1 MISO Investigation Report on the NERC TLR Level 5 Event North Platte Stockville 115kV for the loss of the Gentleman Red Willow 345kV Flowgate 6023 August 22 nd / 23 rd, 2002 Report issued: September 3 rd, 2002 This report is submitted in accordance with the NERC Transmission Loading Relief (TLR) Investigation Procedure for the TLR event that occurred on Flowgate 6023 on August 22 nd and 23 rd, Flowgate 6023 is a Nebraska Public Power District (NPPD) Flowgate. The duration of TLR Level 5 was approximately five hours, and resulted in the partial curtailment of firm transmission service as well as Network and Native Load (NNL) Service relief. The NERC TLR Log is included as Appendix A. 1. Description of purpose/cause of hold/curtailment: Flowgate 6023 flow gate consists of the following elements. Monitored Facility: North Platte - Stockville 115kV Line Contingent Facility: Gentleman Red Willow 345kV Line On Thursday August 22 nd, 2002 the Gentleman-Red Willow 345kV line loading increased quickly and exceeded the OSL. Loading on the flow gate did not exceed the 455mw OSL for 30-minutes or longer at any point in time throughout this event. NERC TLR 5a was initiated after a 3b failed to provide sufficient flow gate relief. The high or heavy loading on this flow gate is a nightly occurrence. Export flows in the MAPP region increase significantly during the off-peak hours. The Western Nebraska Western Kansas interface operating guide calls for NERC TLR non-firm curtailments to be implemented in order to maintain the loading within the limit parameters. If all nonfirm schedules have been curtailed, and still a loading problem continues on the flow gate, the opening of the 115kV breaker 1110 at Red Willow is initiated as long as the real-time security analysis application provides adequate support for this action. Opening breaker 1110 isolates the 115kV system from the voltage stability concern as identified in the operating guide. However, on the eve of August 22 nd and the early morning of August 23 rd, there were storms throughout much of Nebraska and Kansas. The storms prevented opening breaker 1110 at Red Willow. 2. Facility/Flowgate limitations and flow at the time the TLR was initiated: The Western Nebraska Western Kansas (WNE_WKS) Interface is currently defined as both a post-contingent voltage constrained interface and a post-contingent thermally constrained interface. The worst contingency for the WNE_WKS Interface is loss of the Gentleman-Red Willow and Gentleman -Sweetwater Circuit #2 345 kv double-circuit. Loss of the 345 kv double circuit results in post-contingent voltages at or near the 0.90 p.u. emergency limit, as well as post-contingent line loadings at or near the overload limit of 110%. With Page 1 of 9

2 the Gentleman - Red Willow 345 kv line open, bulk transmission system power flows are imposed across the parallel 115 kv lines to get back to the low impedance path on the 345 kv line from Red Willow to Mingo. Although the 345 kv double circuit outage is the worst contingency, sensitivity analysis has demonstrated that monitoring and limiting the flows on the GGS-Red Willow 345 kv line alone is adequate to address operating security limits associated with the WNE_WKS Interface. It has been determined through studies that the voltage based flow limit for the Gentleman-Red Willow 345kV line is 455MW. This is the level of loading on that facility that has been determined to cause voltage stability problems for the underlying 115kV system, which includes the North Platte-Stockville 115kV line. At 2205 the flows on the Gentleman-Red Willow 345kV line were at 458MW. A TLR 1 was issued with expectations of non-firm curtailments, and then NPPD opening breaker 1110 at Red Willow to alleviate the problem. As flows started to increase, NPPD informed MISO St Paul they would be unable to open the breaker due to storms in the Red Willow area and requested relief to maintain 455MW. A TLR 3b was initiated for across 2230 CDT with all non-firm scheduled curtailed (51MW of relief was implemented). A TLR 3a was issued at 2227 for across 2300 CDT continuing all nonfirm scheduled curtailed. At 2237 CDT the flow increased to 484MW, and the IDC was projecting the flow gate loading to continue to increase. A NERC TLR 5a was initialized with relief requested for across 2300, and remained in effect until 0432 CDT, with one exception. At 0133 CDT, the flow on the Gentleman-Red Willow decreased to 356MW. A level 3a was issued across 0200 CDT with all non-firm schedules remaining curtailed. (42MW of relief continued), and all firm curtailments released. At 0205 CDT the flow increased to 480MW when SPS lost the 540MW Tolk unit. A TLR 5b with 60MW of relief was issued for across 0230 CDT, and reissued as TLR 5a across 0300 CDT continuing current relief level and remained in effect until 0432 CDT when firm schedules were allowed to reload and a TLR 1 was issued. Storms in Nebraska had cleared by this time, and breaker 1110 was opened at The event concluded with a TLR 0 at 0603 CDT. 3. TLR Levels, timing (CDT) and relief amounts TLR LEVEL TIME (CDT) Flowgate Relief Entered into IDC (MW) Number of transactions curtailed, priority, and magnitude of transactions b (1NS) 275 MW schedules curtailed. 4 (2NH) 245 MW schedules curtailed. 1 Page 2 of 9

3 (5NM) 50 MW schedule curtailed. 3 (6NN) 245 MW schedules curtailed. 3a Did not take effect due to change to 5a. 5a (1NS) 250 MW schedules curtailed. 5 (2NH) 270 MW schedules curtailed. 1 (5NM) 50 MW schedule curtailed. 3 (6NN) 270 MW schedules curtailed. 24 (7F) 254 MW schedules curtailed, a (1NS) 70 MW schedules curtailed. 2 (6NN) 270 MW schedules curtailed. 26 (7F) 315 MW schedules curtailed, a (1NS) 70 MW schedules curtailed. 2 (6NN) 270 MW schedules curtailed. 25 (7F) 260 MW schedules curtailed, a (1NS) 70 MW schedules curtailed. 2 (6NN) 270 MW schedules curtailed. 5b (1NS) 70 MW schedules curtailed. 2 (6NN) 270 MW schedules curtailed. 25 (7F) 164 MW schedules curtailed, a (1NS) 70 MW schedules curtailed. 2 (6NN) 270 MW schedules curtailed. 24 (7F) 145 MW schedules curtailed, a (1NS) 95 MW schedules curtailed. 2 (6NN) 270 MW schedules curtailed. 23 (7F) 82 MW schedules curtailed, 18.2 MW NNL prescribed End Event Page 3 of 9

4 4. Transmission and generation outage or changes from prediction that may have contributed: Loading on this flow gate typically increases during off-peak hours. It is normal to implement NERC TLR non-firm curtailments, and then open breaker 1110 thereafter in order to maintain the loading on the flow gate within the safe operating parameters. However as far as other impacts, we did experience the flow dramatically increase when SPS lost the Tolk unit 540MW at Procedures implemented prior to hold/curtailment: There were no procedures implemented prior to hold/curtailment. No operating procedures or reconfiguration actions were available for mitigating the loading problem. 6. Compare Complete Transaction Curtailment List with the Whole Transaction List as generated by the IDC, before and after curtailments: All non-firm transactions that impacted Flow gate 6023 by 5% or greater were curtailed and reloaded as required by NERC policy. Firm transactions impacting flow gate 6023 by 5% or greater were partially curtailed and reloaded per NERC policy. 7. Known Transactions not in the IDC and actions taken: There were no known transactions not in the IDC at the time this TLR was in effect that were impacting this flow gate. 8. RCIS or other system messages: Information was provided to NERC Reliability Coordinators via the NERC IDC. The IDC automatically sent TLR Level information via the RCIS. Curtailment information was sent out via the MISO MCN. 9. State estimator snapshots and security analysis including contingency analysis or stability analysis along with any other recorded data indicating the need for TLR: Relief requirements were calculated by using real-time loadings on monitored and contingent elements. Real-time security analysis was monitored at the NPPD control center, as well as at the MISO St. Paul Security Center. NPPD confirmed that the MISO results were consistent with their state estimator/contingency analysis results. Page 4 of 9

5 10. ATC Limitations before, during, and after the event: There were no ATC / AFC limitations on this flow gate. The ATC s was zero throughout the entire night, which is normal for when the interface is operating at the limit. No new reservations on the MAPP or MISO tariff that impact this flow gate by 5% (or greater) were approved. 11. Description of actions taken to avoid future hold/curtailments: As soon as the storms moved out of the area, breaker 1110 at Red Willow was opened to permit the transactions to be reloaded. 12. Re-dispatch actions taken: There was no system emergency declared. The re-dispatch actions associated with the NERC TLR level 5 for mitigating the NNL was the only re-dispatch ordered or implemented. 13. If Firm transaction curtailments took place, description of Transactional Contribution Factor calculation and results as well as how necessary relief was obtained through network service and native load contributions: Per the IDC file, there were five MISO control areas with NNL responsibilities. (NPPD, LES, MEC, WAPA and WPEK). GSF s were attained from the IDC. 1) NPPD decremented Gentleman and increased the McCook generation. In addition, NPPD decremented Gentleman generation as control area irrigation load was intentionally decreased. NPPD complied with the NNL responsibility. 2) MEC took off-line and purchased energy from WPEK generation. MEC and WPEK complied with the NNL responsibility. 3) WAPA increased flow west on the Miles City DC tie. This increased the south to north and east to west flow which reduced the Gentleman Red Willow 345kv line flow. WAPA complied with the NNL responsibility. 4) LES had firm schedules curtailed that were serving native load, and replaced the energy with the Rokeby generators in Lincoln. In addition, LES backed down its share of Laramie River Station during the later stages of the TLR which increased the south to north and east to west flow which reduced the Gentleman Red Willow 345kv line flow. The double counting in the IDC for LES has been resolved. Per the IDC, LES had an NNL reduction responsibility based upon their share of ownership of the Gentleman, Cooper and Sheldon generators. However, the LES ownership megawatts are tagged and were curtailed. The firm LES tags are NPPD_LES _LES, NPPD_LES _LES, and NPPD_LES _LES. Changes have been made in the IDC to identify the LES ownership of each generator Page 5 of 9

6 correctly, and therefore will remove LES from having any NNL responsibility in the future per firm curtailments on this flow gate that were caused by these particular generators. I.e. the double counting has been eliminated. Control area actions to mitigate the NNL requirements: for 2300 to 0000 CDT NPPD ** 41.5 Mccook (46) Dec load (34) Dec load (26) GGS (46) GGS1 (34) GGS2 (26) LES 7.7 * * * * MEC 3.4 WPEK (14) MEC (14) WAPA 5 WAPA E WAPA W WPEK 5.8 WPEK (26) MEC (26) Control area actions to mitigate the NNL requirements: for 0000 to 0100 CDT NPPD 49.8 Mccook(46) Dec load (68) Dec load (52) GGS (46) GGS1 (68) GGS2 (52) LES 9.3 * * * * MEC 4.1 WPEK (14) MEC (14) WAPA 6 WAPA E WAPA W WPEK 7 WPEK (26) MEC (26) Page 6 of 9

7 Control area actions to mitigate the NNL requirements: for 0100 to 0200 CDT NPPD 42.8 Mccook (46) Dec load (68) Dec load (52) GGS (46) GGS1 (68) GGS2 (52) LES 7.8 * * * * MEC 3.4 WPEK (14) MEC (14) WAPA 5.1 WAPA E WAPA W WPEK 5.9 WPEK (26) MEC (26) ***A TLR level 3A was implemented for across All firm was restored across At 02:08, flows significantly increased again, requiring a TLR level 5B to be initiated at 02:17. Control area actions to mitigate the NNL requirements: for 0217 to 0300 CDT NPPD 24.9 Mccook (46) GGS (46) LES 4.6 * * * * MEC 1.8 MEC (10) WPEK (10) 30 3 WAPA 2.9 WPEK 3.4 WAPA E WPEK (20) WAPA W MEC (20) 30 6 Page 7 of 9

8 Control area actions to mitigate the NNL requirements: for 0300 to 0400 CDT NPPD 21.8 Mccook (46) GGS (46) LES 4 * * * * MEC 1.6 MEC (10) WPEK (10) 30 3 WAPA 2.6 WPEK 3 WAPA E WPEK (20) WAPA W MEC (20) 30 6 Control area actions to mitigate the NNL requirements: for 0400 to 0432 CDT NPPD 12 Mccook (46) GGS (46) LES 2.2 * * * * MEC.9 MEC (10) WPEK (10) 30 3 WAPA 1.4 WPEK 1.6 WAPA E WPEK (10) WAPA W MEC (10) Other options considered before/during to avoid hold/curtailment: Curtailing non-firm and opening the 115kV breaker at Red Willow is a nightly action. The severe weather removed the option of opening the breaker, forcing a NERC TLR level 5 to be declared. 15. Lessons learned: Even though the NERC TLR timing requirements with respect to the TLR procedure, and TLR level 5 procedures are communicated to the control area operators at the regional spring and fall training seminars, we have discovered that we need to train more frequently. Some control areas knew exactly what was required with the NNL reduction requirements. Others required extra time of the Reliability Coordinator in order to discuss what needed to be done. We will work on improving this training process in order to be able to reach more system operators. Page 8 of 9

9 Appendix A NERC TLR Log for Flowgate 6023 (North Platte-Stockville 115kV flo Gentleman-Red Willow 345kV) Page 9 of 9

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007

MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007 MISO Investigation Report on the NERC TLR Level 5 Event Alliant Energy Flowgate 14266: Wisdom-Triboji 161kV flo Sherco #3 June 11, 2007 Report submitted to NERC on: July 12, 2007. This report is submitted

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September 23, 2009 TABLE OF CONTENTS INTRODUCTION A. RESPONSIBILITIES

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Cherrywood Circuit Breaker Incident - December 12, 2005

Cherrywood Circuit Breaker Incident - December 12, 2005 Public IESO_REP_0316 Cherrywood Circuit Breaker Incident - December 12, 2005 Public IESO_REP_0316 Document ID IESO_REP_0316 Document Name Cherrywood Circuit Breaker Incident - December 12, 2005 Issue Issue

More information

LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL. September 2001

LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL. September 2001 LAKE ERIE EMERGENCY RE-DISPATCH OPERATIONS MANUAL September 2001 TABLE OF CONTENTS INTRODUCTION...3 SECTION A: GENERATION SHIFT FACTORS...4 SECTION B: COMMUNICATIONS PROTOCOLS...ERROR! BOOKMARK NOT DEFINED.

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO

MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO 1 MISO Online Dynamic Security Assessment(DSA) Raja Thappetaobula Senior Advisor MISO 2 MISO Overview MISO is an independent, non-profit, memberbased organization committed to reliability. We serve as

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Enhanced Curtailment Calculator Update

Enhanced Curtailment Calculator Update Enhanced Curtailment Calculator Update December 13, 2017 Member Advisory Committee Meeting Brett Wangen Chief Engineering and Technology Officer Jeremy West Manager, Interconnection Reliability Initiatives

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Available Transfer Capability Definitions and Determination

Available Transfer Capability Definitions and Determination Available Transfer Capability Definitions and Determination A framework for determining available transfer capabilities of the interconnected transmission networks for a commercially viable electricity

More information

Wide Area Measurements & Control Systems

Wide Area Measurements & Control Systems The 8 th Electric Power Control Centers Workshop June 5-8, 2005, Les Diablerets, Switzerland Wide Area Measurements & Control Systems NERC Security Coordinators and Interregional Security Network Nodes

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Operating Reliability Subcommittee Presentations. February 10-11, 2015

Operating Reliability Subcommittee Presentations. February 10-11, 2015 Operating Reliability Subcommittee Presentations February 10-11, 2015 Presentation 1 ORS February 10, 2015 EInet Transition Efforts All current RC nodes on NERCNet have placed orders for new network EIDSN

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Mountain West Transmission Group. WECC MIC Update October 17, 2017

Mountain West Transmission Group. WECC MIC Update October 17, 2017 Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain

More information

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015

SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 SPP RTO Compliance Forum Western Area Power Administration March 11, 2015 Mark Buchholz WAPA Upper Great Plains Region Compliance Manager What is Western? One of four Power Marketing Administration within

More information

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study

Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities. Non-Tariff System Impact Study Interconnection of Navajo-Gallup Water Supply Project Electrical Transmission Facilities Non-Tariff System Impact Study March 204 Prepared by: Utility System Efficiencies, Inc (USE) Under Contract with:

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

MOD Transmission Reliability Margin Implementation Document

MOD Transmission Reliability Margin Implementation Document Transmission Margin Implementation Document Transmission Margin Implementation Document For NERC Page 1 of 7 Transmission Margin Implementation Document 1.0 Purpose The California Independent System Operator

More information

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration

Mountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

2016 Fall ITO Stakeholder Meeting. Topics in Operations

2016 Fall ITO Stakeholder Meeting. Topics in Operations 2016 Fall ITO Stakeholder Meeting Topics in Operations 11/17/2016 TOP-003-3 Requirement R1. Each Transmission Operator shall maintain a documented specification for the data necessary for it to perform

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

Terry Williams Tennessee Valley Authority

Terry Williams Tennessee Valley Authority Knox - Douglas 161 (FLO) E Knox - Dumplin Valley 161 exceedance Presentation 1 Use of Proxy Flowgate for Exceedance to: Knox - Douglas 161kV (FLO) E Knox - Dumplin Valley 161kV line 9/29/2015 Terry Williams

More information

Standard EOP Disturbance Reporting

Standard EOP Disturbance Reporting A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment

More information

Year Assessment Preliminary Solutions

Year Assessment Preliminary Solutions 2016 10-Year Assessment Preliminary Solutions Stakeholder and Customer Presentation May 26, 2016 Jeremy Voigt Purpose Summarize Asset Renewal Solution Identification Process Summarize Preliminary Changes

More information

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1

BC Hydro Open Access Transmission Tariff Effective: January 26, 2018 OATT Attachment Q-1 First Revision of Page 1 OATT Attachment Q-1 First Revision of Page 1 ATTACHMENT Q-1 Dynamic Scheduling This attachment contains the eligibility requirements and the terms and conditions for the provision of dynamic scheduling

More information

AC-DC ERCOT. Bill Bojorquez Dejan J. Sobajic ERCOT Grid Engineering LLC. June 6, 2005 Les Diablerets, Switzerland

AC-DC ERCOT. Bill Bojorquez Dejan J. Sobajic ERCOT Grid Engineering LLC. June 6, 2005 Les Diablerets, Switzerland The 8 th Electric Power Control Centers Workshop June 5-8, 2005, Les Diablerets, Switzerland Panel Session "Monitoring and Control of Large Interconnections under Normal and Emergency Operating Conditions"

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

Transmission Service Reference Manual. May 08, 2017

Transmission Service Reference Manual. May 08, 2017 Transmission Service Reference Manual May 08, 2017 Revision History Revision History Date or Version Number April 29, 2015 Version 1.0 May 08, 2017 Version 2.0 Author Shari Brown Julie Gerush Change Description

More information

Open Access Transmission Tariff of Southern Companies

Open Access Transmission Tariff of Southern Companies Open Access Transmission Tariff of Southern Companies Procedures for Reserving Transmission Capacity for Future Load Growth, Designating/Undesignating Network Resources, and Arranging for Other Related

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures.

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

Coordinate Interchange

Coordinate Interchange Coordinate Interchange Purpose: The purpose of this standard is to define procedures for market participants to request the implementation of Interchange Transactions. Applicability: This Standard applies

More information

Coordinate Interchange

Coordinate Interchange Coordinate Interchange Purpose: The purpose of this standard is to define procedures for market participants to request the implementation of Interchange Transactions. Applicability: This Standard applies

More information

N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL

N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL Michehl R. Gent President and CEO N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL Princeton Forrestal Village, 116-390 Village Boulevard, Princeton, New Jersey 08540-5731 The Honorable Patrick H. Wood III,

More information

Unused Generation Capacity Study Scope. Informational Analysis

Unused Generation Capacity Study Scope. Informational Analysis Unused Generation Capacity Study Scope Informational Analysis MISO Jan 9, 2014 Table of Contents 1.0 Project Overview... 3 2.0 Scope of Work... 4 2.1 Phase 1 - Preliminary Analysis... 5 2.2 Phase 2 System

More information

Peak Reliability Coordination Services in the West March 30, 2018

Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability Coordination Services in the West March 30, 2018 Peak Reliability, 2018. 1 Peak Reliability Coordination Services in the West Peak s fundamental mission is to enhance and promote the reliability

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

RELIABILITY OF THE BULK POWER SYSTEM

RELIABILITY OF THE BULK POWER SYSTEM RELIABILITY OF THE BULK POWER SYSTEM Jim Burley, VP of Compliance, Mitigation and Standards October 26, 2011 Promoting RELIABILITY and Mitigating RISKS to the Bulk Power System Context In the Beginning-2003

More information

December 13, Sw. Power Pool, Inc., 144 FERC 61,224 (2013) ( September 2013 Order ).

December 13, Sw. Power Pool, Inc., 144 FERC 61,224 (2013) ( September 2013 Order ). The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 December 13, 2013 Re: Southwest Power Pool, Inc., Docket No. ER12-1179-00 SPP

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision Table of Contents I. Purpose... 2 II. Introduction... 2 III. Peak Roles and Responsibilities... 2 IV. Applicability and Obligations... 3 V. Questions and Comments... 6 VI. Data Request Spreadsheet... 6

More information

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble

NETWORK INTEGRATION TRANSMISSION SERVICE. Preamble Seventh Revised Volume No. 5 (MT) Original Sheet No. 53 III. NETWORK INTEGRATION TRANSMISSION SERVICE Preamble The Transmission Provider will provide Network Integration Transmission Service pursuant to

More information

Midwest ISO Year in Review Accomplishments

Midwest ISO Year in Review Accomplishments Midwest ISO Year in Review 2006 Accomplishments 1 Reliability Accomplishments Spring storms Sustained summer heat July 31 ramping at 6,000 Megawatts (MW) per hour

More information

The various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control

The various functions of an energy control center can be enumerated as under: 1. Load forecasting 6. Automatic generation control ENERGY CONTROL CENTERS To generated, Transmission and Distribution system, Number of customers and Total investment. Installed capacity in India exceeds 206 GW with annual energy generated energy exceeding

More information

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC September 21, 2018 Penelec Transmission Zone Need Number: PN-2018-001 Consider upgrading transmission line equipment (switches, conductor, splices,

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

1. Project Description

1. Project Description Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

WECC Criterion INT-001-WECC-CRT-3

WECC Criterion INT-001-WECC-CRT-3 WECC Criterion INT-001-WECC-CRT-3 A. Introduction 1. Title: e-tag Requirements for WECC including Wrongful Denial of Request for Interchange (RFI) 2. Number: INT-001-WECC-CRT-3 3. Purpose: To manage Arranged

More information

Year Assessment Preliminary Needs

Year Assessment Preliminary Needs 2018 10-Year Assessment Preliminary Needs Stakeholder and Customer Presentation March 1, 2018 Jeremy Voigt Purpose Key Study Assumptions Reminder Summarize Preliminary Changes to Needs Solicit Input on

More information

Achieving Smarter Grid Operation With On-Line DSA Technology

Achieving Smarter Grid Operation With On-Line DSA Technology Achieving Smarter Grid Operation With On-Line DSA Technology Powercon 2014 October 20-22, 2014, Chengdu, China Lei Wang Powertech Labs Inc. 12388 88 th Avenue Surrey, BC, Canada A very simple version of

More information

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor

Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor May 10, 2017 ISAS Salt Lake City, UT WECC Standard TOP 007 WECC 1a Title: System Operating Limits Purpose: To limit instances where

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50 BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50 VOLTAGE STABILITY OPERATING LIMITS AND PROCEDURES FOR USING THE REAL TIME VOLTAGE STABILITY APPLICATION (RTVSA) Supercedes 7T-50 dated 02 May

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

Reliability Coordinator Procedure

Reliability Coordinator Procedure No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...

More information

Standards Authorization Request Justification

Standards Authorization Request Justification Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

Warrenton Wheeler Gainesville 230kV Reliability Project

Warrenton Wheeler Gainesville 230kV Reliability Project Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.:

City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM. RFI No.: City of Farmington Farmington Electric Utility System REQUEST FOR INFORMATION AUTOMATED CALL-OUT SYSTEM Closing Date: July 17, 2018 at 2:00 p.m. RFI No.: 19-127502 Description: The City of Farmington Electric

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Powering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director

Powering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director Powering the North West s Future: From DNO to DSO Paul Bircham Commercial Strategy & Support Director 1 Introducing Electricity North West 5 million 2.4 million (45% of demand) 20,000 I&C (55% of demand)

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

SRP Ten Year Transmission Plan

SRP Ten Year Transmission Plan 2018 SRP Ten Year Transmission Plan 2018-2027 Prepared for the Arizona Corporation Commission January 2018 Docket No. E-00000D-17-0001 Page1 Page1 Table of Contents 1. Introduction... 1 2. Planning Organizations...

More information

Geomagnetic Disturbances

Geomagnetic Disturbances Geomagnetic Disturbances Managing Risk to the North American Power Grid Mark Olson, Reliability Standards Developer Worcester Polytechnic Institute Energy Symposium September 25, 2013 About NERC The North

More information

Electric Transmission Reliability

Electric Transmission Reliability 1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013 Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently

More information

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way California Independent System Operator October 30, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N

B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N B O N N E V I L L E A D M I N I S T R A T I O N B O N N E V I L L E P O W E R A D M I N I S T R A T I O N NERC Monitoring and Situational Awareness Conference Bonneville Power Administration Self-Monitoring:

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach

Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach Manitoba Hydro TSR Facility Study Meeting CapX Transmission Owners Proposal/Study Approach How should the CapX TO s approach the response to the MISO Request For Proposal for the MH TSR Facility Study?

More information

City of Grand Island Tuesday, February 28, 2017 Council Session

City of Grand Island Tuesday, February 28, 2017 Council Session City of Grand Island Tuesday, February 28, 2017 Council Session Item G-6 #2017-50 - Approving Transmission Services Agreement with Nebraska Public Power District Staff Contact: Tim Luchsinger, Stacy Nonhof

More information

Getting Effective Transmission Built on the SPP-MISO Seam. MISO-SPP IPSAC Meeting March 2016

Getting Effective Transmission Built on the SPP-MISO Seam. MISO-SPP IPSAC Meeting March 2016 Getting Effective Transmission Built on the SPP-MISO Seam MISO-SPP IPSAC Meeting March 2016 1 General Information MISO and SPP have roughly over 60 interconnections most at lower voltage (less than 345kV).

More information

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (

More information

136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ]

136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ] 136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Parts 39.10 and 40 [Docket No. RM11-16-000] Transmission Relay Loadability Reliability Standard (September 15, 2011)

More information

edart Quick Reference Guide

edart Quick Reference Guide edart Quick Reference Guide Revision: 05 Effective Date: 08/16/2017 PJM 2017 Prepared by edart Project Team Table of Contents Table of Contents... 2 Revision History... 6 About the Quick Reference Guide...

More information

Chapter X Security Performance Metrics

Chapter X Security Performance Metrics DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Real-time Power System Operation. Energy Management Systems. Introduction

Real-time Power System Operation. Energy Management Systems. Introduction 1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern

More information

Building a Topology Estimator for Large Inter-regional Networks

Building a Topology Estimator for Large Inter-regional Networks Building a Topology Estimator for Large Inter-regional Networks ETREP02.pdf Robin Podmore *, Margaret Goodrich**, David Becker***, Peter Hirsch***, Stephen Lee ***, Marck Robinson**** robin@incsys.com,

More information

Tri-State Generation & Transmission Association, Inc.

Tri-State Generation & Transmission Association, Inc. Tri-State Generation & Transmission Association, Inc. Available Transfer Capability Implementation Document (ATCID) Determination and Posting of Total Transfer Capability (TTC) and Available Transfer Capability

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

WECC Path Concept White Paper

WECC Path Concept White Paper Document name Category WECC Path Concept White Paper ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Regional Business Practice ( ) Policy ( ) Guideline (X) Report or other ( ) Charter Document

More information

Tri-State Generation & Transmission Association, Inc.

Tri-State Generation & Transmission Association, Inc. Tri-State Generation & Transmission Association, Inc. Available Transfer Capability Implementation Document (ATCID) Determination and Posting of Total Transfer Capability (TTC) and Available Transfer Capability

More information

2012 Grid of the Future Symposium. Demonstration of Pulsecloser Applications and Benefits in Ameren s Distribution Automation Program

2012 Grid of the Future Symposium. Demonstration of Pulsecloser Applications and Benefits in Ameren s Distribution Automation Program 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Demonstration of Pulsecloser Applications and Benefits in Ameren s Distribution Automation

More information