PHASE I ENERGY STORAGE: LESSONS LEARNED

Size: px
Start display at page:

Download "PHASE I ENERGY STORAGE: LESSONS LEARNED"

Transcription

1 PHASE I ENERGY STORAGE: LESSONS LEARNED ESAG Meeting, June 28, 2018 Innovation Research and Development

2 Table of Contents 1. History and Background 2. Pre-Commissioning: Challenges experienced 3. Project Registration and Commissioning 4. Missing pieces and solutions developed along the way 5. Lessons still to be learned 2

3 Phase I Energy Storage program lessons learned HISTORY AND BACKGROUND 3

4 Ontario Long Term Energy Plan Phase I Energy Storage Program History Minister s Directive authorizing phase I and II storage programs Phase I RFP: 12 projects by 5 different proponents: 9 RSVC facilities and 3 regulation service facilities Various changes of location and control by many projects Phase I storage facilities reach the Market Commissioning stage and begin entering the electricity market (7 out of 11 as of May, 2018) 4

5 5

6 IESO contracted energy storage portfolio (110.5 MW) as of April, 2018 Eleven Phase I Energy Storage facilities now entering the market or in final stages of commissioning as of April,

7 Phase I Energy Storage program lessons learned PRE-COMMISSIONING: CHALLENGES EXPERIENCED 7

8 Sources of delay prior to the final registration and commissioning stages Commercial: Delays in finalizing legal agreements between the host LDC and the project proponent and in other cases, between the project proponent and their technology vendors or financiers. One project affected by a component supplier exiting the market Co-operation of the host LDC is a key success factor and it varies Regulatory environment: In some cases, limitation in technical resources within LDCs to conduct Connection Impact Assessments Environmental assessment of MOECC noise impact has resulted in additional project work to enclose works in soundproofed buildings Absence of formalized framework to integrate storage projects at the distribution level Delays to permitting affects multiple construction dependencies if it is delayed. Applicability of distribution charges is emerging as a significant issue: 3 differing views of transmission-connected resources in Ontario: Wholesale market rules, OEB distribution rules and Transmission Tariff rules Inadequate assessment of materiality of these charges by some phase I participants 8

9 Typical timeline for Phase 1 facilities 3.5 years from contract signing to Registration Authorization into the electricity market A majority of the time spent site selection, local connection approvals and other activities before the IESO registration process begins Approximately 1year for IESO registration/commissioning 9

10 Understanding a typical phase I project arrangement Ministry of Energy OEB Directive Licencing IESO Min of Env. and Climate change Phase I agreement + market participant Noise reduction regulations Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 10

11 Commercial Risks Establishing, revising, and maintaining commercial s has extended project timelines for several phase I projects. Ministry of Energy Directive OEB Licencing IESO Phase I agreement + market participant Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 11

12 Permitting Risks For some phase I projects, administrative delays and changing requirements have all pushed out timelines for the permitting process, which have multiple downstream dependencies for development timelines. Ministry of Energy Directive OEB Licencing IESO Min of Env. and Climate change Phase I agreement + market participant Noise reduction regulations Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 12

13 Connection risks For some phase I projects, the with the Host LDC has been a crucial factor affecting project timelines. In some cases estimated connection timelines of months have been cited by some LDCs. Competing, formalized priorities for FIT/microFIT connections have sometimes been offered as a reason. Ministry of Energy Directive OEB Licencing IESO Min of Env. and Climate change Phase I agreement + market participant Noise reduction regulations Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 13

14 Distribution charges Ministry of Energy Directive In Ontario, there are different views as to the boundary of the transmission system based upon: Voltage and connection topology (IESO Market Rules, Electricity Act) Ownership of connecting assets (OEB codes, and Transmission Tariff orders) In some cases, the applicability of distribution charges to transmission connected phase I projects was an extensive, ongoing OEB topic of discussion between ASPs and the host LDC. Licencing IESO Min of Env. and Climate change Phase I agreement + market participant Noise reduction regulations Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 14

15 The ongoing role of storage While the OEB has created an Electricity Storage Licence in Ontario, the characteristics of energy storage facilities and their treatment have yet to permeate into the more detailed levels of codes, market rules and priority setting at all levels of the Ontario electricity system. For new entrants, basic information gathering on the treatment of their facilities is a complex, and sometimes error-prone, undertaking that can add to project timelines. Ministry of Energy OEB Directive Licencing IESO Min of Env. and Climate change Phase I agreement + market participant Noise reduction regulations Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 15

16 Registration Risk Phase I Energy Storage participants AND their facilities must be registered in the IESO-administered markets a complex 6-8 month process Ministry of Energy Directive OEB Licencing IESO Min of Env. and Climate change Phase I agreement + market participant Noise reduction regulations Ancillary Service Provider (ASP) Ownership Leases, connection agreements and customer Host LDC Metering Service Provider Financier(s) Various debt/equity arrangements ASP Project holding entity Services Permits Local municipality Critical service agreements Developer(s) Other component manufacturers Systems Integrator(s) Purchase agreements Storage technology manufacturer 16

17 Phase I Energy Storage program lessons learned PROJECT REGISTRATION AND COMMISSIONING: CHALLENGES EXPERIENCED 17

18 General Challenges: Project Registration and Commissioning A highly complex process even for experienced market participants A lengthy process particularly for facilities with a short development cycle No specific market rules expressly set out the application of registration and commissioning requirements for energy storage facilities Multiple market manuals and related documents govern the process. Some requirements clearly only apply to generation facilities but no official guidance from the IESO market rules as to which ones. 18

19 Phase I Energy Storage program lessons learned MISSING PIECES AND SOLUTIONS DEVELOPED ALONG THE WAY 19

20 Interim Operating Guide for RSVC facilities Applies to RSVC facilities only. The 2 Regulation facilities will resemble today s operations with the ATR fleet 20

21 Phase I Energy Storage program lessons learned LESSONS STILL TO BE LEARNED 21

22 Ontario s first dispatchable storage facilities are just beginning operations Looming questions: Can market participants adequately manage state of charge on their own? Is this the most efficient solution? Is the mandatory window for bid/offer changes too restrictive? Can storage facilities feasibly offer reliable operating reserve without state of charge monitoring in the DSO algorithm? Will conflicting dispatch between generator and load segments become a serious problem? 22

23 End of Slides 23

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

Entergy Arkansas, Inc. Transition Plan Technical Conference #1

Entergy Arkansas, Inc. Transition Plan Technical Conference #1 Entergy Arkansas, Inc. Transition Plan Technical Conference #1 May 5, 2010 1 Why Technical Conferences? Complex subject matter Venue for stakeholders to develop an awareness and understanding of the issues

More information

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1 OATT Attachment Q-1 First Revision of Page 1 ATTACHMENT Q-1 Dynamic Scheduling This attachment contains the eligibility requirements and the terms and conditions for the provision of dynamic scheduling

More information

Public Safety Canada. Audit of the Business Continuity Planning Program

Public Safety Canada. Audit of the Business Continuity Planning Program Public Safety Canada Audit of the Business Continuity Planning Program October 2016 Her Majesty the Queen in Right of Canada, 2016 Cat: PS4-208/2016E-PDF ISBN: 978-0-660-06766-7 This material may be freely

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO

RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO June 27, 2016 Training provided for Ontario market participants by the Market Assessment and Compliance Division of the IESO Module 1 A MACD training presentation

More information

Memorandum. Stakeholder Advisory Committee. Sorana Ionescu Director, Smart Metering. Doug Thomas Vice President, I&TS and CIO. Date: August 15, 2017

Memorandum. Stakeholder Advisory Committee. Sorana Ionescu Director, Smart Metering. Doug Thomas Vice President, I&TS and CIO. Date: August 15, 2017 Memorandum To: From: CC: Stakeholder Advisory Committee Sorana Ionescu Director, Smart Metering Doug Thomas Vice President, I&TS and CIO Date: August 15, 2017 Subject: IESO Business Update Smart Metering

More information

Business Continuity Planning

Business Continuity Planning Information Systems Audit and Control Association www.isaca.org Business Continuity Planning AUDIT PROGRAM & INTERNAL CONTROL QUESTIONNAIRE The Information Systems Audit and Control Association With more

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

SME License Order Working Group Update - Webinar #3 Call in number:

SME License Order Working Group Update - Webinar #3 Call in number: SME License Order Working Group Update - Webinar #3 Call in number: Canada Local: +1-416-915-8942 Canada Toll Free: +1-855-244-8680 Event Number: 662 298 966 Attendee ID: check your WebEx session under

More information

Description of the Application Process for Small Embedded Generators

Description of the Application Process for Small Embedded Generators Description of the Application Process for Small Embedded Generators This document describes the Application Process for Small Embedded Generators (as required under section 5.3.3A of the National Electricity

More information

Follow-Up on VFM Section 3.11, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW

Follow-Up on VFM Section 3.11, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.11 Ministry of Energy Smart Metering Initiative Follow-Up on VFM Section 3.11, 2014 Annual Report Chapter 1 Follow-Up Section 1.11 RECOMMENDATION STATUS OVERVIEW # of Status of Actions

More information

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17 Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11

More information

Accreditation of Product Certification Scheme for Construction Materials By Ir C K Cheung Hong Kong Accreditation Service

Accreditation of Product Certification Scheme for Construction Materials By Ir C K Cheung Hong Kong Accreditation Service Accreditation of Product Certification Scheme for Construction Materials By Ir C K Cheung Hong Kong Accreditation Service 1. Overview of HKAS Originated as an accreditation scheme called HOKLAS in 1985

More information

Session 2: CORSIA MRV System: Monitoring of CO 2 Emissions. ICAO Secretariat

Session 2: CORSIA MRV System: Monitoring of CO 2 Emissions. ICAO Secretariat Session 2: CORSIA MRV System: Monitoring of CO 2 Emissions ICAO Secretariat Monitoring, Reporting and Verification (MRV) of CO 2 Emissions A monitoring, reporting and verification (MRV) system is a key

More information

Ministry of Government and Consumer Services. ServiceOntario. Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report

Ministry of Government and Consumer Services. ServiceOntario. Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report Chapter 3 Section 3.06 Ministry of Government and Consumer Services ServiceOntario Standing Committee on Public Accounts Follow-Up on Section 4.09, 2015 Annual Report In March 2016, the Committee held

More information

NOTICES FROM MEMBER STATES

NOTICES FROM MEMBER STATES C 400/4 EN Official Journal of the European Union 13.11.2014 NOTICES FROM MEMBER STATES Notice from the Government of the Hellenic Republic concerning Directive 94/22/EC of the European Parliament and

More information

Connection Process: For Negotiated High Voltage Retail Customer Connections and Embedded Generators >30kW

Connection Process: For Negotiated High Voltage Retail Customer Connections and Embedded Generators >30kW Connection Process: For Negotiated High Voltage Retail Customer Connections and Embedded Generators >30kW August 2015 26 August 2015 ISSUE 10 ENQUIRIES: PLEASE CONTACT NETWORK CONNECTIONS ON 13 23 91 E

More information

REVIEW OF MANAGEMENT AND OVERSIGHT OF THE INTEGRATED BUSINESS MANAGEMENT SYSTEM (IBMS) January 16, 2009

REVIEW OF MANAGEMENT AND OVERSIGHT OF THE INTEGRATED BUSINESS MANAGEMENT SYSTEM (IBMS) January 16, 2009 APPENDIX 1 REVIEW OF MANAGEMENT AND OVERSIGHT OF THE INTEGRATED BUSINESS MANAGEMENT SYSTEM (IBMS) January 16, 2009 Auditor General s Office Jeffrey Griffiths, C.A., C.F.E. Auditor General City of Toronto

More information

CIP Standards Development Overview

CIP Standards Development Overview CIP Standards Development Overview CSSDTO706 Meeting with FERC Technical Staff July 28, 2011 Objectives Historical Timeline CIP-002-4 CIP-005-4 CIP Version 5 2 Project 2008-06 Overview FERC Order 706 SDT

More information

UAE Nuclear Energy Program Overview

UAE Nuclear Energy Program Overview UAE Nuclear Energy Program Overview Workshop on Nuclear Power Newcomers and International Cooperative Actions November 3 rd,2009 Ambassador Hamad Al Kaabi Permanent Representative of the UAE to the IAEA

More information

6 th European Energy Forum

6 th European Energy Forum 1 UNLOCKING SMART CAPABILITIES FOR LOCAL AUTHORITIES Jan Kowalczyk, CEO, Banner Group, Warsaw, Poland 6 th European Energy Forum Unlocking smart capabilities for local authorities Paris, 22-23 May 2017

More information

Public consultation on the revision of the Recommendation on relevant markets

Public consultation on the revision of the Recommendation on relevant markets PER E-MAIL cnect-relevant-markets@ec.europa.eu EUROPEAN COMMISSION DG Communications Networks, Content & Technology Regulatory Coordination and Markets Unit (B3) BU33 6/26 CM Groep Konijnenberg 30 4825

More information

GDPR Processor Security Controls. GDPR Toolkit Version 1 Datagator Ltd

GDPR Processor Security Controls. GDPR Toolkit Version 1 Datagator Ltd GDPR Processor Security Controls GDPR Toolkit Version 1 Datagator Ltd Implementation Guidance (The header page and this section must be removed from final version of the document) Purpose of this document

More information

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO

More information

Data Processing Agreement

Data Processing Agreement In accordance with the European Parliament- and Council s Directive (EU) 2016/679 of 27th April 2016 (hereinafter GDPR) on the protection of physical persons in connection with the processing of personal

More information

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket Clause 5 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 28, 2018. 5 Servicing Capacity Assignment

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

TERMS OF REFERENCE FOR AUDITS WASTE ELECTRICAL AND ELECTRONIC EQUIPMENT COMPLIANCE SCHEME [UPDATED 11 APRIL 2016]

TERMS OF REFERENCE FOR AUDITS WASTE ELECTRICAL AND ELECTRONIC EQUIPMENT COMPLIANCE SCHEME [UPDATED 11 APRIL 2016] TERMS OF REFERENCE FOR AUDITS BY AN AUTHORISED WASTE ELECTRICAL AND ELECTRONIC EQUIPMENT COMPLIANCE SCHEME [UPDATED 11 APRIL 2016] The auditor shall be independent, certified, and approved by the Environment

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

Ontario Smart Grid Forum: Support Presentation. Tuesday, March 8 th 2011

Ontario Smart Grid Forum: Support Presentation. Tuesday, March 8 th 2011 Ontario Smart Grid Forum: Support Presentation Tuesday, March 8 th 2011 Agenda Item # 1 S.G.F. Minutes 2 Agenda Item # 1: Minutes January 17 th 2011 minutes: no further comments received. Recommended as

More information

EX0-101_ITIL V3. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0. Exin EX0-101

EX0-101_ITIL V3.  Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0. Exin EX0-101 EX0-101_ITIL V3 Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Exin EX0-101 ITIL Foundation V 3.0 & ITIL Foundation Version: 8.0 Exin EX0-101 Exam Topic

More information

Municipal Broadband Project. City Council Meeting February 4, 2016

Municipal Broadband Project. City Council Meeting February 4, 2016 Municipal Broadband Project City Council Meeting February 4, 2016 Broadband Timeline 12 Months February March 2015 Feasibility Study April May 2015 Business Plan Development June August 2015 Renegotiation

More information

BENCHMARKING PPP PROCUREMENT 2017 IN ARMENIA

BENCHMARKING PPP PROCUREMENT 2017 IN ARMENIA BENCHMARKING PPP PROCUREMENT 2017 IN ARMENIA Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory

More information

REQUEST FOR PROPOSALS KOOTENAY SPORT FISHING PROJECT

REQUEST FOR PROPOSALS KOOTENAY SPORT FISHING PROJECT REQUEST FOR PROPOSALS KOOTENAY SPORT FISHING PROJECT PROVISION OF COPY WRITING FOR WESPORTFISH.CA WEB PORTAL CONTENT ISSUE DATE October 4, 2018 CLOSING TIME October 22, 2018 by 12:00 pm Pacific Time HARDCOPY

More information

DECISION ON INTERCONNECTION RATES FROM THE 36 th COUNCIL OF MINISTERS MEETING

DECISION ON INTERCONNECTION RATES FROM THE 36 th COUNCIL OF MINISTERS MEETING DECISION ON INTERCONNECTION RATES FROM THE 36 th COUNCIL OF MINISTERS MEETING At its thirty-sixth meeting held on March 9, 2018, the ECTEL Council of Ministers approved the recommendation for new interconnection

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

ITU Asia-Pacific Centres of Excellence Training on Conformity and Interoperability. Session 2: Conformity Assessment Principles

ITU Asia-Pacific Centres of Excellence Training on Conformity and Interoperability. Session 2: Conformity Assessment Principles ITU Asia-Pacific Centres of Excellence Training on Conformity and Interoperability Session 2: Conformity Assessment Principles 12-16 October 2015 Beijing, China Keith Mainwaring ITU Expert Agenda 1. Context

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

REPORT 2015/149 INTERNAL AUDIT DIVISION

REPORT 2015/149 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2015/149 Audit of the information and communications technology operations in the Investment Management Division of the United Nations Joint Staff Pension Fund Overall results

More information

GDPR AMC SAAS AND HOSTED MODULES. UK version. AMC Consult A/S June 26, 2018 Version 1.10

GDPR AMC SAAS AND HOSTED MODULES. UK version. AMC Consult A/S June 26, 2018 Version 1.10 GDPR AMC SAAS AND HOSTED MODULES UK version AMC Consult A/S June 26, 2018 Version 1.10 INDEX 1 Signatures...3 2 General...4 3 Definitions...5 4 Scoping...6 4.1 In scope...6 5 Responsibilities of the data

More information

ISO / IEC 27001:2005. A brief introduction. Dimitris Petropoulos Managing Director ENCODE Middle East September 2006

ISO / IEC 27001:2005. A brief introduction. Dimitris Petropoulos Managing Director ENCODE Middle East September 2006 ISO / IEC 27001:2005 A brief introduction Dimitris Petropoulos Managing Director ENCODE Middle East September 2006 Information Information is an asset which, like other important business assets, has value

More information

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NARUC Energy Regulatory Partnership Program The Public Services Regulatory Commission of Armenia and The Iowa Utilities Board Janet Amick Senior Utility

More information

BENCHMARKING PPP PROCUREMENT 2017 IN GABON

BENCHMARKING PPP PROCUREMENT 2017 IN GABON BENCHMARKING PPP PROCUREMENT 2017 IN GABON Regulatory and Institutional Framework for PPPs framework in your country allow procuring PPPs?. If yes, please specify the relevant regulatory framework and

More information

FNM Expansion Training Webinar

FNM Expansion Training Webinar FNM Expansion Training Webinar Cynthia Hinman Lead Client Trainer August 11, 2014 The information contained in these materials is provided for general information only and does not constitute legal or

More information

Advent IM Ltd ISO/IEC 27001:2013 vs

Advent IM Ltd ISO/IEC 27001:2013 vs Advent IM Ltd ISO/IEC 27001:2013 vs 2005 www.advent-im.co.uk 0121 559 6699 bestpractice@advent-im.co.uk Key Findings ISO/IEC 27001:2013 vs. 2005 Controls 1) PDCA as a main driver is now gone with greater

More information

Why you should adopt the NIST Cybersecurity Framework

Why you should adopt the NIST Cybersecurity Framework Why you should adopt the NIST Cybersecurity Framework It s important to note that the Framework casts the discussion of cybersecurity in the vocabulary of risk management Stating it in terms Executive

More information

C106: DEMO OF THE INFORMATION SECURITY MANAGEMENT SYSTEM - ISO: 27001:2005 AWARENESS TRAINING PRESENTATION KIT

C106: DEMO OF THE INFORMATION SECURITY MANAGEMENT SYSTEM - ISO: 27001:2005 AWARENESS TRAINING PRESENTATION KIT C106: DEMO OF THE INFORMATION SECURITY MANAGEMENT SYSTEM - ISO: 27001:2005 AWARENESS TRAINING PRESENTATION KIT Buy: http://www.globalmanagergroup.com/iso27001training.htm Chapter-1.0 CONTENTS OF ISO 27001-2005

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

ASIC RG206 CPD PROGRAM

ASIC RG206 CPD PROGRAM ASIC RG206 CPD PROGRAM FLEXIBLE FINANCIAL SERVICES This program meets the ASIC licence requirements for RG206. ACHIEVE YOUR ASIC LICENSING NEEDS WITH INDUSTRY EXPERTS. UNDERTAKE THIS ONLINE PROGRAM TO

More information

Specific topics covered in this brief include:

Specific topics covered in this brief include: April 2008 Summary Welcome to the Fifteenth National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 28, 2008, Transmission Update conference

More information

INNOVENT LEASING LIMITED. Privacy Notice

INNOVENT LEASING LIMITED. Privacy Notice INNOVENT LEASING LIMITED Privacy Notice Table of Contents Topic Page number KEY SUMMARY 2 ABOUT US AND THIS NOTICE 3 USEFUL WORDS AND PHRASES 4 WHAT INFORMATION DO WE COLLECT? 4 WHY DO WE PROCESS YOUR

More information

Information Technology General Control Review

Information Technology General Control Review Information Technology General Control Review David L. Shissler, Senior IT Auditor, CPA, CISA, CISSP Office of Internal Audit and Risk Assessment September 15, 2016 Background Presenter Senior IT Auditor

More information

From NAPAs to NAPs and LEDS, Green LECRDS to NAMAs

From NAPAs to NAPs and LEDS, Green LECRDS to NAMAs From NAPAs to NAPs and LEDS, Green LECRDS to NAMAs Frameworks to scale-up, coordinate and mainstream climate action Stephen Gold, Head, Green LECRDS Team, Principal Technical Advisor - UNDP Global Climate

More information

Contents USER S MANUAL 1

Contents USER S MANUAL 1 USER S MANUAL IRENA 2016 This manual was prepared by the International Renewable Energy Agency (IRENA) to provide comprehensive, step-by-step guidance to users of the web-based Sustainable Energy Marketplace

More information

Responsibilities of the Contracting Government

Responsibilities of the Contracting Government International Port Security Program Port Facility Security Audit Seminar Responsibilities of the MAR'01 1 Purpose The goal of this lesson is to provide a general understanding of the responsibilities s

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

Government Resolution No of February 15, Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security

Government Resolution No of February 15, Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security Government Resolution No. 2443 of February 15, 2015 33 rd Government of Israel Benjamin Netanyahu Resolution: Advancing National Regulation and Governmental Leadership in Cyber Security It is hereby resolved:

More information

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public

More information

bcuc British Columbia Utilities Commission

bcuc British Columbia Utilities Commission January 26, 2018 bcuc British Columbia Utilities Commission Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700

More information

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012 CAISO Metering & Telemetry Requirements Jeremy Laundergan - Director, EnerNex November 8, 2012 Background and Overview Both federal and state regulatory authorities are advocating the participation of

More information

USA HEAD OFFICE 1818 N Street, NW Suite 200 Washington, DC 20036

USA HEAD OFFICE 1818 N Street, NW Suite 200 Washington, DC 20036 US-China Business Council Comments on The Draft Measures for Security Review of Online Products and Services March 6, 2017 On behalf of the more than 200 members of the US-China Business Council (USCBC),

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

HIPAA Compliance Checklist

HIPAA Compliance Checklist HIPAA Compliance Checklist Hospitals, clinics, and any other health care providers that manage private health information today must adhere to strict policies for ensuring that data is secure at all times.

More information

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

Expanding Metering and Telemetry Options Technical Stakeholder Initiative Expanding Metering and Telemetry Options Technical Stakeholder Initiative August 28th, 2013 9:00 a.m. 12:00 p.m. (Pacific Time) Web Conference Information Web Conference Information Web Address (URL):

More information

Service Plan for Infrastructure Engineering

Service Plan for Infrastructure Engineering Service Plan for Infrastructure 2016-2019 Capital Regional District Date submitted: Revised: August 14, 2017 Table of Contents 1 Overview... 1 1.1 Division & Service Summary... 1 1.2 Organization Chart...

More information

LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE. Loughborough University (LU) Research Office SOP 1027 LU

LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE. Loughborough University (LU) Research Office SOP 1027 LU LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE Loughborough University (LU) Research Office SOP 1027 LU Process for Writing Study Protocols for NHS Research Sponsored by Loughborough

More information

Approved 10/15/2015. IDEF Baseline Functional Requirements v1.0

Approved 10/15/2015. IDEF Baseline Functional Requirements v1.0 Approved 10/15/2015 IDEF Baseline Functional Requirements v1.0 IDESG.org IDENTITY ECOSYSTEM STEERING GROUP IDEF Baseline Functional Requirements v1.0 NOTES: (A) The Requirements language is presented in

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) PHASE II REBUTTAL TESTIMONY KURTIS W. CASTLEBERRY DIRECTOR, RESOURCE PLANNING

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION ) ) ) ) ) ) ) ) PHASE II REBUTTAL TESTIMONY KURTIS W. CASTLEBERRY DIRECTOR, RESOURCE PLANNING BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF ENTERGY ARKANSAS, INC. S REQUEST FOR APPROVAL OF CERTAIN WHOLESALE BASE LOAD CAPACITY TO SERVE EAI CUSTOMERS AND A PROPOSED RIDER RECOVERY

More information

ISMS Implementation ISO IT Governance CEN 667

ISMS Implementation ISO IT Governance CEN 667 ISMS Implementation ISO 27003 IT Governance CEN 667 1 2 Standard Title: ISO/IEC 27003:2010 Information technology Security techniques Information security management system implementation guidance ISO/IEC

More information

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

Expanding Metering and Telemetry Options Technical Stakeholder Initiative Expanding Metering and Telemetry Options Technical Stakeholder Initiative April 24, 2013 Todays Agenda Time Topic Presenter 10:00 10:10 Opening Comments/Introductions Khaled Abdul-Rahman 10:10 10:20 Stakeholder

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

Building Information Modeling and Digital Data Exhibit

Building Information Modeling and Digital Data Exhibit Document E203 2013 Building Information Modeling and Digital Data Exhibit This Exhibit dated the day of in the year is incorporated into the agreement (the Agreement ) between the Parties for the following

More information

STAFF REPORT. January 26, Audit Committee. Information Security Framework. Purpose:

STAFF REPORT. January 26, Audit Committee. Information Security Framework. Purpose: STAFF REPORT January 26, 2001 To: From: Subject: Audit Committee City Auditor Information Security Framework Purpose: To review the adequacy of the Information Security Framework governing the security

More information

Information Technology Security Plan Policies, Controls, and Procedures Identify Governance ID.GV

Information Technology Security Plan Policies, Controls, and Procedures Identify Governance ID.GV Information Technology Security Plan Policies, Controls, and Procedures Identify Governance ID.GV Location: https://www.pdsimplified.com/ndcbf_pdframework/nist_csf_prc/documents/identify/ndcbf _ITSecPlan_IDGV2017.pdf

More information

Stakeholder Participation Guidance

Stakeholder Participation Guidance Climate, Community & Biodiversity Alliance, Verra Stakeholder Participation Guidance Guidance to support stakeholder participation in design, implementation and assessment of policies and actions May 2018

More information

Data Protection. Practical Strategies for Getting it Right. Jamie Ross Data Security Day June 8, 2016

Data Protection. Practical Strategies for Getting it Right. Jamie Ross Data Security Day June 8, 2016 Data Protection Practical Strategies for Getting it Right Jamie Ross Data Security Day June 8, 2016 Agenda 1) Data protection key drivers and the need for an integrated approach 2) Common challenges data

More information

Follow-up to Information Technology Security Audit

Follow-up to Information Technology Security Audit Follow-up to Information Technology Security Audit July 2004 Report Clearance Steps Follow-up process initiated September 2003 Report completed March 2004 Follow-up report approved by Departmental Audit

More information

Blackout 2003 Reliability Recommendations

Blackout 2003 Reliability Recommendations Blackout 2003 Reliability Recommendations 2005 NPCC General Meeting The Cranwell Resort Lenox, MA September 29, 2005 Philip A. Fedora Director, Market Reliability Interface Northeast Power Coordinating

More information

Proposed Implementation Plan to Adopt Updates of the Regulatory Air Dispersion Models referenced in O.Reg. 419/05 Presentation to AWMA Air

Proposed Implementation Plan to Adopt Updates of the Regulatory Air Dispersion Models referenced in O.Reg. 419/05 Presentation to AWMA Air Proposed Implementation Plan to Adopt Updates of the Regulatory Air Dispersion Models referenced in O.Reg. 419/05 Presentation to AWMA Air Practitioner s Group February 11 th, 2015 Overview Background

More information

Stakeholder Comments Template. Energy Storage and Distributed Energy Resources (ESDER) Phase 4. Submitted by Organization Date Submitted

Stakeholder Comments Template. Energy Storage and Distributed Energy Resources (ESDER) Phase 4. Submitted by Organization Date Submitted Stakeholder Comments Template Energy Storage and Distributed Energy Resources (ESDER) Phase 4 Submitted by Organization Date Submitted Ted Ko ted.ko@stem.com 510-381-6159 Stem, Inc. 2/27/19 The Issue Paper

More information

CIP Cyber Security Configuration Change Management and Vulnerability Assessments

CIP Cyber Security Configuration Change Management and Vulnerability Assessments CIP-010-2 3 Cyber Security Configuration Change Management and Vulnerability Assessments A. Introduction 1. Title: Cyber Security Configuration Change Management and Vulnerability Assessments 2. Number:

More information

The Open Group Certification for People. Training Course Accreditation Requirements

The Open Group Certification for People. Training Course Accreditation Requirements The Open Group Certification for People Training Course Accreditation Requirements Version 1.1 February 2014 Copyright 2013-2014, The Open Group All rights reserved. No part of this publication may be

More information

Smart Metering and Smart Grids: the Enel

Smart Metering and Smart Grids: the Enel Smart Metering and Smart Grids: the Enel experience Brussels, 8 March 2010 Dario Garofalo Regulatory and Environment, Enel SpA Agenda Smart grids potential Enel achievements and strategy Smart grids regulation

More information

Ontario Energy Board Cyber Security Framework

Ontario Energy Board Cyber Security Framework Ontario Energy Board Cyber Security Framework Accelerating compliance using Security-as-a-Service (SECaaS) Office: 888.876.0504 Email: info@stratejm.com Website: www.stratejm.com About this Whitepaper

More information

GUIDE TO TRUE ZERO WASTE CERTIFICATION

GUIDE TO TRUE ZERO WASTE CERTIFICATION GUIDE TO TRUE ZERO WASTE CERTIFICATION VERSION 1.0 September 2017 Green Business Certification, Inc (GBCI) Washington, DC OVERVIEW GBCI s TRUE Zero Waste certification program is used by facilities to

More information

Version 1/2018. GDPR Processor Security Controls

Version 1/2018. GDPR Processor Security Controls Version 1/2018 GDPR Processor Security Controls Guidance Purpose of this document This document describes the information security controls that are in place by an organisation acting as a processor in

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Utility Applications for Energy Storage. NY-BEST Capture the Energy 2018 March 15, 2018 Albany, NY

Utility Applications for Energy Storage. NY-BEST Capture the Energy 2018 March 15, 2018 Albany, NY Utility Applications for Energy Storage NY-BEST Capture the Energy 2018 March 15, 2018 Albany, NY Presenter Pete Falcier VP Analytics & Regulatory Affairs pfalcier@gienergyus.com (646) 786-1256 2 REV Demo

More information

Audit Report. Chartered Management Institute (CMI)

Audit Report. Chartered Management Institute (CMI) Audit Report Chartered Management Institute (CMI) 10 October 2012 Note Restricted or commercially sensitive information gathered during SQA Accreditation monitoring activities is treated in the strictest

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: January 30, 2019 Re: Decision on

More information

ISO27001:2013 The New Standard Revised Edition

ISO27001:2013 The New Standard Revised Edition ECSC UNRESTRICTED ISO27001:2013 The New Standard Revised Edition +44 (0) 1274 736223 consulting@ecsc.co.uk www.ecsc.co.uk A Blue Paper from Page 1 of 14 Version 1_00 Date: 27 January 2014 For more information

More information

Overview of DSASP; Telemetry/Communication Alternatives

Overview of DSASP; Telemetry/Communication Alternatives Overview of DSASP; Telemetry/Communication Alternatives The New York Independent System Operator Price Responsive Load Working Group May 12, 2010 Agenda Overview of DSASP Market Rules Current Communications/Telemetry

More information

ELECTIVE INTERCONNECTION FACILITIES

ELECTIVE INTERCONNECTION FACILITIES Title: ELECTIVE INTERCONNECTION FACILITIES Business Practice Department: External Affairs Document No: BP-0506 v3.0 Issue Date: 12-15-2017 Previous Date: 12/11/2006 Contents 1 PURPOSE... 2 2 DEFINITIONS...

More information

ITU Regional Workshop on Competition in Telecommunications Market Khartoum-Sudan, May Competition and Infrastructure Sharing

ITU Regional Workshop on Competition in Telecommunications Market Khartoum-Sudan, May Competition and Infrastructure Sharing ITU Regional Workshop on Competition in s Market Khartoum-Sudan, 24-26 May 2016 Competition and Infrastructure Sharing By Anne Rita Ssemboga Program Officer- ITU Regional Office for Africa anne.rita.ssemboga@itu.int

More information

BENCHMARKING PPP PROCUREMENT 2017 IN UGANDA

BENCHMARKING PPP PROCUREMENT 2017 IN UGANDA BENCHMARKING PPP PROCUREMENT 2017 IN UGANDA Regulatory and Institutional Framework for PPPs Does the regulatory framework in your country allow procuring PPPs?. specify the relevant regulatory framework

More information

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure

Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure 1 2 3 Introduction: Model Relationships Network Model Overview Example Commercial Model Overview Component Hierarchy & Definitions Example of Structure MISO Functions Served by the Network Model by the

More information

Kick-off Meeting DPIA Test phase

Kick-off Meeting DPIA Test phase Kick-off Meeting DPIA Test phase Directorate General for European Commission Brussels, 05/03/2015 Content Welcome and Introduction Upcoming Data Protection Reform Commission Recommendation Test Phase of

More information