Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Size: px
Start display at page:

Download "Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281"

Transcription

1 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc.

2 PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection request on the reliability of the Progress Energy Carolina, Inc. (PEC) transmission system with respect to power-flow, short circuit and stability issues. The CUSTOMER requested that the proposed project be considered and studied as a Network Resource Interconnection. Estimates of the cost and time required to interconnect the generation as well as to resolve the issued identified in this impact analysis are also included. The PEC internal system analysis consists of an evaluation of the internal PEC transmission system utilizing documented transmission planning criteria. The request is described in Table 1 below. Table 1: Request PEC Generator Interconnection Queue No. MW In-Service Date Queue # /31/14 County Pamlico County, NC Facility Bayboro 230 kv Substation The 200 MW total is comprised of 111 individual 1.8 MW wind turbine generators. Interconnection to PEC s substation is via a 34.5 kv collector system and a 34.5/230 kv transformer. ASSUMPTIONS The following impact study results are from the PEC internal power-flow models that reflect specific conditions of the PEC system at points in time consistent with the generator interconnection requests being evaluated. The cases include the most recent information for load, generation additions, transmission additions, interchange, and other pertinent data necessary for analysis. Future years may include transmission, generation, and interchange modifications that are not budgeted and for which no firm commitments have been made. Further, PEC retains the right to make modifications to power-flow cases as needed if additional information is available or if specific scenarios necessitate changes. For the systems surrounding PEC, data is based on the ERAG MMWG model. The suitability of the model for use by others is the sole responsibility of the user. Higher queued generator interconnection requests were considered in this analysis. Specifically, Q#277, a 900 MW block of offshore wind generation was assumed to be connected at Morehead Wildwood 230 kv substation in 2017, along with transmission upgrades identified in the Q#277 impact study dated January 6, 2011, but is no longer included since Q#277 has now been withdrawn. The results of this analysis are based on Interconnection Customer s queue requests including generation equipment data provided. If the facilities technical data or interconnection points to the transmission system change, the results of this analysis may need to be reevaluated. This study was based on the following assumptions: CUSTOMER would have one interconnection point to PEC s Bayboro 230 kv Substation off the Aurora - New Bern 230 kv Line. CUSTOMER would construct, own and operate the electrical infrastructure that would connect their generation to the PEC s existing Bayboro 230 kv substation, - 2 -

3 RESULTS including any step up transformers and lines from the wind farm, but excluding the 230 kv circuit breaker in the Bayboro 230 kv substation. Higher queued request (Q#277) had been assumed to come on-line in 2017, but has subsequently been withdrawn. Power-flow Analysis Results (Network Resource Interconnection) Facilities that may require upgrade within the first three to five years following the in-service date are identified. Based on projected load growth on the PEC transmission system, facilities of concern are those with post-contingency loadings of 95% or greater of their thermal rating or low voltage of 0.92 pu and below, for the requested in-service year or the in-service year of a higher queued request. The identification of these facilities is crucial due to the construction lead times necessary for certain system upgrades. This process will ensure that appropriate focus is given to these problem areas to investigate whether construction of upgrade projects is achievable to accommodate the requested interconnection service. As requested, the 200 MW wind farm was studied interconnected to PEC s Bayboro 230 kv substation. Contingency analysis study results show that interconnection of this generation facility results in the following thermal issues on the PEC system. Based on study results for 2014, Table 2 shows thermal facility loadings for this request: Table 2: Power-flow Thermal Results Transmission Facility Loading % Contingency Bayboro 230 kv Tap 121% Base Case Additionally, it will be necessary to install a transfer trip protection scheme to separate this generation facility from the PEC system for faults on the Aurora -New Bern 230 kv line. Estimate of Resolutions for Power-flow Impacts The following are PEC s current best estimates for resolution of impacts identified in Table 2 and the addition of transfer trip protection. Solutions, cost estimates and implementation schedules will be refined in the Customer s Generator Interconnection Facility Study Report. The Wave Trap on the Bayboro Tap limits the existing rating to 400 amps. The existing Wave Trap in the tap will be removed and a Wave Trap will be added at Grantsboro POD and Bayboro 230 kv substation. Facility Upgrades Required in 2014 Bayboro 230 k V Tap (Two(2) New Wave Traps) Potential Solution: Install One (1) 230 kv Wave Trap at Tideland EMC Grantsboro POD and One(1) 230 kv Wave Trap at Bayboro 230 kv substation. See Figure

4 Distance: N/A Estimated Cost: $200,000 Estimated Schedule: 10/31/2014 Bayboro, New Bern and Aurora 230 kv Substations (Install Transfer Trip Scheme) Potential Solution: Install protection system and transfer trip for coordination between the Aurora-New Bern 230 kv line and proposed generation facility. See Figure 1. Distance: N/A Estimated Cost: $100,000 Estimated Schedule: 10/31/2014 Total Power-flow Cost Estimate: $300,000 (total) Stability Analysis Results A stability analysis was performed to determine the impact of the proposed generation addition on the PEC transmission system and other nearby generation. The proposed 200 MW wind farm generation is comprised of 111 Vestas V100, 1.8 MW wind turbine generators. The wind turbine collector branches are connected to a single 34.5 kv collector bus and a single 34.5/230 kv step-up transformer. For the dynamics analysis, all wind turbines and collector branches were represented by one lumped equivalent including a generator, a step-up transformer, and a collector system impedance. The interconnection of the equivalent wind farm system to PEC s Bayboro 230 kv substation is via one 34.5/230 kv transformer and one short (less than 500 feet) 230 kv line, each modeled explicitly. These wind machines were modeled using the Customer supplied Vestas Generic PSS/E Model Version 7.2 and Customer supplied model parameters, including those for the voltage and frequency protection settings. The collector system configuration and impedances were also provided by the Customer. A number of normally clearing and delayed clearing faults were simulated to assess the stability and voltage ride-through capabilities of the proposed wind generation. Both summer peak and off-peak conditions were simulated for each fault. The proposed wind farm generation was stable with acceptable voltage ride-through for all faults simulated. No adverse impact to other area generation was noted as a result of the proposed wind farm. If the Customer provided data changes from that provided, these results will need to be reevaluated. LGIP Power Factor Requirements PEC s Large Generator Interconnection Procedure (LGIP) requires the proposed generating units to be capable of delivering the power to the point of interconnection (POI) at a 0.95 lagging power factor. The POI is the Bayboro 230 kv substation. The Customer provided data indicates a wind farm total capacity of 200 MW. Since the wind generators themselves - 4 -

5 may not be capable of supplying an appreciable amount of MVARs, a separate dynamic var source, such as a static var compensator or similar FACTS device, may need to be installed by the Customer to meet this requirement. As additional design plans and details becomes available, PEC will work with the Customer to determine the adequacy of the wind generators themselves to provide the required dynamic var capability requirements at the point of interconnection. Estimate to Meet LGIP Power Factor Requirements The majority of the costs to meet the LGIP Power Factor requirement will be associated with the design and installation of Customer owned equipment. Since these costs will be incurred by the Customer, they are not included in this estimate. Short Circuit Analysis Results A short circuit analysis was performed to assess the impact of the proposed wind farm generation addition on transmission system equipment capabilities. The analysis conservatively modeled the proposed wind generation as an equivalent amount of classical generating units for short circuit purposes. The analysis indicates that no short circuit equipment capabilities will be exceeded as result from the proposed generation addition and associated transmission upgrades. The results of the short circuit study are based on Customer provided generation equipment data and location. Also, the prudent use of engineering assumptions and typical values for some data were used. If the units technical data or interconnection points to the transmission system changes, the results of this analysis may need to be reevaluated. Interconnection of Customer s Generation The point of interconnection (POI) for Queue #281 is at PEC s Bayboro 230 kv substation. See Figure 1. The costs of expanding the Bayboro 230 kv substation to install a new 230 kv circuit breaker and associated equipment, including protection system, are summarized below. Estimated Costs: $1, 200, 000 Estimated Schedule: 10/31/2014 Also, the customer should verify that the MVA ratings of their lines are sufficient to accommodate delivering the total wind farm MVA output to the point of interconnection at the required 0.95 power factor. SUMMARY This Generator Interconnection Impact Study assesses the impact of interconnecting a new generation facility consisting with a total NET summer/winter rating of 200 MW. Studies - 5 -

6 indicate that thermal and interconnection upgrades are necessary to the PEC Transmission System to accommodate this queue request. Current estimates are that the proposed upgrades can be completed to meet the Customer s schedule. This is based on an assumption that PEC would have a firm commitment from the customer no later than 24 months in advance of the request in-service date. The additional cost for telecommunications and metering can be estimated as a monthly charge of $3,000/month. Network Resource Interconnection Estimate Cost: Power-flow (2014) $300, 000 Stability $0 Short Circuit $0 Power Factor * $0 Interconnection (2014) $1, 200,000 Total Estimate $1, 500,000 *Not including any cost the for Customer installed/owned equipment (such as a static var compensator) that may be required to meet the Power Factor requirement

7 -Figure

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

ISO New England Data Modeling Requirements

ISO New England Data Modeling Requirements A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662 Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately

More information

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models Problem Statement With the proliferation of distributed energy resources (DER), Transmission Planners must adapt

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013 Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

Minnesota Hosting Capacity Analysis

Minnesota Hosting Capacity Analysis Minnesota Hosting Capacity Analysis MIPSYCON November 8, 2017 Chris Punt, P.E. Outline What is Hosting Capacity? Background DRIVE Results Visualization Accuracy Timeline Next Steps 2 What is Hosting Capacity?

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Dominion Supplemental Projects

Dominion Supplemental Projects Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer

More information

Real Time Digital Simulator Testing of an On Line Integrated Stability Control System

Real Time Digital Simulator Testing of an On Line Integrated Stability Control System Real Time Digital Simulator Testing of an On Line Integrated Stability Control System R.P. Wierckx, M. Kawasaki, N. Saito, K. Anzai, S.C. Verma Abstract The paper describes the testing of an on line integrated

More information

Unused Generation Capacity Study Scope. Informational Analysis

Unused Generation Capacity Study Scope. Informational Analysis Unused Generation Capacity Study Scope Informational Analysis MISO Jan 9, 2014 Table of Contents 1.0 Project Overview... 3 2.0 Scope of Work... 4 2.1 Phase 1 - Preliminary Analysis... 5 2.2 Phase 2 System

More information

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC September 21, 2018 Penelec Transmission Zone Need Number: PN-2018-001 Consider upgrading transmission line equipment (switches, conductor, splices,

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

FACTS and HVDC for Grid Connection of Large Wind Farms

FACTS and HVDC for Grid Connection of Large Wind Farms David Larsson Power-Gen Europe 2005 Milan, Italy FACTS and HVDC for Grid Connection of Large Wind Farms www.abb.com/facts FACTS Agenda Wind Generators Response to Grid Faults PICTURE JPG-FORMAT WEB OPTIMIZED

More information

Real-time Power System Operation. Energy Management Systems. Introduction

Real-time Power System Operation. Energy Management Systems. Introduction 1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY PURPOSE: The purpose of this lab is to introduce PSS/E. This lab will introduce the following aspects of PSS/E: Introduction to

More information

JEA. Facility Connection Requirements

JEA. Facility Connection Requirements JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1 Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms May 22, 2009 Slide 1 FACTS Applications Flexible AC Transmission Systems May 22, 2009 Slide 4 System Studies - Grid Codes

More information

USE CASE 14 CONTROLLED ISLANDING

USE CASE 14 CONTROLLED ISLANDING I USE CASE 14 CONTROLLED ISLANDING Use Case Title Centralized application separates grid into islands to prevent blackout Use Case Summary Controlled islanding is a method that can significantly improve

More information

Facility Connection Requirements

Facility Connection Requirements SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Large Embedded Generators Register of Completed Projects

Large Embedded Generators Register of Completed Projects Large Embedded Generators Register of Completed Projects This document contains a description of the completed projects relating to the connection of Large Embedded Generators to the TasNetworks distribution

More information

Year Assessment Preliminary Needs

Year Assessment Preliminary Needs 2018 10-Year Assessment Preliminary Needs Stakeholder and Customer Presentation March 1, 2018 Jeremy Voigt Purpose Key Study Assumptions Reminder Summarize Preliminary Changes to Needs Solicit Input on

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)

For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Electrical Company: PacifiCorp For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Designated Contact Person: Robin Moore Address

More information

N-1-1 Reactive Upgrades

N-1-1 Reactive Upgrades N-1-1 Reactive Upgrades Previous Analysis Discussed at November 2011 TEAC Voltage collapse for multiple 500 kv N-1-1 contingency pairs A number of reactive upgrade locations evaluated to determine a optimal

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

LAB6 ADDITION OF GENERATION EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

LAB6 ADDITION OF GENERATION EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY LAB6 ADDITION OF GENERATION EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY PURPOSE: The purpose of this lab is to introduce a wind farm into a base case and analyze the effects using PSS/E. Introduction

More information

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

Smart Distribution Technology

Smart Distribution Technology Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications

More information

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc.

Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation. Consolidated Edison Company of New York, Inc. Fault Current Margin Queuing Position Process for Parallel Synchronous Distributed Generation Purpose: To establish an equitable process for allocating fault current margin, where available, to applicants

More information

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,

Sacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10, Sacramento Municipal Utility District SMUD May 10, 2010 1 SMUD Facts and Figures 900 Sq. Miles Service Area 585,500 Customers 1.4 million Area Population 10 Bulk Substations 473 Miles of Transmission Lines

More information

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

Awareness of the Situation

Awareness of the Situation 17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog

More information

STCP22-1 Issue 003 Production of Models for GB System Planning

STCP22-1 Issue 003 Production of Models for GB System Planning STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission

More information

Chapter 2 State Estimation and Visualization

Chapter 2 State Estimation and Visualization Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation

More information

Feeder Hosting Capacity and Impacts of Distribution Connected Generation. NGN Tutorial. Prepared for GOTF October 22, 2017

Feeder Hosting Capacity and Impacts of Distribution Connected Generation. NGN Tutorial. Prepared for GOTF October 22, 2017 Feeder Hosting Capacity and Impacts of Distribution Connected Generation NGN Tutorial Matthew Rylander, PhD Technical Leader Power System Studies Electric Power Research Institute mrylander@epri.com Prepared

More information

Transmission Expansion Advisory Committee JCPL Supplemental Projects

Transmission Expansion Advisory Committee JCPL Supplemental Projects Transmission Expansion Advisory Committee JCPL Supplemental Projects April 11, 2019 Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider

More information

Wind Farm Volt/VAR Control Using a Real-Time Automation Controller

Wind Farm Volt/VAR Control Using a Real-Time Automation Controller Wind Farm Volt/VAR Control Using a Real-Time Automation Controller Michael Thompson, Tony Martini, and Nicholas Seeley Schweitzer Engineering Laboratories, Inc. Published in Wide-Area Protection and Control

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

Local Area Studies Update - PACW Kevin Putnam

Local Area Studies Update - PACW Kevin Putnam Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton

More information

Year Assessment Preliminary Solutions

Year Assessment Preliminary Solutions 2016 10-Year Assessment Preliminary Solutions Stakeholder and Customer Presentation May 26, 2016 Jeremy Voigt Purpose Summarize Asset Renewal Solution Identification Process Summarize Preliminary Changes

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action Mapping Document Mapping Document Showing of PRC-001-2 System Protection Coordination to PRC-027-1 Protection System Coordination for Performance During Faults Updated 10-31 to reflect changes made to

More information

Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014

Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014 Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014 PREPARED BY: Systems Capability DATE: 6 June 2014 STATUS: FINAL

More information

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: _Cleco Power LLC Designated Contact Person: Cindy Guillot Address: P.O Box 70, (2180 St. Landry Hwy) St. Landry, LA 71367

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

DESCRIPTION OF COST ALLOCATION METHODOLOGY

DESCRIPTION OF COST ALLOCATION METHODOLOGY Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate

More information

USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION

USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION H USE CASE 13 ADAPTIVE TRANSMISSION LINE PROTECTION Use Case Title Adaptive Transmission Line Protection Use Case Summary The requirements for improvement in the performance of protection relays under

More information

Chapter 2 Communication for Control in Heterogeneous Power Supply

Chapter 2 Communication for Control in Heterogeneous Power Supply Chapter 2 Communication for Control in Heterogeneous Power Supply The need to modernize the power grid infrastructure, and governments commitment for a cleaner environment, is driving the move towards

More information

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022 Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer

More information

NETS SQSS Review of Requirement of Onshore Connection Facilities for Offshore Wind Farm Connections (GSR014) Working Group Report

NETS SQSS Review of Requirement of Onshore Connection Facilities for Offshore Wind Farm Connections (GSR014) Working Group Report NETS SQSS Review of Requirement of Onshore Connection Facilities for Offshore Wind Farm Connections (GSR014) Working Group Report January 2014 Executive Summary This document summarises the results of

More information

Advanced SIPS using PMU and SCADA data

Advanced SIPS using PMU and SCADA data Advanced SIPS using and SCADA data June 3, 2013 Yutaka Kokai Hitachi America, Ltd. Hitachi, Ltd. 2013. All rights reserved. Hitachi Group s Industry Segments Copy Right Hitachi, Ltd. 2013. All rights reserved.

More information

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012

Generation Interconnection Process. NEMSTF Education Session 1 January 19, 2012 Generation Interconnection Process NEMSTF Education Session 1 January 19, 2012 www.pjm.com Follows FERC Pro Forma Process Queues are open for a 3 month period Spreads Workload Out Over Year Generation,

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)

SMALL GENERATOR INTERCONNECTION REQUEST. (Application Form) Attachment 2 Transmission Provider: SMALL GENERATOR INTERCONNECTION REQUEST Designated Contact Person: Address: Telephone Number: (Application Form) An Interconnection Request is considered complete when

More information

Revision 6.0. Transmission Interconnection Guide

Revision 6.0. Transmission Interconnection Guide Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview

More information

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network

More information

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study Facilities Study for the Mora Line Transmission Project Non-Tariff Facilities Study November 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for

More information

ATTACHMENT I: Generator Interconnection Procedures (GIP)

ATTACHMENT I: Generator Interconnection Procedures (GIP) ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections

More information

POWER WORLD LAB MANUAL

POWER WORLD LAB MANUAL POWER WORLD LAB MANUAL Power world is a great powerful tool for solving power flows. Solving a power system is a little different from circuit analysis. Instead of being given voltages at certain nodes

More information

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities Non-Tariff System Impact Study March 204 Prepared by: Utility System Efficiencies, Inc (USE) Under Contract with:

More information

ASPEN Software - Introduction

ASPEN Software - Introduction ASPEN Software - Introduction ASPEN is a very user-friendly software package that is capable of doing load-flow and shortcircuit studies, as well as relay application and coordination. Its simple graphical

More information