1 Managing The Infrastructure Of Data Centers David Cuthbertson Square Mile Systems Ltd

2 Square Mile Background Develop toolsets, training and techniques for operational management of complex IT infrastructure Focus areas Data center management Connectivity management System change impact analysis Documentation techniques Infrastructure visualisation All technologies! Business Processes Departmental, Company Services End user, infrastructure, supplier Applications PC, server, mainframe, SOA Virtual Infrastructure Network, Servers, Storage, DBMS Hardware Infrastructure Network, Servers, UPS, Storage, Other Fixed Infrastructure (Cabling, Power, Cabinets, Buildings) Data Center Infrastructure

3 Seminar overview Understand management issues to aid selection of technology and techniques Communicating best practice Develop your own perspectives and learn from others Exercises covering typical DC issues Have a few laughs on the way Only two uses of the word green

4 Common Management Issues Data Centre is often not visible, nor are the staff If it s not broke attitude isn t good, infrastructure risks need to be managed IT groups are often task and project orientated, less focus on operational issues Getting funds allocated for improving management techniques is difficult Skills sets need to evolve with technology and organisation control requirements

5 Defining Management Planning what needs to be done to achieve a particular result Organising and directing resources. Controlling and making adjustments as needed Motivating all those involved.

6 Management Maturity Reactive Repeatable Defined Managed Optimised Individual approach Some process, often informal Process documented and explained Process checked and reviewed for gaps Process open to external review and updated regularly Where might you be if you a) Didn t label patch cables b) Labelled patch cables consistently? c) Audited records against patching documentation?

7 Why Improve DC Management? 1. New technology demands Cooling, power, cabling, weight 2. Save on capital and operational costs Optimise existing facilities Reduce power and other costs 3. Less tolerance of outages and disruption 4. Speed of change 5. External need for evidence of control

8 Changing Requirements BEFORE AFTER No. of Servers per cabinet Power Disipated per cab W 3kW - 25kW Current service to cabinet 16A 2x32 A or 3 phase Types of Equipment Servers Blade Servers Monitor Power Distribution Units KVMs MidSpan Boxes Power Strips Disk Arrays (Storage) UPS Smart Power Strips Regular Power Strips Network types 100M 1G, 10G, SAN No. of Cables Power 1 or 2 2 to 6 (per server) Network 1 or 2 5 to 10 Cabinet Total

9 New Technology Challenges Sun Blade 8000 Blade Chassis 4 Power supplies (N+1) 9kW 3 chassis per rack 27kW? HP C7000 Blade Chassis Up to 6 Power Supplies 13kW 4 chassis per rack Cisco Nexus 7000 Data Center Switch 3 Power Supplies 12kW Up to 384 ports And in the next few weeks?

10 Starting Well 1. Specify and build the infrastructure using a standards based approach 1. TIA942 data centre design 2. Other standards TIA, EN, etc. 2. Test installation for conformance to requirements 3. Handover of documentation, skills transfer and operational procedures to customer

11 So How Did This Happen?

12 Different Working Practices

13 Exercise 1 Cable Management Both are cabling implementations using different management styles 1. Explain why the cabinet on the left is preferred 2. Explain what you may have to do to keep the left cabinet maintained in the same style

14 Exercise 1 Review Risk Organisation Speed Process Cost Technology

15 So You may understand, but you can t assume others do Professionally designed infrastructure will be compromised without professional management practices!

16 Defining Best Practices You could define your own best practice Authority Experience Technically qualified Best communicator Management information Or you could adopt a framework Quicker path to end result with less opinions

17 Management Frameworks ITIL / ISO20000 Service Management BS25999 ISO27001 CoBit Business Continuity Information Security IT Governance All have a continuous process Plan But no equivalent for data center management! Act Check Do

18 ISO20000/ITIL V2 Security Management Service Continuity & Availability Management Release Processes Release Management Service Delivery Processes Service Level Management Service Reporting Control Processes Configuration Management Change Management Resolution Processes Incident Management Problem Management Capacity Management Financial Management Relationship Processes Business Relationship Management Supplier Management

19 Why have a framework? Common understanding of complex issues Terms, Processes, Roles Measurement, identification of gaps Communication Training for individuals and teams Focus provided Easier adoption of industry techniques Overcomes internal reluctance to change

20 Example of Best Practice Procuring a new server Policies - sign off, payment Ordering process life cycle Purchase orders common reference Roles and responsibilities specify, order and approve

21 Design Best Practice in Data Centers TIA942 standard, Uptime Institute, manufacturer guidelines Build and Install Standards and regulations TIA, etc. Operate??? EU Code of Conduct for Data Centers New!

22 OUTLET # BLINK = REMOTE = U OFF I = ON LINK 10/100 I/U TOGGLE CURRENT LAN SER IAL FEATURE OUTLET # BLINK = REMOTE = U OFF I = ON CURRENT LAN SER IAL LINK 10/100 I/U TOGGLE FEATURE Different Power Views 16A feed What should the working limit 16A feed be for the power strip? KVM STATUS V RESERVED 50~ 60Hz 1.2A Servers ~

23 Exercise 2 Power Calculations What types of equipment power/current rating should be known and used when assessing and planning changes?

24 So. Monitoring tools are useful, but they only tell you what they see For managing power infrastructure we may need multiple values Manufacturer power rating Derated power often 60% of manufacturer Design power Actual power

25 Data Center Management No public framework exists for data centers yet In other areas it is easier ITIL, ISO20000 Service Management ISO27001 Information Security Cobit IT Controls Prince 2 Projects ISO9000/6 Sigma Quality

26 Exercise 3- Wasted Costs Give an example where because of lack of knowledge or understanding, unplanned or unnecessary costs were incurred

27 Exercise 4 Server Provisioning You have received a request to move 10 existing servers into a data centre. What tasks might have to be done to fulfil this request?

28 Exercise 4 Server Provisioning Assess Plan Implement Test Completion Concentrate on these two and the tasks appropriate to each It is important to identify specific tasks and whether they should be in the assessment or detailed planning phases

29 Provisioning Review What did we learn? Types of information required at each stage Tracking and control Communication needs Complexity of infrastructure changes

30 Managing Existing Data Centers Environment limits Information sets - formal and informal Working practices - formal and informal Roles / responsibilities Current issues Establish priorities

31 Typical Power Distribution Incoming feeds 32 & 16 Amp Sockets UPS 3 Phase PDU 100A 100A 100A Remote Controlled Power Strips Circuit Breakers 16A 32A 16A Power Strips Power Strips Power Strips 10A 16A Ethernet

32 Exercise 5 Power Trips Your first objective as the new data centre manager is to prevent circuit breakers tripping unexpectedly due to loading issues. What would you do and in what order? One day One week One month

33 Establishing a Baseline Know your environment design limits Understand the gaps Roles Knowledge Practices Decide on priorities and actions

34 Baseline troubleshooting 1. Establish control 2. Assess information provided 3. Create plan of action 4. Gather more information if required 5. Stabilise 6. Change process 7. Optimise

35 Room Establish Design Limits Architectural and Structural - Weight Mechanical - Cooling, fire detection /suppression Electrical Power Cabling standards and limitations

36 Controlling the Environment Known design limits A baseline of the current estate Change approval process Forward planning for capacity Regular reviews against limits Maintenance practices Routine Verification on process adoption

37 PROLIANT mic ros ys tems WARNING: DRIVE SURFACES MAY BE HOT ALLOWTO COOL BEFORE TOUCHING A001 A002 A003 A004 A005 A006 A007 A008 A009 A010 A011 A012 A013 A014 A015 A016 A017 A018 A019 A020 A021 A022 A023 A mic ros ys tems mic ros ys tems mic ros ys tems Is this Rack Full? FRONT UK_BIRM_UX08 UK_BIRM_UX07 UK_BIRM_UX06 UK_BIRM_UX05 It depends on Space Weight Power Cooling Connectivity SVR-BHAM Cable Mgmt PP PWR01-07-B PWR01-07-A

38 Data Center Documentation It s common sense that you should know what is in your data centre and how it is configured But achieving this is not so easy Why is it so difficult?

39 Data Center Documentation Commissioning documentation Project plans and designs Testing results Initial systems provision BMS Operational documentation Various sets for ongoing management

40 Exercise 6 Data Center Records The 10 servers have been successfully installed in the data center. What records or systems would you expect to have been updated or modified directly as a result of the additional servers? Data Center A to Z

41 Different Teams, Different Focus Business Processes Departmental, Company Systems Services End user, infrastructure, supplier Applications Service Management Applications PC, server, mainframe, SOA Networks LAN/SAN Mid-range Servers Virtual Infrastructure PCs, Network, Servers, Storage, DBMS Hardware Infrastructure PCs, Network, Servers, UPS, Storage, Other Desktops IMAC Data Centre Fixed Infrastructure (Cabling, Power, Racks, Rooms, Buildings)

42 Different views of a server Rack Position Service impact BLADE_BIRM01 Floor Plan H/W Build BLADE-BIRM01.BLADE-SW2 UK_BIRM01_BLADE-05 UK_BIRM01_BLADE-04 UK_BIRM01_BLADE-12 UK_BIRM01_BLADE-03 UK_BIRM01_BLADE-02 UK_BIRM01_BLADE-10 UK_BIRM01_BLADE-01 UK_BIRM01_BLADE-09 BLADE-BIRM01.BLADE-SW1 Power Supply Network Connections

43 Recommended Information Sets Space Environment (power, cooling) Connectivity (power, networks) Asset and Inventory controls Device management Service management

44 Space Management Space management systems Floor layouts and plans Rack layouts Floor loading Cabinet functions (customer, comms, servers etc.)

45 Environment Management Building management systems Fire, cooling, temperature, power, humidity Power management systems PDU, UPS, power strips Access controls Power distribution diagrams and lists Current and projected power / cooling Hot/cold aisle views

46 Connectivity Management TIA 942 Cabling architecture involving rooms, zones, cabinets, paths

47 Where to Start? Structured cabling only LAN diagrams KVM Architecture Inventory list Storage diagrams Patching spreadsheets KVM WAN diagrams Point to Point Cabling Asset list IIS Architecture Building wiring diagrams Power architecture Computer room layout Edge switches Backbone switches Legacy systems Power distribution Blade switches PDUs Circuit breakers Labelling standards SAN Architecture PABX port mapping LAN Architecture Power strip connections

48 Use the Boston Matrix Method Identifying Focus for a Power Baseline Impact of Power Outage Low High PDU Circuit Breakers UPS Mainframe Storage Firewalls Modems Management Tools Power Strips Servers Networks Lighting Office outlets Low Amount of Connections High

49 Exercise 7 LAN Connectivity Identifying Focus for LAN Baseline Project User Impact of Disconnect Low High 1 3 Low High Amount of Connections Backbone cabling 2. Cabinet/Zone cabling 3. Floor boxes 4. Servers 5. Core Switches 6. Edge Switches 7. Wireless Access Points 8. Routers 9. Firewalls 10.SANs 11.Power strips 12.KVMs 13.IP phones 14. Desktops

50 To Manage Connectivity 1. Document the fixed infrastructure first Backbone, power, vertical 2. The active components Switches, servers, SAN etc. 3. Finally the connectivity Local, path and endpoints

51 Defining the Level of Detail 1. Local patch? 2. End to End path? Patch Panel Patch Panel Patch Panel 3. All devices connected to the switch? Patch Panel Patch Panel

52 Asset Controls Lists of all devices and assets Their current status and location Previous history and audit trail Often combined with maintenance and procurement data Auto-discovery can help, but often limited in value in data centers.

53 Device or Element Management Network, server, storage monitoring Configuration systems Automated deployment / provisioning Network and other architecture diagrams Automated discovery and scanning Backup and failover

54 Service & Risk Management Help or service desk system Project control or workflow system Services maps Devices mapped to critical services Service monitoring tools Billing and charging Recovery planning and testing

55 DC Capacity Management Demand management to capture requests Existing + allocated demand recorded Capacity Plan and database Reporting and trending on Space Power Cooling Network, SAN Port availability Resource (staff) Green reporting

56 Charging and Funding Different perspectives Space Power Cooling Network Ports used Shared Infrastructure Costs and Support Hardware Maintenance Costs and Support Operations Costs and Support

57 Exercise 8 - Reducing Costs Without buying new technology, or changing staffing, you are targeted with improving the cost base of the data center. What management initiatives can you undertake that will reduce direct costs? You have your team, they need direction

58 Meeting the Needs of 3rd Parties SOX, PCI, FSA, auditors, etc. Building & planning requirements Employment and buildings legislation Disability Health and safety Electricity at work Carbon tax And others Insurance What would be sufficient evidence to satisfy them of your controls in most cases?

59 Energy Issues EU Regulations already in place Energy performance of buildings Energy using product directive (colour codes on white goods) WEEE and RoHS directives US Green Building Council LEED Program Leadership in Environmental Design The Green Grid programme EU Code of Conduct for Data Centres Completed 1Q2009 Covers all data center, server and equipment rooms UK draft climate change bill Carbon trading

60 EU Code of Conduct Aim is to inform and stimulate data center owners to reduce energy consumption Understand energy usage Raise awareness Communicate practices which will reduce energy consumption Voluntary at present Available at

61 EU Code of Conduct Measurements against best practices for Cooling Power equipment Other data center equipment Data center utilisation, management & planning IT equipment and services Energy monitoring Temperature and humidity requirements for equipment Suggested limits are 5ºC- 40ºC

62 EU Code of Conduct Additional best practices document is useful for all as it covers Design Operate New equipment and retrofit issues IT equipment selection Power, cooling, storage Monitoring and reporting

63 What presents the greatest risk? Managing Risk

64 Evidence of Conformance Policies covering control, security etc. Evidence of processes that support the policies Change records Build and test records Written material or trails Communications Incident reviews Access lists

65 Access and Security Practices Secure access is a common feature in data centres Access control will depend on organisational issues Building access Room access Cabinet, equipment Layering - multiple needs to authenticate access Many types What you have Card or token What you know Pass code, keypad Who you are Biometric (finger, eye) Use a standard framework (ISO27001, CoBit etc.)

66 Security Impacts Physical access will be more difficult Access requests and tracking Changes will have to be logged at an increased level of detail Verification / audits will be more common to meet auditor / customer needs Without improving the infrastructure documentation, changes will take longer

67 Current Issues Security of data on individual s financial and personal lives is becoming high profile. The data in the data center is valuable! Example ITRC NYPD Pension Fund 3/4/2009 A civilian official of the NYPD s pension fund has been charged with stealing the identities of 80,000 current and retired cops, sources said. He allegedly got into a secret backup-data warehouse on Staten Island last month and walked out with eight tapes packed with Social Security numbers, direct-deposit information for bank accounts, and other sensitive material.

68 Management Maturity Reactive Repeatable Defined Managed Optimised Individual approach Some process, often informal Process documented and explained Process checked and reviewed for gaps Process open to external review and updated regularly What will be different next year?

69 Managing the Infrastructure Planning what needs to be done to achieve a particular result Organising and directing resources. Controlling and making adjustments as needed Motivating all those involved

70 Thank you for your attention Questions or feedback? David Cuthbertson Square Mile Systems Ltd

Managing The Infrastructure Of Data Centers

Managing The Infrastructure Of Data Centers Managing The Infrastructure Of Data Centers David Cuthbertson Square Mile Systems Ltd david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Square Mile Background Develop toolsets, training

More information

Automating Physical Infrastructure Documentation. David Cuthbertson Director

Automating Physical Infrastructure Documentation. David Cuthbertson Director Automating Physical Infrastructure Documentation David Cuthbertson Director david.cuthbertson@assetgen.com www.assetgen.com 1 AssetGen Overview UK based Cirencester, Glos, UK Sister company - Square Mile

More information

Documenting and Managing Infrastructure Connectivity

Documenting and Managing Infrastructure Connectivity Documenting and Managing Infrastructure Connectivity David Cuthbertson Square Mile Systems Ltd david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Square Mile Background Develop toolsets,

More information

Best Practices for Managing Data Centres

Best Practices for Managing Data Centres Best Practices for Managing Data Centres David Cuthbertson Square Mile Systems david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Tel 0870 950 4651 Mob 07717 883177 Best Practices? Guidelines?

More information

Practical Data Centre Management Part 1

Practical Data Centre Management Part 1 Practical Data Centre Management Part 1 David Cuthbertson BSc MBCS MIOD Mobile 07717 883177 david.cuthbertson@squaremilesystems.com 1 Housekeeping Fire evacuation Toilets Refreshments 11:15 Mid morning

More information

Mapping and Auditing Your DevOps Systems

Mapping and Auditing Your DevOps Systems Mapping and Auditing Your DevOps Systems David Cuthbertson, CEO Square Mile Systems Ltd david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Personal Background Personal Experience Industry

More information

How To Document Campus Infrastructure Offices, Hospitals, Universities, Airports, Etc. 29 th November 2012

How To Document Campus Infrastructure Offices, Hospitals, Universities, Airports, Etc. 29 th November 2012 How To Document Campus Infrastructure Offices, Hospitals, Universities, Airports, Etc. 29 th November 2012 David Cuthbertson, Director Square Mile Systems Ltd www.squaremilesystems.com Some Background

More information

Automating IT Asset Visualisation

Automating IT Asset Visualisation P a g e 1 It s common sense to know what IT assets you have and to manage them through their lifecycle as part of the IT environment. In practice, asset management is often separate to the planning, operations

More information

San Francisco Chapter. What an auditor needs to know

San Francisco Chapter. What an auditor needs to know What an auditor needs to know Course Objectives Understand what a data center looks and feels like Know what to look for in a data center and what questions to ask Deepening understanding of controls that

More information

Case Study Automating Data Centre Infrastructure Diagrams

Case Study Automating Data Centre Infrastructure Diagrams Case Study Automating Data Centre Infrastructure Diagrams Daniel Nunn, UK Data Centres Manager ICM Business Continuity ICM Overview Phoenix IT Group 2400 employees Acquired ICM in 2007. Other group companies

More information

Visualising Your CMDB With Visio

Visualising Your CMDB With Visio Visualising Your CMDB With Visio David Cuthbertson Square Mile Systems Square Mile Overview Develop AssetGen toolsets, training and techniques for operational management of complex IT infrastructure Focus

More information

Avoiding High Density Spaghetti - Managing High Density Modular Cabling Systems

Avoiding High Density Spaghetti - Managing High Density Modular Cabling Systems Avoiding High Density Spaghetti - Managing High Density Modular Cabling Systems David Cuthbertson Square Mile Systems Disclaimer All references to manufacturers or products are for illustration only and

More information

Reducing Network Documentation Effort by Visio Automation. David Cuthbertson

Reducing Network Documentation Effort by Visio Automation. David Cuthbertson Reducing Network Documentation Effort by Visio Automation David Cuthbertson Diagrams Are Very Useful! But Not all Diagrams Help! 3 If A Picture Paints a Thousand Words How do we paint a thousand pictures?

More information

Ensure that all windows servers are patched and virus checked to the correct levels and that changes are made in line with ISO standards

Ensure that all windows servers are patched and virus checked to the correct levels and that changes are made in line with ISO standards Job description and person specification Senior ICT Officer Reports to: ICT Manager Purpose This role supports the provision of a high quality and measurable ICT infrastructure support service whilst delivering

More information

Over IP Group. Data Centre Infrastructure Management (DCIM)

Over IP Group. Data Centre Infrastructure Management (DCIM) Over IP Group Data Centre Infrastructure Management (DCIM) Mission To Protect the World s Network Through Innovation Let s Get Connected Over IP Group Agenda The Aim of CenterOS DCIM What is the CenterOS

More information

David Cuthbertson. Mapping Services, Systems & Servers. Chairman BCS-SMSG

David Cuthbertson. Mapping Services, Systems & Servers. Chairman BCS-SMSG David Cuthbertson Chairman BCS-SMSG Mapping Services, Systems & Servers david.cuthbertson@squaremilesystems.com www.squaremilesystems.com Tel 0870 950 4651 Mob 07717 883177 Square Mile Systems 1 Why Map

More information

ROLE DESCRIPTION IT SPECIALIST

ROLE DESCRIPTION IT SPECIALIST ROLE DESCRIPTION IT SPECIALIST JOB IDENTIFICATION Job Title: Job Grade: Department: Location Reporting Line (This structure reports to?) Full-time/Part-time/Contract: IT Specialist D1 Finance INSETA Head

More information

IT MANAGER PERMANENT SALARY SCALE: P07 (R ) Ref:AgriS042/2019 Information Technology Manager. Reporting to. Information Technology (IT)

IT MANAGER PERMANENT SALARY SCALE: P07 (R ) Ref:AgriS042/2019 Information Technology Manager. Reporting to. Information Technology (IT) DESIGNATION Reporting to Division Office Location IT MANAGER PERMANENT SALARY SCALE: P07 (R806 593.00) Ref:AgriS042/2019 Information Technology Manager CEO Information Technology (IT) Head office JOB PURPOSE

More information

Visio Automation for Infrastructure Design and Management. David Cuthbertson Square Mile Systems / AssetGen

Visio Automation for Infrastructure Design and Management. David Cuthbertson Square Mile Systems / AssetGen Visio Automation for Infrastructure Design and Management David Cuthbertson Square Mile Systems / AssetGen A Few Questions Anyone here attended previous Visio workshops? Which is easier and faster to complete?

More information

Manager, Infrastructure Services. Position Number Community Division/Region Yellowknife Technology Service Centre

Manager, Infrastructure Services. Position Number Community Division/Region Yellowknife Technology Service Centre IDENTIFICATION Department Position Title Infrastructure Manager, Infrastructure Services Position Number Community Division/Region 32-11488 Yellowknife Technology Service Centre PURPOSE OF THE POSITION

More information

Data Centre Monitoring. Nexans Cabling Solutions

Data Centre Monitoring. Nexans Cabling Solutions Data Centre Monitoring Nexans Cabling Solutions Agenda Changes in LAN usage & management implications Business issues How LANsense can help Traditional model Remote Access GSM CCTV Storage Wireless IT

More information

DCIM Software and IT Service Management - Perfect Together

DCIM Software and IT Service Management - Perfect Together DCIM Software and IT Service Management - Perfect Together A White Paper from Raritan 2015 Raritan Inc Overview Information Technology is so fundamental to every business today that every organization

More information

The ITIL v.3. Foundation Examination

The ITIL v.3. Foundation Examination The ITIL v.3. Foundation Examination ITIL v. 3 Foundation Examination: Sample Paper 4, version 3.0 Multiple Choice Instructions 1. All 40 questions should be attempted. 2. There are no trick questions.

More information

Visio Automation for Infrastructure Design and Management. David Cuthbertson Square Mile Systems / AssetGen

Visio Automation for Infrastructure Design and Management. David Cuthbertson Square Mile Systems / AssetGen Visio Automation for Infrastructure Design and Management David Cuthbertson Square Mile Systems / AssetGen A Few Questions Anyone here attended the workshops in 2014 and 2016? Which is easier and faster

More information

The Efficient Enterprise. All content in this presentation is protected 2008 American Power Conversion Corporation

The Efficient Enterprise. All content in this presentation is protected 2008 American Power Conversion Corporation Ee The Efficient Enterprise All content in this presentation is protected 2008 American Power Conversion Corporation Keystrokes Kilowatts Heat OUT Electricity IN Need for bandwidth exploding Going hyperbolic!

More information

IT CONTINUITY, BACKUP AND RECOVERY POLICY

IT CONTINUITY, BACKUP AND RECOVERY POLICY IT CONTINUITY, BACKUP AND RECOVERY POLICY IT CONTINUITY, BACKUP AND RECOVERY POLICY Effective Date May 20, 2016 Cross- Reference 1. Emergency Response and Policy Holder Director, Information Business Resumption

More information

SERVICE DEFINITION G-CLOUD 7 THALES PSN REMOTE ACCESS. Classification: Open

SERVICE DEFINITION G-CLOUD 7 THALES PSN REMOTE ACCESS. Classification: Open SERVICE DEFINITION G-CLOUD 7 THALES PSN REMOTE ACCESS Classification: Open Classification: Open ii MDS Technologies Ltd 2015. Other than for the sole purpose of evaluating this Response, no part of this

More information

Networks - Technical specifications of the current networks features used vs. those available in new networks.

Networks - Technical specifications of the current networks features used vs. those available in new networks. APPENDIX V TECHNICAL EVALUATION GUIDELINES Where applicable, the following guidelines will be applied in evaluating the system proposed by a service provider: TABLE 1: HIGH LEVEL COMPONENTS Description

More information

Crises Control Cloud Security Principles. Transputec provides ICT Services and Solutions to leading organisations around the globe.

Crises Control Cloud Security Principles. Transputec provides ICT Services and Solutions to leading organisations around the globe. Crises Control Cloud Security Principles Transputec provides ICT Services and Solutions to leading organisations around the globe. As a provider of these services for over 30 years, we have the credibility

More information

IT Information Security Manager Job Description

IT Information Security Manager Job Description IT Information Security Manager Job Description IT Information Security Manager Responsible to: Accountable to: IT Service Manager Head of IT Services Overall Purpose To provide effective response, protection

More information

Information Services IT Security Policies L. Network Management

Information Services IT Security Policies L. Network Management Information Services IT Security Policies L. Network Management Version 1.1 Last updated: 11th August 2010 Approved by Directorate: 2nd July 2009 Review date: 1st August 2011 Primary owner of security

More information

Green IT (ICT) (Accredited by British Computer Society)

Green IT (ICT) (Accredited by British Computer Society) Green IT (ICT) (Accredited by British Computer Society) 1. What is Green IT? An Overview (4 hrs)* 1.1. Understand the overall need for an organization to adopt a Green IT strategy. (30 - The reality of

More information

Data Centre Solutions Expertly Engineered APC Management Software

Data Centre Solutions Expertly Engineered APC Management Software Data Centre Solutions Expertly Engineered APC Management Software Data Centre Solutions Expertly Engineered A vendor neutral software suite, which provides a unified view and analysis of complex IT physical

More information

REPORT 2015/010 INTERNAL AUDIT DIVISION

REPORT 2015/010 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2015/010 Audit of information and communications technology strategic planning, governance and management in the Investment Management Division of the United Nations Joint

More information

National Infrastructure Group. Paul McLaren (Updated by Russell Fleming and Stuart Graham)

National Infrastructure Group. Paul McLaren (Updated by Russell Fleming and Stuart Graham) Document Control Document Title Infrastructure Standard Version 2.0 Owner Authors National Infrastructure Group Paul McLaren (Updated by Russell Fleming and Stuart Graham) Created date 5 th August 2013

More information

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft The Project Charter Project Title: VDI Data Center Design and Build Project Sponsor: South Alberta Data Centers Inc. (SADC Inc.) Project Customer: The City of Calgary Project Manager: Moe Yousof Document

More information

Government Data Center Modernization

Government Data Center Modernization Government Data Center Modernization Service Standards Focus Group Discussion 13 March 2017 Table of Contents Welcome and Introduction What are standards and their need Key challenges Standard functional

More information

Protecting Critical Infrastructure from Our Bad Habits

Protecting Critical Infrastructure from Our Bad Habits Protecting Critical Infrastructure from Our Bad Habits Jerry L. Bowman, RCDD, RTPM, NTS, CISSP, CPP, CDCDP Square Mile Systems - US Bethel, Ohio, USA David Cuthbertson, MBCS, MIOD Square Mile Systems -

More information

Features and Benefits: dctrack DCIM Operations Solution

Features and Benefits: dctrack DCIM Operations Solution 1 : Asset Auto Discovery Allows for automatic recognition integration into dctrack asset management system for a newly added asset. Automatic recognition of make model of asset makes adding or changing

More information

Altius IT Policy Collection Compliance and Standards Matrix

Altius IT Policy Collection Compliance and Standards Matrix Governance Context and Alignment Policy 4.1 4.4 800-26 164.308 12.4 EDM01 IT Governance Policy 5.1 800-30 12.5 EDM02 Leadership Mergers and Acquisitions Policy A.6.1.1 800-33 EDM03 Context Terms and Definitions

More information

Information Technology General Control Review

Information Technology General Control Review Information Technology General Control Review David L. Shissler, Senior IT Auditor, CPA, CISA, CISSP Office of Internal Audit and Risk Assessment September 15, 2016 Background Presenter Senior IT Auditor

More information

CCISO Blueprint v1. EC-Council

CCISO Blueprint v1. EC-Council CCISO Blueprint v1 EC-Council Categories Topics Covered Weightage 1. Governance (Policy, Legal, & Compliance) & Risk Management 1.1 Define, implement, manage and maintain an information security governance

More information

Changing the way companies run their data centers

Changing the way companies run their data centers Infrastructure Management & Monitoring for Business-Critical Continuity TM Changing the way companies run their data centers The Aperture TM Suite Optimize performance of your data center without COmpromising

More information

Altius IT Policy Collection Compliance and Standards Matrix

Altius IT Policy Collection Compliance and Standards Matrix Governance Context and Alignment Policy 4.1 4.4 800-26 164.308 12.4 EDM01 IT Governance Policy 5.1 800-30 12.5 EDM02 Leadership Mergers and Acquisitions Policy A.6.1.1 800-33 EDM03 Context Terms and Definitions

More information

David Palmer-Stevens System Integrator Manager EMEA Tel: Mob:

David Palmer-Stevens System Integrator Manager EMEA Tel: Mob: David Palmer-Stevens System Integrator Manager EMEA Tel: +208 601 7318 Mob: +447703194479 email: gb-dps@panduit.com The Next $1Million Opportunity Larry Ellison CEO Oracle You need an Inflection Point

More information

Applications/Data To Include in Survey (include applications that meet one or more of the following criteria)

Applications/Data To Include in Survey (include applications that meet one or more of the following criteria) Objective of Survey The purpose of this survey is to identify and understand 1) the nature of critical and sensitive campus-wide applications and/or data, 2) where the data is located, 3) how the data

More information

HOW WELL DO YOU KNOW YOUR IT NETWORK? BRIEFING DOCUMENT

HOW WELL DO YOU KNOW YOUR IT NETWORK? BRIEFING DOCUMENT HOW WELL DO YOU KNOW YOUR IT NETWORK? BRIEFING DOCUMENT ARE YOU REALLY READY TO EXECUTE A GLOBAL IOT STRATEGY? Increased demand driven by long-term trends of the Internet of Things, WLAN, connected LED

More information

Predictive Resilience: Leveraging Integrated DCIM to Reduce Data Center Downtime

Predictive Resilience: Leveraging Integrated DCIM to Reduce Data Center Downtime July 17, 2013 Predictive Resilience: Leveraging Integrated DCIM to Reduce Data Center Downtime siemens.com/answers Predictive Resilience Table of content What is DCIM & Its Business Value Extract Maximum

More information

Overcoming the Challenges of Server Virtualisation

Overcoming the Challenges of Server Virtualisation Overcoming the Challenges of Server Virtualisation Maximise the benefits by optimising power & cooling in the server room Server rooms are unknowingly missing a great portion of their benefit entitlement

More information

Free ITIL Foundation Exam Paper 40 Questions 60 Minutes Allowed. Minimum of 26/40 to Pass. With the Compliments of www.itservicesuccess.com Good Luck!! GIVE YOURSELF THE UNFAIR ADVANTAGE! MULTIPLE CHOICE

More information

APC by Schneider Electric Elite Data Centre Partner

APC by Schneider Electric Elite Data Centre Partner Data Centre Solutions...energy efficient by design APC by Schneider Electric Elite Data Centre Partner APC s leading Elite Data Centre Solutions Partner providing customers with expert advice, integration

More information

DCIM Solutions to improve planning and reduce operational cost across IT & Facilities

DCIM Solutions to improve planning and reduce operational cost across IT & Facilities DCIM Solutions to improve planning and reduce operational cost across IT & Facilities Presented by: Chi Sen, Director, Data Centre Software Solutions, APJ & EMEA Schneider Electric Data Center Solutions

More information

Certified Information Systems Auditor (CISA)

Certified Information Systems Auditor (CISA) Certified Information Systems Auditor (CISA) 1. Domain 1 The Process of Auditing Information Systems Provide audit services in accordance with IT audit standards to assist the organization in protecting

More information

Survey and Audit Service Schedule. Airflow and Thermal Imaging Survey Service Schedule. Data Centre Solutions Expertly Engineered

Survey and Audit Service Schedule. Airflow and Thermal Imaging Survey Service Schedule. Data Centre Solutions Expertly Engineered Survey and Audit Service Schedule Airflow and Thermal Imaging Survey Service Schedule Data Centre Solutions Expertly Engineered Consult optimisation, audit and survey services Data Centre Services Workspace

More information

1.0 Executive Summary. 2.0 Features and Benefits

1.0 Executive Summary. 2.0 Features and Benefits Table of Contents 1.0 EXECUTIVE SUMMARY 2.0 FEATURES AND BENEFITS 3.0 DETAILS OF SERVICE 4.0 Deliverable 5.0 Exclusions 6.0 SCOPE OF RESPONSIBILITY 7.0 PROJECT WORK DETAILS 8.0 ORDERING INFORMATION 9.0

More information

Server room guide helps energy managers reduce server consumption

Server room guide helps energy managers reduce server consumption Server room guide helps energy managers reduce server consumption Jan Viegand Viegand Maagøe Nr. Farimagsgade 37 1364 Copenhagen K Denmark jv@viegandmaagoe.dk Keywords servers, guidelines, server rooms,

More information

HP 3PAR Storage System Installation and Startup Service

HP 3PAR Storage System Installation and Startup Service HP 3PAR Storage System Installation and Startup Service HP Care Pack Services Technical data For smooth startup, the HP 3PAR Storage System Installation and Startup Service provides deployment of your

More information

Data Center Infrastructure Management (DCIM) Demystified

Data Center Infrastructure Management (DCIM) Demystified software is quickly becoming the core engine of data center operations. Only 5 years ago, manual spreadsheets, sometimes supplemented with Visio diagrams, were accepted as the default tools for data center

More information

Product Brochure Eaton 93PR UPS kw

Product Brochure Eaton 93PR UPS kw Product Brochure Eaton 93PR UPS 25-200 kw For more than 50 years, Eaton has been safeguarding the critical systems of businesses across the globe. Whether protecting a single desktop or the largest data

More information

WELCOME ISO/IEC 27001:2017 Information Briefing

WELCOME ISO/IEC 27001:2017 Information Briefing WELCOME ISO/IEC 27001:2017 Information Briefing Denis Ryan C.I.S.S.P NSAI Lead Auditor Running Order 1. Market survey 2. Why ISO 27001 3. Requirements of ISO 27001 4. Annex A 5. Registration process 6.

More information

Automating for Agility in the Data Center. Purnima Padmanabhan Jeff Evans BMC Software

Automating for Agility in the Data Center. Purnima Padmanabhan Jeff Evans BMC Software Automating for Agility in the Data Center Purnima Padmanabhan Jeff Evans BMC Software 9/5/2006 Agenda The Situation Challenges Objectives BMC Solution for Data Center Closed-Loop Change Data Center Optimization

More information

DCIM Data Center Infrastructure Management

DCIM Data Center Infrastructure Management DCIM Data Center Infrastructure Management Part 3 Operational Management Moves Adds and Changes & Electrical Infrastructure November 5, 2013 Presented by Julius Neudorfer Sponsored by Today s Topics Operational

More information

Business Continuity Management: How to get started. Presented by: Tony Drewitt, Managing Director IT Governance Ltd 19 April 2018

Business Continuity Management: How to get started. Presented by: Tony Drewitt, Managing Director IT Governance Ltd 19 April 2018 Business Continuity Management: How to get started Presented by: Tony Drewitt, Managing Director IT Governance Ltd 19 April 2018 Introduction Tony Drewitt - Managing Director: IT Governance UK and EU One

More information

HP MSA Family Installation and Startup Service

HP MSA Family Installation and Startup Service Technical data HP MSA Family Installation and HP Services Service benefits Allows your IT resources to stay focused on their core tasks and priorities Reduces implementation time, impact, and risk to your

More information

Information Security Policy

Information Security Policy April 2016 Table of Contents PURPOSE AND SCOPE 5 I. CONFIDENTIAL INFORMATION 5 II. SCOPE 6 ORGANIZATION OF INFORMATION SECURITY 6 I. RESPONSIBILITY FOR INFORMATION SECURITY 6 II. COMMUNICATIONS REGARDING

More information

Los Anseles W Department of 5* Water & Power

Los Anseles W Department of 5* Water & Power Los Anseles W Department of 5* Water & Power 3D RESOLUTION NO. BOARD LETTER APPROVAL DAVID H. WRIGHT MARCIE L. EDWARDS Chief Operating Officer General Manager DATE: May 26, 2016 SUBJECT: Lease Agreement

More information

Optimize Your Data Center. Gary Hill VP, Business Development DVL Group, Inc.

Optimize Your Data Center. Gary Hill VP, Business Development DVL Group, Inc. Optimize Your Data Center Gary Hill VP, Business Development DVL Group, Inc. Data Center Age Profile Gartner Group Survey Legacy Data Centers Challenges Under Powered - Room or Racks Inadequate Air Delivery

More information

KantanMT.com. Security & Infra-Structure Overview

KantanMT.com. Security & Infra-Structure Overview KantanMT.com Security & Infra-Structure Overview Contents KantanMT Platform Security... 2 Customer Data Protection... 2 Application Security... 2 Physical and Environmental Security... 3 ecommerce Transactions...

More information

University of Pittsburgh Security Assessment Questionnaire (v1.7)

University of Pittsburgh Security Assessment Questionnaire (v1.7) Technology Help Desk 412 624-HELP [4357] technology.pitt.edu University of Pittsburgh Security Assessment Questionnaire (v1.7) Directions and Instructions for completing this assessment The answers provided

More information

Advent IM Ltd ISO/IEC 27001:2013 vs

Advent IM Ltd ISO/IEC 27001:2013 vs Advent IM Ltd ISO/IEC 27001:2013 vs 2005 www.advent-im.co.uk 0121 559 6699 bestpractice@advent-im.co.uk Key Findings ISO/IEC 27001:2013 vs. 2005 Controls 1) PDCA as a main driver is now gone with greater

More information

EU Code of Conduct on Data Centre Energy Efficiency. Endorser Guidelines and Registration Form. Version 3.1.0

EU Code of Conduct on Data Centre Energy Efficiency. Endorser Guidelines and Registration Form. Version 3.1.0 EUROPEAN COMMISSION DIRECTORATE-GENERAL JRC JOINT RESEARCH CENTRE Institute for Energy Renew able Energies Unit Ispra, 1 st January 2016 EU Code of Conduct on Data Centre Energy Efficiency Endorser Guidelines

More information

Data Center Power Savings

Data Center Power Savings Data Center Power Savings Data Center Power Savings Keith Mastrian, Regional Sales Manager, Raritan Data center power usage effectiveness (PUE), developed by The Green Grid, has received a lot of attention.

More information

SAS SOLUTIONS ONDEMAND

SAS SOLUTIONS ONDEMAND DECEMBER 4, 2013 Gary T. Ciampa SAS Solutions OnDemand Advanced Analytics Lab Birmingham Users Group, 2013 OVERVIEW SAS Solutions OnDemand Started in 2000 SAS Advanced Analytics Lab (AAL) Created in 2007

More information

The ITIL Foundation Examination

The ITIL Foundation Examination The ITIL Foundation Examination Sample Paper A, version 5.1 Multiple Choice Instructions 1. All 40 questions should be attempted. 2. All answers are to be marked on the answer grid provided. 3. You have

More information

Help your Cisco customers defend against downtime and reduce costs

Help your Cisco customers defend against downtime and reduce costs Help your Cisco customers defend against downtime and reduce costs Why and when to sell Eaton Power Management solutions Incorporating power management with Cisco solutions boosts your sales revenue, while

More information

Administration and Data Retention. Best Practices for Systems Management

Administration and Data Retention. Best Practices for Systems Management Administration and Data Retention Best Practices for Systems Management Agenda Understanding the Context for IT Management Concepts for Managing Key IT Objectives Aptify and IT Management Best Practices

More information

Position Description IT Auditor

Position Description IT Auditor Position Title IT Auditor Position Number Portfolio Performance and IT Audit Location Victoria Supervisor s Title IT Audit Director Travel Required Yes FOR OAG HR USE ONLY: Approved Classification or Leadership

More information

1.0 Executive Summary. 2.0 Available Features & Benefits

1.0 Executive Summary. 2.0 Available Features & Benefits Statement Of Work Energy Management Services Table of Contents 1.0 Executive Summary 2.0 Available Features & Benefits 3.0 Assessment Deliverables Selection 4.0 On Site Assessment Activities 5.0 Exclusions

More information

RFP Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service

RFP Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service RFP 2017 845 Annex A Terms of Reference UNHCR HQ Data Centre Colocation Service Version 1 Contents Project objectives... 1 Background... 1 Scope... 1 Timeframe and Cost... 4 Stakeholders, roles and responsibilities...

More information

Comprehensive Data Center Energy Management Solutions

Comprehensive Data Center Energy Management Solutions FROM INSIGHT TO EFFICIENCY: Comprehensive Data Center Energy Management Solutions Since 1995, facility managers and BAS professionals have relied on the Niagara framework to provide full convergence of

More information

Marine Institute Job Description

Marine Institute Job Description Marine Institute Job Description Position Contract Service Group Location Temporary Systems Administrator Team Leader Temporary Specified Purpose contract for a duration of up to 3 years Ocean Science

More information

TARGET2-SECURITIES INFORMATION SECURITY REQUIREMENTS

TARGET2-SECURITIES INFORMATION SECURITY REQUIREMENTS Target2-Securities Project Team TARGET2-SECURITIES INFORMATION SECURITY REQUIREMENTS Reference: T2S-07-0270 Date: 09 October 2007 Version: 0.1 Status: Draft Target2-Securities - User s TABLE OF CONTENTS

More information

Data Protection. Practical Strategies for Getting it Right. Jamie Ross Data Security Day June 8, 2016

Data Protection. Practical Strategies for Getting it Right. Jamie Ross Data Security Day June 8, 2016 Data Protection Practical Strategies for Getting it Right Jamie Ross Data Security Day June 8, 2016 Agenda 1) Data protection key drivers and the need for an integrated approach 2) Common challenges data

More information

Power Monitoring in the Data Centre

Power Monitoring in the Data Centre Power Monitoring in the Data Centre Fixed or Wireless Steve Strange RCDD ANIXTER INTERNATIONAL Agenda Energy Consumption Case Study Reasons to Monitor Power Monitoring Environmental Monitoring Asset Tags

More information

1.0 Executive Summary

1.0 Executive Summary Statement of Work - 1 - Power and Cooling Assessment for Data Center Professional Services Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service

More information

PLAYBOOK. How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy

PLAYBOOK. How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy PLAYBOOK F O R C H A N G E How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy The world is becoming more digital every day. The demand for feature-rich,

More information

IaaS Buyer s Checklist.

IaaS Buyer s Checklist. Problem Solved IaaS Buyer s Checklist. Yes it s another checklist, but this one s actually useful. 2 Problem Solved Service levels. Does the provider offer your required SLA/SLG? Example: 99.9%, 99.95%,100%

More information

RAMP DCIM Data Center Infrastructure Management Software

RAMP DCIM Data Center Infrastructure Management Software RAMP DCIM Data Center Infrastructure Management Software RFP TEMPLATE 1-866-612-3637 SALES@TUANGRU.COM TUANGRU.COM DCIM RFP TEMPLATE Dear Sir or Madam, Your company has been invited to submit your company

More information

The European Programme for Energy Efficiency in Data Centres: The Code of Conduct

The European Programme for Energy Efficiency in Data Centres: The Code of Conduct The European Programme for Energy Efficiency in Data Centres: The Code of Conduct Paolo Bertoldi European Commission DG JRC Institute for Energy and Transport 1 Why Data Centres? Continuing demand for

More information

Implementing ITIL v3 Service Lifecycle

Implementing ITIL v3 Service Lifecycle Implementing ITIL v3 Lifecycle WHITE PAPER introduction GSS INFOTECH IT services have become an integral means for conducting business for all sizes of businesses, private and public organizations, educational

More information

EX0-101_ITIL V3. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0. Exin EX0-101

EX0-101_ITIL V3.  Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0. Exin EX0-101 EX0-101_ITIL V3 Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ Exin EX0-101 ITIL Foundation V 3.0 & ITIL Foundation Version: 8.0 Exin EX0-101 Exam Topic

More information

Network Performance, Security and Reliability Assessment

Network Performance, Security and Reliability Assessment Network Performance, Security and Reliability Assessment Presented to: CLIENT NAME OMITTED Drafted by: Verteks Consulting, Inc. 2102 SW 20 th Place, Suite 602 Ocala, Fl 34474 352-401-0909 ASSESSMENT SCORECARD

More information

Information Technology Procedure IT 3.4 IT Configuration Management

Information Technology Procedure IT 3.4 IT Configuration Management Information Technology Procedure IT Configuration Management Contents Purpose and Scope... 1 Responsibilities... 1 Procedure... 1 Identify and Record Configuration... 2 Document Planned Changes... 3 Evaluating

More information

Data Sheet The PCI DSS

Data Sheet The PCI DSS Data Sheet The PCI DSS Protect profits by managing payment card risk IT Governance is uniquely qualified to provide Payment Card Industry (PCI) services. Our leadership in cyber security and technical

More information

Why you should adopt the NIST Cybersecurity Framework

Why you should adopt the NIST Cybersecurity Framework Why you should adopt the NIST Cybersecurity Framework It s important to note that the Framework casts the discussion of cybersecurity in the vocabulary of risk management Stating it in terms Executive

More information

Manchester Metropolitan University Information Security Strategy

Manchester Metropolitan University Information Security Strategy Manchester Metropolitan University Information Security Strategy 2017-2019 Document Information Document owner Tom Stoddart, Information Security Manager Version: 1.0 Release Date: 01/02/2017 Change History

More information

IT Governance ISO/IEC 27001:2013 ISMS Implementation. Service description. Protect Comply Thrive

IT Governance ISO/IEC 27001:2013 ISMS Implementation. Service description. Protect Comply Thrive IT Governance ISO/IEC 27001:2013 ISMS Implementation Service description Protect Comply Thrive 100% guaranteed ISO 27001 certification with the global experts With the IT Governance ISO 27001 Implementation

More information

"Charting the Course... ITIL 2011 Managing Across the Lifecycle ( MALC ) Course Summary

Charting the Course... ITIL 2011 Managing Across the Lifecycle ( MALC ) Course Summary Course Summary Description ITIL is a set of best practices guidance that has become a worldwide-adopted framework for IT Service Management by many Public & Private Organizations. Since early 1990, ITIL

More information

Let Energy Monitoring Solutions Do the Heavy Lifting

Let Energy Monitoring Solutions Do the Heavy Lifting Let Energy Monitoring Solutions Do the Heavy Lifting Let Energy Monitoring Solutions Do the Heavy Lifting Duke Dunsford & John Forsyth Schneider Electric This session is eligible for 1 Contact Hour. For

More information

PIM Pretium Intelligent Management

PIM Pretium Intelligent Management Cable Systems PIM Pretium Intelligent Management Dirk van Moll Private networks, EMEA What is Intelligent Patching? Discovering, documenting, monitoring, and managing the physical network connections and

More information