HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION. Presentation to ANC 3E April 13, 2017
|
|
- James Cummings
- 5 years ago
- Views:
Transcription
1 HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION Presentation to ANC 3E April 13,
2 PURPOSE AND NEED We are committed to providing reliable electric service to our customers. As part of this commitment, we are upgrading and modernizing the Harrison Street Substation in the Friendship Heights area of the District of Columbia The existing Harrison Street Substation has been in service since the 1940s and is nearing its maximum capacity While the facility has undergone regular maintenance and upgrades over the years, the infrastructure and some of the equipment have reached the end of their intended service life and require upgrades The modernization and upgrade will enhance system reliability for customers throughout the service area 2
3 PROJECT SUMMARY The Harrison Street Substation is currently providing electric service to the area The Project involves transferring the electric load from Harrison Street Substation to the temporary equipment so that it can provide electric service to the area during the upgrade demolishing the interior of the existing substation upgrading and modernizing the Harrison Street Substation putting the newly upgraded substation back in service removing the temporary electrical equipment final site work landscaping in front of the substation along Wisconsin Avenue 3
4 BENEFITS TO THE COMMUNITY An upgraded Harrison Street Substation will provide several direct and indirect benefits to customers as well as to the community, including: enhancing the reliability of service ensuring we can meet the community s growing energy needs providing a state-of-the art substation that is quieter and highly efficient enhancing the aesthetics of the building by enclosing the substation to conceal equipment upgrading the façade of the building along Wisconsin Avenue, NW 4
5 In 2011, we purchased the property at 5220 Wisconsin Avenue, formerly Classic Motors In 2013, we undertook site preparation of the new lot, constructing an entrance, completing site remediation and grading , extensive infrastructure work was conducted to support the modernization of the Harrison Street Substation, including overhead and underground distribution upgrades conversion of feeders from 4kV to 13kV alleviating 4kV load from the Harrison Substation by transferring some electrical load to neighboring substations BACKGROUND 5
6 BACKGROUND (Continued) , underground transmission lines were extended along River Road, Western Avenue, Jenifer Street and Wisconsin Avenue temporary equipment was installed at 5220 Wisconsin Avenue, with an in-service date, April , Wisconsin Avenue repaved 6
7 PROJECT OVERVIEW 7
8 PROJECT OVERVIEW 8
9 Phase 1: Equipment Removal May to August 2017* Remove equipment housed in existing substation Remove equipment through alley Shore up interior walls Remove transformer bay walls Interior abatement Soil abatement Community Impact Work Schedule: Monday-Saturday, 7 a.m. 7 p.m. Truck Traffic Parking Restrictions (as needed for large deliveries) *Approximate Schedule; subject to change based on a variety of factors 9
10 Phase 2: Upgrade of Harrison Substation Transfer Load to Upgraded Substation September 2017 to September 2018* Construct new exterior wall to enclose equipment Pour concrete for new cable vault Grade for new foundation Replace existing infrastructure Install Solar Panels Construct Green Wall Finalize interior and exterior fit-out Install new equipment Commission upgraded Harrison Substation Community Impact Work Schedule: Monday-Saturday, 7 a.m. to 7 p.m. Truck Traffic Parking Restrictions (January April 2018)* *Approximate schedule; subject to change based on a variety of factors 10
11 Phase 3: Remove Temporary Electrical Equipment Site Work & Landscaping August to December 2018* Remove temporary electrical equipment Remove site safety fencing Remove silt fencing Final site work Landscape in front of the substation along Wisconsin Avenue Community Impact Work Schedule: Monday-Friday 7 a.m. to 7 p.m. Truck Traffic Minimal *Approximate schedule; subject to change based on a variety of factors 11
12 COMMUNICATION Our goal is to keep residents in the project area informed at every step of the project and to complete the work with as little disruption as possible We will notify residents and businesses near the project area of project updates or any changes to the schedule We will maintain a special area on our website for updates and additional project information Visit pepco.com and click on Community Commitment, then Reliability Projects to find updated information For additional information, please Linda Greenan, External Affairs Manager, at linda.greenan@pepco.com. Community Meeting, Tuesday, April 18 th, 6:30 8pm, at American University Washington College of Law, Warren Building, Room NT08, 4300 Nebraska Avenue, NW 12
13 Rendering of Façade Upgrade Daytime 13
14 Rendering of Façade Upgrade Night View with Lighting 14
STRATHCONA AREA TRANSMISSION UPGRADE PROJECT
STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a
More informationAppendix F Notices
Appendix F Email Notices 2015 2016 Scoping Period From: Sent: To: Subject: CoSu Line Project on behalf of CoSu Line Project Friday, December
More informationCHAPTER TWELVE SECURITY. Oakland Alive
CHAPTER TWELVE SECURITY Oakland Alive 165 SECURITY Importance Oakland is a site full of landmark buildings, elaborate grave art, and extensive infrastructure. A comprehensive security system supported
More informationStudy Area and Location District PSA Ward ANC Phase Description D Proposed 1900 Block Foxhall Road Northwest Southbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 19 Block Foxhall Road NW S/B Study Area and Location District PSA Ward ANC Phase Description 2 25 3
More informationENMAX Power Corporation
Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application
More informationSpeed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia East Capitol Street at Southern Avenue NE
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia East Capitol Street at Southern Avenue NE Study Area and Location District PSA Ward ANC Phase Description
More informationStudy Area and Location District PSA Ward ANC Phase Description G Proposed 2900 Block Military Road Northwest Eastbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 29 Block Military Road NW E/B Study Area and Location District PSA Ward ANC Phase Description 2 21 3
More informationSpeed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 1100 Block 4th Street NE
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 11 Block 4th Street NE Study Area and Location District PSA Ward ANC Phase Description 1 14 6 6C Proposed
More informationAddison, Irving Park, Montrose, and Damen Stations Community Meeting
Addison, Irving Park, Montrose, and Damen Stations Community Meeting Design Update September 19, 2005 Sulzer Library Chicago Transit Authority 1 Addison, Irving Park, Montrose, and Damen Stations Community
More informationReliability & Resiliency in the US Capitol Region/Hardening the Grid One Year after Hurricane Sandy
1 Reliability & Resiliency in the US Capitol Region/Hardening the Grid One Year after Hurricane Sandy 2 Pepco D.C. Distribution System 260,000 Customers 175,000 Customers Supplied by Underground System
More informationStudy Area and Location District PSA Ward ANC Phase Description C Existing 3500 Block Massachusetts Avenue Northwest Eastbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 35 Block Massachusetts Avenue NW Study Area and Location District PSA Ward ANC Phase Description 2 24
More informationSpeed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Inside Southern part of 3rd Street Tunnel
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Inside Southern part of 3rd Street Tunnel Study Area and Location District PSA Ward ANC Phase Description
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of July 19, 2008 DATE: July 11, 2008 SUBJECT: SP#125 SITE PLAN AMENDMENT for proposed conversion of retail and conference space to cable television
More informationFOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT
Jack Strollo, Broker 500 S. Florida Avenue, Suite 420 Lakeland, Florida 33801 O. 863.683.3425 x103 C. 863.640.8238 jstrollo@resbroadway.com FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT
More informationStudy Area and Location District PSA Ward ANC Phase Description A Proposed I-395 Southwest after Exit 4, Eastbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia I-395 SW after Exit 4 E/B Study Area and Location District PSA Ward ANC Phase Description 1 71 8 8A
More informationStudy Area and Location District PSA Ward ANC Phase Description A Existing 1700 Block North Portal Drive Northwest Southwest-bound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 17 Block North Portal Drive NW Study Area and Location District PSA Ward ANC Phase Description 4 41
More informationROADWAY LIGHTING CURFEW
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS Rhode Island Department of Transportation ROADWAY LIGHTING CURFEW IMPLEMENTATION PLAN March 25, 21 TABLE OF CONTENTS INTRUDUCTION/OVERVIEW... 1 1.1. ANTICIPATED
More informationStudy Area and Location District PSA Ward ANC Phase Description A Proposed 6100 Block Georgia Avenue Northwest Southbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 6100 Block Georgia Avenue NW Study Area and Location District PSA Ward ANC Phase Description 4 402 4
More informationBUILDINGS AND FACILITIES
EB-00-0 Exhibit C Tab Schedule Page of BUILDINGS AND FACILITIES FACILITIES AND ASSET MANAGEMENT OVERALL STRATEGY THESL s buildings and facilities (the facilities ) include operating centers (00 Commissioners,
More informationDecision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement
Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,
More informationATTACHMENT 3 ZAB Page 1 of 8. The police department feels that the expanded use and hours are okay with the recommended security upgrades.
Page 1 of 8 From: White, Byron E. Sent: Wednesday, April 24, 2013 8:28 AM To: Greene, Elizabeth Subject: Re: 1799 University comments The police department feels that the expanded use and hours are okay
More informationSite 40. Recreational Center
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Georgia Avenue S/B at Missouri Avenue NW Study Area and Location District PSA Ward ANC Phase Description
More informationInstructions for Filling Out the Indiana 811 Membership Agreement
Instructions for Filling Out the Indiana 811 Membership Agreement 1. Please fill out and return to Indiana 811. Once you are on-line and are receiving locate requests, a copy will be signed and returned
More informationIEEE 2014 T&D Conference Paper 14TD Storm & Flood Hardening of Electrical Substations
1 IEEE 2014 T&D Conference Paper 14TD0564 - Storm & Flood Hardening of Electrical Substations FORUM 2 Transformers, Substations and Switchgear Forum Room: W185BC, Paper: 14TD0564 Tuesday, April 15, 2014
More informationFerguson Township e-newsletter: November 2017
Ferguson Township e-newsletter Dear Diana, Thank you for welcoming us into your inbox and WELCOME to our newest subscribers. Here is your November 2017 issue of the Ferguson Township e-newsletter. Deadline
More informationEVANSTON PUBLIC LIBRARY BOARD OF TRUSTEES FACILITIES COMMITTEE
EVANSTON PUBLIC LIBRARY BOARD OF TRUSTEES FACILITIES COMMITTEE Wednesday, July 19, 2017 5:30 P.M. Evanston Public Library, Community Meeting Room, 1703 Orrington Ave. 1. CALL TO ORDER 2. NEW BUSINESS AGENDA
More informationHealth Facilities and Utility Providers
Health Facilities and Utility Providers Strengthening the Partnership Ann Steeves, CEO HC-EMI November 2017 National Healthcare Coalition Preparedness Conference 2017 HC-EMI. All rights reserved. 1 Learning
More informationDiscussion Guide. Benvoulin Substation Project.
Discussion Guide Benvoulin Substation Project A Growing Region South Central Kelowna has experienced substantial growth over the last ten years. FortisBC is enhancing the electrical power supply system
More informationSite 17 W3-160 KEY: District Department of Transportation 55 M Street, SE, Suite 400 Washington, DC 20003
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Connecticut Avenue at Calvert Street NW Study Area and Location District PSA Ward ANC Phase Description
More informationStudy Area and Location District PSA Ward ANC Phase Description G Planned Connecticut Avenue Northbound at Military Road Northwest
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Connecticut Avenue at Military Road NW Study Area and Location District PSA Ward ANC Phase Description
More informationSpeed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia DC Miles South of Pennsylvania Avenue SE
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia DC 295.4 Miles South of Pennsylvania Avenue SE Study Area and Location District PSA Ward ANC Phase Description
More informationStandard CIP Cyber Security Critical Cyber Asset Identification
Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed
More informationWashington Square FPO. 111 Washington Square > Office Space FOR LEASE > OFFICE SPACE 111 WASHINGTON AVENUE, MINNEAPOLIS, MN 55401
FOR LEASE > OFFICE SPACE Washington Square 111 WASHINGTON AVENUE, MINNEAPOLIS, MN 55401 FPO 111 Washington Square > Office Space HENNEPIN AVE PARKING RAMP > Built in 1987, 111 Washington is part of a three
More informationStandard CIP Cyber Security Critical Cyber Asset Identification
Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed
More informationWATERFORD PATIO HOMEOWNERS ASSOCIATION. NEWSLETTER JULY 2016 Information for residents of Ivanhoe Waterford Patio Homeowners Association, Inc.
WATERFORD PATIO HOMEOWNERS ASSOCIATION Mailing Address: 15010 S. WATERFORD DRIVE, DAVIE, FL 33331 EMAIL: waterfordpatiohomes@gmail.com NEWSLETTER JULY 2016 Information for residents of Ivanhoe Waterford
More informationCITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION. Ryan Sagar 1196 Grant Street, Suite 313 Denver, CO 80203
CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION HEARING DATE: January 11, 2018 PROJECT NAME: FTC Chippers SC CASE NUMBER: PDP #170027 APPLICANT: OWNER: HEARING OFFICER: LRK Consulting
More informationSite 59 W5-147 KEY: District Department of Transportation 55 M Street, SE, Suite 400 Washington, DC 20003
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 11 Block Bladensburg Road NE SW/B Study Area and Location District PSA Ward ANC Phase Description 5
More information2016 Calendar of System Events and Moratoriums
2016 Calendar of System Events and Moratoriums Table of Contents 1. Terminology and Information 2 2. Quarterly Scheduled System Upgrades and Moratoriums 3 3. Scheduled Infrastructure Window 4 4. Scheme
More informationDealing With a Disaster and Its Effect on the Utility Operation
Nashville Electric Service Dealing With a Disaster and Its Effect on the Utility Operation UTA Fall Conference Florence, Alabama October 12-14, 2011 Outline Who We Are Typical Emergency Response Challenges
More informationVancouver Terminal Grain Storage Project. Feedback Form Inside. Community Engagement. October 1 19, 2012 PROJECT OV ERVIE W
Feedback Form Inside Vancouver Terminal Grain Storage Project Community Engagement October 1 19, 2012 PROJECT OV ERVIE W www.richardson.ca/news/vancouver-grain-terminal RICHARDSON INTERNATIONAL LIMITED
More informationFormer DuPont Barksdale Works Project Update
Former DuPont Barksdale Works Project Update September 10, 2003 Presented by: DuPont Corporate Remediation Group Presenters and Topics Brad Nave - DuPont Corporate Remediation Group Tonight s Topics Update
More informationBicycle Access & Parking Plan Project List Review
Bicycle Access & Parking Plan Project List Review Bicycle Advisory Committee September 19th, 2013 Strategy Overview New Bicycle Issues and Ideas (BAC, staff, public) Funding External Agency Lead BAPP s
More informationStakeholder Engagement Summary Report
Stakeholder Engagement Summary Report South Shore Corridor Project 1. INTRODUCTION 1.1 Project Overview Port Metro Vancouver s South Shore Trade Area is of critical importance to Canadian trade. One of
More informationUE CONNECTION APPLICATION - POLE to PIT (Underground Electricity Supply)
Phone 1300 131 689 Business Hours 8:00AM 5:00PM United Energy ABN 70 064 651 029 Scan & Email undergroundsupply@ue.com.au Attn: Customer and Market Operations PO Box 449 Mount Waverley VIC 3149 Thank you
More informationBoard of Zoning Adjustments Staff Report Monthly Meeting Monday, August 13, 2018
Board of Zoning Adjustments Staff Report Monthly Meeting Monday, August 13, 2018 Docket Number: BZA052-18 Prepared by: Applicant or Agent: William Casey Frew, Lewis Robinson Property Location: 1308 Henriette
More informationWORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES
Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS
More informationInstructions for Filling Out The Indiana 811 Membership Agreement
Instructions for Filling Out The Indiana 811 Membership Agreement 1. There are two (2) copies of the membership agreement. Please fill out both copies and return them to Indiana 811. Once you are on-line
More informationMetrobus 30s Line Enhancements
Customer Service, Operations and Safety Committee Action Item III-C February 14, 2008 Metrobus 30s Line Enhancements Washington Metropolitan Area Transportation Authority Board Action/Information Summary
More informationEBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston
EBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston Decision Summary EBRO File No.: 16EBR001.R Issue: The Ministry
More informationStudy Area and Location District PSA Ward ANC Phase Description B Planned Branch Avenue Northbound at Alabama Avenue Southeast
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia Branch Avenue at Alabama Avenue SE Study Area and Location District PSA Ward ANC Phase Description 6
More information1 of 8 10/10/2018, 12:52 PM RM-01, 10/10/2018. * Required. 1. Agency Name: * 2. Fiscal year reported: * 3. Date: *
1 of 8 10/10/2018, 12:52 PM RM-01, 10/10/2018 * Required 1. Agency Name: * 2. Fiscal year reported: * 3. Date: * Example: December 15, 2012 4. Name of agency staff member completing this report: * The
More informationStem Beach Solar 1041 Application
Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project
More informationWelcome! June 2015 Quarterly Meeting
Welcome! June 2015 Quarterly Meeting Georgeann W. Smith Interim Executive Director, Facilities Services E-mail GSmith@Central.UH.EDU Facilities Services Organizational Changes Lock Shop Key Control General
More informationThe Board grants site licenses for utilities that do not interfere with the park function.
Date: August 26, 2008 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Rogers Telecommunications Proposal - Hillcrest Park RECOMMENDATION A. THAT the Board enters
More informationB-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:
B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: 0-- E-mail: janet.fraser@bctc.com October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street,
More informationIntroduction. We are excited about the possibility of bringing Google Fiber to your city and look forward to working with you.
Introduction Over the last few years, gigabit Internet has moved from idea to reality, with dozens of communities working hard to build networks with speeds capable of supporting the future of the Internet.
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of May 20, 2017 DATE: May 10, 2017 SUBJECT: SP-339-U-17-2 USE PERMIT ASSOCIATED WITH A SITE PLAN for a telecommunications facility at Clarendon
More informationa) Provision of a chilled water supply b) Provision of electric power supply and other fuels
10.0 UTILITIES ELEMENT The purpose of this element is to ensure coordinated provision of utility services required to meet the future needs of the University, consistent with current efforts to address
More informationJoshua Kreutzberger Lighting/Electrical Thesis Proposal December 15, 2006 Dr. Mistrick. Dorrance H. Hamilton Building Philadelphia, PA
Joshua Kreutzberger Thesis Proposal December 15, 2006 EXECUTIVE SUMMARY The depth and breadth proposals provide the foundation for the analysis of the in the spring semester. Four topics will be investigated
More informationSetting up Residential Electrical Service with Cowlitz Public Utility District #I
Setting up Residential Electrical Service with Cowlitz Public Utility District # 1. Fill out Cowlitz Public Utility District #l's Residential Electrical Service Applications Requirement. a. Applications
More information6 th European Energy Forum
1 UNLOCKING SMART CAPABILITIES FOR LOCAL AUTHORITIES Jan Kowalczyk, CEO, Banner Group, Warsaw, Poland 6 th European Energy Forum Unlocking smart capabilities for local authorities Paris, 22-23 May 2017
More informationADDENDUM # 3. To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar at JFK Long-Term Parking Lot:
PROCUREMENT DEPARTMENT 4 WORLD TRADE CENTER 150 GREENWICH STREET, 21ST FL. NEW YORK, NY 10007 12/7/2018 ADDENDUM # 3 To prospective Proposers on RFI # 55144: Solar Energy Development and Community Solar
More information2017 Capital Improvement Budget Police Department
2017 Capital Improvement Budget Police Department (in thousands) Projects Bonds State Federal Other Total APD Headquarters Campus Perimeter Security Project 500 - - - 500 APD Investigation Interview Room
More informationKEEPING YOU OUT IN FRONT
URBACON DATA CENTRE SOLUTIONS KEEPING YOU OUT IN FRONT A next generation data centre in the core of downtown Toronto DOWNTOWN DATA CENTRE 281 FRONT STREET TORONTO, ON 1 2 X URBACON BUILDING GROUP 70 Lake
More informationFor Lease. Up to 24,000 Square Feet Divisible to 4,000 sqft Office Suites Also divisible to 3,583, 5,400 and 7,000 sqft warehouse/office suites
For Lease Up to 24,000 Square Feet Divisible to 4,000 sqft Office Suites Also divisible to 3,583, 5,400 and 7,000 sqft warehouse/office suites 4600 Ryzex Way Bellingham WA Extremely well designed Corporate
More informationAddendum: Final Design Noise Analysis Study Noise Sensitive Area (NSA) 11 Post March 15, 2016 Open House Response to Comments
Final Design Township of Lower Makefield, Bucks County, Pennsylvania Township of Ewing, Mercer County, New Jersey Addendum: Final Design Noise Analysis Study Noise Sensitive Area (NSA) 11 Post March 15,
More informationMath Olympiads Registration Information & FAQ
Registration Information & FAQ Thank you for your interest in our popular Math Olympiads course. In order to ensure your registration is valid and processed correctly it is imperative that you read carefully
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationContents. 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map
Ranchtown Substation Project Open House Displays 08/16/2012 Contents 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map 2. Scope, Purpose and Need Existing Helotes
More informationInstitute For Arts & Digital Sciences SHORT COURSES
Institute For Arts & Digital Sciences SHORT COURSES SCHEDULES AND FEES 2017 SHORT COURSES - GRAPHIC DESIGN Adobe Photoshop Basic 07 February 28 February Tuesdays 14:30-17:30 Adobe Photoshop Basic 07 February
More informationINFRASTRUCTURE ELECTRIC UTILITY CAPITAL IMPROVEMENT PROJECTS DRAFT
INFRASTRUCTURE ELECTRIC UTILITY CAPITAL IMPROVEMENT PROJECTS 2014-2023 DRAFT November 5, 2012 Project Costs Infrastructure - Electric Utility F - 2 City of Lethbridge Infrastructure - Electric Utility
More informationBenbow 397S Substation Upgrade Needs Identification Document
APPENDIX C AESO PIP Benbow 397S Substation Upgrade Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to December 2015, the AESO conducted a Participant Involvement Program
More informationITC HOLDINGS, CORP. Edison Electric Institute 9
ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy
More informationSTORAGE. UOVO's storage is designed to meet or exceed the standards set by the world's leading museums. Storage Options
STORAGE UOVO's storage is designed to meet or exceed the standards set by the world's leading museums. Zachary Harper, Art Storage Manager for the Rubin Museum of Art All four UOVO facilities feature:
More informationAPPENDICES RISK ASSESSMENT MITIGATION STRATEGY PLANNING PROCESS APPROVAL PROCESS. Page 352 of 524
APPENDICES RISK ASSESSMENT MITIGATION STRATEGY PLANNING PROCESS APPROVAL PROCESS Page 352 of 524 PLANNING PROCESS Plan Maintenance: Record of Revisions Form Meeting Agendas and Sign-In Sheets Notices Examples
More information26 th Street North and Old Dominion Drive Master Planning Task Force
26 th Street North and Old Dominion Drive Master Planning Task Force Presentation to Arlington Joint Facilities Advisory Commission October 24, 2018 Site Master Planning Task Force On September 2018, the
More informationDowntown to NAIT LRT Concept Plan Attachment 4 Public Involvement Summary
north, lrt, light, transit, rail, track, line, closure, close, road, interuption, partial, lane, construction, bulletin, NAIT, line, motorist, pedestrian, map, metro, line,downtown to NAIT LRT Concept
More informationSection 4: Citizen s Guide to SDEIS
Section 4: Citizen s Guide to SDEIS Improving mobility Record Page 40 Easing congestion Strengthening our communities Central Corridor Light Rail Transit Citizens Guide to the Supplemental Draft State
More informationADDENDUM #1. Date: 12/21/2018
Minnesota State Colleges and Universities Request for Proposals for Architectural and Engineering Services Physical Security Enhancements at St. Cloud State University Date: 12/21/2018 ADDENDUM #1 1. The
More informationCALENDAR OF FILING DEADLINES AND SEC HOLIDAYS
CALENDAR OF FILING S AND SEC HOLIDAYS INFORMATION IN THIS CALENDAR HAS BEEN OBTAINED BY SOURCES BELIEVED TO BE RELIABLE, BUT CANNOT BE GUARANTEED FOR ACCURACY. PLEASE CONSULT WITH PROFESSIONAL COUNSEL
More informationMetro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018
Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps Park Board Committee Meeting Monday, January 15, 2018 Purpose To provide an update on Metro Vancouver s Stanley Park Water
More information3. OUTSTANDING All matters arising are noted under the relevant Sub-Committee
Dynamic Property Services Pty Ltd Level 5, 162 Goulburn Street Sydney NSW 2010 DX 11643 Downtown Sydney T (02) 9267 6334 F (02) 9267 6337 E dps@pip.com.au ABN 67 002 006 760 The Executive Committee By
More informationALPINE MINISTRIES Alpine Adventures & Alpine Retreats
ALPINE MINISTRIES Alpine Adventures & Alpine Retreats 161 College Dr., Mt. Hope, WV 25880 (800) 806-2180 (304) 877-6427 FAX (304) 877-5046 Email: alpineretreats@abc.edu Please Print: 2018 Registration
More informationSECURITY PLAN. Library Bar 630 W. 6 th Street, Suite 116A Los Angeles, California 90017
SECURITY PLAN Library Bar 630 W. 6 th Street, Suite 116A Los Angeles, California 90017 Owned and Operated by: Sixth and Hope, LLC Michael Leko & William Shamlian Security plan prepared by: Elizabeth Peterson
More informationCity Reso-A Requests FY 2018 (City Council and Borough Presidents)
Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2017-18 through FY 2021-22 Project Funding Type Five-Year Plan Total ($ 000s) Replacement of Unit Ventilation
More informationPROSPECTUS ALTERATION PHILLIP BURTON FEDERAL BUILDING & U.S. COURTHOUSE SAN FRANCISCO, CA
Prospectus Number: PCA-0154-S F15 FY2015 Project Summary The General Services Administration () proposes a repair and alteration project to upgrade several building systems and reconfigure existing space
More informationFor Sale or Lease. I-20 Midway Commerce Center 30 Industrial Park Boulevard Trenton, South Carolina ±421,200 s.f. of Class A industrial space
I-20 Midway Commerce Center 30 Industrial Park Boulevard Trenton, South Carolina 29847 For Sale or Lease ±421,200 s.f. of Class A industrial space Expandable footprint: up to +1MM s.f. Minimum divisibility:
More informationExample. Section: PS 709 Examples of Calculations of Reduced Hours of Work Last Revised: February 2017 Last Reviewed: February 2017 Next Review:
Following are three examples of calculations for MCP employees (undefined hours of work) and three examples for MCP office employees. Examples use the data from the table below. For your calculations use
More informationCHAPTER WIRELESS TELECOMMUNICATION FACILITIES
CHAPTER 19.85 WIRELESS TELECOMMUNICATION FACILITIES Section 19.85.010 PURPOSE 19.85.020 DEFINITIONS 19.85.030 APPLICABILITY 19.85.040 STANDARDS FOR WIRELESS TELECOMMUNICATION FACILITIES 19.85.050 LOCATIONAL
More informationIt is acceptable to place all required information in the main element (such as G4010) and delete the sub-elements provided in this template.
6. ENGINEERING SYSTEMS REQUIREMENTS G40 SITE ELECTRICAL UTILITIES SYSTEMS REQUIREMENTS SITE ELECTRICAL UTILITIES TEMPLATE 02/18 Instructions for using this template: There are template files for each UNIFORMAT
More information8505 Baycenter Road Jacksonville, FL
Your Company Name Here 8505 Baycenter Road Jacksonville, FL OFFERING SUMMARY Newmark Grubb Knight Frank is pleased to offer 8505 Baycenter to the market for purchase or master lease. This Robert C. Broward
More informationSF set to start process for building modular housing for formerly homeless
Local SF set to start process for building modular housing for formerly homeless By J.K. Dineen January 22, 2018 Updated: January 22, 2018 8:19pm 8 http://www.sfchronicle.com/bayarea/article/sf-set-to-start-process-for-building-modular-12516479.php
More informationBOARD APPROVES STATE FUNDING MATCH FOR CONSTRUCTION OF CAREER TECHNOLOGY CENTER
Contact: Joe Verkennes, Director of Marketing, (734) 384-4207 January 24, 2011 FOR IMMEDIATE RELEASE BOARD APPROVES STATE FUNDING MATCH FOR CONSTRUCTION OF CAREER TECHNOLOGY CENTER MONROE, Mich. At its
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationSTATE STREET CORRIDOR
CITY OF WEST LAFAYETTE AND PURDUE UNIVERSITY STATE STREET CORRIDOR March 11, 2015 1 March 11, 2015 2 STATE STREET CORRIDOR AGENDA STATE STREET CORRIDOR 1. Project Fundamentals Project History Project Goals
More informationPoints of Discussion. Big Dig Project Schedule Next 6 Months of Construction Site Logistics Truck Traffic
Points of Discussion Big Dig Project Schedule Next 6 Months of Construction Site Logistics Truck Traffic Dust Controls Contractor Parking Web Cameras Community Communication 19 June 2017 1 Looking Back
More informationVariance Project Black Flag Attachments:
Variance 15-01 Project Black Flag Attachments: 1. Locator 2. VAR 15-01 Staff report 3. Variance Exhibit 4. Applicant s Statement E Lookout Dr N Plano Rd 1402 E. Lookout Dr. N Greenville Ave Woodglen Dr
More informationDevelopment trends in Substation Design
Development trends in Substation Design on behalf of SC B3 Hans-Erik Olovsson Convenor Activity Area 1 (AA1) «Substation concepts and development» hans-erik.olovsson@se.abb.com 1 Agenda Evolution of primary
More informationNATIONAL DEMOLITION ASSOCIATION PROJECT PRE-START SURVEY
NATIONAL DEMOLITION ASSOCIATION PROJECT PRE-START SURVEY PROJECT INFORMATION Project Name Project Number Project Location City Legal Description: Plat # State Zip Code County Client Client Address Contact(s)
More informationBGE Service Application Guidelines Residential Development Projects
BGE Service Application Guidelines Residential Development Projects To the Developer Following is important information to assist you in applying for BGE gas and/or electric service and completing the
More information