1 Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

2 System Impact Study Report TABLE OF CONTENTS 1.0 Description of the Project Scope and Objective of the Study Facilities Analysis Results Point of Interconnection Scope of Work Interconnection Customer s Small Generating Facility (Collector substation: Chautauqua) Interconnection Customer will be responsible to Transmission Provider will be responsible to kV Pavant Chautauqua Tie Line Requirements Interconnection Customer will be responsible to Transmission Provider will be responsible to Transmission Provider s Substation (Pavant) Transmission Provider will be responsible to Other sites Transmission Provider will be responsible to Cost Estimate Schedule Appendices Appendix A: Cost Estimate Appendix B: Schedule... 9 i March 7, 2016

3 1.0 DESCRIPTION OF THE PROJECT ( Interconnection Customer ) proposed interconnecting 20 MW of new generation to PacifiCorp s ( Transmission Provider ) Pavant substation located in Millard County, Utah. The project ( Project ) will consist of eleven (11) TMEiC Solar Ware Samurai PVL-L1833GRM inverters at 1818 kw each for a total output of 20 MW. The requested commercial operation date is December 1, Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Transmission Provider has assigned the Project Q SCOPE AND OBJECTIVE OF THE STUDY The objective of the Facilities Study is to: Specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). Identify: (1) The electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters, and other station equipment. (2) The nature and estimated cost of the Transmission Provider s Interconnection Facilities and Upgrades necessary to accomplish the interconnection. (3) An estimate of the time required to complete the construction and installation of such facilities. 3.0 FACILITIES ANALYSIS RESULTS All active higher priority transmission service and/or generator interconnection requests will be considered in this study. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change. For study purposes there are two separate queues: o Transmission Service Queue: to the extent practical, all network upgrades that are required to accommodate active transmission service requests submitted prior to Interconnection Customer s generation interconnection request will be modeled in this study. Generation Interconnection Queue: when relevant, interconnection facilities associated with higher queue interconnection requests will be modeled in this study. However, no generation will be simulated from any higher queued project unless a commitment has been made to obtain transmission service. Interconnection Customer s request for interconnection service in and of itself does not convey transmission service. This study assumes the Project will be integrated into Transmission Provider s system at the agreed upon and/or proposed Point of Interconnection. 1 March 11, 2016

4 Interconnection Customer will construct and own the any facilities required between the Point of Interconnection and the Project unless specifically identified by the Transmission Provider. Generator tripping may be required for certain outages. All facilities will meet or exceed the minimum Western Electricity Coordinating Council ( WECC ), North American Electric Reliability Corporation ( NERC ), and Transmission Provider performance and design standards This report is based on information available at the time of the study. It is Interconnection Customer s responsibility to check the Transmission Provider s web site regularly for transmission system updates ( 3.1 POINT OF INTERCONNECTION The proposed Small Generating Facility is to be interconnected at Transmission Provider s Pavant substation. Figure 1 is a one-line diagram that illustrates the interconnection of the proposed Small Generating Facility to the Transmission Provider s system. 2 March 11, 2016

5 Change of Ownership 52-L1 12/16/20 MVA Z = 8 % 52-C1 52-C kv Q0684 Substation Loads Pavant Substation Q kv 43 Arapahoe Substation Loads M 1,550 feet 46 kv Point of Interconnection Figure 1: Simplified System One-line Diagram 3 March 11, 2016

6 4.0 SCOPE OF WORK 4.1 INTERCONNECTION CUSTOMER S SMALL GENERATING FACILITY (COLLECTOR SUBSTATION: CHAUTAUQUA) The following outlines the design, procurement, installation, testing and ownership of equipment for Interconnection Customer s Small Generating Facility Interconnection Customer will be responsible to As the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases, a standard model from the WECC Approved Dynamic Model Library is required prior to interconnection. The list of approved generator models is continually updated and is available on the website. Obtain all necessary permits, lands, Rights of Way and easements required for the construction and continued maintenance of the Q0684 Small Generating Facility and the radial interconnect line to the Point of Interconnection substation. All easements and permits shall be recorded in the name of the Transmission Provider and shall be on forms acceptable to the Transmission Provider. All easements and rights of way will be obtained for durations acceptable to the Transmission Provider; this includes all permits/easements for ingress and egress prior to the start of construction. Engineer, purchase, and construct all facilities required for the Q0684 collector station except for those common facilities/components indicated as supplied by the Transmission Provider. Install one (1) 72.5kV 1200A circuit breaker at the Small Generating Facility for connection to the 46kV radial interconnect line. The Transmission Provider will review the specifications for the breaker to insure compatibility with the control and protection schemes. Design and procure protective relays for fault detection for the 46kV transformer and 34.5kV lines. Provide a secure space with outside access in the Small Generating Facility control building for installation of the Transmission Provider owned and maintained panels and racks. Front and rear access will be required for this equipment. The control house shall be temperature controlled to the tolerance of the electronic communications equipment being installed. Provide power supplies for common equipment at configurations and voltages as specified by the Transmission Provider. Provide a 130VDC or 48VDC battery and charger system that will support the Transmission Provider s electronic communications equipment with at least 24 hour backup. The following equipment will be owned and maintained by the Transmission Provider and located in the Small Generating Facility control building: 1. Relay panel with protective relays 2. RTU, fuse panel, rack and other miscellaneous equipment 3. DC-DC converters 4. Multiplex equipment with the appropriate channel cards and a fiber patch panel. 4 March 11, 2016

7 5. Router for Ethernet connectivity Install one (1) 3 conduit from collector substation deadend structure to the control house to be used for the fiber optic cable. Transmission Provider will provide installation and material specifications. Interconnection Customer will need to provide the secondary outputs from two three phase sets of current transformers from their 72.5 kv circuit breaker and secondary output from a three phase set of 46 kv voltage transformers for the line relays. The line relays will trip Interconnection Customer s 72.5 kv circuit breaker for faults on the 46 kv tie line to Pavant substation. The relays in this panel will communicate with the relays to be installed in Pavant substation for the detection of faults on the 46 kv line. Interconnection Customer RTU data points will all be hard wired to Transmission Provider s RTU Transmission Provider will be responsible to Provide a list of data inputs and outputs required for protection, control and data collection in accordance with the interconnection agreement. Supply all specifications required to facilitate design of the Small Generating Facility Design, procure, install, own and maintain a line protection relay system for fault detection on the 46kV radial transmission lines to the Pavant substation. This panel will be installed in the Q0684 Small Generating Facility control house, in a secure area accessible to the Transmission Provider, and will communicate via fiber cable with the relay to be installed in the Pavant substation. Design, purchase, install, own, and maintain an RTU, multiplex equipment and a fiber patch panel in the Q0684 control building. This equipment will be powered by either a 48VDC or a 125VDC battery and charger system from the Q0684 Small Generating Facility. Design, procure, install, own and maintain the underground ADSS fiber optic cable from the substation deadend tower to the control building located in the Q0684 Small Generating Facility. The cable and innerduct are to be installed in the conduit provided by Interconnection Customer. Perform final checkout and testing of the radial transmission line protection and control panels. Perform, in conjunction with Interconnection Customer, final checkout and testing of the communications devices for data acquisition and control KV PAVANT CHAUTAUQUA TIE LINE REQUIREMENTS Interconnection Customer will be responsible to Obtain all necessary permits, easements, and rights of way for the construction of the 46kV radial interconnection line from the Point of Interconnection substation to the Q0684 Small Generating Facility. Design their substation deadend to the specifications provided by the Transmission Provider. 5 March 11, 2016

8 4.2.2 Transmission Provider will be responsible to Design, install, own and maintain the 46kV radial feeder from the Q0684 Small Generating Facility to the Pavant substation. Design, install, own and maintain the fiber optic communication system from the Pavant substation control building to the Q0684 Small Generating Facility control building. The fiber optic cable will be OPGW installed in the shield wire position of the 46kV transmission line. 4.3 TRANSMISSION PROVIDER S SUBSTATION (PAVANT) The following outlines the design, procurement, installation, testing and ownership of equipment for Transmission Provider s Pavant substation Transmission Provider will be responsible to Design, procure, install, own and maintain a new 46kV line position, complete with circuit breaker, switches, instrument transformers and all necessary appurtenances, including all protective relays. Design, procure, install, own and maintain a line protection relay system for fault detection on the 46kV radial transmission lines to the Q0684 Small Generating Facility. This panel will communicate via fiber cable with the relay to be installed in the Q0684 Small Generating Facility. The line differential relay will trip Interconnection Customer s 34.5kV breakers as well as the breaker at Pavant substation in the tie line position. Design, procure, install, own and maintain a protective relay to monitor the voltage magnitude and frequency. If the voltage magnitude or frequency is outside of the normal operation range this relay will send a trip signal through the communication system for the line current differential relay system to cause Interconnection Customer s 34.5kV line breakers at the collector substation to open. Tripping the line breakers instead of the transformer breaker will facilitate the restoration of the Small Generating Facility. Design, procure, install, own and maintain a protective relay to monitor the current flow on the Pavant Sigurd 230kV line to detect an overload condition. The 46 kv breaker in Pavant substation to be installed for this Project will be tripped for the operation either of the kv transformer lockout relays, if CB 216 and CB 226 are opened, or if the Sigurd line is overloaded. The transformer lockout relays currently exist. The new relay will monitor the status of the line breakers to generate a trip for either the overloading of the line or the loss of the line. Perform final checkout and testing/commissioning of the protective relays. Design, purchase, install, and own the revenue metering system for the Q0684 Small Generating Facility, to be installed at the Pavant substation. The metering will be designed as bidirectional and rated for the total net generation of the Small Generating Facility including the retail load (per tariff) delivered to Interconnection Customer. This includes the metering transformers, metering panels, junction boxes and secondary metering wire. Perform final checkout and testing/commissioning of the metering system. 6 March 11, 2016

9 Install an Ethernet connection for retail sales and generation accounting via the MV- 90 translation system. Design, procure, install, own and maintain the underground ADSS fiber optic cable from the collector substation deadend tower to the control building located in the Pavant substation. Fiber optic cards will be installed in the existing Pavant multiplex to provide for connectivity to the new multiplex installed in the Q0684 collector substation control house. The channels required at the Pavant substation include: o A channel for the SEL-3530 and primary meter o A channel for the backup meter o A channel for a RAS relay circuit between the Sigurd substation and the Pavant substation via a Interconnection Customer supplied leased circuit between Richfield Service Center and Delta Service Center. o An additional multiplex will be installed to provide for the required RAS redundancy requirements. 4.4 OTHER SITES The following outlines the design, procurement, construction, installation, and ownership of equipment past the Point of Interconnection Transmission Provider will be responsible to Design, procure, install, own and maintain a protective relay to key transfer trip to Pavant substation for the opening of the Sigurd substation end of the line so that the status of the Sigurd breakers will be known at the Pavant end of the line. Additional multiplex equipment will be required at the Sigurd substation, the Delta Service Center, and the Richfield Service Center to provide for redundant RAS communications between the Sigurd 230 kv substation and the Pavant substation. 5.0 COST ESTIMATE See attached Appendix A. 6.0 SCHEDULE See attached Appendix B. 7.0 APPENDICES 7 March 11, 2016

10 7.1 APPENDIX A: COST ESTIMATE The following estimate represents only scopes of work that will be performed by the Transmission Provider. Costs for any work being performed by Interconnection Customer are not included. Direct Assigned Interconnection Customer s Small Generating Facility $413,000 Add RTU, relays and communication. Transmission tie line and Fiber $ 345,000 Add 46kV transmission line from Q0684 Small Generating Facility to Pavant substation Sigurd substation $132,000 Add B stage keying of transfer trip Control Centers $ 52,000 Modify communications at control centers Network Upgrades Direct Assigned Total $941,000 Pavant substation $1,608,000 Add new 46kV breaker bay Network Upgrade Total $1,608,000 Project Totals $2,550,000 Note: Costs for all excavation, duct installation and easements shall be borne by Interconnection Customer and are not included in this estimate. This estimate approximates the costs incurred by Transmission Provider in interconnecting this generator to Transmission Provider s electrical system. Interconnection Customer will be responsible for all actual costs, regardless of the estimated costs communicated to or approved by Interconnection Customer. 8 March 11, 2016

11 7.2 APPENDIX B: SCHEDULE Milestone Date Small Generator Interconnect Agreement Signed March 4, 2016 Provision of Financial Security March 4, 2016 *RAS Design Submission to WECC April 1, 2016 **Energy Imbalance Market Modeling Data Submittal May 1, 2016 Interconnection Customer Property/Permits/ROW Procured June 1, 2016 Installation and Construction Begins August 1, 2016 Construction Complete October 31, 2016 Interconnection Customer Facilities Receive Backfeed November 19, 2016 Initial Synchronization/Generation Testing December 2, 2016 Commercial Operation Date December 16, 2016 *The WECC RAS committee meetings have not yet been formally scheduled. As such, this milestone is an approximate date. Commercial operation is contingent on approval of the RAS design by WECC. As the Transmission Provider has no authority to require specific timing of said approval, the remaining milestones could be impacted. It is possible that approval may not be provided in a timeframe to support Interconnection Customer s desired commercial operation date. **Any design modifications to Interconnection Customer s Small Generating Facility after this date requiring updates to the Transmission Provider s network model will result in a minimum of 3 months added to all future milestones including Commercial Operation. Please note, the time required to perform the scope of work identified in this report appears to result in a timeframe that does not support Interconnection Customer s requested Commercial Operation date of December 1, March 11, 2016

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662 Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately

More information

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022 Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

March 4, Mona Substation Line position & assoc relaying, communications & metering

March 4, Mona Substation Line position & assoc relaying, communications & metering 700 N.E. Multnomah, Suite 550 Portland, OR 97232 March 4, 2004 Merrill Brimhall PacifiCorp Merchant 201 South Main, Suite 2200 Salt Lake City, Utah 84111 Dear Mr. Brimhall: PacifiCorp Transmission Systems

More information

ATTACHMENT I: Generator Interconnection Procedures (GIP)

ATTACHMENT I: Generator Interconnection Procedures (GIP) ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

WN U-60 Original Sheet No. 152

WN U-60 Original Sheet No. 152 WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet Reference: ZD23 Version: 1.1 Issue date: 15 May 2014 Contents 1 Scope... 3 2 Deer Park Terminal

More information

IntelliTeam II Automatic Restoration System

IntelliTeam II Automatic Restoration System No system is too complex to automate with... IntelliTeam II Automatic Restoration System Introduced in 1997, the IntelliTeam Automatic Restoration System was the first product of its kind. Using peer-to-peer

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

REAL-TIME MONITORING DATA SPECIFICATION

REAL-TIME MONITORING DATA SPECIFICATION REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...

More information

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

Small Generator Interconnection System Impact Study Report. Completed for Q0373

Small Generator Interconnection System Impact Study Report. Completed for Q0373 Small Generator Interconnection Completed for Q0373 Proposed Interconnection To the Existing Q0006 500kV substation on the 13.8kV side of the bus July 7, 2011 TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING

More information

Presented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011

Presented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011 Photovoltaic Solutions Make the most of your solar PV project Presented by: Oscar Araujo Photovoltaic Solutions Manager 4 th Canadian German Solar PV Conference March 2 nd 2011 Agenda Solutions for Renewable

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information

Synchronous switching of distribution sub networks

Synchronous switching of distribution sub networks Synchronous switching of distribution sub networks Paul Stergiou ConEdison USA Manuel P Pimenta, - ConEdison USA Sergio A Rodriguez ConEdison USA Thomas Horan ConEdison USA Andre Smit- Siemens Industry

More information

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 978 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE MP 1.1 Objective

More information

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011 Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 2. Initial Technical Review a. The following flowchart provides, for illustrative purposes, the major steps in the Initial Technical Review process:

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are

More information

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot: PROCUREMENT DEPARTMENT 4 WORLD TRADE CENTER 150 GREENWICH STREET, 21ST FL. NEW YORK, NY 10007 12/7/2018 ADDENDUM # 3 To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

Electric Utility Facility Connection Requirements

Electric Utility Facility Connection Requirements City of Coffeyville Municipal Light and Power Electric Utility Facility Connection Requirements Approved: Date: Version Date Change Tracking Reviewer/Editor 1.0 June, 2010 Original document. Steve McGie

More information

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network

More information

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting

More information

OC IEEE IAS/PES Meeting February 21, 2013

OC IEEE IAS/PES Meeting February 21, 2013 San Diego International Airport: Building For The Future, Through Underground Distribution Automation and SCADA OC IEEE IAS/PES Meeting February 21, 2013 1 Presenter: Randy Denton, PE Under Ground Utility

More information

WON Security Guideline

WON Security Guideline WON Security Guideline Data Exchange Work Group October 7, 2015 155 rth 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WON Security Guideline 1 Table of Contents Purpose... 1 Background... 1 Security

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

JEA. Facility Connection Requirements

JEA. Facility Connection Requirements JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Review of Generator Interconnection Agreements and Procedures American Wind Energy Association Docket No. RM16-12-000 Docket No. RM15-21-000

More information

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc.

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc. Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation Purpose: To establish an equitable process for allocating fault current margin, where available, to applicants

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

Warrenton Wheeler Gainesville 230kV Reliability Project

Warrenton Wheeler Gainesville 230kV Reliability Project Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three

More information

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM Version 1.2 May 28, 2009 Transmission Planning Department Revisions Rev. No. Date Description By Approval 1.0 8/10/06

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

Flexible High-Speed Load Shedding Using a Crosspoint Switch

Flexible High-Speed Load Shedding Using a Crosspoint Switch Flexible High-Speed Load Shedding Using a Crosspoint Switch Will Allen and Tony Lee Schweitzer Engineering Laboratories, Inc. Published in Wide-Area Protection and Control Systems: A Collection of Technical

More information

1. Project Description

1. Project Description Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL DISTRIBUTION SYSTEM Revised and Issued March 2003 I.

More information

Operations ISO Version: 1.2. Communication Block Diagram Requirements Effective Date: 082/07/2017. Checklist

Operations ISO Version: 1.2. Communication Block Diagram Requirements Effective Date: 082/07/2017. Checklist Checklist REVISION HISTORY VERSION NO. DATE REVISED DESCRIPTION (Must match header) BY 1.1 07/03/2017 Created Document 1.2 08/07/2017 RLS Removed watermark. No technical changes. Contents Purpose... 4

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids Enrico Ragaini (ABB Low Voltage Products), Alexandre Oudalov (ABB Corporate Research), ISGT Europe 2012, Berlin Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

Oncor Application for Interconnection of Distributed Generation

Oncor Application for Interconnection of Distributed Generation Oncor Application for Interconnection of Distributed Generation Operating Mode: Parallel Operation Longer than 100 milliseconds (07/11/2018) This application is for generator systems that synchronously

More information

Distributed Generation Interconnection in Illinois

Distributed Generation Interconnection in Illinois Distributed Generation Interconnection in Illinois David Rearden January 31, 2014 1a In the beginning Electricity system was vertically integrated: the utility generated the electricity, transmitted to

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection 1 Process PG&E Order No. 754 Analysis Receive Bus List from Planning that Meet the Criteria in Table A Protection Computes Actual Clearing

More information

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 17-035-36 Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Kelcey A. Brown August 2017 1 2 3 4

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Title. Critical Infrastructure Protection Getting Low with a Touch of Medium. CanWEA Operations and Maintenance Summit 2018.

Title. Critical Infrastructure Protection Getting Low with a Touch of Medium. CanWEA Operations and Maintenance Summit 2018. Critical Infrastructure Protection Getting Low with a Touch of Medium Title CanWEA Operations and Maintenance Summit 2018 January 30, 2018 George E. Brown Compliance Manager Acciona Wind Energy Canada

More information

Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory

Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Authority: This Interconnection Standard is filed in compliance with the Delaware Public Utility Commission in

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Product Description. S&C IntelliNode Interface Module. Table of Contents. Instruction Sheet

Product Description. S&C IntelliNode Interface Module. Table of Contents. Instruction Sheet S&C IntelliNode Interface Module Product Description Table of Contents Section Page Section Page Introduction Qualified Persons.......................... 2 Read this Instruction Sheet..................

More information

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS

More information

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (

More information

Interconnection Application

Interconnection Application Interconnection Application Member interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

Digital substations. Introduction, benefits, offerings

Digital substations. Introduction, benefits, offerings Digital substations Introduction, benefits, offerings Outline What is a digital substation? Benefits of digital substations ABB offering for digital substations Substation evolution June 26, 2017 Slide

More information

ASSET RISK MANAGEMENT Criticality Framework

ASSET RISK MANAGEMENT Criticality Framework ASSET RISK MANAGEMENT Criticality Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to

More information

Electrical Demand Specification (Reference SOP: )

Electrical Demand Specification (Reference SOP: ) Project: Equipment Description: Location: Equipment No.: Project No: Protocol No.: Content Index 1. GENERAL...3 Design Standards...3 1.1. Standards...3 2. DESIGN...3 2.1. Safety...3 2.2. Circuit protection...3

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

Transmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel

Transmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel Utility Bulletin: TD-1013B-002 Publication Date: 07/03/2012 Rev: 0 Direct Transfer Trip (DTT) Telecommunication Options Summary Interconnection partners (customers) are requesting additional options for

More information

LCRA Transmission Services Corporation. Facility Connection Requirements

LCRA Transmission Services Corporation. Facility Connection Requirements LCRA Transmission Services Corporation Facility Connection Requirements May 2018 Table of Contents 1.0 INTRODUCTION... 3 2.0 Facility Connection Requirements... 3 2.1 Summary of Basic Interconnection Requirements...

More information

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS STATE OF MINNESOTA DISTRIBUTED GENERATION INTERCONNECTION TABLE OF CONTENTS Foreword 2 1. Introduction 3 2. References 6 3. Types of Interconnections 7 4. Interconnection Issues and Technical Requirements

More information

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information

115 kv / 34.5 kv Solar Power Plant / Substation

115 kv / 34.5 kv Solar Power Plant / Substation 115 kv / 34.5 kv Solar Power Plant / Substation Project Plan MAY1602 INDUSTRY CLIENT: ADVISORS: TEAM EMAIL: TEAM: Black and Veatch Corporation Venkataramana Ajjarapu, Anne Kimber may1602@iastate.edu Chase

More information