Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013

Size: px
Start display at page:

Download "Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013"

Transcription

1 Mark W. Maher Chief Executive Officer Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013

2 Agenda WECC Overview WECC Strategic Planning Initiative Western Interconnection Synchrophasor Program (WISP) 2

3 WECC Profile Incorporated: 2002 (WECC) Business: 501(c)(6) not-for-profit Board of Directors elected by WECC members Employees: 216* Members: 363* Registered Entities: 467* Registered Functions: 1,234* *data as of 02/26/2013 3

4 WECC FACTS Largest geographic g area of the eight Regional Entities Western Interconnection (1.8 million square miles) includes all or part of 14 Western states, two Canadian provinces, and a portion of Baja California Norte, Mexico 4

5

6 WECC Board of Directors WECC is governed by an independent and balanced stakeholder board consisting of seven Non-Affiliated Directors and 26 Directors drawn from WECC membership classes. The WECC CEO is also a member of the WECC Board. 6

7 WECC MEMBERSHIP Membership is voluntary and is open to any person or entity that t has an interest t in the reliable operation of the Western Interconnection bulk power system. WECC has 363 members divided into seven membership classes: 1. Large Transmission Owners 2. Small Transmission Owners 3. Transmission Dependent Energy Service Providers 4. End Users 5. Representatives ti of State t and Provincial i Governments 6. Canadian Members 7. Members at large 7

8 WECC REGIONAL ENTITY FUNCTIONS 8 Reliability Standards Development Reliability Assessment and Performance Analysis o Data Gathering and Reliability Trending Activities o WECC s Transmission Expansion Planning Program o Resources Adequacy Assessments (Loads and Resources) o Base case model development and Technical Studies WECC Compliance o Registers Entities, Monitors Compliance with Standards o Enforces Compliance, Administration including audit coordination

9 WECC REGIONAL ENTITY FUNCTIONS Event Analysis and Reliability Improvement Training and Education Situation Awareness o WECC s Reliability Coordinator Functions o Western Interconnection Synchrophasor Program o WECC Interchange Tool o all necessary supporting activities) Infrastructure Security 9

10 Strategic Planning Initiative WECC will bifurcate into: o Reliability Coordination Company (RCCo): Registered functions of Reliability Coordinator and dinterchange Authority o WECC (Reliability Entity) GNC, FAC, and HRCC continue working on aspects of structure, governance, funding, and resourcing of the two entities Held January and February Special Board meetings made good progress 10

11 Current Recommendations Functional Split - White Paper Proposal Organizational Area Function RE RCCO Organizational Area Function RE RCCO Registration Power Flow and Dynamics Data Compliance Monitoring and Auditing Enforcement Enforcing Bulk Electric System Exception Training/Outreach Processing Reliability Coordination Support for Dynamic Model Seasonal Planning Studies Development WISP Map of Principal Transmission Restoration training and drills Planning Services Lines and Planned Facilities Reliability Coordination EMS Engineering Map EMS Applications Planning Coordination and EMS Information Technology Studies Registered Function Project Coordination and Path Compliance Rating Process Interchange Authority Interchange Authority Transmission Planning NERC Standards Process * Oversight Standards Regional Business Practice * Entity Certification (BA/TOP) * Development Event Analysis (EA) * Regional Criteria Development * WECC Interchange Tool (WIT) Regional Standards * Situational Awareness Development Operations Unscheduled Flow Mitigation Data and Models Transmission Expansion Plan (USFMP) and websas Planning Studies and Planning System Operator Training Interconnection-wide Plans Remedial Action Scheme Reliability Assessment and Data Analysis and Database Reliability Assessments Collection Committee Support Member Committees System Performance Analysis Legal Services General Counsel Corporate Secretary Corporate Compliance Administration Communications Corporate Services Human Resources Information Technology Accounting/Finance

12 Governance Reliability Coordination Company (RCCo) o Independent Board (seven members) o Strong Member Advisory Committee o RCCo CEO search process now underway o RCCo Interim Board Committee search WECC o Independent Board (nine members) o Strong Member Advisory Committee 12

13 Funding Pre-bifurcation (2013) Section 215 funding Post-bifurcation ti (January 2014) WECC Section 215 RCCo Section 215 being pursued with FERC 13

14 FERC FERC wants the strategic planning initiative to succeed and is interested in how to make this happen FERC staff is following this closely and giving i it critical thought, ht and is working collaboratively with WECC Legal Declaratory Order 14

15 Next Steps March Board meeting June Annual membership meeting September Board meeting December 4-6 Board meeting January 1, 2014 RCCo established 15

16 16 Western Interconnection Synchrophasor Program (WISP) US DOE grant of $53.9 million awarded April 1, 2010 Funding matches dollars committed by nine WISP Participant Entities in the WECC Region to extend and deploy synchrophasor technologies within their electrical systems Total WISP funding g$ $107.8 million Ten additional parties participating outside the grant in addition to nine original Participant Entities

17 Western Interconnection Synchrophasor h Program (WISP) cont. Will install more than 500 new or upgraded Phasor Measurement Units (PMU) in the Western Interconnection Will tie PMUs together with a dedicated secure communications network, and deploy software tools to manage an increasingly complex power grid PMUs deployed d today 399 Phasor Data Concentrators deployed today 62 17

18 WISP Benefits Large-scale outage avoidance Increased transmission usage Increased use of intermittent itt t renewable generation Reduced capacity firming costs for intermittent generation Critical infrastructure protection (CIP) and cyber security 18

19 Questions? Mark W. Maher

History of NERC January 2018

History of NERC January 2018 History of NERC January 2018 Date 1962 1963 The electricity industry created an informal, voluntary organization of operating personnel to facilitate coordination of the bulk power system in the United

More information

NERC Staff Organization Chart Budget 2019

NERC Staff Organization Chart Budget 2019 NERC Staff Organization Chart Budget 2019 President and CEO Associate Director to the Office of the CEO Senior Vice President and Chief Reliability Senior Vice President, General Counsel and Corporate

More information

NERC Staff Organization Chart Budget 2019

NERC Staff Organization Chart Budget 2019 NERC Staff Organization Chart Budget 2019 President and CEO Associate Director to the Office of the CEO Senior Vice President and Chief Reliability Officer Senior Vice President, General Counsel and Corporate

More information

History of NERC December 2012

History of NERC December 2012 History of NERC December 2012 Timeline Date 1962-1963 November 9, 1965 1967 1967-1968 June 1, 1968 July 13-14, 1977 1979 1980 Description Industry creates an informal, voluntary organization of operating

More information

NERC Staff Organization Chart Budget 2018

NERC Staff Organization Chart Budget 2018 NERC Staff Organization Chart Budget 2018 President and CEO Associate Director to the Office of the CEO Senior Vice President and Chief Reliability Senior Vice President, General Counsel and Corporate

More information

NERC Staff Organization Chart 2015 Budget

NERC Staff Organization Chart 2015 Budget NERC Staff Organization Chart President and CEO (Dept. 2100) Executive Assistant (Dept. 2100) Associate Director, Member Relations and MRC Secretary (Dept. 2100) Senior Vice President and Chief Reliability

More information

History of NERC August 2013

History of NERC August 2013 History of NERC August 2013 Timeline Date 1962 1963 November 9, 1965 1967 1967 1968 June 1, 1968 July 13 14, 1977 1979 Description The electricity industry creates an informal, voluntary organization of

More information

BPA and NERC, WECC, ERO

BPA and NERC, WECC, ERO BPA and NERC, WECC, ERO March 2006 1 Reliability Organizations BPA has relationship with two reliability organizations: 1. North American Electric Reliability Council (NERC) 2. Western Electric Coordinating

More information

NERC Staff Organization Chart Budget 2017

NERC Staff Organization Chart Budget 2017 NERC Staff Organization Chart Budget 2017 President and CEO Administrative Associate Director to the Office of the CEO Senior Vice President and Chief Reliability Senior Vice President, General Counsel

More information

NERC Staff Organization Chart Budget 2017

NERC Staff Organization Chart Budget 2017 NERC Staff Organization Chart Budget 2017 President and CEO Administrative Associate Director to the Office of the CEO Senior Vice President and Chief Reliability Senior Vice President, General Counsel

More information

Member Representatives Committee. Pre-Meeting and Informational Webinar January 16, 2013

Member Representatives Committee. Pre-Meeting and Informational Webinar January 16, 2013 Member Representatives Committee Pre-Meeting and Informational Webinar January 16, 2013 Objectives Review preliminary agenda topics for February 6 Member Representatives Committee (MRC) meeting. Review

More information

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION NARUC Energy Regulatory Partnership Program The Public Services Regulatory Commission of Armenia and The Iowa Utilities Board Janet Amick Senior Utility

More information

ERO Enterprise IT Projects Update

ERO Enterprise IT Projects Update ERO Enterprise IT Projects Update Stan Hoptroff, Vice President, Chief Technology Officer and Director of Information Technology Technology and Security Committee Meeting November 6, 2018 Agenda ERO IT

More information

NERC Staff Organization Chart

NERC Staff Organization Chart NERC Staff Organization Chart President and CEO Administrative Associate Director to the Office of the CEO Associate Director, Member Relations and MRC Secretary Senior Vice President and Chief Reliability

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO

RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO RELIABILITY COMPLIANCE ENFORCEMENT IN ONTARIO June 27, 2016 Training provided for Ontario market participants by the Market Assessment and Compliance Division of the IESO Module 1 A MACD training presentation

More information

NERC Staff Organization Chart Budget

NERC Staff Organization Chart Budget NERC Staff Organization Chart 2013 2014 President and CEO (Dept. 2100) Executive Assistant (Dept. 2100) Senior Vice President and Chief Operating Officer (Dept. 2100) Senior Vice President General Counsel

More information

Introduction to the NYISO

Introduction to the NYISO Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the

More information

Electric Transmission Reliability

Electric Transmission Reliability 1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

EEI Fall 2008 Legal Conference Boston, Massachusetts Stephen M. Spina November 1,

EEI Fall 2008 Legal Conference Boston, Massachusetts Stephen M. Spina November 1, EEI Fall 2008 Legal Conference Boston, Massachusetts Stephen M. Spina November 1, 2008 www.morganlewis.com Overview Reliability Standards Enforcement Framework Critical Infrastructure Protection (CIP)

More information

Peak Reliability Coordination Services in the West March 30, 2018

Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability, 2018. 1 Peak Reliability Coordination Services in the West Peak s fundamental mission is to enhance and promote the reliability

More information

Multi-Region Registered Entity Coordinated Oversight Program

Multi-Region Registered Entity Coordinated Oversight Program Multi-Region Registered Entity Coordinated Oversight Program Ken McIntyre, Vice President and Director of Standards and Compliance Compliance Committee Open Meeting February 7, 2018 Coordinated Oversight

More information

RELIABILITY OF THE BULK POWER SYSTEM

RELIABILITY OF THE BULK POWER SYSTEM RELIABILITY OF THE BULK POWER SYSTEM Jim Burley, VP of Compliance, Mitigation and Standards October 26, 2011 Promoting RELIABILITY and Mitigating RISKS to the Bulk Power System Context In the Beginning-2003

More information

Compliance Enforcement Initiative

Compliance Enforcement Initiative Compliance Enforcement Initiative Filing and Status Update November 2, 2011 Rebecca Michael Status of the Filings NERC filed several components of the Compliance Enforcement Initiative on September 30,

More information

Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13

Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 I. Vision A highly reliable and secure bulk power system in the Electric Reliability Council of Texas

More information

Critical Infrastructure Protection Version 5

Critical Infrastructure Protection Version 5 Critical Infrastructure Protection Version 5 Tobias Whitney, Senior CIP Manager, Grid Assurance, NERC Compliance Committee Open Meeting August 9, 2017 Agenda Critical Infrastructure Protection (CIP) Standards

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Analysis of CIP-006 and CIP-007 Violations

Analysis of CIP-006 and CIP-007 Violations Electric Reliability Organization (ERO) Compliance Analysis Report Reliability Standard CIP-006 Physical Security of Critical Cyber Assets Reliability Standard CIP-007 Systems Security Management December

More information

Standard CIP 005 4a Cyber Security Electronic Security Perimeter(s)

Standard CIP 005 4a Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-4a 3. Purpose: Standard CIP-005-4a requires the identification and protection of the Electronic Security Perimeter(s)

More information

Standard CIP Cyber Security Electronic Security Perimeter(s)

Standard CIP Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-1 3. Purpose: Standard CIP-005 requires the identification and protection of the Electronic Security Perimeter(s)

More information

OPUC Workshop March 13, 2015 Cyber Security Electric Utilities. Portland General Electric Co. Travis Anderson Scott Smith

OPUC Workshop March 13, 2015 Cyber Security Electric Utilities. Portland General Electric Co. Travis Anderson Scott Smith OPUC Workshop March 13, 2015 Cyber Security Electric Utilities Portland General Electric Co. Travis Anderson Scott Smith 1 CIP Version 5 PGE Implementation Understanding the Regulations PGE Attended WECC

More information

Critical Cyber Asset Identification Security Management Controls

Critical Cyber Asset Identification Security Management Controls Implementation Plan Purpose On January 18, 2008, FERC (or Commission ) issued Order. 706 that approved Version 1 of the Critical Infrastructure Protection Reliability Standards, CIP-002-1 through CIP-009-1.

More information

Steve Ashbaker Director Operations. NASPI Workgroup Meeting February 21, 2013 Atlanta, GA

Steve Ashbaker Director Operations. NASPI Workgroup Meeting February 21, 2013 Atlanta, GA Steve Ashbaker Director Operations NASPI Workgroup Meeting February 21, 2013 Atlanta, GA September 8, 2011 Event Update May 1 FERC/NERC Inquiry Report issued o 27 Recommendations in 8 categories July 26

More information

ERO Enterprise Strategic Planning Redesign

ERO Enterprise Strategic Planning Redesign ERO Enterprise Strategic Planning Redesign Mark Lauby, Senior Vice President and Chief Reliability Officer Member Representatives Committee Meeting February 10, 2016 Strategic Planning Redesign Current

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

Standard CIP Cyber Security Electronic Security Perimeter(s)

Standard CIP Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-2 3. Purpose: Standard CIP-005-2 requires the identification and protection of the Electronic Security Perimeter(s)

More information

John P Buechler NYISO Executive Regulatory Policy Advisor. NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY

John P Buechler NYISO Executive Regulatory Policy Advisor. NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY Eastern Interconnection Planning Collaborative Update John P Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY November 30, 2010

More information

Misoperations Information Data Analysis System (MIDAS)

Misoperations Information Data Analysis System (MIDAS) Misoperations Information Data Analysis System (MIDAS) End User Guide June 2016 NERC Report Title Report Date I Table of Contents Preface... iii Chapter 1 Reporting Obligations...1 Entities Obligated to

More information

Perry. Lakeshore. Avon. Eastlake

Perry. Lakeshore. Avon. Eastlake Perry Lorain Avon Lakeshore Eastlake Ashtabula Mansfield Sammis Beaver Valley Conesville Tidd Burger & Kammer Muskingum Perry Lorain Avon Lakeshore Eastlake Ashtabula Mansfield Sammis Beaver Valley Conesville

More information

Blackout 2003 Reliability Recommendations

Blackout 2003 Reliability Recommendations Blackout 2003 Reliability Recommendations 2005 NPCC General Meeting The Cranwell Resort Lenox, MA September 29, 2005 Philip A. Fedora Director, Market Reliability Interface Northeast Power Coordinating

More information

Standard Authorization Request Form

Standard Authorization Request Form Standard Authorization Request Form Title of Proposed Standard: Project 2009-02: Real-time Reliability Monitoring and Analysis Capabilities Original Request Date: June 4, 2009 Revised Date: January 15,

More information

Standards. Howard Gugel, Director of Standards Board of Trustees Meeting February 11, 2016

Standards. Howard Gugel, Director of Standards Board of Trustees Meeting February 11, 2016 Standards Howard Gugel, Director of Standards Board of Trustees Meeting February 11, 2016 Balancing Authority Reliability-based Controls Reliability Benefits Data requirements for Balancing Authority (BA)

More information

Grid Security & NERC

Grid Security & NERC Grid Security & NERC Janet Sena, Senior Vice President, Policy and External Affairs Southern States Energy Board 2017 Associate Members Winter Meeting February 27, 2017 Recent NERC History Energy Policy

More information

WISP. Western Interconnection Synchrophasor Program. Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012

WISP. Western Interconnection Synchrophasor Program. Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012 WISP Western Interconnection Synchrophasor Program Vickie VanZandt & Dan Brancaccio NASPI Work Group Meeting October 17-18, 2012 1 Acknowledgement and Disclaimer Acknowledgment: This material is based

More information

Grid Security & NERC. Council of State Governments. Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016

Grid Security & NERC. Council of State Governments. Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016 Grid Security & NERC Council of State Governments The Future of American Electricity Policy Academy Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016 1965 Northeast blackout

More information

Implementing Cyber-Security Standards

Implementing Cyber-Security Standards Implementing Cyber-Security Standards Greg Goodrich TFIST Chair, CISSP New York Independent System Operator Northeast Power Coordinating Council General Meeting Montreal, QC November 28, 2012 Topics Critical

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

CIP Version 5 Evidence Request User Guide

CIP Version 5 Evidence Request User Guide CIP Version 5 Evidence Request User Guide Version 1.0 December 15, 2015 NERC Report Title Report Date I Table of Contents Preface... iv Introduction... v Purpose... v Evidence Request Flow... v Sampling...

More information

Enhanced Curtailment Calculator Update

Enhanced Curtailment Calculator Update Enhanced Curtailment Calculator Update December 13, 2017 Member Advisory Committee Meeting Brett Wangen Chief Engineering and Technology Officer Jeremy West Manager, Interconnection Reliability Initiatives

More information

WIRAB Report to the Peak RC Board of Directors

WIRAB Report to the Peak RC Board of Directors WIRAB Report to the Peak RC Board of Directors Eric Baran & Holly Taylor WIRAB Staff December 14, 2017 1 WIRAB Activities Peak RC Activities Outline 2 WIRAB Activities Fall 2017 Leadership Delegation to

More information

CERTIFICATE IN LUXEMBOURG COMPANY SECRETARIAL & GOVERNANCE PRACTICE

CERTIFICATE IN LUXEMBOURG COMPANY SECRETARIAL & GOVERNANCE PRACTICE CERTIFICATE IN LUXEMBOURG COMPANY SECRETARIAL & GOVERNANCE PRACTICE POLICY ILA asbl 19, rue de Bitbourg L-1273 Luxembourg TABLE OF CONTENTS Program Entry 3 Eligibility criteria 3 Training program 4 Application

More information

The Africa Utilities Telecom Council Johannesburg CC, South Africa 1 st December, 2015

The Africa Utilities Telecom Council Johannesburg CC, South Africa 1 st December, 2015 The Africa Utilities Telecom Council Johannesburg CC, South Africa 1 st December, 2015 Utilities Telecom Council Global Focus on Utility Information and Communications Technology (ICT) Formed more than

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Critical Infrastructure Protection Committee Strategic Plan

Critical Infrastructure Protection Committee Strategic Plan Critical Infrastructure Protection Committee Strategic Plan 2013-2016 CIPC Executive Committee 5/14/2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, Georgia 30326 404-446-2560 www.nerc.com Table

More information

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Loss of EMS:

More information

Comments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference

Comments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference Introduction The Northeast Power Coordinating Council 1 (NPCC) is an international electric regional reliability council formed shortly after the 1965 Northeast Blackout to promote the reliability and

More information

Standard CIP 005 2a Cyber Security Electronic Security Perimeter(s)

Standard CIP 005 2a Cyber Security Electronic Security Perimeter(s) A. Introduction 1. Title: Cyber Security Electronic Security Perimeter(s) 2. Number: CIP-005-2a 3. Purpose: Standard CIP-005-2 requires the identification and protection of the Electronic Security Perimeter(s)

More information

Cyber Security Standards Drafting Team Update

Cyber Security Standards Drafting Team Update Cyber Security Standards Drafting Team Update Michael Assante, VP & Chief Security Officer North American Electric Reliability Corp. February 3, 2008 Overview About NERC Project Background Proposed Modifications

More information

Proposed Clean and Redline for Version 2 Implementation Plan

Proposed Clean and Redline for Version 2 Implementation Plan Exhibit A Implementation Plans for CIP-002-2 through CIP-009-2 and CIP-002-3 and CIP-009-3 For Generator Owners and Generator Operators of U.S. Nuclear Power Plants Proposed Clean and Redline for Version

More information

Standard CIP-006-4c Cyber Security Physical Security

Standard CIP-006-4c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-4c 3. Purpose: Standard CIP-006-4c is intended to ensure the implementation of a physical security

More information

Reviewed by ADM(RS) in accordance with the Access to Information Act. Information UNCLASSIFIED.

Reviewed by ADM(RS) in accordance with the Access to Information Act. Information UNCLASSIFIED. Assistant Deputy Minister (Review Services) Reviewed by in accordance with the Access to Information Act. Information UNCLASSIFIED. Security Audits: Management Action Plan Follow-up December 2015 1850-3-003

More information

CIP Standards Development Overview

CIP Standards Development Overview CIP Standards Development Overview CSSDTO706 Meeting with FERC Technical Staff July 28, 2011 Objectives Historical Timeline CIP-002-4 CIP-005-4 CIP Version 5 2 Project 2008-06 Overview FERC Order 706 SDT

More information

Time Synchronization and Standards for the Smart Grid

Time Synchronization and Standards for the Smart Grid Time Synchronization and Standards for the Smart Grid Tom Nelson National Institute of Standards and Technology 2011 NIST - ATIS - Telcordia Workshop on Synchronization in Telecommunication Systems (WSTS

More information

Reliability Standards Development Plan

Reliability Standards Development Plan Reliability Standards Development Plan Steven Noess, Director of Standards Development Standards Oversight and Technology Committee Meeting November 1, 2016 2017-2019 Reliability Standards Development

More information

Standard CIP Cyber Security Incident Reporting and Response Planning

Standard CIP Cyber Security Incident Reporting and Response Planning A. Introduction 1. Title: Cyber Security Incident Reporting and Response Planning 2. Number: CIP-008-4 3. Purpose: Standard CIP-008-4 ensures the identification, classification, response, and reporting

More information

Misoperation Information Data Analysis System

Misoperation Information Data Analysis System Misoperation Information Data Analysis System User Guide October, 2017 NERC Report Title Report Date I Table of Contents Preface... iv Overview... v Chapter 1: User Setup... 1-1 Creating an Account...

More information

The North American Electric Reliability Corporation ( NERC ) hereby submits

The North American Electric Reliability Corporation ( NERC ) hereby submits March 3, 2011 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 Re: North American Electric

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Electricity Sub-Sector Coordinating Council Charter FINAL DISCUSSION DRAFT 7/9/2013

Electricity Sub-Sector Coordinating Council Charter FINAL DISCUSSION DRAFT 7/9/2013 Electricity Sub-Sector Coordinating Council Charter FINAL DISCUSSION DRAFT 7/9/2013 Purpose and Scope The purpose of the Electricity Sub-Sector Coordinating Council (ESCC) is to facilitate and support

More information

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Self-Monitoring:

More information

FERC Reliability Technical Conference Panel III: ERO Performance and Initiatives ESCC and the ES-ISAC

FERC Reliability Technical Conference Panel III: ERO Performance and Initiatives ESCC and the ES-ISAC : ERO Performance and Initiatives June 4, 2015 Chairman Bay, Commissioners, and fellow panelists, I appreciate the opportunity to address the topics identified for the third panel of today s important

More information

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table

More information

Analysis of System Protection Misoperations

Analysis of System Protection Misoperations Analysis of System Protection Misoperations December 2015 Table of Contents Preface... ii Executive Summary...1 Introduction...2 Chapter 1 Misoperation Data Analysis...4 Misoperation Data Reported...4

More information

North American SynchroPhasor Initiative (NASPI) Overview

North American SynchroPhasor Initiative (NASPI) Overview North American SynchroPhasor Initiative (NASPI) Overview Data Exchange Panel ipcgrid 2013 hosted by Pacific Gas & Electric March 28, 2013 Jeff Dagle, PE Chief Electrical Engineer Advanced Power and Energy

More information

1. Post for 45-day comment period and pre-ballot review. 7/26/ Conduct initial ballot. 8/30/2010

1. Post for 45-day comment period and pre-ballot review. 7/26/ Conduct initial ballot. 8/30/2010 Standard CIP 011 1 Cyber Security Protection Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes

More information

Budget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017

Budget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017 2017-18 Budget Review Process (BRP) Preliminary List of Business Initiatives Stakeholder Meeting April 10, 2017 Purpose / Agenda The purpose of this presentation is to: Provide stakeholders with a BRP

More information

Peter J. Buerling Director, Records & Information Compliance. ReliabilityFirst Workshop April 15, 2016

Peter J. Buerling Director, Records & Information Compliance. ReliabilityFirst Workshop April 15, 2016 Peter J. Buerling Director, Records & Information Compliance April 15, 2016 Opening Comments Presentation Topic Disclaimer Presentation Support Introductions Mark Koziel Consultant, CIP Compliance Don

More information

EXHIBIT A: PROJECT SCOPE AND SCHEDULE The Project consists of the activities and delivery dates identified in this Exhibit A, implemented in accordance with the Agreement. The Parties have included a schedule

More information

Low Impact Generation CIP Compliance. Ryan Walter

Low Impact Generation CIP Compliance. Ryan Walter Low Impact Generation CIP Compliance Ryan Walter Agenda Entity Overview NERC CIP Introduction CIP-002-5.1, Asset Classification What Should Already be Done CIP-003-7, Low Impact Requirements Tri-State

More information

Cyber Threats? How to Stop?

Cyber Threats? How to Stop? Cyber Threats? How to Stop? North American Grid Security Standards Jessica Bian, Director of Performance Analysis North American Electric Reliability Corporation AORC CIGRE Technical Meeting, September

More information

RC Coordination Efforts

RC Coordination Efforts RC Coordination Efforts WECC RC FORUM JULY 19, 2018 CAISO, Peak, SPP, and AESO Steering Group Purpose and Participants Provide Update on Recent RC Coordination Activities Provide Opportunity for Interested

More information

Standard CIP-006-3c Cyber Security Physical Security

Standard CIP-006-3c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-3c 3. Purpose: Standard CIP-006-3 is intended to ensure the implementation of a physical security

More information

Standards Authorization Request Justification

Standards Authorization Request Justification Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

CIP Version 5 Transition. Steven Noess, Director of Compliance Assurance Member Representatives Committee Meeting November 12, 2014

CIP Version 5 Transition. Steven Noess, Director of Compliance Assurance Member Representatives Committee Meeting November 12, 2014 CIP Version 5 Transition Steven Noess, Director of Compliance Assurance Member Representatives Committee Meeting November 12, 2014 Purpose of the Transition Program Transitioning entities confident in

More information

WECC Internal Controls Evaluation Process WECC Compliance Oversight Effective date: October 15, 2017

WECC Internal Controls Evaluation Process WECC Compliance Oversight Effective date: October 15, 2017 WECC Internal Controls Evaluation Process WECC Compliance Oversight Effective date: October 15, 2017 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WECC Internal Controls Evaluation Process

More information

DHS Cybersecurity: Services for State and Local Officials. February 2017

DHS Cybersecurity: Services for State and Local Officials. February 2017 DHS Cybersecurity: Services for State and Local Officials February 2017 Department of Established in March of 2003 and combined 22 different Federal departments and agencies into a unified, integrated

More information

Standard CIP 007 4a Cyber Security Systems Security Management

Standard CIP 007 4a Cyber Security Systems Security Management A. Introduction 1. Title: Cyber Security Systems Security Management 2. Number: CIP-007-4a 3. Purpose: Standard CIP-007-4 requires Responsible Entities to define methods, processes, and procedures for

More information

Emergency Management BC Update

Emergency Management BC Update Emergency Management BC Update Provincial Emergency Program Emergency Management BC Update on Initiatives Union of BC Municipalities 2016 Conference September 29, 2016 Agenda Emergency Management BC Overview

More information

March 6, Dear Electric Industry Vendor Community: Re: Supply Chain Cyber Security Practices

March 6, Dear Electric Industry Vendor Community: Re: Supply Chain Cyber Security Practices March 6, 2019 Dear Electric Industry Vendor Community: Re: Supply Chain Cyber Security Practices On July 21, 2016, the Federal Energy Regulatory Commission (FERC) directed the North American Electric Reliability

More information

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Hetch Hetchy Water and Power of the City and County of San Francisco Joint Transmission Planning Base Case Preparation Process This is a living document. Please

More information

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused

Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Technology Innovation Delivering Value to BPA Organized, Disciplined, Focused Keeping the Lights on for the Long Term The Basics Bonneville Power

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standard CIP Cyber Security Security Management Controls

Standard CIP Cyber Security Security Management Controls A. Introduction 1. Title: Cyber Security Security Management Controls 2. Number: CIP-003-4 3. Purpose: Standard CIP-003-4 requires that Responsible Entities have minimum security management controls in

More information

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1 DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...

More information

Annual Report for the Utility Savings Initiative

Annual Report for the Utility Savings Initiative Report to the North Carolina General Assembly Annual Report for the Utility Savings Initiative July 1, 2016 June 30, 2017 NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY http://portal.ncdenr.org Page

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission