NERC EAS Update. Tim Reynolds Sr. Reliability Engineer W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L

Size: px
Start display at page:

Download "NERC EAS Update. Tim Reynolds Sr. Reliability Engineer W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L"

Transcription

1 NERC EAS Update Tim Reynolds Sr. Reliability Engineer

2 2 Changes to the ERO EAP Changes to the EAP to facilitate collecting data Events involving near-misses Inverter disturbances Other things as identified in a ERO audit

3 3 EAS Documents Generating Unit Operations During Complete Loss of Communications Review Going over comments, issue was they did not get everything in time. Clarify what is redundant and diversely routed from TOP-001-4, R20 and R21. Hope to finish in May 2019.

4 4 Monitoring and Situational Conference October 2-3, 2018 in Carmel, IN Link to previous conference presentation Conferences-and-Workshops.aspx

5 5 New Lessons Learned 2018 LL Loss of Substation Data Circuits to SCADA LL Firewall Failure After Time Limit Exceeded

6 6 LL Numbers 10 NERC Lessons Learned have been published to date in Generation Facilities 4 Communications 5 Transmission Facilities 9 NERC Lessons Learned were published in Communications 1 Facilities Design, Commission, and Maintenance 3 Generation Facilities 1 Transmission Facilities

7 Lessons Learned Submitted to NERC being currently worked Lessons Learned submitted to NERC currently under review 7 FRCC 0 MRO 1 NERC 0 NPCC 2 RF 1 SERC 0 TRE 0 WECC 1 WECC LL174 Substation Fires and First Responders This LL comes from two 2017 events. Getting several expert Firefighter inputs. NPCC LL184 Avoiding IROL Exceedances by Rigorous Commissioning & Clear Procedures Transformer differential tripped, remaining transformers picked up load, causing an IROL (post contingency thermal limit). IROL reduction actions were not completed before exceeding T V. RE/Entity answers to questions are being incorporated. MRO LL188 Networking Packet Broadcast Storm When a 2 nd network cable was connected from a Voice Over IP (VOIP) phone to a network, a packet broadcast storm prevented network communications. SCADA was lost for several hours. This should be ready for approval on next EAS call. RF LL178 Initiatives to Address and Reduce Misoperations A misops reduction initiative success story. This should be ready for approval on next EAS call. NPCC LL189 Field Modification & RAS Operation Lead to Partial System Collapse A relay mod enabled line stub bus protection, which misop ed. The mod also kept a RAS from working right. The review team is selecting a time to meet.

8 Lessons Learned Submitted to NERC still needing info Lessons Learned ideas submitted to NERC for review, consideration and development of potential lessons learned waiting for draft or initial review of draft. 8 FRCC 1 +½* MRO 0 NERC 0 NPCC 0 RF 0 SERC 0 TRE ½* WECC 0 FRCC LL173 Static Wire failures (mostly on Preformed Deadends) Needs a draft. *TRE/FRCC LL179 Use of Drones in Storm Recovery Post Harvey/Irma success stories - accelerated assessment of damage, allocation of resources, prioritization, estimates of materials needed, access to difficult to enter locations. Waiting for a draft. Could use photos, links to videos, & some info on expediting FAA permissions. This LL may be taken over by WECC.

9 9 Lessons Learned Metrics Total FRCC MRO NERC NPCC RF SERC TRE WECC Total

10 10 Where to Find NERC LL On the NERC website, Go to > Click on the Program Areas & Departments tab and click Reliability Risk Management Then on the left side menu under Event Analysis click Lessons Learned Link to Lessons Learned At the lower left corner of the NERC.com homepage a/rrm/ea/pages/lessons -Learned.aspx At the lower left corner of the NERC.com homepage

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NARUC Energy Regulatory Partnership Program The Public Services Regulatory Commission of Armenia and The Iowa Utilities Board Janet Amick Senior Utility

More information

Misoperation Information Data Analysis System

Misoperation Information Data Analysis System Misoperation Information Data Analysis System User Guide October, 2017 NERC Report Title Report Date I Table of Contents Preface... iv Overview... v Chapter 1: User Setup... 1-1 Creating an Account...

More information

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014 Request for Data or Information Protection System Misoperation Data Collection August 14, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 15 Table of

More information

State of Reliability Report 2013

State of Reliability Report 2013 State of Reliability Report 2013 Jessica Bian, Director of Performance Analysis Reliability Assessment and Performance Analysis (RAPA), NERC Risk Issues Steering Committee Meeting, July 11-12, 2013 State

More information

Grid Security & NERC

Grid Security & NERC Grid Security & NERC Janet Sena, Senior Vice President, Policy and External Affairs Southern States Energy Board 2017 Associate Members Winter Meeting February 27, 2017 Recent NERC History Energy Policy

More information

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1 DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Reliability Standards Development Plan

Reliability Standards Development Plan Reliability Standards Development Plan 2012-2014 October 13, 2011 For SC Approval 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents...ii

More information

Comment Form for 1 st Draft of Standard for Backup Facilities (Project )

Comment Form for 1 st Draft of Standard for Backup Facilities (Project ) Comment Form for 1 st Draft of Standard for Backup Facilities (Project 2006-04) Please use this form to submit comments on the 1 st draft of the standards for Backup Facilities (Project 2006-04). Comments

More information

Analysis of System Protection Misoperations

Analysis of System Protection Misoperations Analysis of System Protection Misoperations December 2015 Table of Contents Preface... ii Executive Summary...1 Introduction...2 Chapter 1 Misoperation Data Analysis...4 Misoperation Data Reported...4

More information

Misoperations Information Data Analysis System (MIDAS)

Misoperations Information Data Analysis System (MIDAS) Misoperations Information Data Analysis System (MIDAS) End User Guide June 2016 NERC Report Title Report Date I Table of Contents Preface... iii Chapter 1 Reporting Obligations...1 Entities Obligated to

More information

Grid Security & NERC. Council of State Governments. Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016

Grid Security & NERC. Council of State Governments. Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016 Grid Security & NERC Council of State Governments The Future of American Electricity Policy Academy Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016 1965 Northeast blackout

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-012-1 Cyber Security Communications between Control Centers This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity:

More information

Compliance Enforcement Initiative

Compliance Enforcement Initiative Compliance Enforcement Initiative Filing and Status Update November 2, 2011 Rebecca Michael Status of the Filings NERC filed several components of the Compliance Enforcement Initiative on September 30,

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Critical Asset Identification Methodology. William E. McEvoy Northeast Utilities

Critical Asset Identification Methodology. William E. McEvoy Northeast Utilities Critical Asset Identification Methodology William E. McEvoy Northeast Utilities Disclaimer This NPCC TFIST workshop provides a forum for the presentation and discussion of member experience in the implementation

More information

Entity Registration: CFRs

Entity Registration: CFRs Entity Registration: CFRs End User Guide: Registered Entities December 12 th, 2017 1 Table of Contents 1 Overview... 3 1.1 Entity Registration Overview... 3 1.2 CFR Overview... 3 1.2.1 CFR States... 3

More information

CIP Version 5 Evidence Request User Guide

CIP Version 5 Evidence Request User Guide CIP Version 5 Evidence Request User Guide Version 1.0 December 15, 2015 NERC Report Title Report Date I Table of Contents Preface... iv Introduction... v Purpose... v Evidence Request Flow... v Sampling...

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

FRCC Disturbance Reporting Processes and Procedures

FRCC Disturbance Reporting Processes and Procedures Page 1 of 13 FRCC Disturbance Reporting Processes and FRCC RE OP 001-3.2 Effective Date: September 29, 2016 Version: 3.2 3000 Bayport Drive, Suite 600 Tampa, Florida 33607-8410 (813) 289-5644 - Phone (813)

More information

Standards Authorization Request Justification

Standards Authorization Request Justification Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

ERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016

ERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 ERO Reliability Risk Priorities Report Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 RISC s Proposed 2016 Risk Profiles Changing Resource Mix Bulk Power System Planning

More information

Standard and Project Cross References

Standard and Project Cross References Standard and Project Cross References February 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents... 1 Cross References Sorted

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Cyber Security Incident Report

Cyber Security Incident Report Cyber Security Incident Report Technical Rationale and Justification for Reliability Standard CIP-008-6 January 2019 NERC Report Title Report Date I Table of Contents Preface... iii Introduction... 1 New

More information

Essential Reliability Services NERC Staff Report

Essential Reliability Services NERC Staff Report Essential Reliability Services NERC Staff Report Mark Lauby, Senior Vice President and Chief Reliability Officer Annual Meeting of the National Conference of State Legislators August 20, 2014 About NERC

More information

Standards Development Update

Standards Development Update Standards Development Update Steven Noess, Director of Standards Development FRCC Reliability Performance Industry Outreach Workshop September 20, 2017 Supply Chain Risk Management 1 Cyber Security Supply

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

primary Control Center, for the exchange of Real-time data with its Balancing

primary Control Center, for the exchange of Real-time data with its Balancing A. Introduction 1. Title: Reliability Coordination Monitoring and Analysis 2. Number: IRO-002-5 3. Purpose: To provide System Operators with the capabilities necessary to monitor and analyze data needed

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Lesson Learned CIP Version 5 Transition Program

Lesson Learned CIP Version 5 Transition Program Lesson Learned CIP Version 5 Transition Program CIP-002-5: BES Cyber Assets Version: December 7, 2015 This document is designed to convey lessons learned from NERC s various CIP version 5 transition activities.

More information

DRAFT Risks and Mitigations for Losing EMS Functions

DRAFT Risks and Mitigations for Losing EMS Functions DRAFT Risks and Mitigations for Losing EMS Functions 1.0 Executive Summary Energy Management System (EMS) is a system of computer-aided tools used by System Operators to monitor, control, and optimize

More information

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval. Introduction 1. Title: IROL and SOL Mitigation in the ERCOT Region 2. Number: IRO-006-TRE-1 3. Purpose: To provide and execute transmission loading relief procedures that can be used to mitigate SOL or

More information

DRAFT Reliability Standard Audit Worksheet 1

DRAFT Reliability Standard Audit Worksheet 1 DRAFT Reliability Standard Audit Worksheet 1 PRC-025-2 Generator Relay Loadability This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR Number: Compliance

More information

Agenda Event Analysis Subcommittee Conference Call

Agenda Event Analysis Subcommittee Conference Call Agenda Event Analysis Subcommittee Conference Call September 11, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Meeting- Overview of. Development

Meeting- Overview of. Development NPCC 2008 General Meeting- Standards Program Area- Overview of Regional Standards Development Guy V. Zito Assistant Vice President Standards September 25, 2008 September 25, 2008 1 Standards Program Area

More information

Questions and Answers about Consistent Protection System Misoperation Reporting

Questions and Answers about Consistent Protection System Misoperation Reporting Questions and Answers about Consistent Protection System Misoperation Reporting 1. Are the Misoperation Categories consistent with the NERC Glossary? Yes, the categories are consistent with the definitions

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 FAC-003-4 Transmission Vegetation Management. Registered Entity Name: Applicable Function(s): Applicable only for TO and GO Compliance Monitoring Method: RSAW Version:

More information

Critical Infrastructure Protection Committee Strategic Plan

Critical Infrastructure Protection Committee Strategic Plan Critical Infrastructure Protection Committee Strategic Plan 2018-2019 CIPC Executive Committee Updated:xxxxxxxx NERC Report Title Report Date I Table of Contents Preface... iii CIPC Organizational Structure...

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR

More information

TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018

TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018 TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements FRCC Spring RE Workshop April 17-18, 2018 Objectives Background Reference Documents TOP-001-3 to TOP-001-4 Changes o R10 (TOP) Monitoring

More information

Entergy Development and Deployment of IEC Protection and Control Including Process Bus

Entergy Development and Deployment of IEC Protection and Control Including Process Bus Entergy Development and Deployment of IEC 61850 Protection and Control Including Process Bus Chan Y. Wong Entergy Transmission Eric A. Udren and Solveig Ward Quanta Technology, LLC Presented at CIGRÉ Grid

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Standard Authorization Request Form

Standard Authorization Request Form Standard Authorization Request Form Title of Proposed Standard: Project 2009-02: Real-time Reliability Monitoring and Analysis Capabilities Original Request Date: June 4, 2009 Revised Date: January 15,

More information

Compliance Exception and Self-Logging Report Q4 2014

Compliance Exception and Self-Logging Report Q4 2014 Agenda Item 5 Board of Trustees Compliance Committee Open Session February 11, 2015 Compliance Exception and Self-Logging Report Q4 2014 Action Information Introduction Beginning in November 2013, NERC

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered

More information

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia Page 1 of 15 British Columbia Utilities Reliability Standards with s adopted in British Columbia BAL-001-2 Standard Real Power Balancing Control Performance R-14-16 July 1, 2016 BAL-002-1 1 Disturbance

More information

Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13

Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 I. Vision A highly reliable and secure bulk power system in the Electric Reliability Council of Texas

More information

Standard EOP Disturbance Reporting

Standard EOP Disturbance Reporting A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment

More information

Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays

Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays Prepared by the System Protection and Control Task Force of

More information

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015 Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

Electric Transmission Reliability

Electric Transmission Reliability 1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at

More information

Board of Trustees Compliance Committee

Board of Trustees Compliance Committee Board of Trustees Compliance Committee August 13, 2014 10:00 a.m. 11:00 a.m. Pacific The Westin Bayshore 1601 Bayshore Drive Vancouver, BC V6G 2V4 Reliability Assurance Initiative (RAI) Progress Report

More information

Agenda Event Analysis Subcommittee Conference Call

Agenda Event Analysis Subcommittee Conference Call Agenda Event Analysis Subcommittee Conference Call August 14, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security

More information

October 2, CIP-014 Report Physical Security Protection for High Impact Control Centers Docket No. RM15-14-

October 2, CIP-014 Report Physical Security Protection for High Impact Control Centers Docket No. RM15-14- October 2, 2017 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: CIP-014 Report Physical Security Protection for High Impact Control Centers

More information

Implementation Plan for COM-001-2

Implementation Plan for COM-001-2 Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.

More information

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage

More information

Low Impact Generation CIP Compliance. Ryan Walter

Low Impact Generation CIP Compliance. Ryan Walter Low Impact Generation CIP Compliance Ryan Walter Agenda Entity Overview NERC CIP Introduction CIP-002-5.1, Asset Classification What Should Already be Done CIP-003-7, Low Impact Requirements Tri-State

More information

Disturbance Monitoring Standard Drafting Team August 7, p.m. 5 p.m. August 8, a.m. 5 p.m. August 9, a.m. noon

Disturbance Monitoring Standard Drafting Team August 7, p.m. 5 p.m. August 8, a.m. 5 p.m. August 9, a.m. noon Disturbance Monitoring Standard Drafting Team August 7, 2007 1 p.m. 5 p.m. August 8, 2007 8 a.m. 5 p.m. August 9, 2007 8 a.m. noon Florida Power and Light Offices 700 Universe Blvd. Juno Beach, Florida

More information

Assessment Report & Update

Assessment Report & Update 2011 Pilot Probabilistic Assessment Report & Update July 26-27, 2012 LOLE Best Practices Working Group John Moura, NERC Staff Coordinator; Kevan Jefferies, RAS-ProbA Team Lead Background - Probabilistic

More information

Multi-Region Registered Entity Coordinated Oversight Program

Multi-Region Registered Entity Coordinated Oversight Program Multi-Region Registered Entity Coordinated Oversight Program Ken McIntyre, Vice President and Director of Standards and Compliance Compliance Committee Open Meeting February 7, 2018 Coordinated Oversight

More information

Official Comment Form Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Official Comment Form Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Official Comment Form Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Please use this form to submit comments on the proposed Reliability Guideline: Generating

More information

Version Sept2017. Hummingbird IRB Approved 09/19/2017

Version Sept2017. Hummingbird IRB Approved 09/19/2017 We invite you to create your account in the Global PWS Registry and add your story. The purpose of the Global PWS Registry is to collect and analyze PWS patient data to enhance the understanding of PWS.

More information

Standard CIP 005 2a Cyber Security Electronic Security Perimeter(s)

Standard CIP 005 2a Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-2a 3. Purpose: Standard CIP-005-2 requires the identification and protection of the Electronic Security Perimeter(s)

More information

Table of Issues and Directives Project Relay Loadability: Stable Power Swings

Table of Issues and Directives Project Relay Loadability: Stable Power Swings Table of Issues and Directives Project 2010-13.3 Relay Loadability: Stable Power Swings FERC Order 733 150. We will not direct the ERO to modify PRC-023-1 to address stable power swings. However, because

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

CIP V5 Updates Midwest Energy Association Electrical Operations Conference

CIP V5 Updates Midwest Energy Association Electrical Operations Conference CIP V5 Updates Midwest Energy Association Electrical Operations Conference May 2015 Bob Yates, CISSP, MBA Principal Technical Auditor ReliabilityFirst Corporation Agenda Cyber Security Standards Version

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

Lesson Learned CIP Version 5 Transition Program CIP R1: Grouping BES Cyber Assets Version: March 2, 2014

Lesson Learned CIP Version 5 Transition Program CIP R1: Grouping BES Cyber Assets Version: March 2, 2014 Lesson Learned CIP Version 5 Transition Program CIP-002-5.1 R1: Grouping BES Cyber Assets Version: March 2, 2014 This document is designed to convey lessons learned from NERC s various CIP version 5 transition

More information

Reliability Standards Development Plan

Reliability Standards Development Plan Reliability Standards Development Plan Steven Noess, Director of Standards Development Standards Oversight and Technology Committee Meeting November 1, 2016 2017-2019 Reliability Standards Development

More information

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support TOP/IRO Standards RC Users Group January 21, 2016 Vic Howell Manager, Operations Engineering Support Saad Malik Manager, Real-Time Operations Engineering New/Revised TOP & IRO Standards November 19, 2015,

More information

Comment Form for Compliance Elements

Comment Form for Compliance Elements Please use this form to submit comments on the Compliance Elements Standard Drafting Team s second draft of the 20 Missing Compliance Measures and Elements standards. Comments must be submitted by August

More information

Risk-Based Compliance Monitoring & Enforcement Oversight Framework. FRCC Spring Compliance Workshop April 14 16, 2015

Risk-Based Compliance Monitoring & Enforcement Oversight Framework. FRCC Spring Compliance Workshop April 14 16, 2015 Risk-Based Compliance Monitoring & Enforcement Oversight Framework FRCC Spring Compliance Workshop April 14 16, 2015 Upcoming Events FRCC is Conducting Individual Outreach NERC CIP Version 5 Workshop &

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

NERC Monitoring and Situational Awareness Conference: Loss of Control Center Procedures and Testing Practices

NERC Monitoring and Situational Awareness Conference: Loss of Control Center Procedures and Testing Practices NERC Monitoring and Situational Awareness Conference: Loss of Control Center Procedures and Testing Practices Ed Batalla Director of Technology Florida Power & Light Company September 19, 2013 Florida

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

Agenda Event Analysis Subcommittee Conference Call

Agenda Event Analysis Subcommittee Conference Call Agenda Event Analysis Subcommittee Conference Call October 23, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security

More information

NPCC Regional Reliability Reference Directory # 4 Bulk Power System Protection Criteria

NPCC Regional Reliability Reference Directory # 4 Bulk Power System Protection Criteria NPCC Regional Reliability Reference Directory # 4 Task Force on System Protection Revision Review Record: December 1 st, 2009 September 30 th, 2015 Adopted by the Members of the Northeast Power Coordinating

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Implementation Plan. Project CIP Version 5 Revisions. January 23, 2015

Implementation Plan. Project CIP Version 5 Revisions. January 23, 2015 Implementation Plan Project 2014-02 CIP Version 5 Revisions January 23, 2015 This Implementation Plan for the Reliability Standards developed as part of Project 2014-02 CIP Version 5 Revisions replaces

More information

2017 MRO Performance Areas and an Update on Inherent Risk Assessments

2017 MRO Performance Areas and an Update on Inherent Risk Assessments MIDWEST RELIABILITY ORGANIZATION 2017 MRO Performance Areas and an Update on Inherent Risk Assessments Adam Flink, Risk Assessment and Mitigation Engineer November 16, 2016 Improving RELIABILITY and mitigating

More information

2018 MRO Regional Risk Assessment

2018 MRO Regional Risk Assessment MIDWEST RELIABILITY ORGANIZATION 2018 MRO Regional Risk Assessment Ben Lewiski, Risk Assessment and Mitigation Engineer November 28, 2017 Improving RELIABILITY and mitigating RISKS to the Bulk Power System

More information

Member Representatives Committee Meeting

Member Representatives Committee Meeting Member Representatives Committee Meeting August 13, 2014 1:15 p.m. 5:15 p.m. Pacific The Westin Bayshore, Vancouver 1601 Bayshore Drive Vancouver, BC V6G 2V4 Canada Opening Remarks by MRC Chair Consent

More information

FERC Reliability Technical Conference Panel I: 2015 State of Reliability Report Introduction Overview of the State Of Reliability

FERC Reliability Technical Conference Panel I: 2015 State of Reliability Report Introduction Overview of the State Of Reliability : 2015 State of Reliability Report Remarks of Thomas Burgess, Vice President and Director of Reliability Assessment and Performance Analysis Introduction Chairman Bay and Commissioners, members of the

More information

Implementation Plan. Project CIP Version 5 Revisions 1. January 23, 2015

Implementation Plan. Project CIP Version 5 Revisions 1. January 23, 2015 Implementation Plan Project 2014-02 CIP Version 5 Revisions January 23, 2015 This Implementation Plan for the Reliability Standards developed as part of Project 2014 02 CIP Version 5 Revisions replaces

More information

Implementation Plan for Version 5 CIP Cyber Security Standards

Implementation Plan for Version 5 CIP Cyber Security Standards Implementation Plan for Version 5 CIP Cyber Security Standards April 10September 17, 2012 Note: On September 17, 2012, NERC was alerted that some references in the Initial Performance of Certain Periodic

More information

Standard CIP 005 4a Cyber Security Electronic Security Perimeter(s)

Standard CIP 005 4a Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-4a 3. Purpose: Standard CIP-005-4a requires the identification and protection of the Electronic Security Perimeter(s)

More information

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 Power System Resilience & Reliability Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 NERC, Reliability, & Resilience NERC has addressed reliability

More information

NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM September 6, 2013

NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM September 6, 2013 NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM-003-1 September 6, 2013 At the August 14-15, 2013 meeting of the Board of Trustees ( Board ) of the North

More information

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013 Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently

More information

Project Retirement of Reliability Standard Requirements

Project Retirement of Reliability Standard Requirements Project 2013-02 Retirement of Reliability Standard Requirements Unofficial Comment Form for Paragraph 81 (P81) Project Retirement of Reliability Standard Requirements This form is provided in a Word format

More information

Lesson Learned CIP Version 5 Transition Program CIP : Communications and Networking Cyber Assets Version: October 6, 2015

Lesson Learned CIP Version 5 Transition Program CIP : Communications and Networking Cyber Assets Version: October 6, 2015 Lesson Learned CIP Version 5 Transition Program CIP-002-5.1: Communications and Networking Cyber Assets Version: October 6, 2015 Authorized by the Standards Committee on October 29, 2015 for posting as

More information

Chapter X Security Performance Metrics

Chapter X Security Performance Metrics DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the

More information