SRP Ten Year Transmission Plan

Size: px
Start display at page:

Download "SRP Ten Year Transmission Plan"

Transcription

1 2018 SRP Ten Year Transmission Plan Prepared for the Arizona Corporation Commission January 2018 Docket No. E-00000D Page1 Page1

2 Table of Contents 1. Introduction Planning Organizations Regional Planning Organizations Western Electricity Coordinating Council (WECC) WestConnect Subregional Planning Group Southwest Area Transmission (SWAT) Biennial Transmission Assessment (BTA) Order Requirements th BTA Order Requirements Prior BTA Order Requirements SRP Ten Year Transmission Plan Study Work Changes from Previous Plan Projects Placed in Service in Revised Projects New Projects Removed Projects Potential Projects Project Maps Figure 1 SRP 500kV System Figure 2 SRP 230kV System West Figure 3 SRP 230kV System East Figure 4 SRP 115kV System (Eastern Mining Area) Project Descriptions Browning Corbell 230kV & Santan Rogers 230kV Line Reconfiguration (2019) Coolidge Hayden 115kV Reroute (2020) SunZia Southwest Transmission 500kV Project (2021) Price Road Corridor (2021) Abel Pfister Ball 230kV (2021-TBD) Copper Crossing Abel 230kV (2023) Southeast Power Link (2024) Hassayampa Pinal West 500kV #2 Line (2024) Silver King New Oak Flat New Superior 230kV (2026) Superior Silver King 115kV Reroute (2027) Attachment Attachment Ten Year Plan Technical Study SRP Ten Year Transmission Plan i

3 1. Introduction This report updates and replaces the Ten Year Transmission Plan of the Salt River Project Agricultural Improvement and Power District (SRP), submitted in January 2017 pursuant to A.R.S. Section Plans; filing; failure to comply; classification. The plan describes planned transmission line projects of 115kV or higher that SRP may construct or participate in over the next ten years. SRP Ten Year Transmission Plan Page 1 of 25

4 2. Planning Organizations SRP continues to be involved in regional and subregional planning organizations. SRP s primary goal in these various planning activities is to ensure that a reliable and economical transmission system is connected to energy sources. Participation also allows SRP to coordinate its transmission plans with the plans of the other transmission providers. 2.1 Regional Planning Organizations Western Electricity Coordinating Council (WECC) WECC is a non-profit corporation approved by the Federal Energy Regulatory Commission (FERC) to serve as the Regional Entity tasked with assuring a reliable bulk electric system in the geographical area known as the Western Interconnection. SRP is an active participant in the WECC committees that develop and integrate new system and generation models, develop WECC-wide base cases, develop WECC reliability criteria, and coordinate planning methodologies WestConnect SRP participates in the regional transmission planning activities of WestConnect. WestConnect is comprised of utility companies and independent transmission developers with transmission assets or potential transmission projects in the western United States. Its members collaboratively assess stakeholder needs and develop cost-effective transmission enhancements. WestConnect is committed to coordinating its work with other regional and interregional industry efforts to ensure consistency within the Western Interconnection. SRP continues to be an active participant in the WestConnect regional transmission planning and cost allocation processes established by FERC Order No In August 2016, the 5 th Circuit Court of Appeals vacated FERC s Compliance Orders on the WestConnect Order 1000 process. The WestConnect utilities continue to work through the regional transmission planning process while they wait for FERC to reassess the compliance orders. While SRP is not required to participate in the Order No process, SRP recognizes the importance of maintaining a collaborative and cooperative transmission planning process in the Western Interconnection. The Order No planning process began January 1, 2015 with an abbreviated, one-year planning cycle. The regular, biennial regional transmission planning process began January 1, The outcome of Order No regional transmission planning is a regional transmission plan that selects regional transmission projects to meet identified reliability, economic, or public SRP Ten Year Transmission Plan Page 2 of 25

5 policy transmission needs. The regional participants did not identify any transmission needs in the Regional Transmission Plan Subregional Planning Group Southwest Area Transmission (SWAT) The SWAT Subregional Planning Group addresses future transmission needs on a subregional (desert southwest) basis. SRP participates in SWAT activities to help meet obligations for the Arizona Corporation Commission (ACC) and the Ten Year Transmission Plan filing. SWAT disseminates its work publicly and coordinates its studies and data with other subregional planning groups and WestConnect. 1 WestConnect 2017 Regional Transmission Plan is available at: SRP Ten Year Transmission Plan Page 3 of 25

6 3. Biennial Transmission Assessment (BTA) Order Requirements 3.1 9th BTA Order Requirements On November 21, 2016, the ACC issued Decision No , which suspended the requirement from the 8 th BTA that required utilities to provide the anticipated load level range at which each transmission project may be needed. Consistent with the 8 th BTA, utilities must continue to describe whether each project is driven by load growth or reliability. Factors driving each of SRP s transmission projects may change over time as resource plans change. 3.2 Prior BTA Order Requirements The following sections highlight SRP s responses to ongoing activities related to prior BTA orders. As ordered by the ACC in its 7 th BTA decision, entities are required to notify parties requesting generation or transmission interconnections to the Bulk Electric System of the appropriate ACC filing requirements. SRP placed an advisory notice on SRP s OASIS page on March 19, 2013 to satisfy this requirement: This notice continues to meet the requirements of the 7 th BTA that was further affirmed in the 8 th and 9 th BTAs. SRP does not take responsibility for any third-party interconnector s compliance with ACC requirements. The ACC s 6 th BTA order adopted several requirements that remain in force. The ongoing requirements include: a) Report relevant findings in future BTAs regarding compliance with transmission planning standards (e.g. TPL-001 through TPL-004) 2 from NERC/WECC reliability audits that have been finalized and filed with FERC. SRP was last audited on its compliance with NERC Standards TPL-001-0, TPL , and TPL in August The WECC Audit team determined that SRP is in compliance with these three Standards. The next audit of TPL has not been scheduled. b) Identify planned transmission reconductor projects, transformer capacity upgrade projects, and reactive power compensation facility additions at 115kV and above in ten year plan filings. 2 NERC Standards TPL-001 through TPL-004 have been replaced with TPL SRP Ten Year Transmission Plan Page 4 of 25

7 SRP s planned transmission reconductor, transformer capacity upgrades, and reactive power compensation additions in this ten year period are shown below. In-service dates may change to reflect load changes in the local system. Reactive Devices SRP s planned reactive device addition and anticipated in-service year: 18 Ohm Series Reactors on Palo Verde Hassayampa 500kV Ties #1-3 (2020) Transformers SRP s planned transformer additions to existing stations to accommodate load growth and anticipated in-service year: Rudd 230/69kV Transformer (2022) Browning 230/69kV Transformer (2024) Reconductor SRP does not have any planned reconductor projects. c) Discuss the effects of distributed renewable generation and energy efficiency programs on future transmission needs in ten year plan filings. SRP includes the effects of energy efficiency programs and distributed generation (traditional and renewable) in its resource planning and transmission system models. Thus, each of the transmission projects identified in the Ten Year Transmission Plan includes the effects of energy efficiency and distributed generation. In addition, the 8 th BTA (Decision No , dated October 24, 2014) called for a technical study to analyze the effects of removing DG and EE. To comply with this order, SRP is analyzing the effects of DG and EE through a separate study that will be reported for the upcoming 10 th BTA. SRP Ten Year Transmission Plan Page 5 of 25

8 4. SRP Ten Year Transmission Plan Study Work Attachment 1 contains the 2018 Ten Year Transmission Plan Technical Study. This study analyzed the reliability impacts of the projects identified in the Ten Year Transmission Plan. Study work for joint projects is covered by subregional planning groups. SRP Ten Year Transmission Plan Page 6 of 25

9 5. Changes from Previous Plan The following changes are noted between the Ten Year Transmission Plan submitted in January 2017 and this submittal. The changes include project or substation names, in-service dates, projects now in service, and newly identified projects. 5.1 Projects Placed in Service in 2017 SRP s placed the following projects in service in 2017: 12 Ohm Series Reactors on Palo Verde Hassayampa 500kV Ties # Revised Projects Revised Project 2017 Plan 2018 Revision Price Road Corridor 2019 TBD 2021 TBD Southeast Power Link TBD Mesa Technology Corridor Copper Crossing Abel 230kV Superior Silver King 115kV Reroute Southeast Power Link 5.3 New Projects SRP did not add any new projects. 5.4 Removed Projects SRP did not remove any projects. 5.5 Potential Projects The following projects were included in previous plans with TBD in-service dates and have not advanced in SRP s planning process. In order to provide further transparency, SRP will continue to reflect these and other projects under consideration that fall outside of the ten year planning window as Potential Projects in future filings. SRP Ten Year Transmission Plan Page 7 of 25

10 Potential Project Eastern Mining Expansion Superior 230kV Loop-in Thunderstone Browning 230kV Silver King Knoll New Hayden 230kV New Hayden 115kV Loop-in RS25 Project RS26 Project Pinal Central Abel RS kV Palo Verde Saguaro 500kV Ball (RS17) 230kV Loop-in Pinnacle Peak Brandow 230kV Abel 500kV Substation Purpose Accommodate growing mining customer load in SRP s Eastern Mining Area. Provide adequate transmission capacity in the event of future load growth in SRP s eastern service territory. Provide additional transfer capability from the south and east to the north and central areas of SRP s service territory. Increase the transmission capacity to serve new customer load in SRP s eastern service territory. Increase the transmission capacity to serve new customer load in SRP s eastern service territory. Serve growing Salt River Pima Maricopa Indian Community load. Serve load growth in the Fountain Hills area and to relieve stress on the lower voltage system that serves the Fountain Hills/Rio Verde area. Deliver remote resources into the southeast portion of SRP s service territory. Increase the adequacy of the existing EHV transmission system and permit increased power delivery throughout the state. Serve customer load in the Gilbert/Queen Creek area. Provide adequate transmission capacity to accommodate SRP customer load. Provide adequate transmission capacity for future load growth. SRP Ten Year Transmission Plan Page 8 of 25

11 6. Project Maps This section includes maps showing the general location of existing and future transmission projects. Substation locations and line routings depict an electrical connection only and do not reflect any assumed physical locations or routing. Separate maps are provided for the 500kV system (Figure 1), the 230kV System West (Figure 2), the 230kV System East (Figure 3), and the 115kV system (Figure 4). The 115kV map primarily covers the 115kV Eastern Mining Area of SRP s service territory; however, some 230kV projects are also included. SRP Ten Year Transmission Plan Page 9 of 25

12 6.1 Figure 1 SRP 500kV System Substation locations and line routings depict an electrical connection only and do not reflect any assumed physical locations or routing. SRP Ten Year Transmission Plan Page 10 of 25

13 6.2 Figure 2 SRP 230kV System West Substation locations and line routings depict an electrical connection only and do not reflect any assumed physical locations or routing. SRP Ten Year Transmission Plan Page 11 of 25

14 6.3 Figure 3 SRP 230kV System East Substation locations and line routings depict an electrical connection only and do not reflect any assumed physical locations or routing. SRP Ten Year Transmission Plan Page 12 of 25

15 6.4 Figure 4 SRP 115kV System (Eastern Mining Area) Substation locations and line routings depict an electrical connection only and do not reflect any assumed physical locations or routing. SRP Ten Year Transmission Plan Page 13 of 25

16 7. Project Descriptions This section includes project details in accordance with the requirements of A.R.S. Section Plans; filing; failure to comply; classification. Each project is identified by name, estimated in-service date, sizing details, routing, purpose, and major milestone dates. SRP Ten Year Transmission Plan Page 14 of 25

17 7.1 Browning Corbell 230kV & Santan Rogers 230kV Line Reconfiguration (2019) Size Browning Corbell Voltage 230kV 230kV Santan Rogers Capacity To be determined To be determined Point of Origin Browning 230kV Substation SEC 12, T1S, R7E Intermediate Point NA NA Point of Termination Corbell 230kV Substation SEC 10, T1S, R5E Santan 230kV Substation SEC 21, T1S, R6E Rogers 230kV Substation SEC 13, T1N, R5E Length Approximately 130 feet Approximately 70 feet Routing The Browning Corbell line reconfiguration will follow the current route of the Browning Santan and Santan Corbell 230kV lines. The Santan Rogers line reconfiguration will follow the current route of the Santan Thunderstone 230kV line. This project will use existing circuit positions on existing structures. Reconfiguration of these two lines will be done in tandem. Purpose To create a third 230kV circuit serving the Corbell 230/69kV substation and prevent the loss of the Corbell 69kV area in the event of multiple 230kV line outages. This is a reliability driven project and is not triggered by rising system load levels forecasted in the next ten years. Schedule Notes Right of Way / Property Acquisition NA Construction Start 2018 Estimated In-Service 2019 The in-service year for this project advanced from 2020 to 2019 to coincide with other 2019 projects that mitigate short circuit fault current issues at Kyrene 230kV. Together, the projects mitigate short circuit problems without causing any thermal overloads on the system. A CEC is not expected to be needed at this time. SRP Ten Year Transmission Plan Page 15 of 25

18 7.2 Coolidge Hayden 115kV Reroute (2020) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 115kV To be determined Coolidge 115kV Substation SEC 16, T1S, R13E None N/A this is a reroute of an intermediate portion of the line. SEC 16, T1S, R13E Approximately 1.5 miles The portion of the line that may be relocated begins about 0.5 miles northeast of the Coolidge substation and runs north along the Union Pacific Railroad until it crosses the Gila River where it turns northeast following a canal and drainage feature. The portion to be rerouted is 1.25 miles in length. The new line will be from 1.25 to 2.0 miles long. Purpose A short segment of the subject 115kV line is located on Gila River Indian Community (GRIC) land. SRP is negotiating an extension of the current land grant for the line. SRP may elect to move this portion of the line onto private land if negotiations with the GRIC are unsuccessful or if SRP determines it is in the best interest of its customers. Schedule Right of Way / Property Acquisition Notes 2019 Construction Start 2020 Estimated In-Service 2020 SRP plans to pursue a CEC for this project in 2018 if negotiations with the GRIC are unsuccessful. SRP will begin the relocation of the impacted portion of the line once a certificate is received. SRP Ten Year Transmission Plan Page 16 of 25

19 7.3 SunZia Southwest Transmission 500kV Project (2021) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing Two single-circuit 500kV AC lines WECC Approved Rating of 3000MVA Central New Mexico Willow 500kV Substation Pinal Central 500kV Substation SEC 30, T6S, R8E 515 miles From Lincoln County area in central New Mexico to the Willow 500kV substation 15 miles north of Bowie, Arizona to Pinal Central 500kV substation in Coolidge, Arizona. Purpose SRP s interest in this project is to provide the opportunity to develop additional transmission from existing generation sources in eastern Arizona and western New Mexico to serve load in central Arizona. Schedule Notes Right of Way / Property Acquisition Construction Start Estimated In-Service 2021 In progress To be determined Southwestern Power Group is the project manager on the development of this project. SRP is a participant. SRP Ten Year Transmission Plan Page 17 of 25

20 7.4 Price Road Corridor (2021) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 230kV To be determined Knox 230kV Substation SEC 32, T1S, R4E None New Henshaw 230kV Substation SEC 7, T2S, R5E Approximately 7 miles The final line route was determined through the CEC process. The project consists of a new double circuit 230kV line from the existing Knox Substation to the new Henshaw Substation. Henshaw will be located near to the intersection of Price Road and Germann Road in Chandler. Purpose To serve growing industrial and commercial customer loads along the Price Road Corridor, adjacent to Price Road in Chandler. Schedule Notes Right of Way / Property Acquisition Construction Start Mid 2019 Estimated In-Service 2021: Knox Henshaw 230kV Line 2021: Henshaw 230kV Substation SRP received a CEC for this project by unanimous approval by the Arizona Corporation Commission line siting committee on September 12, 2017 Case No.00175, Decision # The CEC expires in September SRP Ten Year Transmission Plan Page 18 of 25

21 7.5 Abel Pfister Ball 230kV (2021-TBD) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 230kV To be determined Santan Schrader 230kV Line (near existing Moody 69kV substation and future Ball (RS-17) 230kV substation) SEC 1, T2S, R6E New Pfister (RS-24) 230kV Substation SEC 25, T2S, R7E Abel 230kV Substation SEC 19, T3S, R9E Approximately 20 miles This project is a double circuit 230kV line that bisects and connects the existing Santan Schrader 230kV line #2 to Abel 230kV Substation. The new double circuit 230kV line will be routed generally south and east from a point on the Santan Schrader 230kV line near the existing Moody 69kV substation and future Ball (RS-17) 230kV substation to the new Pfister (RS-24) 230kV substation in the southeastern portion of the town of Queen Creek. From the Pfister 230kV substation, the 230kV line will continue south and east to the Abel 230kV substation. Purpose This project was originally proposed to serve long-term load growth in the southeast valley. Load growth remains a driver for this project. However, the current timeline reflects a nearterm reliability need driven by new generation resources connecting near Abel Substation. Schedule Notes Right of Way/ Property Acquisition Construction Start Estimated In-Service 2021: Abel Santan 230kV Line 2021: Abel Schrader 230kV Line TBD: Pfister 230kV Substation TBD: Ball 230kV Substation This project was formerly known as Abel Moody. SRP received a CEC for this project on December 23, 2009, Case No. 148, Decision # The CEC expires December 23, The Pfister 230kV and Ball 230kV substations in-service dates are TBD depending on load growth in the Queen Creek area. SRP Ten Year Transmission Plan Page 19 of 25

22 7.6 Copper Crossing Abel 230kV (2023) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 230kV To be determined New Copper Crossing Energy Center SEC 24, T3S, R8E NA Abel 230kV Substation SEC 19, T3S, R9E Less than 1 mile This project is a double circuit 230kV line to connect new generation units to Abel 230kV substation. Purpose To accommodate near term new generation resources connecting in the Abel area. This is a reliability driven project and is not triggered by rising system load levels forecasted in the next ten years. Schedule Right of Way / Property Acquisition NA Construction Start Estimated In-Service 2023: Copper Crossing Energy Center Abel 230kV Line #1 2024: Copper Crossing Energy Center Abel 230kV Line #2 Notes If the installed generation capacity is over 925 MW, a new 230kV switchyard will need to be built near Abel Substation in order to limit the amount of generation loss from a single contingency. SRP Ten Year Transmission Plan Page 20 of 25

23 7.7 Southeast Power Link (2024) Size Voltage Capacity Point of Origin Intermediate Point Intermediate Point Point of Termination Length Routing 230kV To be determined Section of Santan Browning 230kV Line SEC 9, T1S, R7E RS kV Substation TBD RS kV Substation (if needed) TBD Section of Abel Pfister Ball 230kV Line SEC 10, T2S, R7E TBD Several options are under consideration to accommodate potential southeast valley load growth in the City of Mesa and the Town of Queen Creek. The analysis indicates that adding one or two new 230kV substations and a connection between the existing Santan Browning corridor to the future Abel Pfister Ball corridor would provide the greatest benefit to the area. The location of the 230kV substations and any new lines will be determined by the public siting process and load growth in the area. Purpose To meet potential growing customer loads in the southeast valley. Schedule Notes Right of Way / Property Acquisition 2019 Construction Start 2022 Estimated In-Service 2024 SRP does not yet hold a CEC for this project but plans to begin pursuing one in Construction of the facilities will be dependent upon the load growth in this area. This project was formerly identified as the Mesa Technology Corridor. SRP Ten Year Transmission Plan Page 21 of 25

24 7.8 Hassayampa Pinal West 500kV #2 Line (2024) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 500kV TBD Hassayampa 500kV Switchyard SEC 15, T1S, R6W Jojoba 500kV Switchyard SEC 25, T2S, R4W Pinal West 500kV Switchyard SEC 18, T5S, R2E Approximately 51 miles South and east of the Hassayampa Switchyard along the existing Palo Verde Kyrene 500kV line to a point where the gas pipeline splits from the transmission line, then generally along the pipeline (except in the Maricopa County Mobile Planning Area) to the Pinal West 500kV switchyard. Purpose The Central Arizona Transmission System study identified system additions to provide access to new generation in western or central Arizona. This project is needed as a result of the EPA ruling on Section 111(d) of the Clean Air Act (October 23, 2015), establishing emission performance rates representing the best system of emission reduction. This project can accommodate increased access to existing and potentially new load growth; however, future load growth was not identified as a driver. This is a reliability driven project not triggered by system load forecasts within the next ten years. Schedule Notes Right of Way / Property Acquisition 2004 Construction Start 2023 Estimated In-Service 2024 The CEC for Case No. 124 was awarded in May 2004 (ACC Decision # 67012). The CEC expires May 24, The first of the two permitted transmission lines was placed in service in October SRP Ten Year Transmission Plan Page 22 of 25

25 7.9 Silver King New Oak Flat New Superior 230kV (2026) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 230kV To be determined Silver King 230kV Substation SEC 16, T1S, R13E New 230kV Substation near the existing Oak Flat 115kV Substation, tentatively named New Oak Flat Near SEC32, T1S, R13E (exact location not determined) New 230kV Substation near the existing Goldfield Silver King 230kV line, tentatively named New Superior Near SEC34, T1S, R12E (exact location not determined) Approximately 6.5 miles The alignment will closely follow the existing 115kV circuit connecting Silver King to Oak Flat. The line starts at the Silver King Receiving Station, heading south and then turning southwest into the New Oak Flat 230kV Substation. The alignment will then traverse to the west into the New Superior 230kV Substation. In addition, the existing Goldfield Silver King 230kV line will be looped into the New Superior 230kV Substation. The location of the New Oak Flat and the New Superior sites are still being determined. Purpose To serve growing customer loads at Oak Flat and Superior. Schedule Notes Right of Way / Property Acquisition N/A Construction Start 2024 Estimated In-Service 2026 SRP does not yet hold a CEC for this project. SRP will pursue a Certificate when required by load growth in this area. SRP Ten Year Transmission Plan Page 23 of 25

26 7.10 Superior Silver King 115kV Reroute (2027) Size Voltage Capacity Point of Origin Intermediate Point Point of Termination Length Routing 115kV Approximately 165MVA Point on existing Superior Silver King 115kV Line SEC 34, T1S, R12E None Point on existing Superior Silver King 115kV Line SEC 26, T1S, R12E Approximately 1.25 miles The new alignment will traverse to the north and west of the historical line and adjacent to the existing Goldfield Silver King 230kV circuit. Purpose To move an existing 115kV line on a single Customer s private property to accommodate Customer s land use needs. This is a single customer driven and requested project and is not triggered by system load growth. Schedule Notes Right of Way / Property Acquisition None Construction Start 2027 Estimated In-Service 2027 SRP was granted a CEC for Case No. 166 on October 4, 2012 (Decision # 73551) which expired in 5 years (October 16, 2017). An extension to the CEC termination date was submitted in July If approved, the CEC will be extended through The actual timing of the 115kV line relocation is dependent upon the Customer s land use needs. SRP Ten Year Transmission Plan Page 24 of 25

27 8. Attachment 8.1 Attachment Ten Year Transmission Plan Technical Study SRP Ten Year Transmission Plan Page 25 of 25

P. O. Box 52025, MS POB100 Phoenix, Arizona (602) Feb 9, 2018

P. O. Box 52025, MS POB100 Phoenix, Arizona (602) Feb 9, 2018 P. O. Box 52025, MS POB100 Phoenix, Arizona 85072-2025 (602) 236-8788 philip.augustin@srpnet.com Feb 9, 2018 Peter Mackin Chair, WECC Studies Subcommittee Utility System Efficiencies, Inc. Phone: (916)

More information

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D (.laps Lisa Malagon Leader Federal and State Compliance Mail Station 9704 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250- 5671 Elisa.Malagon@aps.com January 31, 2014 Docket Control Arizona Corporation

More information

TUCSON ELECTRIC POWER COMPANY TEN YEAR PLAN FOR YEARS

TUCSON ELECTRIC POWER COMPANY TEN YEAR PLAN FOR YEARS TEN YEAR PLAN FOR YEARS 2012-2021 SUBMITTED TO THE ARIZONA CORPORATION COMMISSION JANUARY 2012 DOCKET NO: E-00000D-11-0017 CONTENTS INTRODUCTION... 3 Tortolita 500/138kV Transformer T3... 13 Vail 345/138kV

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011 Western DSW Planning Stakeholder Meeting (Western OATT Attachment P) June 9, 2011 Agenda: 1. Welcome and Introductions of Attendees 2. Planning Process 3. Interconnection Requests 4. Comments/questions

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group SUNZIA SOUTHWEST TRANSMISSION PROJECT David Getts General Manager SouthWestern Power Group PROJECT UPDATE NEW MEXICO RETA 8.22.12 SouthWestern Power Group Independent developer of utility-scale generation

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013

Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Mark W. Maher Chief Executive Officer Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Agenda WECC Overview WECC Strategic Planning Initiative Western Interconnection Synchrophasor

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Presentation to Local/State/Federal Agency Mtg November 10, 2015

Presentation to Local/State/Federal Agency Mtg November 10, 2015 Presentation to Local/State/Federal Agency Mtg November 10, 2015 Summary Proposed 114 mile 500 kv transmission project that will connect with Delaney Substation near Palo Verde Nuclear Generating Station,

More information

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019

Introduction. ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019 ADSTF Report of Lessons Learned from the Implementation of the 2028 ADS Anchor Data Set Task Force February 22, 2019 Introduction Throughout 2015 and 2016 the structure of committees in the Western Electricity

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

History of NERC January 2018

History of NERC January 2018 History of NERC January 2018 Date 1962 1963 The electricity industry created an informal, voluntary organization of operating personnel to facilitate coordination of the bulk power system in the United

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

TransWest Express and Gateway South

TransWest Express and Gateway South TransWest Express and Gateway South Co-developed by four leading entities: Arizona Public Service PacifiCorp National Grid Wyoming Infrastructure Authority Regional Stakeholder Meeting January 23, 2008

More information

BPA and NERC, WECC, ERO

BPA and NERC, WECC, ERO BPA and NERC, WECC, ERO March 2006 1 Reliability Organizations BPA has relationship with two reliability organizations: 1. North American Electric Reliability Council (NERC) 2. Western Electric Coordinating

More information

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Hetch Hetchy Water and Power of the City and County of San Francisco Joint Transmission Planning Base Case Preparation Process This is a living document. Please

More information

NERC History, Mission and Current Issues Southern States Energy Board. October 16, 2011

NERC History, Mission and Current Issues Southern States Energy Board. October 16, 2011 NERC History, Mission and Current Issues Southern States Energy Board October 16, 2011 Electricity Vital to America 2 RELIABILITY ACCOUNTABILITY Risk Curve with Actual Events Severity ( Log Base 10) 2003

More information

History of NERC December 2012

History of NERC December 2012 History of NERC December 2012 Timeline Date 1962-1963 November 9, 1965 1967 1967-1968 June 1, 1968 July 13-14, 1977 1979 1980 Description Industry creates an informal, voluntary organization of operating

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

Cyber Security Standards Drafting Team Update

Cyber Security Standards Drafting Team Update Cyber Security Standards Drafting Team Update Michael Assante, VP & Chief Security Officer North American Electric Reliability Corp. February 3, 2008 Overview About NERC Project Background Proposed Modifications

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

RELIABILITY OF THE BULK POWER SYSTEM

RELIABILITY OF THE BULK POWER SYSTEM RELIABILITY OF THE BULK POWER SYSTEM Jim Burley, VP of Compliance, Mitigation and Standards October 26, 2011 Promoting RELIABILITY and Mitigating RISKS to the Bulk Power System Context In the Beginning-2003

More information

The Blue Line Extension

The Blue Line Extension The Blue Line Extension NORTH CAROLINA JOINT TRANSPORTATION OVERSIGHT COMMITTEE Presented by Carolyn Flowers CATS Chief Executive Officer Raleigh, NC February 10, 2012 Overview Charlotte Area Transit System

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES PROOF OF SERVICE NOTICE TO COMMUNITY ORGANIZATIONS PUBLIC NOTICE NOTICE IN UTILITY BILLS NOTICE OF OWNERS OF PROPERTY

More information

MISO-PJM Cross-Border Planning. February 19, 2014 MISO-PJM JCM

MISO-PJM Cross-Border Planning. February 19, 2014 MISO-PJM JCM MISO-PJM Cross-Border Planning February 19, 2014 MISO-PJM JCM Planning Issues at the Seam 2 Background JOA Historical and Projected Congestion Study - 2012 to 2014 Future Scenario based 80+ major project

More information

Warrenton Wheeler Gainesville 230kV Reliability Project

Warrenton Wheeler Gainesville 230kV Reliability Project Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three

More information

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator Assembly Standing Committee on Energy Kevin A. Cahill, Chairman Assembly Standing Committee on Corporations, Authorities and Commissions James F. Brennan, Chairman Assembly Standing Committee on Cities

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

History of NERC August 2013

History of NERC August 2013 History of NERC August 2013 Timeline Date 1962 1963 November 9, 1965 1967 1967 1968 June 1, 1968 July 13 14, 1977 1979 Description The electricity industry creates an informal, voluntary organization of

More information

A. Introduction. B. Requirements and Measures

A. Introduction. B. Requirements and Measures A. Introduction 1. Title: Communications 2. Number: COM-001-3 3. Purpose: To establish Communication capabilities necessary to maintain reliability. 4. Applicability: 4.1. Functional Entities: 4.1.1. Transmission

More information

Minnesota Hosting Capacity Analysis

Minnesota Hosting Capacity Analysis Minnesota Hosting Capacity Analysis MIPSYCON November 8, 2017 Chris Punt, P.E. Outline What is Hosting Capacity? Background DRIVE Results Visualization Accuracy Timeline Next Steps 2 What is Hosting Capacity?

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1 DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

Compliance Enforcement Initiative

Compliance Enforcement Initiative Compliance Enforcement Initiative Filing and Status Update November 2, 2011 Rebecca Michael Status of the Filings NERC filed several components of the Compliance Enforcement Initiative on September 30,

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NARUC Energy Regulatory Partnership Program The Public Services Regulatory Commission of Armenia and The Iowa Utilities Board Janet Amick Senior Utility

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

Reston Town Center North Development. Community Update

Reston Town Center North Development. Community Update Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive

More information

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document Decision 2014-271 Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014 The Alberta Utilities Commission Decision 2014-271: Alberta Electric System Operator

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

Québec Interconnection Approach to BES

Québec Interconnection Approach to BES Québec Interconnection Approach to BES Placer une photo ici s il y a lieu NPCC Governmental/Regulatory Affairs Advisory Group Sylvain Clermont November 27, 2012 Introduction: HQT Our mission HQT operates

More information

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of

More information

Comments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference

Comments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference Introduction The Northeast Power Coordinating Council 1 (NPCC) is an international electric regional reliability council formed shortly after the 1965 Northeast Blackout to promote the reliability and

More information

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Background Power Grid has evolved from a vertically integrated

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network

More information

Unofficial Comment Form

Unofficial Comment Form Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

ERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016

ERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 ERO Reliability Risk Priorities Report Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 RISC s Proposed 2016 Risk Profiles Changing Resource Mix Bulk Power System Planning

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket

5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket Clause 5 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 28, 2018. 5 Servicing Capacity Assignment

More information

John P Buechler NYISO Executive Regulatory Policy Advisor. NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY

John P Buechler NYISO Executive Regulatory Policy Advisor. NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY Eastern Interconnection Planning Collaborative Update John P Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY November 30, 2010

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

CIP Version 5 Evidence Request User Guide

CIP Version 5 Evidence Request User Guide CIP Version 5 Evidence Request User Guide Version 1.0 December 15, 2015 NERC Report Title Report Date I Table of Contents Preface... iv Introduction... v Purpose... v Evidence Request Flow... v Sampling...

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

Municipal Service Park 3 December Consolidation of City services to one centralized complex

Municipal Service Park 3 December Consolidation of City services to one centralized complex Municipal Service Park 3 December 2010 Consolidation of City services to one centralized complex Overview: Operational Challenges and Opportunities South East Connector impacts Opportunities: The South

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements. MISO Investigation Report on the NERC TLR Level 5 Event North Platte Stockville 115kV for the loss of the Gentleman Red Willow 345kV Flowgate 6023 August 22 nd / 23 rd, 2002 Report issued: September 3

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities

Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities NRECA TechAdvantage March 2014 Patti Metro Manager, Transmission & Reliability Standards NRECA

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

OPPD Board Committee Meeting April 13, 2017 Transmission Right of Way Acquisition & Routing, Siting and Public Involvement Stakeholder Engagement

OPPD Board Committee Meeting April 13, 2017 Transmission Right of Way Acquisition & Routing, Siting and Public Involvement Stakeholder Engagement OPPD Board Committee Meeting April 13, 2017 Transmission Right of Way Acquisition & Routing, Siting and Public Involvement Stakeholder Engagement Process and Condemnation Update Right-of-Way Easement

More information