PSERC EVALUATING PROTECTIVE RELAY OPERATION THROUGH TESTING
|
|
- Daniel Watson
- 6 years ago
- Views:
Transcription
1 EVALUATING PROTECTIVE RELAY OPERATION THROUGH TESTING Mladen Kezunovic Eugene E. Webb Professor Texas A&M University Seminar, April 6, 2004
2 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) testing methodology and tools? What would be the benefits? Conclusions Q/A 2
3 Why Relay Testing? This varies according to specific needs: - verify that a relay product is acceptable (production)=type test - verify that relay settings are calibrated and relays are connected correctly=commissioning test - verify that a relay maintains correct calibration of settings=periodic maintenance test - verify that the performance for a given application is adequate=application test - explain relay miss operation= Troubleshooting test 3
4 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) test methodology and tools? What would be the benefits? Conclusions Q/A 4
5 What is the relay performance of interest? Type, commissioning and periodic tests: -Correct operating characteristic (comparing to what is given in manuals) -Correct settings (comparing to what was calculated and entered) Application and troubleshooting tests: - Trip/no trip decision - If a correct trip, what is the operating time - If an incorrect trip, what was the reason 5
6 What is the relay performance of interest? Recommended statistics: - Dependability (should trip when there is a fault) - Security (should not trip when there is no fault) Recommended practices after an event (Northeast black out of August 14, 2003): - NERC Actions, February 10, Group: Data Exploration and Requirements 6
7 NERC Actions:February 10, 2004 Overview of conclusions: - Available system protection technologies were not consistently applied to optimize the ability to slow or stop an uncontrolled cascading failure of the power system Overview of recommendations: - Improve system protection to slow or limit the spread of future cascading outages 7
8 Recommendations Strategic (#5): Need to improve relay protection schemes and coordination Technical (#8): Improve system protection to slow or limit the spread of future cascading outages: a.) better application of Zone III relays b.) selective use of under-voltage load shedding c.) revision to the criteria for slowing/limiting propagation of cascading failures 8
9 Recommendation #8 #8a.: Zone III relays - Zone III relay should not operate at or below 150% of the emergency power rating of a line assuming.85% p.u. voltage and line phase angle of 30 degrees - Out of step conditions should not confuse the relay #8b.: Under-voltage load shedding -low voltage with both high and low frequencies should be considered - coordination with generator under- and overfrequency protection and controls #8c.: propose revisions to the planning criteria 9
10 Group for Data Exploration and Requirements NERC Planning Standard specifies Testing and maintenance requirements: Responsibility for maintenance and/or testing Relay type,settings, targets and causes of trips were requested Group did not make any reference to the relay test data being available and used for blackout investigation Recommendation was to standardize data collection but NOT to perform any relay tests 10
11 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) test methodology and tools? What would be the benefits? Conclusions Q/A 11
12 What is the existing relay test practice? Phasor testing procedure: - Uses traditional test sets (Doble, Megger, Omicron, Manta, etc) - Sets a fixed voltage and ramps current from zero until the relay operates - Repeats such a test for several operating points - Performs tests in the field or on a relay manufacturing floor 12
13 13
14 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) testing methodology and tools? What would be the benefits? Conclusions Q/A 14
15 How the existing practice may be enhanced? Phasor testing: - More MEANINGFUL tests - BETTER testing TOOLS Transient testing: - use it to evaluation performance of relay products BEFORE PURCHASE - Use it to evaluate relay performance IN- SERVICE 15
16 Comprehensive list of Test Cases (Phasor Testing) 16
17 Artificial Test Waveforms 17
18 One-terminal system representation 18
19 19
20 20
21 21
22 22
23 Test result summary Different Cases Different fault types for the same relay Different relays Different load currents Different source impedance ratio 23
24 ABC fault x: Case I o: Case II *: Case III 24
25 Test result summary Different Cases Different fault types for the same relay Different relays Different load currents Different source impedance ratio 25
26 A-G fault (Relay A) x: Case I o: Case II *: Case III 26
27 BC fault (Relay A) x: Case I o: Case II *: Case III 27
28 BC-G fault (Relay A) x: Case I o: Case II *: Case III 28
29 Test result summary Different Cases Different fault types for the same relay Different relays Different load currents Different source impedance ratio 29
30 BC fault (Relay B) x: Case I o: Case II *: Case III 30
31 BC fault (Relay C) x: Case I o: Case II *: Case III 31
32 : Three-phase fault theoretical characteristics : Single-line-to-ground fault theoretical characteristics : Line-to-line fault theoretical characteristics x : Three-phase fault test results o : Single-line-to-ground fault test results * : Line-to-line fault test results Comparison of theoretical analysis and test for Relay B 32
33 Test result summary Different Cases Different fault types for the same relay Different relays Different load currents Different source impedance ratio 33
34 Relay A, BC fault x: I = 5-30 A; o: I = 0 A; *: I = A 34
35 Test result summary Different Cases Different fault types for the same relay Different relays Different load currents Different source impedance ratio 35
36 Relay C, BC fault x: SIR = 1.24 o: SIR =
37 Two-terminal system representation 37
38 How the existing practice may be enhanced? Phasor testing: - More MEANINGFUL tests - BETTER testing TOOLS Transient testing: - use it to evaluate performance of relay products BEFORE PURCHASE - Use it to evaluate relay performance IN- SERVICE 38
39 Transient Testing Case I: Creating test waveforms through modeling and simulation Case II: Creating test test waveforms through replaying the field-recorded data Evaluating - Application: Correct/incorrect operation for a selected application - Statistical properties: trip/no trip decision and trip time for number of applications 39
40 Example: Application tests 40
41 Example: Application tests Sequence of events: fault on the STP-SKY line Relay #2 trips first and sends the carrier signal Relay #1 trips after receiving the carrier signal the auto-reclosure is not successful and both relays trip 41
42 Example: Application Tests Sequence of events: fault on the STP-SKY line Relay #2 trips first and sends the carrier signal Relay #1 trips after receiving the carrier signal the auto-reclosure is not successful and both relays trip 42
43 Example: Statistical Tests Trip/no trip decision: - Repetitive tests to assess dependability/security Trip time: - Repetitive tests to assess application features (time coordination, etc.) 43
44 Example: Trip/No-Trip Evaluation 44
45 Example: Trip time 45
46 Example: Trip time (comparative) 46
47 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) test methodology and tools? What would be the benefits? Conclusions Q/A 47
48 Typical Hardware Options Simulation Computer I/O Subsystem Digital Analog Digital Data Acquisition RELAY 48
49 Typical Hardware Tools Relay Commercial Amplifiers Commercial Amplifiers Commercial D/A Boards PC bus Commercial Test Sets Commercial I/O Boards Std. comm. Interface Custom I/O Hardware Custom Interface PC Simulation Computer (PC) 49
50 Hardware Options AVO s PULSAR Test Sets V-Amplifier V-Amplifier V-Amplifier TLI s I/O Box (D/A conversion) V-Amplifier V-Amplifier V-Amplifier TLI s I/O Box (D/A conversion) C-Amplifier C-Amplifier C-Amplifier C-Amplifier C-Amplifier C-Amplifier TLI s I/O Box + High Power Amplifiers PC-based Open-Loop Simulator 50
51 Typical Software Tools DFR Transient Simulation Program (EMTP, ATP, etc.) DFR Files Comtrade Files ATP/ EMTP Files Other Waveform Files Data Generating Routine File Format Conversions Processing Relay Response GUI Processing Processing Processing FFT FFT Spectrum Editing Cut, Paste Waveform Replaying Engine Comm. Program To I/O Hardware 51
52 Software Options ATPDraw Base Model ATPDraw Input File Base Model ATP Input File Test Cases ATP Input Files BGEN ATP Test Cases ATP Output Files Batch of Tests Relay Assistant File (COMTRADE waveforms) Relay Assistant Simulator Hardware Reports Text Files Connected to Relay 52
53 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) testing methodology and tools? What would be the benefits? Conclusions Q/A 53
54 What would be the benefits? Purchase the best products for a given application Make sure the installed equipment is operating correctly Analyze any problems efficiently and in great detail Demonstrate to a regulator a reliable (selective) performance 54
55 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (preferred) testing methodology and tools? What would be the benefits? Conclusions Q/A 55
56 Conclusions Existing test practice serves a limited purpose The purpose IS to check Setting CALIBRATION and NOT to evaluate relay application performance Relay PERFORMANCE needs to be evaluated to assure the BEST decision regarding: - investment - application practices - relay performance under critical conditions 56
57 References M. Kezunovic, Y.Q. Xia, Y. Guo, C.W. Fromen, D.R. Sevcik, "Distance Relay Application Testing Using a Digital Simulator", IEEE Transactions on Power Delivery, Vol.12, No.1,January 1997, pp M. Kezunovic, Y.Q. Xia, Y. Guo, C.W. Fromen, D.R. Sevcik, "An Advanced Method for Testing of Distance Relay Operating Characteristic", IEEE Transactions on Power Delivery, Vol.11, No.1, pp , January W. Fromen, D.R. Sevcik, M. Kezunović, Trouble Shooting of Generator Differential Relay Operation Using Digital Simulators, 53 rd Annual Conference for Protective Relay Engineers, College Station, April
58 Outline Why relay testing? What is the relay performance of interest? What is the existing relay test practice? How the existing practice may be enhanced? What would be the new (proffered) test methodology and tools? What would be the benefits? Conclusions Q/A 58
59 The End Q/A 59
60 Appendix Simulator types Simulator architecture (generic) Simulator software Simulator hardware Vendor information: 60
61 Simulator Types Open-loop Simulator (Playback Digital Simulator): the response of an apparatus under test does not affect the simulation Close-loop Simulator: the response of an apparatus under test is fed back into the simulator and possibly affects the simulation (trip signals relayed to the models of circuit breakers, for example) 61
62 Simulator Types Real-time Simulator: the calculations for the output signals require less time than the sampling period. Thus, the computations can be done on-the-fly, i.e. in real-time Playback Simulator: the calculations for the output signals require more time than the sampling period. Thus, the computations must be done off-line, the results stored and next just played-back 62
63 Generic Architecture U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 63
64 Generic Architecture EMTP Software U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 64
65 Generic Architecture EMTP Software EMTP (EPRI/DCG) ATP (US/Canada/European) MORGAT, ARENE (EdF) NETOMAC (Siemens / TU Berlin) MicroTran EMTDC (Manitoba Hydro / RTDS Inc.) RTS (TAMU / TLI Inc.) 65
66 Generic Architecture IT Models U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 66
67 Generic Architecture IT Models Instrument Transformers (ITs) have to be modeled for accurate relay testing: ITs can be simulated by the EMTP software of a simulator ITs can be simulated by the specialized software for enhancing the simulation power of the entire simulator 67
68 Generic Architecture IT Models - Example: CCVT PCA-5 CCVT 68
69 Generic Architecture Relay Models U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 69
70 Generic Architecture Relay Models A given relay can be tested using simulation if its software model is available Also, to test a given physical relay in situations involving relay interaction, other relays may need to be simulated by the simulator 70
71 Generic Architecture User Interface U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 71
72 Generic Architecture User Interface Means for Network Modeling Tools for Signal Editing and Viewing Test Set-up and Selection of Test Files Automated Batch Processing of Tests Test Result Reporting and Analyzing 72
73 Generic Architecture I/O Interface U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 73
74 Generic Architecture I/O Interface D/A Conversion Digital I/O A/D Conversion 74
75 Generic Architecture Signal Reconstruction Requirements WAVEFORM RECONSTRUCTION SUBSYSTEM Simulation Computer I/O Subsystem Power Amplifiers Device Under Test Waveform Reconstruction Subsystem Requirements I/O Subsystem Requirements Power Amplifiers Subsystem Requirements Voltage Amplifiers Requirements Current Amplifiers Requirements 75
76 Generic Architecture Typical I/O Subsystem Specifications 76
77 Generic Architecture Power Amplifiers U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 77
78 Generic Architecture Typical Power Amplifiers Specifications 78
79 Generic Architecture Relay Requirements U S E R I N T E R F A C E EMTP Software IT Models Relay Models I/O Interface Power Amplifiers Protective Relay Simulation Environment Digital Simulator 79
80 Generic Architecture Relay Requirements 80
81 Further reading Simulator types Simulator architecture Simulator hardware/software Relay modeling Instrument transformer modeling User Interface Web site with references that can be downloaded: 81
82 Simulator types M. Kezunović, J. Domaszewicz, V. Skendžić, M. Aganagić, J.K. Bladow, S.M. McKenna, D.M. Hamai, Design, Implementation and Validation of a Real-Time Digital Simulator for Protection Relay Testing, IEEE Transactions on Power Delivery, Vol. 11, No. 1, pp , January M. Kezunović, S.M. McKenna, Real-Time Digital Simulator for Protective Relay Testing, IEEE Computer Applications in Power, Vol. 7, No. 3, pp , July M. Kezunović, Modular Simulators Match Cost and Performance Criteria, IEEE Computer Applications in Power, pp , April M. Kezunović, A. Abur, Lj. Kojović, V. Skendžić, H. Singh, DYNA- TEST Simulator for Relay Testing, Part I: Design Characteristics, IEEE Transactions on Power Delivery, Vol. 6, No. 4, pp , October M. Kezunović, A. Abur, Lj. Kojović, V. Skendžić, H. Singh, DYNA- TEST Simulator for Relay Testing, Part II: Performance Evaluation, IEEE Transactions on Power Delivery, Vol. 7, No. 3, pp , July
83 Simulator Architecture M. Kezunović, Z. Galijasević, PC Based Dynamic Relay Test Bench, Int l. Conference on Modern Trends in the Protection Schemes of Electric Power Apparatus and Systems, New Delhi, India, October M. Kezunović, C.W. Fromen, D.R. Sevcik, S.M. McKenna, B.A. Pickett, N. Izquierdo, Advanced Testing Methods for Protective Relays Using New Digital Simulator Designs, 1996 CIGRÉ Session, Paris, France, August S.M. McKenna, M. Kezunović, D. Hamai, Z. Galijasević, The Choice of a Simulation Time Step in the Real-Time Simulator Applications, First International Conference on Digital Power System Simulators (ICDS '95), College Station, Texas, April 1995 M. Kezunović, A. Gopalakrishnan, J. Domaszewicz, Q. Chen, F. Ji, X. Qi, I. Rikalo, C.W. Fromen, D.R. Sevcik, S.M. McKenna, M. Hammam, Design Characteristics of an Advanced Two-Terminal Digital Simulator for Relay Testing, First International Conference on Digital Power System Simulators (ICDS '95), College Station, April
84 Simulator Hardware/software M. Kezunović, B.A. Pickett, M.G. Adamiak, G.E. Alexander, K.R. Carr, G. Chirco, J. Esztergalyos, M. Jerosolimski, W.C. Kotheimer, R. Marttila, J.L. McElray, S.M. McKenna, P.G. McLaren, R.J. Murphy, J. Nordstrom, R. Ryan, V. Skendzic, S.I. Thompson, D.A. Tziouvaras F.M. Phillips, T. Sakaguchi, R.B. Sollero, Digital Simulator Performance Requirements for Relay Testing, IEEE Transactions on Power Delivery, Vol. 13, No. 1, pp , January M. Kezunović, D. Tziouvaras, B.A. Pickett, P.G. McLaren, Digital Simulator Activity within IEEE Power Systems Relaying Committee, First International Conference on Digital Power System Simulators (ICDS '95), College Station, April 1995 N. Izquierdo Jr., M. Kezunović, Z. Galijasević, F. Ji, A. Gopalakrishnan, J. Domaszewicz, Digital Simulator Design for Real-Time and Open-Loop Applications, First International Conference on Digital Power System Simulators (ICDS '95), College Station, Texas, April
85 Relay Modeling P.G. McLaren, C. Henville, V. Skendzic, A. Girgis, M. Sachdev, G. Benmouyal, K. Mustaphi, M. Kezunović, Lj. Kojovic, M. Meisinger, C. Simon, T. Sidhu, R. Marttila, D. Tziouvaras, Software Models for Relays, IEEE Transactions on Power Delivery, Vol. 16, No.2, pp , April M. Kezunović, User Friendly, Open System Software for Teaching Protective Relaying Application and Design Concepts, IEEE Transactions on Power Systems, Vol. 18, No. 3, August M. Kezunović, Y. Guo, Modeling and Simulation of the Power Transformer Faults and Related Protective Relay Behavior, IEEE Transactions On Power Delivery, Vol. 15, No. 1, pp , January M. Kezunović, B. Kasztenny, R. Martinez-Lagunes, N. Suphasan, New Software Tools for Power System Relaying Utilizing Modeling and Simulation, ISCA 14 th Int l. Conference on Computers and Their Applications, Cancun, Mexico, April
86 Instrument Transformer modeling D. Tziouvaras, P. McLaren, C. Alexander, D. Dawson, J. Esztergalyos, C. Fromen, M. Glinkowski, I. Hasenwinkle, M. Kezunović, L. Kojović, B. Kotheimer, R. Ruffel, J. Nordstrom, S. Zochol, Mathematical Models for Current, Voltage and Coupling Capacitor Voltage Transformers, IEEE Transactions on Power Delivery, Vol. 15, No. 1, pp , January M. Kezunović, Lj.Kojović, V. Skendžić, C.W. Fromen, D.R. Sevcik, S.L. Nilsson, Digital Models of Coupling Capacitor Voltage Transformers for Protective Relay Transient Studies, IEEE Transactions on Power Delivery, Vol. 7, No. 4, pp , October M. Kezunović, C. Fromen, F. Phillips, Lj. Kojović, A. Abur, D. Sevcik, Experimental Evaluation of EMTP Based Current Transformer Models for Protective Relay Transient Study, IEEE Transactions on Power Delivery, Vol. 9, No. 1, pp , January
87 User Interface M Kezunović, T. Popović, D. Sevcik, M. DoCarmo, Transient Testing of Protection Relays: Results, Methodology and Tools, International Conference on Power System Transients IPST 2003, New Orleans, September 2003 M.Kezunović, T. Popović, Assessing Application Features of Protective Relays and Systems Through Automated Testing Using Transients, IEEE/PES T&D 2002 Asia Pacific Conference, Yokohama, Japan, October M. Kezunović, F. Ji, S.M. McKenna, D.Hamai, Graphical User Interface for a Digital Real-Time Simulator, First International Conference on Digital Power System Simulators (ICDS '95), College Station, Texas, April B. Kasztenny, M. Kezunović, J. Galijasević, D. Williams, A New ATP Add-On for Modeling Internal Faults in Power Transformers, American Power Conference, Chicago, April
ANALYSIS OF PROTECTIVE RELAYING OPERATION AND RELATED POWER SYSTEM INTERACTION. Mladen Kezunovic, Slavko Vasilic
ANALYSIS OF PROTECTIVE RELAYING OPERATION AND RELATED POWER SYSTEM INTERACTION Mladen Kezunovic, Slavko Vasilic Texas A&M University Department of Electrical Engineering College Station, TX 77843-3128,
More informationPlease do not type here IMPROVING RELAY PERFORMANCE BY OFF-LINE AND ON-LINE EVALUATION
Please do not type here IMPROVING RELAY PERFORMANCE BY OFF-LINE AND ON-LINE EVALUATION Mladen Kezunovic, Jinfeng Ren, Chengzong Pang Texas A&M University U.S.A kezunov@ece.tamu.edu ABSTRACT: Protective
More informationNew Test Methodology for Evaluating Protective Relay Security and Dependability
1 New Test Methodology for Evaluating Protective Relay Security and Dependability M. Kezunovic, Fellow, IEEE, and J. Ren, Student Member, IEEE Abstract--This paper presents a new test methodology for evaluating
More informationDigital Simulator Applications in Protective Relay Testing
Digital Simulator Applications in Protective Relay Testing D. Sevcik, H. DoCarmo CenterPoint Energy Houston, TX, USA M. Kezunovic Texas A&M University College Station, TX, USA T. Popovic Test Laboratories
More informationA Novel Digital Relay Model Based on SIMULINK and Its Validation Based on Expert System
A Novel Digital Relay Model Based on SIMULINK and Its Validation Based on Expert System X. Luo, Student Member, IEEE, and M. Kezunovic, Fellow, IEEE Abstract This paper presents the development of a novel
More informationUser-Friendly, Open-System Software for Teaching Protective Relaying Application and Design Concepts
986 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 18, NO. 3, AUGUST 2003 User-Friendly, Open-System Software for Teaching Protective Relaying Application and Design Concepts Mladen Kezunovic, Fellow, IEEE Abstract
More informationModeling and Simulation Tools for Teaching Protective Relaying Design and Application for the Smart Grid
Modeling and Simulation Tools for Teaching Protective Relaying Design and Application for the Smart Grid J. Ren, M. Kezunovic Department of Electrical and Computer Engineering, Texas A&M University College
More informationNew Software Framework for Automated Analysis of Power System Transients
New Software Framework for Automated Analysis of Power System Transients M. Kezunovic Texas A&M University College Station, TX 77843, USA kezunov@ee.tamu.edu Z. Galijasevic Texas A&M University College
More informationADVANCED SOFTWARE ENVIRONMENT FOR EVALUATING THE PROTECTION PERFORMANCE USING MODELING AND SIMULATION
ADVANCED SOFTWARE ENVIRONMENT FOR EVALUATING THE PROTECTION PERFORMANCE USING MODELING AND SIMULATION ABSTRACT In this paper a new interactive simulation environment is proposed for protective algorithm
More informationReal Time Monitoring of
Real Time Monitoring of Cascading Events Mladen Kezunovic Nan Zhang, Hongbiao Song Texas A&M University Tele-Seminar, March 28, 2006 Project Reports (S-19) M. Kezunovic, H. Song and N. Zhang, Detection,
More informationTeaching Protective Relaying Design and Application Using New Modeling and Simulation Tools
Journal of Energy and Power Engineering 6 (2012) 762-770 D DAVID PUBLISHING Teaching Protective Relaying Design and Application Using New Modeling and Simulation Tools Jinfeng Ren and Mladen Kezunovic
More informationImplementing an Advanced Simulation Tool for Comprehensive Fault Analysis
Implementing an Advanced Simulation Tool for Comprehensive Fault Analysis 1 Nan Zhang, Student Member, IEEE, and Mladen Kezunovic, Fellow, IEEE Abstract Many large scale system blackouts involve relay
More informationAutomated Analysis of Digital Relay Data Based on Expert System
Automated Analysis of Digital Relay Data Based on Expert System X. Luo, Student Member, IEEE, and M. Kezunovic, Fellow, IEEE Abstract Modern digital protective relays generate various files and reports
More informationAutomatic simulation of IED measurements for substation data integration studies
1 Automatic simulation of IED measurements for substation data integration studies Y. Wu, Student Member, IEEE, and M. Kezunovic, Fellow, IEEE Abstract With the deregulation and restructuring of utility
More informationData Warehouse and Analysis Agents
Data Warehouse and Analysis Agents M. Kezunovic, T. Popovic Abstract - The paper discusses automated substation data integration and analysis. Recorded data collected from various substation IEDs is stored
More informationAUTOMATED ANALYSIS OF PROTECTIVE RELAY DATA
AUTOMATED ANALYSIS OF PROTECTIVE RELAY DATA M. Kezunovic, X. Luo Texas A&M University, U. S. A. kezunov@ee.tamu.edu, xuluo@ee.tamu.edu SUMMARY Validation and diagnosis of relay operation is very important
More informationRobust Topology Determination Based on Additional Substation Data from IEDs
Robust Topology Determination Based on Additional Substation Data from IEDs M. Kezunovic 1, Fellow IEEE, T. Djokic, T. Kostic 2, Member IEEE Abstract This paper describes an approach for more robust power
More informationVerifying the Protection System Operation Using an Advanced Fault Analysis Tool Combined with the Event Tree Analysis
1 Verifying the Protection System Operation Using an Advanced Fault Analysis Tool Combined with the Event Tree Analysis N. Zhang, Student Member, IEEE, and M. Kezunovic, Fellow, IEEE Abstract Relay misoperations
More informationA DIGITAL SIMULATOR DESIGN FOR REAL-TIME AND OPEN-LOOP APPLICATIONS
A DIGITAL SIMULATOR DESIGN FOR REAL-TIME AND OPEN-LOOP APPLICATIONS N.A. Izquierdo Jr. Commonwealth Edison Company M.Kezunovic, Z.Galijasevic, F.Ji 1, A.Gopalakrishnan, J.Domaszewicz Texas A&M University
More informationAUTOMATED FAULT AND DISTURBANCE DATA ANALYSIS. Special Report for PS#2. Special Reporter: Mladen Kezunovic * U.S.A.
AUTOMATED FAULT AND DISTURBANCE DATA ANALYSIS Special Report for PS#2 Special Reporter: Mladen Kezunovic * U.S.A. This paper gives a set of questions stimulated by twenty one papers submitted by the authors
More informationLocating faults in the transmission network using sparse field measurements, simulation data and genetic algorithm
Electric Power Systems Research 71 (2004) 169 177 Locating faults in the transmission network using sparse field measurements, simulation data and genetic algorithm Shanshan Luo a, Mladen Kezunovic b,,
More informationIntelligent Processing of IED data for Protection Engineers in the Smart Grid
Intelligent Processing of IED data for Protection Engineers in the Smart Grid M. Kezunovic,Fellow,F. Xu,B. Cuka,Student Member,IEEE Electrical and Computer Engineering Department Texas A&M University College
More informationAN ADVANCED FAULT DATA/INFORMATION PRESENTATION IN POWER SYSTEMS
AN ADVANCED FAULT DATA/INFORMATION PRESENTATION IN POWER SYSTEMS Mladen Kezunovic Biljana Matic Cuka Ozgur Gonen Noah Badayos Electrical and Computer Engineering Electrical and Computer Engineering Visualization
More informationImproving Real-time Fault Analysis and Validating Relay Operations to Prevent or Mitigate Cascading Blackouts
1 Improving Real-time Fault Analysis and Validating Relay Operations to Prevent or Mitigate Cascading Blackouts Nan Zhang, Student Member, IEEE, and Mladen Kezunovic, Fellow, IEEE Abstract This paper proposes
More informationMonitoring of Power System Topology in Real-Time
Monitoring of Power System Topology in Real-Time Mladen Kezunovic Texas A&M University Email: kezunov@ee.tamu.edu Abstract Power system topology is defined by the connectivity among power system components
More informationBlackstart Hardware-in-the-loop Relay Testing Platform
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Blackstart Hardware-in-the-loop Relay Testing Platform R. LIU R. SUN M. TANIA Washington
More informationAUTOMATED ANALYSIS OF FAULT RECORDS AND DISSEMINATION OF EVENT REPORTS
AUTOMATED ANALYSIS OF FAULT RECORDS AND DISSEMINATION OF EVENT REPORTS D. R. Sevcik, R. B. Lunsford M. Kezunovic Z. Galijasevic, S. Banu, T. Popovic Reliant Energy HL&P Texas A&M University Test Laboratories
More informationIntelligent Design. Substation Data Integration for Enhanced Asset Management Opportunities. By Mladen Kezunovic
Intelligent Design Data Integration for Enhanced Asset Management Opportunities By Mladen Kezunovic THIS ARTICLE EXPLORES A NONTRADITIONAL approach to asset management in which operational and nonoperational
More informationIMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS
IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage
More informationFuture Uses of Substation Data
1 Future Uses of Substation Data M. Kezunovic, Fellow, IEEE Abstract--The trend in today s development of power system monitoring, control and protection solutions is to install more Intelligent Electronic
More informationApplication of synchronized monitoring for dynamic performance analysis. Monitoring Power System Dynamic Performance Using Synchronized Sampling
Application of synchronized monitoring for dynamic performance analysis Monitoring Power System Dynamic Performance Using Synchronized Sampling Mladen Kezunovic, Zheng Ce Texas A&M University College Station,
More informationComparing Protective-Relaying Commissioning and Test Philosophies and Methods
Comparing Protective-Relaying Commissioning and Test Philosophies and Methods Abstract This paper will discuss the differences in types of testing philosophies, test set units and different automated testing
More informationSubstation Secondary Asset Health Monitoring and Management System
Substation Secondary Asset Health Monitoring and Management System Heng (Kevin) Chen and Lin Zhang Electric Power Group chen@electricpowergroup.com; zhang@electricpowergroup.com Oct. 23, 2018 Philadelphia,
More informationAutomated Circuit Breaker Monitoring
1 Automated Circuit Breaker Monitoring Maja Knezev, Zarko Djekic, Student Members, IEEE, and Mladen Kezunovic, Fellow, IEEE Abstract-- Circuit breakers are used in a power system to break or make current
More informationSupplemental Information
Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year
More informationUSER INTERFACING FOR AN AUTOMATED CIRCUIT BREAKER MONITORING AND ANALYSIS
USER INTERFACING FOR AN AUTOMATED CIRCUIT BREAKER MONITORING AND ANALYSIS Goran Latiško 1, Mladen Kezunović 2 1 Faculty of Technical Sciences, Novi Sad, Yugoslavia 2 Texas A&M University,College Station,
More informationAUTOMATED MONITORING OF SUBSTATION EQUIPMENT PERFORMANCE AND MAINTENANCE NEEDS USING SYNCHRONIZED SAMPLING
AUTOMATED MONITORING OF SUBSTATION EQUIPMENT PERFORMANCE AND MAINTENANCE NEEDS USING SYNCHRONIZED SAMPLING M. Kezunovic A. Edris D. Sevcik J. Ciufo, A. Sabouba Texas A&M University EPRI CenterPoint Energy
More informationSubstation Automated Data Analysis: Deployment Challenges
Substation Automated Data Analysis: Deployment Challenges M. Kezunovic, T. Popovic S. Sternfeld B. Fardanesh B. Clowe P. Myrda TLI, Inc. FirstEnergy Corp. NYPA CenterPoint Energy EPRI College Station,
More informationUses of Operational and Non-Operational Data
Mladen Kezunovic Texas A&M University http://www.ee.tamu.edu/~pscp/index.html Uses of Operational and Non-Operational Data Research Seminar Abu Dhabi, UAE, March 8, 2007 Outline Introduction Background:
More informationA real time fault analysis tool for monitoring operation of transmission line protective relay
Electric Power Systems Research 77 (2007) 361 370 A real time fault analysis tool for monitoring operation of transmission line protective relay Nan Zhang, Mladen Kezunovic Department of Electrical and
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More information20 Years and Counting: Deploying a System for Automated Analysis of Transmission Line Faults
20 Years and Counting: Deploying a System for Automated Analysis of Transmission Line Faults Mladen Kezunovic #1, Donald Sevcik *2, Robert Lunsford *3, Brian Clowe *4, Tomo Popovic **5 # Dept. Electrical
More informationDigital Protection Past, Present, and Future
Digital Protection Past, Present, and Future Eric A. Udren Quanta Technology, LLC Pittsburgh, PA Presentation for CIGRÉ Grid of the Future Symposium Boston, MA October 22, 2013 eudren@quanta-technology.com
More informationAutomating Power System Fault Diagnosis through Multi-Agent System Technology
Automating Power System Fault Diagnosis through Multi-Agent System Technology S. D. J. McArthur, E. M. Davidson, J.A. Hossack and J. R. McDonald Institute for Energy and Environment, University of Strathclyde,
More informationOptimizing Performance of Fast Transfer Schemes
MOTOR BUS TRANSFER Application Note #19 Optimizing Performance of Fast Transfer Schemes 1. INTRODUCTION The sequential fast transfer method for plant auxiliary motor buses has been practised and applied
More informationSynchronized Sampling Uses for Real-Time Monitoring and Control
Synchronized Sampling Uses for Real-Time Monitoring and Control Ce Zheng Dept. of Electrical Engineering Texas A&M University College Station, U.S. zhengce@neo.tamu.edu Mladen Kezunovic Dept. of Electrical
More informationSoftware for Enhanced Monitoring in Integrated Substations
Software for Enhanced Monitoring in Integrated Substations Sasa Jakovljevic, Student Member, IEEE and Mladen Kezunovic, Fellow, IEEE Abstract--Substation data integration is facilitated by existence and
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationDynamic State Estimation Based Protection: Laboratory Validation
Dynamic State Estimation Based Protection: Laboratory Validation Paul Myrda - EPRI & A.P. Meliopoulos and G. J. Cokkinides - Georgia Tech October 21, 2014, Houston, TX Contents Background and Motivation
More informationAUTOMATION OF POWER DISTRIBUTION USING SCADA
1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from
More informationIntegrating Electromagnetic Transient Simulation with Other Design Tools
Integrating Electromagnetic Transient Simulation with Other Design Tools A.M. Gole, P. Demchenko, D. Kell, G.D. Irwin University of Manitoba Manitoba HVDC Research Centre Winnipeg, Canada Abstract - Recent
More informationTHE INTEGRATED TESTING SOLUTION
Test & Data Management Software TDMS protective relays energy meters transducers power quality CT-VT-PT transformers ground grid circuit breakers batteries surge arresters THE INTEGRATED TESTING SOLUTION
More informationAn Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems
An Artificial Intelligence Based Approach for Bus Bar Differential Protection Faults Analysis in Distribution Systems By Eng. Sameh Moustafa Mohamed Abd Elgowad Elbana A thesis submitted to The Faculty
More informationPSC 2014 CLEMSON UNIVERSITY
PSC 2014 CLEMSON UNIVERSITY HAND-IN-HAND THE EVOLUTION OF REAL -TIME SIMULATION AND SMART GRID NETWORKS Presentation Outline 1 Brief history of real time simulation First steps toward Smart Grid Devices
More informationHardware In the Loop Optimization Using a Real Time Simulation Environment
Hardware In the Loop Optimization Using a Real Time Simulation Environment In-Kwon Park, A. M. Gole, Paul Forsyth, Rick Kuffel Abstract The optimization enabled electromagnetic transient simulation technique
More informationT&D Technology Research Stem
T&D Technology Research Stem Highlights of T&D Stem Activity (2000-2005) Mladen Kezunovic Former Stem Leader IAB Meeting Madison, June 1, 2006 1 Outline History Research Areas Projects Survey Initiatives
More informationREQUIREMENTS FOR AUTOMATED ANALYSIS OF SUBSTATION DATA
REQUIREMENTS FOR AUTOMATED ANALYSIS OF SUBSTATION DATA Presented to: North American Transmission & Distribution Conference & Expo May 9-11, 2005, Toronto, Canada J. Ciufo, K. Rolston Hydro One M. Kezunovic,
More informationCommission Testing Methods for Protection Systems
Commission Testing Methods for Protection Systems Tom Ernst GE Grid Solutions Ken Sletten Minnesota Power Abstract Commission testing should be designed to assure that the protection system is set and
More informationSubstation SCADA Monitoring
Substation SCADA Monitoring Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Substations are a critical component
More informationC I R E D 22 nd International Conference on Electricity Distribution Stockholm, June 2013
C I R E D 22 nd International Conference on Electricity Distribution Stockholm, 0-3 June 203 Paper 399 PROTECTION OPERATION ANALYSIS IN SMART GRIDS Alexander Apostolov OMICRON electronics - USA alex.apostolov@omicronusa.com
More informationi-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection
i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection 1 Process PG&E Order No. 754 Analysis Receive Bus List from Planning that Meet the Criteria in Table A Protection Computes Actual Clearing
More informationMeasures of Value. By Tomo Popovic and Mladen Kezunovic /12/$ IEEE. september/october IEEE power & energy magazine
Measures of Value By Tomo Popovic and Mladen Kezunovic 58 IEEE power & energy magazine 1540-7977/12/$31.00 2012 IEEE september/october 2012 Data Analytics for Automated Fault Analysis THE POWER INDUSTRY
More informationF6150. Power System Simulator For Testing Protection Relays and Schemes.
F6TesT Visual protection testing software for f6000 power system simulators The ultimate software for the automated testing of individual relays and complete protection schemes F6TesT software offers the
More informationData Exchange Design and A Textured State Estimation Algorithm For Distributed Multi-Utility Operations In Electric Power Market.
Data Exchange Design and A Textured State Estimation Algorithm For Distributed Multi-Utility Operations In Electric Power Market Jiansheng Lei Advisor: Dr. Garng M. Huang Department of Electrical Engineering
More informationData Integration and Information Exchange for Enhanced Control and Protection of Power Systems
Data Integration and Information Exchange for Enhanced Control and Protection of Power Systems Mladen Kezunovic, IEEE Fellow Texas A&M University, Department of Electrical Engineering, College Station,
More informationCMC 256plus. The High Precision Relay Test Set and Universal Calibrator
CMC 256plus The High Precision Relay Test Set and Universal Calibrator CMC 256plus High Precision Relay Testing and The CMC 256plus is the first choice for applications requiring very high accuracy. This
More informationNew concept and solution for monitoring and control system for the 21 st century substation
1 New concept and solution for monitoring and control system for the 21 st century substation M. Kezunovic, Fellow, IEEE, C. Guo, Student Member, IEEE, Y. Guan, Student Member, IEEE, M. Ghavami, Student
More informationThe Real-Time Simulator for Protective Relays Testing Using MATLAB/Simulink Software
The Real-Time Simulator for Protective Relays Testing Using MATLAB/Simulink Software Adam Smolarczyk Warsaw University of Technology Warsaw, Poland Adam.Smolarczyk@ien.pw.edu.pl Ryszard Kowalik Warsaw
More informationBlackout 2003 Reliability Recommendations
Blackout 2003 Reliability Recommendations 2005 NPCC General Meeting The Cranwell Resort Lenox, MA September 29, 2005 Philip A. Fedora Director, Market Reliability Interface Northeast Power Coordinating
More informationInformation Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationRELAY CO-ORDINATION IN A 11KV SUBSTATION USING ETAP
International Journal of Recent Innovation in Engineering and Research Scientific Journal Impact Factor - 3.605 by SJIF e- ISSN: 2456 2084 RELAY CO-ORDINATION IN A 11KV SUBSTATION USING ETAP Ms. Serene
More informationPG&E ARRA Synchrophasor Project
PG&E ARRA Synchrophasor Project End-to-End Testing June 9, 2011 Vahid Madani Proof of Concept Testing San Ramon 1 Proof of Concept Stage (POC) POC is a smaller scale synchrophasor system used to test,
More informationIowa State University
Iowa State University Cyber Security Smart Grid Testbed Senior Design, Final Report Dec 13-11 Derek Reiser Jared Pixley Rick Sutton Faculty Advisor: Professor Manimaran Govindarasu 1 Table of Contents
More informationHVDC Control and Protection Testing Using the RTDS Simulator
HVDC Control and Protection Testing Using the RTDS Simulator Yong-Beum Yoon, Tae-Kyun Kim, Seung-Tae Cha Power System Research Laboratory, Korea Electric Power Research Institute, Korea Abstract: Many
More informationTexas A&M University (TAMU), Department of ECEN, College Station, TX. Director, Power Systems Control and Protection Laboratory 1992-Present
Dr. Mladen Kezunovic, P.E. Department of Electrical and Computer Engineering Texas A&M University Tel: 979-845-7509; FAX: 979-845-6259; E-mail: kezunov@ece.tamu.edu CURRENT Texas A&M University (TAMU),
More informationIEC Test Equipment Requirements
OMICRON K02 03 20060309 IEC 61850 Test Equipment Requirements Dr. Alexander Apostolov K02 03 20060309 Page: 1 Intelligent Substation Automation Systems OMICRON K02 03 20060309 Page: 2 Intelligent Sensor
More informationDESIGN OF INTEGRATED ANALYSIS REPORTS USING DATA FROM SUBSTATION IEDs
DESIGN OF INTEGRATED ANALYSIS REPORTS USING DATA FROM SUBSTATION IEDs M. Kezunovic*, P. Myrda**, B. Matic-Cuka* * Texas A&M University, ** Electric Power Research Institute Abstract Full advantage of data
More informationHitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0027 Hardwired Back Up System
Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0027 Hardwired Back Up System RO TITLE: Hardwired Back Up System REVISION : 5 Overall RO Closure Date (Planned):
More informationAUTOMATED TESTING OF BUSBAR DIFFERENTIAL PROTECTION USING A SYSTEM-BASED APPROACH. Christopher Pritchard, Florian Fink
AUTOMATED TESTING OF BUSBAR DIFFERENTIAL PROTECTION USING A SYSTEM-BASED APPROACH Christopher Pritchard, Florian Fink OMICRON electronics GmbH, Klaus, Austria; Christopher.Pritchard@omicronenergy.com ABSTRACT
More informationIdentify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements
Introduction to Bus Protection By Matt Horvath, P.E. November 6, 2018 Electrical Buses Physical and Electrical Junction A bus is a critical element of a power system, as it is the point of convergence
More informationENTERPRISE-WIDE USES OF DIAGNOSTICS DATA
ENTERPRISE-WIDE USES OF DIAGNOSTICS DATA M. Kezunovic, B. Matic-Cuka A. Edris Texas A&M University Electric Power Research Institute Abstract The paper discusses how the data integration and information
More informationInternational Journal of Engineering Trends and Technology (IJETT) Volume 26 Number 2- August 2015
Microprocessor-Based Protective Applications in Nigeria Power System Protections J.O. Aibangbee #1, S.O. Onohaebi *2. # Department of Electrical &Computer Engineering, Bells University of Technology, Ota,
More informationLow Impact Generation CIP Compliance. Ryan Walter
Low Impact Generation CIP Compliance Ryan Walter Agenda Entity Overview NERC CIP Introduction CIP-002-5.1, Asset Classification What Should Already be Done CIP-003-7, Low Impact Requirements Tri-State
More informationSmart Grid Protection through Self-Healing
Smart Grid Protection through Self-Healing Chathurika Chandraratne, R.T. Naayagi, Thillainathan Logenthiran School of Electrical and Electronic Engineering Newcastle University (Singapore) Singapore 567739
More informationSPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS. G. Steynberg
SPECIAL CONSIDERATION OF FEEDER PROTECTION FOR BREAKER-AND-A-HALF CONFIGURA- TIONS G. Steynberg Siemens AG; Energy Sector, Energy Automation, Nuremberg 1. INTRODUCTION The breaker-and-a-half configuration
More informationChapter 2 State Estimation and Visualization
Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation
More informationControl and Protection System Win-TDC
HVDC Control & Protection Control and Protection System Win-TDC HVDC Aysen -SIC Basics of HVDC Basic Design Equipment Info Control & Protection Station Design Logistics Project Management Maintenance 1
More informationDevelopment of a Real-Time Simulator Using EMTP-ATP Foreign models for Testing Relays
Development of a Real-Time Simulator Using EMTP-ATP Foreign models for Testing Relays September 17-18, 2018 - Arnhem, the Netherlands Renzo G. Fabián Espinoza Independent, Peru/Brazil Lise R. Romero Navarrete
More informationThe Six Ways to Ensure Improper Operation of Microprocessor Relays
1 The Six Ways to Ensure Improper Operation of Microprocessor Relays Kevin Donahoe (GE Grid Solutions) Abstract At the 44th Annual Conference for Protective Relay Engineers in 1991, Walt Elmore presented
More informationAutomated Fault and Disturbance Analysis: Understanding the Configuration Challenge
Automated Fault and Disturbance Analysis: Understanding the Configuration Challenge M. Kezunovic, Fellow, IEEE, S. Sternfeld, M. Datta-Barua, Member, IEEE, D. Maragal, Member, IEEE, and T. Popovic, Senior
More informationSCADA Training - T&D Automation
SCADA Training - T&D Automation Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq This course covers all the
More informationLooking into the Future Protection, Automation and Control Systems
1 Looking into the Future Protection, Automation and Control Systems, Power System Relaying Committee Substation Subcommittee Working Group K15 on Centralized Substation Protection and Control Presented
More informationBREAKER FAILURE PROTECTION
0 th Annual HANDS-ON RELAY SCHOOL March 11-15, 201 REAKER FAILURE PROTECTION brent.c@relayapplication.com OUTLINE Protection System Failures and reaker Failures Protection versus Relaying Relay Schemes
More informationUse of Substation IED Data for Improved Alarm Processing and Fault Location
Use of Substation IED Data for Improved Alarm Processing and Fault Location Papiya Dutta, Yufan Guan Student Member, IEEE and M. Kezunovic, Fellow, IEEE 1 Abstract-- With the advent of technology, substations
More informationDesign of Communication Function Test System for Intelligent Low Voltage Electrical Apparatus Based on LabVIEW and Modbus RTU Protocol
2017 Asia-Pacific Engineering and Technology Conference (APETC 2017) ISBN: 978-1-60595-443-1 Design of Communication Function Test System for Intelligent Low Voltage Electrical Apparatus Based on LabVIEW
More informationINTELLIGENT ELECTRONIC DEVICE DATA EXTRACTION AT HYDRO ONE. Sheng Hsu Senior Protection & Control Engineer Hydro One
INTELLIGENT ELECTRONIC DEVICE DATA EXTRACTION AT HYDRO ONE Sheng Hsu Senior Protection & Control Engineer Hydro One sheng.hsu@hydroone.com Adam Gauci Field Applications Engineer Cooper Power Systems adam.gauci@cybectec.com
More informationAn Integrated System for Automating Fault Analysis in EHV Network
496 An Integrated System for Automating Fault Analysis in EHV Network K. Elanseralathan, M. Jayalakshmi, G. Koperundevi, S. Sivasankari and R. Subha Abstract--This work proposes an integrated system for
More informationIJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Comparison of Shunt Facts Devices for the Improvement of Transient Stability of Two Machine
More informationYour Power Grid Your Conditions
Your Power Grid Your Conditions In Real Time Knowledge Being the first of its kind, the RTDS Simulator is the world s benchmark for performing real time simulations. Since worstcase power system conditions
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More information