Generation Interconnection Feasibility Study Report
|
|
- Charity Welch
- 5 years ago
- Views:
Transcription
1 Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning
2 TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study Parameters... 6 Steady-State Power Flow Analysis... 6 Fault Duty Analysis... 7 Conclusions... 8 Required Mitigation... 8 Next Steps... 8 Appendix: One-Line Drawing
3 Executive Summary NorthWestern Energy (NWE) has completed the Feasibility Study for Project 169 near the Yellowtail Substation in southeast Montana. NWE studied this project as a small generation energy resource (ERIS). The results of the Feasibility Study confirm that the addition of 10 MW interconnected to the NWE 230 kv Yellowtail-Steamplant 230 kv transmission line, approximately 0.5 miles north of PacifiCorp s Yellowtail substation, is feasible under normal operating conditions (i.e., all lines in service) without any additional network upgrades beyond the facilities needed for interconnection. The findings included in this study do not assure the Interconnection Customer (Customer) that the planned facility will be allowed to operate at full capacity under all operating conditions. Generation curtailment may be required under certain outage conditions. More detailed studies may reveal other operating constraints not seen in the Feasibility Study. The feasibility study identified no adverse impacts due to the Generation Project under normal operating conditions. Since the Customer did not specify either an exact point of interconnection (POI) or a specific turbine, NWE used professional engineering judgment to model this interconnection request. In the interconnection request, the Customer states, Yellowtail substation is approximately 1.25 miles from the proposed project site. NWE does not own the Yellowtail substation or the nearby Big Horn substation and, as a result, the study could not use either substation as the point of interconnection (POI). NWE owns the 230 kv line between Yellowtail and the Billings Steam Plant, therefore, the project tap was assumed on that line near the proposed project site. NWE modeled the Customer s point of interconnection as a new substation approximately a half mile north of the Yellowtail substation on NWE s 230 kv transmission line. Because the request entails a new substation on a 230 kv line, there will be a need for redundant communications as well as a temporary bypass (shoefly) line to keep the 230 kv line in service. The 230 kv line of interest is on a major transmission path, as defined by the Western Electricity Coordinating Council, and the temporary bypass allows NWE to maintain flows on that line during the construction of the substation. Once construction of the substation has been completed, the temporary bypass will be removed. The Customer did not specify a turbine, therefore, this report will not address the results of fault duty analysis. The Customer will be required to select a turbine and point of interconnection before the System Impact Study (SIS) can begin. The SIS is a detailed technical analysis, and the fault duty will be addressed in this study. 3
4 A high level, non-binding cost estimate to interconnect the Generation Project is summarized in Table I. Table 1: High Level Non Binding Estimate of Interconnection Costs Department Estimate Notes Transmission $750,000 Includes the construction and removal of the temporary 230 kv bypass. Substation $2,270,000 New substation on 230 kv line. Lands/Permitting $43,900 Estimate depends on substation location (private or public land). Environmental issues cannot be addressed until specific POI has been selected. Relay $400,000 System protection. Communications $15,000 NWE will install and lease a satellite connection. The Customer must arrange for the circuits. Ongoing monthly costs are estimated at $130/month; this provides a connection from EMS to a supervisory at the substation. Metering $14,000 EMS $12,000 Generation modeling/licensing, and system scada point licensing Total $3,504,900 4
5 Generator and Interconnection Data The proposed generator and interconnection data used in the studies was based on the information received from the Interconnection Customer. From the initial application, NWE identified the following project information. Project Name Project 169 Size (Rated) 10 MW total Location near Fort Smith, MT Special Resources/Technology -- Unspecified Proposed Commercial Operation Date 2017 Facilities NWE 230 kv substation approximately one half mile north of the Yellowtail substation on the 230 kv Yellowtail-Steamplant line. Assumptions o MW Output = 10 MW o Scheduled Voltage (p.u.) = 1.00 at the Point of Interconnection o The generator was modeled to have operational characteristics of 0.95 leading to 0.95 lagging power factor ranges. 5
6 Study Parameters In analyzing the Generation Project, NWE utilized PSS/E software to conduct the Feasibility Study for the proposed Generation Project. These studies simulated the connection of the Generation Project to NWE s Transmission System in a computer model to study the interaction of the Generation Project with other resources and loads. All studies were conducted through a steady state power-flow analysis only. Two WECC base cases adjusted to include the NWE Transmission System detail representing 2014 light summer and 2014 heavy summer load profiles were used for this study. Steady-State Power Flow Analysis A review of the impact to the local area was conducted for this feasibility study. The local area impact study examined system normal operating conditions with all lines in service (i.e., N-0 conditions) as well as a limited number of critical local area single line outages (i.e., N-1 conditions). Power-flow simulations were done and a search of the study results for unacceptable thermal overload and voltage excursion was made for each power-flow study. Based on the study work, the following text summarizes those results. The addition of this project to NWE s Transmission System under N-0 conditions causes no adverse effects. The addition of this project to NWE s Transmission System under N-1 conditions does not cause any voltage or thermal violations. No system mitigation is required at this time. 6
7 Fault Duty Analysis When a fault occurs on a power line, protective relaying equipment detects the fault current flowing and signals associated circuit breakers to open. When the circuit breakers open they must be capable of interrupting the fault current. If the magnitude of fault current exceeds the interrupt rating of the circuit breakers, the fault may not be cleared, and damage to system equipment and voltage collapse may result. Because the Customer did not provide a specific turbine, NWE is unable to conduct a Fault Duty Analysis in the Feasibility Study. The Customer will be required to specify a turbine for the System Impact Study where the Fault Duty Analysis for this project will be conducted. 7
8 Conclusions The results of this analysis confirm that the addition of 10 MW of generation interconnected to the NWE 230 kv transmission system in the Yellowtail-Steamplant 230 kv segment approximately 0.5 miles north of the Yellowtail substation, is feasible under normal operating conditions without any additional network upgrades beyond those necessary for interconnection. At this time, no system upgrades beyond the facilities required for interconnection are needed in order to interconnect the full output of the Generation Project under system normal operating conditions. Required Mitigation Since the generation project caused no adverse effects, no mitigation is required at this time for interconnection of the generation project. Curtailment of the project may be required under certain outage conditions. The findings included in this study do not assure the Interconnection Customer that the planned facility will be allowed to operate at full capacity under all operating conditions. Further and more detailed studies may reveal other operating constraints not revealed in the Feasibility Study. Next Steps NWE will be scheduling a meeting to discuss the findings of the Feasibility Study with the Interconnection Customer. If, after the meeting, the Interconnection Customer wishes to continue with the project, a System Impact Study specific to the project will be required to further determine the requirement for the interconnection. The System Impact Study is a much more detailed study that includes transient stability, fault duty, post transient, and comprehensive outage studies (i.e., N-1 and N-2) and will require identification of generator turbine type and point of interconnection. It is possible that the System Impact Study could identify concerns which may require mitigation in order to interconnect the Generation Project. This study does not constitute a request for transmission service. The study examined the physics of the electrical system and does not imply that the Customer will receive any transmission required to deliver the generation output to load. The Customer must follow the procedures described in the transmission tariff available on ( to request and/or receive transmission service. 8
9 Appendix: One-Line Drawing Figure 1: One-Line Drawing of Interconnection Project
Generation Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationFeasibility Study on Load Flow and Short Circuit Project
Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationTECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM
TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM Version 1.2 May 28, 2009 Transmission Planning Department Revisions Rev. No. Date Description By Approval 1.0 8/10/06
More informationGeneration, Transmission, and End User Facilities
Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3
More informationSystem Impact Study for Power Supply 400 MW Import on the EAL BCHA Path
System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationGeneration Interconnection Impact Study Report. For. Interconnection Customer Q0022
Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationInterconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study
Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities Non-Tariff System Impact Study March 204 Prepared by: Utility System Efficiencies, Inc (USE) Under Contract with:
More informationQ44 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,
More informationGrid Interconnection of Renewable Generation
Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection
More informationISO New England Data Modeling Requirements
A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationFacilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study
Facilities Study for the Mora Line Transmission Project Non-Tariff Facilities Study November 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for
More informationInterconnection and Transmission
Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationReal Time Monitoring of
Real Time Monitoring of Cascading Events Mladen Kezunovic Nan Zhang, Hongbiao Song Texas A&M University Tele-Seminar, March 28, 2006 Project Reports (S-19) M. Kezunovic, H. Song and N. Zhang, Detection,
More informationSE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality,
SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality, integrity, and innovation. Our mission is to offer the safest,
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationNERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010
Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationSub Regional RTEP Committee Mid-Atlantic First Energy MAAC
Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC September 21, 2018 Penelec Transmission Zone Need Number: PN-2018-001 Consider upgrading transmission line equipment (switches, conductor, splices,
More informationChapter 2 State Estimation and Visualization
Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation
More informationEvolution of Control for the Power Grid
Evolution of Control for the Power Grid Anjan Bose Washington State University Pullman, WA, USA PaiFest In Honor of Prof. M. A. Pai Urbana-Champaign, IL October 15, 2015 The Past (before 1960s) Hard
More informationAPPENDIX B-2. TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES. and SMALL GENERATION FACILITIES
APPENDIX B-2 TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES and SMALL GENERATION FACILITIES Revision: 4.0 12/30/2011 Page 1 of 39 TABLE OF CONTENTS DEFINITIONS A. Scope 1. Ownership 2.
More information1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.
MISO Investigation Report on the NERC TLR Level 5 Event North Platte Stockville 115kV for the loss of the Gentleman Red Willow 345kV Flowgate 6023 August 22 nd / 23 rd, 2002 Report issued: September 3
More informationITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems
ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017
More informationIntroduction to Generation Availability Data System (GADS) Wind Reporting
Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationPacifiCorp Transmission Technical Workshop
PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt
More informationDominion Supplemental Projects
Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationLocal Area Studies Update - PACW Kevin Putnam
Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton
More informationHigh-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY
S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are
More informationAPPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS. for GENERATION & INTERCONNECTION FACILITIES
APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS for GENERATION & INTERCONNECTION FACILITIES Revision: 4.0 12/28/2011 Page 1 of 40 DEFINITIONS TABLE OF CONTENTS A. Scope 1. Generation Connection and Operating
More informationLC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update
October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More information2009 SPP TransCanada Pipeline Study Report
2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table
More informationFacility Connection Requirements
SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...
More informationSmall Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662
Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately
More informationWECC Criterion MOD-(11 and 13)-WECC-CRT-1.1
WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements
More informationSPP RTO Compliance Forum Western Area Power Administration March 11, 2015
SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 Mark Buchholz WAPA Upper Great Plains Region Compliance Manager What is Western? One of four Power Marketing Administration within
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More informationCOGENERATION INTERCONNECTION REQUIREMENTS. Parallel Operation of Connecting Parties Generation
COGENERATION INTERCONNECTION REQUIREMENTS Parallel Operation of Connecting Parties Generation Cogeneration Interconnection Requirements (ID 195440).docx 1 (This page left blank intentionally) Cogeneration
More informationThe various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control
ENERGY CONTROL CENTERS To generated, Transmission and Distribution system, Number of customers and Total investment. Installed capacity in India exceeds 206 GW with annual energy generated energy exceeding
More informationReal-time Power System Operation. Energy Management Systems. Introduction
1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationStudies Overview and Data Requirements. Robert Pan
Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application
More informationNETWORK INTEGRATION TRANSMISSION SERVICE. Preamble
Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to
More informationSupplemental Information
Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationIMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS
IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage
More informationFor the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)
Electrical Company: PacifiCorp For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Designated Contact Person: Robin Moore Address
More informationATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service
Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network
More informationWestern Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document
Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System
More informationRFP Attachment 13. January 2010
PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt
More informationSECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE
SECTION 16262 - APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE PART 1 - GENERAL 1.01 RELATED SECTIONS A. Section 01300 Submittals B. Section 16262 Static Frequency Converter C. Section 16262A Appendix A SFC
More informationAUTOMATION OF POWER DISTRIBUTION USING SCADA
1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from
More informationLC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update
January 7, 2019 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission
More informationPOWER SYSTEM SECURITY CONCEPTS
POWER SYSTEM SECURITY CONCEPTS 1.1 INTRODUCTION The Power System needs to be operationally secure, i.e. with minimal probability of blackout and equipment damage. An important component of power system
More informationJEA. Facility Connection Requirements
JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities
More informationTransWest Express Transmission Project Interregional Transmission Project Submittal
TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March
More informationOrder No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015
Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee
More informationTENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT
TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN >>> TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN Tengiz is one of the largest oil fields in the world, and is located in western
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved
More informationSouthern Company Smart Grid
Southern Company Smart Grid Smart Grid Investment Grant Update July 25, 2011 Southern Company Southern Company is one of the nations largest generators of electricity Has 4.4 million retail customers across
More informationIowa State University
Iowa State University Cyber Security Smart Grid Testbed Senior Design, Final Report Dec 13-11 Derek Reiser Jared Pixley Rick Sutton Faculty Advisor: Professor Manimaran Govindarasu 1 Table of Contents
More informationLoad Management of Industrial Facilities Electrical System Using Intelligent Supervision, Control and Monitoring Systems
Load Management of Industrial Facilities Electrical Using Intelligent Supervision, and Monitoring s Selahattin Kucuk TÜPRAŞ İzmit Refinery selahattin.kucuk@tupras.com.tr Fahrettin Arslan Istanbul University
More informationSmart Grid Operations - Combining the Power of Smart Meters and The Control Room ADMS
Smart Grid Operations - Combining the Power of Smart Meters and The Control Room ADMS United Energy case study Andrew Steer Manager - Network Control Centre Support United Energy Bradley Williams, P.E.
More informationPublic Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM
Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities
More informationFeeder Hosting Capacity and Impacts of Distribution Connected Generation. NGN Tutorial. Prepared for GOTF October 22, 2017
Feeder Hosting Capacity and Impacts of Distribution Connected Generation NGN Tutorial Matthew Rylander, PhD Technical Leader Power System Studies Electric Power Research Institute mrylander@epri.com Prepared
More informationWN U-60 Original Sheet No. 152
WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H
More informationMemorandum. This memorandum requires Committee action.
California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure
More informationN-1-1 Reactive Upgrades
N-1-1 Reactive Upgrades Previous Analysis Discussed at November 2011 TEAC Voltage collapse for multiple 500 kv N-1-1 contingency pairs A number of reactive upgrade locations evaluated to determine a optimal
More informationSMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2
SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:
More informationLarge Embedded Generators Register of Completed Projects
Large Embedded Generators Register of Completed Projects This document contains a description of the completed projects relating to the connection of Large Embedded Generators to the TasNetworks distribution
More informationLevel 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW
Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &
More informationUnused Generation Capacity Study Scope. Informational Analysis
Unused Generation Capacity Study Scope Informational Analysis MISO Jan 9, 2014 Table of Contents 1.0 Project Overview... 3 2.0 Scope of Work... 4 2.1 Phase 1 - Preliminary Analysis... 5 2.2 Phase 2 System
More informationOrder No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process
Order No. 1000 Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Thinh Nguyen Manager, Interconnection Projects New York Independent System Operator Joint
More informationLCRA Transmission Services Corporation. Facility Connection Requirements
LCRA Transmission Services Corporation Facility Connection Requirements April 2017 Table of Contents 1.0 INTRODUCTION... 3 2.0 Facility Connection Requirements... 3 2.1 Summary of Basic Interconnection
More informationLessons Learned Implementing an IEC based Microgrid Power- Management System. K.A. GRAY, J.J. MRAZ* POWER Engineers, Inc.
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Lessons Learned Implementing an IEC 61850-based Microgrid Power- Management System K.A.
More informationLCRA Transmission Services Corporation. Facility Connection Requirements
LCRA Transmission Services Corporation Facility Connection Requirements May 2018 Table of Contents 1.0 INTRODUCTION... 3 2.0 Facility Connection Requirements... 3 2.1 Summary of Basic Interconnection Requirements...
More informationSMALL GENERATOR INTERCONNECTION REQUEST (Application Form)
SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: _Cleco Power LLC Designated Contact Person: Cindy Guillot Address: P.O Box 70, (2180 St. Landry Hwy) St. Landry, LA 71367
More informationMONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS
MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS Table of Contents I. Introduction... 5 A. Authority... 5 B. Objectives... 5 C. Interconnection
More informationB O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Self-Monitoring:
More informationCollector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co.
Collector System Design Considerations for Wind Farms Sean Carr Ernst Camm S&C Electric Co. 1 Overview Challenges in wind farm collector systems Design considerations for collector systems Summary The
More informationQuantum Chargers Enhanced AC Line Transient Immunity
Introduction Quantum Chargers Enhanced AC Line Transient Immunity By: Nasser Kutkut, PhD, DBA Advanced Charging Technologies Inc. This white paper outlines the most common AC power quality disturbances
More informationGlencoe Light and Power
Glencoe Light and Power REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS 1 Table of Contents Page I. INTRODUCTION...5 A. Authority... 5 B. Objectives...5 C. Interconnection
More informationRationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays
Rationale for the Use of Local and Remote (Zone 3) Protective Relaying Backup Systems A Report On The Implications And Uses Of Zone 3 Relays Prepared by the System Protection and Control Task Force of
More informationWestern Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document
Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System
More information