YATES IS COMPLETING CENTURYLINK S NEW TECHNOLOGY CENTER OF EXCELLENCE. BY RUSS GAGER

Size: px
Start display at page:

Download "YATES IS COMPLETING CENTURYLINK S NEW TECHNOLOGY CENTER OF EXCELLENCE. BY RUSS GAGER"

Transcription

1 Commercial YATES CONSTRUCTION CENTURYLINK TECHNOLOGY CENTER OF EXCELLENCE Future Tech YATES IS COMPLETING CENTURYLINK S NEW TECHNOLOGY CENTER OF EXCELLENCE. BY RUSS GAGER Technology is a major driver of the U.S. economy, and contributing to that growth is the new Technology Center of Excellence being completed for CenturyLink next to its headquarters in Monroe, La. The third-largest telecommunications company in the United States, CenturyLink hosts IT solutions for enterprise customers and provides cloud infrastructure in the network services market. Constructing the futuristic, three-story, 325,000-square-foot facility has been a challenging, fast-track project for construction manager Yates Construction. It s quite unique, Project Executive Cleet McHenry declares. It s not a typical building everything slopes and curves. We had a site package and a steel package that came out initially to get started with the foundations 24 and steel. The interior package came along after that. Additional construction challenges were the weather. We ve had two of the worst winters we ve had in a long time, McHenry laments. Our biggest obstacle was just the weather. It was really colder and wetter than normal. Despite these challenges, when construction of the project began in March 2013, Yates Construction had no lost man-hours due to accidents or injuries on the job, and the ribbon-cutting was held on schedule on March 26. Yates Construction self-performed some minor activities such as assisting with concrete, erosion control and site maintenance, but hired approximately 35 subcontractors 60 percent of whom were local to work on the technology center. Until summer, the finishing touches are being put on the building. The CenturyLink Technology Center of Excellence includes a technology research and development lab, a network opera- Yates Construction CenturyLink Technology Center of Excellence Location: Monroe, La. Employees onsite at peak: 12 Scope of work: Technology center It s not a typical building everythingslopes and curves. Cleet McHenry, project executive

2 More than 1,700 augur cast pilings were driven for the center and a five-story concrete parking garage next to it that handles 1,202 vehicles. Adjacent to the garage is a separate mechanical building that houses the chillers, cooling towers, back-up electrical generators and other equipment. This design eliminates the need for roof-mounted mechanical equipment. The center s concrete foundation stabilizes its steel structure and features a concrete deck flooring system. Approximately 60 percent of the exterior is an insulated curved aluminum panel system and 40 percent is curved curtainwall that gives a futuristic feel to the building and its sloped roof. Network Lab The second floor of the center is approximately 36,000 square feet that is dedicated Yates is happy to work on the CenturyLink Technology Center of Excellence with its unique design. tions center and collaborative office and meeting space. It also includes a customer experience center where the company s latest offerings will be demonstrated, along with an executive briefing center that will enable sales and support teams to present solutions to current and prospective customers challenges. Innovation Hub In the center, employees with skills in networking, the cloud, information technology and other areas will work together to create innovative products and services for CenturyLink s customers. They will have unique workspace options that will enable them to collaborate and innovate anywhere on the campus through voice-over-internet Protocol service. The company is transitioning from a traditional network communications provider to an integrated provider of advanced IP-enabled network, cloud, hosting and IT services. CenturyLink considers the Technology Center of Excellence to be key to accomplishing this transition successfully. 25 JULY/AUGUST 2015 CONSTRUCTION-TODAY.COM

3 Commercial YATES CONSTRUCTION CENTURYLINK TECHNOLOGY CENTER OF EXCELLENCE» The technology center s concrete foundation stabilizes its steel structure. to the network lab, which has a capacity of 800 racks, each of which will hold multiple servers. The floor is raised two feet above the actual floor to allow the routing of communication cables, electricity and room for ventilation. When the temperature is right on the outside, the lab will circulate 100 percent of outside fresh air, McHenry says. When the temperature outside is 55 degrees and the humidity is right, they ll utilize that to cool the lab. Once it is fully occupied, keeping it cool will be a huge load. The network operations center is also on the second floor. It can seat up to 160 people and has a large wall covered with flat screen displays that monitor the entire computer network. remembers. We had to get the zoning and planning for it. The street was removed and the 365,000-square-foot corporate headquarters connected to the new technology center with a circle-shaped plaza 26 Move a Street The CenturyLink Technology Center of Excellence has been built in a portion of a street, a pecan grove and a small parking lot. We had to basically go in and move a half-mile-long city street, McHenry

4 that measures approximately 50,000 square feet or 2.2 acres and is covered with brick pavers. There s about 17,500 square feet of water with 11 fountains in it, McHenry says. To make way for the technology center, approximately 82 pecan trees were harvested and milled locally. This yielded approximately 20,000 square feet of lumber, from which veneer paneling and flooring, as well as solid material for coffee bar countertops throughout the facility, were produced. This is a project that will win numerous national awards for design. We ended up with 72,000 3-inch pecan, tongue-and-groove veneer panels with a birch backer on it, McHenry says. Approximately 18,000 square feet of the paneling covers walls throughout the center, except for 1,100 square feet, which was used as a border in the executive briefing conference room around a large carpet inlay under the conference tables. The landscape design for the campus included planting a new tree for each tree that was removed, and more than 100 trees have been planted, along with other vegetation. LEED Silver The architectural firm of Moody Nolan designed the CenturyLink Technology Center of Excellence to aim for LEED Silver certification. It features a mixture of 28 varieties of slow-growing The new CenturyLink structure has been designed to have a lot of energy-saving features. 27 JULY/AUGUST 2015 CONSTRUCTION-TODAY.COM

5 The technology center will employ a daylight harvesting system to help it save energy. Commercial YATES CONSTRUCTION CENTURYLINK TECHNOLOGY CENTER OF EXCELLENCE vegetation that bloom throughout the year on the lower roof along with a white membrane on the upper roof. These roof surfaces are visible from the adjacent existing headquarters facility and provide a striking visual appearance along with emphasizing the sustainable features of the two materials. Other energy-saving features include tankless, point-of-source 28 hot water heating in restrooms and break rooms, smart building controls for mechanical and electrical systems, LED lighting, intelligent electrochromic windows, audio/visual equipment, security devices, uninterruptible power supplies and generator backup systems. The carpeting and systems furniture are 100 percent recyclable. McHenry attributes the single-biggest energy savings to the 37,000 square feet of electrochromic glass, which CenturyLink calculates is the single-largest installation of that glass in the country. It changes tinting based on the angle of the sun and the time of day. It also helps out on the radiant heat inside the building and helps control the lighting, McHenry says. If you have as much glass as we have here, if it s really bright outside, it s hard to work in here. The tinting helps with the glare of the sun. The electrochromic glass leverages nanotechnology and pre-programmed intelligence to tint automatically in response to outside conditions and user preferences, eliminating the need for blinds or shades. Its manufacturer reports it has been shown to reduce lighting, heating and cooling loads in typical buildings by 20 percent or more. The technology center s daylight harvesting system features dimmable ballasts, which allow the building to save energy. The lighting design reportedly optimizes energy performance by 20 percent over the current energy code. High-performance luminaries and daylight harvesting will contribute to reductions in energy-use goals. Building occupants have control of their environment through low-voltage controls within the space as well as task lighting. Each floor of the technology center has dedicated storage areas for recycling glass, plastic, metal and paper. Items from these collection points will be gathered weekly, and a similar recycling program will be established in the current headquarters building. This is a project that will win numerous national awards for design, McHenry predicts. It s really unique, and we want to make sure we do it justice.

WAREHOUSE / DISTRIBUTION EXPERIENCE

WAREHOUSE / DISTRIBUTION EXPERIENCE WAREHOUSE / DISTRIBUTION EXPERIENCE BERRY WHOLESALE DRUGS Walter Knestrick Contractor, Inc. The warehouse space includes a partial mezzanine with administrative offices and staff support areas. The mezzanine

More information

CHAPTER 5. Special Cases

CHAPTER 5. Special Cases CHAPTER 5 Special Cases OVERHANGS To be treated as an overhang, slotted and louvered shading devices must have the slats arranged so that no direct solar radiation penetrates the overhang at any time during

More information

Running Your Data Center Under Ideal Temperature Conditions

Running Your Data Center Under Ideal Temperature Conditions TECHNICAL BRIEF Mastering Data Center Environmental Controls to Help Drive Your Bottom Line Running Your Data Center Under Ideal Temperature Conditions Challenge Many data centers waste energy using inefficient

More information

Why and How to Benchmark Building Energy Use in Office Buildings

Why and How to Benchmark Building Energy Use in Office Buildings Why and How to Benchmark Building Energy Use in Office Buildings Presented by Felix Flechas, P.E. Environmental Compliance and Sustainability Engineering, LLC March 2015 Making the case for energy efficiency

More information

Lighting the Way for Innovation at Launch Fishers with Digital Ceiling PoE LED Solutions.

Lighting the Way for Innovation at Launch Fishers with Digital Ceiling PoE LED Solutions. CASE STUDY Lighting the Way for Innovation at Launch Fishers with Digital Ceiling PoE LED Solutions. / CUSTOMER / Fishers, Indiana is an entrepreneurial city geared for economic development and already

More information

RF Code Delivers Millions of Dollars in Annual Power & Cooling Savings for CenturyLink

RF Code Delivers Millions of Dollars in Annual Power & Cooling Savings for CenturyLink INDUSTRIAL INTERNET IN ACTION CASE STUDY RF Code Delivers Millions of Dollars in Annual Power & Cooling Savings for CenturyLink CLIENT PROFILE CenturyLink Technology Solutions is the second largest telecommunications

More information

100 SIMPLEX DRIVE WESTMINSTER, MA

100 SIMPLEX DRIVE WESTMINSTER, MA FO R LEA SE 100 SIMPLEX DRIVE WESTMINSTER, MA 19,91 SF WORLD-CLASS 6 CLEAR DISTRIBUTION BUILDING Salient details include: Prominent Route visibility Institutional quality asset ensconced on a 95 acre pristine

More information

Technology Incubation Center. High Tech Cleanroom Laboratory & Production Facility.

Technology Incubation Center. High Tech Cleanroom Laboratory & Production Facility. High Tech Cleanroom Laboratory & Production Facility www.technologyincubationcenter.com Jay Chmieleski 612 275 3775 mobile Dan Friedner FOR SALE OR LEASE Technology Incubation Center VADNAIS HEIGHTS, MINNESOTA

More information

M E M O R A N D U M. To: California State Lottery Commission Date: October 16, Item 9(c): Approval to Hire Project Management Consultant

M E M O R A N D U M. To: California State Lottery Commission Date: October 16, Item 9(c): Approval to Hire Project Management Consultant M E M O R A N D U M To: California State Lottery Commission Date: From: Joan M. Borucki Director Prepared By: Linh Nguyen Chief Deputy Director Subject: Item 9(c): Approval to Hire Project Management Consultant

More information

100 SIMPLEX DRIVE WESTMINSTER, MA

100 SIMPLEX DRIVE WESTMINSTER, MA FOR LEASE 100 SIMPLEX DRIVE WESTMINSTER, MA WAREHOUSE SPACE 198,788 SF ON 95 ACRES As the exclusive listing agent, The Stubblebine Company is pleased to present Route Commerce Park for lease. With robust

More information

Beverly D. Grappone Hall Certified LEED Silver Home of NHTI s State-of-the Art Nursing Simulation Center

Beverly D. Grappone Hall Certified LEED Silver Home of NHTI s State-of-the Art Nursing Simulation Center Beverly D. Grappone Hall Certified LEED Silver Home of NHTI s State-of-the Art Nursing Simulation Center Project: Beverly D. Grappone Hall Facility Size: 30,500 sq. ft. Location: Concord, New Hampshire

More information

Maximising Energy Efficiency and Validating Decisions with Romonet s Analytics Platform. About Global Switch. Global Switch Sydney East

Maximising Energy Efficiency and Validating Decisions with Romonet s Analytics Platform. About Global Switch. Global Switch Sydney East Maximising Energy Efficiency and Validating Decisions with Romonet s Analytics Platform Case Study - Global Switch Sydney East About Global Switch Global Switch is a leading owner, operator and developer

More information

Washington Square FPO. 111 Washington Square > Office Space FOR LEASE > OFFICE SPACE 111 WASHINGTON AVENUE, MINNEAPOLIS, MN 55401

Washington Square FPO. 111 Washington Square > Office Space FOR LEASE > OFFICE SPACE 111 WASHINGTON AVENUE, MINNEAPOLIS, MN 55401 FOR LEASE > OFFICE SPACE Washington Square 111 WASHINGTON AVENUE, MINNEAPOLIS, MN 55401 FPO 111 Washington Square > Office Space HENNEPIN AVE PARKING RAMP > Built in 1987, 111 Washington is part of a three

More information

100 SIMPLEX DRIVE WESTMINSTER, MA

100 SIMPLEX DRIVE WESTMINSTER, MA FOR LEASE 100 SIMPLEX DRIVE WESTMINSTER, MA 203,000 SF WORLD-CLASS 18 CLEAR MANUFACTURING/DISTRIBUTION SPACE The Stubblebine Company is pleased to offer 100 Simplex Drive, Westminster, MA, a World-Class

More information

Cannon T4 Modular Data Center (MDC)

Cannon T4 Modular Data Center (MDC) SOLUTIONS Cannon T4 Modular Data Center (MDC) Cannon T4 Modular Data Centers are part of Cannon T4 Data Center Solutions Cannon T4 Data Center Solutions Overview T4 Data Centers T4 Mini Data Centers T4

More information

Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design.

Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. Data Centre Stockholm II, Sweden Flexible, advanced and efficient by design. TelecityGroup Kvastvägen 25-29 128 62 Sköndal Stockholm Sweden Tel: +46 (0) 8 799 3800 se.info@telecity.com www.telecitygroup.se

More information

Technical Computing in the New Hess Tower. Jeff Davis Gary Whittle Jim Breef Vic Forsyth

Technical Computing in the New Hess Tower. Jeff Davis Gary Whittle Jim Breef Vic Forsyth Technical Computing in the New Hess Tower Jeff Davis Gary Whittle Jim Breef Vic Forsyth Hess Tower - Worldwide headquarters of Hess Exploration and Production - The building is 844,000 square feet and

More information

ASCENT DATA CENTER. 30 MW Data Center Enterprise Grade Facility LEED Gold ATLANTA, GA ABOUT ASCENT CO LO CAT I O N SUI T E S AVAI LAB LE NO W!

ASCENT DATA CENTER. 30 MW Data Center Enterprise Grade Facility LEED Gold ATLANTA, GA ABOUT ASCENT CO LO CAT I O N SUI T E S AVAI LAB LE NO W! ASCENT DATA CENTER CO LO CAT I O N SUI T E S AVAI LAB LE NO W! ATLANTA, GA 30 MW Data Center Enterprise Grade Facility LEED Gold ABOUT ASCENT Ascent Data Center is located in the greater Atlanta, Georgia

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline Georgia Institute of Technology Advanced Computing Technology Building Draft Program Vision Program Outline Issued April 2, 2001 I N T R O D U C T I O N Scope This document is a summary of the Vision Session

More information

Building for Sale American Parkway Madison, WI. Key Commercial Real Estate LLC

Building for Sale American Parkway Madison, WI. Key Commercial Real Estate LLC Building for Sale 4800 American Parkway Madison, WI Key Commercial Real Estate LLC 608-729-1800 www.keycomre.com TABLE OF CONTENTS Property Overview................... Pg. 3 Property Details......................Pg.

More information

Gold: points Platinum: 80+ points. Certified: points Silver: points

Gold: points Platinum: 80+ points. Certified: points Silver: points What is LEED? LEED, or Leadership in Energy & Environmental Design, is redefining the way we think about the places where we live, work and learn. As an internationally recognized mark of excellence, LEED

More information

Energy Performance Contracting

Energy Performance Contracting Energy Performance Contracting December 2017 Outlines Section One: Jonson Controls as an Energy Service Company (ESCO) Reasons behind investment in Energy Efficiency Section Two: Funding Options of Energy

More information

Addressing the Coverage Requirements of Enterprise Customers

Addressing the Coverage Requirements of Enterprise Customers Addressing the Coverage Requirements of Enterprise Customers Small Cell World Summit, London June 11, 2015 Mark Newlin Product Manager Vodafone UK Mobile: +44 7810 813788 Email: mark.new lin@vodafone.com

More information

Custom Designed Prefabricated Data Centre Buildings

Custom Designed Prefabricated Data Centre Buildings Custom Designed Prefabricated Data Centre Buildings ecentre TM is a complete, pre-equipped, custom designed modular technical facility to house and power data and communication equipment. A modern prefabricated

More information

FACT SHEET: IBM NEW ZEALAND DATA CENTRE

FACT SHEET: IBM NEW ZEALAND DATA CENTRE FACT SHEET: IBM NEW ZEALAND DATA CENTRE IBM and the Data Centre IBM is the largest occupier of data centre space in the world and currently owns or occupies approximately one million square metres globally.

More information

Engineering and Design Services Mechanical HVAC Plumbing Electrical Chemical/Process Structural Instrumentation

Engineering and Design Services Mechanical HVAC Plumbing Electrical Chemical/Process Structural Instrumentation Commissioning Profile + Services About Us Established in 1965, DEDC is a privately owned, full-service multidisciplined engineering and design firm. We offer in-house expertise in mechanical HVAC, electrical,

More information

7th Annual Statewide Energy Efficiency Forum Applying Building Technologies to Realize Savings June 16, 2016

7th Annual Statewide Energy Efficiency Forum Applying Building Technologies to Realize Savings June 16, 2016 . Lessons Learned - SMUD s East Campus Operations Center Jim Parks 7th Annual Statewide Energy Efficiency Forum Applying Building Technologies to Realize Savings June 16, 2016 Powering forward. Together.

More information

LEADERS IN MEP, COMMISSIONING & ICT FOR BOSTON AND THE NORTHEAST

LEADERS IN MEP, COMMISSIONING & ICT FOR BOSTON AND THE NORTHEAST LEADERS IN MEP, COMMISSIONING & ICT FOR BOSTON AND THE NORTHEAST SYSKA BOSTON provides full-range, high-performance MEP/FP engineering, vertical transportation, sustainable design and commissioning services

More information

Energy Action Plan 2015

Energy Action Plan 2015 Energy Action Plan 2015 Purpose: In support of the Texas A&M University Vision 2020: Creating a Culture of Excellence and Action 2015: Education First Strategic Plan, the Energy Action Plan (EAP) 2015

More information

Run a Smart Workplace Introducing the Digital Building. Digital Building Solutions

Run a Smart Workplace Introducing the Digital Building. Digital Building Solutions Digital Building Solutions Run a Smart Workplace Introducing the Digital Building Maximize efficiency and productivity Enhance infrastructure flexibility & network security Reduce installation and operating

More information

AMERICAN PKWY. FOR SALE CLASS A OFFICE HEADQUARTERS 4800 American Parkway, Madison, WI

AMERICAN PKWY. FOR SALE CLASS A OFFICE HEADQUARTERS 4800 American Parkway, Madison, WI FOR SALE CLASS A OFFICE HEADQUARTERS American Parkway, Madison, WI American Parkway Overview American Parkway is a Class A, 3-story, approximately 34,000 SF office building, within The American Center

More information

CenturyLink Data Center Services Omaha, Nebraska

CenturyLink Data Center Services Omaha, Nebraska CenturyLink Data Center Services Omaha, Nebraska HIGH AVAILABILITY ENTERPRISE COMPUTING Designed and equipped to meet the demands of enterprises, wholesale businesses and government agencies, CenturyLink

More information

Remodel. New server deployment time is reduced from weeks to minutes

Remodel. New server deployment time is reduced from weeks to minutes SOLUTIONS CONSOLIDATION VIRTUALIZATION A Radical Remodel Emerson virtualizes on Dell servers, eliminating 3,600 servers, reducing approximately 135 data centers down to 4, and decreasing the operating

More information

CenturyLink Data Center Services Herndon, Virginia

CenturyLink Data Center Services Herndon, Virginia CenturyLink Data Center Services Herndon, Virginia DATA CENTER SOLUTIONS TO SUPPORT GLOBAL ENTERPRISE IT The IT environment is rapidly changing. Organizations are expanding their IT infrastructure to accommodate

More information

GOLDENI. Owners Manual & Safety Instructions. English. model# GOLDi600. Copyright 2017 Smart Grow Technologies, INC All Rights Reserved

GOLDENI. Owners Manual & Safety Instructions. English. model# GOLDi600. Copyright 2017 Smart Grow Technologies, INC All Rights Reserved GOLDENI 600 model# GOLDi600 English Copyright 2017 Smart Grow Technologies, INC All Rights Reserved Owners Manual & Safety Instructions INTRODUCTION This User Manual is for Smart Grow Technologies (SGS):

More information

98,000 sq. ft. Crescent Building For Sale. Sale Price: $5,500,000. Jim Koon, Managing Broker (208) or (208)

98,000 sq. ft. Crescent Building For Sale. Sale Price: $5,500,000. Jim Koon, Managing Broker (208) or (208) 10220 E. Sprague Ave Spokane Valley, Washington 99206 The Crescent building offers a unique opportunity to acquire a building for fraction of the replacement cost. The two story 98,000 square foot concrete

More information

We have you walking on air

We have you walking on air Building FlexSys TM Underfloor air simplified distribution We have you walking on air If you own or operate a building today, it s critical that you control energy costs, reduce the environmental impact

More information

WHITE PAPER. Solutions OnDemand Hosting Overview

WHITE PAPER. Solutions OnDemand Hosting Overview WHITE PAPER SAS Title Solutions OnDemand Hosting Overview ii Contents Overview... 1 Cary 1 (US) Facility Specifications...2 Cary 2 (US) Facility Specifications (SAS New Cloud Computing Center)...3 Charlotte

More information

SUB-CONTRACTOR PRE-QUALIFICATION FORM

SUB-CONTRACTOR PRE-QUALIFICATION FORM CONTACT INFORMATION Company Contact Person: Title: Street Address: Suite No.: EXPERIENCE City: Zip: 1. Please check the CSI Codes applicable to your business: 02 00 00 Existing Conditions 02 20 00 Assessment

More information

STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT

STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT STRATEGIC ADVISORY AND CAPITAL IMPROVEMENT OVERSIGHT CURRENT STATE THE C&W WAY College athletic departments throughout the country are spending at an unprecedented pace to develop and renovate facilities

More information

PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST

PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST PISCATAWAY, NEW JERSEY NJ1 DATA CENTERS POWERED BY TRUST THE CENTER THAT NEVER SLEEPS The greater New York metro area is a pulsing capital of industry and finance alive 24 x 7 x 365 with critical transactions

More information

18,000-19,000 square feet. ELEVATORS 16 passenger elevators in three banks 1 dedicated garage shuttle elevator 1 dedicated freight elevator

18,000-19,000 square feet. ELEVATORS 16 passenger elevators in three banks 1 dedicated garage shuttle elevator 1 dedicated freight elevator www.50cal.com Bay Views with a Premier Location About was designed by architect Welton Becket & Associates. The lobby has flame-cut red and black granite finished floors and mahogany wall panels trimmed

More information

RAPID CITY CALL CENTER 1400 TURBINE DRIVE RAPID CITY, SD FOR SALE / FOR LEASE OFFICE / CALL CENTER 133,102 SQ. FT.

RAPID CITY CALL CENTER 1400 TURBINE DRIVE RAPID CITY, SD FOR SALE / FOR LEASE OFFICE / CALL CENTER 133,102 SQ. FT. FOR SALE / FOR LEASE OFFICE / CALL CENTER 133,102 SQ. FT. PROPERTY OVERVIEW FOR SALE $12,000,000.00 FOR LEASE $12.50/SF NNN EST. NNN EXPENSES $6.33/SF BUILDING SIZE 133,102 SF LAND SIZE 15.01 acres (including

More information

DATA CENTER AIR HANDLING COOLING SOLUTIONS

DATA CENTER AIR HANDLING COOLING SOLUTIONS DATA CENTER AIR HANDLING COOLING SOLUTIONS World-class performance and reliability from YORK As data storage and protection needs grow, so can costs and complexity. That s why having the right partner

More information

Trane mytest Water-cooled Chiller Performance Validation What you spec is what you get *

Trane mytest Water-cooled Chiller Performance Validation What you spec is what you get * Trane mytest Water-cooled Chiller Performance Validation What you spec is what you get * Trane CenTraVac chillers: Designed and built to be the best; tested to prove it Ongoing innovation. Unmatched capabilities.

More information

ASHRAE CHAPTER TECHNOLOGY AWARD Illinois Chapter, Region VI

ASHRAE CHAPTER TECHNOLOGY AWARD Illinois Chapter, Region VI CHICAGO GRAND RAPIDS PHILADELPHIA DELHI AHMEDABAD ASHRAE CHAPTER TECHNOLOGY AWARD Illinois Chapter, Region VI Chinatown Branch Chicago Public Library 2100 South Wentworth Avenue Chicago, IL 60616 CHAPTER/REGIONAL

More information

Memo to the Planning Commission HEARING DATE: JULY 9, 2015

Memo to the Planning Commission HEARING DATE: JULY 9, 2015 Memo to the Planning Commission HEARING DATE: JULY 9, 2015 Case Nos.: Project Address: Zoning: 2006.1524EBXV; 2013.0276BX 350 MISSION STREET C-3-O(SD) (Downtown Office Special Development) Transit Center

More information

SUMMIT TECHNOLOGY CAMPUS 777 NW BLUE PARKWAY I 850 NW CHIPMAN ROAD LEE S SUMMIT MO 64086

SUMMIT TECHNOLOGY CAMPUS 777 NW BLUE PARKWAY I 850 NW CHIPMAN ROAD LEE S SUMMIT MO 64086 SUMMIT TECHNOLOGY CAMPUS 777 NW BLUE PARKWAY I 850 NW CHIPMAN ROAD LEE S SUMMIT MO 64086 INFALLIBLE INFRASTRUCTURE. The Summit Technology Campus is comprised of two buildings totaling approximately 1,037,000

More information

FAIRFIELD COUNTY S PREMIER TECHNOLOGY CENTER River Bend 2

FAIRFIELD COUNTY S PREMIER TECHNOLOGY CENTER River Bend 2 FAIRFIELD COUNTY S PREMIER TECHNOLOGY CENTER River Bend 2 River Bend 6 River Bend 11 RIVER BEND CENTER OVERVIEW 7 8 6 1 2 12 highly flexible buildings situated on 40 sprawling acres in the Springdale section

More information

DR and EE Standards for SCE Buildings

DR and EE Standards for SCE Buildings Design & Engineering Services DR and EE Standards for SCE Buildings Prepared by: Design & Engineering Services Customer Service Business Unit Southern California Edison December 2011 Acknowledgements Southern

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

Tier IV Standards as Specified in the TIA 942 Document

Tier IV Standards as Specified in the TIA 942 Document S No Architectural Proximity of visitor parking to data 18.3 m / 60 ft minimum separation with physical barriers to prevent vehicles from 1 center perimeter building walls driving closer 2 Building Construction

More information

The University of Arizona Biomedical Sciences Partnership Building

The University of Arizona Biomedical Sciences Partnership Building The University of Arizona Biomedical Sciences Partnership Building A CASE STUDY BY LEVEL 3 AUDIOVISUAL The Phoenix Biomedical Campus which is transforming 40 acres of downtown Phoenix, Arizona into a biomedical

More information

HVAC Energy Management System

HVAC Energy Management System HVAC Energy Management System Spotlight coordinates the complex tasks required by a building s heating, cooling, fresh air, humidification and lighting systems resulting in increased efficiencies. OVERVIEW

More information

Why would you ever use ordinary glass again?

Why would you ever use ordinary glass again? SmartGlass Active insulation technology Why would you ever use ordinary glass again? Introducing affordable energy efficient glass with active insulation technology. The latest advance in home insulation.

More information

Critical IT Facilities at the Edge

Critical IT Facilities at the Edge Critical IT Facilities at the Edge Mark Howell Global IT Facilities Planning & Engineering Ford Motor Company Critical IT Facilities at the Edge What are critical IT facilities at the Edge? Why are critical

More information

PoE Lighting Benefits and Design Considerations. Creating more meaningful connections in the digital building

PoE Lighting Benefits and Design Considerations. Creating more meaningful connections in the digital building PoE Lighting Benefits and Design Considerations Creating more meaningful connections in the digital building Introduction Smart devices, smart cars, smart grids, smart cities. More meaningful connections

More information

Sustainable Facility Design for Collaborative Research and Development

Sustainable Facility Design for Collaborative Research and Development Sustainable Facility Design for Collaborative Research and Development Dante Tedaldi, PhD, PE Directorate Head, Facilities Maintenance and Engineering SAIC-Frederick, Inc. May 09, 2013 DEPARTMENT OF HEALTH

More information

CCBC is equipped with 3 computer rooms, one at each main campus location:

CCBC is equipped with 3 computer rooms, one at each main campus location: Policy: Computer Room Procedures Policy: Draft 12/14/2009 1.0 Purpose The purpose of this document is to establish procedures for the Community College of Baltimore County (CCBC) Information Technology

More information

PROSPECTUS ALTERATION PHILLIP BURTON FEDERAL BUILDING & U.S. COURTHOUSE SAN FRANCISCO, CA

PROSPECTUS ALTERATION PHILLIP BURTON FEDERAL BUILDING & U.S. COURTHOUSE SAN FRANCISCO, CA Prospectus Number: PCA-0154-S F15 FY2015 Project Summary The General Services Administration () proposes a repair and alteration project to upgrade several building systems and reconfigure existing space

More information

J. Alstan Jakubiec Jeff Neimasz Modeling Dynamic Shading Devices with the DIVA Advanced Shading Module 1 / 30

J. Alstan Jakubiec Jeff Neimasz Modeling Dynamic Shading Devices with the DIVA Advanced Shading Module 1 / 30 Modeling Dynamic Shading Devices with the DIVA Advanced Shading Module J. Alstan Jakubiec alstan@solemma.net Jeff Neimasz jeff@solemma.net Modeling Dynamic Shading Devices with the DIVA Advanced Shading

More information

Downtown Denver Partnership Tenant Improvement

Downtown Denver Partnership Tenant Improvement 2018 ACE AWARDS Category 8: Best Building Project (General Contractor Under $10 Million) Downtown Denver Partnership Tenant Improvement PROJECT TEAM OWNER Downtown Denver Partnership GENERAL CONTRACTOR/

More information

World Class. Globally Certified. High Availability.

World Class. Globally Certified. High Availability. Intellicentre 2 World Class. Globally Certified. High Availability. Intellicentre 2 Macquarie Park, Sydney 2 Intellicentre 2 A new generation of data centre solutions. Australia s first showcase Tier III

More information

210,000 rsf Typical floorplate 67,549 rsf

210,000 rsf Typical floorplate 67,549 rsf Under Construction 3050 SOUTH DELAWARE STREET SAN MATEO Building Features Floor Plans Elevation Site Plan Location Map Amenities Timeline Signage Gallery 210,000 rsf Typical floorplate 67,549 rsf Robert

More information

Vantage 70 Frederick s Most Visible Location

Vantage 70 Frederick s Most Visible Location Vantage 70 Frederick s Most Visible Location The Vantage70 Advantage Located at the intersection of Interstates 70 and 270 just minutes from Frederick, MD s historic downtown, Vantage70 is the most visible

More information

August 2017 Welcome Design Topic Product Focus

August 2017 Welcome Design Topic Product Focus EngineeringAdvantage Newsletter August 2017 In This Issue: Welcome Design Topic Smart Buildings Product Focus Siemens Total Room Automation Welcome to Siemens EngineeringAdvantage Newsletter We hope you

More information

CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM

CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM 1. Category (Check one and indicate New or Existing, if applicable) Commercial Buildings New or Existing Institutional Buildings: Educational Facilities New

More information

6500 Harry Hines Boulevard Dallas, TX 75235

6500 Harry Hines Boulevard Dallas, TX 75235 CoStar-41051 LoopNet- 17906172 Xceligent -1379536 6500 Harry Hines Boulevard Dallas, TX 75235 Dallas Medical District Unique Site 5.31 Acres 81,000 + SF Offices Offered Exclusively by JacksonCooksey For

More information

N O W A V A I L A B L E

N O W A V A I L A B L E N O W A V A I L A B L E T I E R I I I + B U I L D T O S U I T D A T A C E N T E R University Research Park Charlotte, North Carolina Contact Doug Hollidge for more information Email: doug@five9sdigital.com

More information

Deferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M

Deferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M Landscape 1,340 acres, 66 miles of sidewalks, 20 miles of roads Irrigation state of the art central control system; 70 systems, 8 fountains, 4 underground storage systems Stormwater management 119 sites,

More information

TX1 230,000 SQ. FT. 16MW AVAILABLE NOW RAGINGWIRE DALLAS, TX 1MW, 2MW, 3MW AND 5MW 42 ACRE DATA CENTER CAMPUS CUSTOMIZABLE PRIVATE SUITES

TX1 230,000 SQ. FT. 16MW AVAILABLE NOW RAGINGWIRE DALLAS, TX 1MW, 2MW, 3MW AND 5MW 42 ACRE DATA CENTER CAMPUS CUSTOMIZABLE PRIVATE SUITES 230,000 SQ. FT. 16MW AVAILABLE NOW 42 ACRE DATA CENTER CAMPUS 1MW, 2MW, 3MW AND 5MW CUSTOMIZABLE PRIVATE SUITES 866-599-0998 info@ragingwire.com www.ragingwire.com ONE MILLION SQUARE FOOT DATA CENTER CAMPUS

More information

Ecotect is not intuitive. Finding the location of the tools and their purposes is very difficult and time consuming.

Ecotect is not intuitive. Finding the location of the tools and their purposes is very difficult and time consuming. Ecotect 1. Rebuild model in Ecotect. 2. Check surface normals. 3. Assign Properties: Materials for Occupied Spaces: Concrete Floor on Slab (Lobby only) Concrete Floor Suspended Acoustic Ceiling Tile Brick

More information

Deferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M

Deferred Maintenance Backlog is $907M State-supported $738M Exterior infrastructure $169M 1 Landscape 1,335 acres, 64 miles of sidewalks, 20 miles of roads Irrigation state of the art central control system; 70 systems, 8 fountains, 4 underground storage systems Stormwater management 119 sites,

More information

See operational efficiency in a whole new light The Redwood intelligent lighting network solution from CommScope. Intelligent Building Solutions

See operational efficiency in a whole new light The Redwood intelligent lighting network solution from CommScope. Intelligent Building Solutions See operational efficiency in a whole new light The Redwood intelligent lighting network solution from CommScope Intelligent Building Solutions Efficiency opportunities are as close as your ceiling Data

More information

PLAYBOOK. How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy

PLAYBOOK. How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy PLAYBOOK F O R C H A N G E How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy The world is becoming more digital every day. The demand for feature-rich,

More information

Energy Efficient Commercial Building Tax Deduction Internal Revenue Code Section 179D

Energy Efficient Commercial Building Tax Deduction Internal Revenue Code Section 179D Energy Efficient Commercial Building Tax Deduction Internal Revenue Code Section 179D May 5-6, 2016 Investment advisory services are offered through CliftonLarsonAllen Wealth Advisors, LLC, an SEC-registered

More information

Concord Hospital Infrastructure Upgrades Increased Energy and Operating Efficiencies with a Tangible Reduction in Operating Costs

Concord Hospital Infrastructure Upgrades Increased Energy and Operating Efficiencies with a Tangible Reduction in Operating Costs Concord Hospital Infrastructure Upgrades Increased Energy and Operating Efficiencies with a Tangible Reduction in Operating Costs Project: Concord Hospital Infrastructure Upgrades Facility Size: 600,000+

More information

DURO-LAST ROOFING, INC.

DURO-LAST ROOFING, INC. DURO-LAST ROOFING, INC. Duro-Last: Defining Rooftop Sustainability In the commercial roofing industry, reflectivity has been the dominant discussion point for several years, and the Duro-Last Cool Zone

More information

Philips helps create a comfortable, productive and sustainable environment at The Edge

Philips helps create a comfortable, productive and sustainable environment at The Edge Connected office lighting The Edge Case study Philips helps create a comfortable, productive and sustainable environment at The Edge The Edge is an innovative, multi-tenant office building in Amsterdam.

More information

Data Centers: The Case For Energy Risk Management and Energy Reliability

Data Centers: The Case For Energy Risk Management and Energy Reliability Data Centers: The Case For Energy Risk Management and Energy Reliability Author: Alberto Rios, Director Risk Management Published: July 2013 Acclaim Energy Advisors, (www.acclaimenergy.com), is a full-

More information

PRESS KIT. Who We Are SINGLE SOURCE SUPPLIER IN-HOUSE ENGINEERS AND R&D STAFF MADE IN THE U.S.A. CUSTOM DESIGNS THERMALLY ENHANCED PRODUCTS

PRESS KIT. Who We Are SINGLE SOURCE SUPPLIER IN-HOUSE ENGINEERS AND R&D STAFF MADE IN THE U.S.A. CUSTOM DESIGNS THERMALLY ENHANCED PRODUCTS Who We Are SINGLE SOURCE SUPPLIER Single source supplier of aluminum, wood, and vinyl composite glazing systems; creating consistency throughout your project. IN-HOUSE ENGINEERS AND R&D STAFF Our in-house

More information

Summary Information. Demographic Profile

Summary Information. Demographic Profile Summary Information 8526 S. W. Kansas Ave. (Unit B-4 Building B) Parcel ID: 08-39-41-005-002-00040-0 Lease amount: $12 PSF (annual) Property Taxes, Condominium Assessments, Trash Removal and Water Included.

More information

Smart Buildings and Connected Lighting: The Perfect Partnership. February, 2018

Smart Buildings and Connected Lighting: The Perfect Partnership. February, 2018 Smart Buildings and Connected Lighting: The Perfect Partnership February, 2018 1 Who I Am John O Connell Director of End User Systems & Services Office & Industry 2 2 Businesses in North America could

More information

50 Years of Facility Operations or Rebuilding from the inside out

50 Years of Facility Operations or Rebuilding from the inside out 50 Years of Facility Operations or Rebuilding from the inside out National Optical Astronomy Observatory (NOAO) NORTH Kitt Peak National Observatory and Tucson Headquarters Facility Presented by John Dunlop

More information

Twin Core Data Center Munich

Twin Core Data Center Munich Twin Core Data Center Munich T-Systems Data Center Munich Sister Site, Back Up Location/Twin Core DC ALL (Allach) 1st Route: 13km DWDM System 2nd Route: 27km DC EIP (Euro Industrie Park) Point to Point

More information

SerraGlaze Q&A. What is SerraGlaze? Why do you want it? How does it work?

SerraGlaze Q&A. What is SerraGlaze? Why do you want it? How does it work? Harnessing the Power of Daylight SerraGlaze Q&A SerraLux is in the business of daylighting, and our product is called SerraGlaze. We will begin the discussion with three questions, each of which will be

More information

DISASTER RECOVERY CAPABILITIES

DISASTER RECOVERY CAPABILITIES DISASTER RECOVERY CAPABILITIES We are there for our clients whenever disaster strikes. Golden Sands Disaster Recovery & Business Continuity division provides strategies, solutions, and comprehensive resources

More information

LaGuardia Community College

LaGuardia Community College Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2018-19 through FY 2022-23 Project Funding Type Five - Year Plan Total ( $ 000 s ) Center 3 Infrastructure Upgrade

More information

Green Computing and Sustainability

Green Computing and Sustainability Green Computing and Sustainability Damien Lecarpentier (CSC) einfranet Workshop, Brussels, 15th April 2010 CSC Tieteen tietotekniikan keskus Oy CSC IT Center for Science Ltd. 1 Green Computing: a hot topic

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

REPORT. Energy Efficiency of the San Diego Supercomputer Center and Distributed Data Centers at UCSD. Prepared for:

REPORT. Energy Efficiency of the San Diego Supercomputer Center and Distributed Data Centers at UCSD. Prepared for: REPORT Energy Efficiency of the San Diego Supercomputer Center and Distributed Data Centers at UCSD Prepared for: San Diego Supercomputer Center 10100 John J Hopkins Drive San Diego, CA 92037 May 11, 2009

More information

Hines Buildings. Phoenix, Arizona

Hines Buildings. Phoenix, Arizona Hines Buildings Phoenix, Arizona Hines Buildings Earn US EPA/DOE Energy Star Label for Buildings Of the four buildings in the Phoenix/Tempe metropolitan area that have earned the U.S. EPA/DOE Energy Star

More information

8505 Baycenter Road Jacksonville, FL

8505 Baycenter Road Jacksonville, FL Your Company Name Here 8505 Baycenter Road Jacksonville, FL OFFERING SUMMARY Newmark Grubb Knight Frank is pleased to offer 8505 Baycenter to the market for purchase or master lease. This Robert C. Broward

More information

Committed to Energy Efficiency

Committed to Energy Efficiency RESOLUTE Resolute Helps PNC Arena Reduce Energy Consumption and Costs While Improving Fan Comfort Lacking the visibility, real-time data and analytics needed to optimize facility performance and reduce

More information

Russ Building. Modern office space in an Historic Building. About. Property Facts. Property Features LEASING CONTACT

Russ Building. Modern office space in an Historic Building. About. Property Facts. Property Features LEASING CONTACT www.russbldg.com Modern office space in an Historic Building About The is a California State Historic Landmark. Constructed in 1927, the building has a neo-gothic architectural design giving it a majestic

More information

A Natural Workspace. Tucked away among 35 wooded acres, located in the center of it all.

A Natural Workspace. Tucked away among 35 wooded acres, located in the center of it all. Where Nature Works Where Nature Works A Natural Workspace Tucked away among 35 wooded acres, located in the center of it all. 400,000 SF expandable to over 700,000 SF Adjacent outdoor park & nature Expansion

More information

The Road to Net Zero. Bill Glover. Deputy Laboratory Director and Chief Operating Officer. The Sustainable Operations Summit.

The Road to Net Zero. Bill Glover. Deputy Laboratory Director and Chief Operating Officer. The Sustainable Operations Summit. The Road to Net Zero Bill Glover Deputy Laboratory Director and Chief Operating Officer The Sustainable Operations Summit May 16, 2011 NREL/PR-6A42-51124 NREL is a national laboratory of the U.S. Department

More information

CenterPoint Energy Retro-Commissioning Program Application

CenterPoint Energy Retro-Commissioning Program Application CenterPoint Energy Retro-Commissioning Program Application CenterPoint Energy Retro-Commissioning Program is offered to Commercial and Industrial customers in our service territory to enhance their facility

More information

DESIGN-BUILD FOR MISSION CRITICAL FACILITIES

DESIGN-BUILD FOR MISSION CRITICAL FACILITIES DESIGN-BUILD FOR MISSION CRITICAL FACILITIES Case Study: California ISO Iron Point Facility Folsom, CA MISSION POSSIBLE Mission Critical Headquarters Design-Build Delivery Delivered Early Delivered Under

More information

City Reso-A Requests FY 2018 (City Council and Borough Presidents)

City Reso-A Requests FY 2018 (City Council and Borough Presidents) Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2017-18 through FY 2021-22 Project Funding Type Five-Year Plan Total ($ 000s) Replacement of Unit Ventilation

More information