Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)

Similar documents
Title Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP)

Title Power Supply Units for Signalling Equipment - DC (Regulated & Filtered) Units. Reference Number SPS 30 - (RIC Standard: SC SP)

Status Date Prepared Reviewed Endorsed Approved

AC Immune DC Track Circuits Set-Up, Test and Certification

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM

DC Track Circuits Set-Up, Test and Certification

Vector Drive - Troubleshooting Guide

Specification Voltage Limiting Device

PGR-6101 MANUAL GROUND-FAULT & INSULATION MONITOR

Electrical Demand Specification (Reference SOP: )

Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium

2 Check that Public Safety has been considered (e.g. cabinet secured and locked, trip hazards removed where applicable).

Standards Update Notice (SUN) Issued: April 25, 2017

Vector Drive - Troubleshooting Guide

MESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS

Vector Drive - Troubleshooting Guide

PRODUCT. Battery Charger

DGSZV-EP DIGITAL GALVANIC LONGITUDINAL DIFFERENTIAL PROTECTION. Application field

1. Project Description

PUBLIC SERVICE OF NEW HAMPSHIRE. Technical Requirements for Non Utility Generation Interconnecting to the PSNH Distribution System

Signal Service Schedules Index

MESP MODULAR SUBSTATION USER REQUIREMENTS

Microlok Data Design Records (Addressing, File Control, Checking, and FAT Testing)

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

ELG4125: System Protection

1510 MOTOR CONTROLLERS

DIN Series MINIATURE CIRCUIT BREAKERS, RESIDUAL CURRENT CIRCUIT BREAKERS. Introducing the DIN Series High-quality, high-performance circuit breakers

MESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR

CFW-09HD LINE DC LINK POWER SUPPLY

ELECTRICAL, INSTRUMENTATION & CONTROL SYSTEMS

SECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE

aentron Energy System 1 to 900 Vdc

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

MTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES

MMLB 01/MMLB 02 Multi-finger Test Plug/ Single-finger Test Plug Technical Data MMLB_EN_TD_A

DC Substations / Supply Program

ABB Group - Bob van Evelingen. March 26, 2009 Slide Series. 600-Series. Transmiss. ABB Group - Bob van Evelingen. March 26, 2009 Slide 5

DTRV-EP. COMPLEX DIGITAL PROTECTION FOR 120 kv / MEDIUM VOLTAGE TRANSFORMERS. Application field

Switching modules for AC 230 V, non-potential-free, single and double module

PGR-6100 MANUAL GROUND-FAULT & INSULATION MONITOR

Power Supply. Users Guide PRODUCT MANUAL. WESTELL.COM Westell Technologies MNL rd

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

AIR COOLED MODULAR RECTIFIER

Commission Testing Methods for Protection Systems

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

High Voltage Power Supply (MMPS) - Troubleshooting Guide

HID. GE Consumer & Industrial Multilin. High Impedance Differential Module Instruction manual GEK Copyright 2005 GE Multilin

ABB Digital medium-voltage switchgear

H Series PLC. ! : Indicates Compulsion. EH-150 Analog input module EH-AXH8M Instruction manual. Safety precautions DANGER CAUTION COMPULSION

INSTITUTE OF TESTING AND CERTIFICATION (INDIA) PVT. LTD.

File E Project 00SC September 27, 2000 REPORT COMPONENT - POWER SUPPLIES, MEDICAL AND DENTAL EQUIPMENT

SRI LANKA STANDARD CODE OF PRACTICE FOR GRID CONNECTED PHOTOVOLTAIC POWER SYSTEMS SLS 1522:2016

Selection Guide. Control Circuit and Load Protection. Allen-Bradley 1489-M2C020

Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly

Switching module for AC V and up to three load stages, with manual switching

EFASOLAR PVStation Solutions

Design Guidelines for SCADA & DSA

Two-hand relay modules SRB 201ZH 44 Schmersal Industrial switching systems

REQ. No. 32/2012/E Cooling Towers Electrical Substation

Package Substation. The efficient solution for your electrical distribution network

Document Title Issue Date. TBE/KBE-DOC TBE/KBE Document List TBE/KBE-REV TBE/KBE Revision List

11 kv Indoor Switchgear - SCADA Controlled

INSTALLATION AND MAINTENANCE MANUAL FOR GROUND MONITOR GM-300

Binary output and supervision 520CSD01 Data sheet

Testing Instruments Manufactured by

BOX TRANSDUCER SMALL SIZED AC TRANSDUCER 90 SERIES

S82S (3/7.5-W Models)

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

REYROLLE 2RMLG. Operating Recommendations

Application Note. Common Bussing AC Drives. For 584SV and 620 series drives APP-AC-02

Options. 24-VDC service power supply. RUN output. No Yes No 24 VDC 70 W NX-PD7001

6 Check that the earth system is complete, undamaged and bonded to earth points ( including capacitor and control).

Masterpact NW Restricted Earth Fault Protection

AS-i Safety Relay Output Module with Diagnostic Slave and 1 EDM Input

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL

INTERCONNECTION FACILITIES STUDY REPORT

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

ST: TP14D/2 TEST SHEET COMBINED LV CT & METER CABINET INSTALLATIONS OFF-LOAD TESTING

Analog output 520AOD01 Data sheet

Document C0. Use for:

Content. Time delay relays mounting position. Multifunctional time delay relay Clock-pulse generator time delay relay... 3.

ABB i-bus KNX Analogue Input, 4-fold, MDRC AE/S , 2CDG110190R0011

HITACHI. EH-150 series PLC EH-RTD8 Resistance Temperature Detective input module Instruction manual. Safety precautions

Certification Exams. Detailed Content Outlines Level 2 Certified Assistant Technician Level 3 Certified Technician Level 4 Certified Senior Technician

AC-DC Converter REC K10

ECP SECONDARY SUBSTATION COMMISSIONING PROCEDURE

RTU511. Binary Output 23BO62. Characteristics. Application. Data Sheet Binary Output 23BO62. The binary output is made via relay contacts.

TECHNICAL SPECIFICATION FOR A 1500V DC SWITCHGEAR ASSEMBLY

ECS LUCY GEMINI 3 CONFIGURATION PROCEDURE

Presented by: Oscar Araujo Photovoltaic Solutions Manager. 4 th Canadian German Solar PV Conference March 2 nd 2011

BNS SERIES - COMPATIBLE SERIES AES SAFETY CONTROLLERS SELECTION CHART AVAILABLE STANDARD MODELS

LED Driver Compact fixed output

US CATALOG SMISSLINE TP

LINE VOLTAGE TESTER CT101 USER S MANUAL. Please read this manual carefully and thoroughly before using this product.

Operating Instructions

////// SUBSTATIONS. DC Switchgear Range. Type MBS (IEEE/ANSI standards)

BRC SERIES 20kW High Voltage Power Supply

Operating Manual -ENGLISH- Page 1 KWG-ISO

SCADA Training - T&D Automation

PSU. User s manual. Rev. 0

Transcription:

Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards and Systems Refer to Reference Number Signalling Standards Engineer T Moore GM Infrastructure Strategy & Performance M Owens Safety Committee Refer to minutes of meeting 24/01/05

Disclaimer Australian Rail Track Corporation has used its best endeavors to ensure that the content, layout and text of this document is accurate, complete and suitable for its stated purpose. It makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems of work or operation. Australian Rail Track Corporation will not be liable to pay compensation in respect of the content or subsequent use of this document for any other purpose than its stated purpose or for any purpose other than that for which it was prepared except where it can be shown to have acted in bad faith or there has been willful default. Document Approval The technical content of this document has been approved by the relevant ARTC engineering authority and has also been endorsed by the ARTC Safety Committee. Document Supply and Control The Primary Version of this document is the electronic version that is available and accessible on the Australian Rail Track Corporation Internet and Intranet website. It is the document user s sole responsibility to ensure that copies are checked for curency against the Primary Version prior to its use. Copyright The information in this document is Copyright protected. Apart from the reproduction without alteration of this document for personal use, non-profit purposes or for any fair dealing as permitted under the Copyright Act 1968, no part of this document may be reproduced, altered, stored or transmitted by any person without the prior written consent of ARTC. March 2005 Page 2 of 10

About This Standard This publication sets out the general requirements for the testing and the recording of test results during the commissioning of a new system substation. The relevant sections of this publication shall also apply when a new item of equipment is commissioned in an existing system substation or an existing piece of equipment re-commissioned following an overhaul. This publication does not cover the actual testing methods. It requires that the tester determine the necessary tests and the acceptable results. However some minimum acceptable values for Insulation Resistance and Continuity tests are provided. March 2005 Page 3 of 10

Document History Primary Source RIC Standard EP 99 00 00 02 SP Version 2.0 List of Amendments ISSUE DATE CLAUSE DESCRIPTION 1.1 11/03/2005 Disclaimer Minor editorial change March 2005 Page 4 of 10

Contents 1 Introduction...6 2 Documentation of Test Methods and Results...6 3 Tests for Installed Equipment and Sub-systems...6 3.1 Description of Tests...6 3.1.1 Connections...6 3.1.2 Continuity...6 3.1.3 Control Voltages...6 3.1.4 Earthing...6 3.1.5 Electrolyte...7 3.1.6 Insulation...7 3.1.7 Leakage...7 3.1.8 Oil...7 3.1.9 Operation...7 3.1.10 Phase Check...7 3.1.11 Protection...7 3.2 Equipment and Sub-system Tests...7 3.2.1 1500 V Links...7 3.2.2 1500 V Bus Isolating Switches...7 3.2.3 Air Break Switches, Manual...8 3.2.4 Air Break Switches, Motor Operated...8 3.2.5 Battery...8 3.2.6 Battery Charger...8 3.2.7 Bus Bars, Outdoor...8 3.2.8 Cables, DC...8 3.2.9 Cables, High Voltage...8 3.2.10 Circuit Breakers, AC Feeder & Bus Section...8 3.2.11 Circuit Breakers, AC Rectifier...8 3.2.12 Circuit Breakers, DC Feeder Sectioning Hut...8 3.2.13 Circuit Breakers, DC Feeder Substation...8 3.2.14 Circuit Breakers, DC Rectifier...8 3.2.15 Earthing System...8 3.2.16 High Voltage Supplies...9 3.2.17 Low Voltage Light & Power Circuits...9 3.2.18 Rail-Earth Contactor...9 3.2.19 Reactor...9 3.2.20 Rectifiers...9 3.2.21 SCADA system...9 3.2.22 Transformers, Auxiliary...9 3.2.23 Transformers, Rectifier & System...9 3.2.24 Transformer, Rectifier and AC & DC Circuit Breakers as a Unit...9 4 Insulation Resistance Values...10 5 Continuity Test Values...10 March 2005 Page 5 of 10

1 Introduction Before a new system substation, or a new item of equipment in an existing system substation, can be livened up and placed into service, it is necessary to test and/or check all equipment to ensure that the design and construction process has been satisfactory. All items of equipment shall be individually tested to the relevant Australian Standard at the time of purchase. Where such a standard does not exist, the method of determining the equipment s suitability shal be stated. Section 3 of this publication specifies the additional tests and/or checks that are necessary to verify the performance of the installed equipment individually and as part of various sub-systems (eg rectifier, rectifier transformer and rectifier AC and DC circuit breakers operation as a whole). 2 Documentation of Test Methods and Results The proposed method of carrying out all commissioning tests and the acceptable results shall be documented for each type of equipment, and submitted to ARTC for approval. The test results shall be recorded. Absolute minimum standards for Insulation Resistance and Continuity tests are stated in Table 1 of section 4 and Table 3, of section 5, respectively. 3 Tests for Installed Equipment and Sub-systems 3.1 Description of Tests 3.1.1 Connections All connections shall be checked for correct tightness. 3.1.2 Continuity Continuity of circuits shall be tested with all switches and circuit breakers in the closed position. The resistance of the contacts for each pole shall be tested. Continuity of all transformer windings and tap changers shall be tested. 3.1.3 Control Voltages Correct operation of equipment shall be tested at the minimum and maximum control voltages. 3.1.4 Earthing Equipment earths shall be tested by measuring the resistance from the equipment earth to the substation earth mat. March 2005 Page 6 of 10

3.1.5 Electrolyte Batteries shall have electrolyte checked for correct level and density. 3.1.6 Insulation Equipment insulation levels shall be tested using a suitable insulation resistance meter. For ac equipment, the insulation shall be tested between phases, and each phase to earth. For 1500 Vdc the insulation shall be tested between the 1500 V circuit and earth. 3.1.7 Leakage High voltage and 1500 V cables shall be tested by applying a high dc voltage to each core for 1 minute and measuring the leakage. Any screens must be earthed. The cables are insulation tested before and after this test. 3.1.8 Oil An oil sample shall be taken from all oil-cooled equipment and tested. The oil level shall also be checked. 3.1.9 Operation Correct operation of equipment shall be tested in response to all automatic controls, safety interlocks, protection devices and alarms. Local and remote controls shall be tested. 3.1.10 Phase Check All high voltage supplies shall be tested to ensure that they are in phase. All auxiliary supplies shall be tested to ensure that they are in phase. 3.1.11 Protection Correct functioning of all protection devices shall be tested in response to all fault conditions at appropriate magnitudes. Where appropriate, this may be tested by suitable simulation techniques such as secondary injection. 3.2 Equipment and Sub-system Tests The following is a list of equipment which must be tested in a typical system substation. Appropriate tests for equipment not listed shall be determined by analysis and submitted to ARTC for approval on an individual basis. 3.2.1 1500 V Links Insulation, continuity, operation, earthing. 3.2.2 1500 V Bus Isolating Switches Insulation, continuity, operation, earthing. March 2005 Page 7 of 10

3.2.3 Air Break Switches, Manual Insulation, continuity, operation, earthing. 3.2.4 Air Break Switches, Motor Operated Insulation, continuity, operation, control voltages, earthing. 3.2.5 Battery Insulation, voltage, connections, electrolyte. 3.2.6 Battery Charger Insulation, voltage, connections, operation. 3.2.7 Bus Bars, Outdoor Insulation, continuity, earthing. 3.2.8 Cables, DC Insulation, continuity, leakage. 3.2.9 Cables, High Voltage Insulation, continuity, leakage. 3.2.10 Circuit Breakers, AC Feeder & Bus Section Insulation, continuity, operation, control voltages, protection, earthing. 3.2.11 Circuit Breakers, AC Rectifier Insulation, continuity, operation, control voltages, protection, earthing. 3.2.12 Circuit Breakers, DC Feeder Sectioning Hut Insulation, continuity, operation, control voltages, protection. 3.2.13 Circuit Breakers, DC Feeder Substation Insulation, continuity, operation, control voltages, protection. 3.2.14 Circuit Breakers, DC Rectifier Insulation, continuity, operation, control voltages, protection. 3.2.15 Earthing System Visual inspection, earth resistance. March 2005 Page 8 of 10

3.2.16 High Voltage Supplies Phase check. 3.2.17 Low Voltage Light & Power Circuits Insulation, continuity, operation, control voltages, protection, earthing. 3.2.18 Rail-Earth Contactor Continuity, connections, operation. 3.2.19 Reactor Insulation, continuity, oil. 3.2.20 Rectifiers Insulation, continuity, earthing, protection. 3.2.21 SCADA system Operation, control voltages. 3.2.22 Transformers, Auxiliary Insulation, continuity, operation, voltage, protection, earthing. 3.2.23 Transformers, Rectifier & System Insulation, continuity, oil, control voltages, protection, earthing. 3.2.24 Transformer, Rectifier and AC & DC Circuit Breakers as a Unit Operation, control voltages, protection. March 2005 Page 9 of 10

4 Insulation Resistance Values The minimum acceptable Insulation Resistance values for equipment shall be as shown in Table 1. Equipment Voltage Test voltage of Insulation Resistance Meter Minimum acceptable value in dry conditions @ 20 C 11 kv and above 5 kv 100 M 1500 V incl. 600 V transf. windings 2.5 kv 20 M* 415/240/120 V wiring & C.T. wiring 500 V 10 M Table 1 Minimum acceptable Insulation Resistance * DC positive feeder cables shall have a minimum acceptable value of 100 Mbetween the core and screen. A minimum value of 20 M i s acceptable between the earth and screen. Insulation Resistance is a function of temperature. Values measured at other than 20 C can be converted to 20 C as follows: Temperature at which measurement made Multiply measured resistance value by 10 C 0.5 30 C 2.0 40 C 4.0 50 C 8.0 5 Continuity Test Values Table 2 Insulation Resistance temperature conversion The maximum acceptable resistances of closed contacts shall be as shown in Table 3. Equipment Voltage Resistance @ 20 C 1500 V 20 11 kv 30 33 kv and above 100 Table 3 Minimum resistances of closed contacts March 2005 Page 10 of 10