NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

Size: px
Start display at page:

Download "NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016"

Transcription

1 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

2 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons Learned Program Update 2 RELIABILITY ACCOUNTABILITY

3 ERO Event Analysis Process Update 3 RELIABILITY ACCOUNTABILITY

4 Event Analysis Process Update New draft posted for industry comment Version 3.1 Three main revisions Category 1g was revised to increase the upper threshold from 1,399 MWs to 1,999 MWs Category 2a was revised to align with COM and use of Interpersonal Communication capability Category 3a was revised to align all interconnection to a loss of 2,000 MWs or higher 4 RELIABILITY ACCOUNTABILITY

5 Category 1g and 3a Initial request to revise the categories was driven by Texas Regional Entity The request was reviewed and discussed by the Event Analysis Subcommittee (EAS) EAS agreed with the revision and the justification proposed by TRE TRE was asked to document the justification (available on the EA Program webpage) EAS received approval from the NERC Operating Committee to post the draft for a 45 day comment period (due by November 14, 2016) 5 RELIABILITY ACCOUNTABILITY

6 How to find the document Go to Program Areas & Departments > Reliability Risk Management > EA Program m/ea/pages/ea- Program.aspx 6 RELIABILITY ACCOUNTABILITY

7 Lesson Learned Presentation from Entity Maxime Nadeau Manager, System Control Operations and Scheduling Hydro Québec TransÉnergie 7 RELIABILITY ACCOUNTABILITY

8 NERC Lesson Learned Published December 29, RELIABILITY ACCOUNTABILITY

9 Management and monitoring of an SOL and IROL exceedances leading to an unrequired manual load shedding

10 HQT Main Transmission System Large generation complex located in the province northern area. 45,717 MW of installed capacity including 3,255 MW of wind generation. More than 90% is hydro generation. Around 50% of the load is in the southern part of the System. Winter peak is 175% of the summer peak. Historical peak load is 39,240 MW in ,224 MW of export capacity, mostly HVDC inter-ties. Bay JAMES BAY (15,000 MW) United States CHURCHILL FALLS (5,600 MW) New MANIC-OUTARDES (8,100 MW) 300 MW and more power plants 735 kv Substations 735 kv Lines Series compensation ± 450 kv DC Lines 10

11 Event summary During the morning peak, the Transmission System Operator ordered the de-energization of a shunt reactor at La Vérendrye substation (XL9) connected to a high voltage transmission line (L7016) for voltage control. During the operation, a fault occurred in the shunt reactor breaker causing the trip of the high voltage transmission line. Two IROL exceedances resulted. 11

12 Event Summary 12

13 Event Summary 13

14 Emergency Control Actions The System Operators (Transmission, Balancing, and Interchange) then took emergency operation control actions to restore the interface flows below the IROLs, such as: Starting gas turbines (400 MW); Curtailment of interchange transactions (1 000 MW); Emergency energy imports (1 000 MW); Regional (South) voltage reduction; 14

15 Emergency Control Actions 15

16 What the SO Saw on the Display 16

17 Load Shedding After 23 minutes, the interface flows was back under the IROL but still above the SOL. However, the System Operator - Transmission was still thinking he was exceeding the IROL being confused from his interpretation of the displays. Thus, 28 minutes after the event, the System Operator Transmission initiated MW of manual load shedding to restore system within IROL in 30 minutes or less. 37 minutes after the event, the line 7016 was put back in service and all the load was restored 35 minutes after it was shed. 17

18 Load Shedding 18

19 Similar Event on December 4,

20 Corrective Actions Analyze all the EMS monitoring tools to determine if SOL and IROL are clearly differentiated. Two issues were found: The SOL/IROL exceedance timer display was misleading; The System Operators were managing emergency situations with a static control actions list in which the operator had to identify by himself the control actions to apply. Thus, the following corrective actions were put in place: Upgrade the current timer display to make it more ergonomic and make sure that IROL and SOL are clearly differentiated; Create a new tool for System Operators (Transmission and Balancing) that would help them quickly select the required control actions according to the type of exceedance (SOL or IROL). 20

21 New Control Room Timer Display 21

22 SO Would Now See One Minute After the Line Trip 22

23 What the SO Would Now See After 23 Minutes 23

24 Limit Exceedance Management Tool Objectives: Provide real-time accurate situation awareness Centralize required mitigating emergency control actions Provide a follow-up on deployed actions Characteristics: Executed every minute by the Reserve Monitor Embedded in the EMS Dynamic throughout the event management Usable in test mode to do contingency analysis 24

25 New Limit Exceedance Management Tool 25

26 New Limit Exceedance Management Tool Messages that warn if it is an IROL or SOL exceedance Linear programming model manages multiple exceedances simultaneously Operator can exclude actions if deployment delay of that action exceeds his need for the current emergency situation Color coded and blinking to attract attention on important messages Messages that warn when Emergency Transmission Limits need to be implemented When Emergency Transmission Limits applied, recalculation of the solution 26

27 What the SO Would See 27

28 Lessons Learned Adequately differentiate the SOL and IROL limits in the EMS displays and the control room timer display for SOL/IROL exceedances. Improve System Operators simulation type training to add more stressful conditions in order to enhance their situational awareness and response during emergency operations. Review on a regular basis the System Operators understanding of the SOL and IROL limits and the emergency operation control actions permitted. 28

29 FYI NERC OC Reliability Guidelines 29 RELIABILITY ACCOUNTABILITY

30 Draft Reliability Guidelines Posted Draft NERC Operating Committee Reliability Guidelines Posted for Comment 30 Inadvertent Interchange Integrating Reporting ACE with the NERC Reliability Standards Situational Awareness for the System Operator Comment Period ends November 14, 2016 Go to > Committees > Operating Committee > Reliability Guidelines (on right side) Pages/Reliability-Guidelines.aspx RELIABILITY ACCOUNTABILITY

31 Situational Awareness for the SO Objective: To provide information on situational awareness and its applicability to real-time operation of the BES Provides global recognition of the importance for SOs to maintain situational awareness while operating the BES Meant to assist (TOP), Balancing Authorities (BA), Reliability Coordinators (RC), Generator Operators (GOP) to use with the primary goal of supporting BES reliability 31 RELIABILITY ACCOUNTABILITY

32 ERO Lessons Learned Program Update 32 RELIABILITY ACCOUNTABILITY

33 2015/2016 Event Count Event Category Count (Total) Count (2015/2016) Comments CAT /115 In 2015/2016: 37/47 Three or more BPS facilities lost (1a); 6/0 Islanding (1b); 6/3 BPS SPS/RAS Misoperation (1c); 1/0 Volt Red (1d); 7/0 Control Room evacuations (1f); 0/1 Loss of MW gen (ERCOT) (1g); 69/64 Partial EMS (1h) CAT /4 In 2015/2016: 16/0- EMS events (2b); 1/1 LOOP (2d); 4/3 Loss of >300MW Firm Load (2f) CAT /2 In 2015/2016: 1/2 Loss of > 1400MW of generation (3a) CAT 4 3 0/0 SW Winter Weather (2011) SW Blackout (2011) Derecho (2012) CAT 5 2 0/0 Hurricane Sandy (2012) Polar Vortex (2014) Total CAT 1-5 Events /121 Non-Qualified Occurrences reported / RELIABILITY ACCOUNTABILITY

34 Lessons Learned Metrics Published Lessons Learned By Year 34 RELIABILITY ACCOUNTABILITY

35 Category of Lessons Learned Published to Date 7 NERC lessons learned published to date in Relaying and Protection Systems 5 Communications 16 NERC lesson learned published in Relaying and Protection Systems 7- Communications 1- Transmission Facilities 2- Generation Facilities 2- Bulk-Power System Operations 35 RELIABILITY ACCOUNTABILITY

36 Lesson Learned Review Process Draft submitted Regional EA staff review/cleanup NERC EA staff review/cleanup NERC EAS initial review and recommendation to pursue or not NERC EAS sets small team to review with entity if available and willing NERC EAS final review and approval to post NERC Technical writing review 36 RELIABILITY ACCOUNTABILITY

37 Lessons Learned Input Methods ERO Event Analysis Process reports Major Disturbances Minor occurrences (or events that do not qualify for EA) Good outcomes that have information worthy of passing along Near miss (or near hit) Automatic Voltage Regulator Example Events not in North America 37 RELIABILITY ACCOUNTABILITY

38 Lessons Learned Feedback NERC s goal with publishing lessons learned is to provide industry with technical and understandable information that assists them with maintaining the reliability of the bulk power system. NERC requests that industry provide input on lessons learned by taking the short survey. A link is provided in the PDF version of each Lesson Learned. 38 RELIABILITY ACCOUNTABILITY

39 Access Lessons Learned Go to Program Areas & Departments > Reliability Risk Management > Event Analysis > Lessons Learned 39 RELIABILITY ACCOUNTABILITY

40 Contact Information Hassan Hamdar Chair, Event Analysis Subcommittee Jule Tate NERC Associate Director, Event Analysis General NERC Event Analysis Mailbox 40 RELIABILITY ACCOUNTABILITY

41 For more Information please contact: (via ) 41 RELIABILITY ACCOUNTABILITY

Québec Interconnection Approach to BES

Québec Interconnection Approach to BES Québec Interconnection Approach to BES Placer une photo ici s il y a lieu NPCC Governmental/Regulatory Affairs Advisory Group Sylvain Clermont November 27, 2012 Introduction: HQT Our mission HQT operates

More information

NERC EAS Update. Tim Reynolds Sr. Reliability Engineer W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L

NERC EAS Update. Tim Reynolds Sr. Reliability Engineer W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L NERC EAS Update Tim Reynolds Sr. Reliability Engineer 2 Changes to the ERO EAP Changes to the EAP to facilitate collecting data Events involving near-misses Inverter disturbances Other things as identified

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

2017 MRO Performance Areas and an Update on Inherent Risk Assessments

2017 MRO Performance Areas and an Update on Inherent Risk Assessments MIDWEST RELIABILITY ORGANIZATION 2017 MRO Performance Areas and an Update on Inherent Risk Assessments Adam Flink, Risk Assessment and Mitigation Engineer November 16, 2016 Improving RELIABILITY and mitigating

More information

FERC Reliability Technical Conference Panel I: 2015 State of Reliability Report Introduction Overview of the State Of Reliability

FERC Reliability Technical Conference Panel I: 2015 State of Reliability Report Introduction Overview of the State Of Reliability : 2015 State of Reliability Report Remarks of Thomas Burgess, Vice President and Director of Reliability Assessment and Performance Analysis Introduction Chairman Bay and Commissioners, members of the

More information

Agenda Event Analysis Subcommittee Conference Call

Agenda Event Analysis Subcommittee Conference Call Agenda Event Analysis Subcommittee Conference Call August 14, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security

More information

State of Reliability Report 2013

State of Reliability Report 2013 State of Reliability Report 2013 Jessica Bian, Director of Performance Analysis Reliability Assessment and Performance Analysis (RAPA), NERC Risk Issues Steering Committee Meeting, July 11-12, 2013 State

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Wide-Area Reliability Monitoring and Visualization Tools

Wide-Area Reliability Monitoring and Visualization Tools OE Visualization and Controls Peer Review Wide-Area Reliability Monitoring and Visualization Tools Carlos Martinez CERTS - Electric Power Group 21 October 2008 Washington, D.C. Presentation Outline Research

More information

Standards Authorization Request Justification

Standards Authorization Request Justification Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.

5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval. Introduction 1. Title: IROL and SOL Mitigation in the ERCOT Region 2. Number: IRO-006-TRE-1 3. Purpose: To provide and execute transmission loading relief procedures that can be used to mitigate SOL or

More information

Standard EOP Disturbance Reporting

Standard EOP Disturbance Reporting A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

Enhanced Curtailment Calculator Update

Enhanced Curtailment Calculator Update Enhanced Curtailment Calculator Update December 13, 2017 Member Advisory Committee Meeting Brett Wangen Chief Engineering and Technology Officer Jeremy West Manager, Interconnection Reliability Initiatives

More information

Project Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018

Project Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018 Project 2017-01 Modifications to BAL-003-1.1 Frequency Response and Frequency Bias Setting Industry Webinar December 18, 2018 Administrative Items North American Electric Reliability Corporation (NERC)

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013 Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently

More information

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support TOP/IRO Standards RC Users Group January 21, 2016 Vic Howell Manager, Operations Engineering Support Saad Malik Manager, Real-Time Operations Engineering New/Revised TOP & IRO Standards November 19, 2015,

More information

Reliability Standards Development Plan

Reliability Standards Development Plan Reliability Standards Development Plan 2012-2014 October 13, 2011 For SC Approval 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents...ii

More information

Implementation Plan for COM-001-2

Implementation Plan for COM-001-2 Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.

More information

FRCC Disturbance Reporting Processes and Procedures

FRCC Disturbance Reporting Processes and Procedures Page 1 of 13 FRCC Disturbance Reporting Processes and FRCC RE OP 001-3.2 Effective Date: September 29, 2016 Version: 3.2 3000 Bayport Drive, Suite 600 Tampa, Florida 33607-8410 (813) 289-5644 - Phone (813)

More information

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols

Unofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Operating Personnel Communications Protocols Please DO NOT use this form. Please use the electronic comment form to submit comments

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

Project Posting 8 Frequently Asked Questions Guide

Project Posting 8 Frequently Asked Questions Guide Project 2007-02 Posting 8 Frequently Asked Questions Guide General Questions 1. What were the inputs that drove the development of posting 8 of Project 2007-02? The NERC Board of Trustees November 7 th,

More information

Reliability Compliance Update. Reliability Standards and Compliance Subcommittee Preston Walker August 16, 2018

Reliability Compliance Update. Reliability Standards and Compliance Subcommittee Preston Walker August 16, 2018 Reliability Compliance Update Reliability Standards and Compliance Subcommittee Preston Walker August 16, 2018 NERC Standards Under Development Standards Project Action End Date Comment 08/27/2018 Draft

More information

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia

British Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia Page 1 of 15 British Columbia Utilities Reliability Standards with s adopted in British Columbia BAL-001-2 Standard Real Power Balancing Control Performance R-14-16 July 1, 2016 BAL-002-1 1 Disturbance

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Draft CIP Standards Version 5

Draft CIP Standards Version 5 Draft CIP Standards Version 5 Technical Webinar Part 1 Project 2008-06 Cyber Security Order 706 Standards Drafting Team November 15, 2011 Agenda Opening Remarks John Lim, Consolidated Edison, Chair V5

More information

Agenda Event Analysis Subcommittee Conference Call

Agenda Event Analysis Subcommittee Conference Call Agenda Event Analysis Subcommittee Conference Call September 11, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security

More information

requirements in a NERC or Regional Reliability Standard.

requirements in a NERC or Regional Reliability Standard. CIP 002 5.1 Cyber Security BES Cyber System Categorization A. Introduction 1. Title: Cyber Security BES Cyber System Categorization 2. Number: CIP 002 5.1 3. Purpose: To identify and categorize BES Cyber

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

Standard Authorization Request Form

Standard Authorization Request Form Standard Authorization Request Form E-mail completed form to rsm@texasre.org Texas RE to Complete SAR No: Title of Proposed Standard IRO-006-TRE-1 IROL and SOL Mitigation in the ERCOT Region Request Date

More information

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 Power System Resilience & Reliability Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 NERC, Reliability, & Resilience NERC has addressed reliability

More information

FERC Reliability Technical Conference -- Panel I State of Reliability and Emerging Issues

FERC Reliability Technical Conference -- Panel I State of Reliability and Emerging Issues -- State of Reliability and Emerging Issues Remarks of Thomas Burgess, Vice President and Director, Reliability Assessment and Performance Analysis Chairman Wellinghoff, Commissioners, Staff, and fellow

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

Standard Development Timeline

Standard Development Timeline CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements.

1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements. MISO Investigation Report on the NERC TLR Level 5 Event North Platte Stockville 115kV for the loss of the Gentleman Red Willow 345kV Flowgate 6023 August 22 nd / 23 rd, 2002 Report issued: September 3

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Analysis of System Protection Misoperations

Analysis of System Protection Misoperations Analysis of System Protection Misoperations December 2015 Table of Contents Preface... ii Executive Summary...1 Introduction...2 Chapter 1 Misoperation Data Analysis...4 Misoperation Data Reported...4

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

2018 MRO Regional Risk Assessment

2018 MRO Regional Risk Assessment MIDWEST RELIABILITY ORGANIZATION 2018 MRO Regional Risk Assessment Ben Lewiski, Risk Assessment and Mitigation Engineer November 28, 2017 Improving RELIABILITY and mitigating RISKS to the Bulk Power System

More information

USE CASE 14 CONTROLLED ISLANDING

USE CASE 14 CONTROLLED ISLANDING I USE CASE 14 CONTROLLED ISLANDING Use Case Title Centralized application separates grid into islands to prevent blackout Use Case Summary Controlled islanding is a method that can significantly improve

More information

BAL Real Power Ba la ncing Control Performance Standard Background Document

BAL Real Power Ba la ncing Control Performance Standard Background Document BAL-001-1 Real Power Ba la ncing Control Performance Standard Background Document January 2012 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents

More information

Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13

Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 Texas Reliability Entity, Inc. Strategic Plan for 2017 TEXAS RE STRATEGIC PLAN FOR 2017 PAGE 1 OF 13 I. Vision A highly reliable and secure bulk power system in the Electric Reliability Council of Texas

More information

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project ) Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic

More information

Agenda Event Analysis Subcommittee Conference Call

Agenda Event Analysis Subcommittee Conference Call Agenda Event Analysis Subcommittee Conference Call October 23, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security

More information

ERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016

ERO Reliability Risk Priorities Report. Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 ERO Reliability Risk Priorities Report Peter Brandien, RISC Chair Member Representatives Committee Meeting November 1, 2016 RISC s Proposed 2016 Risk Profiles Changing Resource Mix Bulk Power System Planning

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014 Request for Data or Information Protection System Misoperation Data Collection August 14, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 15 Table of

More information

Standards. Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013

Standards. Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013 Standards Mark Lauby, Vice President and Director of Standards Board of Trustees Meeting November 7, 2013 Geomagnetic Disturbance Operations EOP-010-1 Reliability benefits Enhance operating response to

More information

Essential Reliability Services NERC Staff Report

Essential Reliability Services NERC Staff Report Essential Reliability Services NERC Staff Report Mark Lauby, Senior Vice President and Chief Reliability Officer Annual Meeting of the National Conference of State Legislators August 20, 2014 About NERC

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

Standard Development Timeline

Standard Development Timeline CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities

Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities Impacts and Implementation: NERC Reliability Standards, Compliance Initiatives, and Regulatory Activities NRECA TechAdvantage March 2014 Patti Metro Manager, Transmission & Reliability Standards NRECA

More information

Member Representatives Committee Meeting

Member Representatives Committee Meeting Member Representatives Committee Meeting August 13, 2014 1:15 p.m. 5:15 p.m. Pacific The Westin Bayshore, Vancouver 1601 Bayshore Drive Vancouver, BC V6G 2V4 Canada Opening Remarks by MRC Chair Consent

More information

DER Data Collection Guideline. Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017

DER Data Collection Guideline. Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017 DER Data Collection Guideline Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017 Since the August 3, 2017, Meeting Data Collection Guideline has been through two rounds of comment from DER Subgroup

More information

Achieving Smarter Grid Operation With On-Line DSA Technology

Achieving Smarter Grid Operation With On-Line DSA Technology Achieving Smarter Grid Operation With On-Line DSA Technology Powercon 2014 October 20-22, 2014, Chengdu, China Lei Wang Powertech Labs Inc. 12388 88 th Avenue Surrey, BC, Canada A very simple version of

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor May 10, 2017 ISAS Salt Lake City, UT WECC Standard TOP 007 WECC 1a Title: System Operating Limits Purpose: To limit instances where

More information

Risk-Based Approach to Compliance Monitoring and Enforcement

Risk-Based Approach to Compliance Monitoring and Enforcement Risk-Based Compliance Oversight Plan Process for Risk Elements and Associated The ERO Enterprise continues to identify risks to the reliability of the BPS, as well as mitigating factors that may reduce

More information

Member Representatives Committee. Pre-Meeting and Informational Webinar January 16, 2013

Member Representatives Committee. Pre-Meeting and Informational Webinar January 16, 2013 Member Representatives Committee Pre-Meeting and Informational Webinar January 16, 2013 Objectives Review preliminary agenda topics for February 6 Member Representatives Committee (MRC) meeting. Review

More information

NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM September 6, 2013

NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM September 6, 2013 NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM-003-1 September 6, 2013 At the August 14-15, 2013 meeting of the Board of Trustees ( Board ) of the North

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

Standard TOP Transmission Operations

Standard TOP Transmission Operations A. Introduction 1. Title: Transmission Operations 2. Number: TOP-001-34 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1 DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...

More information

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September 23, 2009 TABLE OF CONTENTS INTRODUCTION A. RESPONSIBILITIES

More information

DRAFT Risks and Mitigations for Losing EMS Functions

DRAFT Risks and Mitigations for Losing EMS Functions DRAFT Risks and Mitigations for Losing EMS Functions 1.0 Executive Summary Energy Management System (EMS) is a system of computer-aided tools used by System Operators to monitor, control, and optimize

More information

Methods for Establishing IROLs Task Force

Methods for Establishing IROLs Task Force Methods for Establishing IROLs Task Force Progress Update Ryan D. Quint Senior Manager, Advanced Analytics and Modeling OC/PC Joint Meeting March 7, 2017 Background MEITF kicked off in December to: Address

More information

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision Table of Contents I. Purpose... 2 II. Introduction... 2 III. Peak Roles and Responsibilities... 2 IV. Applicability and Obligations... 3 V. Questions and Comments... 6 VI. Data Request Spreadsheet... 6

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

COM Communications and Coordination

COM Communications and Coordination COM-002-2 Communications and Coordination February 27, 2014 Lonnie Lindekugel ~ SPP Jim Nail ~ City of Independence INTRODUCTION NERC Reliability Standard COM-002-2 (Communications and Coordination) serves

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures.

More information

Chapter X Security Performance Metrics

Chapter X Security Performance Metrics DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the

More information

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS

IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS IMPROVING POWER SYSTEM RELIABILITY USING MULTIFUNCTION PROTECTIVE RELAYS Armando Guzmán Schweitzer Engineering Laboratories, Inc. Pullman, WA 99163 A reliable power system maintains frequency and voltage

More information

Project , COM Operating Personnel Communications Protocols Rationale and Technical Justification

Project , COM Operating Personnel Communications Protocols Rationale and Technical Justification Project 2007-02, COM-002-4 Operating Personnel Communications Protocols Rationale and Technical Justification Posting 8: Background and Justification for COM-002-4 Requirements The purpose of the proposed

More information

Reliability Coordinator Procedure

Reliability Coordinator Procedure No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR

More information

Steve Ashbaker Director Operations. NASPI Workgroup Meeting February 21, 2013 Atlanta, GA

Steve Ashbaker Director Operations. NASPI Workgroup Meeting February 21, 2013 Atlanta, GA Steve Ashbaker Director Operations NASPI Workgroup Meeting February 21, 2013 Atlanta, GA September 8, 2011 Event Update May 1 FERC/NERC Inquiry Report issued o 27 Recommendations in 8 categories July 26

More information

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table

More information

Standard Authorization Request Form

Standard Authorization Request Form Standard Authorization Request Form Title of Proposed Standard: Project 2009-02: Real-time Reliability Monitoring and Analysis Capabilities Original Request Date: June 4, 2009 Revised Date: January 15,

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Critical Asset Identification Methodology. William E. McEvoy Northeast Utilities

Critical Asset Identification Methodology. William E. McEvoy Northeast Utilities Critical Asset Identification Methodology William E. McEvoy Northeast Utilities Disclaimer This NPCC TFIST workshop provides a forum for the presentation and discussion of member experience in the implementation

More information

Peak Reliability Coordination Services in the West March 30, 2018

Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability, 2018. 1 Peak Reliability Coordination Services in the West Peak s fundamental mission is to enhance and promote the reliability

More information

History of NERC January 2018

History of NERC January 2018 History of NERC January 2018 Date 1962 1963 The electricity industry created an informal, voluntary organization of operating personnel to facilitate coordination of the bulk power system in the United

More information

ERO Enterprise Strategic Planning Redesign

ERO Enterprise Strategic Planning Redesign ERO Enterprise Strategic Planning Redesign Mark Lauby, Senior Vice President and Chief Reliability Officer Member Representatives Committee Meeting February 10, 2016 Strategic Planning Redesign Current

More information

Table of Issues and Directives Project Relay Loadability: Stable Power Swings

Table of Issues and Directives Project Relay Loadability: Stable Power Swings Table of Issues and Directives Project 2010-13.3 Relay Loadability: Stable Power Swings FERC Order 733 150. We will not direct the ERO to modify PRC-023-1 to address stable power swings. However, because

More information

BESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2

BESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2 Table of Contents BESNet User Manual Exception Request Preparation for Registered Entities June 29, 2014 Version 1-2 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com

More information

ERO Enterprise IT Projects Update

ERO Enterprise IT Projects Update ERO Enterprise IT Projects Update Stan Hoptroff, Vice President, Chief Technology Officer and Director of Information Technology Technology and Security Committee Meeting November 6, 2018 Agenda ERO IT

More information

Comments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference

Comments by the Northeast Power Coordinating Council FERC Reactive Power Technical Conference Introduction The Northeast Power Coordinating Council 1 (NPCC) is an international electric regional reliability council formed shortly after the 1965 Northeast Blackout to promote the reliability and

More information