List
New Concept for Article 36 Networking and Management of the List Kerstin Gross-Helmert, AFSCO 28 th Meeting of the Focal Point Network EFSA, MTG SEAT 00/M08-09 THE PRESENTATION Why a new concept? What
More informationCouncil, 26 March Information Technology Report. Executive summary and recommendations. Introduction
Council, 26 March 2014 Information Technology Report Executive summary and recommendations Introduction This report sets out the main activities of the Information Technology Department since the last
More informationarpet Floorin Join us and see excellence beneath your feet... Green International Carpet & Flooring Exhibition 1-3 Oct 2015 ADNEC Abu Dhabi, U.A.
International Carpet & Flooring Exhibition 1-3 Oct 2015 ADNEC Abu Dhabi, U.A.E Join us and see excellence beneath your feet... Incorporated Events: O INTERNATIONAL Green arpet and Floorin CONFERENCE 2-3
More informationRenewable Energy Investment Trends in sub-saharan Africa
Renewable Energy Investment Trends in sub-saharan Africa Wikus Kruger MIRA Graduate School of Business, University of Cape Town Nov 2018 Nr of Projects Number of utility-scale RE IPPs in SSA 25 (ex. RSA)
More informationGuidance: Operational Conditions Precedent (OCPs) September 2016 Version 1
Guidance: Operational Conditions Precedent (OCPs) September 2016 Version 1 Contents 1 Introduction 4 2 Operational Conditions Precedent requirements 4 3 Low Carbon Contracts Company Process 8 4 Supporting
More informationAvira Test Results 2013
Avira s anti-malware solutions received numerous awards and certifications this year. VIRUS BULLETIN: As evidence of sustained good performance, Avira received a VB100 award for every test it participated
More informationREQUEST FOR PROPOSALS Consultant to Develop Educational Materials for the Applied Informatics Team Training
REQUEST FOR PROPOSALS Consultant to Develop Educational Materials for the Applied Informatics Team Training Table of Contents: Part I. Overview Information Part II. Full Text of Announcement Section I.
More informationImpact of Policy Uncertainty on Renewable Energy Investment: Wind Power and the PTC
Impact of Policy Uncertainty on Renewable Energy Investment: Wind Power and the PTC Merrill Jones Barradale PhD Candidate, Energy and Resources Group, UC Berkeley 27th USAEE Conference, Houston, TX, September
More informationWorkshop: Innovation Procurement in Horizon 2020 PCP Contractors wanted
Workshop: Innovation Procurement in Horizon 2020 PCP Contractors wanted Supercomputing Centre Institute for Advanced Simulation / FZJ 1 www.prace-ri.eu Challenges: Aging Society Energy Food How we can
More informationBRITISH WATER. UK water sector supply chain, innovation and opportunities 15 th February Paul Mullord UK Director
BRITISH WATER UK water sector supply chain, innovation and opportunities 15 th February 2016 Paul Mullord UK Director British Water Overview Not-for-profit organisation - Company Limited by Guarantee Funded
More informationOverview of the Re:fit Programme
Overview of the Re:fit Programme Delivering savings in the public sector Vicky Kingston Project Director Vicky.kingston@local.gov.uk +447876 594 041 The Re:fit Framework Introducing Re:fit Re:fit allows
More informationCALENDAR FOR THE YEAR 2018
27 Dubai 08-12 Jan 1 Advance Budgeting Workshop 386 Istanbul 11-1 Mar 396 London 13-17 May 2 Advance Business Writing 296 Abu Dhabi 1-19 Jan 3 Contract Management 396 London 22-26 Jan 27 Dubai 18-22 Mar
More informationOffshore renewables structural monitoring. Safeguarding the quality and productivity of your offshore wind farm assets.
Offshore renewables structural monitoring Safeguarding the quality and productivity of your offshore wind farm assets. Strainstall / Offshore renewables structural monitoring Specialist offshore expertise
More information13174/15 AT/tl 1 DGE 2B
Council of the European Union Brussels, 6 November 2015 (OR. en) 13174/15 ER 359 COEST 325 RELEX 833 INFORMATION NOTE From: General Secretariat of the Council To: Delegations Subject: External energy relations
More informationQUALITY CONTROL Prepared: TenneT team Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... 2
POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.8 SCADA, communication interface and data links Filename ONL 15-185-T8_SCADA, communication
More informationJapan s Measures against Spam
June 22, 2, 2006 Japan s Measures against Spam Yoshichika Imaizumi Telecommunications Bureau, Ministry of Internal Affairs and Communications (MIC), Japan Characteristics of spam in Japan 1.. Media 2004
More informationInnovationPartnership Talking Traffic
The Dutch Ministry of Infrastructure and Environment Presentation InnovationPartnership Talking Traffic Smart Mobility! Michael van Scheijndel 10 oktober 2017 Procurement team Program manager Direction
More informationPacifiCorp Transmission Energy Gateway Update. John Cupparo Vice President, Transmission January 2010
PacifiCorp Transmission Energy Gateway Update John Cupparo Vice President, Transmission January 2010 Topics Overview and current status Rightsizing Challenges and opportunities Summary 2 Energy Gateway
More informationMA SREC-II Extension Application Instructions
MA SREC-II Extension Application Instructions Qualification in SREC-II Less than or equal to 25 kw Systems interconnected on or before January 8, 2017 Original SREC-II factors Systems interconnected after
More informationEnergy Engineering: Tools and Trends
Energy Engineering: Tools and Trends AEE Northeast Ohio Chapter Meeting March 27, 2008 1 Introduction Background and Experience Energy Engineer for Trane 20 years in HVAC Industry Equipment design and
More informationDEPARTMENT OF THE ARMY *ER U.S. Army Corps of Engineers CECW-EC Washington, DC Administration PROJECT SCHEDULES
DEPARTMENT OF THE ARMY *ER 1-1-11 U.S. Army Corps of Engineers CECW-EC Washington, DC 20314-1000 Regulation No. 1-1-11 18 September 17 Administration PROJECT SCHEDULES 1. Purpose. This regulation states
More informationAutodesk and Spatial Business Systems Strategic Alliance Frequently Asked Questions for Customers
Autodesk and Spatial Business Systems Strategic Alliance Frequently Asked Questions for Customers Table of Contents OVERVIEW... 1 1.1 WHAT IS CHANGING?... 2 1.2 WHY IS AUTODESK MAKING THIS CHANGE?... 2
More informationBENCHMARKING PPP PROCUREMENT 2017 IN GABON
BENCHMARKING PPP PROCUREMENT 2017 IN GABON Regulatory and Institutional Framework for PPPs framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory framework and
More informationUnited States Energy Association Energy Technology and Governance Program REQUEST FOR PROPOSALS
United States Energy Association Energy Technology and Governance Program REQUEST FOR PROPOSALS UTILITY CYBER SECURITY INITIATIVE (UCSI) CYBERSECURITY CAPABILITY MATURITY MODEL (C2M2) ASSESSMENT FOR THE
More informationProgramme Headlines. Project Headlines. Appendix - Watford 2020 Progress Update Report 8 November 2017
Completed by: Liam Hornsby Period from: 23 October 2017 Date completed: 6 November 2017 Period to: 6 November 2017 Current Programme Status Trend since last report Programme Headlines R R/A A/G G Worse
More informationPowering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director
Powering the North West s Future: From DNO to DSO Paul Bircham Commercial Strategy & Support Director 1 Introducing Electricity North West 5 million 2.4 million (45% of demand) 20,000 I&C (55% of demand)
More informationWIND. Representing clients across the renewable energy industry. Troutman Sanders LLP. troutman.com
WIND Representing clients across the renewable energy industry Troutman Sanders renewable energy attorneys offer innovative legal solutions to help clients succeed in the wind energy industry. Our deep
More informationHorizon Nuclear Power signs further development contracts to advance Anglesey reactor plans
FOR IMMEDIATE RELEASE Horizon Nuclear Power signs further development contracts to advance Anglesey reactor plans Bechtel appointed Project management Contractor, Further contracts agreed with Hitachi
More informationAnnual Membership Meeting. San Francisco, CA June 19, 2014
Annual Membership Meeting San Francisco, CA June 19, 2014 1 Antitrust Statement Although the Cool Roof Rating Council is a broad-based 501(c)3 organization, it does include numerous competitors in the
More informationStakeholder consultation process and online consultation platform
Stakeholder consultation process and online consultation platform Grant agreement no.: 633107 Deliverable No. D6.2 Stakeholder consultation process and online consultation platform Status: Final Dissemination
More informationPromoting Quality Infrastructure Investment
Promoting Quality Infrastructure Investment - Japan s contribution to infrastructure development - Mitsutoshi Kajikawa Director, Development Policy Division Ministry of Finance, Japan 1 Quality Infrastructure
More informationIT Management Excellence. Contents are subject to change. For the latest updates visit Page 1 of 7
IT Management Excellence Page 1 of 7 Why Attend Managing an IT function is very different from developing or supporting technical IT solutions. General management skills are helpful to the IT manager,
More informationInternational cooperation on power interconnection: Mongolian Regulatory perspective
4 th Northeast Asia Energy Security Forum International cooperation on power interconnection: Mongolian Regulatory perspective ENKHTUVSHIN Ganbaatar Ph.D. candidate Energy and Environmental Department,
More informationO F F S H O R E WIND POWER S Y S T E M S O F T E X A S L L C
September 12, 2011 To Whom it May Consern: Subject: Nationwide Permit 5 GOM Test Site and Supporting Facilities Dear Sir: We are sending you information related to our recently fully permitted test site
More informationADDENDUM #1. Date: 12/21/2018
Minnesota State Colleges and Universities Request for Proposals for Architectural and Engineering Services Physical Security Enhancements at St. Cloud State University Date: 12/21/2018 ADDENDUM #1 1. The
More informationCONTENTS. Shabiya Police Station
CONTENTS Shabiya Police Station Abu Dhabi Water & Electricity Company (ADWEC) - ADWEC s Role 5 - Mission, Vision & Values 5 About the Sector - Sector Structure 7 - Sector Costs & Regulation 7 ADWEC s Exports
More informationSUPERGEN Wind Wind Energy Technology
SUPERGEN Wind Wind Energy Technology SUPERGEN: Wind Hub Bill Leithead University of Strathclyde 20 March 2014 Supergen Wind Hub EPSRC funded 3.0M 2014-2019 1.2M Described research programme 1.2M Flexible
More informationGC0102 Mod Title: EU Connection Codes GB Implementation Mod 3
Stage 01: Modification Proposal Grid Code GC0102 Mod Title: EU Connection Codes GB Implementation Mod 3 Purpose of Modification: This modification (3/4) will set out within the Grid Code the following
More informationReal-time Data Infrastructure Applied to the Monitoring of Renewables Assets
Real-time Data Infrastructure Applied to the Monitoring of Renewables Assets Presented by Aurélie Nasse, Operations Control Center Manager EDF EN Services Copyright 2011 OSIsoft, LLC Disclaimer The figures
More informationDoD Environmental Security Technology Certification Program (ESTCP) Tim Tetreault DoD August 15, 2017
DoD Energy Testbed DoD Environmental Security Technology Certification Program (ESTCP) Tim Tetreault DoD August 15, 2017 Tampa Convention Center Tampa, Florida About ESTCP Established in 1995 to: Improve
More informationQUALITY CONTROL Prepared: TenneT team Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... 2
POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.8 SCADA, communication interface and data links Filename ONL 15-185-T8_SCADA, communication
More informationRamsey/Washington Recycling and Energy Board. September 22, 2016 Meeting
Ramsey/Washington Recycling and Energy Board September 22, 2016 Meeting Item IV. a. Facility Committee Report (pp. 8 16) Odors and Odor Measurement Sensory Perception, Subjective to each Individual May
More informationCONNECTING THE DEFENCE COMMUNITY WITH INSIGHT, INTELLIGENCE & OPPORTUNITIES. Defence Themes Officially supported by:
CONNECTING THE DEFENCE COMMUNITY WITH INSIGHT, INTELLIGENCE & OPPORTUNITIES Defence Themes 2018 Officially supported by: Official media partners for: Defence Online Themes for 2018 January 2018 Clothing
More informationSmartECR Business Value Through Real-Time Data
SmartECR Business Value Through Real-Time Data Presented by Uwe Fischer E.ON Copyright 2011 OSIsoft, LLC Agenda Company Overview SmartECR Scope SmartECR Challenges SmartECR Solutions Next Steps Copyright
More information