Probabilistic Cost Analysis for the High Speed Rail between Porto and Lisbon. Alignments A & B close to Leira.

Size: px
Start display at page:

Download "Probabilistic Cost Analysis for the High Speed Rail between Porto and Lisbon. Alignments A & B close to Leira."

Transcription

1 Probabilistic Cost Analysis for the High Speed Rail between Porto and Lisbon. by Y. Moret, R. L. Sousa and H. H. Einstein February 2008

2 1. Introduction The aim of this report is to present the progress on the cost analysis of the Porto-Lisbon high speed rail line for the two 50km long alignments close to the city of Leira. In the previous work we estimated the total cost of two different alignments and compared them with the cost estimation of RAVE. The approach was deterministic, i.e. no uncertainties in the geology and the construction method were included. The main conclusion from the previous work was to extend the work by including the uncertainties on the costs of the construction method. The results of this step are presented in the report. In the first part of this report, a brief introduction to the DAT structure, the background information on the project and the results from the previous work are presented. Then, the assumptions made to simulate probabilistically the total costs are explained and the results shown. Finally, next steps are suggested. 2. The DAT in brief Geology Input / Module Normally along the tunnel (or alignment) the geology is subdivided into Areas and Zones. An Area is a set of continuous and sequential regions that may consist of only one Zone or many Zones. The term "Zone" is used to express what can be described as a geologically homogeneous Zone, namely, a stretch of ground in which a particular set of parameters and parameter states may occur. Construction Simulation / Input The Construction Simulation simulates the construction process through the generated profiles. This involves relating the different geologic conditions (Ground Classes) to the construction methods (Construction Classes) through an interface that allows one to convert Ground Classes into Construction Classes, taking into account the excavation method chosen. Construction Classes define tunnel cross sections (or other structures), as well as the excavation method that best suits a particular Ground Class. This information and the relationship between construction methods, costs and advance rates must be prescribed by the user. 2/20

3 Figure 1 shows an example the relationships between Geologies, Geometries and Methods for a network of a tunnel. Figure 1 Relationships between Geologies, Geometries and Methods [1] The simulation of the construction process is based on the Monte Carlo method (probabilistic case). Each possible generated profile is simulated and related to a corresponding constructive sequence, which is simulated by the Construction Simulation, through that profile producing a total cost and a total time. This process is repeated for the many probabilistic profiles, producing at the end a Time-Cost scattergram. Figure 2 illustrates this process. 3/20

4 Figure 2 DAT Schema [2] In the present analysis for RAVE only cost uncertainties were considered, and therefore the final result consists of points aligned vertically on the t=0 line, instead of the typical scattergram presented in Figure Background information on the project Initially (July 2007), the total costs of the 50km section close to the city of Leira were estimated deterministically using the program DAT [3]. This was followed by a probabilistic evaluation of costs with the DAT, which is reported here. In order to produce a cost estimate in the DAT the following input data are necessary: areas, zones, ground parameter sets, ground classes, geometries, methods and the network. Since the only new information available is the minimum, mean and maximum costs, the input data have not been changed from the previous work with exception of the cost distributions. The input data are summarized in the next paragraphs. For more details we refer to the previous report [3]. 4/20

5 Areas Alignment A was divided into 6 areas, whereas alignment B was divided into 5 areas. These areas correspond to the different sections of the RAVE project (see Table 1 and 2). Table 1 Alignment A Area Section Length ST. ST Table 2 Alignment B Area Section Length ST. ST Zones and ground parameter sets Each area was divided into zones, which are defined by assigning a ground parameter set. A ground parameter set is defined by a combination of ground parameters. Each ground parameter has its own state. Ground classes Ground classes describe the ground conditions along the alignments and are a particular combination of ground parameter states. Ground classes are used to determine the construction method used. 5/20

6 Geometries After defining the ground classes it is necessary to define the geometries, which will then lead to the methods. Each area has a different geometry for viaduct, normal and special embankment, cut or tunnel. The reason is that the costs provided by RAVE are in euro/m 2 (for viaducts) and euro/m 3 (for the embankments and cuts). In order to be used in the DAT, these costs were then transformed into linear costs. This was done by dividing the total cost of each type of structure by their total length (in a particular area). Thus each area has a different linear cost for the different structures. More details can be found in report [3]. Methods Once the geometries have been defined it is necessary to define the methods that will then be related to the geometries and the ground classes. Table 3 presents the (possible) different methods and their description. Table 3 Possible methods Method Nor-Embank Spe-Embank Cut-A Cut-B Cut-C Cut-D Tunnel-Type1 Tunnel-Type2 Tunnel-Type3 Viaduct Nor-Embank-a Nor-Embank-A Spe-Embank-a Spe-Embank-A Description Normal Embankment construction method. Special Embankment construction method. Cutting construction method A Cutting construction method B Cutting construction method C Cutting construction method D Tunnel section type 1 construction method Tunnel section type 2 construction method Tunnel section type 3 construction method Viaduct construction method Normal Embankment construction method with replacement of soil (alluvium) Normal Embankment construction method with replacement of soil (terra rossa) Special Embankment construction method with replacement of soil (alluvium) Special Embankment construction method with replacement of soil (terra rossa) 6/20

7 Network The tunnel network for the simulation is normally constructed considering the construction sequence, project layout and different geometries (cut, normal embankment, special embankment, viaduct and tunnel). In this initial phase we have considered that the construction will start in area 1 and will progress linearly until the end of the alignment (area 6 in alignment A, area 5 in alignment B). This does not correspond to reality but since we are doing a cost analysis and not considering the time of construction this will not constitute a problem. For the future we will have to consider the different planning and sequencing of construction. Deterministic results The results obtained in the deterministic simulation for both alignments are presented in Table 4. See report [3] for more details on this simulation. Table 4 DAT simulation and RAVE results Alignment Cost - DAT simulation (euro) Cost RAVE (euro) A 265,245, ,245,719 B 446,018, ,018, Probabilistic estimation of costs 4.1. Comparison of previous [4] and new [5] data sources on costs In the previous work, based on information from [4], we transformed the total costs of a structure, e.g. a cut, into linear costs by dividing the total cost by the structure length. Thus a cut in an area has a different linear cost from a cut in another area. As explained previously, this was necessary because the DAT work with cost per linear meter. Costs of structures like the superior passages were introduced in the DAT as fixed costs. As an example, the cost for cleaning and for a superior passage (in section 2.1.3, alignment A) are given in Table 5. For the probabilistic estimation the new source of information [5] provides minimum, mean and maximum costs of single activities, e.g. cleaning, and of structures, e.g. 7/20

8 superior passages. These new data relate to the entire alignment Lisbon Porto and are given in cost per cubic meter in the case of cleaning, and in cost per square meter in the case of the superior passages. The minimum, mean and maximum cost from [5] for cleaning and for a superior passage in the Lisbon Porto alignment are given in Table 5. A comparison between the data from the two sources in Table 5 shows that the value used for the deterministic analysis (from previous source [4]) does not coincide with the mean value from the new source. The differences in values between the previous [4] and the new [5] source occur also for other cost items. Therefore, a direct comparison of the two sources of data is not possible. As the previous source [4] does not give any information on cost distribution, the two data sources needed to be related in order to 1) run a probabilistic analysis and 2) compare the results from the deterministic and the probabilistic analyses. How the data sources are related is explained in the next paragraph. Table 5 Cost data used in the deterministic analysis (from previous data source [4]) and cost data from new data source [5] used in the deterministic analysis (from [4]) New data source [5] unit - unit mínimo médio máximo Earthwork: cleaning cost/m cost/m Superior passage cost/m cost/m Derivation of minimum and maximum values In order to relate the data from the two sources and obtain results which could be compared to the results from the deterministic analysis, we first calculated the percentage increase from the mean to the maximum value, and the percentage decrease from the mean to the minimum value of the cost from the new data source [5]. Then, we multiplied these percentages with the cost from the previous source [4] in order to have estimates of the minimum and maximum cost to input in the DAT. A more detailed example of this calculation procedure is presented below. The minimum, mean, maximum cost per cubic meter for cleaning, and the cost per square meter of a superior passage are given in Table 6. These data are available from the new source [5]. 8/20

9 Table 6 Cost data from the new information source [5] unit minimum mean maximum Earthwork: cleaning cost/m Superior passage cost/m The values from Table 6 were used to calculate the percentage decrease from the mean to minimum value, and the percentage increase from the mean to the maximum value. These percentages are reported in Table 7. In the case of cleaning the minimum cost is 0.30 euro/m 3, which corresponds to a decrease of 40% from the mean value of 0.50 euro/m 3. The maximum cost is 1.0 euro/ m 3, which corresponds to an increase of 100% from the mean value. Table 7 Example of calculate percentage using the new information source [5] unit minimum mean maximum Earthwork: cleaning cost/m % % 1.0 Superior passage cost/m % % 750 These percentage values were used to calculate the increase in cost of activities and structures currently used in the DAT. The costs of cleaning and of a superior passage, from the previous data source [4] and currently used in the DAT, are given in Table 8 for section of alignment A. Table 8 Cost data from the previous information source [4] unit cost Earthwork: cleaning cost/m Superior passage cost/m The percentages calculated in Table 7 were applied to the cost data in Table 8. For example, the minimum cost of cleaning is the mean cost of 0.70 euro/m 3 decreased by 40%, resulting in 0.42 euro/m 3 (see Table 9). 9/20

10 Table 9 Example of calculated minimum and maximum costs to input in the DAT unit minimum mean maximum Earthwork: cleaning cost/m % % 1.40 Superior passage cost/m % % 625 The calculation procedure explained above has been carried out for all activities and structures in all sections of both Alignments A and B. The construction of an embankment requires more than one activity, namely removing, cleaning, constructing the embankment, and placing the ballast layer. The minimum, mean and maximum costs of these activities were summed up to give the minimum, mean and maximum cost for the construction of the embankment. This same procedure was followed to calculate the minimum, mean and maximum value for the cuts, the tunnels and the viaducts. The values were then input in the DAT. Table 10 summarizes the values for section for normal and special embankments; cuts A/B/C and D; tunnel types 2 and 3; viaduct; inferior (PI) and superior (PS) passages Probability distribution of costs Minimum, mean and maximum values for all the constructions methods and structures were used to calculate the variation in total cost of alignments A and B. This is done with probability distributions. 10/20

11 Table 10 Minimum, mean and maximum cost in section Nor-Embank Cost Variables (cost/m) Activities min mean max Remove Clean Embankment Ballast Nor-Embank Spe-Embank Cost Variables (cost/m) Activities min mean max Remove Clean Embankment Ballast Spe-Embank Cut-A/B/C Cost Variables (cost/m) Activities min mean max Cut-A Ballast Cut-A/B/C Cut-D Cost Variables (cost/m) Activities min mean max Cut-D Ballast Cut-D Tunnel-Type2 Cost Variables (cost/m) Activities min mean max Exca-support Drain-waterproof-lining Equip-security TA Tunnel-Type Tunnel-Type3 Cost Variables (cost/m) Activities min mean max Exca-support Drain-waterproof-lining Equip-security TA Tunnel-Type Viaduct Cost Variables (cost/m) Activities min mean max Viaduct PI - Small viaduct Cost Variables (cost) Activities min mean max PI - Small viaduct PS - Small viaduct Cost Variables (cost) Activities min mean max PS - Small viaduct /20

12 SimJava works with three distributions: uniform, triangular and bounded triangular [1]. In the case of the uniform distribution, the variable has the same probability of taking on any value between the minimum and maximum value (see Figure 3 (a)). For the triangular distribution, a minimum value, a most likely value, called mode, and a maximum value need to be provided (see Figure 3 (b)). The area under the triangle must sum up to the total probability of one. In the case of the bounded triangular distribution, probabilities greater than zero can be attributed to the minimum and maximum boundaries of the triangle. These probabilities are shown in Figure 3 (c) in form of spikes at the outer apices of the triangle. The area of the minimum value, the maximum value and the area under the triangle must sum up to the total probability of one. For the probabilistic analysis of alignments A and B we worked with the triangular distribution. The required input is the minimum, mode and maximum value. Given the minimum, the mean and the maximum value, the mode can easily be calculated. If the minimum, mean and maximum values could not be fitted into a triangular distribution, the bounded triangular distribution was used. The mode and the bounds were calculated for all cost variables in both alignments A and B. The minimum, the mean, the maximum, the mode and the bounds of the cost variables in section of alignment A are listed in Table 11. Table 11 Minimum, mode, mean and maximum cost values of section 2.1.3, alignment A min. bound Cost Variables minimum mode mean maximum max. bound Nor-Embank , , Spe-Embank , , , , Cut-A/B/C , , , , Cut-D , , , , Tunnel-Type , , , , Tunnel-Type , , , , Viaduct , , , , PI - Small viaduct , , , , PS - Small viaduct , , , , /20

13 (a) (b) (c) Figure 3 Uniform (a), triangular (b) and bounded triangular (c) distributions 13/20

14 4.4. Simulation results One thousand simulations were run for each alignment. In every simulation for every cost variable a value between the minimum and maximum is picked according to the probability distribution. Therefore every simulation provides a different total cost. The results of the simulations are shown in Figure 4 for alignment A and in Figure 5 for alignment B. For alignment A the mean total cost is approximately million with a standard deviation of 6.7 million, whereas for alignment B the mean value is approximately million with a standard deviation of 10.3 million. In Table 12 the mean values are compared with the deterministic value and the total costs provided by RAVE. Table 12 - Comparison of total costs Total costs (euro) Alignment RAVE Deterministic simulation Probabilistic simulation (mean value) A 265,245, ,245, ,312,005 B 446,018, ,018, ,319,193 The differences are small with the mean value from the probabilistic data slightly higher for alignment A and lower for alignment B. 14/20

15 [mio. euro] [of 1,000 simulations] Figure 4 Total cost distribution for alignment A; mean = 265,312,005 euro [mio. euro] [of 1,000 simulations] Figure 5 Total cost distribution for alignment B; mean = 445,319,193 euro 15/20

16 4.5. Alternative probability distribution of costs The new data source [5] reports mínimo, médio, and máximo cost. An example was already given in Table 5. In the analyses so far, we interpreted the médio value, as the statistical mean value. In the report [5] on page 43, thought, the mean is considered equivalent to the mode ( médio ou mais provável). For this reason, we run another set of simulations assuming that all the médio values in report [5] are mode values, rather than statistical mean values. As an example, the minimum, the mode and the maximum values in section of alignment A are listed in Table 13. Table 13 Minimum, mode and maximum cost values of section 2.1.3, alignment A Cost Variables minimum mode (=médio) maximum Nor-Embank , , Spe-Embank , , , Cut-A/B/C , , , Cut-D , , , Tunnel-Type2 24, , , Tunnel-Type3 33, , , Viaduct , , , PI - Small viaduct 137, , , PS - Small viaduct 375, , , A comparison between Table 13 and Table 11 shows that the mode values of Table 13 are equal to the mean values of Table 11. As explained above, in this case we are assuming that the data given in [5] as médio are mode values. Again 1000 simulations were run for each alignment. The results of this set of simulations are shown in Figure 6 for alignment A and in Figure 7 for alignment B. For alignment A the mean total cost is approximately million with a standard deviation of 6.2 million, whereas for alignment B the mean value is approximately million with a standard deviation of 9.9 million. In Table 14 the results from this set of simulations are compared with the total costs provided by RAVE, the deterministic values, and the probabilistic values from the first set of simulations. 16/20

17 [mio. euro] [of 1,000 simulations] Figure 6 Total cost distribution for alignment A, using médio as mode. Average total cost = 287,910,820 [mio. euro] [of 1,000 simulations] Figure 7 Total cost distribution for alignment B, using médio as mode. Average total cost = 467,992,279 17/20

18 Table 14 Comparison of total costs Alignment RAVE Total costs (euro) Mean total costs (euro) Deterministic Probabilistic simulation simulation médio = mean médio = mode A 265,245, ,245, ,312, ,910,820 B 446,018, ,018, ,319, ,992,279 The comparison of the mean values of the simulations, using first the médio as mean and then the médio as mode, shows that in the latter case the average total costs increase by approximately 10%. 18/20

19 5. Conclusion and future work This second study attempted a probabilistic approach to a high speed railway line using the DAT. It is unclear at this point whether the médio values in report [5] should be interpreted as mean or as mode values. Simulations for both scenarios were run, and it is possible to conclude that interpreting the médio values as mode values, i.e. most probable values, causes the average total costs to increase by 10%. Below are some suggestions of possible future work regarding the RAVE high speed lines: Main Suggestions: 1. Include time uncertainties 2. Include uncertainties in the geology Additional suggestions: 3. Extend the analysis to the entire line Lisbon-Porto (Question: deterministic first and then probabilistic?) 4. Extension of the DAT to include life cycle costs 5. Include uncertainty on the location of karst caverns (to study where to reinforce the structures or apply mitigation methods) 6. Include environmental issues/ costs 7. More detailed studies on a particular (long) tunnel construction method, time and cost of construction, section type (one tube, double tube), location of shafts 8. Resource managing (probably only in an more advanced stage of the project) Note that the suggestions mentioned above can be combined. 19/20

20 7. References [1] SimJava (2007). Decision Aids for Tunneling (DAT), User s Manual. Massachusetts Institute of Technology, Cambridge. [2] Einstein, H.H. (2002). Risk assessment and management in geotechnical engineering. 8th Portuguese Geotechnical Congress, Lisbon, pp [3] Sousa, R. L., Min, S., Einstein, H. H. (2007). Deterministic Cost Analysis for the High Speed Rail between Porto and Lisbon. Alignments A & B close to Leira. Report to RAVE, June [4] Ligação Ferroviária de Alta Velocidade entre Lisboa e Porto. Lote C1. Troco Alenquer (Ota) Pombal. Estudo previo. Volume 3, [5] Relatório de Custos. Eixos Lisboa-Porto e Lisboa-Madrid, Revisão A, /20

Dynamic Bayesian network for probabilistic modeling of tunnel excavation processes

Dynamic Bayesian network for probabilistic modeling of tunnel excavation processes Manuscript accepted for publishing in J. of Computer Aided Civil and Infrastructure Engineering DOI: 10.1111/j.1467-8667.2012.00759.x Dynamic Bayesian network for probabilistic modeling of tunnel excavation

More information

PARAMETRIC STUDY WITH GEOFRAC: A THREE-DIMENSIONAL STOCHASTIC FRACTURE FLOW MODEL. Alessandra Vecchiarelli, Rita Sousa, Herbert H.

PARAMETRIC STUDY WITH GEOFRAC: A THREE-DIMENSIONAL STOCHASTIC FRACTURE FLOW MODEL. Alessandra Vecchiarelli, Rita Sousa, Herbert H. PROCEEDINGS, Thirty-Eighth Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, February 3, 23 SGP-TR98 PARAMETRIC STUDY WITH GEOFRAC: A THREE-DIMENSIONAL STOCHASTIC

More information

Borgonovo Giorgio,Contini Alessio, Locatelli Livio, Ramelli Enzo. Golder Associates (Milan - Italy)

Borgonovo Giorgio,Contini Alessio, Locatelli Livio, Ramelli Enzo. Golder Associates (Milan - Italy) A comprehensive monitoring system of mechanized tunnelling in urban area Automated control of geotechnical measures, topographic surveys, rail tracks geometry and TBM data Borgonovo Giorgio,Contini Alessio,

More information

Embankment design and soil settlement prediction D-SETTLEMENT

Embankment design and soil settlement prediction D-SETTLEMENT Embankment design and soil settlement prediction D-SETTLEMENT Embankment design and soil settlement prediction D-SETTLEMENT General Peat and clay layers will compress significantly after embankment construction,

More information

GEMINI 8-M Telescopes Project

GEMINI 8-M Telescopes Project GEMINI 8-M Telescopes Project TN-O-G0003 Effects on Surface Figure Due to Random Error in Support Actuator Forces for an 8-m Primary Mirror Myung K. Cho Optics Group February 22, 1993 ABSTRACT The effects

More information

Introducing Settle 3D...

Introducing Settle 3D... Introducing Settle 3D... Rocscience will soon be releasing Settle 3D, a totally new software package for analysis of consolidation and settlement under foundations, embankments and surface excavations.

More information

5 Applications of Definite Integrals

5 Applications of Definite Integrals 5 Applications of Definite Integrals The previous chapter introduced the concepts of a definite integral as an area and as a limit of Riemann sums, demonstrated some of the properties of integrals, introduced

More information

Uncertainty analysis in spatial environmental modelling. Kasia Sawicka Athens, 29 Mar 2017

Uncertainty analysis in spatial environmental modelling. Kasia Sawicka Athens, 29 Mar 2017 Uncertainty analysis in spatial environmental modelling Kasia Sawicka Athens, 29 Mar 2017 Uncertainty propagation overview Input ± U Model (± U) Output ± U Input data Model parameters Model structure Solution

More information

UNDERGROUND M 3. UPC GROUP - Barcelona A. Ledesma & A. Gens. Prague meeting, 24 th October 2006

UNDERGROUND M 3. UPC GROUP - Barcelona A. Ledesma & A. Gens. Prague meeting, 24 th October 2006 UNDERGROUND M 3 UPC GROUP - Barcelona A. Ledesma & A. Gens Prague meeting, 24 th October 2006 UPC GROUP Profs. Antonio Gens & Alberto Ledesma Experience on Geotechnical analysis, including systematic backanalysis

More information

FINAL REPORT. Numerical modelling of track-box behaviour. PROJECT CO-ORDINATOR : Norwegian Geotechnical Institute (NGI)

FINAL REPORT. Numerical modelling of track-box behaviour. PROJECT CO-ORDINATOR : Norwegian Geotechnical Institute (NGI) FINAL REPORT Numerical modelling of track-box behaviour CONTRACT N : G1RD-CT-2002-00777 PROJECT N : ACRONYM : SUPERTRACK TITLE : Sustained Performance of Railway Tracks PROJECT CO-ORDINATOR : Norwegian

More information

USING NEURAL NETWORK FOR PREDICTION OF THE DYNAMIC PERIOD AND AMPLIFICATION FACTOR OF SOIL FOR MICROZONATION IN URBAN AREA

USING NEURAL NETWORK FOR PREDICTION OF THE DYNAMIC PERIOD AND AMPLIFICATION FACTOR OF SOIL FOR MICROZONATION IN URBAN AREA USING NEURAL NETWORK FOR PREDICTION OF THE DYNAMIC PERIOD AND AMPLIFICATION FACTOR OF SOIL FOR MICROZONATION IN URBAN AREA Tahamoli Roodsari, Mehrzad 1 and Habibi, Mohammad Reza 2 1 M.S. in Earthquake

More information

GTS. midas GTS Advanced Webinar. Date: June 5, 2012 Topic: General Use of midas GTS (Part II) Presenter: Vipul Kumar

GTS. midas GTS Advanced Webinar. Date: June 5, 2012 Topic: General Use of midas GTS (Part II) Presenter: Vipul Kumar midas GTS Advanced Webinar Date: June 5, 2012 Topic: General Use of midas GTS (Part II) Presenter: Vipul Kumar Bridging Your Innovations to Realities GTS MIDAS Information Technology Co., Ltd. [1/30] Contents:

More information

Modelling of Tunnels in 2D & 3D

Modelling of Tunnels in 2D & 3D MIDAS Geotechnical Know-how Sharing Series November 28 th, 2017 (Tue) 10:00 ~ 11:00 AM (CET) Session 3. Modelling of Tunnels in 2D & 3D JaeSeok Yang Principal Geotechnical Engineer, MIDAS IT Integrated

More information

v Prerequisite Tutorials Required Components Time

v Prerequisite Tutorials Required Components Time v. 10.0 GMS 10.0 Tutorial MODFLOW Stochastic Modeling, Parameter Randomization Run MODFLOW in Stochastic (Monte Carlo) Mode by Randomly Varying Parameters Objectives Learn how to develop a stochastic (Monte

More information

v MODFLOW Stochastic Modeling, Parameter Randomization GMS 10.3 Tutorial

v MODFLOW Stochastic Modeling, Parameter Randomization GMS 10.3 Tutorial v. 10.3 GMS 10.3 Tutorial MODFLOW Stochastic Modeling, Parameter Randomization Run MODFLOW in Stochastic (Monte Carlo) Mode by Randomly Varying Parameters Objectives Learn how to develop a stochastic (Monte

More information

Lab Practical - Limit Equilibrium Analysis of Engineered Slopes

Lab Practical - Limit Equilibrium Analysis of Engineered Slopes Lab Practical - Limit Equilibrium Analysis of Engineered Slopes Part 1: Planar Analysis A Deterministic Analysis This exercise will demonstrate the basics of a deterministic limit equilibrium planar analysis

More information

Chapter 5. Track Geometry Data Analysis

Chapter 5. Track Geometry Data Analysis Chapter Track Geometry Data Analysis This chapter explains how and why the data collected for the track geometry was manipulated. The results of these studies in the time and frequency domain are addressed.

More information

Vocabulary: Looking For Pythagoras

Vocabulary: Looking For Pythagoras Vocabulary: Looking For Pythagoras Concept Finding areas of squares and other figures by subdividing or enclosing: These strategies for finding areas were developed in Covering and Surrounding. Students

More information

Settlement of a circular silo foundation

Settlement of a circular silo foundation Engineering manual No. 22 Updated: 02/2018 Settlement of a circular silo foundation Program: FEM File: Demo_manual_22.gmk The objective of this manual is to describe the solution to a circular silo foundation

More information

Module 1 Lecture Notes 2. Optimization Problem and Model Formulation

Module 1 Lecture Notes 2. Optimization Problem and Model Formulation Optimization Methods: Introduction and Basic concepts 1 Module 1 Lecture Notes 2 Optimization Problem and Model Formulation Introduction In the previous lecture we studied the evolution of optimization

More information

February Regional Geometry Team: Question #1

February Regional Geometry Team: Question #1 February Regional Geometry Team: Question #1 A = area of an equilateral triangle with a side length of 4. B = area of a square with a side length of 3. C = area of a regular hexagon with a side length

More information

THE GENERATION OF CHINESE ICE-RAY LATTICE STRUCTURES FOR 3D FAÇADE DESIGN

THE GENERATION OF CHINESE ICE-RAY LATTICE STRUCTURES FOR 3D FAÇADE DESIGN THE GENERATION OF CHINESE ICE-RAY LATTICE STRUCTURES FOR 3D FAÇADE DESIGN Rudi Stouffs 1, Mark Wieringa 2 r.m.f.stouffs@tudelft.nl 1, m.wieringa@planet.nl 2 Department of Building Technology, Faculty of

More information

S206E Lecture 15, 4/27/2018, Rhino 3D, Grasshopper, Shanghai Tower modeling

S206E Lecture 15, 4/27/2018, Rhino 3D, Grasshopper, Shanghai Tower modeling S206E057 -- Lecture 15, 4/27/2018, Rhino 3D, Grasshopper, Shanghai Tower modeling Copyright 2018, Chiu-Shui Chan. All Rights Reserved. Creation of high-rise building models has a typical algorithm, which

More information

Developer s Tips. Groundwater analysis using Slide

Developer s Tips. Groundwater analysis using Slide Developer s Tips Groundwater analysis using Slide In this article we introduce the new groundwater/seepage analysis module, which was built into version 5.0 of Slide. The groundwater module uses a finite

More information

Terrain settlement analysis

Terrain settlement analysis Engineering manual No. 21 Updated: 02/2018 Terrain settlement analysis Program: File: FEM Demo_manual_21.gmk This example contains the solution to terrain settlement under surcharge loading using the Finite

More information

A comparative study of the tensor and upscaling methods for evaluating permeability in fractured reservoirs

A comparative study of the tensor and upscaling methods for evaluating permeability in fractured reservoirs IAMG2015 - Proceedings F1203 A comparative study of the tensor and upscaling methods for evaluating permeability in fractured reservoirs R. FLÓRIO 1* and J. ALMEIDA 2 1 Departamento de Ciências da Terra

More information

FLAC/Slope User s Guide Contents - 1

FLAC/Slope User s Guide Contents - 1 FLAC/Slope User s Guide Contents - 1 TABLE OF CONTENTS 1 FLAC/SLOPE 1.1 Introduction... 1-1 1.1.1 Overview... 1-1 1.1.2 Guide to the FLAC/Slope Manual... 1-2 1.1.3 Summary of Features... 1-2 1.1.4 Analysis

More information

- Freehaul: Distance with which there is a fixed price for excavating, hauling, and dumping regardless of the distance moved.

- Freehaul: Distance with which there is a fixed price for excavating, hauling, and dumping regardless of the distance moved. mp UFreehaul, Overhaul, and Mass Haul Diagram: Normally, cost of excavation includes; cost of transporting of material (unwanted soil) from either cut or fill for a maximum distance called the Ufreehaul

More information

Cpk: What is its Capability? By: Rick Haynes, Master Black Belt Smarter Solutions, Inc.

Cpk: What is its Capability? By: Rick Haynes, Master Black Belt Smarter Solutions, Inc. C: What is its Capability? By: Rick Haynes, Master Black Belt Smarter Solutions, Inc. C is one of many capability metrics that are available. When capability metrics are used, organizations typically provide

More information

DEVELOPMENT OF PROTOTYPE OF INTEGRATED EARTHQUAKE DISASTER SIMULATOR USING DIGITAL CITY AND STRONG GROUND MOTION SIMULATOR WITH HIGH-RESOLUTION

DEVELOPMENT OF PROTOTYPE OF INTEGRATED EARTHQUAKE DISASTER SIMULATOR USING DIGITAL CITY AND STRONG GROUND MOTION SIMULATOR WITH HIGH-RESOLUTION 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 1418 DEVELOPMENT OF PROTOTYPE OF INTEGRATED EARTHQUAKE DISASTER SIMULATOR USING DIGITAL CITY AND STRONG

More information

Multivariate Capability Analysis

Multivariate Capability Analysis Multivariate Capability Analysis Summary... 1 Data Input... 3 Analysis Summary... 4 Capability Plot... 5 Capability Indices... 6 Capability Ellipse... 7 Correlation Matrix... 8 Tests for Normality... 8

More information

Community Update. May 31, 2011

Community Update. May 31, 2011 Community Update May 31, 2011 Presented to: Leaside Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Introduction: RS 3 Tutorial 1 Quick Start

Introduction: RS 3 Tutorial 1 Quick Start Introduction: RS 3 Tutorial 1 Quick Start Welcome to RS 3. This tutorial introduces some basic features of RS 3. The model analyzes the effect of tank loading on an existing sloped underground tunnel.

More information

STP: Monte Carlo Evaluation of a Subsurface Testing Program

STP: Monte Carlo Evaluation of a Subsurface Testing Program Kintigh: Tools for Quantitative Archaeology Subsurface 108 STP: Monte Carlo Evaluation of a Subsurface Testing Program STP performs a Monte Carlo evaluation of an arbitrary layout of test units within

More information

CCBC Math 081 Geometry Section 2.2

CCBC Math 081 Geometry Section 2.2 2.2 Geometry Geometry is the study of shapes and their mathematical properties. In this section, we will learn to calculate the perimeter, area, and volume of a few basic geometric shapes. Perimeter We

More information

BIM applications to underground projects: the example of the extension of Catania Railway

BIM applications to underground projects: the example of the extension of Catania Railway BIM applications to underground projects: the example of the extension of Catania Railway Paolo Cucino, Gabriele Eccher, Luca Schiavinato, Stefano Colombelli & Domenico Nave SWS Engineering SpA, Trento,

More information

EDA - Electronic Design Automation or Electronic Design Assistance?

EDA - Electronic Design Automation or Electronic Design Assistance? EDA - Electronic Design Automation or Electronic Design Assistance? NSF Workshop Electronic Design Automation Past, Present, and Future Andreas Kuehlmann NSF Workshop, July 8 9 2009 The Past The Vision

More information

Embankment design and soil settlement prediction. D-Settlement. User Manual

Embankment design and soil settlement prediction. D-Settlement. User Manual Embankment design and soil settlement prediction D-Settlement User Manual D-SETTLEMENT Embankment design and soil settlement prediction User Manual Version: 16.1 Revision: 00 9 February 2016 D-SETTLEMENT,

More information

Groundwater in Hydrologic Cycle

Groundwater in Hydrologic Cycle Groundwater in Hydrologic Cycle Types of Terrestrial Water Surface Water Soil Moisture Ground water Pores Full of Combination of Air and Water Unsaturated Zone / Zone of Aeration / Vadose (Soil Water)

More information

Community Update. June 21, 2011

Community Update. June 21, 2011 Community Update June 21, 2011 Presented at Beth Sholom Synagogue Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Let s take a closer look at the standard deviation.

Let s take a closer look at the standard deviation. For this illustration, we have selected 2 random samples of 500 respondents each from the voter.xls file we have been using in class. We recorded the ages of each of the 500 respondents and computed the

More information

Seismic Soil-Structure Interaction Analysis of the Kealakaha Stream Bridge on Parallel Computers

Seismic Soil-Structure Interaction Analysis of the Kealakaha Stream Bridge on Parallel Computers Seismic Soil-Structure Interaction Analysis of the Kealakaha Stream Bridge on Parallel Computers Seung Ha Lee and Si-Hwan Park Department of Civil and Environmental Engineering University of Hawaii at

More information

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for

More information

TTUSD Math Essential Standards Matrix 4/16/10 NUMBER SENSE

TTUSD Math Essential Standards Matrix 4/16/10 NUMBER SENSE TTUSD Math Essential Standards Matrix 4/16/10 NUMBER SENSE 3 rd 4 th 5 th 6th 1.1 Read and write whole numbers in the millions 1.2 Order and compare whole numbers and decimals to two decimal places. 1.1

More information

Statistical surfaces and interpolation. This is lecture ten

Statistical surfaces and interpolation. This is lecture ten Statistical surfaces and interpolation This is lecture ten Data models for representation of surfaces So far have considered field and object data models (represented by raster and vector data structures).

More information

Developer s Tip. An Introduction to the Theory of Planar Failure. Concepts of Planar Rock Slope Failure

Developer s Tip. An Introduction to the Theory of Planar Failure. Concepts of Planar Rock Slope Failure Developer s Tip An Introduction to the Theory of Planar Failure In this article we explain the basic concepts behind planar failure analysis of rock slopes. We also discuss the geometric conditions that

More information

Reduction Deliverable Intelligent V2V and V2I communication

Reduction Deliverable Intelligent V2V and V2I communication Reduction 2011-2014 Deliverable 1.4.1 Intelligent V2V and V2I communication Test report with communication between the Bluetooth detectors and the incar system or smart phones 26-08- 2013 Public Document

More information

Parametric. Practices. Patrick Cunningham. CAE Associates Inc. and ANSYS Inc. Proprietary 2012 CAE Associates Inc. and ANSYS Inc. All rights reserved.

Parametric. Practices. Patrick Cunningham. CAE Associates Inc. and ANSYS Inc. Proprietary 2012 CAE Associates Inc. and ANSYS Inc. All rights reserved. Parametric Modeling Best Practices Patrick Cunningham July, 2012 CAE Associates Inc. and ANSYS Inc. Proprietary 2012 CAE Associates Inc. and ANSYS Inc. All rights reserved. E-Learning Webinar Series This

More information

Community Update. June 8, 2011

Community Update. June 8, 2011 Community Update June 8, 2011 Presented to: Scarborough Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Robotics. Lecture 5: Monte Carlo Localisation. See course website for up to date information.

Robotics. Lecture 5: Monte Carlo Localisation. See course website  for up to date information. Robotics Lecture 5: Monte Carlo Localisation See course website http://www.doc.ic.ac.uk/~ajd/robotics/ for up to date information. Andrew Davison Department of Computing Imperial College London Review:

More information

Oasys Pdisp. Copyright Oasys 2013

Oasys Pdisp. Copyright Oasys 2013 Oasys Pdisp Copyright Oasys 2013 All rights reserved. No parts of this work may be reproduced in any form or by any means - graphic, electronic, or mechanical, including photocopying, recording, taping,

More information

Statistical Pi Simulation by Java

Statistical Pi Simulation by Java Statistical Pi Simulation by Java Katherine Lim Eleanor Murray Fallon Middle School 3601 Kohnen Way, Dublin, CA 94568 katherinelim65@gmail.com Abstract Pi, the ratio of a circle's circumference to its

More information

4.2 and 4.6 filled in notes.notebook. December 08, Integration. Copyright Cengage Learning. All rights reserved.

4.2 and 4.6 filled in notes.notebook. December 08, Integration. Copyright Cengage Learning. All rights reserved. 4 Integration Copyright Cengage Learning. All rights reserved. 1 4.2 Area Copyright Cengage Learning. All rights reserved. 2 Objectives Use sigma notation to write and evaluate a sum. Understand the concept

More information

2016(v1.1) Release Notes

2016(v1.1) Release Notes 2016(v1.1) Release Notes Ver 4.0.0. 개정내용 2016(v1.1) Release Notes Copyright c 1989~2014. MIDAS Information Technology Co., Ltd. ALL RIGHTS RESERVED. 1 / 21 Release Note 2016(v1.1) Release Notes Pre-Processing

More information

MIDAS Geotechnical Training Series

MIDAS Geotechnical Training Series MIDAS Geotechnical Training Series Fully Coupled vs Consolidation Analysis Seongwan Bae Angel F. Martinez MIDAS Information Technology Integrated Solver Optimized for the next generation 6-bit platform

More information

3DReshaper Help DReshaper Beginner's Guide. Surveying

3DReshaper Help DReshaper Beginner's Guide. Surveying 3DReshaper Beginner's Guide Surveying 1 of 29 Cross sections Exercise: Tunnel analysis Surface analysis Exercise: Complete analysis of a concrete floor Surveying extraction Exercise: Automatic extraction

More information

The Occurrence of Surface Casing Pressure in the Denver-Julesburg Basin

The Occurrence of Surface Casing Pressure in the Denver-Julesburg Basin The Occurrence of Surface Casing Pressure in the Denver-Julesburg Basin (Airwatergas.org) Greg Lackey, Harihar Rajaram, Owen A. Sherwood, Troy L. Burke and Joseph N. Ryan Surface Casing Pressure Undesired

More information

VISUALIZATION OF VARIATION IN EARLY DESIGN PHASES: A CONVEX HULL APPROACH

VISUALIZATION OF VARIATION IN EARLY DESIGN PHASES: A CONVEX HULL APPROACH INTERNATIONAL DESIGN CONFERENCE - DESIGN 2006 Dubrovnik - Croatia, May 15-18, 2006 VISUALIZATION OF VARIATION IN EARLY DESIGN PHASES: A CONVEX HULL APPROACH J. Lööf, R. Söderberg and L. Lindkvist Keywords:

More information

OPTUM COMPUTATIONAL ENGINEERING ANALYSIS

OPTUM COMPUTATIONAL ENGINEERING ANALYSIS OPTUM COMPUTATIONAL ENGINEERING ANALYSIS Version 2016 OptumG2: Analysis K Krabbenhoft, AV Lymain, J Krabbenhoft (Editors) c Optum Computational Engineering 2016 www.optumce.com CONTENTS Contents 1 GENERAL

More information

Transactions on the Built Environment vol 28, 1997 WIT Press, ISSN

Transactions on the Built Environment vol 28, 1997 WIT Press,   ISSN Shape/size optimization of truss structures using non-probabilistic description of uncertainty Eugenio Barbieri, Carlo Cinquini & Marco Lombard! LWveraz'ry of fawa, DeparfmcMf q/#r%cf%ra7 Mzc/zamcj, fawa,

More information

Empirical Development of 3D Terrain Processing Platform for Autonomous Excavation System

Empirical Development of 3D Terrain Processing Platform for Autonomous Excavation System Empirical Development of 3D Terrain Processing Platform for Autonomous Excavation System Seok Kim 1, Tae-yeong Kim 2, Soonwook Kwon 3, Jongwon Seo 4 1 Senior Researcher, Korean Institute of Civil Engineering

More information

Slope Stability of Open Pit Mine in 2D & 3D

Slope Stability of Open Pit Mine in 2D & 3D Slope Stability of Open Pit Mine in D & D MIDASoft Inc. Angel Francisco Martinez Civil Engineer Email : a.martinez@midasit.com Integrated Solver Optimized for the next generation64-bit platform Finite

More information

Modeling Uncertainty in the Earth Sciences Jef Caers Stanford University

Modeling Uncertainty in the Earth Sciences Jef Caers Stanford University Modeling spatial continuity Modeling Uncertainty in the Earth Sciences Jef Caers Stanford University Motivation uncertain uncertain certain or uncertain uncertain Spatial Input parameters Spatial Stochastic

More information

NUMERICAL METHOD TO ESTIMATE TOLERANCES COMBINED EFFECTS ON A MECHANICAL SYSTEM

NUMERICAL METHOD TO ESTIMATE TOLERANCES COMBINED EFFECTS ON A MECHANICAL SYSTEM INTERNATIONAL DESIGN CONFERENCE - DESIGN 2004 Dubrovnik, May 18-21, 2004. NUMERICAL METHOD TO ESTIMATE TOLERANCES COMBINED EFFECTS ON A MECHANICAL SYSTEM D. Cambiaghi, A. Magalinia and D. Vetturi Keywords:

More information

The Accuracy of Determining the Volumes Using Close Range Photogrammetry

The Accuracy of Determining the Volumes Using Close Range Photogrammetry IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. VII (Mar - Apr. 2015), PP 10-15 www.iosrjournals.org The Accuracy of Determining

More information

Surveying Prof. Bharat Lohani Indian Institute of Technology, Kanpur. Lecture - 1 Module - 6 Triangulation and Trilateration

Surveying Prof. Bharat Lohani Indian Institute of Technology, Kanpur. Lecture - 1 Module - 6 Triangulation and Trilateration Surveying Prof. Bharat Lohani Indian Institute of Technology, Kanpur Lecture - 1 Module - 6 Triangulation and Trilateration (Refer Slide Time: 00:21) Welcome to this another lecture on basic surveying.

More information

Reliability Analysis for Tunnel Supports System by Using Finite Element Method

Reliability Analysis for Tunnel Supports System by Using Finite Element Method American Journal of Engineering Research (AJER) e-issn: 2320-0847 p-issn : 2320-0936 Volume-5, Issue-9, pp-01-08 www.ajer.org Research Paper Open Access Reliability Analysis for Tunnel Supports System

More information

GTS NX INTERFACES AUTOCAD MIDAS GEN FOR TUNNEL SOIL PILE INTERACTION ANALYSIS

GTS NX INTERFACES AUTOCAD MIDAS GEN FOR TUNNEL SOIL PILE INTERACTION ANALYSIS INTERFACES AUTOCAD MIDAS GEN FOR TUNNEL SOIL PILE INTERACTION ANALYSIS Angel F. Martinez Civil Engineer MIDASOFT Integrated Solver Optimized for the next generation 64-bit platform Finite Element Solutions

More information

Combining Appropriate Soil Behavior Models for simulating Taham Rockfill Dam. Lecturer of Islamic Azad university-tehran Jonoub Branch, Tehran, Iran

Combining Appropriate Soil Behavior Models for simulating Taham Rockfill Dam. Lecturer of Islamic Azad university-tehran Jonoub Branch, Tehran, Iran Combining Appropriate Soil Behavior Models for simulating Taham Rockfill Dam Mohammadkeya Khosravi 1, Dr. Mohammad Hadi Davoudi 2, Akbar Pashazadeh 3 1 Lecturer of Islamic Azad university-tehran Jonoub

More information

Thoughts on Representing Spatial Objects. William A. Huber Quantitative Decisions Rosemont, PA

Thoughts on Representing Spatial Objects. William A. Huber Quantitative Decisions Rosemont, PA Thoughts on Representing Spatial Objects William A. Huber Quantitative Decisions Rosemont, PA Overview 1. Some Ways to Structure Space 2. What to Put into a Grid 3. Objects and Fields 4. Hybrid Structures

More information

APPENDIX K MONTE CARLO SIMULATION

APPENDIX K MONTE CARLO SIMULATION APPENDIX K MONTE CARLO SIMULATION K-1. Introduction. Monte Carlo simulation is a method of reliability analysis that should be used only when the system to be analyzed becomes too complex for use of simpler

More information

Summary of New DARWIN TM Capabilities for Surface Damage Tolerance Assessment and Related Enhancements

Summary of New DARWIN TM Capabilities for Surface Damage Tolerance Assessment and Related Enhancements Summary of New DARWIN TM Capabilities for Surface Damage Tolerance Assessment and Related Enhancements Mike Enright, Luc Huyse, Yi-Der Lee, Graham Chell, Craig McClung, Gerald Leverant Southwest Research

More information

Diamond Engineer: Tunnel Series Training 2

Diamond Engineer: Tunnel Series Training 2 Diamond Engineer: Tunnel Series Training 2 Angel Francisco Martinez Application Engineer MIDAS NY Content 01 Introduction 02 Construction Stages 03 Demo 04 Post - Processing Introduction About MIDAS No.

More information

Seismic regionalization based on an artificial neural network

Seismic regionalization based on an artificial neural network Seismic regionalization based on an artificial neural network *Jaime García-Pérez 1) and René Riaño 2) 1), 2) Instituto de Ingeniería, UNAM, CU, Coyoacán, México D.F., 014510, Mexico 1) jgap@pumas.ii.unam.mx

More information

Model data extraction. Mass property data. Mass property data. Mass property data. Integral Processes. Units and volume

Model data extraction. Mass property data. Mass property data. Mass property data. Integral Processes. Units and volume Model data extraction Most solid modelers permit information to be extracted directly from the model database. Graphic profile data 2D drawings annotation Solid model database details the distribution

More information

PHASED EXCAVATION OF A SHIELD TUNNEL

PHASED EXCAVATION OF A SHIELD TUNNEL 5 PHASED EXCAVATION OF A SHIELD TUNNEL The lining of a shield tunnel is often constructed using prefabricated concrete ring segments, which are bolted together within the tunnel boring machine to form

More information

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Sheet Pile Wall

GEO-SLOPE International Ltd, Calgary, Alberta, Canada  Sheet Pile Wall 1 Introduction Sheet Pile Wall Deep excavation on a level group usually results in a very low factor of safety, unless it is properly reinforced. The purpose of this example is to illustrate how the stability

More information

Local Linear Approximation for Kernel Methods: The Railway Kernel

Local Linear Approximation for Kernel Methods: The Railway Kernel Local Linear Approximation for Kernel Methods: The Railway Kernel Alberto Muñoz 1,JavierGonzález 1, and Isaac Martín de Diego 1 University Carlos III de Madrid, c/ Madrid 16, 890 Getafe, Spain {alberto.munoz,

More information

Slip Surface Optimization

Slip Surface Optimization Slip Surface Optimization GEO-SLOPE International Ltd. www.geo-slope.com 1200, 700-6th Ave SW, Calgary, AB, Canada T2P 0T8 Main: +1 403 269 2002 Fax: +1 888 463 2239 Introduction Traditionally, trial slip

More information

CHAPTER 8 ANALYSIS USING ANSYS MAXWELL SOFTWARE. 8.1 Ansys Maxwell Software

CHAPTER 8 ANALYSIS USING ANSYS MAXWELL SOFTWARE. 8.1 Ansys Maxwell Software CHAPTER 8 8.1 Ansys Maxwell Software ANALYSIS USING ANSYS MAXWELL SOFTWARE The Ansys Maxwell software is widely used in designing and optimizing electrostatic, electromagnetic and eddy current problems.

More information

In this section you will learn some simple data entry, editing, formatting techniques and some simple formulae. Contents

In this section you will learn some simple data entry, editing, formatting techniques and some simple formulae. Contents In this section you will learn some simple data entry, editing, formatting techniques and some simple formulae. Contents Section Topic Sub-topic Pages Section 2 Spreadsheets Layout and Design S2: 2 3 Formulae

More information

Pseudo 3-D deposition and large-strain consolidation modeling of tailings deep deposits

Pseudo 3-D deposition and large-strain consolidation modeling of tailings deep deposits Pseudo 3-D deposition and large-strain consolidation modeling of tailings deep deposits Murray Fredlund, Matt Donaldson, Krishna Chaudhary SoilVision Systems Ltd ABSTRACT The design of deep deposits requires

More information

Visualizing Large Parallel Finite Element Simulations

Visualizing Large Parallel Finite Element Simulations Visualizing Large Parallel Finite Element Simulations J Leng 1, L Margetts 2 1 Manchester Visualization Centre, University of Manchester 2 Manchester Computing, University of Manchester (currently at the

More information

Approximating geometrical graphs via spanners and banyans

Approximating geometrical graphs via spanners and banyans Approximating geometrical graphs via spanners and banyans S. B. Rao & W. D. Smith Proc of STOC, 1998: 540-550 Recap (Arora s Algorithm) Recap (Arora s Algorithm) Recap (Arora s Algorithm) Recap (Arora

More information

INTRODUCTION TO VOLUME MEASUREMENTS Volume measurements are needed for three different categories of pay items:

INTRODUCTION TO VOLUME MEASUREMENTS Volume measurements are needed for three different categories of pay items: INTRODUCTION TO VOLUME MEASUREMENTS Volume measurements are needed for three different categories of pay items: Earthwork --items such as borrow excavation, and subsoil excavation Concrete -- the various

More information

PLAXIS 3D Tunnel. Tutorial Manual

PLAXIS 3D Tunnel. Tutorial Manual PLAXIS 3D Tunnel Tutorial Manual TABLE OF CONTENTS TABLE OF CONTENTS 1 Introduction...1-1 2 Getting started...2-1 2.1 Installation...2-1 2.2 General modelling aspects...2-1 2.3 Input procedures...2-3

More information

PROBABILISTIC ANALYSIS OF EMBANKMENTS USING MONTE CARLO SIMULATION

PROBABILISTIC ANALYSIS OF EMBANKMENTS USING MONTE CARLO SIMULATION 4 th International Conference on Earthquake Geotechnical Engineering June 25-28, 2007 Paper No. 1310 PROBABILISTIC ANALYSIS OF EMBANKMENTS USING MONTE CARLO SIMULATION Evangelos C. GEORGOPOULOS 1, Yiannis

More information

ANNUAL NATIONAL ASSESSMENT 2014 ASSESSMENT GUIDELINES MATHEMATICS GRADE 8

ANNUAL NATIONAL ASSESSMENT 2014 ASSESSMENT GUIDELINES MATHEMATICS GRADE 8 ANNUAL NATIONAL ASSESSMENT 2014 ASSESSMENT GUIDELINES MATHEMATICS GRADE 8 INTRODUCTION The 2014 cycle of Annual National Assessment (ANA 2014) will be administered in all public and designated 1 independent

More information

Level E TJ Book CHECKLIST

Level E TJ Book CHECKLIST St Ninian s High School Level E TJ Book CHECKLIST I understand this part of the course = I am unsure of this part of the course = I do not understand this part of the course = Name Class Teacher Topic

More information

Level-set and ALE Based Topology Optimization Using Nonlinear Programming

Level-set and ALE Based Topology Optimization Using Nonlinear Programming 10 th World Congress on Structural and Multidisciplinary Optimization May 19-24, 2013, Orlando, Florida, USA Level-set and ALE Based Topology Optimization Using Nonlinear Programming Shintaro Yamasaki

More information

Chapter 20. Finite Element Method (FEM) Introduction

Chapter 20. Finite Element Method (FEM) Introduction Chapter 20. Finite Element Method (FEM) Introduction The objective of this chapter is to explain basic terms of the particular field of problems and practical application of GEO 5 FEM program to solve

More information

3D Excavation by Tunnel Boring Machine

3D Excavation by Tunnel Boring Machine 3D Excavation by Tunnel Boring Machine Angel Francisco Martinez Application Engineer MIDAS NY Content 01 Introduction 02 Advantages of GTS NX for Tunneling 03 TBM Demo Introduction About MIDAS No. 1 in

More information

Masking Lidar Cliff-Edge Artifacts

Masking Lidar Cliff-Edge Artifacts Masking Lidar Cliff-Edge Artifacts Methods 6/12/2014 Authors: Abigail Schaaf is a Remote Sensing Specialist at RedCastle Resources, Inc., working on site at the Remote Sensing Applications Center in Salt

More information

Notes for Recitation 9

Notes for Recitation 9 6.042/18.062J Mathematics for Computer Science October 8, 2010 Tom Leighton and Marten van Dijk Notes for Recitation 9 1 Traveling Salesperson Problem Now we re going to talk about a famous optimization

More information

SPSS TRAINING SPSS VIEWS

SPSS TRAINING SPSS VIEWS SPSS TRAINING SPSS VIEWS Dataset Data file Data View o Full data set, structured same as excel (variable = column name, row = record) Variable View o Provides details for each variable (column in Data

More information

Deformation Monitoring and Monitoring Data Management at the Metro Project Cityringen Copenhagen

Deformation Monitoring and Monitoring Data Management at the Metro Project Cityringen Copenhagen Deformation Monitoring and Monitoring Data Management at the Metro Project Cityringen Copenhagen K. Chmelina, K. Rabensteiner, A. Charalambides Geodata Group, Hans Kudlichstraße 28, A-8700 Leoben, Austria

More information

Simulation-Supported Decision Making. Gene Allen Director, Collaborative Development MSC Software Corporation

Simulation-Supported Decision Making. Gene Allen Director, Collaborative Development MSC Software Corporation Simulation-Supported Decision Making Gene Allen Director, Collaborative Development MSC Software Corporation Simulation A Tool for Decision Making Quickly Identify and Understand How a Product Functions:

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK M.E: CAD/CAM I SEMESTER ED5151 COMPUTER APPLICATIONS IN DESIGN Regulation 2017 Academic

More information

Numerical calculation of the wind action on buildings using Eurocode 1 atmospheric boundary layer velocity profiles

Numerical calculation of the wind action on buildings using Eurocode 1 atmospheric boundary layer velocity profiles Numerical calculation of the wind action on buildings using Eurocode 1 atmospheric boundary layer velocity profiles M. F. P. Lopes IDMEC, Instituto Superior Técnico, Av. Rovisco Pais 149-1, Lisboa, Portugal

More information

Mathematics Curriculum

Mathematics Curriculum 6 G R A D E Mathematics Curriculum GRADE 6 5 Table of Contents 1... 1 Topic A: Area of Triangles, Quadrilaterals, and Polygons (6.G.A.1)... 11 Lesson 1: The Area of Parallelograms Through Rectangle Facts...

More information