INTERCONNECTION FACILITIES STUDY REPORT
|
|
- Martina Mason
- 5 years ago
- Views:
Transcription
1 INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December 5, 2005
2 1.0 Executive Summary This is the Generator Interconnection Facilities Study (GIFS) for the Northeast Wyoming 250MW generation (NE WYO) interconnection request submitted by Basin Electric Power Cooperative - Merchant Function. The proposed facility is a 250MW coal fired generating plant located approximately 20 miles north of Gillette Wyoming. Commercial operation is scheduled for January The purpose of the GIFS is to estimate the cost of equipment, engineering, procurement and construction work needed to physically and electrically interconnect NE WYO. The GIFS will also identify the electrical switching configuration, metering points, switchgear and any other major equipment associated with the Interconnection. An estimated construction schedule associated with Facility Upgrades will also be provided as part of this report. The GIFS is performed in accordance with the Interconnection Facilities Study Agreement (IFSA) dated February 8, 2005, and Section 8 of the Large Generator Interconnection Procedures of the Joint Open Access Transmission Tariff of Black Hills Power, Inc., as Joint Tariff Administrator (Black Hills Power), Basin Electric Power Cooperative, and Powder River Energy Corporation (Joint Tariff). Basin Electric Power Cooperative Merchant Function is the Interconnection Customer and Black Hills Power, Powder River Energy Corporation and Basin Electric Power Cooperative is the Transmission Provider coordinating through the Joint Tariff. The Transmission Provider owns and operates combined transmission facilities referred to as the Common Use System (CUS). A final System Impact Study (SIS) for NE WYO was completed on December 12, Detailed short-circuit, steady state, and transient stability analysis were performed as part of the SIS. Results of the SIS indicated that two major CUS Network Upgrades must be in-service in order to interconnect NE WYO. The first upgrade consists of a 105 mile 230KV transmission line from Hughes to a new substation in the Sheridan, Wyoming area. This line will be tapped by a new 230KV substation in the vicinity of NE WYO. The second upgrade consists of a 35 mile 230KV transmission line from the NE WYO 230KV substation to the Carr Draw substation. These upgrades, however, are required to meet projected Coal-Bed Methane (CBM) load growth in the NE Wyoming area and therefore will not be associated with NE WYO Network Upgrades, provided that the upgrades are constructed in support of CBM-related loads. Both upgrades will be completed well before the NE WYO in-service date. The transmission line upgrades and location of NE WYO are shown in Figure 4-1 below. Results of the GIFS show that interconnection of NE WYO will require the addition of two 230Kv transmission line terminals at the NE WYO 230KV substation. The total cost for these additions, comprised of Direct Assigned Facilities and Network Upgrades, is $2,420,000. A cost breakdown is provided in Section 6.0 below. 2.0 Introduction This is the Generator Interconnection Facilities Study (GIFS) for the Northeast Wyoming 250MW generation (NE WYO) interconnection request. The proposed facility is a
3 250MW coal fired generating plant located approximately 20 miles north of Gillette Wyoming with a commercial operation date of January The short circuit study performed as part of the SIS indicated that there is not a substantial increase in fault duty at area substations. Based on the existing breaker interrupt ratings, the addition of NE WYO requires no breaker upgrades. It is assumed that the Hughes-NE WYO-Sheridan and NE WYO-Carr Draw 230KV lines will be in service prior to the addition of NE WYO. Furthermore, it is assumed that the load shown on the projected CBM load forecast sheets will come to fruition. In the event those facilities are not constructed in support of CBM load, the Interconnection Customer may be required to bear additional costs or financing obligations with respect to facilities required for the interconnection of NE WYO with the Transmission Provider s Transmission System. The costs for modifying the transmission network will be broken out by Direct Assigned Facilities and Network Upgrade Facilities. Direct Assigned Facilities are those facilities or portion of facilities that are required for the sole purpose and benefit of the Interconnection Customer. Network Upgrade Facilities are those transmission facilities that are integrated with and support the Transmission Provider s transmission system for the overall benefit of all users of the system. Results from this study are based on data provided by the Interconnection Customer and other information on the CUS and surrounding transmission system. Any significant changes to transmission development plans or generator data may prompt a restudy. The Interconnection Customer is responsible for providing the Transmission Provider with any significant generator facility design or operational changes. 3.0 CUS Network Upgrade Facilities NE WYO 230KV Substation: A one-line diagram for this substation is provided in Figure 4-2. This substation will support the CBM load growth in the NE Wyoming area as well as provide for a point of interconnection for NE WYO. The substation will be a modified three bay breaker-and-a-half design with five line terminals including a terminal for NE WYO startup power. Network Upgrade Facilities required to support the NE WYO interconnection consists of a new substation bay including two 230KV line terminals. The line terminals include two 230KV/3000 Amp/63KA Gas Circuit Breakers, associated buswork, disconnects, grounding switches, protection systems and any other equipment deemed necessary for the safe and reliable operation of the transmission system. 4.0 Interconnection Customer Facility Requirements The point of interconnection for NE WYO will be the electrical connection between transmission line deadend insulator hardware and the jumper from the transmission line deadend insulator hardware to the substation buswork. The Interconnection Point is shown in Figure 4-2.
4 Direct Assigned Facilities will include all facilities from the Generator Step-Up (GSU) transformer high side bushing hardware to the point where the radial line jumper connects to the substation busbar. Direct Assigned Facilities include two deadend structures at the GSU and substation respectively, a radial 230KV line, line disconnects, grounding switches, revenue metering, protection systems and any other equipment deemed necessary for the safe and reliable operation of the transmission system. The Transmission Provider will design, procure, construct and own all Direct Assigned Facilities, all at the Interconnection Customer s sole expense. NE WYO will require startup and backup power and therefore, a separate line terminal at the NE WYO substation will be provided, at Interconnection Customer s expense, for startup power. The point of interconnection for NE WYO startup power will be the electrical connection between transmission line deadend insulator hardware and the jumper from the transmission line deadend insulator hardware to the substation buswork. Direct Assigned Facilities include two deadend structures at the startup transformer and substation respectively, a radial 230KV line, line disconnects, grounding switches, revenue metering, protection systems and any other equipment deemed necessary for the safe and reliable operation of the transmission system. The Transmission Provider will design, procure, construct and own all Direct Assigned Facilities, all at the Interconnection Customer s sole expense. A Power System Stabilizer (PSS) will be required on the generator. PSS design and installation shall be coordinated with the Transmission Provider. The generator exciter shall be of the High Initial Response (HIR) type and conform to the latest WECC exciter design criteria. FIGURE 4-1: Transmission System Diagram
5 To Sheridan WY Area To Hughes N.E. WYO Generator N.E. WYO Generator Back-Up Station Service M Point Of Interconnection M To Carr Draw Figure 4-2: NE WYO 230KV Substation oneline. 5.0 Construction Schedule. Table 5-1 below provides a completion date for major milestones in the construction process. Transmission Provider and Interconnection Customer will coordinate any changes to this schedule. Table 5-1: Construction Schedule TASK Completion Date Start Construction Summer kV Line Terminal Additions Winter 2008 Back-Feed Plant Summer 2009 Generator Synch Summer 2010 Generator Testing Summer 2010 Commercial Operation January 2011
6 The Interconnection Customer must coordinate generator testing with the Transmission Provider and Control Area Operator. 6.0 Network Upgrade and Direct Assigned Cost Estimate Facility costs are broken out between Network Upgrade Facility Costs and Direct Assigned Facility Costs. Direct Assigned Facilities are those facilities or portion of facilities that are required for the sole purpose and benefit of the Interconnection Customer. Network Upgrade Facilities are those transmission facilities that are integrated with and support the Transmission Provider s transmission system for the overall benefit of all users of the system. This cost estimate is a + 20% estimate based on Attachment A to Appendix 4 of the Interconnection Facilities Study Agreement dated February 8, The actual cost to complete this project can be affected by many factors such as actual construction costs, increases in material costs, increases in labor costs, scheduling and material availability. Network Upgrade Costs: The Network Upgrade Cost estimate is $1,920,000. Facilities included in this cost estimate are provided in Section 3.0 above. Direct Assigned Costs: The Direct Assigned Cost estimate is $500,000. Facilities included in this cost estimate are provided in Section 4.0 above. In addition to the above mentioned costs, the Interconnection Customer will be responsible for an annual fee for the testing and maintenance of the necessary revenue metering equipment. The Interconnection Customer will also be responsible for a monthly operating fee associated with SCADA metering. 7.0 Conclusions Results from the Generator Interconnection Facilities Study (GIFS) indicated that two additional 230KV transmission line terminals at the NE WYO 230KV substation are required in order to interconnect NE WYO. Prior to the NE WYO in-service date, the CUS is expected to add two 230KV transmission lines to support the rapid CBM load growth in NE Wyoming. The first line is from Hughes to the Sheridan Wyoming area with a new substation along this line in the vicinity of NE WYO. The second 230KV line is from the NE WYO 230KV substation to the Carr Draw substation. Based on stability and power flow analysis, these 230KV lines will provide sufficient support for NE WYO. The total cost to interconnect NE WYO to the CUS is $2,420,000. A breakdown of Direct Assigned and Network Upgrade Costs is provided in Section 6.0 above.
Generation Interconnection Feasibility Study Report
Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study
More informationTECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM
TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM Version 1.2 May 28, 2009 Transmission Planning Department Revisions Rev. No. Date Description By Approval 1.0 8/10/06
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationGrid Interconnection of Renewable Generation
Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationQ44 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationInterconnection Application
Interconnection Application Member interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationSystem Impact Study for Power Supply 400 MW Import on the EAL BCHA Path
System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power
More informationGeneration, Transmission, and End User Facilities
Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More informationDESCRIPTION OF COST ALLOCATION METHODOLOGY
Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems
ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017
More informationElectric Utility Facility Connection Requirements
City of Coffeyville Municipal Light and Power Electric Utility Facility Connection Requirements Approved: Date: Version Date Change Tracking Reviewer/Editor 1.0 June, 2010 Original document. Steve McGie
More informationGlencoe Light and Power
Glencoe Light and Power REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS 1 Table of Contents Page I. INTRODUCTION...5 A. Authority... 5 B. Objectives...5 C. Interconnection
More informationOpen Access Transmission Tariff of Southern Companies
Open Access Transmission Tariff of Southern Companies Procedures for Reserving Transmission Capacity for Future Load Growth, Designating/Undesignating Network Resources, and Arranging for Other Related
More informationDominion Supplemental Projects
Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer
More informationSmall Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662
Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately
More informationGeneration Interconnection Impact Study Report. For. Interconnection Customer Q0022
Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer
More informationMidwest ISO. Module B- Network Integration Transmission Service Overview. Vikram Godbole Lead, Transmission Service Planning October 20, 2010
Midwest ISO Module B- Network Integration Transmission Service Overview Vikram Godbole Lead, Transmission Service Planning October 20, 2010 DISCUSSION POINTS 1. What is NITS 2. How to get Designated NITS
More informationFeasibility Study on Load Flow and Short Circuit Project
Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationFor the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form)
Electrical Company: PacifiCorp For the State of Washington SMALL GENERATOR INTERCONNECTION REQUEST (Tier 1 [Non-Net Meter], Tier 2, Tier 3) (Application Form) Designated Contact Person: Robin Moore Address
More informationPublic Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM
Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities
More informationGeneration Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationFacility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements
Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The
More informationISO New England Data Modeling Requirements
A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda
More informationMONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS
MONTANA-DAKOTA UTILITIES REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITY INTERCONNECTIONS Table of Contents I. Introduction... 5 A. Authority... 5 B. Objectives... 5 C. Interconnection
More informationADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:
PROCUREMENT DEPARTMENT 4 WORLD TRADE CENTER 150 GREENWICH STREET, 21ST FL. NEW YORK, NY 10007 12/7/2018 ADDENDUM # 3 To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar
More informationSMALL GENERATOR INTERCONNECTION REQUEST. (Application Form)
Attachment 2 Transmission Provider: SMALL GENERATOR INTERCONNECTION REQUEST Designated Contact Person: Address: Telephone Number: (Application Form) An Interconnection Request is considered complete when
More informationLevel 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW
Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &
More informationJEA. Facility Connection Requirements
JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities
More informationFacilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study
Facilities Study for the Mora Line Transmission Project Non-Tariff Facilities Study November 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for
More informationSMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2
SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:
More informationInstructions. Interconnection Customer declares its intention to interconnect with the AEP Distribution System.
APPLICATION FOR INTERCONNECTION WITH THE Indiana Michigan Power Company INDIANA DISTRIBUTION SYSTEM (Project capacity greater than 10kW) Instructions Interconnection Customer declares its intention to
More informationInterconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study
Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities Non-Tariff System Impact Study March 204 Prepared by: Utility System Efficiencies, Inc (USE) Under Contract with:
More informationLarge Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities
Large Generator Interconnection Generator, Transmission, & Distribution Asset Responsibilities Effective Date: May 12, 2014 Revision History Date May 1, 2013 May 12, 2014 Description Initial document Revision
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationTHE NEXT BIG THING IN DISTRIBUTION AUTOMATION
THE NEXT BIG THING IN DISTRIBUTION AUTOMATION Unrestricted Siemens Industry, Inc. 2017 usa.siemens.com/digitalgrid Siemens Distribution Feeder Automation (SDFA) Automatic Transfer Systems (ATS) Page 2
More informationJanuary 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.
California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California
More informationInterconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory
Interconnection Standards for Delmarva Power & Light Company s Delaware Operating Territory Authority: This Interconnection Standard is filed in compliance with the Delaware Public Utility Commission in
More informationATTACHMENT I: Generator Interconnection Procedures (GIP)
ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections
More informationIntroduction to Generation Availability Data System (GADS) Wind Reporting
Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationRocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH
Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation
More informationSMALL GENERATOR INTERCONNECTION REQUEST (Application Form)
SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: _Cleco Power LLC Designated Contact Person: Cindy Guillot Address: P.O Box 70, (2180 St. Landry Hwy) St. Landry, LA 71367
More informationAPPENDIX B-2. TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES. and SMALL GENERATION FACILITIES
APPENDIX B-2 TECHNICAL CONNECTION REQUIREMENTS for LOAD DELIVERY FACILITIES and SMALL GENERATION FACILITIES Revision: 4.0 12/30/2011 Page 1 of 39 TABLE OF CONTENTS DEFINITIONS A. Scope 1. Ownership 2.
More informationPacifiCorp Transmission Technical Workshop
PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt
More informationMemorandum. This memorandum requires Committee action.
California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationSPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5
Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationRevision 6.0. Transmission Interconnection Guide
Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview
More informationSMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM
SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the
More informationTENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT
TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN >>> TENGIZ PROJECT - FIELD SUBSTATION REPLACEMENT / KAZAKHSTAN Tengiz is one of the largest oil fields in the world, and is located in western
More informationSuperseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011
Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 2. Initial Technical Review a. The following flowchart provides, for illustrative purposes, the major steps in the Initial Technical Review process:
More informationHigh-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY
S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are
More informationAPPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS. for GENERATION & INTERCONNECTION FACILITIES
APPENDIX B-1 TECHNICAL CONNECTION REQUIREMENTS for GENERATION & INTERCONNECTION FACILITIES Revision: 4.0 12/28/2011 Page 1 of 40 DEFINITIONS TABLE OF CONTENTS A. Scope 1. Generation Connection and Operating
More informationATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service
Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network
More informationSTCP22-1 Issue 003 Production of Models for GB System Planning
STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission
More informationLCRA Transmission Services Corporation. Facility Connection Requirements
LCRA Transmission Services Corporation Facility Connection Requirements April 2017 Table of Contents 1.0 INTRODUCTION... 3 2.0 Facility Connection Requirements... 3 2.1 Summary of Basic Interconnection
More informationThe NYISO shall assign a Queue Position based upon the date and time of receipt of the
30.4 Queue Position 30.4.1 General The NYISO shall assign a Queue Position based upon the date and time of receipt of the valid Interconnection Request; provided that, if the sole reason an Interconnection
More informationStudies Overview and Data Requirements. Robert Pan
Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationWestern Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document
Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System
More informationPG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.
Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4
More informationGenerator Interconnection Process. Wholesale Transmission Overview
1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent
More informationWestern Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document
Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System
More informationOur Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium
Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium Voltage Panels and Enclosures designed and built with
More informationFacility Connection Requirements
SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...
More informationAppendix I: LOAD OPERATING AGREEMENT
PG&E Transmission Interconnection Handbook Appendix I: LOAD OPERATING AGREEMENT Purpose The following agreement establishes operating responsibilities and associated procedures for communications between
More information2009 SPP TransCanada Pipeline Study Report
2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table
More informationWN U-60 Original Sheet No. 152
WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H
More informationERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018
ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used
More informationApproval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9
PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6
More informationLocal Area Studies Update - PACW Kevin Putnam
Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton
More informationRelevant Electrical Standards (RES) Grid Code Review Panel January 2014
Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same
More informationOriginal Sheet A 1. APPLICATION OF STATEMENT OF RATES... 1
Original Sheet A TABLE OF CONTENTS Section Sheet 1. APPLICATION OF STATEMENT OF RATES... 1 2. RATES 2.1 Installation Charges... 2 2.2 Local Network Interconnection Equipment... 3 2.3 Local Network Interconnection
More informationSTCP 04-3 Issue 005 Real Time Data Provision
STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationOrder No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process
Order No. 1000 Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Thinh Nguyen Manager, Interconnection Projects New York Independent System Operator Joint
More informationCampus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE
Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Key Factors of Resilient Electrical
More informationInterconnection and Transmission
Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection
More informationWORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES
Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS
More informationHigh and Medium Voltage Substation Design, Testing and Maintenance. KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel.
Training Course : High and Medium Voltage Substation Design, Testing and Maintenance Training Course For One Week In KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel Which Be Held As Under Details : Tel.
More informationSubstation SCADA Monitoring
Substation SCADA Monitoring Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Substations are a critical component
More informationTransWest Express and Gateway South
TransWest Express and Gateway South Co-developed by four leading entities: Arizona Public Service PacifiCorp National Grid Wyoming Infrastructure Authority Regional Stakeholder Meeting January 23, 2008
More informationExercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION
Exercise 2 Single Bus Scheme EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with electric power substations using the single bus scheme with bus section circuit breakers.
More informationReal-time Power System Operation. Energy Management Systems. Introduction
1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern
More informationRFP Attachment 13. January 2010
PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt
More information