Project Features. Power Sector Improvement Project (RRP KGZ ) $ 44.8 million (62.7% grant % loan) ADF amount:

Size: px
Start display at page:

Download "Project Features. Power Sector Improvement Project (RRP KGZ ) $ 44.8 million (62.7% grant % loan) ADF amount:"

Transcription

1 Power Sector Improvement Project (RRP KGZ ) Project Concept Outline Project Features ADF amount: ADF Country allocation: ADF Regional allocation: PPTA Budget (TASF IV): Sector (subsectors): Themes: Safeguards: Gender: Board consideration: Expected physical completion: $ 44.8 million (62.7% grant % loan) $ 17.8 million $ 27.0 million US$ 225,000 (S-PPTA) Energy (electricity transmission and distribution; energy sector development) Economic Growth; Regional Cooperation and Integration; Capacity Development Environment - Category B Involuntary Resettlement - Category B Indigenous people - Category C No Gender Elements Sep 2010 Dec

2 Power Sector Sector Performance 1 General Obsolete Soviet system. Vertically integrated utility unbundled in No substantial capital investment or efficiency gains through reform. Generation 95% of energy from hydropower; low output in winter. Low efficiency thermal power; expensive imported fuel. Transmission Frequent faults Inherent bottlenecks (north south) Technical loss at 6%. 3 Distribution Distribution loss at 26% of which 40% reported to be commercial. Obsolete end-user meters; insufficient master meters. Inadequate customer database and poor billing system. Power Sector Sector Performance 2 Power Trade Largest next exporter of CAPS (2,200 gigawatt-hours ave ) Recent reduction low hydrology; less regional cooperation Tariff End-user tariff = Kyrgyz Som 70/kWh ( 1.5/kWh). Cost recovery 2.3/kWh (without considering future investments) Financial Performance All utilities have poor performance. Energy sector quasi-fiscal deficit = 4.9% of GDP (2007) 4 Governance Country fiduciary system is weak. Energy sector also has poor governance. Non-transparent flows of electricity and cash. April Event partly related to public anger towards corrupt energy sector. 2

3 Power Sector Government Strategy 1. Transparency 2. Energy efficiency (loss reduction). 3. Energy security and energy trade Decree on Transparency Initiative for Fuel and Energy Sector (July 2010) 5 Utility performance monitoring Transparent management of cash flow (including escrow account) Transparent tariff methodology Transparent competitive procurement and power trade Information disclosure Participation Impact, Outcome, Output Impact Stronger reliability of national and regional power supply. Outcome Better operational efficiency of the power companies. 6 Output 1. Automated Metering and Data Acquisition System (AMDA) linking 190 substations with control centers; Recommendation on Wholesale Electricity Transaction Settlement Mechanism 2. Substation Rehabilitation of over 50 selected substations 3. Supervisory Control and Data Acquisition System (SCADA) linking seven major substations with control centers 4. Corporate Management Capacity Building of National Electric Grid of Kyrgyzstan (NEGK) 3

4 Project Scope AMDA & Settlement Mechanism Settlement Center (proposed) Accurate, tamper-free commercial metering data (i) between power companies (ii) between neighboring countries Metering System MHC NEGK Access Router VPN Enterprise Router GGSN Brings transparency and accountability to power sector. Sets basis for improved commercial operations. Enhance regional power trade. Feeder-wise data to contribute to distribution loss reduction. Cellular Provider GPRS Interface 7 GPRS Modems in 190 NEGK substations, and EPP switchyards used for power trade APN Project Scope AMDA & Settlement Mechanism EPP LICs Export DISCOs NEGK S V O J Settlement Center (proposed) Customers 8 DISCOs = distribution companies (Jalalabadelectro, Oshelectro, Severelectro, Vostokelectro), EPP = Electric Power Plant, LICs = large industrial consumers, NEGK = National Electric Grid of Kyrgyzstan. 4

5 Project Scope Substation Rehabilitation Replacement of obsolete circuit-breakers and instrument transformers (current and voltage transformers) in over 50 selected substations. Avoidance of accidents and faults. Meeting accuracy class requirement for regional power trade. 9 Project Scope SCADA & Communications Upgrading to modern SCADA linking seven major substations with control centers. Installation of optical fiber communication. 10 Real-time data makes informed dispatching decision possible. Reduced technical losses from avoided overloading. Detection and prompt remedy of faults adds to system stability. Future development to include remote control. Optical fiber enables upgrading of protection relay system. Leasing of dark-fibers to telecom companies. 5

6 Project Scope Corporate Management Improvement Advisory service to improve financial management (e.g. introducing IFRS and corporate accounting software) Preparation of business plan Improved management practices. Loss reduction. Long-term planning and tariff petition. Transparency. 11 Implementation Schedule Project Processing Consultant Recruitment Outline Design/ Procurement Installation Board approval: Sep 2010 Contract award: Jan 2011 Contract award: Dec 2011 Commissioning: Dec Project closing: June

Environmental Monitoring Report. Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project. Semiannual Report January June 2016

Environmental Monitoring Report. Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project. Semiannual Report January June 2016 Environmental Monitoring Report Semiannual Report January June 2016 Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project Prepared by OJSC National Electric Grid of Kyrgyzstan for the Kyrgyz Republic

More information

Prepared by the Joint Stock Company National Electric Grid of Kyrgyzstan for the Kyrgyz Republic and the Asian Development Bank.

Prepared by the Joint Stock Company National Electric Grid of Kyrgyzstan for the Kyrgyz Republic and the Asian Development Bank. Environmental Monitoring Report Bi-annual Report Covering the period of January June 2015 KGZ: Power Sector Improvement Project Project Number: 43456-023 ADB Loan/Grant Number: L2671/G0218-KGZ Prepared:

More information

The strategic plan of HEDNO for the Non- Interconnected Islands Investments Smart Islands Innovation

The strategic plan of HEDNO for the Non- Interconnected Islands Investments Smart Islands Innovation The strategic plan of HEDNO for the Non- Interconnected Islands Investments Smart Islands Innovation Ioannis Margaris Vice-Chairman BoD Hellenic Electricity Distribution Network Operator (ΔΕΔΔΗΕ - HEDNO)

More information

Improved Regional Fiber Connectivity via Digital CASA: The Opportunity for Central and South Asia

Improved Regional Fiber Connectivity via Digital CASA: The Opportunity for Central and South Asia Improved Regional Fiber Connectivity via Digital CASA: The Opportunity for Central and South Asia Michael Ruddy Director of International Research Terabit Consulting PART I: THE BANDWIDTH DIVIDE International

More information

Digital Transformation of Power Delivery

Digital Transformation of Power Delivery Digital Transformation of Power Delivery Keynote Speech Professor Saifur Rahman, PhD Virginia Tech, USA IEEMA Engineer Infinite Conference, Delhi NCR, India, 14 March 2018 Traditional Electricity Delivery

More information

Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program (P096207)

Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program (P096207) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program

More information

Implementation of projects to increase energy efficiency in high-voltage power transmission systems

Implementation of projects to increase energy efficiency in high-voltage power transmission systems Implementation of projects to increase energy efficiency in high-voltage power transmission systems Sergey Katyshev JSC KEGOC 28 30 September, 2010 Astana International Energy Efficiency Forum Agenda 1.

More information

Telecom Sector Outlook and Spectrum Trading: the Case of Pakistan

Telecom Sector Outlook and Spectrum Trading: the Case of Pakistan Telecom Sector Outlook and Spectrum Trading: the Case of Pakistan Shahbaz Nasir Pakistan Telecommunication Authority ITU Workshop on Economic Aspects of Spectrum Management 21 st 23 rd November 2016 Tehran

More information

Southern California Edison. Leading the Way in Electricity TM

Southern California Edison. Leading the Way in Electricity TM Southern California Edison Leading the Way in Electricity TM Smart Metering Essentials at SCE End-Use Energy Reductions through Monitoring, Feedback, and Behavior Modification Precourt Institute for Energy

More information

TELECOM & ENERGY «Collaborating to Power the Smart Grids for Digital Growth«

TELECOM & ENERGY «Collaborating to Power the Smart Grids for Digital Growth« REPUBLIC OF ALBANIA ELECTRONIC AND POSTAL COMMUNICATIONS AUTHORITY - AKEP TELECOM & ENERGY «Collaborating to Power the Smart Grids for Digital Growth« SUMMARY What is Smart Grid Communications Networks

More information

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report.

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report. Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com November 0, 05 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

Southern Company Smart Grid

Southern Company Smart Grid Southern Company Smart Grid Smart Grid Investment Grant Update July 25, 2011 Southern Company Southern Company is one of the nations largest generators of electricity Has 4.4 million retail customers across

More information

Public Private Partnerships for sustainable and smart cities. Milano, 4 July 2017

Public Private Partnerships for sustainable and smart cities. Milano, 4 July 2017 Public Private Partnerships for sustainable and smart cities Milano, 4 July 2017 PPP FOR CITIES PPP FOR CITIES International Centre of Excellence The United Nations Economic Commission for Europe (UNECE)

More information

Integrated Resource Planning April 20, 2010

Integrated Resource Planning April 20, 2010 Integrated Resource Planning April 20, 2010 Judy Stokey, Executive Government and External Affairs Jack McGinley, Development Director, Renewables Gary Smith, Project Director-Smart Technologies Presentation

More information

DIGITAL CENTRAL ASIA SOUTH ASIA (CASA) PROGRAM. Transport and ICT Global Practice World Bank

DIGITAL CENTRAL ASIA SOUTH ASIA (CASA) PROGRAM. Transport and ICT Global Practice World Bank DIGITAL CENTRAL ASIA SOUTH ASIA (CASA) PROGRAM Rajendra Singh, Senior Regulatory Specialist ICT Sector Unit November 1 2, 2017 Sixth session of the Asia Pacific Information Superhighway (AP IS) Steering

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Network Planning for Smart Grid

Network Planning for Smart Grid Network Planning for Smart Grid UTC Telecom 2009 June 3, 2009 David Boroughs Experience you can trust. Objectives Smart Grid Architecture Overview Network Planning & Dimensioning Aspects Network Performance

More information

Evolution of Control for the Power Grid

Evolution of Control for the Power Grid Evolution of Control for the Power Grid Anjan Bose Washington State University Pullman, WA, USA PaiFest In Honor of Prof. M. A. Pai Urbana-Champaign, IL October 15, 2015 The Past (before 1960s) Hard

More information

The current state of the electrical grid And the technologies that will enable its transformation

The current state of the electrical grid And the technologies that will enable its transformation ABB POWER GRIDS The current state of the electrical grid And the technologies that will enable its transformation IEEE POWER & ENERGY SOCIETY - SUBSTATIONS COMMITTEE May 7-11 th Agenda State of the Industry

More information

North Carolina legislature. April 21, 2010

North Carolina legislature. April 21, 2010 North Carolina legislature April 21, 2010 Colman Keane, CPA EPB State of Tennessee, Fiscal Director 5 years CAFR, Statewide Indirect Cost Allocation Plan Public Accounting/ Private Industry, CFO 9 years

More information

Sector(s) Public administration- Information and communications (50%), General public administration sector (50%)

Sector(s) Public administration- Information and communications (50%), General public administration sector (50%) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) IDENTIFICATION/CONCEPT STAGE Report No.: PIDC28685

More information

Digital substations. Introduction, benefits, offerings

Digital substations. Introduction, benefits, offerings Digital substations Introduction, benefits, offerings Outline What is a digital substation? Benefits of digital substations ABB offering for digital substations Substation evolution June 26, 2017 Slide

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4802 Project Name. ECOWAS Broadband Connectivity Program Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4802 Project Name. ECOWAS Broadband Connectivity Program Region PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4802 Project Name ECOWAS Broadband Connectivity Program Region AFRICA Sector Telecommunications (60%); General information and communications

More information

DESCRIPTION OF COST ALLOCATION METHODOLOGY

DESCRIPTION OF COST ALLOCATION METHODOLOGY Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE FORMULA ) RATE PLAN FILINGS OF OKLAHOMA GAS ) GAS AND ELECTRIC COMPANY ) DOCKET NO. -0-FR PURSUANT TO APSC DOCKET ) NO. -0-U ) Direct

More information

AMI in Smart Substation Pilot Project

AMI in Smart Substation Pilot Project AMI in Smart Substation Pilot Project Knathip Spuntupong Metropolitan Electricity Authority Metering, Billing, CRM Asia 2013 22-23 May 2013 Bangkok Convention Centre at CentralWorld, Thailand Presentation

More information

Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection

Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection by: Adnan Al-Mohaisen, GM, GCCIA S. Sud, V.P., SNC-Lavalin Power

More information

AMR and SCADA in Outage Management System for MSEDCL Sangita B. Patil 1, Bapu K. Patil 2

AMR and SCADA in Outage Management System for MSEDCL Sangita B. Patil 1, Bapu K. Patil 2 e-issn: 2349-9745 p-issn: 2393-8161 Scientific Journal Impact Factor (SJIF): 1.711 International Journal of Modern Trends in Engineering and Research www.ijmter.com AMR and SCADA in Outage Management System

More information

MR. PATRICIO CHRISTIAN VALENZUELA VÁSQUEZ Mobile: SUMMARY

MR. PATRICIO CHRISTIAN VALENZUELA VÁSQUEZ Mobile: SUMMARY MR. PATRICIO CHRISTIAN VALENZUELA VÁSQUEZ Mobile: +56 78073638 pcvalenzuelav@gmail.com SUMMARY Civil Electrical Engineer graduated from the Pontifical Catholic University of Valparaiso with an MBA degree

More information

ADB s Energy Program in Myanmar

ADB s Energy Program in Myanmar ADB s Energy Program in Myanmar March 2014 Chong Chi Nai Director, Energy Division Southeast Asia Regional Department 1 Current Sector Context Low electrification ratio Need to develop cost effective way

More information

Substation SCADA Monitoring

Substation SCADA Monitoring Substation SCADA Monitoring Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Substations are a critical component

More information

The various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control

The various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control ENERGY CONTROL CENTERS To generated, Transmission and Distribution system, Number of customers and Total investment. Installed capacity in India exceeds 206 GW with annual energy generated energy exceeding

More information

ICT Policy in Japan - Broadband and Mobile -

ICT Policy in Japan - Broadband and Mobile - ICT Policy in Japan - Broadband and Mobile - April 16, 2009 Hiroyuki HISHINUMA Director for New Competition Policy Telecommunications Policy Division Telecommunications Business Department Telecommunications

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Kenya at the tipping Point?

Kenya at the tipping Point? Kenya at the tipping Point? with a special focus on the ICT revolution and Mobile Money World Bank Economic Team Presentation by Jane Kiringai Nairobi December 2, 2010 Main messages 1 2 Kenya may now be

More information

The Telecommunication infrastructure for the smart grid

The Telecommunication infrastructure for the smart grid The Telecommunication infrastructure for the smart grid Challenges for DSOs EURELECTRIC Survey intermediate results Koen Noyens, Advisor Networks Unit Brussels, 5 March 2012 1 EURELECTRIC SURVEY TELECOMMUNICATION

More information

PPP and regional infrastructure networks

PPP and regional infrastructure networks Policy Dialogue on Infrastructure Financing Strategies for Sustainable Development in North and Central Asia Tbilisi, 7-8 June 2017 PPP and regional infrastructure networks Mr Mathieu Verougstraete Economic

More information

Sapphire Wind Farm 330/33kV Substation

Sapphire Wind Farm 330/33kV Substation Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. PID7026 PID7026.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. PID7026 PID7026. PID7026.TXT Project Name Region Sector Project ID Borrower Implementing Agency Environment Category Estonia-Transport Project (@+) Europe and Central Asia Report No. PID7026 Infrastructure (Transport Sub-Sector)

More information

IFC ENERGY STORAGE MARKET REPORT

IFC ENERGY STORAGE MARKET REPORT IFC ENERGY STORAGE MARKET REPORT DEVELOPMENTS AND OPPORTUNITIES FOR ENERGY STORAGE IN EMERGING MARKETS JANUARY 9, 2016 ANISSA DEHAMNA PRINCIPAL RESEARCH ANALYST NAVIGANT RESEARCH 1 / 2016 NAVIGANT CONSULTING,

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

Challenges & Experiences in AMR Application to Support the Philippine WESM

Challenges & Experiences in AMR Application to Support the Philippine WESM Challenges & Experiences in AMR Application to Support the Philippine WESM Emmanuel M. Sotomil Sr. Dept. Manager & Head Metering Services Group National Transmission Corporation Renato B. Afurong Metering

More information

Transmission Infrastructure Investment & Development in Vietnam

Transmission Infrastructure Investment & Development in Vietnam Transmission Infrastructure Investment & Development in Vietnam Presented by: Mr. Cao Duc Dung Expert of Technical Department National Power Transmission Corporation (NPT) 28 September, 2011 1 CONTENTS

More information

EU DONOR FUNDED SMART GRID PROGRAMME

EU DONOR FUNDED SMART GRID PROGRAMME EU DONOR FUNDED SMART GRID PROGRAMME 1 Historical Background Msunduzi Local Municipality is a local municipality in Umgungundlovu District Municipality, KwaZulu-Natal, South Africa. It encompasses the

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized AFRICA Western Africa Transport & ICT Global Practice IBRD/IDA Investment Project Financing FY 2013 Seq No: 9 ARCHIVED on 29-Oct-2017 ISR29795 Implementing Agencies: Ministry

More information

in the operating segments.

in the operating segments. 9 Development of business in the operating segments. Germany. Customer development. G 27 Mobile customers. G 29 Fixed-network lines. 4, 36,568 37,5 37,492 37,936 38,625 24, 22,384 22,113 21,88 21,625 21,417

More information

International cooperation on power interconnection: Mongolian Regulatory perspective

International cooperation on power interconnection: Mongolian Regulatory perspective 4 th Northeast Asia Energy Security Forum International cooperation on power interconnection: Mongolian Regulatory perspective ENKHTUVSHIN Ganbaatar Ph.D. candidate Energy and Environmental Department,

More information

ICM Project Station Infrastructure and Equipment

ICM Project Station Infrastructure and Equipment EB 0 00 Schedule B ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B I EXECUTIVE SUMMARY. Description THESL relies on an extensive Supervisory Control and Data Acquisition

More information

Digitalization of energy systems leads to innovation, growth and jobs

Digitalization of energy systems leads to innovation, growth and jobs Digitalization of energy systems leads to innovation, growth and jobs Nikos Hatziargyriou Chairman of the Board and CEO, Hellenic Electricity Distribution Network Operator HEDNO The digital transformation

More information

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace.

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace. Power delivery Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace. Forward-thinking power grid design This evolution has

More information

GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY

GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY INTERCONNECTION PROJECT PHASE I STATUS & DEVELOPMENTS By: Adnan I. Al-Mohaisen - CEO Introduction Established in July 2001 by a Royal Decree No. M/21.

More information

Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899)

Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899) Public Disclosure Authorized Public Disclosure Authorized Implementation Status & Results Montenegro Energy Community of South East Europe APL 3 - Montenegro Project (P106899) Operation Name: Energy Community

More information

Building Efficiency as a Service

Building Efficiency as a Service Building Efficiency as a Service Based on a Managed Service Agreement Restricted Siemens Switzerland Ltd 2017 siemens.com The building efficiency imperative 41% buildings share of global emissions. CO

More information

For further information, please contact Geoff Higgins at or by at

For further information, please contact Geoff Higgins at or by  at Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com February, 06 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth

More information

Power Trade in Greater Mekong Sub-region

Power Trade in Greater Mekong Sub-region Power Trade in Greater Mekong Sub-region Priyantha Wijayatunga, PhD Principal Energy Specialist Asian Development Bank Workshop on Sustainable Development of Power Sector and Enhancement of Electricity

More information

The Clarksville Department of Electricity dba CDE Lightband. Fiscal Year 2013 Budget Presentation

The Clarksville Department of Electricity dba CDE Lightband. Fiscal Year 2013 Budget Presentation The Clarksville Department of Electricity dba CDE Lightband Fiscal Year 2013 Budget Presentation CDE Lightband Electric Division FY 2013 Proposed Budget FY 2013 12% 7% Salaries/Benefits Operating Expenses

More information

INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010

INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010 INFRASTRUCTURE PLANNING, FINANCING AND INVESTMENT 22 OCTOBER 2010 OVERVIEW OF PRESENTATION 2 LANDSCAPE CHALLENGES FUNDING SOURCES (ROLE OF FINANCIAL INSTITUTIONS) ROLE OF GOVERNMENT OBSERVATIONS SUGGESTED

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EUROPE AND CENTRAL ASIA Turkey Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 4 ARCHIVED on 02-Oct-2017 ISR29601

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PETITION OF PECO ENERGY COMPANY FOR APPROVAL OF ITS SMART METER UNIVERSAL DEPLOYMENT PLAN

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PETITION OF PECO ENERGY COMPANY FOR APPROVAL OF ITS SMART METER UNIVERSAL DEPLOYMENT PLAN PECO ENERGY COMPANY STATEMENT NO. 2 BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PETITION OF PECO ENERGY COMPANY FOR APPROVAL OF ITS SMART METER UNIVERSAL DEPLOYMENT PLAN DOCKET NO. M-2009-2123944

More information

The World Bank Central African Backbone - APL4 - Gabon (P122776)

The World Bank Central African Backbone - APL4 - Gabon (P122776) Public Disclosure Authorized AFRICA Gabon Transport & ICT Global Practice IBRD/IDA Adaptable Program Loan FY 2012 Seq No: 9 ARCHIVED on 25-Jan-2016 ISR22499 Implementing Agencies: Public Disclosure Authorized

More information

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577)

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577) Operation Name: Local Government

More information

HIGHLIGHTS +8.0% +1.6% +5.9% 1,026 beneficiaries STRONG REVENUE GROWTH OF NEW SUBSIDIARIES

HIGHLIGHTS +8.0% +1.6% +5.9% 1,026 beneficiaries STRONG REVENUE GROWTH OF NEW SUBSIDIARIES HIGHLIGHTS RETURN TO GROWTH OF OUTGOING MOBILE REVENUE IN MOROCCO THANKS TO SUCCESS WITH DATA +1.6% INCREASE OF 1.4 PT IN THE GROUP EBITDA MARGIN TO 50% STRONG REVENUE GROWTH OF NEW SUBSIDIARIES +8.0%

More information

An Introduction to Network Codes & The Links Between Codes

An Introduction to Network Codes & The Links Between Codes An Introduction to Network Codes & The Links Between Codes April 2014 About ENTSO-E 41 TSOs from 34 countries 532 million citizens served 828 GW generation 305 Thousand Km of transmission lines Ten-Year

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

Blackout 101. Dr. B. Don Russell Texas A&M University. Dr. Bruce Wollenberg University of Minnesota. Mr. John McDonald KEMA, Inc.

Blackout 101. Dr. B. Don Russell Texas A&M University. Dr. Bruce Wollenberg University of Minnesota. Mr. John McDonald KEMA, Inc. Blackout 101 Dr. B. Don Russell Texas A&M University Dr. Bruce Wollenberg University of Minnesota Mr. John McDonald KEMA, Inc. Dr. Pete Sauer University of Illinois at Urbana-Champaign An Electric Power

More information

Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India

Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India SCADA in Transmission Line Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India ABSTRACT: Transmission line equivalent circuit parameters are often 25%

More information

Silicon Valley Power:

Silicon Valley Power: Critical Facilities Roundtable Silicon Valley Power: Santa Clara s Hometown Advantage John Roukema Assistant Director Silicon Valley Power June 2, 2006 1 SVP: Santa Clara s Hometown Advantage High value

More information

SCADA Training - T&D Automation

SCADA Training - T&D Automation SCADA Training - T&D Automation Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq This course covers all the

More information

GO15 Reliable & Sustainable Power Grids

GO15 Reliable & Sustainable Power Grids Travis Rouillard Markets & Distributed Resources GE Grid Solutions GO15 Reliable & Sustainable Power Grids April 13, 2016 Corporate Enterprise February 2014 1 2040 GLOBAL POPULATION: 9 billion INCREASED

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Establishment of Regional Fiber Optic Network for *the Central Asian Countries (*Kazakhstan, Kyrgyzstan, Tajikistan, Turkmenistan, and Uzbekistan)

Establishment of Regional Fiber Optic Network for *the Central Asian Countries (*Kazakhstan, Kyrgyzstan, Tajikistan, Turkmenistan, and Uzbekistan) Establishment of Regional Fiber Optic Network for *the Central Asian Countries (*Kazakhstan, Kyrgyzstan, Tajikistan, Turkmenistan, and Uzbekistan) Mamoru Hirayama Japan Telecommunications Engineering and

More information

Port Moresby Power Grid Development Project.

Port Moresby Power Grid Development Project. Environmental Monitoring Report Semi-annual Report January 2017 Port Moresby Power Grid Development Project. Prepared by PNG Power Limited for the Asian Development Bank. This Semi-annual Environmental

More information

O2 Czech Republic. Quarterly Results January June st August 2014

O2 Czech Republic. Quarterly Results January June st August 2014 O2 Czech Republic Quarterly Results January June 2014 1 st August 2014 CAUTIONARY STATEMENT Any forward-looking statements concerning future economic and financial performance of O2 Czech Republic a.s.

More information

Reliable Monitoring Data for PV plants

Reliable Monitoring Data for PV plants Reliable Monitoring Data for PV plants Mind4Energy Mind4Energy was founded in 2011 by four enthusiastic engineers with a common idea: delivering an industrial quality data acquisition solution for monitoring

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Implementation of Online ABT monitoring System In The TATA Power Co. Ltd. Mumbai. S. G. Patki, S. C. Dhapre, S. G. Joshi, S. A.

Implementation of Online ABT monitoring System In The TATA Power Co. Ltd. Mumbai. S. G. Patki, S. C. Dhapre, S. G. Joshi, S. A. 1 Implementation of Online ABT monitoring System In The TATA Power Co. Ltd. Mumbai S. G. Patki, S. C. Dhapre, S. G. Joshi, S. A. Wangade 2 Topics Discussed Metering system between TPC & MSETCL. Need for

More information

Mergers and Acquisitions: Growth Value in Uncertain Times. Milan, June 5 th 2013

Mergers and Acquisitions: Growth Value in Uncertain Times. Milan, June 5 th 2013 Mergers and Acquisitions: Growth Value in Uncertain Times Milan, June 5 th 2013 BOCCONI CAREFIN, June 5 th 2013 1 Global Cables Reference Market World-Wide Cable Reference Market Size, 2012 2012 Global

More information

Smart Finance for Smart Buildings

Smart Finance for Smart Buildings Financing Energy Efficiency in Greece and Cyprus Smart Finance for Smart Buildings Athens, 31 May 2018 Clean Energy for All Europeans Package What are our objectives? Creating jobs & growth, bringing down

More information

Connectivity in Central Asia

Connectivity in Central Asia Connectivity in Central Asia Markets, Infrastructure, and Policy Options for Enhancing Cross Border Connectivity Michael Ruddy Director of International Research Terabit Consulting Int l Internet Bandwidth

More information

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Wendy al-mukdad, PE Utilities Engineer Grid Planning & Reliability Section, Energy Division California Public Utilities

More information

World Bank regional broadband programs and proposed Central Asian regional fiber optic network (CARFON) Juan Navas-Sabater Program Leader

World Bank regional broadband programs and proposed Central Asian regional fiber optic network (CARFON) Juan Navas-Sabater Program Leader World Bank regional broadband programs and proposed Central Asian regional fiber optic network (CARFON) Juan Navas-Sabater Program Leader June 2015 Outline World Bank Group Regional Broadband Programs:

More information

Web Page. Advertisement for SCADA System Manager post

Web Page. Advertisement for SCADA System Manager post Web Page Advertisement for SCADA System Manager post SCADA System Manager Closing Date: 9 June 2017 Job Category: Technical Job Location: Sophia, Georgetown Job Schedules: Employed --- Contents ---------------------------------------------------------------------------------------------------------------------

More information

SmartSacramento Distribution Automation

SmartSacramento Distribution Automation SmartSacramento Distribution Automation Presented by Michael Greenhalgh, Project Manager Lora Anguay, Sr. Project Manager Agenda 1. About SMUD 2. Distribution Automation Project Overview 3. Data Requirements

More information

World Bank. Regional Interconnections in South Asia. Anjum Ahmad Senior Energy Specialist World Bank, Islamabad

World Bank. Regional Interconnections in South Asia. Anjum Ahmad Senior Energy Specialist World Bank, Islamabad World Bank Regional Interconnections in South Asia Anjum Ahmad Senior Energy Specialist World Bank, Islamabad Regional integration in electricity and gas in South Asia TUTAP CASA-1000 Pakistan- India TAPI

More information

MEDIA RELEASE LIBERALISATION OF THE SERVICES SECTOR

MEDIA RELEASE LIBERALISATION OF THE SERVICES SECTOR MEDIA RELEASE LIBERALISATION OF THE SERVICES SECTOR In presenting the mini-budget for the Second Stimulus Package on 10 March 2009, I had announced that the Government will take steps to liberalise the

More information

Statistical Release Gross Domestic Product First Quarter 2012

Statistical Release Gross Domestic Product First Quarter 2012 Statistical Release Gross Domestic Product First Quarter 2012 1.0 Economic performance Provisional estimates for the first quarter of 2012 show that the economy exped by 3.5 per cent over a similar quarter

More information

AUTOMATION OF POWER DISTRIBUTION USING SCADA

AUTOMATION OF POWER DISTRIBUTION USING SCADA 1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Midwest ISO. Module B- Network Integration Transmission Service Overview. Vikram Godbole Lead, Transmission Service Planning October 20, 2010

Midwest ISO. Module B- Network Integration Transmission Service Overview. Vikram Godbole Lead, Transmission Service Planning October 20, 2010 Midwest ISO Module B- Network Integration Transmission Service Overview Vikram Godbole Lead, Transmission Service Planning October 20, 2010 DISCUSSION POINTS 1. What is NITS 2. How to get Designated NITS

More information

AIR INTELLIGENT GRID AUTOMATION

AIR INTELLIGENT GRID AUTOMATION AIR INTELLIGENT GRID AUTOMATION Felipe ROVER Tiago MORAIS Jorge AITH Elektro Brazil Elektro Brazil Elektro Brazil felipe.rover@elektro.com.br tiago.morais@elektro.com.br jorge.aith@elektro.com.br ABSTRACT

More information

16 November 2016 r. 1

16 November 2016 r. 1 16 November 2016 r. 1 Grounds for updating the ENERGA Group s Strategy The electricity market is undergoing RAPID CHANGE Retaining its position will call for aligning the model to changes as they take

More information

Advanced Two-Way Metering. Looking Forward

Advanced Two-Way Metering. Looking Forward Advanced Two-Way Metering Looking Forward June 5 2017 Seeking board guidance today Beginning Detailed Technical Design & Request For Proposal Include Opt-Out & Opt-Up Alternatives Through the RFP Chelan

More information

DUKE ENERGY OHIO SMART GRID / GRID MODERNIZATION. Don Schneider GM, Smart Grid Field Deployment May 24, 2012

DUKE ENERGY OHIO SMART GRID / GRID MODERNIZATION. Don Schneider GM, Smart Grid Field Deployment May 24, 2012 DUKE ENERGY OHIO SMART GRID / GRID MODERNIZATION Don Schneider GM, Smart Grid Field Deployment May 24, 2012 FACTS ABOUT DUKE ENERGY 150+ years of service 4 million customers Fortune 500 $50 billion in

More information

UNITED INTERNET AG. 6-Month Frankfurt/Main, August 13, 2018

UNITED INTERNET AG. 6-Month Frankfurt/Main, August 13, 2018 UNITED INTERNET AG 6-Month 2018 Frankfurt/Main, August 13, 2018 1 H1 2018 Frankfurt/Main, August 13, 2018 AGENDA Ralph Dommermuth Company development Outlook Frank Krause Results H1 2018 2 H1 2018 Frankfurt/Main,

More information

CYBERSECURITY INITIATIVES IN VANUATU

CYBERSECURITY INITIATIVES IN VANUATU CYBERSECURITY INITIATIVES IN VANUATU OUTLINE COUNTRY OVERVIEW TELECOMMUNICATIONS/ICT SECTOR REFORM PROGRAM MODERN BUSINESS ENABLING ENVIRONMENT POLICIES RELATING TO TELECOMMS POLICIES RELATING TO ICT LESSONS

More information

Agenda for the Day Morning: Afternoon:

Agenda for the Day Morning: Afternoon: Agenda for the Day Morning: Overview of Internet economic building blocks Afternoon: How to translate Internet growth into overall economic growth, follow-up on issues of interest, Q&A TunIXP Workshop

More information

CHAPTER 13 ELECTRONIC COMMERCE

CHAPTER 13 ELECTRONIC COMMERCE CHAPTER 13 ELECTRONIC COMMERCE Article 13.1: Definitions For the purposes of this Chapter: computing facilities means computer servers and storage devices for processing or storing information for commercial

More information

To: Honorable Public Utilities Board Submitted by: From: Diosdado Hernandez, P. E. Approved by:

To: Honorable Public Utilities Board Submitted by: From: Diosdado Hernandez, P. E. Approved by: AGENDA ITEM NO.: 4.F.1 ADMINISTRATIVE REPORT NO.: 2018-50 To: Honorable Public Utilities Board Submitted by: /S/ Andre Basler AGM Engineering and Operations From: Diosdado Hernandez, P. E. Approved by:

More information

INOGATE Technical Secretariat Key Expert 2: Nikos Tsakalidis Electricity & Gas Activities Tashkent, January 2014

INOGATE Technical Secretariat Key Expert 2: Nikos Tsakalidis Electricity & Gas Activities Tashkent, January 2014 INOGATE Technical Secretariat Key Expert 2: Nikos Tsakalidis Electricity & Gas Activities Tashkent, January 2014 BUILDING PARTNERSHIPS FOR ENERGY SECURITY www.inogate.org REGIONAL ACTIVITIES SPECIFIC ASSISTANCE

More information

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region

Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region Call for Papers GCC POWER 2011 GCC Cigre s Leading Electric Power Conference & Exhibition In the Gulf Region Kuwait - November 2011 GCC Cigre, is pleased to announce its 7 th International Conference GCC

More information