July 26, Dear Mr. Millar:

Size: px
Start display at page:

Download "July 26, Dear Mr. Millar:"

Transcription

1 July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA Dear Mr. Millar: As you are aware, Clean Line Energy Partners (Clean Line) is developing the Centennial West Clean Line transmission project, an estimated 900-mile 3,500 MW, high voltage direct current (HVDC) transmission line connecting renewable energy resources in Arizona and New Mexico to load centers in California. As an independently developed, privately financed interstate transmission line designed specifically to move renewable energy, the Centennial West Clean Line project has no clear way to attain Transmission Planning (TP) deliverability rights through the current Generator Interconnection and Deliverability Allocation Procedures (GIDAP). Without these rights, the project will be unable to deliver clean, low-cost energy to California from new generation in other states. These future wind and solar facilities are completely dependent on new, interstate high-voltage transmission projects, and cannot apply for interconnection through the existing CAISO process. With these concerns in mind, the CAISO interconnection process should be modified such that a transmission facility, alone, can be granted TP-deliverability rights. Clean Line appreciates the opportunity to provide a list of modifications that we believe warrant discussion in order to allow external transmission projects like Centennial West the opportunity to participate in the CAISO interconnection processes. The issues and modifications are discussed in more detail, including suggested modification to the CAISO tariff, in the attachment to this letter. 1. Large Facility Interconnection Agreement The CAISO should create a Large Facility Interconnection Agreement by modifying the language of its existing Large Generation Interconnection Agreement. The modified language would allow merchant HVDC transmission lines to interconnect to the CAISO system and receive TP deliverability. 2. Transmission Planning (TP) Deliverability Eligibility Criteria The current eligibility criteria in the GIDAP are too onerous for a merchant HVDC transmission project. Modifying the environmental permitting progress, financing and land acquisition criteria as indicated in Attachment 1 will provide a more reasonable path to deliverability for merchant transmission projects. 3. Site Exclusivity The current definition of site exclusivity, modeled on a generation project, should be adapted such that merchant HVDC transmission projects can demonstrate site exclusivity without having to acquire the right to build along the entire route of the line. 4. Refunds of Letters of Credit Tariff language providing for partial recovery of Interconnection Financial Security should be modified to make it applicable to merchant HVDC projects. 5. Network Upgrade Costs Responsibility for the cost of network upgrades should be divided amongst projects based not on the size of the project, but on the effect that a project has on identified constraints.

2 6. Modeling Software The CAISO should accept modeling files in both the currently required PSLF and the widely-used PSS/E formats to address an intellectual property concern with HVDC models in PSLF format. At your earliest convenience, we would like to have a meeting with CAISO staff to discuss these issues and receive feedback. Keith Sparks, Director of Development for the Centennial West Clean Line, will contact you to schedule this meeting. Respectfully submitted, Jayshree Desai, Executive Vice President Clean Line Energy Partners LLC CC: Keith Casey, VP of Market and Infrastructure Development CAISO Lorenzo Kristov, Principal Market Design Architect CAISO Robert Sparks, Manager of Regional Transmission, South CAISO Ashutosh Bhagwat, CAISO Board Robert Foster, CAISO Board Angelina Galiteva, CAISO Board Richard Maullin, CAISO Board David Olsen, CAISO Board Carlos Clay, Deputy Director of Electric Power Regulation, West FERC Saeed Farrokhpay, Energy Industry Analyst, CAISO FERC

3 Attachment 1 1. Large Facility Interconnection Agreements Summary: Large Generator Interconnection Agreements (LGIAs) serve to outline the scope of interconnection service; conditions, rights and obligations in management of the engineering, construction, and procurement activities for interconnection facilities; and many other items of importance for a new generation facility that is being interconnected to an existing transmission system. Without an equivalent agreement for transmission lines such as the Centennial West Project, it is unclear how such a facility would interconnect with a host transmission system and ensure proper operational agreements are in place to ensure reliable operation.. Ask: Clean Line requests that the CAISO modify Appendix V of the CAISO Tariff the Large Generator Interconnection Agreement (LGIA) in order to allow HVDC facilities to execute the equivalent of a LGIA. Clean Line proposes that the Agreement would be re-named to identify this new flexibility: e.g., Large Facility Interconnection Agreement or simply Interconnection Agreement. An example of this concept exists in the case of Hudson Transmission Partners, NYISO, and Consolidated Edison. 1 As in the Hudson case, a FERC approval of the LFIA may be required. CAISO may eventually choose to initiate a stakeholder process to implement an ongoing process for Large Facility Interconnection Agreements; however, projects currently under development and/or already in the CAISO queue cannot afford to wait for the completion of a stakeholder process. It is necessary to have an alternative process in the meantime, as outlined above. 2. Transmission Planning (TP) Deliverability Eligibility Criteria Summary: Attachment DD of the CAISO Tariff describes the eligibility criteria for projects to receive (section 8.9.2) and retain (section 8.9.3) TP Deliverability. Specifically, the language states that an Interconnection Customer must, at a minimum, meet criteria (1)d and (2)a or (2)d. Specific to projects like Centennial West, the language of these criteria is geared toward generators and not transmission lines and therefore meeting the minimum criteria is impossible unless additional language is added to reflect the nature of controllable transmission lines. Ask: Clean Line requests that the eligibility criteria for TP Deliverability be modified to incorporate the ability for HVDC transmission lines to meet the criteria. Examples are shown below through redline of the criteria as filed by the CAISO with FERC on May 25, (1) Permitting Status: An Interconnection Customer s Generating Facility must meet at least one of the following: as to the entire Generating Facility: 1 FERC Docket No. ER Merchant Transmission Facility Interconnection Agreement among NYISO, ConEd and Hudson Transmission Partners, LLC

4 a. The Interconnection Customer has received its final governmental permit(s) or authorization allowing the Facility to commence construction. b. The Interconnection Customer has received a draft environmental report document (or equivalent environmental permitting document) indicating likely approval of the requested permit and/or which indicates that the permitting authority has not found an environmental impact which would likely prevent the permit approval. c. The Interconnection Customer has applied for the necessary governmental permits or authorizations, has submitted an application to become a Public Utility or has filed with the FERC for negotiated rate authority and the authority has deemed such documentation as data adequate for the authority to initiate its review process. d. The Interconnection Customer has applied for the necessary governmental permit or authorization for the construction, and has submitted an application to become a Public Utility, or has filed with the FERC for negotiated rate authority. (2) Project financing status. An Interconnection Customer s Generating Facility must meet at least one of the following: as to the entire Generating Facility: a. The Generating Facility will be balance-sheet financed or has otherwise received a commitment of project financing, and the Interconnection Customer represents to the ISO that either it has a regulator-approved power purchase agreement or capacity contract (in the case of a Merchant Transmission Facility) or that the Interconnection Customer is proceeding to commercial operation without a power purchase agreement or capacity contract. b. The Interconnection Customer has an executed and regulator-approved power purchase agreement or capacity contract for the full MW generating capacity of the Generating Facility or of the full MW transmission capacity of the Merchant Transmission Facility as specified in the Interconnection Request. c. The Interconnection Customer has an executed power purchase agreement or transmission capacity contract but such agreement has not yet received regulatory approval. d. The Interconnection Customer does not have an executed power purchase agreement or transmission capacity contract but the Interconnection Customer is included on an active short list or other commercially recognized method of preferential ranking of power providers by a prospective purchaser Load Serving Entity. (3) Land acquisition a. The Interconnection Customer demonstrates a present legal right to begin construction of the Generation Facility on one hundred percent (100%) of the real property footprint necessary for the entire Generating facility or HVDC Converter facility. b. The Interconnection Customer demonstrates Site Exclusivity 2. 2 Clean Line also requests modification of the definition of Site Exclusivity as documented herein under #3.

5 3. Site Exclusivity Summary: A long-distance transmission line cannot be expected to provide site exclusivity, as defined in Appendix A of the CAISO Tariff, for a significant portion of the project right-of-way prior to receiving an interconnection agreement. Control of adequate land at the point of interconnection within California (or to CAISO facilities) is a more reasonable measure of site exclusivity for a Merchant Transmission Line. Ask: Clean Line requests that the definition for site exclusivity be modified as suggested in the redline of the Site Exclusivity definition as shown below. Site Exclusivity Documentation reasonably demonstrating: (1) For private land: (a) Ownership of, a leasehold interest in, or a right to develop property upon which the Generating Facility will be located consisting of a minimum of 50% of the acreage reasonably necessary to accommodate the Generating Facility or HVDC Converter facility; or (b) an option to purchase or acquire a leasehold interest in property upon which the Generating Facility will be located consisting of a minimum of 50% of the acreage reasonably necessary to accommodate the Generating Facility or HVDC Converter facility. (2) For public land, including that controlled or managed by any federal, state or local agency, a final, non-appealable permit, license, or other right to use the property for the purpose of generating, or converting and transmitting, electric power and in acreage reasonably necessary to accommodate the Generating Facility or HVDC Converter Station, which exclusive right to use public land under the management of the federal Bureau of Land Management shall be in a form specified by the Bureau of Land Management. 4. Refunds of Letters of Credit for HVDC Transmission Facilities Summary: There are several reasons why an Interconnection Customer is able to secure partial recovery of Interconnection Financial Security upon withdrawal of an interconnection request or termination of an interconnection agreement. Some of these conditions, as currently written in the tariff, are inapplicable to HVDC Transmission Facilities. Ask: Clean Line requests that the conditions for partial recovery of Interconnection Financial Security, as outlined in section of Attachment DD of the CAISO Tariff, be modified in order to incorporate provisions for HVDC transmission facilities. The following redlined tariff language is offered as an example:

6 A portion of the Interconnection Financial Security shall be released to the Interconnection Customer, consistent with Section , if the withdrawal of the Interconnection Request or termination of the GIA Interconnection Agreement occurs for any of the following reasons: (a) Failure to Secure a Power Purchase Agreement or Transmission Capacity Contract. At the time of withdrawal of the Interconnection Request or termination of the Interconnection Agreement, the Interconnection Customer demonstrates to the CAISO that it has failed to secure an acceptable power purchase agreement for the Energy or capacity of the Generating Facility or a transmission capacity contract for the HVDC Transmission Facility after a good faith effort to do so. A good faith effort can be established by demonstrating participation in a competitive solicitation process or bilateral negotiations with an entity other than an Affiliate that progressed, at minimum, to the mutual exchange by all counter-parties of proposed term sheets. (b) Failure to Secure a Necessary Permit. At the time of withdrawal of the Interconnection Request or termination of the GIA Interconnection Agreement, the Interconnection Customer demonstrates to the CAISO that it has received a final denial from the primary issuing Governmental Authority of any permit or other authorization necessary for the construction or operation of the Generating Facility or HVDC Transmission Facility. (c) Increase in the Cost of Participating TO s Interconnection Facilities. The Interconnection Customer withdraws the Interconnection Request or terminates the GIA Interconnection Agreement based on an increase of more than 30% or $300,000, whichever is greater, in the estimated cost of Participating TO s Interconnection Facilities between the Phase I Interconnection Study and the Phase II Interconnection Study, provided, however, that the Interconnection Financial Security shall not be released if this increase in the estimated cost is due to the Interconnection Customer s requested modification to the interconnection configuration. (d) Material Change in Interconnection Customer Interconnection Facilities Created by a CAISO Change in the Point of Interconnection. The Interconnection Customer withdraws the Interconnection Request or terminates the GIA Interconnection Agreement based on a material change from the Phase I Interconnection Study in the Point of Interconnection for the Generating Facility or HVDC Transmission Facility mandated by the CAISO and included in the final Phase II Interconnection Study. A material change in the Point of Interconnection shall be where Point of Interconnection has moved to (i) a different substation, (ii) a different line on a different right of way, or (iii) a materially different location than previously identified on the same line. (e) An Interconnection Customer having selected Option (A) in accordance with Section 7.2 is not allocated TP Deliverability and notifies the CAISO of its election to withdraw by the

7 deadline for the second posting of Interconnection Financial Security. This condition does not apply to an Interconnection Customer whose Generating Facility or HVDC Transmission Facility was allocated TP Deliverability for a portion of its Interconnection Request and elected to seek additional Deliverability in the next TP Deliverability allocation process. (f) For an Interconnection Customer having selected Option (B) in accordance with Section 7.2 an increase in the Phase II Interconnection Study cost estimates for ANDUs over the Phase I Interconnection Study cost estimates for ADNUs of either twenty (20) percent, or $20 million, whichever is less. Provided, however, that the Interconnection Financial Security shall not be released if this increase in the estimated cost of ADNUs is due to the Interconnection customer s requested modification to the interconnection configuration. 5. Pro-Rata Assignment of Network Upgrade Costs Summary: Reliability Network Upgrades (RNU) are identified during interconnection studies and, per section of Attachment DD of the CAISO Tariff, are then cost allocated to interconnection customers, pro rata, on the basis of the maximum megawatt electrical output of each proposed new Generating Facility This process does not take into consideration the fact that nearby projects might have greater impacts to the needed RNU. Ask: Clean Line requests that the cost allocation of identified RNUs be accomplished through pro rata cost allocation on the basis of a project s impact on the identified constraints that promote the need for the RNU. Impact here refers to a project s contribution to the constraint taking into account proximity to the constraint rather than just maximum megawatt electrical output of the facility. Without using a methodology that considers cost causation, as suggested here, larger projects are unduly taking on larger costs than otherwise would be the case. Under the CAISO s long standing policy of RNU reimbursement by the Participating Transmission Owner, this was not an issue; however, with the new designation of Option B projects under the GIDAP, the Participating Transmission Owner (PTO) is not required to pay back the cost of RNUs and therefore this issue becomes more important for large projects. 6. Generation Application Requirements PSLF Models Summary: GE s PSLF software is the package of choice for the CAISO to perform interconnection studies. Generation models are therefore required to be submitted in PSLF format. In consideration of HVDC transmission projects, however, vendor competition makes it very difficult to use PSLF due to the inability to encode modeling files and protect Intellectual Property. GE s recent acquisition of Chinese HVDC vendors has raised security concerns that make it impossible to procure necessary modeling files in PSLF format. PSS/E, a Siemens PTI software package, is used throughout the Eastern Interconnection as well as by some entities within the WECC to perform the same studies as are conducted using PSLF, including steady-state, powerflow-based analyses and stability analyses. PSS/E modeling files, however, can be encoded to ensure protection of intellectual property and are therefore preferred by vendors for provision of accurate model data.

8 The Centennial West Clean Line is a multi-terminal, VSC-based HVDC project. A model exists that can represent this configuration and technology but this model is only available in PSS/E format. Due to concerns of intellectual property protection, there is currently no plan to build a model that can be used in the GE PSLF format as needed by the CAISO for interconnection studies. Ask: Clean Line requests the ability to submit modeling files in either PSLF or PSS/E format in order to participate in the interconnection studies.

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: January 30, 2019 Re: Decision on

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements In accordance with the Federal Energy Regulatory Commission (FERC) order issued on January 24, 2003 (as modified

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

Specific topics covered in this brief include:

Specific topics covered in this brief include: April 2008 Summary Welcome to the Fifteenth National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 28, 2008, Transmission Update conference

More information

Agreements & Queue Management

Agreements & Queue Management Agreements & Queue Management Resource Interconnection Fair February 24, 2016 Page 1 Interconnection Process Map You are here Page 2 Topics 1. Generator Interconnection Agreement (GIA) 2. Affected Systems

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Order No. 1000 Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Thinh Nguyen Manager, Interconnection Projects New York Independent System Operator Joint

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM)

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM) Business Practice Manual For Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM) Version 1.0 Last Revised: June 176July 26, 2013 Approval History Approval Date: MM DD YYYY07/26/2013

More information

ATTACHMENT I: Generator Interconnection Procedures (GIP)

ATTACHMENT I: Generator Interconnection Procedures (GIP) ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

The NYISO shall assign a Queue Position based upon the date and time of receipt of the

The NYISO shall assign a Queue Position based upon the date and time of receipt of the 30.4 Queue Position 30.4.1 General The NYISO shall assign a Queue Position based upon the date and time of receipt of the valid Interconnection Request; provided that, if the sole reason an Interconnection

More information

132 FERC 61,005 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

132 FERC 61,005 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 132 FERC 61,005 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, and John R. Norris. California Independent

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted By Company Date Submitted Shannon Eddy (shannon@consciousventuresgroup.com) Rachel Gold (Rachel@consciousventuresgroup.com) Large-scale Solar Association (LSA) December

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION HORUS Central Valley Solar 1, LLC ) HORUS Central Valley Solar 2, LLC ) ) v. ) Docket No. EL16-104-000 ) California Independent

More information

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator Assembly Standing Committee on Energy Kevin A. Cahill, Chairman Assembly Standing Committee on Corporations, Authorities and Commissions James F. Brennan, Chairman Assembly Standing Committee on Cities

More information

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission The following White Paper proposes a draft methodology for determining the incremental amount of transfer capability that would be the basis for the quantity of Merchant Transmission CRRs to be allocated

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service ) Docket No. ER Company )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service ) Docket No. ER Company ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Arizona Public Service ) Docket No. ER14-2430 Company ) COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION The California

More information

March 15, 2011 VIA ELECTRONIC FILING

March 15, 2011 VIA ELECTRONIC FILING California Independent System Operator Corporation VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20246 Re: California

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Effective Date: May 12, 2014 Revision History Date May 1, 2013 May 12, 2014 Description Initial document Revision

More information

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Steve Rutty Director, Grid Assets Lou Fonte Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Lead Engineer, Grid Assets September 3, 2014 Transmission Planning

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Review of Generator Interconnection Agreements and Procedures American Wind Energy Association Docket No. RM16-12-000 Docket No. RM15-21-000

More information

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT THIS AGREEMENT is made and entered into this day of, 20 by and between [Customer Name (Project Name, QXXXX)], a [Type of company] organized

More information

Unofficial Comment Form

Unofficial Comment Form Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop a Successor to Existing Net Energy Metering Tariffs Pursuant to Public Utilities Code Section 2827.1,

More information

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, 2018 1:00 p.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 1:00-1:10 Stakeholder Process and Schedule Kristina Osborne

More information

Open Access Transmission Tariff of Southern Companies

Open Access Transmission Tariff of Southern Companies Open Access Transmission Tariff of Southern Companies Procedures for Reserving Transmission Capacity for Future Load Growth, Designating/Undesignating Network Resources, and Arranging for Other Related

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for the California Solar Initiative, the Self-Generation Incentive

More information

OPUC Transmission Workshop 2 FERC Pro Forma Transmission

OPUC Transmission Workshop 2 FERC Pro Forma Transmission OPUC Transmission Workshop 2 FERC Pro Forma Transmission Eric Christensen, Cairncross & Hempelmann Karen Kruse, PacifiCorp February 28, 2019 Background of FERC Pro Forma Documents (Refresher from morning

More information

RESOLUTION NO. 14-R-

RESOLUTION NO. 14-R- RESOLUTION NO. 14-R- A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF MARION COUNTY, FLORIDA DIRECTING AND AUTHORIZING THE ACQUISITION OF SUBSTANTIALLY ALL OF THE REAL AND PERSONAL PROPERTY COMPRISING

More information

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 July 30, 2010 Re: Q2 Quarterly

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

WEBSITE DESIGN, DEVELOPMENT AND HOSTING SERVICES

WEBSITE DESIGN, DEVELOPMENT AND HOSTING SERVICES REQUEST FOR PROPOSAL WEBSITE DESIGN, DEVELOPMENT AND HOSTING SERVICES FOR FIRST NATIONS HEALTH MANAGERS ASSOCIATION (FNHMA) TABLE OF CONTENTS PART A INTRODUCTION Pages 3 5 1.0 Introduction 2.0 Scope of

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

Policy for Accrediting Assessment Bodies Operating within the Cradle to Cradle Certified Product Certification Scheme. Version 1.2

Policy for Accrediting Assessment Bodies Operating within the Cradle to Cradle Certified Product Certification Scheme. Version 1.2 Policy for Accrediting Assessment Bodies Operating within the Cradle to Cradle Certified Product Certification Scheme Version 1.2 July 2015 Copyright, Cradle to Cradle Products Innovation Institute, 2015

More information

151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued April 23, 2015)

151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued April 23, 2015) 151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

Competitive Solicitation Process Enhancements. Status Update / Issue Paper

Competitive Solicitation Process Enhancements. Status Update / Issue Paper Competitive Solicitation Process Enhancements Status Update / Issue Paper October 7, 2014 Table of Contents 1 Introduction... 3 2 Stakeholder process... 4 3 Background on the competitive solicitation process...

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Small Hydro Regulatory and Permitting Requirements California

Small Hydro Regulatory and Permitting Requirements California Small Hydro Regulatory and Permitting Requirements California Lon W. House, Ph.D. 530.409.9702 Water & Energy Small Hydro Regulatory and Compliance FERC QF, Small Hydro License or Exemption EIA Generator

More information

CELL PHONE POLICY Page 1 of 5 City of Manteca Administrative Policy and Procedure

CELL PHONE POLICY Page 1 of 5 City of Manteca Administrative Policy and Procedure CELL PHONE POLICY Page 1 of 5 Section 1: Purpose The City of Manteca recognizes that cellular telephones enhance the level of City services by allowing employees to remain in contact with the office or

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Colstrip Transmission System. Transmission Service and Interconnection Processes and Procedures

Colstrip Transmission System. Transmission Service and Interconnection Processes and Procedures APPENDIX A COLSTRIP TRANSMISSION SYSTEM TRANSMISSION SERVICE AND INTERCONNECTION PROCESSES AND PROCEDURES Colstrip Transmission System Transmission Service and Interconnection Processes and Procedures

More information

SALT RIVER PROJECT STANDARDS OF CONDUCT AND WRITTEN PROCEDURES FOR COMPLIANCE WITH FERC ORDER 717 February 11, 2009

SALT RIVER PROJECT STANDARDS OF CONDUCT AND WRITTEN PROCEDURES FOR COMPLIANCE WITH FERC ORDER 717 February 11, 2009 SALT RIVER PROJECT STANDARDS OF CONDUCT AND WRITTEN PROCEDURES FOR COMPLIANCE WITH FERC ORDER 717 February 11, 2009 The Salt River Project Agricultural Improvement and Power District ( SRP ), in compliance

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER07-1034-002 REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 17. Transmission Ownership Rights (TORs)... 2 17.1 TRTC Instructions... 2 17.1.1 Responsibility to Create TRTC Instructions... 2 17.1.2 TOR Scheduling Coordinator Responsibilities...

More information

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17 Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 978 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE MP 1.1 Objective

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

The Internet Society. on behalf of. The IETF Administrative Oversight Committee. Request for Proposal. RFC Editor RFC Format CSS Design

The Internet Society. on behalf of. The IETF Administrative Oversight Committee. Request for Proposal. RFC Editor RFC Format CSS Design The Internet Society on behalf of The IETF Administrative Oversight Committee Request for Proposal RFC Editor RFC Format CSS Design Date of Issuance: July 22, 2016 Proposal Submission Deadline: September

More information

April 11, 2016 VIA ELECTRONIC FILING

April 11, 2016 VIA ELECTRONIC FILING April 11, 2016 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.

More information

BPA and NERC, WECC, ERO

BPA and NERC, WECC, ERO BPA and NERC, WECC, ERO March 2006 1 Reliability Organizations BPA has relationship with two reliability organizations: 1. North American Electric Reliability Council (NERC) 2. Western Electric Coordinating

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Proposed Improvements for NERC MOD Standards July 10, 2012

Proposed Improvements for NERC MOD Standards July 10, 2012 Agenda Item 3.6 Planning Committee Meeting September 18-19, 2012 Proposed Improvements for NERC MOD Standards July 10, 2012 Background This paper outlines proposed improvements for NERC Reliability Standards

More information

Balance of Power in the Hudson Valley

Balance of Power in the Hudson Valley 1 Balance of Power in the Hudson Valley Chris Hogan, NYSDEC Major Project Management Unit May 3, 2017 2 Objective Provide an overview of the various state and federal processes by which energy projects

More information

Agreements & Contracts: Electronic Documents User Agreement CUSTOMER SERVICE SKOWHEGAN SAVINGS

Agreements & Contracts: Electronic Documents User Agreement CUSTOMER SERVICE SKOWHEGAN SAVINGS Agreements & Contracts: Electronic Documents User Agreement CUSTOMER SERVICE SKOWHEGAN SAVINGS 800.303.9511 CUSTSERV@SKOWSAVINGS.COM TABLE OF CONTENTS ELECTRONIC DELIVERY OF DOCUMENTS...3 SYSTEM REQUIREMENTS...3

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO

RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO June 27, 2016 Training provided for Ontario market participants by the Market Assessment and Compliance Division of the IESO Module 1 A MACD training presentation

More information

TERMS OF REFERENCE. Scaling-up Renewable Energy Program (SREP) Joint Mission. Lesotho

TERMS OF REFERENCE. Scaling-up Renewable Energy Program (SREP) Joint Mission. Lesotho TERMS OF REFERENCE Scaling-up Renewable Energy Program (SREP) Joint Mission September 27-29, 2017 Lesotho 1 SUMMARY 1. Mission objectives. The main objective of the Joint Mission ( the Mission ) is to

More information

November 9, Revisions to the Violation Risk Factors for Reliability Standards IRO and TOP

November 9, Revisions to the Violation Risk Factors for Reliability Standards IRO and TOP !! November 9, 2016 VIA ELECTRONIC FILING Jim Crone Director, Energy Division Manitoba Innovation, Energy and Mines 1200-155 Carlton Street Winnipeg MB R3C 3H8 RE: Revisions to the Violation Risk Factors

More information

Transition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007

Transition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007 Data Center Operations Outsourcing Transition Plan Implementation: Final Page 1 of 15 DOCUMENT CONTROL SHEET Schedule/Exhibit Amendment Control Sheet Title of Amended Document: Section 4 Transition Plan

More information

TIER Program Funding Memorandum of Understanding For UCLA School of

TIER Program Funding Memorandum of Understanding For UCLA School of TIER Program Funding Memorandum of Understanding For UCLA School of This Memorandum of Understanding is made between the Office of Information Technology (OIT) and the School of ( Department ) with reference

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

Wireless Communication Stipend Effective Date: 9/1/2008

Wireless Communication Stipend Effective Date: 9/1/2008 Category: Financial Policy applicable for: Faculty/Staff Policy Title: Policy Number: Wireless Communication Stipend Effective Date: 9/1/2008 Enabling Act(s) IRS rule 2.1.7 Policy Owner: Sr. VP for Administration

More information

Reliability Coordinator Procedure PURPOSE... 1

Reliability Coordinator Procedure PURPOSE... 1 No. RC0550 Restriction: Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 1.1.1. CAISO RC... 2 1.1.2. RC Working Groups... 2 1.1.3. Operationally Affected Parties... 2 1.1.4. RC Oversight Committee...

More information

Re: Filing of Windstream's Comments to Notice of Proposed Rulemaking; Case No. NNTRC

Re: Filing of Windstream's Comments to Notice of Proposed Rulemaking; Case No. NNTRC New Mexico Office of External Affairs 1660 Old Pecos Trail- Suite D Santa Fe; NM 87505 1:505.9559700 f:505.955.9699 windstream September 19, 2011 Executive Director Navajo Nation Telecommunications Regulatory

More information

UNCONTROLLED IF PRINTED

UNCONTROLLED IF PRINTED 161Thorn Hill Road Warrendale, PA 15086-7527 1. Scope 2. Definitions PROGRAM DOCUMENT PD 1000 Issue Date: 19-Apr-2015 Revision Date: 26-May-2015 INDUSTRY MANAGED ACCREDITATION PROGRAM DOCUMENT Table of

More information

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 17-035-36 Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Kelcey A. Brown August 2017 1 2 3 4

More information

Posted October 17, 2006 QWEST CORPORATION COMPARABLY EFFICIENT INTERCONNECTION PLAN FOR ENHANCED DIRECTORY ASSISTANCE

Posted October 17, 2006 QWEST CORPORATION COMPARABLY EFFICIENT INTERCONNECTION PLAN FOR ENHANCED DIRECTORY ASSISTANCE Posted October 17, 2006 QWEST CORPORATION COMPARABLY EFFICIENT INTERCONNECTION PLAN FOR ENHANCED DIRECTORY ASSISTANCE I. INTRODUCTION Qwest Corporation ( Qwest ) hereby posts its Comparably Efficient Interconnection

More information

Table of Contents. Purpose. Meter Data Acquisition and Processing Procedure. Procedure No Version No. 1.3 Effective Date 2/14/2018

Table of Contents. Purpose. Meter Data Acquisition and Processing Procedure. Procedure No Version No. 1.3 Effective Date 2/14/2018 Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 3 2.1 Background... 3 2.2 Scope / Applicability... 3 3. Detail... 3 3.1 ISOMEs Interrogation... 3 3.2 ISOMEs Validation...

More information

March 18, Potomac-Appalachian Transmission Highline, LLC PJM Interconnection, L.L.C. Docket Nos. ER ER Refund Report

March 18, Potomac-Appalachian Transmission Highline, LLC PJM Interconnection, L.L.C. Docket Nos. ER ER Refund Report The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-239-3300 Fax: 202-239-3333 Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Potomac-Appalachian

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

ATTACHMENTS ATTACHMENT X GENERATOR INTERCONNECTION PROCEDURES (GIP)

ATTACHMENTS ATTACHMENT X GENERATOR INTERCONNECTION PROCEDURES (GIP) GENERATOR INTERCONNECTION PROCEDURES (GIP) SECTION 1. DEFINITIONS. 10 kw Inverter Process shall mean the procedure for evaluating an Interconnection Request for a certified inverter-based Small Generating

More information

Unofficial Comment Form Project Modifications to CIP Standards Requirements for Transient Cyber Assets CIP-003-7(i)

Unofficial Comment Form Project Modifications to CIP Standards Requirements for Transient Cyber Assets CIP-003-7(i) Unofficial Comment Form Project 2016-02 Modifications to CIP Standards Requirements for Transient Cyber Assets CIP-003-7(i) Do not use this form for submitting comments. Use the electronic form to submit

More information

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group SUNZIA SOUTHWEST TRANSMISSION PROJECT David Getts General Manager SouthWestern Power Group PROJECT UPDATE NEW MEXICO RETA 8.22.12 SouthWestern Power Group Independent developer of utility-scale generation

More information

Terms and Conditions - Dedicated Internet Access Service

Terms and Conditions - Dedicated Internet Access Service Terms and Conditions - Dedicated Internet Access Service 1. Description of Service: Dedicated Internet Access ( DIA ) Service ( Service ), which includes T1, DS-3, Ethernet, Fast Ethernet, Gigabit Ethernet

More information

Candidate Manual Certified Commissioning Firm (CCF) Program

Candidate Manual Certified Commissioning Firm (CCF) Program Candidate Manual Certified Commissioning Firm (CCF) Program Building Commissioning Certification Board 1600 NW Compton Drive, Suite 200 Beaverton, OR 97006 Phone: 1-877-666-BCXA (2292) E-mail: certification@bcxa.org

More information

CERTIFICATE SCHEME THE MATERIAL HEALTH CERTIFICATE PROGRAM. Version 1.1. April 2015

CERTIFICATE SCHEME THE MATERIAL HEALTH CERTIFICATE PROGRAM. Version 1.1. April 2015 CERTIFICATE SCHEME For THE MATERIAL HEALTH CERTIFICATE PROGRAM Version 1.1 April 2015 Copyright Cradle to Cradle Products Innovation Institute, 2015 1 Purpose The intention of the Certificate Scheme is

More information

Table of Contents. Purpose. Certification of Metering Facilities. Procedure No Version No. 1.4 Effective Date 2/14/2018. Operating Procedure

Table of Contents. Purpose. Certification of Metering Facilities. Procedure No Version No. 1.4 Effective Date 2/14/2018. Operating Procedure No. 5710 Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 3 2.1 Background... 3 2.2 Scope / Applicability... 3 3. Detail... 3 3.1 Certifying Metering Facilities... 3 3.1.1

More information

GENERAL OPERATIONS MANUAL FOR ASTM PERSONNEL CERTIFICATE PROGRAMS

GENERAL OPERATIONS MANUAL FOR ASTM PERSONNEL CERTIFICATE PROGRAMS GENERAL OPERATIONS MANUAL FOR ASTM PERSONNEL CERTIFICATE PROGRAMS INTERNATIONAL Standards Worldwide Issued September 19 th, 2012 Updates Approved by CCP on March 23 rd, 2012 Version 5.0 BY AMERICAN SOCIETY

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information