Implementation Status & Results Philippines Support for Strategic Local Development and Investment Project (P064925)

Size: px
Start display at page:

Download "Implementation Status & Results Philippines Support for Strategic Local Development and Investment Project (P064925)"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Philippines Support for Strategic Local Development and Investment Project (P064925) Operation Name: Support for Strategic Local Development and Investment Project Stage: Implementation Seq.No: 11 Status: ARCHIVED Archive : 10-Jul-2013 Project (P064925) Country: Philippines Approval FY: 2006 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key s Board Approval 29-Jun-2006 Original Closing 30-Jun-2012 Planned Mid Term Review 31-May-2009 Last Archived ISR 12-Nov-2012 Effectiveness 28-Feb-2007 Revised Closing Actual Mid Term Review 31-May-2009 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve local public service provision and management by facilitating LGU access to viable financing to implement strategic infrastructure investments. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) losure Authorized Public Disclosure Authorized Component Name Component Cost Sub-projects for Infrastructure and Finance Improvement LGU Capacity Building & Project Implementation Support 5.56 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview The project continued to show headway in achieving its development objective of improving local public service provision and management by facilitating LGU access to viable financing to implement strategic infrastructure investments. Nearly all project outcomes and outputs have been achieved; some are already beyond their targets. During project extension, however, subproject processing was slowed down by the additional processing requirement of National Government for local government borrowings and by the May 2013 local elections. LBP has indicated that it may request for additional loan closing extension to complete six subprojects that are unlikely to be completed by loan closing, including two large subprojects that have been persistently facing implementation issues. LBP also wishes to utilize remaining project funds to fund additional subprojects. Page 1 of 7

2 Locations Country First Administrative Division Location Planned Actual Philippines Eastern Visayas Tomas Oppus Philippines Not Entered Tiaong Philippines Central Luzon Tarlac Philippines Caraga Tandag Philippines Central Visayas Talisay Philippines Central Visayas Talibon Philippines Caraga Tagbina Philippines Soccsksargen Province of Sultan Kudarat Philippines Eastern Visayas Sulat Philippines Western Visayas Sipalay Philippines Eastern Visayas Santa Rita Philippines Cagayan Valley San Pablo Philippines Cagayan Valley San Mateo Philippines Not Entered San Juan Philippines Eastern Visayas San Isidro Philippines Eastern Visayas Salcedo Philippines Eastern Visayas Pintuyan Philippines Western Visayas Passi Philippines Bicol Panganiban Philippines Eastern Visayas Palapag Philippines Eastern Visayas Padre Burgos Philippines Ilocos Narvacan Philippines Eastern Visayas Merida Philippines Eastern Visayas Mayorga Page 2 of 7

3 Country First Administrative Division Location Planned Actual Philippines Cagayan Valley Maddela Philippines Caraga Lingig Philippines Central Visayas Liloan Philippines Eastern Visayas Province of Leyte Philippines Not Entered Legaspi City Philippines Ilocos Province of La Union Philippines Not Entered Lapu-Lapu City Philippines Eastern Visayas La Paz Philippines Eastern Visayas Kawayan Philippines Soccsksargen Iligan City Philippines Eastern Visayas Hinunangan Philippines Eastern Visayas Hilongos Philippines Eastern Visayas Hernani Philippines Central Visayas Guindulman Philippines Eastern Visayas Giporlos Philippines Not Entered General Santos City Philippines Zamboanga Peninsula Municipality of Dumingag Philippines Not Entered Dipolog City Philippines Davao Province of Davao Oriental Philippines Central Visayas Dagohoy Philippines Eastern Visayas Culaba Philippines Eastern Visayas Catbalogan Philippines Central Visayas Carcar Philippines Caraga Cantilan Philippines Ilocos Candon Page 3 of 7

4 Philippines Eastern Visayas Can-Avid Philippines Mimaropa Buenavista Philippines Eastern Visayas Borongan Philippines Caraga Bislig Philippines Central Visayas Bilar Philippines Central Visayas Basay Philippines Bicol Barcelona Philippines Central Luzon Balanga Philippines Eastern Visayas Allen Philippines Central Luzon Abucay Philippines Cordillera Administrative Region Province of Abra Philippines Caraga Municipality of Loreto Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of households benefitting from the Text Value 221, , ,000 project with improved access to basic social, economic and environmental infrastructure services in participating LGUs Data for the number of HHs Achieved. Project already with access is currently being exceeded the EOP target by collected. 79%. Increase in proportion of infrastructure investment to total expenditure among participating LGUs Intermediate Results Indicators Text Value 25% 60% No target Figure is based on CY 2006 data. 140% increase in proportion from baseline; 34% can be attributed to the project; figure based on available data for CY Page 4 of 7

5 Indicator Name Core Unit of Measure Baseline Current End Target At least 50 subprojects are physically complete Text Value at EOP Achieved. 108% of the EOP target. Number of sub-projects with revenue Text Value enhancing measures at EOP Achieved. EOP target of 25 subprojects was set at MTR. Number of non-performing loans in LBP's LGU Text Value <2% % <2% portfolio remains low Achieved; figure based on PMO computation 100% of targeted participating LGUs receive training and other forms of assistance. PMO and Project Implementation Units are established and supported by technically equipped staff and are functioning Text Value 0 100% 100% of targeted participating LGUs All 63 LGUs received procurement orientation; 42 LGUs received construction supervision training. Capacity-building activities will be undertaken for LGUs with completed water supply subprojects. LGUs are only counted once. Double counting is already eliminated. Text Value None 63 PMO established at LBP and Project Implementation Units are established and functioning in 100% of participating LGUs. All PIUs are operational. 48 subprojects are now completed. Page 5 of 7

6 Operations Manual completed, disseminated and updated M and E system is installed and corresponding M&E manual completed, disseminated and updated Text Value None Operations Manual completed, disseminated and updated Operations Manual completed, disseminated and updated Text Value None M&E system installed and M&E system installed and corresponding M&E manual corresponding M&E manual completed, disseminated and completed, disseminated and updated. updated. Semi-annual progress report for the period October March 2013 submitted. Data on Financial Performance (as of 19-Dec-2012) Financial Agreement(s) Key s Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P IBRD Effective 29-Jun Oct Feb Jun-2012 P TF Closed 11-Jul Jul Jul Jul Jul-2011 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IBRD Effective USD P TF Closed USD Disbursement Graph Page 6 of 7

7 Key Decisions Regarding Implementation LBP is encouraged to intensify monitoring particularly of critical subprojects as the project closing date draws near. The PMO will review the project implementation schedule and determine and inform the Bank if further extension is necessary. Restructuring History Level two Approved on 22-Jun-2012 Related Projects There are no related projects. Page 7 of 7

Implementation Status & Results Philippines Support for Strategic Local Development and Investment Project (P064925)

Implementation Status & Results Philippines Support for Strategic Local Development and Investment Project (P064925) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Philippines Support for Strategic Local Development and Investment Project (P064925) Operation Name:

More information

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577)

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Operation Name: Local Government

More information

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577)

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Operation Name: Local Government

More information

Implementation Status & Results Bangladesh BD Identification System for Enhancing Access to Services (IDEA) Project (P121528)

Implementation Status & Results Bangladesh BD Identification System for Enhancing Access to Services (IDEA) Project (P121528) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Bangladesh BD Identification System for Enhancing Access to Services (IDEA) Project (P121528) Operation Name: BD

More information

Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899)

Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899) Operation Name: Energy Community

More information

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy Implementation Status & Results Pakistan Balochistan Disaster Management Project (P127253) Operation Name: Balochistan Disaster Management Project (P127253) Project Stage: Implementation Seq.No: 4 Status:

More information

Implementation Status & Results Africa West Africa Regional Communications Infrastructure Program (P116273)

Implementation Status & Results Africa West Africa Regional Communications Infrastructure Program (P116273) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Africa West Africa Regional Communications Infrastructure Program (P116273) Operation Name: West

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 02-Oct-2017 ISR29601

More information

Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program (P096207)

Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program (P096207) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Ethiopia Economic Policy Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 2 ARCHIVED on 29-Jun-2015 ISR19269 Implementing Agencies:

More information

Bangladesh Urban Resilience Project (P149493)

Bangladesh Urban Resilience Project (P149493) Public Disclosure Authorized SOUTH ASIA Bangladesh Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2015 Seq No: 8 ARCHIVED on 30-Dec-2018 ISR35201

More information

ICT Sector Support in Somalia Phase II (P152358)

ICT Sector Support in Somalia Phase II (P152358) Public Disclosure Authorized AFRICA Somalia Transport & ICT Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 2 ARCHIVED on 31-Aug-2016 ISR24913 Implementing Agencies:

More information

Result of 2017 Customer Experience Survey Renewal of Business Permit

Result of 2017 Customer Experience Survey Renewal of Business Permit Result of 2017 Customer Experience Survey Renewal of Business Permit Executive Brief BACKGROUND In 2010, the Department of Trade and Industry (DTI) and the Department of Interior and Local Government (DILG)

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Western Africa Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 9 ARCHIVED on 29-Oct-2017 ISR29795 Implementing Agencies: Ministry

More information

The World Bank. losure Authorized Public Disclosure Authorized. Public Disclosure Copy. Key Dates. Project Development Objectives.

The World Bank. losure Authorized Public Disclosure Authorized. Public Disclosure Copy. Key Dates. Project Development Objectives. Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Philippines Kapitbisig Laban sa Kahirapan-Comprehensive and Integrated Delivery of Social Services

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Western Africa Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2011 Seq No: 9 ARCHIVED on 03-Feb-2016 ISR21999 Implementing Agencies: Ministry of

More information

The World Bank Central African Backbone - APL4 - Gabon (P122776)

The World Bank Central African Backbone - APL4 - Gabon (P122776) Public Disclosure Authorized AFRICA Gabon Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2012 Seq No: 9 ARCHIVED on 25-Jan-2016 ISR22499 Implementing Agencies: Public Disclosure Authorized

More information

Public Disclosure Copy

Public Disclosure Copy AFRICA Western Africa Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 6 ARCHIVED on 31-Jan-2016 ISR20991 Implementing Agencies: Ministry of Employment, Professional Education

More information

The World Bank Central African Backbone - APL4 - Gabon (P122776)

The World Bank Central African Backbone - APL4 - Gabon (P122776) Public Disclosure Authorized AFRICA Africa Global Information/Communications Technology Global Practice IBRD/IDA Adaptable Program Loan FY 2012 Seq No: 8 ARCHIVED on 16-Jun-2015 ISR19741 Implementing Agencies:

More information

The World Bank KI: Telecommunications and ICT Development Project (P126324)

The World Bank KI: Telecommunications and ICT Development Project (P126324) Public Disclosure Authorized EAST ASIA AND PACIFIC Kiribati Transport & ICT Global Practice IBRD/IDA Technical Assistance Loan FY 2013 Seq No: 8 ARCHIVED on 23-Mar-2017 ISR27153 Implementing Agencies:

More information

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17 Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11

More information

The Philippine O&O Industry

The Philippine O&O Industry The Philippine O&O Industry SSME Conference 7 August 2008 Secretary Ray Anthony Roxas-Chua III Commission on Information and Communications Technology Industry Overview O&O Industry Growth Total Employees

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. PID7026 PID7026.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. PID7026 PID7026. PID7026.TXT Project Name Region Sector Project ID Borrower Implementing Agency Environment Category Estonia-Transport Project (@+) Europe and Central Asia Report No. PID7026 Infrastructure (Transport Sub-Sector)

More information

Promoting Quality Infrastructure Investment

Promoting Quality Infrastructure Investment Promoting Quality Infrastructure Investment - Japan s contribution to infrastructure development - Mitsutoshi Kajikawa Director, Development Policy Division Ministry of Finance, Japan 1 Quality Infrastructure

More information

Governing Body 313th Session, Geneva, March 2012

Governing Body 313th Session, Geneva, March 2012 INTERNATIONAL LABOUR OFFICE Governing Body 313th Session, Geneva, 15 30 March 2012 Programme, Financial and Administrative Section PFA FOR INFORMATION Information and communications technology questions

More information

Re-Positioning AzerPost

Re-Positioning AzerPost WORLD BANK Re-Positioning AzerPost for the 21 st Century Financial Services Development Project Michael Edwards Lead Financial Sector Specialist medwards1@worldbank.org The project overarching goal is

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 22-Mar-2016

More information

LEGAZPI CITY: DISASTER RESPONSE AND RESILIENCY INITIATIVES

LEGAZPI CITY: DISASTER RESPONSE AND RESILIENCY INITIATIVES LEGAZPI CITY: DISASTER RESPONSE AND RESILIENCY INITIATIVES GILBERT C. GONZALES Regional Director DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES Philippines 6TH HIGH LEVEL SEMINAR ON ENVIRONMENTALLY SUSTAINABLE

More information

DATA FOR DEVELOPMENT June 13, 2017

DATA FOR DEVELOPMENT June 13, 2017 DATA FOR DEVELOPMENT June 13, 2017 1 Recent economic developments and outlook 2 Data for development Malaysia s development and its data ecosystem o Data and the public sector- public service delivery

More information

INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010

INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010 INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010 OVERVIEW OF PRESENTATION 2 LANDSCAPE CHALLENGES FUNDING SOURCES (ROLE OF FINANCIAL INSTITUTIONS) ROLE OF GOVERNMENT OBSERVATIONS SUGGESTED

More information

Sony Ericsson starts 2007 with strong first quarter

Sony Ericsson starts 2007 with strong first quarter PRESS RELEASE April 20, 2007 Sony Ericsson starts 2007 with strong first quarter Q1 Highlights: Year-on-year volume & sales growth of 63% and 47% respectively Income before tax rose 139% year-on-year to

More information

Wi-Fi Hotspot Lending Project Phase 2 Findings and Future Directions

Wi-Fi Hotspot Lending Project Phase 2 Findings and Future Directions STAFF REPORT INFORMATION ONLY 21. Wi-Fi Hotspot Lending Project Phase 2 Findings and Future Directions Date: January 29, 2018 To: From: Toronto Public Library Board City Librarian SUMMARY The purpose of

More information

Towngas to Invest in Foshan Water Environmental Protection Co., Ltd

Towngas to Invest in Foshan Water Environmental Protection Co., Ltd Towngas to Invest in Foshan Water Environmental Protection Co., Ltd Poised To Capture Synergy with Its First Water Services Project in the Greater Bay Area (16 October 2018, Hong Kong) The Hong Kong and

More information

HLG Briefly. HLG was established on March 6, 2015 during the 46 th Session of the UN Statistical Commission

HLG Briefly. HLG was established on March 6, 2015 during the 46 th Session of the UN Statistical Commission HLG Briefly Activity of the High-Level Group for Partnership, Coordination and Capacity Building for Statistics for Agenda 030 on Sustainable Development (HLG) HLG was established on March 6, 015 during

More information

Implementation Status & Results Vietnam Vietnam - ICT Development (P079344)

Implementation Status & Results Vietnam Vietnam - ICT Development (P079344) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Vietnam Vietnam - ICT Development (P079344) Operation Name: Vietnam - ICT Development (P079344)

More information

1/8. Note by the Chair. Executive Summary. 24 th Senior Officials Meeting of the Environment Management Group. EMGSOM.24(a)_4_Work Plan_2019

1/8. Note by the Chair. Executive Summary. 24 th Senior Officials Meeting of the Environment Management Group. EMGSOM.24(a)_4_Work Plan_2019 24 th Senior Officials Meeting of the Environment Management Group Technical Segment, 17 th September 2018 (15:00-17:00 Geneva time) Via audio-video conference EMGSOM.24(a)_4_Work Plan_2019 Distribution:

More information

Elements of FIP Investment Criteria and Financing Modalities

Elements of FIP Investment Criteria and Financing Modalities FIP/SC.2/4Rev1 January 21, 2010 Meeting of the FIP Sub-Committee Washington, D.C. February 3 and 4, 2010 Criteria and Financing 1 FOREST INVESTMENT PROGRAM Elements of FIP Investment February 2 and 3,

More information

Hitachi Completes Transfer of Hard Disk Drive Business to Western Digital

Hitachi Completes Transfer of Hard Disk Drive Business to Western Digital FOR IMMEDIATE RELEASE Contact: Japan: Hajime Kito Hitachi, Ltd. +81-3-5208-9323 hajime.kito.qy@hitachi.com Hitachi Completes Transfer of Hard Disk Drive Business to Western Digital Tokyo, March 9, 2012

More information

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO

More information

Kenya at the tipping Point?

Kenya at the tipping Point? Kenya at the tipping Point? with a special focus on the ICT revolution and Mobile Money World Bank Economic Team Presentation by Jane Kiringai Nairobi December 2, 2010 Main messages 1 2 Kenya may now be

More information

ADB s Energy Program in Myanmar

ADB s Energy Program in Myanmar ADB s Energy Program in Myanmar March 2014 Chong Chi Nai Director, Energy Division Southeast Asia Regional Department 1 Current Sector Context Low electrification ratio Need to develop cost effective way

More information

ACCREDITATION OF TRAINING INSTITUTIONS (List of Accredited Government Training Institutions) As of June 30, 2001

ACCREDITATION OF TRAINING INSTITUTIONS (List of Accredited Government Training Institutions) As of June 30, 2001 ACCREDITATION OF TRAINING INSTITUTIONS (List of Accredited Government Training Institutions) As of June 30, 2001 ng_ trnginst address tel trnginst dateacc 1 Agricultural Training - Elliptical Rd., Diliman,

More information

An Introduction to the SEforALL Building Efficiency Accelerator Belgrade BEA Kick-off Meeting 31 October 2016 Eric Mackres,

An Introduction to the SEforALL Building Efficiency Accelerator Belgrade BEA Kick-off Meeting 31 October 2016 Eric Mackres, An Introduction to the SEforALL Building Efficiency Accelerator Belgrade BEA Kick-off Meeting 31 October 2016 Eric Mackres, emackres@wri.org Manager, Building Efficiency, WRI Ross Center for Sustainable

More information

Annex 2. Procurement Plan by VEA/ISEA PMU for 2011

Annex 2. Procurement Plan by VEA/ISEA PMU for 2011 losure uthorized Public Disclosure uthorized Public Disclosure uthorized Public Disclosure uthorized nnex 2. Procurement Plan by V/IS PMU for 2011 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Pack. Comp.

More information

Result of Validation of Good Governance Conditions List of Non-Compliant for GOCCs covered by RA 10149

Result of Validation of Good Governance Conditions List of Non-Compliant for GOCCs covered by RA 10149 193e Inter-Agency Task Force on the Harmonization of (Administrative Order No. 255. 2011) 1. DBP Data Center. Inc. 1. Boy Scouts of the Philippines 1. Social Housing Finance Corporation 2. LBP Resources

More information

OFFICIAL DOCUMENTS. Excellency: Re: IDA Financing No PK (TDPs Emergency Recovery Project) Additional Instructions: Disbursement

OFFICIAL DOCUMENTS. Excellency: Re: IDA Financing No PK (TDPs Emergency Recovery Project) Additional Instructions: Disbursement Public Disclosure Authorized OFFICIAL DOCUMENTS - The World Bank 1818 H Street N.W. (202) 473-1000 INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Washington, D.C. 20433 Cable Address: INTBAFRAD

More information

NAC Institutional Committee Meeting

NAC Institutional Committee Meeting Meeting Jet Propulsion Lab July 28-29, 2015 Kathryn Schmoll Chair Membership Committee Members Current Employer Current Position 1 CHAIR: Kathryn (Katy) Schmoll Kathryn Schmoll and Associates, LLC 2 James

More information

Gigabit West Sussex. Report to Cabinet. Executive Summary. Recommendations. Reasons for Recommendations. Background Papers

Gigabit West Sussex. Report to Cabinet. Executive Summary. Recommendations. Reasons for Recommendations. Background Papers Report to Cabinet 21 st September 2017 By the Cabinet Member for Finance & Assets DECISION REQUIRED Not Exempt Gigabit West Sussex Executive Summary This report explains the reasons why the Council should

More information

6. Environmental Assessment Framework

6. Environmental Assessment Framework E2631 6. Environmental Assessment Framework Introduction This energy efficiency project will lend funds to industrial enterprises and to Energy Management Companies (ESCOs) for eligible energy efficient

More information

Headquarters-PPCR Focal Point: Kanta Kumari Rigaud

Headquarters-PPCR Focal Point: Kanta Kumari Rigaud PILOT PROGRAM FOR CLIMATE RESILIENCE Summary - Project Approval Request 1. Country: Mozambique 2. CIF Project XPCRMZ019A ID#: 3. Project Title: Climate Resilience: Transforming Hydro-Meteorological Services

More information

Publication of the National CyberSecurity Plan 2022 (NCSP 2022)

Publication of the National CyberSecurity Plan 2022 (NCSP 2022) Publication of the National CyberSecurity Plan 2022 (NCSP 2022) Launched on December 8, 2016 Various roundtable discussions / consultations with vital sectors were done Published on May 2, 2017 Available

More information

3. Authorize budget changes as outlined in the Financial Impacts and Budget Actions section of this report.

3. Authorize budget changes as outlined in the Financial Impacts and Budget Actions section of this report. City Council Report To: From: Mayor and City Council City Council Meeting: March 1, 2016 Agenda Item: 3.B Jory Wolf, Chief Information Officer, Information Systems Department, Broadband Subject: Digital

More information

Service Plan for Infrastructure Engineering

Service Plan for Infrastructure Engineering Service Plan for Infrastructure 2016-2019 Capital Regional District Date submitted: Revised: August 14, 2017 Table of Contents 1 Overview... 1 1.1 Division & Service Summary... 1 1.2 Organization Chart...

More information

Advancement in the preparation of ROGEP

Advancement in the preparation of ROGEP Advancement in the preparation of ROGEP Funded by: Nicola Bugatti, Project Coordinator 26 th June 2018 WWW.ECREEE.O RG Outline The Regional Off-Grid Electrification Project ROGEP ROGEP s preparation ROGEP

More information

Asian Development Bank s Country Partnership Strategy with the Philippines

Asian Development Bank s Country Partnership Strategy with the Philippines Asian Development Bank s Country Partnership Strategy with the Philippines Session: Infrastructure and Urbanization Improvement for Inclusive Development of Philippines: From Build Build Build to Link

More information

The Main Issues and the Game Changing Concepts of Chinese Economy

The Main Issues and the Game Changing Concepts of Chinese Economy The Main Issues and the Game Changing Concepts of Chinese Economy Syed Hasanat Associate Professor Jilin University 1 Connectivity and integration Belt and Road Initiatives Unimpeded trade Facilitate connectivity

More information

Sector(s) Public administration- Information and communications (50%), General public administration sector (50%)

Sector(s) Public administration- Information and communications (50%), General public administration sector (50%) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) IDENTIFICATION/CONCEPT STAGE Report No.: PIDC28685

More information

Port Moresby Power Grid Development Project.

Port Moresby Power Grid Development Project. Environmental Monitoring Report Semi-annual Report January 2017 Port Moresby Power Grid Development Project. Prepared by PNG Power Limited for the Asian Development Bank. This Semi-annual Environmental

More information

Telefonica in Latin America: Transforming Investment into Growth and Development The EURO: Global Implications and Relevance for Latin America

Telefonica in Latin America: Transforming Investment into Growth and Development The EURO: Global Implications and Relevance for Latin America Telefonica in Latin America: Transforming Investment into Growth and Development The EURO: Global Implications and Relevance for Latin America Maurício Giusti Strategy and Regulation Director March 18

More information

Thailand Climate Change Adaptation Information

Thailand Climate Change Adaptation Information 6 th Asia Pacific Climate Change Adaptation Forum, 5 th Parallel Session: Information infrastructure on adaptation measures and technologies, 17-19 October 2018 in Manila, Philippines Thailand Climate

More information

Supporting Data for a KfW Financed Investment Project on the Montenegrin Coast. 18 May 2017, Wien

Supporting Data for a KfW Financed Investment Project on the Montenegrin Coast. 18 May 2017, Wien Supporting Data for a KfW Financed Investment Project on the Montenegrin Coast 18 May 2017, Wien VODACOM Vodacom is a joint service and coordination company for water and wastewater services for the Montenegrin

More information

Sony Ericsson continues to invest for future growth

Sony Ericsson continues to invest for future growth PRESS RELEASE April 23, 2008 Sony Ericsson continues to invest for future growth Q1 Highlights: Year-on-year volume growth of 2% Income before taxes at higher end of forecast R&D investment continues to

More information

Domestic Private Sector Provider Initiative

Domestic Private Sector Provider Initiative Domestic Private Sector Provider Initiative Peter Roberts Global Funds Department Department for International Development, UK Unlocking the Potential of the Domestic Private Sector in Water and Sanitation

More information

Gateway Transportation Collaboration Forum. 21/01/2015 Gateway Transportation Collaboration Forum 1

Gateway Transportation Collaboration Forum. 21/01/2015 Gateway Transportation Collaboration Forum 1 Gateway Transportation Collaboration Forum 21/01/2015 Gateway Transportation Collaboration Forum 1 21/01/2015 Gateway Transportation Collaboration Forum 2 BACKGROUND AND CONTEXT 2006 Asia-Pacific Gateway

More information

Closing the Infrastructure Gap: The World Bank s contribution. Infrastructure Consortium for Africa

Closing the Infrastructure Gap: The World Bank s contribution. Infrastructure Consortium for Africa Closing the Infrastructure Gap: The World Bank s contribution Infrastructure Consortium for Africa Tokyo, March 2008 IDA-14 scale-up sustained IDA Infrastructure lending in SSA since FY00 ($M) Infrastructure

More information

Sony Ericsson reports second quarter 2010 results

Sony Ericsson reports second quarter 2010 results PRESS RELEASE July 16, 2010 Sony Ericsson reports second quarter 2010 results Q2 Highlights: Income before taxes excl. restructuring charges increases to Euro 63 million Positive cash flow generated from

More information

Memorandum of Understanding between the Central LHIN and the Toronto Central LHIN to establish a Joint ehealth Program

Memorandum of Understanding between the Central LHIN and the Toronto Central LHIN to establish a Joint ehealth Program Memorandum of Understanding between the Central LHIN and the Toronto Central LHIN to establish a Joint ehealth Program Purpose This Memorandum of Understanding (MOU) defines the terms of a joint ehealth

More information

PHILIPPINES RECOGNITION AS A PEST FREE AREA FOR MANGO PULP WEEVIL AND MANGO SEED WEEVIL MERLE PALACPAC CHIEF, NPQSD

PHILIPPINES RECOGNITION AS A PEST FREE AREA FOR MANGO PULP WEEVIL AND MANGO SEED WEEVIL MERLE PALACPAC CHIEF, NPQSD PHILIPPINES RECOGNITION AS A PEST FREE AREA FOR MANGO PULP WEEVIL AND MANGO SEED WEEVIL MERLE PALACPAC CHIEF, NPQSD STATUS OF THE PHILIPPINE MANGO INDUSTRY Mango is the 3rd most important fruit crop of

More information

UNEP Finance Initiative Regional Roundtable in Latin America 5-6 th September, 2017, Buenos Aires. Benoit Lebot, IPEEC

UNEP Finance Initiative Regional Roundtable in Latin America 5-6 th September, 2017, Buenos Aires. Benoit Lebot, IPEEC UNEP Finance Initiative Regional Roundtable in Latin America 5-6 th September, 2017, Buenos Aires Benoit Lebot, IPEEC 1 Energy Efficiency First! 2 *Source: IEA (2016) Key messages G20 Energy Efficiency

More information

Status of REDD+ Readiness in Process in Ethiopia. Eyob Tenkir National REDD+ Secretariat, Ministry of Environment and Forest

Status of REDD+ Readiness in Process in Ethiopia. Eyob Tenkir National REDD+ Secretariat, Ministry of Environment and Forest Status of REDD+ Readiness in Process in Ethiopia Eyob Tenkir National REDD+ Secretariat, Ministry of Environment and Forest Climate Resilient Green Economy (CRGE): Vision CRGE strategy to protect the country

More information

New Products & Innovation

New Products & Innovation New Products & Innovation MTAC May 20, 2015 Gary Reblin V.P., New Products & Innovation 1 2015 Promotion Calendar As of: 5/7/15 JAN FEB - MARCH APRIL MAY - JUNE JULY AUG - SEPT OCT NOV - DEC FIRST-CLASS

More information

PRESS RELEASE January 16, 2009 Sony Ericsson reports results for fourth quarter and full year 2008

PRESS RELEASE January 16, 2009 Sony Ericsson reports results for fourth quarter and full year 2008 PRESS RELEASE January 16, 2009 Sony Ericsson reports results for fourth quarter and full year 2008 Highlights: Global economic slowdown leads to contracting consumer demand Previously announced annual

More information

PRELIMINARY OPERATING RESULTS AND FACTSHEET FOR 3 MONTHS OF 2016

PRELIMINARY OPERATING RESULTS AND FACTSHEET FOR 3 MONTHS OF 2016 INVL Technology, AB company, investing in IT businesses, listed on NASDAQ Baltic stock exchange (Nasdaq Vilnius: INC1L) from June 2014. 1 INVL TECHNOLOGY RESULTS AND KEY EVENTS IN 2016 Equity of the Company

More information

Terms of Reference for the EIF Trust Fund Manager (TFM)

Terms of Reference for the EIF Trust Fund Manager (TFM) Terms of Reference for the EIF Trust Fund Manager (TFM) Introduction 1. The EIF is financed through a multi-donor trust fund (EIFTF) and contributions, whether bilateral, regional or multilateral. The

More information

City and County of Denver

City and County of Denver City and County of Denver Campaign Finance Reporting User s Manual December 11, 2012 Version 1.6 2 Table of Contents 1. The Fundamentals... 5 1.1 Campaign Finance Reporting Responsibilities... 5 2. The

More information

Bachelor of Applied Finance (Financial Planning)

Bachelor of Applied Finance (Financial Planning) Course information for Bachelor of Applied Finance (Financial Planning) Course Number HE20521 Location St George Ultimo Course Structure The structure below is the typical study pattern for a full time

More information

Enhancing LGU Capacities on Disaster Risk Reduction and Management and Climate Change Adaptation 8 th CBMS National Conference

Enhancing LGU Capacities on Disaster Risk Reduction and Management and Climate Change Adaptation 8 th CBMS National Conference Enhancing LGU Capacities on Disaster Risk Reduction and Management and Climate Change Adaptation 8 th CBMS National Conference Department of the Interior and Local Government 19 March 2012 Discussion Coverage

More information

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS

METRO SHORT RANGE TRANSIT PLAN FY Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS METRO SHORT RANGE TRANSIT PLAN FY 2010 2014 2014 Executive Summary May 2009 DIVERSIFIED TRANSPORTATION SOLUTIONS OVERVIEW Purpose of Metro SRTP Develop multi year strategic plan to improve transit quality,

More information

Progress of Regional Cooperation in the Field of Disaster Risk Reduction in Asia

Progress of Regional Cooperation in the Field of Disaster Risk Reduction in Asia Asian Conference on Disaster Reduction 2007 25-27 June 2007, Astana, Republic of Kazakhstan Progress of Regional Cooperation in the Field of Disaster Risk Reduction in Asia Going forward with Hyogo Framework

More information

BUSINESS OVERVIEW. Customer Services and Market Expansion

BUSINESS OVERVIEW. Customer Services and Market Expansion 24 China Communications Services Corporation Limited / Annual Report 2012 The Group is a leading service provider in the PRC that provides integrated support services in the informatization sector including

More information

Initiatives to Promote Overseas Infrastructure Development by MLIT

Initiatives to Promote Overseas Infrastructure Development by MLIT Initiatives to Promote Overseas Infrastructure Development by MLIT November 14, 2015 Parliamentary Vice-Minister Ministry of Land, Infrastructure, Transport and Tourism (MLIT) Kiyoshi EJIMA Overseas Infrastructure

More information

AAPA Smart Ports. Cyber Management for Ports Panel. Small Port Cyber Security Workshops. March 6, 2018

AAPA Smart Ports. Cyber Management for Ports Panel. Small Port Cyber Security Workshops. March 6, 2018 AAPA Smart Ports Cyber Management for Ports Panel Small Port Cyber Security Workshops March 6, 2018 1200 New Jersey Ave., SE Washington DC 20590 w w w. d o t. g o v Port Infrastructure Development More

More information

Project implementation plan Annual work plan for (incl. outlook to )

Project implementation plan Annual work plan for (incl. outlook to ) Building Resilience to High-Impact Hydro-meteorological Events through Strengthening Multi-Hazard Early Warning Systems in Small Island Developing States and Southeast Asia project Project implementation

More information

The Next Wave of Innovation in Canadian Infrastructure

The Next Wave of Innovation in Canadian Infrastructure The Canadian Council for Public-Private Partnerships The Next Wave of Innovation in Canadian Infrastructure Mark Romoff President and CEO 1 PNWER Economic Leadership Forum Whitehorse, Yukon November 15,

More information

Public Private Partnerships for sustainable and smart cities. Milano, 4 July 2017

Public Private Partnerships for sustainable and smart cities. Milano, 4 July 2017 Public Private Partnerships for sustainable and smart cities Milano, 4 July 2017 PPP FOR CITIES PPP FOR CITIES International Centre of Excellence The United Nations Economic Commission for Europe (UNECE)

More information

Oceansgate Plymouth University

Oceansgate Plymouth University Oceansgate Plymouth University Feb 2018 Patrick Hartop Head of City Deal patrick.hartop@plymouth.gov.uk Gareth Simmons Strategic Projects Director gareth.simmons@plymouth.gov.uk Why is this so important

More information

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works Item 7.3.5 Meeting date: August 13, 2018 Department: Prepared by: Reviewed by: SUBJECT: Engineering & Public Works COUNCIL REPORT George Elliott, P.Eng., Director of Engineering & Public Works Greg McClinchey,

More information

FY Bay Area UASI Risk and Grants Management Program Update. November 14, 2013

FY Bay Area UASI Risk and Grants Management Program Update. November 14, 2013 FY 2013-2014 Bay Area UASI Risk and Grants Management Program Update November 14, 2013 Overview FY 2013 Bay Area UASI Risk and Grants Management Program May 2013 December 2013 Data Management Analysis

More information

Pulse of The Industry Periodicals Volume PAG Initiatives. Incentives & Promotions. Open Discussion. Agenda

Pulse of The Industry Periodicals Volume PAG Initiatives. Incentives & Promotions. Open Discussion. Agenda November 19, 2014 Agenda Pulse of The Industry Periodicals Volume PAG Initiatives Incentives & Promotions 2014 Promotions Saturation & High Density Incentive Every Door Direct Mail Alternate Postage Proposed

More information

Post ECC EIA Process. Orientation/Training on the Philippine Environmental Impact Statement System (PEISS) for LGUs Davao City 28 October 2015

Post ECC EIA Process. Orientation/Training on the Philippine Environmental Impact Statement System (PEISS) for LGUs Davao City 28 October 2015 Post ECC EIA Process Orientation/Training on the Philippine Environmental Impact Statement System (PEISS) for LGUs Davao City 28 October 2015 The EIA Process and the Project Cycle Findings and recommendations

More information

BUDGET PLAN KETSANA EMERGENCY RECONSTRUCTION AND REHABILITATION PROJECT (ERRP) COVERING PROJECT PERIOD: THREE YEARS Jul-10

BUDGET PLAN KETSANA EMERGENCY RECONSTRUCTION AND REHABILITATION PROJECT (ERRP) COVERING PROJECT PERIOD: THREE YEARS Jul-10 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. GENERAL INFORMATION Country: Borrower: Project Name: Project Implementation Agency:

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-H Jun ,664,876.51

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-H Jun ,664,876.51 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021364 Public Disclosure Authorized Public Disclosure Authorized Project ID P121755 Country Afghanistan

More information

Privatization of a High Speed Rail Project - lessons learnt. T.C. Kao University of Illinois/ Research Professor Illinois, U.S.A.

Privatization of a High Speed Rail Project - lessons learnt. T.C. Kao University of Illinois/ Research Professor Illinois, U.S.A. Privatization of a High Speed Rail Project - lessons learnt T.C. Kao University of Illinois/ Research Professor Illinois, U.S.A. Why does Taiwan need High Speed Rail? Annual Increasing Rate (%) Per GDP

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2118. Date ISDS Prepared/Updated: 03/07/2006 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2118. Date ISDS Prepared/Updated: 03/07/2006 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 03/07/2006 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

China Nine Provinces and Cities Telephone Network Expansion Project (1) (2) (3)

China Nine Provinces and Cities Telephone Network Expansion Project (1) (2) (3) China Nine Provinces and Cities Telephone Network Expansion Project (1) (2) (3) 1. Project Profile and Japan's ODA Loan Report Date: October 2002 Field Survey: July 2001 Kazakhstan Kyrgyzstan Russian Federation

More information

Mexico Chiller Concessional Lending Pilot Project

Mexico Chiller Concessional Lending Pilot Project Mexico Chiller Concessional Lending Pilot Project World Bank UK Bilateral Current status: 1 st Phase completed Financial Agents Workshop, Washington D.C. 14, 15 April 2004 Project Objectives (i) Test various

More information

The UNISDR Private Sector Alliance for Disaster Resilient Societies

The UNISDR Private Sector Alliance for Disaster Resilient Societies The UNISDR Private Sector Alliance for Disaster Resilient Societies Sandra Amlang United Nations Office for Disaster Risk Reduction (UNISDR) Regional Office- the Americas. 24 August 2017 Increase in Frequency

More information

Chapter 1: Chapter Name. Disclosure Guide. eoperations ADB Disclosure Management System

Chapter 1: Chapter Name. Disclosure Guide. eoperations ADB Disclosure Management System Chapter 1: Chapter Name Disclosure Guide eoperations ADB Disclosure Management System 26 September 2016 1 Abbreviations ADB ADMS COBP CPS CSS DER EIA IEE ICM IMF IPP IPSA MFF MRM PCP PDS PI PP RCS RRP

More information

Sony Ericsson sells over 100 million handsets in 2007

Sony Ericsson sells over 100 million handsets in 2007 PRESS RELEASE January 16, 2008 Sony Ericsson sells over 100 million handsets in 2007 Q4 Highlights: 2007 Highlights: 18% increase in volume year-on-year Continued market share gains and profitable growth

More information

Indonesia Telephone Outside Plant Maintenance Center Project

Indonesia Telephone Outside Plant Maintenance Center Project Indonesia Telephone Outside Plant Maintenance Center Project Report Date: October 2002 Field Survey: July 2001 1. Project Profile and Japan s ODA loan Project Site OPMC Building Storage Maintenance Vehicle

More information