1 HOW TO USE THIS TEMPLATE: Introduction The template reflects the steps set out in the PRINCE2 Method and is designed to prompt the Project Manager and help in the creation of the. The information for the will be found within the IP and SB Processes of the PRINCE2 Manual. There is also a Product Description for the at Appendix A of the PRINCE2 Manual. Loading the file This template has been produced using Microsoft Word 97. To use it, load up the file directly from the directory and starting from page 1 follow the prompts (in [...] brackets). Deleting the [...] text When the template is complete, the whole document can be printed and approved. Prior to printing, you should delete all [...] prompt text. Saving the document under its own name Save the document by selecting the SAVE AS command; this will avoid overwriting the standard template. You must specify your own Project Directory. Once your Document is completed check the document against the following Quality Criteria: Is the plan achievable? Does it support the rest of the Project Initiation Document?

2 PROJECT DOCUMENTATION PROJECT PLAN Project: Release: Date: PRINCE2 Author: Owner: Client:

3 Document Ref: Version No: Page 2

4 1 History 1.1 Document Location This document is only valid on the day it was printed. The source of the document will be found on the project's PC in location 1.2 Revision History Date of this revision: Date of Next revision: Revision date Previous revision date Summary of Changes First issue Changes marked 1.3 Approvals This document requires the following approvals. Signed approval forms are filed in the Management section of the project files. Name Signature Title Date of Issue Version 1.4 Distribution This document has been distributed to: Name Title Date of Issue Version Page 3

5 2 Table of Contents Page 1 History Document Location Revision History 1.3 Approvals 1.4 Distribution 2 Table of Contents 3 Purpose 4 Plan Description 5 Prerequisites 6 External Dependencies 7 Planning Assumptions Gantt or Bar Chart 8.2 Product Breakdown Structure 8.3 Product Flow Diagrams 8.4 Product Descriptions 8.5 Activity Network 8.6 Financial Budget 8.7 Change Budget 8.8 Resource Requirements 8.9 Specific Resources 8.10 Tolerance 8.11 Contingency Plans Page 4

6 3 Purpose [The is a mandatory plan that provides a statement of how and when a project s objectives are to be achieved, by showing the major products, activities and resources required on the project. It provides the Business Case with planned project costs and it identifies the management stages and other major control points It is used by the Project Board as a baseline against which to monitor project progress and cost, stage by stage] 4 Plan Description [A brief description of what the plan covers] 5 Prerequisites [Describe any fundamental aspects which must be in place at the start of the project and which must remain in place for the project to succeed] 6 Dependencies [A description of any external factors, products or processes that the progress and success of the project depends on] 7 Assumptions [Refer to Project Initiation Document (PID). List any assumptions being made that will affect the projects progress or success] Gantt or Bar Chart [with identified management stages] Page 5

7 8.2 Product Breakdown Structure 8.3 Product Flow Diagrams 8.4 Product Descriptions 8.5 Activity Network 8.6 Financial Budget 8.7 Change Budget 8.8 Resource Requirements [Project level table of resource requirements] 8.9 Specific Resources [Requested/assigned specific resources] 8.10 Tolerance [e.g. time and budget] 8.11 Contingency Plans [Explain how it is intended to deal with the consequences of any risks that materialise] Page 6

Saving the Project Brief document under its own name

Saving the Project Brief document under its own name HOW TO USE THIS TEMPLATE: Introduction The template reflects the steps set out in the PRINCE2 Method and is designed to prompt the Project Manager and help in the creation of the. The information for the

More information

When the template is complete, the whole Project Initiation Document can be printed and approved.

When the template is complete, the whole Project Initiation Document can be printed and approved. HOW TO USE THIS TEMPLATE: Introduction The template reflects the steps set out in the PRINCE2 Method and is designed to prompt the Project Manager and help in the creation of the Project Initiation Document

More information

When the template is complete, the whole Lessons Learned Report document can be printed and approved.

When the template is complete, the whole Lessons Learned Report document can be printed and approved. HOW TO USE THIS TEMPLATE: Introduction The template reflects the steps set out in the PRINCE2 Method and is designed to prompt the Project Manager and help in the creation of the Lessons Learned Report.

More information

<PROJECT> WORK BREAKDOWN STRUCTURE

<PROJECT> WORK BREAKDOWN STRUCTURE WORK BREAKDOWN STRUCTURE Version Number: 1.0 Version Date: Notes to the Author [This document is a template of a Work Breakdown Structure document for a project. The template includes

More information

<Project Name> Scope Management Plan. <Author> <Date> Name Date Reason For Changes Version <author> initial draft 1.0 draft1

<Project Name> Scope Management Plan. <Author> <Date> Name Date Reason For Changes Version <author> initial draft 1.0 draft1 Scope Management Plan 1.0 Revision History Name Date Reason For Changes Version initial draft 1.0 draft1 2.0 Statement of Purpose The purpose of this document

More information

<PROJECT NAME> IMPLEMENTATION PLAN

<PROJECT NAME> IMPLEMENTATION PLAN IMPLEMENTATION PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Implementation Plan was controlled and tracked.

More information

On Premise. Service Pack

On Premise. Service Pack On Premise Service Pack 02.0.01 - This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational

More information

On Premise. Service Pack

On Premise. Service Pack On Premise Service Pack 02.0.01 - This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational

More information

AutoCAD/SMARTEAM - DESIGN &PRODUCT LIFE CYCLE MANAGEMENT SOFTWARE. Smarteam User Guide

AutoCAD/SMARTEAM - DESIGN &PRODUCT LIFE CYCLE MANAGEMENT SOFTWARE. Smarteam User Guide AutoCAD/SMARTEAM - DESIGN &PRODUCT LIFE CYCLE MANAGEMENT SOFTWARE Smarteam User Guide 1 Conventions used in Document Text in Bold Indicates a button or option to be selected 2 Contents Connecting to SmarTeam

More information

Communications Management Plan Template

Communications Management Plan Template Communications Management Plan Template Project Name: U.S. Department of Housing and Urban Development October, 2010 Communications Management Plan Template (V1.0) VERSION HISTORY [Provide information

More information

Oracle Project Management Introduction (Family Pack M)

Oracle Project Management Introduction (Family Pack M) Oracle Project Management Introduction (Family Pack M) Page 0 Oracle Project Management Introduction Table of Contents Chapter1: Overview of Oracle Project Management... Error! Bookmark not History of

More information

PK0-003 Q&As. Project+ (2009) Pass CompTIA PK0-003 Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from:

PK0-003 Q&As. Project+ (2009) Pass CompTIA PK0-003 Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from: PK0-003 Q&As Project+ (2009) Pass CompTIA PK0-003 Exam with 100% Guarantee Free Download Real Questions & Answers PDF and VCE file from: 100% Passing Guarantee 100% Money Back Assurance Following Questions

More information

PROJECT INITIATION DOCUMENT

PROJECT INITIATION DOCUMENT PROJECT INITIATION DOCUMENT Project name Email client replacement Release Approved 1.0 Date: 18 May 2006 PRINCE2 Author: Owner: Document Number: John Richards Tim Phillips ICT008-pid-01 Document History

More information

Version 6.5. User Manual Fortes Solutions BV

Version 6.5. User Manual Fortes Solutions BV Version 6.5 User Manual Principal Toolbox User Manual Principal Toolbox 6.5 All rights reserved. No parts of this work may be reproduced in any form or by any means - graphic, electronic, or mechanical,

More information

University Program Office. Clarity - Quick Reference Guide Project and Portfolio Management Tool. Published - 14 September 2017 (Launch Version)

University Program Office. Clarity - Quick Reference Guide Project and Portfolio Management Tool. Published - 14 September 2017 (Launch Version) University Program Office Clarity - Quick Reference Guide Project and Portfolio Management Tool 1 Published - 14 September 2017 (Launch Version) Getting Started with Clarity To access Clarity click the

More information

Version 5.5. User Manual Fortes Solutions BV

Version 5.5. User Manual Fortes Solutions BV Version 5.5 User Manual Principal Toolbox User Manual Principal Toolbox 5.0 All rights reserved. No parts of this work may be reproduced in any form or by any means - graphic, electronic, or mechanical,

More information

Learning objectives. Documenting Analysis and Test. Why Produce Quality Documentation? Major categories of documents

Learning objectives. Documenting Analysis and Test. Why Produce Quality Documentation? Major categories of documents Learning objectives Documenting Analysis and Test Understand the purposes and importance of documentation Identify some key quality documents and their relations Understand the structure and content of

More information

Governing Body 313th Session, Geneva, March 2012

Governing Body 313th Session, Geneva, March 2012 INTERNATIONAL LABOUR OFFICE Governing Body 313th Session, Geneva, 15 30 March 2012 Programme, Financial and Administrative Section PFA FOR INFORMATION Information and communications technology questions

More information

THIS IS AN OBSOLETE COPYRIGHT PAGE. Use Common/Copyright/Copyright

THIS IS AN OBSOLETE COPYRIGHT PAGE. Use Common/Copyright/Copyright Unica Marketing Operations and Unica Campaign Version 8.2.0 Integration Guide Publication Date: September 20, 2010 Copyright THIS IS AN OBSOLETE COPYRIGHT PAGE. Use Common/Copyright/Copyright Table of

More information

<Project Name> Risk List

<Project Name> Risk List Version [Note: The following template is provided for use with the Rational Unified Process. Text enclosed in square brackets and displayed in blue italics (style=infoblue) is included

More information

PRINCE2 Practitioner Course Outline

PRINCE2 Practitioner Course Outline PRINCE2 Practitioner Course Outline 1 PRINCE2 Practitioner Program Overview PRINCE2 provides an easily tailored and scalable method for the management of all types of projects. This method is the de facto

More information

Project 2010 Certification Exams

Project 2010 Certification Exams Project 2010 Certification Exams This information is taken from the Microsoft website and is a compilation of the requirements listed there for the Project 2010 and Project Server 2010 exams. This document

More information

Programme Headlines. Project Headlines. Appendix - Watford 2020 Progress Update Report 8 November 2017

Programme Headlines. Project Headlines. Appendix - Watford 2020 Progress Update Report 8 November 2017 Completed by: Liam Hornsby Period from: 23 October 2017 Date completed: 6 November 2017 Period to: 6 November 2017 Current Programme Status Trend since last report Programme Headlines R R/A A/G G Worse

More information

PRINCE2 FOUNDATION AND PRACTITIONER CERTIFICATION TRAINING COURSE AGENDA

PRINCE2 FOUNDATION AND PRACTITIONER CERTIFICATION TRAINING COURSE AGENDA PRINCE2 FOUNDATION AND PRACTITIONER CERTIFICATION TRAINING COURSE AGENDA This publication has been prepared and written by icert Global and is protected by copyright. Other than for the purposes of and

More information

TEXAS DEPARTMENT OF INFORMATION RESOURCES. Test Scenario. Instructions. Version DEC 2006

TEXAS DEPARTMENT OF INFORMATION RESOURCES. Test Scenario. Instructions. Version DEC 2006 TEXAS DEPARTMENT OF INFORMATION RESOURCES Test Scenario Instructions Version 1.1 8 DEC 2006 Version History Current Framework documents, including a glossary, are available at www.dir.state.tx.us/pubs/framework/.

More information

Project Name System Critical Design Review

Project Name System Critical Design Review Insert project logo Project Name System Critical Design Review Class Number Title Date Location This Critical Design Review assumes that the design team will be following a formalized design process. This

More information

ADDRESS. Tacit Skills N 5 Sturdee Avenue, Suite 301 Rosebank, Johannesburg South Africa 2196 CONTACT US

ADDRESS. Tacit Skills N 5 Sturdee Avenue, Suite 301 Rosebank, Johannesburg South Africa 2196 CONTACT US ADDRESS MICROSOFT PROJECT: MANAGING CONSTRUCTION AND ENGINEERING PROJECTS 3 DAY COURSE This course is Accredited with ECSA / SACPCMP (Registration Number: SAAMA2017272) (Registration Number: SACPCMP/CPD/18/001)

More information

DEPARTMENT OF EDUCATION. LEA Accounting

DEPARTMENT OF EDUCATION. LEA Accounting DEPARTMENT OF EDUCATION LEA ACCOUNTING Contents Revision History... 2 Revision History Chart... 2 Application Permissions... 3 Creating an AIM Account... 4 Create an Account Email Address Entered... 5

More information

Wire Revision List If a wire on the Transaction List needs correcting, it can be sent to the Wire Revision screen and edited.

Wire Revision List If a wire on the Transaction List needs correcting, it can be sent to the Wire Revision screen and edited. Wire Transfers The Wire Transfer service provides secure wire transfer capabilities with a streamlined, easy-to-use web browser interface. The Wire Transfer feature allows you to: Create wires using a

More information

BUDGET ADJUSTMENT FORM INSTRUCTIONS (Revised May 2015)

BUDGET ADJUSTMENT FORM INSTRUCTIONS (Revised May 2015) BUDGET ADJUSTMENT FORM INSTRUCTIONS (Revised May 2015) The Form allows users to enter budget adjustments into the accounting system. The Form can be downloaded from the Financial Services web site under

More information

ECDL / ICDL Project Planning Syllabus Version 1.0

ECDL / ICDL Project Planning Syllabus Version 1.0 ECDL / ICDL Project Planning Syllabus Version 1.0 Purpose This document details the syllabus for ECDL / ICDL Project Planning. The syllabus describes, through learning outcomes, the knowledge and skills

More information

Oracle Primavera P6 Fundementals Courses

Oracle Primavera P6 Fundementals Courses 2018 Oracle Primavera P6 Fundementals Courses Project Management Training Program PMVISION Training PMVISION Training Primavera p6 Fundamentals Course Course Description The Primavera P6 Training Course

More information

ForeScout CounterACT. Track Changes to Network Endpoints. How-to Guide. Version 8.0

ForeScout CounterACT. Track Changes to Network Endpoints. How-to Guide. Version 8.0 ForeScout CounterACT Track Changes to Network Endpoints How-to Guide Version 8.0 Table of Contents About Managing Changes to Network Endpoints... 3 Prerequisites... 3 Create and Apply a Change Policy...

More information

OE-PM Project Charter Document

OE-PM Project Charter Document Enter Project Name Here Enter Department Name OE-PM Project Charter Document Status: (Draft or Published) Version: (0.# or 1.#) Prepared by: Date Created: Date Last Revised: OE-PM Artifact ID: P01.00 Internal

More information

Program and Project Management User Guide

Program and Project Management User Guide IBM TRIRIGA Version 10.3.1 Program and Project Management User Guide Copyright IBM Corp. 2011 i Note Before using this information and the product it supports, read the information in Notices on page 484.

More information

Agency Guide for FedRAMP Authorizations

Agency Guide for FedRAMP Authorizations How to Functionally Reuse an Existing Authorization Version 1.0 August 5, 2015 Revision History Date Version Page(s) Description Author 08/05/2015 1.0 All Initial Publication FedRAMP PMO 06/06/2017 1.0

More information

About the P6 EPPM Importing and Exporting Guide

About the P6 EPPM Importing and Exporting Guide P6 EPPM Importing and Exporting Guide October 2018 Contents About the P6 EPPM Importing and Exporting Guide Scope This guide contains information about import and export formats and the process of importing

More information

Microsoft Project 2007 Level 2. MICROSOFT PROJECT 2007 Level 2

Microsoft Project 2007 Level 2. MICROSOFT PROJECT 2007 Level 2 Contents MICROSOFT PROJECT 2007 Level 2 Contents CONTENTS LESSON 1 - ORGANISING PROJECT DATA... 4 Using the AutoFilter Feature... 5 Filtering Data... 5 Sorting a View... 6 Creating a Custom Sort... 6 Grouping

More information

Employment Ontario Information System (EOIS) Case Management System

Employment Ontario Information System (EOIS) Case Management System Employment Ontario Information System (EOIS) Case Management System Service Provider User Guide Chapter 8B: Service Plan Management for Literacy and Basic Skills Version 2.7 December 2017 Table of Contents

More information

Employment Ontario Information System (EOIS) Case Management System

Employment Ontario Information System (EOIS) Case Management System Employment Ontario Information System (EOIS) Case Management System Service Provider User Guide Chapter 8F2: Service Plan Management for SkillsAdvance Ontario Phase 2 Version 1.0 July 2018 Table of Contents

More information

Work Instruction Study Setup

Work Instruction Study Setup THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO Work Instruction Study Setup Velos - eresearch 10.0 Version: 1.0, 02/16/2018 Revision History Version/Amendment #: Version Date: Description:

More information

COMP 145 UNC-Chapel Hill Contract II PROJECT TITLE. Submitted to. CLIENT NAME and Prof. Greg Welch. Date AUTHOR NAME AUTHOR NAME AUTHOR NAME

COMP 145 UNC-Chapel Hill Contract II PROJECT TITLE. Submitted to. CLIENT NAME and Prof. Greg Welch. Date AUTHOR NAME AUTHOR NAME AUTHOR NAME COMP 145 UNC-Chapel Hill Contract II PROJECT TITLE Submitted to Note CLIENT NAME and Prof. Greg Welch Date Note CLIENT NAME, Client Note PREFACE {LESS THAN 1/2 PAGE} This should let the reader know that

More information

ECDL / ICDL Module 13 - Project Planning Syllabus Version 1.0

ECDL / ICDL Module 13 - Project Planning Syllabus Version 1.0 ECDL / ICDL Module 13 - Project Planning Syllabus Version 1.0 Copyright 2011 ECDL Foundation All rights reserved. No part of this publication may be reproduced in any form except as permitted by ECDL Foundation.

More information

AiM CPPM Capital Project

AiM CPPM Capital Project AiM Navigation icons Budget Manager Date Manager Budget Revision screen is the main source of information on a project. is the central hub to which all other transactions will be associated. How to enter

More information

FISMAand the Risk Management Framework

FISMAand the Risk Management Framework FISMAand the Risk Management Framework The New Practice of Federal Cyber Security Stephen D. Gantz Daniel R. Phi I pott Darren Windham, Technical Editor ^jm* ELSEVIER AMSTERDAM BOSTON HEIDELBERG LONDON

More information

System Requirements Specification

System Requirements Specification System Requirements Specification Template NOTE: Please remove this page when creating a System Requirements Specification deliverable Using This Template The companion tool, System Requirements Specification

More information

A Product of. Structured Solutions Inc.

A Product of. Structured Solutions Inc. SSI Tools Time Scaled Values Analysis Tools Structured Solutions Inc. www.ssitools.com A Product of Structured Solutions Inc. 1 Modify The Columns in the Sheet Named Template SSI Status Workbook Template

More information

Project Management OOTB Introduction. Your Guide: Sara Garvey

Project Management OOTB Introduction. Your Guide: Sara Garvey Project Management OOTB Introduction Your Guide: Sara Garvey Introductions 2 Take 5 Minutes Turn to a Person Near You Introduce Yourself Business Cards Agenda Introduction Managing Projects Staffing Projects

More information

Work Break Down Structure Template

Work Break Down Structure Template WORK BREAKDOWN STRUCTURE (WBS) TEMPLATE This Project WBS Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome your

More information

LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE. Loughborough University (LU) Research Office SOP 1027 LU

LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE. Loughborough University (LU) Research Office SOP 1027 LU LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE Loughborough University (LU) Research Office SOP 1027 LU Process for Writing Study Protocols for NHS Research Sponsored by Loughborough

More information

CompTIA Project+ (2009 Edition) Certification Examination Objectives

CompTIA Project+ (2009 Edition) Certification Examination Objectives CompTIA Project+ (2009 Edition) Certification Examination Objectives DRAFT INTRODUCTION The Project + examination is designed for business professionals involved with projects. This exam will certify that

More information

Foundation for the Philippine Environment: Grants Online-Management Information System User's Manual for Project Proponents

Foundation for the Philippine Environment: Grants Online-Management Information System User's Manual for Project Proponents 77 Matahimik St., Teacher's Village Diliman, Quezon City Tel: +63 (2) 9272186 / 9269629 / 9279403 Fax: +63 (2) 9223022 www.fpe.ph Foundation for the Philippine Environment: User's Manual for Project Proponents

More information

Software Documentation

Software Documentation Software Documentation Quiz with Explainations Hans-Petter Halvorsen, M.Sc. Questions 1. List 4 important Process Documents 2. What are the main Software Documentation Categories? 3. What is SRS? 4. What

More information

DEPARTMENT OF EDUCATION

DEPARTMENT OF EDUCATION DEPARTMENT OF EDUCATION RESEARCH AND DEVELOPMENT Contents Revision History... 3 Revision History Chart... 3 Overview... 4 Application Permissions... 4 1. How do I get started?... 5 System Selection...

More information

Core Staff Review Approve with Contingencies

Core Staff Review Approve with Contingencies Core Staff Review Approve with Contingencies Important Information In the event a submission is Approved with Contingencies, extra steps are required to complete the approval process. The basic steps to

More information

Learn how to login to Sitefinity and what possible errors you can get if you do not have proper permissions.

Learn how to login to Sitefinity and what possible errors you can get if you do not have proper permissions. USER GUIDE This guide is intended for users of all levels of expertise. The guide describes in detail Sitefinity user interface - from logging to completing a project. Use it to learn how to create pages

More information

Purpose Use this to Register with DE through the Supplier Portal (Directenergy.supplier.ariba.com/register)

Purpose Use this to Register with DE through the Supplier Portal (Directenergy.supplier.ariba.com/register) Purpose Use this to Register with DE through the Supplier Portal (Directenergysupplieraribacom/register) Helpful Hints Ariba offers Supplier Support 24/7, the phone number for the US is 1-866-218-255 For

More information

User Guide. Document Last Updated June 30, Financial Training Department 1

User Guide. Document Last Updated June 30, Financial Training Department 1 User Guide Document Last Updated June 30, 2016. Financial Training Department 1 Table of Contents Objectives... 3 Overview of BEN... 4 What Information is Included in a Deposit?... 6 Logging on to BEN

More information

EDMtruePLM True Product Lifecycle Management User s Guide for Version 2.2

EDMtruePLM True Product Lifecycle Management User s Guide for Version 2.2 EDMtruePLM True Product Lifecycle Management User s Guide for Version 2.2 Proprietary notice Information in this publication is subject to change without notice. No part of this publication may be distributed

More information

Web Travel Groups and Routes in the FRED System

Web Travel Groups and Routes in the FRED System Web Travel Groups and Routes in the FRED System Purpose: To set up groups and routes that will be used for Web Travel in the FRED system. Security Access Requirement: You must be setup as a Route Administrator

More information

RFP/RFQ GOODS STANDARDIZATION UPDATE NOVEMBER 2013

RFP/RFQ GOODS STANDARDIZATION UPDATE NOVEMBER 2013 RFP/RFQ GOODS STANDARDIZATION UPDATE NOVEMBER 2013 1 Agenda Sourcing Technology Phase 2 Current RFP Template RFP Goods Template Changes Steps for Creating an RFP/RFQ Goods Event New RFP/RFQ Goods Template

More information

User Manual. Declaration Creation, Submission and Approvals for ERDF For Beneficiary, Approver Beneficiary and Intermediary Body users. Version 0.

User Manual. Declaration Creation, Submission and Approvals for ERDF For Beneficiary, Approver Beneficiary and Intermediary Body users. Version 0. User Manual Declaration Creation, Submission and Approvals for ERDF For Beneficiary, Approver Beneficiary and Intermediary Body users. Version 0.3 Document Version Control Version Amendment Author Date

More information

Workflow Templates in Compliance 360 Version 2018

Workflow Templates in Compliance 360 Version 2018 Workflow Templates in Compliance 360 Version 2018 Workflow Templates 5 Workflow Elements 6 Workflow Teams 6 Workflow Template Changes 6 Create or Edit a Workflow Template 8 Import and Export Workflow Templates

More information

<Project Name> Configuration Management/Data Management Plan

<Project Name> Configuration Management/Data Management Plan [TYPE THE COMPANY NAME] Configuration Management/Data Management Plan Written By: Approved By: 4/28/2011 [Type the abstract of the document here. The abstract is typically a short summary

More information

Georgia State University Spectrum System

Georgia State University Spectrum System Voucher Creation Interface Process Name : APVLGSU Technical Approval: Functional Approval: All Issues Resolved: Date: Date: Date: Designer: Developer: Rosalyn Harvey Date: Revised 7/31/2006 Comments on

More information

MISO Transmission Planning BPM 020 Updates February 16, 2016

MISO Transmission Planning BPM 020 Updates February 16, 2016 MISO Transmission Planning BPM 020 Updates February 16, 2016 Purpose Present final updated BPM 20 language Objectives for Today Purpose and Objectives Briefly discuss posted stakeholder comments and MISO

More information

From the main page click on I Need Something

From the main page click on I Need Something Title of Knowledge Base Article New Computer Request process Brief description or summary of the document Steps to acquire a computer for a new employee or existing employee Contents Prerequisites o Must

More information

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Maintenance Executive Project Statusing Class Conducted by Evans Technology October 2005 Project Initiation and Revision Training Manual Table of Contents Introduction

More information

Work Instruction Study Startup

Work Instruction Study Startup THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO Work Instruction Study Startup Velos - eresearch 9.2 Version: 2.0, 04/29/2015 Version 2.0, 04/29/2015 Revision History Version/Amendment #:

More information

CERTIFICATION ENTITY DOCUMENTS LIST OID s Structure Version control

CERTIFICATION ENTITY DOCUMENTS LIST OID s Structure Version control CERTIFICATION ENTITY DOCUMENTS LIST OID s Version control This specification has been prepared by ANF AC to release to third parties. SECURITY LEVEL PUBLIC DOCUMENT This document is the property of ANF

More information

Project Templates Guidance

Project Templates Guidance This is an official Northern Trust policy and should not be edited in any way Reference Number: NHSCT/11/389 Target audience: The Project Template Guidance applies to all staff using ISPO Project Templates.

More information

Configuring Job Monitoring in SAP Solution Manager 7.2

Configuring Job Monitoring in SAP Solution Manager 7.2 How-To Guide SAP Solution Manager Document Version: 1.0 2017-05-31 Configuring Job Monitoring in SAP Solution Manager 7.2 Typographic Conventions Type Style Example Example EXAMPLE Example Example

More information

PRINCE2 Foundation Certification Exam Training - Brochure

PRINCE2 Foundation Certification Exam Training - Brochure PRINCE2 Foundation Certification Exam Training - Brochure The Skill-set and Certification that Empowers your Project Management Career Course Name : PRINCE2_FOUNDATION Version : INVL_PRINCE2F_BR_02_011_1.2

More information

Oracle Financial Services Behavior Detection Platform: Administration Tools User Guide. Release May 2012

Oracle Financial Services Behavior Detection Platform: Administration Tools User Guide. Release May 2012 Oracle Financial Services Behavior Detection Platform: Administration Tools User Guide Release 6.1.1 May 2012 Oracle Financial Services Behavior Detection Platform: Administration Tools User Guide Release

More information

Enterprise Information Systems

Enterprise Information Systems Enterprise Information Systems Financial Management + Human Resources + Student Administration Posting Charges in Groups Business Process Guide August, 2004 Updates Date Action Page(s) 8/01/2004 Created.

More information

SmartPlant Foundation 4.x Introduction and Administration I

SmartPlant Foundation 4.x Introduction and Administration I Table of Contents Table of Contents - 2 SmartPlant Foundation 4.x Introduction and Administration I SmartPlant Foundation 4.x Introduction and Administration I Table of Contents - 3 1. SmartPlant Architecture

More information

Chart of Accounts (COA) Maintenance Request Form Instructions

Chart of Accounts (COA) Maintenance Request Form Instructions The purpose of the Chart of Accounts Maintenance Request form is to request changes or additions to your financial accounting information. Allow 48 hours after receiving all pertinent information to complete

More information

Employment Ontario Information System (EOIS) Case Management System Service Provider User Guide

Employment Ontario Information System (EOIS) Case Management System Service Provider User Guide Employment Ontario Information System (EOIS) Case Management System Service Provider User Guide Chapter 8C: Service Plan Management for the Canada- Ontario Job Grant Version 2.1July 2018 Table of Contents

More information

Oracle Financial Services Compliance Regulatory Reporting India Suspicious Transaction Report User Guide. Release

Oracle Financial Services Compliance Regulatory Reporting India Suspicious Transaction Report User Guide. Release Oracle Financial Services Compliance Regulatory Reporting India Suspicious Transaction Report User Guide Release 8.0.6.0.0 May 2018 Oracle Financial Services Compliance Regulatory Reporting India Suspicious

More information

ATTENTION TO COME/ISE 491/492 STUDENT

ATTENTION TO COME/ISE 491/492 STUDENT ATTENTION TO COME/ISE 491/492 STUDENT 151 As a part of your requirement analysis section in your final report, you should write a requirement analysis document (RAD). The details of the document, and a

More information

Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite Implementation Guide

Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite Implementation Guide Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 3.1 - Implementation Guide Release 3.1 Part No. E20507-03 September 2011 Oracle Project Portfolio Management

More information

Trade Finance Mar 2018

Trade Finance Mar 2018 Mar 2018 Table of Contents Documentary Credits... 3 Initiate LC...4 Approvals...7 Query LC Requests... 10 Amend LC... 13 Bank Guarantees... 16 Initiate BG... 17 Approval... 19 Query BG Requests... 21 Amend

More information

Submitting an After Action Report

Submitting an After Action Report Submitting an After Action Report User Guide Version 1.6 March 9, 2018 Strong Bonds Table of Contents About This Guide... 3 The Event Management Lifecycle... 3 Submitting an After Action Report... 3 Who

More information

CA Clarity Project & Portfolio Manager

CA Clarity Project & Portfolio Manager CA Clarity Project & Portfolio Manager CA Clarity PPM Connector for Microsoft SharePoint Product Guide v1.1.0 Second Edition This documentation and any related computer software help programs (hereinafter

More information

Project & Portfolio Management Software

Project & Portfolio Management Software Project & Portfolio Management Software Roles How to create and edit a project: General details Resources Expense Types Time Types How to create/edit a project components The plan (the list of tasks and

More information

Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite Implementation Guide

Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite Implementation Guide Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 2.5 - Implementation Guide Release 2.5 Part No. E15794-01 October 2009 Oracle Project Portfolio Management

More information

Access Office Integration for Excel

Access Office Integration for Excel Access Office Integration for Excel Introduction The following document has been designed to guide you through the process of downloading Dimensions data in to Excel via the Access Office Integration tool.

More information

Work Instruction Patient Visits

Work Instruction Patient Visits THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO Work Instruction Patient Visits Velos - eresearch v10.0 Version: 1.0, 02/16/2018 Revision History Version/Amendment #: Version Date: Description:

More information

National Smart Metering Program Testing Framework Work Stream Actions Log

National Smart Metering Program Testing Framework Work Stream Actions Log - ustomer section of the table Description / Progress Source/Origin Workstream/ owner Who By When Status Reporting 20090923 4 TFWG need to feed into the BPPWG the issues about service levels and performance

More information

Title of the Senior Engineering Design Project Report Template

Title of the Senior Engineering Design Project Report Template Çankaya University Department of Electrical and Electronics Engineering Title of the Senior Engineering Design Project Report Template in LATEX EE 407 Innovative Engineering Analysis and Design Project

More information

Financial Manager Change Request

Financial Manager Change Request The Financial Manager Change Request section of the Finance New FOP system replaces the current emailed requests to Finance Systems Management and the Budget Office. The Financial Manager Change Request

More information

PolicyTech. University of Memphis Policy Review Board User Guide for Management of System-wide Policies and Procedures. PolicyTech User Guide

PolicyTech. University of Memphis Policy Review Board User Guide for Management of System-wide Policies and Procedures. PolicyTech User Guide PolicyTech University of Memphis Policy Review Board User Guide for Management of System-wide Policies and Procedures Page 1 of 18 Table of Contents Getting Started... 3 How to Access PolicyTech... 3 PolicyTech

More information

Lab 4-2 Create an Activity Diagram

Lab 4-2 Create an Activity Diagram Create an Activity Diagram Lab 4-2 Create an Activity Diagram Before You Begin In this lab, you ll practice creating an activity diagram that shows the workflow for a use case s basic flow. We will model

More information

Electronic Application of Survivor(s)

Electronic Application of Survivor(s) This document explains how to create and assign an electronic Application of Survivor (s) for Law Firm users that have signed E-Submission agreements with Service New Brunswick. Please refer to the tutorial

More information

The CRISP-DM Process Model

The CRISP-DM Process Model CRISP-DM Discussion Paper March, 1999 The CRISP-DM Process Model Pete Chapman (NCR) Julian Clinton (SPSS) Thomas Khabaza (SPSS) Thomas Reinartz (DaimlerChrysler) Rüdiger Wirth (DaimlerChrysler) This discussion

More information

College of San Mateo Course Outline

College of San Mateo Course Outline College of San Mateo Course Outline New Course Update/No change Course Revision (Minor) Course Revision (Major) Date: 1/26/12 Department: CIS Number: 420 Course Title: Project Management Professional Certificate

More information

How to create Indicators set (ERDF/CF, ESF) and Annual/Final Implementation Report (ERDF/CF, ESF, EFF)?

How to create Indicators set (ERDF/CF, ESF) and Annual/Final Implementation Report (ERDF/CF, ESF, EFF)? and Annual/Final Implementation Report (ERDF/CF, ESF, EFF)? Contents of this guide PURPOSE OF THESE FUNCTIONALITIES...3 REGULATION SOURCE...3 CONCERNED FUNDS...3 USER ROLES AND PERMISSION NEEDED...3 BEFORE

More information

Administration Tools User Guide. Release April 2015

Administration Tools User Guide. Release April 2015 Administration Tools User Guide Release 6.2.5 April 2015 Administration Tools User Guide Release 6.2.5 April 2015 Part Number: E62969_05 Oracle Financial Services Software, Inc. 1900 Oracle Way Reston,

More information

Administering Windows Server Contact Hours

Administering Windows Server Contact Hours Administering Windows Server 2012 36 Contact Hours Course Overview This version of this course 20411A utilizes pre-release software in the virtual machines for the labs. The course is part two of a series

More information

Quick guide to the SmartSimple on-line portal (making an application)

Quick guide to the SmartSimple on-line portal (making an application) EPA Research Programme 2014-2020 Quick guide to the SmartSimple on-line portal (making an application) POWERED BY SMARTSIMPLE Disclaimer Please read this document carefully prior to using the on-line portal.

More information