NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016
|
|
- Mervin Ross
- 6 years ago
- Views:
Transcription
1 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016
2 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons Learned Program Update 2 RELIABILITY ACCOUNTABILITY
3 ERO Event Analysis Process Update 3 RELIABILITY ACCOUNTABILITY
4 Event Analysis Process Update New draft posted for industry comment Version 3.1 Three main revisions Category 1g was revised to increase the upper threshold from 1,399 MWs to 1,999 MWs Category 2a was revised to align with COM and use of Interpersonal Communication capability Category 3a was revised to align all interconnection to a loss of 2,000 MWs or higher 4 RELIABILITY ACCOUNTABILITY
5 Category 1g and 3a Initial request to revise the categories was driven by Texas Regional Entity The request was reviewed and discussed by the Event Analysis Subcommittee (EAS) EAS agreed with the revision and the justification proposed by TRE TRE was asked to document the justification (available on the EA Program webpage) EAS received approval from the NERC Operating Committee to post the draft for a 45 day comment period (due by November 14, 2016) 5 RELIABILITY ACCOUNTABILITY
6 How to find the document Go to Program Areas & Departments > Reliability Risk Management > EA Program m/ea/pages/ea- Program.aspx 6 RELIABILITY ACCOUNTABILITY
7 Lesson Learned Presentation from Entity Maxime Nadeau Manager, System Control Operations and Scheduling Hydro Québec TransÉnergie 7 RELIABILITY ACCOUNTABILITY
8 NERC Lesson Learned Published December 29, RELIABILITY ACCOUNTABILITY
9 Management and monitoring of an SOL and IROL exceedances leading to an unrequired manual load shedding
10 HQT Main Transmission System Large generation complex located in the province northern area. 45,717 MW of installed capacity including 3,255 MW of wind generation. More than 90% is hydro generation. Around 50% of the load is in the southern part of the System. Winter peak is 175% of the summer peak. Historical peak load is 39,240 MW in ,224 MW of export capacity, mostly HVDC inter-ties. Bay JAMES BAY (15,000 MW) United States CHURCHILL FALLS (5,600 MW) New MANIC-OUTARDES (8,100 MW) 300 MW and more power plants 735 kv Substations 735 kv Lines Series compensation ± 450 kv DC Lines 10
11 Event summary During the morning peak, the Transmission System Operator ordered the de-energization of a shunt reactor at La Vérendrye substation (XL9) connected to a high voltage transmission line (L7016) for voltage control. During the operation, a fault occurred in the shunt reactor breaker causing the trip of the high voltage transmission line. Two IROL exceedances resulted. 11
12 Event Summary 12
13 Event Summary 13
14 Emergency Control Actions The System Operators (Transmission, Balancing, and Interchange) then took emergency operation control actions to restore the interface flows below the IROLs, such as: Starting gas turbines (400 MW); Curtailment of interchange transactions (1 000 MW); Emergency energy imports (1 000 MW); Regional (South) voltage reduction; 14
15 Emergency Control Actions 15
16 What the SO Saw on the Display 16
17 Load Shedding After 23 minutes, the interface flows was back under the IROL but still above the SOL. However, the System Operator - Transmission was still thinking he was exceeding the IROL being confused from his interpretation of the displays. Thus, 28 minutes after the event, the System Operator Transmission initiated MW of manual load shedding to restore system within IROL in 30 minutes or less. 37 minutes after the event, the line 7016 was put back in service and all the load was restored 35 minutes after it was shed. 17
18 Load Shedding 18
19 Similar Event on December 4,
20 Corrective Actions Analyze all the EMS monitoring tools to determine if SOL and IROL are clearly differentiated. Two issues were found: The SOL/IROL exceedance timer display was misleading; The System Operators were managing emergency situations with a static control actions list in which the operator had to identify by himself the control actions to apply. Thus, the following corrective actions were put in place: Upgrade the current timer display to make it more ergonomic and make sure that IROL and SOL are clearly differentiated; Create a new tool for System Operators (Transmission and Balancing) that would help them quickly select the required control actions according to the type of exceedance (SOL or IROL). 20
21 New Control Room Timer Display 21
22 SO Would Now See One Minute After the Line Trip 22
23 What the SO Would Now See After 23 Minutes 23
24 Limit Exceedance Management Tool Objectives: Provide real-time accurate situation awareness Centralize required mitigating emergency control actions Provide a follow-up on deployed actions Characteristics: Executed every minute by the Reserve Monitor Embedded in the EMS Dynamic throughout the event management Usable in test mode to do contingency analysis 24
25 New Limit Exceedance Management Tool 25
26 New Limit Exceedance Management Tool Messages that warn if it is an IROL or SOL exceedance Linear programming model manages multiple exceedances simultaneously Operator can exclude actions if deployment delay of that action exceeds his need for the current emergency situation Color coded and blinking to attract attention on important messages Messages that warn when Emergency Transmission Limits need to be implemented When Emergency Transmission Limits applied, recalculation of the solution 26
27 What the SO Would See 27
28 Lessons Learned Adequately differentiate the SOL and IROL limits in the EMS displays and the control room timer display for SOL/IROL exceedances. Improve System Operators simulation type training to add more stressful conditions in order to enhance their situational awareness and response during emergency operations. Review on a regular basis the System Operators understanding of the SOL and IROL limits and the emergency operation control actions permitted. 28
29 FYI NERC OC Reliability Guidelines 29 RELIABILITY ACCOUNTABILITY
30 Draft Reliability Guidelines Posted Draft NERC Operating Committee Reliability Guidelines Posted for Comment 30 Inadvertent Interchange Integrating Reporting ACE with the NERC Reliability Standards Situational Awareness for the System Operator Comment Period ends November 14, 2016 Go to > Committees > Operating Committee > Reliability Guidelines (on right side) Pages/Reliability-Guidelines.aspx RELIABILITY ACCOUNTABILITY
31 Situational Awareness for the SO Objective: To provide information on situational awareness and its applicability to real-time operation of the BES Provides global recognition of the importance for SOs to maintain situational awareness while operating the BES Meant to assist (TOP), Balancing Authorities (BA), Reliability Coordinators (RC), Generator Operators (GOP) to use with the primary goal of supporting BES reliability 31 RELIABILITY ACCOUNTABILITY
32 ERO Lessons Learned Program Update 32 RELIABILITY ACCOUNTABILITY
33 2015/2016 Event Count Event Category Count (Total) Count (2015/2016) Comments CAT /115 In 2015/2016: 37/47 Three or more BPS facilities lost (1a); 6/0 Islanding (1b); 6/3 BPS SPS/RAS Misoperation (1c); 1/0 Volt Red (1d); 7/0 Control Room evacuations (1f); 0/1 Loss of MW gen (ERCOT) (1g); 69/64 Partial EMS (1h) CAT /4 In 2015/2016: 16/0- EMS events (2b); 1/1 LOOP (2d); 4/3 Loss of >300MW Firm Load (2f) CAT /2 In 2015/2016: 1/2 Loss of > 1400MW of generation (3a) CAT 4 3 0/0 SW Winter Weather (2011) SW Blackout (2011) Derecho (2012) CAT 5 2 0/0 Hurricane Sandy (2012) Polar Vortex (2014) Total CAT 1-5 Events /121 Non-Qualified Occurrences reported / RELIABILITY ACCOUNTABILITY
34 Lessons Learned Metrics Published Lessons Learned By Year 34 RELIABILITY ACCOUNTABILITY
35 Category of Lessons Learned Published to Date 7 NERC lessons learned published to date in Relaying and Protection Systems 5 Communications 16 NERC lesson learned published in Relaying and Protection Systems 7- Communications 1- Transmission Facilities 2- Generation Facilities 2- Bulk-Power System Operations 35 RELIABILITY ACCOUNTABILITY
36 Lesson Learned Review Process Draft submitted Regional EA staff review/cleanup NERC EA staff review/cleanup NERC EAS initial review and recommendation to pursue or not NERC EAS sets small team to review with entity if available and willing NERC EAS final review and approval to post NERC Technical writing review 36 RELIABILITY ACCOUNTABILITY
37 Lessons Learned Input Methods ERO Event Analysis Process reports Major Disturbances Minor occurrences (or events that do not qualify for EA) Good outcomes that have information worthy of passing along Near miss (or near hit) Automatic Voltage Regulator Example Events not in North America 37 RELIABILITY ACCOUNTABILITY
38 Lessons Learned Feedback NERC s goal with publishing lessons learned is to provide industry with technical and understandable information that assists them with maintaining the reliability of the bulk power system. NERC requests that industry provide input on lessons learned by taking the short survey. A link is provided in the PDF version of each Lesson Learned. 38 RELIABILITY ACCOUNTABILITY
39 Access Lessons Learned Go to Program Areas & Departments > Reliability Risk Management > Event Analysis > Lessons Learned 39 RELIABILITY ACCOUNTABILITY
40 Contact Information Hassan Hamdar Chair, Event Analysis Subcommittee Jule Tate NERC Associate Director, Event Analysis General NERC Event Analysis Mailbox 40 RELIABILITY ACCOUNTABILITY
41 For more Information please contact: (via ) 41 RELIABILITY ACCOUNTABILITY
Québec Interconnection Approach to BES
Québec Interconnection Approach to BES Placer une photo ici s il y a lieu NPCC Governmental/Regulatory Affairs Advisory Group Sylvain Clermont November 27, 2012 Introduction: HQT Our mission HQT operates
More informationNERC EAS Update. Tim Reynolds Sr. Reliability Engineer W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
NERC EAS Update Tim Reynolds Sr. Reliability Engineer 2 Changes to the ERO EAP Changes to the EAP to facilitate collecting data Events involving near-misses Inverter disturbances Other things as identified
More informationProject Consideration of Commission Directives in Order No. 693
Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that
More information2017 MRO Performance Areas and an Update on Inherent Risk Assessments
MIDWEST RELIABILITY ORGANIZATION 2017 MRO Performance Areas and an Update on Inherent Risk Assessments Adam Flink, Risk Assessment and Mitigation Engineer November 16, 2016 Improving RELIABILITY and mitigating
More informationFERC Reliability Technical Conference Panel I: 2015 State of Reliability Report Introduction Overview of the State Of Reliability
: 2015 State of Reliability Report Remarks of Thomas Burgess, Vice President and Director of Reliability Assessment and Performance Analysis Introduction Chairman Bay and Commissioners, members of the
More informationAgenda Event Analysis Subcommittee Conference Call
Agenda Event Analysis Subcommittee Conference Call August 14, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security
More informationState of Reliability Report 2013
State of Reliability Report 2013 Jessica Bian, Director of Performance Analysis Reliability Assessment and Performance Analysis (RAPA), NERC Risk Issues Steering Committee Meeting, July 11-12, 2013 State
More informationDisclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...
More informationStandard CIP Cyber Security Critical Cyber As s et Identification
A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification
More informationWide-Area Reliability Monitoring and Visualization Tools
OE Visualization and Controls Peer Review Wide-Area Reliability Monitoring and Visualization Tools Carlos Martinez CERTS - Electric Power Group 21 October 2008 Washington, D.C. Presentation Outline Research
More informationStandards Authorization Request Justification
Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,
More information5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.
Introduction 1. Title: IROL and SOL Mitigation in the ERCOT Region 2. Number: IRO-006-TRE-1 3. Purpose: To provide and execute transmission loading relief procedures that can be used to mitigate SOL or
More informationStandard EOP Disturbance Reporting
A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment
More informationThis section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationNERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010
Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission
More informationNew Brunswick 2018 Annual Implementation Plan Version 1
New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...
More informationEnhanced Curtailment Calculator Update
Enhanced Curtailment Calculator Update December 13, 2017 Member Advisory Committee Meeting Brett Wangen Chief Engineering and Technology Officer Jeremy West Manager, Interconnection Reliability Initiatives
More informationProject Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018
Project 2017-01 Modifications to BAL-003-1.1 Frequency Response and Frequency Bias Setting Industry Webinar December 18, 2018 Administrative Items North American Electric Reliability Corporation (NERC)
More informationNERC Overview and Compliance Update
NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance
More informationCIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides
More informationStandard CIP Cyber Security Critical Cyber As s et Identification
A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification
More informationProposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013
Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently
More informationTOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support
TOP/IRO Standards RC Users Group January 21, 2016 Vic Howell Manager, Operations Engineering Support Saad Malik Manager, Real-Time Operations Engineering New/Revised TOP & IRO Standards November 19, 2015,
More informationReliability Standards Development Plan
Reliability Standards Development Plan 2012-2014 October 13, 2011 For SC Approval 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents...ii
More informationImplementation Plan for COM-001-2
Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.
More informationFRCC Disturbance Reporting Processes and Procedures
Page 1 of 13 FRCC Disturbance Reporting Processes and FRCC RE OP 001-3.2 Effective Date: September 29, 2016 Version: 3.2 3000 Bayport Drive, Suite 600 Tampa, Florida 33607-8410 (813) 289-5644 - Phone (813)
More informationUnofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols
Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Operating Personnel Communications Protocols Please DO NOT use this form. Please use the electronic comment form to submit comments
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationProject Posting 8 Frequently Asked Questions Guide
Project 2007-02 Posting 8 Frequently Asked Questions Guide General Questions 1. What were the inputs that drove the development of posting 8 of Project 2007-02? The NERC Board of Trustees November 7 th,
More informationReliability Compliance Update. Reliability Standards and Compliance Subcommittee Preston Walker August 16, 2018
Reliability Compliance Update Reliability Standards and Compliance Subcommittee Preston Walker August 16, 2018 NERC Standards Under Development Standards Project Action End Date Comment 08/27/2018 Draft
More informationBritish Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia
Page 1 of 15 British Columbia Utilities Reliability Standards with s adopted in British Columbia BAL-001-2 Standard Real Power Balancing Control Performance R-14-16 July 1, 2016 BAL-002-1 1 Disturbance
More informationStandards Authorization Request Form
Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationDraft CIP Standards Version 5
Draft CIP Standards Version 5 Technical Webinar Part 1 Project 2008-06 Cyber Security Order 706 Standards Drafting Team November 15, 2011 Agenda Opening Remarks John Lim, Consolidated Edison, Chair V5
More informationAgenda Event Analysis Subcommittee Conference Call
Agenda Event Analysis Subcommittee Conference Call September 11, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security
More informationrequirements in a NERC or Regional Reliability Standard.
CIP 002 5.1 Cyber Security BES Cyber System Categorization A. Introduction 1. Title: Cyber Security BES Cyber System Categorization 2. Number: CIP 002 5.1 3. Purpose: To identify and categorize BES Cyber
More informationERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018
ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used
More informationStandard Authorization Request Form
Standard Authorization Request Form E-mail completed form to rsm@texasre.org Texas RE to Complete SAR No: Title of Proposed Standard IRO-006-TRE-1 IROL and SOL Mitigation in the ERCOT Region Request Date
More informationPower System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017
Power System Resilience & Reliability Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 NERC, Reliability, & Resilience NERC has addressed reliability
More informationFERC Reliability Technical Conference -- Panel I State of Reliability and Emerging Issues
-- State of Reliability and Emerging Issues Remarks of Thomas Burgess, Vice President and Director, Reliability Assessment and Performance Analysis Chairman Wellinghoff, Commissioners, Staff, and fellow
More informationWECC Criterion MOD-(11 and 13)-WECC-CRT-1.1
WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements
More informationSMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2
SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:
More informationStandard Development Timeline
CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the
More information1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.
MISO Investigation Report on the NERC TLR Level 5 Event North Platte Stockville 115kV for the loss of the Gentleman Red Willow 345kV Flowgate 6023 August 22 nd / 23 rd, 2002 Report issued: September 3
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationAnalysis of System Protection Misoperations
Analysis of System Protection Misoperations December 2015 Table of Contents Preface... ii Executive Summary...1 Introduction...2 Chapter 1 Misoperation Data Analysis...4 Misoperation Data Reported...4
More informationSupplemental Information
Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year
More information2018 MRO Regional Risk Assessment
MIDWEST RELIABILITY ORGANIZATION 2018 MRO Regional Risk Assessment Ben Lewiski, Risk Assessment and Mitigation Engineer November 28, 2017 Improving RELIABILITY and mitigating RISKS to the Bulk Power System
More informationUSE CASE 14 CONTROLLED ISLANDING
I USE CASE 14 CONTROLLED ISLANDING Use Case Title Centralized application separates grid into islands to prevent blackout Use Case Summary Controlled islanding is a method that can significantly improve
More informationBAL Real Power Ba la ncing Control Performance Standard Background Document
BAL-001-1 Real Power Ba la ncing Control Performance Standard Background Document January 2012 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents
More informationTexas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13
Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 I. Vision A highly reliable and secure bulk power system in the Electric Reliability Council of Texas
More informationUnofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )
Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic
More informationAgenda Event Analysis Subcommittee Conference Call
Agenda Event Analysis Subcommittee Conference Call October 23, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security
More informationERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016
ERO Reliability Risk Priorities Report Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 RISC s Proposed 2016 Risk Profiles Changing Resource Mix Bulk Power System Planning
More informationConsideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013
Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010
More informationStandard INT Dynamic Transfers
Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately
More informationNERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014
Request for Data or Information Protection System Misoperation Data Collection August 14, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 15 Table of
More informationStandards. Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013
Standards Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013 Geomagnetic Disturbance Operations EOP-010-1 Reliability benefits Enhance operating response to
More informationEssential Reliability Services NERC Staff Report
Essential Reliability Services NERC Staff Report Mark Lauby, Senior Vice President and Chief Reliability Officer Annual Meeting of the National Conference of State Legislators August 20, 2014 About NERC
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationPRC Coordination of Protection Systems for Performance During Faults
PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To
More informationStandard Development Timeline
CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the
More informationImpacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities
Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities NRECA TechAdvantage March 2014 Patti Metro Manager, Transmission & Reliability Standards NRECA
More informationMember Representatives Committee Meeting
Member Representatives Committee Meeting August 13, 2014 1:15 p.m. 5:15 p.m. Pacific The Westin Bayshore, Vancouver 1601 Bayshore Drive Vancouver, BC V6G 2V4 Canada Opening Remarks by MRC Chair Consent
More informationDER Data Collection Guideline. Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017
DER Data Collection Guideline Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017 Since the August 3, 2017, Meeting Data Collection Guideline has been through two rounds of comment from DER Subgroup
More informationAchieving Smarter Grid Operation With On-Line DSA Technology
Achieving Smarter Grid Operation With On-Line DSA Technology Powercon 2014 October 20-22, 2014, Chengdu, China Lei Wang Powertech Labs Inc. 12388 88 th Avenue Surrey, BC, Canada A very simple version of
More informationPhysical Security Reliability Standard Implementation
Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,
More informationPath Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor
Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor May 10, 2017 ISAS Salt Lake City, UT WECC Standard TOP 007 WECC 1a Title: System Operating Limits Purpose: To limit instances where
More informationRisk-Based Approach to Compliance Monitoring and Enforcement
Risk-Based Compliance Oversight Plan Process for Risk Elements and Associated The ERO Enterprise continues to identify risks to the reliability of the BPS, as well as mitigating factors that may reduce
More informationMember Representatives Committee. Pre-Meeting and Informational Webinar January 16, 2013
Member Representatives Committee Pre-Meeting and Informational Webinar January 16, 2013 Objectives Review preliminary agenda topics for February 6 Member Representatives Committee (MRC) meeting. Review
More informationNERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM September 6, 2013
NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM-003-1 September 6, 2013 At the August 14-15, 2013 meeting of the Board of Trustees ( Board ) of the North
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationStandard TOP Transmission Operations
A. Introduction 1. Title: Transmission Operations 2. Number: TOP-001-34 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection
More informationThis section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationDRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1
DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...
More informationSouthwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September
Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September 23, 2009 TABLE OF CONTENTS INTRODUCTION A. RESPONSIBILITIES
More informationDRAFT Risks and Mitigations for Losing EMS Functions
DRAFT Risks and Mitigations for Losing EMS Functions 1.0 Executive Summary Energy Management System (EMS) is a system of computer-aided tools used by System Operators to monitor, control, and optimize
More informationMethods for Establishing IROLs Task Force
Methods for Establishing IROLs Task Force Progress Update Ryan D. Quint Senior Manager, Advanced Analytics and Modeling OC/PC Joint Meeting March 7, 2017 Background MEITF kicked off in December to: Address
More informationPeak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision
Table of Contents I. Purpose... 2 II. Introduction... 2 III. Peak Roles and Responsibilities... 2 IV. Applicability and Obligations... 3 V. Questions and Comments... 6 VI. Data Request Spreadsheet... 6
More informationSystem Impact Study for Power Supply 400 MW Import on the EAL BCHA Path
System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power
More informationCOM Communications and Coordination
COM-002-2 Communications and Coordination February 27, 2014 Lonnie Lindekugel ~ SPP Jim Nail ~ City of Independence INTRODUCTION NERC Reliability Standard COM-002-2 (Communications and Coordination) serves
More informationStandard INT Dynamic Transfers
A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures.
More informationChapter X Security Performance Metrics
DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the
More informationIMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS
IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage
More informationProject , COM Operating Personnel Communications Protocols Rationale and Technical Justification
Project 2007-02, COM-002-4 Operating Personnel Communications Protocols Rationale and Technical Justification Posting 8: Background and Justification for COM-002-4 Requirements The purpose of the proposed
More informationReliability Coordinator Procedure
No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR
More informationSteve Ashbaker Director Operations. NASPI Workgroup Meeting February 21, 2013 Atlanta, GA
Steve Ashbaker Director Operations NASPI Workgroup Meeting February 21, 2013 Atlanta, GA September 8, 2011 Event Update May 1 FERC/NERC Inquiry Report issued o 27 Recommendations in 8 categories July 26
More informationQuébec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan
Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table
More informationStandard Authorization Request Form
Standard Authorization Request Form Title of Proposed Standard: Project 2009-02: Real-time Reliability Monitoring and Analysis Capabilities Original Request Date: June 4, 2009 Revised Date: January 15,
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationCritical Asset Identification Methodology. William E. McEvoy Northeast Utilities
Critical Asset Identification Methodology William E. McEvoy Northeast Utilities Disclaimer This NPCC TFIST workshop provides a forum for the presentation and discussion of member experience in the implementation
More informationPeak Reliability Coordination Services in the West March 30, 2018
Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability, 2018. 1 Peak Reliability Coordination Services in the West Peak s fundamental mission is to enhance and promote the reliability
More informationHistory of NERC January 2018
History of NERC January 2018 Date 1962 1963 The electricity industry created an informal, voluntary organization of operating personnel to facilitate coordination of the bulk power system in the United
More informationERO Enterprise Strategic Planning Redesign
ERO Enterprise Strategic Planning Redesign Mark Lauby, Senior Vice President and Chief Reliability Officer Member Representatives Committee Meeting February 10, 2016 Strategic Planning Redesign Current
More informationTable of Issues and Directives Project Relay Loadability: Stable Power Swings
Table of Issues and Directives Project 2010-13.3 Relay Loadability: Stable Power Swings FERC Order 733 150. We will not direct the ERO to modify PRC-023-1 to address stable power swings. However, because
More informationBESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2
Table of Contents BESNet User Manual Exception Request Preparation for Registered Entities June 29, 2014 Version 1-2 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com
More informationERO Enterprise IT Projects Update
ERO Enterprise IT Projects Update Stan Hoptroff, Vice President, Chief Technology Officer and Director of Information Technology Technology and Security Committee Meeting November 6, 2018 Agenda ERO IT
More informationComments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference
Introduction The Northeast Power Coordinating Council 1 (NPCC) is an international electric regional reliability council formed shortly after the 1965 Northeast Blackout to promote the reliability and
More information