Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Size: px
Start display at page:

Download "Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan"

Transcription

1 Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability of all existing and part of generation projects in the CAISO interconnection queue. The Phase I study included generation projects expected to be commercially operating during summer 2006 while Phase II focused primarily on new generation projects to be commercially operating after 2006 (up to queue number 92 in CAISO interconnection queue). However, as the new interconnection requests are gradually added to the queue, there are a number of new interconnection requests for which the Deliverability Assessments were not covered in the Phase II study. Starting from Phases I & II results, CAISO continues to perform Deliverability Assessment as required by LGIP tariff language. Due to the significantly different amount of interconnection requests received and different pace at which the LGIP study process moves along in three PTO areas, Phase III studied deliverability only on the northern (PG&E) system. The Phase III Deliverability Assessment completed in July, has covered generation interconnection requests from queue number in PG&E area. Since similar issues as in Phase III still exist, this Q3 Deliverability Assessment will focus on generation interconnection requests from queue number 128 to 212 in PG&E area and 93 to 156 in SCE and SDG&E. In addition, the study will update the deliverability of new generation projects from previous assessment because some generation projects have withdrawn from the queue since then. As a reminder, the Deliverability Study Methodology focuses on the Summer Peak load period, when the need for generation capacity is the greatest. The following excerpt from the Deliverability Study Methodology further characterizes the focus of the deliverability study methodology and its limitations. [A] generating facility s interconnection should be studied with the ISO Controlled Grid at peak load, under a variety of severely stressed conditions to determine whether, with the generating facility at full output, the aggregate of generation in the local area can be delivered to the aggregate of load on the ISO Controlled Grid, consistent with the ISO s reliability criteria and procedures. (This definition for deliverability comes from the FERC interconnection order, and this methodology for assessing deliverability has been developed from consultation with PJM officials about their already-established practices.)

2 In addition, the ISO recommends, based on guidance in FERC Order 2003, that the deliverability of a new resource should be assessed on the same basis as all other existing resources interconnected to the ISO Controlled Grid. Because a deliverability assessment will focus on the deliverability of generation capacity when the need for capacity is the greatest (i.e. peak load conditions), it will not ensure that a particular generation facility will not experience congestion during other operating periods. Therefore, other information (i.e. congestion cost analysis for all hours of the year) would be required in addition to the deliverability assessment to evaluate the congestion cost risk of energy purchase agreements, such as a take-or-pay contract with a particular generation facility. Base Case Study Year This Generation Deliverability Assessment will be performed on a power flow base case modeling the year Currently, all generation projects except one in the study have operating dates on or before the year 2011, and the ISO Transmission Planning process develops a detailed transmission plan for a minimum of five years. Therefore, the year 2012 is a good study year choice for the Annual Generation Deliverability Baseline analysis. As such, these Deliverability results will ensure the deliverability of generation for only the year 2012 modeling assumptions described in this study plan. For example, there may be a planned transmission project with initial operation in 2011, and without this project in service, a particular generation project may not be deliverable. However, for generators in this study that go into service between and 2010, System Impact Studies (SIS) have been or will be performed that should adequately assess their deliverability in earlier years. New Generation Projects to be included All new generation projects, with a queue number up to 212 in PG&E and up to 156 in SCE and SDG&E should be modeled in the study. New generation projects connected to the distribution system, but large enough to impact the transmission system should also be explicitly modeled on the electrically closest transmission bus. Appendix A provides information of these projects. New Transmission Projects to be included All ISO approved transmission projects expected to be operational by 2012 should be modeled in the base case. To account for uncertainties associated with some transmission projects such as PVD2 and LEAPS, a sensitivity study without these projects will also be performed. Transmission mitigation plans to mitigate deliverability problems identified in the Phase I and Phase II deliverability studies should also be modeled in the base case. In addition, all reliability and delivery transmission projects identified in generation interconnection studies for generation projects modeled should be included in the base case if they are needed to mitigate impacts identified under summer peak load conditions. If several alternative projects were identified in the SIS that solve the same summer peak problem, and the generation developer has not yet

3 selected a preferred option, then the project with the lowest expected cost that resolves the overload should be modeled, and noted in the case documentation. All transmission projects to mitigate non-summer peak congestion problems, already committed to by generation developers should also be modeled. Each of the PTOs will ensure that these projects are accurately modeled in the base case that they return to the ISO. A list of new transmission projects included in the base case along with their approval history should be provided to the ISO. Appendix B shows all transmission projects based on the CAISO transmission plan. In addition, Appendix C lists the network upgrades from each interconnection requests provided by PTOs. Transmission Facility Ratings The PTOs will ensure that transmission facility ratings are identical to ratings in the ISO transmission register. ISO approved Planned Transmission facilities upgrades that will increase the existing facility rating should be modeled in the base case. A list of new projects, including reconductorings and reratings, included in the base case, should be provided to the ISO. Load Modeling A coincident 1-in-5-year heat wave, ISO Control Area load will be modeled in the base case. Each of the PTOs will modify the load in their area of the starting base case to be 96% of their areas coincident 1 in 5 year heat wave load level. The 96% represents a diversity factor to convert the three area peak load levels to a coincident ISO peak load level. Generation Capacity (Pmax) and behind the meter load in the base case The generation capacity values used in the Phase II baseline study will also be used for this study unless more accurate data is available. Wind generation Pmax data will be updated using available data for the maximum production during summer peak load hours used to calculate the average production for Qualified Capacity valuation. The generation capacity values used in the Phase III study should be modeled in the base case. Generation Dispatch in the base cases Existing generation previously determined to be deliverable should be dispatched similar to the Phase III deliverability base case. New generation in the interconnection queue should be dispatched to balance load and resources. During the study, new generation will be grouped geographically and dispatched together in geographic groups, at a level similar to the existing generation, to balance loads and resources in the base case. Several base cases may be needed to assess the deliverability of each of the generation groups. In all cases, all new generation modeled should be available to be dispatched to full output, based on the study methodology, during the study. Import Levels The 2008 Maximum Import Capability for each branch group based on the methodology for Import Capability Assignment Process for resource adequacy (CAISO Tariff Section

4 ), has been modeled as fully utilized in the base case. Appendix D describes the amount and modeling of imports included in this study. The Study Contingencies to be analyzed The PTOs will provide contingency files with all NERC Category B, C.5 contingencies, and WECC-S2 contingencies on the 500 kv system (common corridor 500 kv lines) in a computer readable format along with a description of the format. The contingency files should include accurate modeling of all existing and ISO approved RAS/SPS assuming generation is at full output. The contingency files should be tested by the PTOs on the base case that they provide to the ISO for this study, to ensure that they are consistent. Updated detailed descriptions of the RAS/SPS included in the contingency files should also be provided by the PTOs. Study Methodology The study methodology is described in Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology on the ISO Website Study Results Generating units that do not pass the deliverability test will be identified. For each overloaded facility identified, the Deliverability Study methodology and tools will provide a list of all new generation units responsible for that overload. This list can then be ranked by queue position and units can be removed sequentially (last on, first off) until the overload is eliminated. The units removed would not pass the deliverability test. The ISO will also include in the study results, for PTO and stakeholder review, new conceptual transmission project alternatives that would allow the new generation projects to pass the deliverability test, or to correct deliverability problems that remain after all new generation projects are removed. The ISO will rely on available transmission studies, as much as possible, in the development of conceptual transmission project alternatives. Study Schedule CAISO anticipates completing this study by mid-november. Task Description Task duration 1 ISO to provide Q3 generation project and transmission project templates 2 PTOs to: 21 days - Fill in generation, transmission projects, after task 1 and network upgrades list (Appendix B,C) - Provide base case with accurate modeling in their area and change files to the ISO. Due Date August 29, 19,

5 3 ISO to consolidate base cases received from PTOs to create Q3 base case and finalize the base case. 4 PTOs will provide information on changes to contingency files and RAS/SPS needed due to modeling Q3 generation and transmission projects 5 ISO to provide list of new units that do not pass the deliverability test 6 ISO to work with PTOs on identifying new conceptual transmission project alternatives that would ensure deliverability for undeliverable units identified in step 7. 7 days after task 2 7 days after task 2 14 days after task 4 14 days after task 5 7 ISO to provide first draft Q3 Report 7 days after task 6 8 PTOs to provide initial comments on first draft 7 days Q3 Report, after task 7 9 ISO to incorporate PTO comments, post draft 7 days report, and schedule stakeholder meeting after task 8 26, 26, October 10, October 24, October 31, November 7, November 14,

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted By Company Date Submitted Shannon Eddy (shannon@consciousventuresgroup.com) Rachel Gold (Rachel@consciousventuresgroup.com) Large-scale Solar Association (LSA) December

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Hetch Hetchy Water and Power of the City and County of San Francisco Joint Transmission Planning Base Case Preparation Process This is a living document. Please

More information

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 July 30, 2010 Re: Q2 Quarterly

More information

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting Contingency Reserve Sharing; Ancillary Services Market Presented to the JCM Joint Stakeholder Meeting 1 Agenda Products and Nature of Current Services Contingency Reserve Sharing Group (CRSG) Agreement

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Steve Rutty Director, Grid Assets Lou Fonte Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Lead Engineer, Grid Assets September 3, 2014 Transmission Planning

More information

2017 RTEP Assumptions for Western Sub-Region

2017 RTEP Assumptions for Western Sub-Region CLICK TO EDIT MASTER TITLE STYLE Click to edit Master text styles 2017 RTEP Assumptions for Western Sub-Region CLICK 2017 RTEP TO EDIT Assumptions MASTER TITLE STYLE Click Duquesne to edit uses Master

More information

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission The following White Paper proposes a draft methodology for determining the incremental amount of transfer capability that would be the basis for the quantity of Merchant Transmission CRRs to be allocated

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

Entergy Arkansas, Inc. Transition Plan Technical Conference #1

Entergy Arkansas, Inc. Transition Plan Technical Conference #1 Entergy Arkansas, Inc. Transition Plan Technical Conference #1 May 5, 2010 1 Why Technical Conferences? Complex subject matter Venue for stakeholders to develop an awareness and understanding of the issues

More information

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way California Independent System Operator October 30, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Open Access Transmission Tariff of Southern Companies

Open Access Transmission Tariff of Southern Companies Open Access Transmission Tariff of Southern Companies Procedures for Reserving Transmission Capacity for Future Load Growth, Designating/Undesignating Network Resources, and Arranging for Other Related

More information

MISO-PJM Cross-Border Planning. February 19, 2014 MISO-PJM JCM

MISO-PJM Cross-Border Planning. February 19, 2014 MISO-PJM JCM MISO-PJM Cross-Border Planning February 19, 2014 MISO-PJM JCM Planning Issues at the Seam 2 Background JOA Historical and Projected Congestion Study - 2012 to 2014 Future Scenario based 80+ major project

More information

_ Dear Secretary Bose: The attached. Folsom, CA

_ Dear Secretary Bose: The attached. Folsom, CA California Independent System Operator June 29, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

Specific topics covered in this brief include:

Specific topics covered in this brief include: April 2008 Summary Welcome to the Fifteenth National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 28, 2008, Transmission Update conference

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

Agreements & Queue Management

Agreements & Queue Management Agreements & Queue Management Resource Interconnection Fair February 24, 2016 Page 1 Interconnection Process Map You are here Page 2 Topics 1. Generator Interconnection Agreement (GIA) 2. Affected Systems

More information

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Agenda Item 1 Administrative Items AQITF Chairman Jim McAvoy called the meeting to order at 9:00 p.m.

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Review of Generator Interconnection Agreements and Procedures American Wind Energy Association Docket No. RM16-12-000 Docket No. RM15-21-000

More information

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Background Power Grid has evolved from a vertically integrated

More information

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019 ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019 Introduction Throughout 2015 and 2016 the structure of committees in the Western Electricity

More information

Small Hydro Regulatory and Permitting Requirements California

Small Hydro Regulatory and Permitting Requirements California Small Hydro Regulatory and Permitting Requirements California Lon W. House, Ph.D. 530.409.9702 Water & Energy Small Hydro Regulatory and Compliance FERC QF, Small Hydro License or Exemption EIA Generator

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Unofficial Comment Form

Unofficial Comment Form Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Midwest ISO. Module B- Network Integration Transmission Service Overview. Vikram Godbole Lead, Transmission Service Planning October 20, 2010

Midwest ISO. Module B- Network Integration Transmission Service Overview. Vikram Godbole Lead, Transmission Service Planning October 20, 2010 Midwest ISO Module B- Network Integration Transmission Service Overview Vikram Godbole Lead, Transmission Service Planning October 20, 2010 DISCUSSION POINTS 1. What is NITS 2. How to get Designated NITS

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: January 30, 2019 Re: Decision on

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

EXHIBIT A: PROJECT SCOPE AND SCHEDULE The Project consists of the activities and delivery dates identified in this Exhibit A, implemented in accordance with the Agreement. The Parties have included a schedule

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT THIS AGREEMENT is made and entered into this day of, 20 by and between [Customer Name (Project Name, QXXXX)], a [Type of company] organized

More information

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

Expanding Metering and Telemetry Options Technical Stakeholder Initiative Expanding Metering and Telemetry Options Technical Stakeholder Initiative August 28th, 2013 9:00 a.m. 12:00 p.m. (Pacific Time) Web Conference Information Web Conference Information Web Address (URL):

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Implementation Plan for COM-001-2

Implementation Plan for COM-001-2 Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.

More information

Business Practice Manual for Managing Full Network Model. Version 910

Business Practice Manual for Managing Full Network Model. Version 910 Business Practice Manual for Managing Full Network Model Version 910 Last Revised: September 7November 16, 2016 Approval History Approval Date: October 1, 2009 Effective Date: October 1, 2009 BPM Owner:

More information

132 FERC 61,005 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

132 FERC 61,005 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 132 FERC 61,005 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, and John R. Norris. California Independent

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

WECC Criterion INT-001-WECC-CRT-3

WECC Criterion INT-001-WECC-CRT-3 WECC Criterion INT-001-WECC-CRT-3 A. Introduction 1. Title: e-tag Requirements for WECC including Wrongful Denial of Request for Interchange (RFI) 2. Number: INT-001-WECC-CRT-3 3. Purpose: To manage Arranged

More information

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012 CAISO Metering & Telemetry Requirements Jeremy Laundergan - Director, EnerNex November 8, 2012 Background and Overview Both federal and state regulatory authorities are advocating the participation of

More information

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009 Midwest ISO Overview - ATC Customer Meeting February 26, 2009 Agenda Overview January 2009 Dashboard Module E RAR Timeline Questions 2 Overview January was characterized by seasonal cold temperatures,

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information

Table of Contents. TOP TOP BA Data Request and Specification Guidelines. Operating Procedure

Table of Contents. TOP TOP BA Data Request and Specification Guidelines. Operating Procedure No. 3140 Table of Contents Purpose... 2 Responsibilities... 2 2. Scope/Applicability... 4 2.1 Background... 4 2.2 Scope / Applicability... 4 3. Detail... 5 3.1... 5 Introduction... 5 3.2 Data Specification

More information

Stakeholder Comments Template. Energy Storage and Distributed Energy Resources (ESDER) Phase 4. Submitted by Organization Date Submitted

Stakeholder Comments Template. Energy Storage and Distributed Energy Resources (ESDER) Phase 4. Submitted by Organization Date Submitted Stakeholder Comments Template Energy Storage and Distributed Energy Resources (ESDER) Phase 4 Submitted by Organization Date Submitted Ted Ko ted.ko@stem.com 510-381-6159 Stem, Inc. 2/27/19 The Issue Paper

More information

I. Tariff language for Transmission Losses Applied to Monthly Reported Network Loads: (for tariff)

I. Tariff language for Transmission Losses Applied to Monthly Reported Network Loads: (for tariff) I. Tariff language for Transmission Losses Applied to Monthly Reported Network Loads: (for tariff) * MISO will add the underlined text provided by the Owners Committee to Section 34.2 of the Tariff with

More information

State Perspectives on the Midwest ISO regional Stakeholder Process: The Indiana Utility Regulatory Commission

State Perspectives on the Midwest ISO regional Stakeholder Process: The Indiana Utility Regulatory Commission State Perspectives on the Midwest ISO regional Stakeholder Process: The Indiana Utility Regulatory Commission October 21, 2010 Dave Johnston Beth Krogel Roads Indiana Utility Regulatory Commission (IURC)

More information

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for the California Solar Initiative, the Self-Generation Incentive

More information

OPUC Workshop March 13, 2015 Cyber Security Electric Utilities. Portland General Electric Co. Travis Anderson Scott Smith

OPUC Workshop March 13, 2015 Cyber Security Electric Utilities. Portland General Electric Co. Travis Anderson Scott Smith OPUC Workshop March 13, 2015 Cyber Security Electric Utilities Portland General Electric Co. Travis Anderson Scott Smith 1 CIP Version 5 PGE Implementation Understanding the Regulations PGE Attended WECC

More information

Designation and Termination of Network Resources

Designation and Termination of Network Resources Transmission & Reliability Services Business Practice: Designation and Termination of Network Resources Posted: February 8, 2010 Effective: May 3, 2010 Revision No.: 5 1. Purpose The purpose of this business

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Generation Interconnection (GI) as an Input to Multi-Driver Approach

Generation Interconnection (GI) as an Input to Multi-Driver Approach Generation Interconnection (GI) as an Input to Multi-Driver Approach August 26, 2014 Example 1 Generator requires upgrade that will be completely replaced by baseline RTEP upgrade Generator enters queue

More information

Minnesota Hosting Capacity Analysis

Minnesota Hosting Capacity Analysis Minnesota Hosting Capacity Analysis MIPSYCON November 8, 2017 Chris Punt, P.E. Outline What is Hosting Capacity? Background DRIVE Results Visualization Accuracy Timeline Next Steps 2 What is Hosting Capacity?

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1 OATT Attachment Q-1 First Revision of Page 1 ATTACHMENT Q-1 Dynamic Scheduling This attachment contains the eligibility requirements and the terms and conditions for the provision of dynamic scheduling

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

BPM Change Management Meeting

BPM Change Management Meeting BPM Change Management Meeting August 22, 2017 Julia Payton BPM Change Management Process BPM_CM@caiso.com Agenda BPM Change Management Meeting, August 22, 2017 Topic Introduction/meeting overview Discussion

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

New Resource Implementation & Market Modeling

New Resource Implementation & Market Modeling New Resource Implementation & Market Modeling Resource Interconnection Fair February 24, 2016 Page 1 Topics Discuss the New Resource Implementation (NRI) process. Structure and timeline for any resource

More information

July 26, Dear Mr. Millar:

July 26, Dear Mr. Millar: July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 Dear Mr. Millar: As you are aware, Clean

More information

Business Practice Manual for Managing Full Network Model. Version 1213

Business Practice Manual for Managing Full Network Model. Version 1213 Business Practice Manual for Managing Full Network Model Version 1213 Last Revised: January 3, 2018January 24, 2018 Approval History Approval Date: October 1, 2009 Effective Date: October 1, 2009 BPM Owner:

More information

Annual Policy Initiatives Roadmap Process Straw Proposal

Annual Policy Initiatives Roadmap Process Straw Proposal Annual Policy Initiatives Roadmap Process Straw Proposal July 18, 2017 Copyright 2017 Table of Contents 1 Introduction... 2 2 Proposal... 3 2.1 Policy Initiatives Catalog... 3 Stakeholder Comments... 4

More information

Reliability Coordinator Procedure PURPOSE... 1

Reliability Coordinator Procedure PURPOSE... 1 No. RC0550 Restriction: Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 1.1.1. CAISO RC... 2 1.1.2. RC Working Groups... 2 1.1.3. Operationally Affected Parties... 2 1.1.4. RC Oversight Committee...

More information

Reliability Coordinator Procedure

Reliability Coordinator Procedure No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

Upper vs. Lower Case BTMG. Resource Adequacy Subcommittee October 11, 2017

Upper vs. Lower Case BTMG. Resource Adequacy Subcommittee October 11, 2017 Upper vs. Lower Case BTMG Resource Adequacy Subcommittee October 11, 2017 Purpose & Key Takeaways Purpose: Address issue assigned to RASC by SC: Define lower case btmg and/or criteria such as MW threshold

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

ATTACHMENT I: Generator Interconnection Procedures (GIP)

ATTACHMENT I: Generator Interconnection Procedures (GIP) ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections

More information

ISO New England Data Modeling Requirements

ISO New England Data Modeling Requirements A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda

More information

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER WELCOME Draft Energy Storage Roadmap Draft Matrix Stakeholder Call November 3, 2014 San Francisco SAFER, SMARTER, GREENER Alignment of Proposed Actions to Storage Configuration and Use Cases Robert Anderson,

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

Generation Interconnection (GI) as an Input to Multi-Driver Approach

Generation Interconnection (GI) as an Input to Multi-Driver Approach eneration Interconnection (I) as an Input to Multi-Driver Approach September 19, 2014 Example 1 enerator requires upgrade that will be completely replaced by baseline RTEP upgrade enerator enters queue

More information

Compliance Enforcement Initiative

Compliance Enforcement Initiative Compliance Enforcement Initiative Filing and Status Update November 2, 2011 Rebecca Michael Status of the Filings NERC filed several components of the Compliance Enforcement Initiative on September 30,

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

Slow Response Local Capacity Resource Assessment CAISO-CPUC Joint Workshop

Slow Response Local Capacity Resource Assessment CAISO-CPUC Joint Workshop Slow Response Local Capacity Resource Assessment CAISO-CPUC Joint Workshop October 4, 2017 Revision as of 10/11/17: Revisions were made on page 62 and page 64 is marked for deletion ISO Public REVISED

More information

Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative. Revised Scope and Schedule

Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative. Revised Scope and Schedule Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative Revised Scope and Schedule June 25, 2015 Table of Contents 1 Introduction... 3 2 Background... 3 3 Stakeholder process...

More information

MISO PJM Joint and Common Market Cross Border Transmission Planning

MISO PJM Joint and Common Market Cross Border Transmission Planning MISO PJM Joint and Common Market Cross Border Transmission Planning May 30, 2018 1 Coordinated System Plan Study 2 Using information from the March 30 Annual Issues Review, the JRPC has decided to perform

More information

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM)

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM) Business Practice Manual For Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM) Version 1.0 Last Revised: June 176July 26, 2013 Approval History Approval Date: MM DD YYYY07/26/2013

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

EIM Entity Readiness Criteria May 6, 2015

EIM Entity Readiness Criteria May 6, 2015 EIM Entity Readiness Criteria May 6, 2015 FERC Directive Regarding Readiness Criteria We therefore direct CAISO to submit a compliance filing within 60 days of issuance of this order, to revise the EIM

More information

Business Practice Manual Change Management Meeting

Business Practice Manual Change Management Meeting Business Practice Manual Change Management Meeting Name Chris Kirsten Date May 24, 2011 Web Address: https://www.webmeeting.att.com Meeting Number: 5114682337 Access code: 9842446 Teleconference Dial-in

More information

MOD Transmission Reliability Margin Implementation Document

MOD Transmission Reliability Margin Implementation Document Transmission Margin Implementation Document Transmission Margin Implementation Document For NERC Page 1 of 7 Transmission Margin Implementation Document 1.0 Purpose The California Independent System Operator

More information

Available Transfer Capability Definitions and Determination

Available Transfer Capability Definitions and Determination Available Transfer Capability Definitions and Determination A framework for determining available transfer capabilities of the interconnected transmission networks for a commercially viable electricity

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Caithness Long Island II, LLC ) ) Complainant, ) ) v. ) Docket No. EL15-84-000 ) New York Independent System Operator, Inc. ) )

More information