Substation Workshop. 7 th February 2018

Similar documents
EOS REMSDAQ CALLISTO NX TYPE E RTU

Embracing Competition Stakeholder Engagement Workshop no May 2018

ECS LUCY GEMINI 3 CONFIGURATION PROCEDURE

EOS LUCY GEMINI 3 TYPE E RTU

ICP. Simplifying. Competition in Connections FOR UNMETERED, METERED AND DISTRIBUTED GENERATION CONNECTIONS

ECP SECONDARY SUBSTATION COMMISSIONING PROCEDURE

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES

EOS LUCY SABRE 'A' RANGE SWITCHGEAR

City of London Stakeholder Consultation

EDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES

EDS GUIDANCE FOR THE APPLICATION OF ENA ENGINEERING RECOMMENDATIONS G88 AND G81 - INSET NETWORKS (IDNOS AND OTHER LICENSED DNOS)

Network Configuration Document Selection for New Substations Framework

EOS SCHNEIDER RINGMASTER 'C' RANGE SWITCHGEAR

Package Substation. The efficient solution for your electrical distribution network

ECP GPRS/3G/4G COMMS DEVICE CONFIGURATION AND COMMISSIONING PROCEDURE

Company Directive STANDARD TECHNIQUE : NC2D/2. Relating to Specification of Connection Assets

providing electricity connection solutions

New connections. You have a choice. It is your choice

EDS LV CUSTOMER UNMETERED SUPPLIES

Solution Mining. tgood.com

EDS SCADA NUMBERING SYSTEM

DNB Power and Control System Information and Interim Safety Procedures. Version draft 5/06/08

Engineering Recommendation G87 Issue

Solution Utility. tgood.com

Owner/Operator Forum 12 December

EDS MW AND MVAR TRANSDUCER CONNECTION

NEXT GENERATION NETWORK RESTORATION APPROACHES ON DISTRIBUTION FEEDERS

Tunnelling SoluTionS

Independent Connections Provider (ICP) Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure

Completing this form accurately will help us process your application as quickly as possible. Please complete all sections relevant to your project.

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM

Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements

Metal Theft Focus Group

Flexible Connections for DG Customers

The iems Refresh Project

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

EFASOLAR PVStation Solutions

Huawei Railway Communication Service Solution Guide

Presented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011

UNDERGROUND HV SUBSTATION DESIGN

Severn Trent Water. Telecommunications Policy and Access Procedure

Integrated and Separate?

SWITCHYARD SYSTEM BC1-SS-11-SD TRAINING SYSTEM DESCRIPTION NRG ENERGY, INC. BIG CAJUN 1

DESIGN STANDARD DS 28

On the other side, performing tests is an expensive task, demanding

Specification Voltage Limiting Device

coal mining Solutions

Distribution Substation Manual (DSM) Section 6: Miscellaneous

CONTROL SYSTEMS DESIGN SPECIFICATION

Policy on the Provision of Mobile Phones

Solution Railway. tgood.com

2.10 Annex. SP Manweb urban network. SP Energy Networks. June SP Energy Networks Business Plan

CAPABILITY STATEMENT. A full list of our services.

ECS TYPE E RTU AND ANCILLARY ITEMS INSTALLATION PROCEDURE

Configurable Output Distribution. 120V / 208V / 240V 60Hz. User Manual English

EDS HV NETWORK DESIGN

October 2017 INVESTING FOR THE FUTURE. NIE Networks summary business plans

CCBC is equipped with 3 computer rooms, one at each main campus location:

Process for Completion of Landowner Permissions and Other Useful Information on Consents Required for ICP Schemes

Electrical Equipment and Comprehensive Power Grid Solutions

SP Energy Networks Business Plan

TECHNICAL BULLETIN Ministry of Transportation

Electrical Demand Specification (Reference SOP: )

Energy Energy Networks. Networks Association. Association. Insert presentation title here. The Voice of the Networks

ECP NORTROLL CABLETROLL 2350 FPI INSTALLATION AND COMMISSIONING PROCEDURE

Distributed Generation Customer Perspectives. Focus on LV to 33kV Connections sector (PV)

IXcellerate Moscow One Datacentre - Phase 1 & 2 Overview

ALLTEC PROTECTION PYRAMID TM FOR PHOTOVOLTAIC SOLAR FIELD

ABB Medium Voltage Days 2016 Asset service innovation Solutions along the lifecycle

CPS VS UPS FOR POWERING DATA CENTERS

IADC HSE Case Guidelines Reference: Number-Title

UPDATES EPC Contract Signed August 2017

Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium

Ventilation Policy Type: Policy Register No: Status: Public. Developed in response to: Contributes to CQC Outcome number: Outcome 8 and 10

Your partner in energy solutions. Systems Division. Automation & services. (Formerly Pauwels Canada Inc)

Transmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel

MNS Platform, low voltage systems Rear Access Power Motor Control Center. Alberto Carini, Global Product Manager

Equipment Strategy For High Voltage Circuit Breakers

Advanced Monitoring Solutions for Critical Electric Power Transmission & Distribution Assets

Intelligent transformer substation HKP-E / HKP-E-U

EDS KV, GRID AND PRIMARY SYSTEM PROTECTION AND CONTROL SCHEMES

MED MI 1005 Network Isolators

Two-Stage Power Distribution: An Essential Strategy to Future Proof the Data Center

Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY

Spring Test 9 due 05/11/2013

Product Details. Contents. Features and Mounting Options for SUNNY STRING-MONITOR SSM24-11

Portable Power Solutions

BUILDING ENGINEERING SERVICES 2018/19

CAPABILITY PRESENTATION

Oncor Residential/Small Commercial Project Requirements

PRODUCT & SYSTEM OFFERINGS

COMPANY PROFILE. Kontrolmatik has accomplished local and international projects with great success. Some of fields that KONTROLMATIK serves,

Thermal Devices Inc. Mount Airy, Maryland USA

Capital Contribution Policy for New Load and Network Extensions Marlborough Lines

icore Kiosk system Installation Guide

Nuclear Power Plant Security

RCP2 Portfolio Overview Document

Level 2 Control and security systems for the digital home technology integrator ( )

Switching Process and Rules Systems Operations Framework. Document Number:

INTERCONNECTION FACILITIES STUDY REPORT

Transcription:

Substation Workshop 7 th February 2018 1

Agenda Welcome and Introductions Antony White Substation Design Overview Andy Moore Question & Answer Session Break 1500kVA Transformers James Devriendt & Andy Moore Question & Answer Session Close / Feedback Antony White Lunch 2

Andy Moore Lead Design Engineer, LPN Substation Design Overview 3

UKPN Substation Design Ideal Scenario Drivers behind the current policy Substation Locations Key Elements Requirements for a basement location UKPN s preferred basement solution Applicable to all areas but predominately an LPN Area guidance 4

Ideal Scenario Since 2011; UKPN s stance regarding new build developments has been: The normal location for a substation, whether in a separate building or integral to a customer owned building, is at ground level. This is a similar stance to all other DNOs. 5

Ground Level Location ~ Key Drivers 24hr unrestricted access ~ OFGEM KPI : Customer Minutes Lost (CML). Manual Handling ~ Design-out MH of heavy plant wherever possible. Working at Height ~ Design-out WAH wherever possible (e.g. cable entry). CDM Designing out risk installation, maintenance and de-commissioning 6

Substation Location: GRP Enclosure EDS 07-3102_01 Unit or Padmount Substation in GRP Enclosure 7

Substation Location: Freestanding Brick EDS 07-3102_15 Freestanding Brick-Built Substation for a Transformer up to 1000kVA (Earth Ring) 8

Substation Location: Ground level Integral EDS 07-3102_20 Integral Substation for a Single Transformer up to 1000kVA 9

UKPN Substation Design Key Elements: Plant Layout Ventilation Cable entry Personnel access Plant access 10

UKPN Substation Design Current requirements are detailed in the UKPN Engineering Design Standard: EDS 07-3102 ~ Secondary Substation Civil Design & associated suite of drawings. Available on the G81 section of the UKPN website. 11

Substation Location: Basement EDS 07-3102_30 Basement Substation for a Single Transformer up to 1000kVA 12

When considering basement locations: Maximum one level below ground floor 24hr unrestricted UKPN staff access Without recourse to a third party (e.g. via Security Guard). Dedicated normal stairway (e.g. no companionway ladders). Dual-locking arrangements (if necessary). Direct UKPN Plant Access 24hr unrestricted. Manual Handling kept to a minimum Natural Ventilation Scheme Open to free air. Passive Stack principle employed. Maintenance free. 13

24hr Unrestricted Personnel Access UKPN dedicated stairway > < Access without 3 rd party involvement 14

Direct Plant Access Plant installation via running beam > Plant installation via running beam & hatch; minimising manual handling > & Plant access hatch > < Drop zone from above close to substation < Minimising manual handling 15

UKPN s preferred basement solution: The Lightwell substation < Personnel access without 3 rd party involvement Via dedicated stairway > 16

Lightwell substation cont d: < Direct plant access via HIAB crane Direct plant access with minimal manual handling > Open to free air ^ Passive stack principles Maintenance free 17

When things go wrong - Simple 18

When things go wrong - Complex 19

Substation Design Summary: Although we will always look for a ground level location in the first instance; UKPN will consider substations located in a basement. A number of aspects need to be considered if we are to meet our own requirements in terms of Health & Safety and network security. Each project requiring a substation will be assessed on its individual circumstances; providing the mandatory elements can be achieved. 20

Answering your questions 21

James Devriendt Connections Manager, SPN & Andy Moore Lead Design Engineer, LPN 1500kVA Transformers 22

Context UK Power Networks charged with stimulating and supporting a competitive market Market share has reduced significantly in majority of relevant market sectors Service delivery has demonstrably improved in recent years Appetite for more competitive offering is increasing Customers want UK Power Networks to be more flexible in offering 23 23

Transformers 11kV transformer specification has typically been limited to 1MVA Reduced unit diversity leads to lower unit cost and simpler maintenance schedule Automatic loss of Connections market share to IDNOs, particularly in high land-value / physically constrained locations We have reviewed specification options with a number of customers to determine most useful offering 1500kVA unit with 2500A LV circuit breakers sourced 24 24

Current Status Asset Management have reviewed options Standard Drawings drafted Engineering Bulletin issued for comment (internally) Relevant standards in the process of being updated on G81 25

Considerations Increased floor loading (compared to 1MVA) Increased ventilation requirements (compared 1MVA) ACB must be close coupled to the transformer (e.g. not wall mounted) 1m deep cable trenches required (due to close coupled ACB) and bending radius requirements for 630mm singles Customer installed back up generation would be strongly recommended 26

Uses Single connected customers (only) includes BNO, TBS and IDNO Outstanding constraints Basement locations currently not approved GRP locations currently not approved Refurbishments / upgrades out of scope 27

Current drawing 28

Answering your questions 29

Feedback & Thank you! 30