Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Size: px
Start display at page:

Download "Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study"

Transcription

1 Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico

2 Foreword This technical report is prepared for Clean Line Energy Partners, LLC (Transmission Developer) by Public Service Company of New Mexico Transmission Planning and Contracts Department in response to a nontariff interconnection facilities study agreement for wires to wires interconnection of a proposed new 345 kv transmission line interconnecting to PNM s Rio Puerco 345 kv Station executed in March 13 th, This document was prepared by PNM. PNM does not: (a) make any warranty or representation whatsoever, express or implied, (i) with respect to the use of any information, apparatus, method, process, or similar item disclosed in this document, including merchantability and fitness for a particular purpose, or (ii) that such use does not infringe on or interfere with privately owned rights, including any party's intellectual property, or (iii) that this document is suitable to any particular user's circumstance; or (b) assumes responsibility for any damages or other liability whatsoever (including any consequential damages, even if PNM or any PNM representative has been advised of the possibility of such damages) resulting from your selection or use of this document or any information, apparatus, method, process, or similar item disclosed in this document. Any correspondence concerning this document, including technical and commercial questions should be referred to: Director, Transmission/Distribution Planning and Contracts Public Service Company of New Mexico 2401 Aztec Road NE, MS-Z220 Albuquerque, NM 87107

3 Table of Contents 1. Executive Summary Required Network Upgrades Expansion of Rio Puerco 345 kv Station Summary of Cost Estimate and Work Schedule... 7 Appendix A: Detailed Schedule and Cost Estimate... 9 List of Figures Figure 1: Western Spirit Clean Line Project Location... 5 Figure 2: Expansion of Rio Puerco Station, the proposed new 345 kv line and associated facilities... 6 List of Tables Table 1 Rio Puerco Station Expansion for Wires-to-Wires Interconnection of Western Spirit Clean Line Cost and Construction Schedule Estimate... 7 Table 2 - Rio Puerco Station Expansion Schedule Estimate... 9 Table 3 - Detailed Network Upgrade Cost Estimate for Rio Puerco Station Expansion... 9 Table 4 - Detailed Transmission Providers Interconnection Facilities Cost Estimate for Rio Puerco Station Expansion... 10

4 1. Executive Summary Public Service Company of New Mexico ( PNM ) performed this Interconnection Facilities Study ( Study Report ) based on the results from a completed System Impact Study ( SIS ) for the Western Spirit Clean Line project dated February The purpose of this Study Report is to provide cost and construction schedule estimates for facilities or system reinforcements needed to interconnect the proposed approximately 140 mile single circuit 345 kv transmission line into PNM s Rio Puerco 345 kv Station ( Rio Puerco ) to transmit 1000 MW of wind from Torrance, Guadalupe and Lincoln counties. The Study Report was developed in accordance with the non-tariff Interconnection Facilities Study Agreement executed in March 13 th, In order to provide wires-to-wires interconnection of the new 345 kv line into Rio Puerco, expansion of Rio Puerco by two breakers, also referred to as the Project in this Study Report, will be required. The total estimated cost of the Project in 2017 dollars required for interconnection of the new line into Rio Puerco is $10,810,423. The Project is estimated to be complete within 16 months after authorization to begin work. Figure 1 shows the proposed new 345 kv line and its general location on the transmission system. 1 Page 4

5 Figure 1: Western Spirit Clean Line Project Location This Study Report details required system improvements needed to accommodate the proposed 140 mile single circuit 345 kv line as well as the associated cost and construction schedule estimates. Section 2 of this Study Report explains the need and scope of system improvements. Cost and construction time estimates are summarized in Section 3 of this Study Report. Appendix A provides detailed schedules and cost estimates. 2. Required Network Upgrades The following system reinforcements have been identified in the SIS as a requirement to interconnect the new 345 kv line: Expansion of Rio Puerco by two breakers Figure 2 shows the Project, the proposed new 345 kv line connecting to Rio Puerco and the nearby transmission system. Page 5

6 WTG Equivalent Generator Step Up 690 V Transformer 34.5 kv R, X, B Equivalent Feeder Model Aggregated WTG model (Assume Type 4) WTG 690 V 34.5 kv R, X, B Equivalent Feeder Model Substation Transformer 345 kv Aggregated WTG model (Assume Type 3) 34.5 kv MSC or SVC/STATCOM (if any needed) To Four Corners Rio Puerco 345 kv Substation To San Juan SVC To West Mesa To West Mesa To BA To BA Existing Facilities New Facilities New Customer Facilites Figure 2: Expansion of Rio Puerco Station, the proposed new 345 kv line and associated facilities 2.1 Expansion of Rio Puerco 345 kv Station The SIS identified the need for expansion of Rio Puerco by adding two additional breakers to interconnect the proposed 140 mile single circuit 345 kv transmission line. Per PNM s Breaker Configuration Policy, a breaker and a half configuration at Rio Puerco will be required to reliably interconnect the new line at Rio Puerco. Figure 2 shows the proposed layout of the station. Rio Puerco expansion will also require metering, protection and control upgrades at Rio Puerco. Page 6

7 3. Summary of Cost Estimate and Work Schedule The total cost and construction schedule estimates are shown below in Table 1. Construction schedule estimates are from the date the Interconnection Customer provides written authorization to proceed, provided all agreements and funding arrangements are in place. It is likely that PNM will incur outage costs during the construction of the identified system reinforcement. The cost of construction outages cannot be estimated at this time. However, in accordance with applicable Federal Energy Regulatory Commission Policy, PNM reserves the right to recover such costs from the Interconnection Customer. Table 1 Rio Puerco Station Expansion for Wires-to-Wires Interconnection of Western Spirit Clean Line Cost and Construction Schedule Estimate Summary of Cost and Construction Schedule Estimate EXPANSION OF RIO PUERCO STATION COST ($M) CONSTRUCTION TIME Network Upgrade months Transmission Provider s Interconnection Facilities (TPIF) months Total months The following general assumptions have been applied in preparing cost and construction schedules estimate: 1. Project is estimated to be complete within minimum of 16 months after authorization to begin work. 2. Unforeseen delays due to permitting, weather, equipment delays or lack of construction resources are not included in the above schedule. 3. Lead times for major equipment are based on current production schedules. 4. Schedule assumes system outages will be available for station cutover when needed. 5. Allowance for Funds Used During Construction (AFUDC) is not collected if the customer makes monthly payment during construction. Major activities are presented in the construction schedule estimate in Appendix A - Table 2 below. The schedule is representative of typical Project timelines and activities. Additional cost estimate details are Page 7

8 presented in Appendix A - Table 3 and in Appendix A - Table 4 for Rio Puerco expansion and associated Transmission Provider s Interconnection Facilities upgrade. Page 8

9 Appendix A: Detailed Schedule and Cost Estimate Table 2 - Rio Puerco Station Expansion Schedule Estimate Table 3 - Detailed Network Upgrade Cost Estimate for Rio Puerco Station Expansion Page 9

10 Table 4 - Detailed Transmission Providers Interconnection Facilities Cost Estimate for Rio Puerco Station Expansion Page 10

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study Facilities Study for the Mora Line Transmission Project Non-Tariff Facilities Study November 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities Non-Tariff System Impact Study March 204 Prepared by: Utility System Efficiencies, Inc (USE) Under Contract with:

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

Status of PNM s Interconnection Requests and Studies 3/31/2017

Status of PNM s Interconnection Requests and Studies 3/31/2017 OASIS ID POI Location ISD MW Output Sum/Win Type of Gen. Appl Rcvd Appl Perfected PISIS DISIS Facilities Study Addtl Study Status DEFINITIVE INTERCONNECTION SYSTEM IMPACT STUDY CLUSTER #4 WINDOW OPENED

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Status of PNM s Interconnection Requests and Studies 9/29/2017

Status of PNM s Interconnection Requests and Studies 9/29/2017 OASIS ID POI Location ISD MW Output Sum/Win Type of Gen. Appl Rcvd Appl Perfected PISIS DISIS Facilities Study Addtl Study Status DEFINITIVE INTERCONNECTION SYSTEM IMPACT STUDY CLUSTER #6 WINDOW OPENED

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

ELECTIVE INTERCONNECTION FACILITIES

ELECTIVE INTERCONNECTION FACILITIES Title: ELECTIVE INTERCONNECTION FACILITIES Business Practice Department: External Affairs Document No: BP-0506 v3.0 Issue Date: 12-15-2017 Previous Date: 12/11/2006 Contents 1 PURPOSE... 2 2 DEFINITIONS...

More information

Status of PNM s Interconnection Requests and Studies 12/29/2017

Status of PNM s Interconnection Requests and Studies 12/29/2017 OASIS ID POI Location ISD MW Output Sum/Win Type of Gen. Appl Rcvd Appl Perfected PISIS DISIS Facilities Study Addtl Study Status DEFINITIVE INTERCONNECTION SYSTEM IMPACT STUDY CLUSTER #6 WINDOW OPENED

More information

10. Unbundled Dark Fiber 10.1 General

10. Unbundled Dark Fiber 10.1 General Verizon New England Inc. Page 1 Second Revision Canceling First Revision 10.1 General 10.1.1 Description A. For purposes of this Part B, Section 10, the terms business line, fiber-based collocator, and

More information

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY Inverter Based Generators 25 kw and This document contains the interconnection requirements for inverter based generators, 25 kw and smaller, that operate

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

A Regulatory Perspective on Distributed Generation

A Regulatory Perspective on Distributed Generation A Regulatory Perspective on Distributed Generation Southwest Electrical Metering Association Spring Meeting Galveston June 10, 2015 Darryl Nelson Rates and Regulatory Agenda Why Rules are Needed Texas

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

SmartSacramento Distribution Automation

SmartSacramento Distribution Automation SmartSacramento Distribution Automation Presented by Michael Greenhalgh, Project Manager Lora Anguay, Sr. Project Manager Agenda 1. About SMUD 2. Distribution Automation Project Overview 3. Data Requirements

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

Filing Date: Effective Date: Issued pursuant to Telecom Regulatory Policy CRTC ,

Filing Date: Effective Date: Issued pursuant to Telecom Regulatory Policy CRTC , CARRIER ACCESS TARIFF CRTC 21462 TELUS Communications Company 2nd Revised Page 226-1 Cancels 1st Revised Page 226-1 226 Wholesale Internet ADSL Service 226.1 Service Description Wholesale Internet ADSL

More information

provides for a single domain name. Additional domain names are available upon request in accordance with the rates, terms and conditions below.

provides for a single domain name. Additional domain names are available upon request in accordance with the rates, terms and conditions below. TELUS Communications Company 4th Revised Page 226-1 Cancels 3rd Revised Page 226-1 226 Wholesale Internet ADSL Service 226.1 Service Description Wholesale Internet ADSL Service is a broadband access service

More information

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Effective Date: May 12, 2014 Revision History Date May 1, 2013 May 12, 2014 Description Initial document Revision

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Dominion Supplemental Projects

Dominion Supplemental Projects Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer

More information

CC COMMUNICATIONS TELEPHONE TARIFF NO. 21 Reissued PAGE NO. 1 CANCELS PAGE NO. 1 INTEGRATED SERVICES DIGITAL NETWORK TABLE OF CONTENTS: REVISION PAGE

CC COMMUNICATIONS TELEPHONE TARIFF NO. 21 Reissued PAGE NO. 1 CANCELS PAGE NO. 1 INTEGRATED SERVICES DIGITAL NETWORK TABLE OF CONTENTS: REVISION PAGE Reissued PAGE NO. 1 CANCELS PAGE NO. 1 TABLE OF CONTENTS: REVISION PAGE Table of Contents Reissued 1 Description of ISDN Service Reissued 2 Regulations and Conditions Reissued 2 Regulations and Conditions

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Terms and Conditions - Dedicated Internet Access Service

Terms and Conditions - Dedicated Internet Access Service Terms and Conditions - Dedicated Internet Access Service 1. Description of Service: Dedicated Internet Access ( DIA ) Service ( Service ), which includes T1, DS-3, Ethernet, Fast Ethernet, Gigabit Ethernet

More information

July 26, Dear Mr. Millar:

July 26, Dear Mr. Millar: July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 Dear Mr. Millar: As you are aware, Clean

More information

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 17-035-36 Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Kelcey A. Brown August 2017 1 2 3 4

More information

Warrenton Wheeler Gainesville 230kV Reliability Project

Warrenton Wheeler Gainesville 230kV Reliability Project Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

Dear Ms. Salak: If you require additional information, please call Carlton Ball at (813)

Dear Ms. Salak: If you require additional information, please call Carlton Ball at (813) . David Christian Assistant Vice President Regulatory Affairs Florida 106 E. College Ave Tallahassee, Florida 32301 Telephone 850-224-3963 Fax 850-222-2912 david.christian@verizon.com December 5, 2005

More information

4. Digital PBX Services 4.1 FLEXPATH

4. Digital PBX Services 4.1 FLEXPATH Page 1 4.1 FLEXPATH Effective November 3, 2012, Flexpath is available only to existing customers with this service. Additions, rearrangements, changes and moves of service are not permitted. Rates and

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Wholesale Very high bit-rate Digital Subscriber Line (VDSL) Service

Wholesale Very high bit-rate Digital Subscriber Line (VDSL) Service COMPETITOR ACCESS TARIFF 1st Revised Page 321 Cancels Original Page 321 ITEM 650.34 Wholesale Very high bit-rate Digital Subscriber Line (VDSL) Service 1. Service Description Wholesale VDSL Service (or

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

April 11, 2016 VIA ELECTRONIC FILING

April 11, 2016 VIA ELECTRONIC FILING April 11, 2016 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.

More information

Updated December 12, Chapter 10 Service Description IBM Cloud for Government

Updated December 12, Chapter 10 Service Description IBM Cloud for Government Updated December 12, 2018 Chapter 10 Service Description IBM Cloud for Government IBM Cloud for Government This Service Description describes IBM s Cloud for Government available to Clients under the Federal

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:

ADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot: PROCUREMENT DEPARTMENT 4 WORLD TRADE CENTER 150 GREENWICH STREET, 21ST FL. NEW YORK, NY 10007 12/7/2018 ADDENDUM # 3 To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar

More information

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Steve Rutty Director, Grid Assets Lou Fonte Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Lead Engineer, Grid Assets September 3, 2014 Transmission Planning

More information

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662 Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

Electronic Disclosure and Electronic Statement Agreement and Consent

Electronic Disclosure and Electronic Statement Agreement and Consent Electronic Disclosure and Electronic Statement Agreement and Consent Please read this "Electronic Disclosure and Electronic Statement Agreement and Consent" carefully and keep a copy for your records.

More information

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.:

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.: City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM Closing Date: July 17, 2018 at 2:00 p.m. RFI No.: 19-127502 Description: The City of Farmington Electric

More information

Southern Company Smart Grid

Southern Company Smart Grid Southern Company Smart Grid Smart Grid Investment Grant Update July 25, 2011 Southern Company Southern Company is one of the nations largest generators of electricity Has 4.4 million retail customers across

More information

Washington DC October Consumer Engagement. October 4, Gail Allen, Sr. Manager, Customer Solutions

Washington DC October Consumer Engagement. October 4, Gail Allen, Sr. Manager, Customer Solutions Consumer Engagement Through Social Media October 4, 2012 Gail Allen, Sr. Manager, Customer Solutions KCP&L Company Overview Key Statistics Customers Generation 9 plant sites 26 generating units 830,000

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

Facilities Study for XXXXXXXXXXXX 50 MW PV

Facilities Study for XXXXXXXXXXXX 50 MW PV Final Report on the Facilities Study for XXXXXXXXXXXX 50 MW PV Project No. 67270 July 2012 Facilities Study for XXXXXXXXXXXX 50 MW PV Prepared for Copany El Paso, Texas July 2012 Project No. 67270 Prepared

More information

EXHIBIT A: PROJECT SCOPE AND SCHEDULE The Project consists of the activities and delivery dates identified in this Exhibit A, implemented in accordance with the Agreement. The Parties have included a schedule

More information

CENTURYLINK OPERATING COMPANIES TARIFF F.C.C. NO. 11 2ND REVISED INDEX PAGE 8-0 CANCELS 1ST REVISED INDEX PAGE 8-0 ACCESS SERVICE

CENTURYLINK OPERATING COMPANIES TARIFF F.C.C. NO. 11 2ND REVISED INDEX PAGE 8-0 CANCELS 1ST REVISED INDEX PAGE 8-0 ACCESS SERVICE 2ND REVISED INDEX PAGE 8-0 CANCELS 1ST REVISED INDEX PAGE 8-0 ALPHABETICAL BY SUBJECT PAGE Changes of Service... 8-3 General... 8-1 Moves... 8-2 Order Modifications... 8-1 Special Construction... 8-1 Termination

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

PART 2 - Provisions - Midwest, West, Southwest Original Page 1 SECTION 7 - Service Provisioning and Rate Conditions

PART 2 - Provisions - Midwest, West, Southwest Original Page 1 SECTION 7 - Service Provisioning and Rate Conditions PART 2 - Provisions - Midwest, West, Southwest Original Page 1 7. Special Access Service 7.1 Service Provisioning Special Access Service provides a transmission path to connect customer designated premises

More information

Product Guide Verizon North LLC. Section 22 Verizon North LLC Original Sheet 1 INTEGRATED SERVICES DIGITAL NETWORK - PRIMARY RATE INTERFACE (ISDN-PRI)

Product Guide Verizon North LLC. Section 22 Verizon North LLC Original Sheet 1 INTEGRATED SERVICES DIGITAL NETWORK - PRIMARY RATE INTERFACE (ISDN-PRI) Original Sheet 1 A. General a. Integrated Services Digital Network (ISDN) - Primary Rate Interface (PRI) is a central office based service arrangement that is an alternative for individual access services,

More information

TARIFF UPDATE. Northwestel Inc. Tariff Notice 998 Operation of the Yukon Mobile Radio System (OYMRS)

TARIFF UPDATE. Northwestel Inc. Tariff Notice 998 Operation of the Yukon Mobile Radio System (OYMRS) October 5, 2017 TARIFF UPDATE Northwestel Inc. Tariff Notice 998 Operation of the Yukon Mobile Radio System (OYMRS) NOTE: Effective date September 14, 2017 This tariff application was submitted to introduce

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016)

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE INVITING POST-TECHNICAL CONFERENCE COMMENTS. (June 3, 2016) UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Review of Generator Interconnection Agreements and Procedures American Wind Energy Association Docket No. RM16-12-000 Docket No. RM15-21-000

More information

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Order No. 1000 Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Thinh Nguyen Manager, Interconnection Projects New York Independent System Operator Joint

More information

Product Guide Verizon Delaware LLC. Section 10B Delaware LLC Original Sheet 1. IntelliLinQ PRI SERVICE

Product Guide Verizon Delaware LLC. Section 10B Delaware LLC Original Sheet 1. IntelliLinQ PRI SERVICE Delaware LLC Original Sheet 1 A. GENERAL Basic IntelliLinQ PRI Service is an optional form of local exchange access based on the Primary Rate Interface (PRI) arrangement of the Integrated Services Digital

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

Outage Management System Pilot Roll-out: Division User Manual

Outage Management System Pilot Roll-out: Division User Manual Outage Management System Pilot Roll-out: Division User Manual February 2017 Table of Contents 1. Outage Management System... 2 1.1. Overall Objective... 2 1.2. Outage Categories... 2 1.3. Division User

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

Dealing With a Disaster and Its Effect on the Utility Operation

Dealing With a Disaster and Its Effect on the Utility Operation Nashville Electric Service Dealing With a Disaster and Its Effect on the Utility Operation UTA Fall Conference Florence, Alabama October 12-14, 2011 Outline Who We Are Typical Emergency Response Challenges

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

General Subscriber Service Tariff: A Original Page Original Page

General Subscriber Service Tariff: A Original Page Original Page BELLSOUTH BellSouth Telecommunications, Inc. Jerry D. Hendrix 150 South Monroe Street Vice President Suite 400 Regulatory Relations Tallahassee, Florida 32301 Jerry.hendrix@bellsouth.com Phone: (850) 577-5550

More information

DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE

DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE REGULATIONS, RATES, AND CHARGES Applying to the Provision of DSL For Customers of Wilson Telephone Company, Inc. This DSL Service Guide does not include Internet

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

R i o V i r g i n T e l e p h o n e C o m p a n y P a g e 1 WIRELINE BROADBAND INTERNET ACCESS SERVICE TERMS AND CONDITIONS OF SERVICE

R i o V i r g i n T e l e p h o n e C o m p a n y P a g e 1 WIRELINE BROADBAND INTERNET ACCESS SERVICE TERMS AND CONDITIONS OF SERVICE R i o V i r g i n T e l e p h o n e C o m p a n y P a g e 1 WIRELINE BROADBAND INTERNET ACCESS SERVICE TERMS AND CONDITIONS OF SERVICE 1. APPLICATION OF TERMS AND CONDITIONS OF SERVICE These Terms and

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011 Western DSW Planning Stakeholder Meeting (Western OATT Attachment P) June 9, 2011 Agenda: 1. Welcome and Introductions of Attendees 2. Planning Process 3. Interconnection Requests 4. Comments/questions

More information

Description of the Application Process for Small Embedded Generators

Description of the Application Process for Small Embedded Generators Description of the Application Process for Small Embedded Generators This document describes the Application Process for Small Embedded Generators (as required under section 5.3.3A of the National Electricity

More information

COCHRANE TELECOM SERVICES CRTC TELEPHONE SYSTEM Revision 1 GENERAL TARIFF Section 630 CARRIER ACCESS TARIFF

COCHRANE TELECOM SERVICES CRTC TELEPHONE SYSTEM Revision 1 GENERAL TARIFF Section 630 CARRIER ACCESS TARIFF Page1 1. GENERAL 1.01 This Section provides for the interconnection (on a trunk-side basis) between the Company s switched network and those of Telecommunications Providers that are interexchange carriers

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

National Pooling Administration Contract #FCC13C nd Revised Change Order Proposal #3B

National Pooling Administration Contract #FCC13C nd Revised Change Order Proposal #3B National Pooling Administration Contract #FCC13C0007 2 nd Revised Change Order Proposal #3B (Development and Support of the PAS NPAC API) March 8, 2017 Neustar, Inc. 21575 Ridgetop Circle Sterling VA,

More information

Year Assessment Preliminary Needs

Year Assessment Preliminary Needs 2018 10-Year Assessment Preliminary Needs Stakeholder and Customer Presentation March 1, 2018 Jeremy Voigt Purpose Key Study Assumptions Reminder Summarize Preliminary Changes to Needs Solicit Input on

More information

An End2End (E2E) Operationalized Pipeline for Predictive Analysis for the Intelligent Grid

An End2End (E2E) Operationalized Pipeline for Predictive Analysis for the Intelligent Grid An End2End (E2E) Operationalized Pipeline for Predictive Analysis for the Intelligent Grid Presented by Peng Li & Yun Zhao China Southern Power Grid EPRI Vijay K Narayanan Microsoft Agenda China Southern

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group SUNZIA SOUTHWEST TRANSMISSION PROJECT David Getts General Manager SouthWestern Power Group PROJECT UPDATE NEW MEXICO RETA 8.22.12 SouthWestern Power Group Independent developer of utility-scale generation

More information