Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

Size: px
Start display at page:

Download "Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process"

Transcription

1 Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Thinh Nguyen Manager, Interconnection Projects New York Independent System Operator Joint ESPWG/TPAS February 5, New York Independent System Operator, Inc. All Rights Reserved. DRAFT FOR DISCUSSION PURPOSES ONLY

2 Topics FERC Compliance Directive Current Interconnection & Transmission Expansion Rules Overview of Proposed Revisions to Existing Processes Types of Projects Subject to the Proposed Transmission Interconnection Process ( TIP ) Projects Remaining in the Transmission Expansion Process Controllable Transmission Seeking UDRs Threshold for Triggering the TIP TIP Overview TIP Detailed Process Description 2

3 FERC Compliance Directive FERC s 12/23/2015 Order on the NYISO s Fourth Order 1000 Compliance Filing directed NYISO to modify its existing interconnection processes Incumbent transmission projects and nonincumbent transmission projects that will seek recovery through NYISO Planning Processes must be subject to the same interconnection requirements The Commission s Order left open the option to propose a process other than the process in Attachments X and S for conducting the interconnection studies necessary for these types of projects 3

4 Current Interconnection & Transmission Expansion Rules All generation (proposed by both incumbent TOs and non-incumbents) with FERC jurisdictional interconnection points are subject to the NYISO s Interconnection Procedures Large Facility Interconnection Procedures in Attachment X (generators > 20 MW) Small Generator Interconnection Procedures in Attachment Z (generators 20 MW) Class Year Study procedures in Attachment S (applicable to all Large Facilities and certain Small Generating Facilities) 4

5 Current Interconnection & Transmission Expansion Rules All transmission projects proposed by entities that are not Transmission Owner signatories to the ISO-Related Agreements are subject to the Large Facility Interconnection Procedures in Attachment X and Attachment S Even if Developer intends to seek cost recovery through a NYISO Attachment Y Planning Process (the Reliability, Economic and Public Policy processes) Even if the project is AC transmission All proposed upgrades or additions to transmission facilities owned by the New York Transmission Owners are subject to the transmission expansion process in OATT 3.7 or OATT 4.5 Includes upgrades/reinforcements proposed by Eligible Customers to current TOs system Subject to a de minimis threshold, below which a project does not trigger the OATT study process 5

6 Considerations for Revisions to Existing Rules As the Commission indicated, the NYISO could propose to require all transmission to proceed through the Large Facility Interconnection Procedures in Attachments X and S of the OATT As the Commission recognized, there are potential drawbacks to that approach, suggesting the NYISO s ability to propose a new process for transmission projects NYISO s proposal seeks to optimize efficiency of existing processes and allow it to evaluate projects based on the proposed technology/ electrical characteristics vs. the characteristics of the proposing entity 6

7 Overview of Proposed Revisions to Existing Rules Develop a new Transmission Interconnection Process ( TIP ) A hybrid of the current Transmission Expansion Process and the Interconnection Process Retain existing Small Generator Interconnection Procedures Retain existing Large Facility Interconnection Procedures in Attachments X and S for all Large Generating Facilities and controllable transmission seeking UDRs (if eligible to seek UDRs) Existing transmission expansion process from OATT 3.7 and 4.5 will apply only to requests not subject to the new TIP 7

8 Types of Projects Subject to the Proposed TIP Overview Proposed TIP would apply to a transmission project, regardless of the entity that proposes it and regardless of the project s intended cost recovery mechanism Two exceptions: Project with de minimis impact will not be required to go through the TIP Controllable transmission that seeks UDRs must go through Attachments X and S 8

9 Types of Projects Subject to the Proposed TIP Specifically, unless below the de minimis threshold, the following would be subject to the TIP: 1) Transmission projects proposed by incumbent NYTOs and non-incumbents in (or that anticipate entering) a NYISO Planning Process 2) Transmission projects proposed by NYTOs triggered by their local planning process 3) Transmission projects proposed by other Eligible Customers that request to pursue expansions of the transmission facilities owned by NYTOs 4) Transmission projects proposed by non-incumbents outside the NYISO Planning Process (i.e., merchant projects), including HVDC and hybrid AC/DC transmission (unless controllable transmission seeking UDRs) 5) Transmission projects from TOs in neighboring regions (e.g., RTEP projects) 9

10 Controllable Transmission Seeking UDRs Controllable transmission lines for which the proposing entity seeks UDRs must proceed through the Large Facility Interconnection Procedures Even if they are seeking cost recovery under the NYISO s Planning Process Both incumbent TOs and non-incumbents can seek UDRs (if eligible for UDRs) by proceeding through Attachment X and Attachment S 10

11 Threshold for Triggering the TIP Currently, an SIS in the Transmission Expansion Process under the OATT 3.7 or is 4.5 is required for transmission projects that have the following potential impacts: Reduction in the transfer capability of a NYISO interface by greater than 10 MW or Increase in the transfer capability of a NYISO interface by greater than 25 MW 11

12 Threshold for Triggering the TIP Proposed de minimis threshold for the new TIP: If the project is connecting to facilities it owns, it will trigger the TIP if: It reduces the transfer capability of a NYISO interface by greater than 10 MW or increases the transfer capability of a NYISO interface by greater than 25 MW; or the proposal has the potential to convert other facilities into NPCC or BPS facilities If the project connects to facilities other than its own facilities, it will trigger the Transmission Interconnection Process, regardless of the MW impact 12

13 TIP Overview Transmission Interconnection Application Scoping Meeting Optional Feasibility Study System Impact Study Facilities Study Cost Responsibility for Network Upgrades Interconnection Agreement 13

14 TIP Application Requirements Transmission Interconnection Application Non-refundable $10,000 application fee NYISO to identify deficiencies within five (5) business days Deficiencies to be addressed within ten (10) business days. Failure to address application deficiencies will result in withdrawal. TIP will include a formal withdrawal provision, providing the ability to cure deficiencies that trigger withdrawal See Transmission Interconnection Application form posted with meeting materials 14

15 TIP Scoping Meeting Scoping Meeting among proposing entity, NYISO and Connecting Transmission Owner(s) To occur no later than thirty (30) calendar days from receipt of a valid application unless otherwise mutually agreed to by the parties To discuss at the Scoping Meeting: Discuss whether Project elects to pursue a Feasibility Study or proceed to a System Impact Study and discuss the scope of such study. Discuss which of the following options Project elects to use to determine interconnection design: Proposing entity to provide proposed interconnection design Proposing entity to request a Feasibility Study to develop and evaluate the proposed interconnection design Parties to include development of the proposed interconnection design as an upfront step of the System Impact Study 15

16 TIP Feasibility Study Optional Feasibility Study available at the proposing entity s option Study deposit of $60,000 Two-party study agreement between NYISO and the proposing entity Study schedule will depend on options elected by proposing entity 16

17 TIP Feasibility Study Feasibility scope may include any of the following, at the option of the proposing entity: Development of conceptual breaker-level one-line diagram of existing system where project proposes to interconnect (i.e., how to integrate the project into the existing system) Review of feasibility/constructability of conceptual breakerlevel one-line diagram of the proposed interconnection (e.g., space for additional breaker bay in existing substation or identification of cable routing concerns inside existing substation) Preliminary review of local protection, communication, grounding issues associated with the proposed interconnection Power flow analyses Short circuit analyses Bus flow analyses Identification of Network Upgrades with non-binding good faith estimate of cost responsibility and non-binding good faith estimated time to construct 17

18 TIP System Impact Study Study deposit of $120,000 Two-party study agreement Schedule dependent on study scope System Impact Study scope and report subject to TPAS review and OC approval 18

19 TIP System Impact Study Scope of Study: Identification of the need for any additional facilities ( Network Upgrades ) to meet reliability criteria Development of non-binding cost estimates and time to construct required Network Upgrades Similar to a System Impact Study/System Reliability Impact Study performed today with thermal, voltage, stability and short circuit analyses, plus an evaluation of transfer limit degradation 19

20 TIP System Impact Study Applicable Standard Transmission security analyses consistent with Minimum Interconnection Standard (i.e., thermal, voltage, stability and short circuit analyses) Transfer limit impact analysis A project will trigger an upgrade if it degrades pre-project transfer limits of any NYISO transmission planning interface (documented in the NYISO s Area Transmission Review) more than 25 MW Project responsible for upgrades necessary to mitigate impacts to the controlling limit (e.g., voltage, stability, thermal) as well as any impact to the thermal limit Even if thermal transfer limit is not the controlling limit, project must mitigate impact to the thermal transfer limit Project that triggers an upgrade would have to fully restore the impacted transfer limits to the pre-project limits 20

21 TIP System Impact Study Base Case Starting case is the most recent Class Year ATBA case If the proposed transmission project is related to/in response to a system condition not reflected in the ATBA, NYISO may, as appropriate, evaluate the proposed transmission project while taking that system condition into consideration Projects responding to solicitation under NYISO Planning Processes may, as appropriate, require modification to the existing system representation in the ATBA based on, for example, a stated Public Policy For a transmission project proposed in response to reliability need triggered by deactivation of a generator, the NYISO may evaluate the proposed transmission project without that generator in-service Allows evaluation of transmission project under the conditions the project is intended to address 21

22 TIP Facilities Study $100,000 study deposit Two-party study agreement Scope of Study: Stand- alone engineering study (similar to a Part 1 Study) for most projects More detailed, focused study of upgrades identified in System Impact Study but not a re-evaluation of analyses performed in the System Impact Study Facilities Study scope and report subject to TPAS review and OC approval 22

23 Network Upgrades Project will be required to post security for Network Upgrades identified in the Facilities Study Transmission projects moving forward in the same time frame that both contribute to a Network Upgrade should share the cost of the Network Upgrade 23

24 Interconnection Agreement Unless proposed transmission project is connecting to facilities it already owns, TIP would require a multi-party interconnection agreement among: Proposing entity; NYISO; and Connecting Transmission Owner(s) 24

25 Modeling of TIP Projects in Interconnection Base Cases For proposed TIP project in an Attachment Y Planning Process to be treated as firm and modeled in the interconnection ATBA: Must have been triggered, selected, or approved Triggered (for reliability projects) Selected (for PPTPP projects;) Approved by beneficiaries (CARIS projects) Must have an Article VII application deemed complete (if applicable) and completed SIS (if applicable); and Must be making reasonable progress under the applicable Attachment Y process 25

26 Modeling of Other Transmission in Interconnection Base Cases For other transmission projects (unless subject to Attachments X and S) to be treated as firm and modeled in the interconnection ATBA: Must have commenced a Facilities Study (if applicable) Must have an Article VII application deemed complete (if applicable) 26

27 Transition Rule NYISO to propose a transition rule for projects in the queue before the effective date of the proposed TIP Transition rule will seek to transition project to the TIP without subjecting the project to unnecessary rework or delay 27

28 Projects Remaining in the Transmission Expansion Process Leave existing pro forma transmission expansion language in OATT 3.7 and 4.5 with slight revisions to clarify its purpose: Change name of study (not really an impact study) Clarify that it would only apply to requests from Eligible Customers for the NYISO to identify potential projects that could meet a stated objective E.g., request to study how to relieve the constraints currently curtailing a generator E.g., request to study how to create incremental transfer capability resulting in incremental TCCs If Eligible Customer decides to move forward with project, it would do so through the new Transmission Interconnection Process 28

29 Next Steps Comments requested by February 17 NYISO to consider comments and bring proposal back for discussion at March 7 Joint ESPWG/TPAS meeting Time permitting, NYISO to share draft tariff language at March 7 Joint ESPWG/TPAS meeting and/or March 18 Operating Committee Review of proposal at March 17 Operating Committee meeting Compliance filing deadline: March 22 29

30 30

The NYISO shall assign a Queue Position based upon the date and time of receipt of the

The NYISO shall assign a Queue Position based upon the date and time of receipt of the 30.4 Queue Position 30.4.1 General The NYISO shall assign a Queue Position based upon the date and time of receipt of the valid Interconnection Request; provided that, if the sole reason an Interconnection

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities

Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Effective Date: May 12, 2014 Revision History Date May 1, 2013 May 12, 2014 Description Initial document Revision

More information

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012 Generation Interconnection Process NEMSTF Education Session 1 January 19, 2012 www.pjm.com Follows FERC Pro Forma Process Queues are open for a 3 month period Spreads Workload Out Over Year Generation,

More information

ELECTIVE INTERCONNECTION FACILITIES

ELECTIVE INTERCONNECTION FACILITIES Title: ELECTIVE INTERCONNECTION FACILITIES Business Practice Department: External Affairs Document No: BP-0506 v3.0 Issue Date: 12-15-2017 Previous Date: 12/11/2006 Contents 1 PURPOSE... 2 2 DEFINITIONS...

More information

ATTACHMENT I: Generator Interconnection Procedures (GIP)

ATTACHMENT I: Generator Interconnection Procedures (GIP) ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Specific topics covered in this brief include:

Specific topics covered in this brief include: April 2008 Summary Welcome to the Fifteenth National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 28, 2008, Transmission Update conference

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

July 26, Dear Mr. Millar:

July 26, Dear Mr. Millar: July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 Dear Mr. Millar: As you are aware, Clean

More information

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements In accordance with the Federal Energy Regulatory Commission (FERC) order issued on January 24, 2003 (as modified

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

MISO PJM Joint and Common Market Cross Border Transmission Planning

MISO PJM Joint and Common Market Cross Border Transmission Planning MISO PJM Joint and Common Market Cross Border Transmission Planning February 28, 2017 1 Agenda 2 Targeted Market Efficiency Projects 2-Year Coordinated System Plan Study FERC Order No. 1000 Interregional

More information

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1 OATT Attachment Q-1 First Revision of Page 1 ATTACHMENT Q-1 Dynamic Scheduling This attachment contains the eligibility requirements and the terms and conditions for the provision of dynamic scheduling

More information

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT

APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT APPENDIX 4 to LGIP INTERCONNECTION FACILITIES STUDY AGREEMENT THIS AGREEMENT is made and entered into this day of, 20 by and between [Customer Name (Project Name, QXXXX)], a [Type of company] organized

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: January 30, 2019 Re: Decision on

More information

OPUC Transmission Workshop 2 FERC Pro Forma Transmission

OPUC Transmission Workshop 2 FERC Pro Forma Transmission OPUC Transmission Workshop 2 FERC Pro Forma Transmission Eric Christensen, Cairncross & Hempelmann Karen Kruse, PacifiCorp February 28, 2019 Background of FERC Pro Forma Documents (Refresher from morning

More information

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Designation and Termination of Network Resources

Designation and Termination of Network Resources Transmission & Reliability Services Business Practice: Designation and Termination of Network Resources Posted: February 8, 2010 Effective: May 3, 2010 Revision No.: 5 1. Purpose The purpose of this business

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Caithness Long Island II, LLC ) ) Complainant, ) ) v. ) Docket No. EL15-84-000 ) New York Independent System Operator, Inc. ) )

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator Assembly Standing Committee on Energy Kevin A. Cahill, Chairman Assembly Standing Committee on Corporations, Authorities and Commissions James F. Brennan, Chairman Assembly Standing Committee on Cities

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

Unofficial Comment Form

Unofficial Comment Form Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc.

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc. Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation Purpose: To establish an equitable process for allocating fault current margin, where available, to applicants

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

Colstrip Transmission System. Transmission Service and Interconnection Processes and Procedures

Colstrip Transmission System. Transmission Service and Interconnection Processes and Procedures APPENDIX A COLSTRIP TRANSMISSION SYSTEM TRANSMISSION SERVICE AND INTERCONNECTION PROCESSES AND PROCEDURES Colstrip Transmission System Transmission Service and Interconnection Processes and Procedures

More information

Interchange Distribution Calculator Billing

Interchange Distribution Calculator Billing Interchange Distribution Calculator Billing Chris Russell Manager, Customer Settlements New York Independent System Operator Billing & Accounting Working Group November 26, 2012 KCC 2012 New York Independent

More information

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission The following White Paper proposes a draft methodology for determining the incremental amount of transfer capability that would be the basis for the quantity of Merchant Transmission CRRs to be allocated

More information

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, 2018 1:00 p.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 1:00-1:10 Stakeholder Process and Schedule Kristina Osborne

More information

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Operating Personnel Communications Protocols Please DO NOT use this form. Please use the electronic comment form to submit comments

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources.

Business Practice. 1.2 Resources must meet certain FERC specified requirements in order to qualify as Designated Network Resources. Business Practice 1. General 1.1 Primary Network Service is a long-term firm service and should only be used by Network Customers when reserving and scheduling delivery of energy from Designated Network

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

State of Minnesota Interconnection Process for Distributed Generation Systems

State of Minnesota Interconnection Process for Distributed Generation Systems State of Minnesota Interconnection Process for Distributed Generation Systems Introduction This document has been prepared to explain the process established in the State of Minnesota, to interconnect

More information

Agreements & Queue Management

Agreements & Queue Management Agreements & Queue Management Resource Interconnection Fair February 24, 2016 Page 1 Interconnection Process Map You are here Page 2 Topics 1. Generator Interconnection Agreement (GIA) 2. Affected Systems

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

CRITICAL ENERGY INFRASTRUCTURE INFORMATION ( CEII ) REQUEST INSTRUCTIONS

CRITICAL ENERGY INFRASTRUCTURE INFORMATION ( CEII ) REQUEST INSTRUCTIONS CRITICAL ENERGY INFRASTRUCTURE INFORMATION ( CEII ) REQUEST INSTRUCTIONS The attached form is intended to facilitate your request to the New York Independent System Operator, Inc. ("NYISO ) for information

More information

Blackout 2003 Reliability Recommendations

Blackout 2003 Reliability Recommendations Blackout 2003 Reliability Recommendations 2005 NPCC General Meeting The Cranwell Resort Lenox, MA September 29, 2005 Philip A. Fedora Director, Market Reliability Interface Northeast Power Coordinating

More information

Open Access Transmission Tariff of Southern Companies

Open Access Transmission Tariff of Southern Companies Open Access Transmission Tariff of Southern Companies Procedures for Reserving Transmission Capacity for Future Load Growth, Designating/Undesignating Network Resources, and Arranging for Other Related

More information

NorthWestern Energy (NWMT)

NorthWestern Energy (NWMT) NorthWestern Energy (NWMT) Open Access Transmission Tariff and OASIS Business Practices Effective 12/27/2007 These business practices apply to transmission service requests made after 10/4/2006. These

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory

Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Authority: This Interconnection Standard is filed in compliance with the Delaware Public Utility Commission in

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Competitive Solicitation Process Enhancements. Status Update / Issue Paper

Competitive Solicitation Process Enhancements. Status Update / Issue Paper Competitive Solicitation Process Enhancements Status Update / Issue Paper October 7, 2014 Table of Contents 1 Introduction... 3 2 Stakeholder process... 4 3 Background on the competitive solicitation process...

More information

Procedure For NPCC Bulk Electric System Asset Database

Procedure For NPCC Bulk Electric System Asset Database Procedure For NPCC Bulk Electric System Asset Database Compliance Procedure 09 (CP-09) Revision 2 Table of Contents 1. Introduction and Purpose... 3 2. Responsibilities... 3 3. Overview... 3 4. Asset Database...

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

U.S. Virgin Islands Water and Power Authority

U.S. Virgin Islands Water and Power Authority U.S. Virgin Islands Water and Power Authority REQUIREMENTS AND PROCEDURES FOR INTERCONNECTION OF SOLAR PHOTOVOLTAIC GENERATION TO THE ELECTRICAL DISTRIBUTION SYSTEM Request for Proposals from Independent

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 978 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE MP 1.1 Objective

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

Consideration of Issues and Directives Federal Energy Regulatory Commission Order No. 791 June 2, 2014

Consideration of Issues and Directives Federal Energy Regulatory Commission Order No. 791 June 2, 2014 Federal Energy Regulatory Commission Order No. 791 June 2, 2014 67 and 76 67. For the reasons discussed below, the Commission concludes that the identify, assess, and correct language, as currently proposed

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Generation Interconnection (GI) as an Input to Multi-Driver Approach

Generation Interconnection (GI) as an Input to Multi-Driver Approach eneration Interconnection (I) as an Input to Multi-Driver Approach September 19, 2014 Example 1 enerator requires upgrade that will be completely replaced by baseline RTEP upgrade enerator enters queue

More information

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011

Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011 Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 2. Initial Technical Review a. The following flowchart provides, for illustrative purposes, the major steps in the Initial Technical Review process:

More information

Policy for Certification of Private Label Products Within the Cradle to Cradle Certified Certification Scheme. Version 1.0.

Policy for Certification of Private Label Products Within the Cradle to Cradle Certified Certification Scheme. Version 1.0. Policy for Certification of Private Label Products Within the Cradle to Cradle Certified Certification Scheme Version 1.0 March 2015 Copyright, Cradle to Cradle Products Innovation Institute, 2015 Cradle

More information

Midwest ISO and PJM Joint Operating Agreement (JOA) Update. Joint Stakeholder Meeting November 14, 2008

Midwest ISO and PJM Joint Operating Agreement (JOA) Update. Joint Stakeholder Meeting November 14, 2008 Midwest ISO and PJM Joint Operating Agreement (JOA) Update Joint Stakeholder Meeting November 14, 2008 JOA Update Introduction Joint Operating Agreement Main Document Initially filed in December 2003 Congestion

More information

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action Mapping Document Mapping Document Showing of PRC-001-2 System Protection Coordination to PRC-027-1 Protection System Coordination for Performance During Faults Updated 10-31 to reflect changes made to

More information

bcuc British Columbia Utilities Commission

bcuc British Columbia Utilities Commission January 26, 2018 bcuc British Columbia Utilities Commission Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project ) Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 3(2018) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

More information

CIP Cyber Security Personnel & Training

CIP Cyber Security Personnel & Training A. Introduction 1. Title: Cyber Security Personnel & Training 2. Number: CIP-004-6 3. Purpose: To minimize the risk against compromise that could lead to misoperation or instability in the Bulk Electric

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Comment Form for 1 st Draft of Standard for Backup Facilities (Project )

Comment Form for 1 st Draft of Standard for Backup Facilities (Project ) Comment Form for 1 st Draft of Standard for Backup Facilities (Project 2006-04) Please use this form to submit comments on the 1 st draft of the standards for Backup Facilities (Project 2006-04). Comments

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

Project Posting 8 Frequently Asked Questions Guide

Project Posting 8 Frequently Asked Questions Guide Project 2007-02 Posting 8 Frequently Asked Questions Guide General Questions 1. What were the inputs that drove the development of posting 8 of Project 2007-02? The NERC Board of Trustees November 7 th,

More information

Critical Cyber Asset Identification Security Management Controls

Critical Cyber Asset Identification Security Management Controls Implementation Plan Purpose On January 18, 2008, FERC (or Commission ) issued Order. 706 that approved Version 1 of the Critical Infrastructure Protection Reliability Standards, CIP-002-1 through CIP-009-1.

More information

This draft standard is being posted for an initial comment and ballot. The draft includes modifications to meet the directives of FERC Order No. 791.

This draft standard is being posted for an initial comment and ballot. The draft includes modifications to meet the directives of FERC Order No. 791. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region Kuwait - November 2011 GCC Cigre, is pleased to announce its 7 th International Conference GCC

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information