1 Optimizing the Existing Building Cx Process: Integrating EBCx into ESPCs Lia Webster, P.E. Senior Engineer Portland Energy Conservation, Inc.
2 AIA Quality Assurance Learning Objectives 1. Identify ways a provider/owner can maximize the benefits of performance contracting by incorporating existing building Cx at the onset of the project. 2. Understand the challenges around including existing building Cx with performance contracting and how it can improve the effectiveness of both projects. 3. Review the current legislative drivers of existing building commissioning in the federal sector as well as current guidelines.
3 Terms: EBCx = RCx The Building Commissioning Association s definition: EBCx: a comprehensive term that encompasses retro-commissioning, recommissioning and ongoing commissioning Federal Government Recommissioning & Retro-Commissioning
4 Presentation Overview Federal drivers of EE and EBCx Legislative background Performance Contracting for Federal facilities Understanding the ESPC process Integrating EBCx into ESPCs Timing, approach, persistence Existing guidance Recent projects Lessons learned What s next Current legislation
5 Federal Drivers of EE & EBCx Legislative mandates for energy conservation at Federal Facilities: National Energy Conservation Policy Act Energy Policy Act of 1992 EPACT 2005 EO EISA Recovery and Reinvestment Act American Clean Energy and Security Act of 2009?
6 Funding Federal Energy Projects 4 primary funding mechanisms: Appropriated funds from Congress Energy Savings Performance Contracts (ESPC) - $2,300 million invested projects Utility Energy Services Contracts (UESC) - $600 million invested - 45 utilities + Energy Incentive Programs - Utility energy efficiency & demand response programs Federal Energy Management Program (FEMP) DOE programs to help Federal agencies manage energy
7 Energy Savings Performance Contracts Federal ESPC mechanisms: DOE s Super ESPC - $1,300 million invested ~ 12 Energy Service Contractors (ESCo) Army ESPC Air Force ESPC IDIQs format: Indefinite Delivery Indefinite Quantity Base contract Defines process, roles and responsibilities, reporting formats Pre-approved contractors
8 Super ESPCs Year Project Count Project Investment Contract Price Guaranteed Cost Savings $6,602,089 $15,018,137 $17,188, $40,934,613 $94,431,913 $95,513, $62,055,135 $135,619,538 $136,639, $121,285,179 $276,057,256 $272,624, $96,939,177 $313,744,546 $314,251, $251,765,121 $543,487,546 $553,366, $22,319,540 $52,330,073 $54,835, $72,184,223 $198,707,333 $199,154, $164,351,251 $413,254,189 $418,288, $144,385,872 $353,891,202 $358,500, $244,335,445 $594,168,698 $607,671,372 Grand Tot 195 $1,227,157,645 $2,990,710,431 $3,028,034,572
9 What Is Performance Contracting? Building owners fund capital improvements through energy savings Capital investment is paid back over time from cost savings A service provider contractually guarantees a project s technical performance / energy savings Energy Services Company (ESCO)
10 Cash Flow for ESPCs Financing costs Ongoing services Possible issues: Load Creep Degradation of savings Equipment life Up to 25 years
11 Energy Services Companies (ESCOs): Provide turn-key services Develop, design, and finance energy efficiency projects Install the equipment Measure, monitor, and verify the project's energy savings Assume the risk that the project will save the amount of energy guarantee Repaid through the avoided energy costs
12 Typical ESCO Measures: Upgrades Focus on equipment replacement / capital improvements Lighting Energy Management & Control System (EMCS) Boilers Chillers Variable Speed Drives (VSDs) Motors
13 EBCx Findings: Operational Issues Equipment scheduling Equipment setpoints & staging Simultaneous heating and cooling Economizer operation Design / installation issues EBCx looks deeply for root cause and solutions
14 Difference between EBCx and ESPCs EBCx: Emphasizes low cost energy improvements Does not typically recommend retrofits Focuses on system integration Relies on measurement and functional testing Has more emphasis on nonenergy benefits, training
15 Processes are complementary! ESPC Scoping Initial Proposal Notice of Intent to Award Investigation EBCx Scoping Investigation Contract Award Design & Implementation Commissioning Hand-off &Training Ongoing M&V O&M Implementation Commissioning Hand-off &Training Ongoing O&M
16 EBCx + ESPC Adds work, cost, and time to ESPC during investigation phase Viable EBCx measures = 1 ECM Requires additional expertise from contractor EBCx adds significant complexity Produces an additional report & information EBCx report should include all deficiencies How systems are currently operating Results in deeper, more comprehensive measures, and useful operating documentation New sequences of operation More successful projects!
17 Federal ESPCs including EBCx Harold Washington Social Security Building
18 An Great ESPC + EBCx Project! Project 690,000 sq ft 10 story all electric building Constructed 1978 Controls upgrade 1995 Customer requested EBCx evaluation in initial project scoping Knew they had a problem Internal project champion Pushed and drug others along
19 If only they were all this good Overly complex systems Didn t fully understand the systems Original design docs Complete drawings were available Some obvious opportunities Complex sequences - some were overridden Design intent not understood Insufficient controls infrastructure Extensive comfort complaints Talented engineering team EBCx experienced firm Calibrations; Point to point (5,000 of 14,000) 2+ months on site Extra foot work to overcome challenges Unbiased controls specialists
20 Project Findings Chiller plant improvements Abandon ice making / glycol loop Re-instate water-side heat recovery ECM design was dramatically impacted by EBCx! Retro-Commissioning Controls communications upgrade Implement CO2 ventilation controls Re-instate air-side heat recovery VAV set-points Optimized schedules / start Lighting controls Lighting Retrofits Controls
21 Keys to this Successful Project! FEMP provided expert support Utilized DOE staff and guidance Excellent documentation and training was provided New sequences of operation for all systems Ongoing training Included on-going Cx as part of the contract Good M&V and O&M oversight plan ESCO checked systems weekly Automated data collection with flags Agency supervised 3 rd party contractor Good relations = additional work
22 FEMP s Guidance Existing Guidance from DOE: financing/superespcs_mvresou rces.html 1) Example Retrocommissioning Scope of Work 2) Including Retro-Commissioning in Federal Energy Saving Performance Contracts Timing, M&V, Pricing, Contractual
23 Pitfalls to Avoid Clear scope of work not provided early in project development phase Large campus without focused data collection No EBCx champion Provides coordination and buy-in Insufficient baseline data collection Basis for savings estimates/ guarantee Insufficient EBCx savings to fund project Costly controls upgrade is not EBCx Ongoing EBCx activities not included Annual M&V is not EBCx
24 Benefits of EBCx as part of ESPC EBCx Saving buy-down capital improvements Paybacks can reduce contract length Historic energy baseline is unaffected Baseline has more robust documentation Deeper understanding of systems / issues May affect scope of retrofit Integration of new equipment into old systems Prevents operational hindrances
25 Lessons Learned EBCx needs to self-pay + Scoping viable opportunities key Controls upgrades sometime sold as EBCx Increased baseline data collection improves quality of capital measures More in-depth understanding of systems May change other ECMs Persistence issues related to EBCx must be addressed Ongoing M&V activities is great mechanism Additional monitoring required for persistence Attention to EBCx improves persistence of all measures
26 Other Key Issues EBCx & ESPC Timing EBCx with ESPC won t affect baseline Funding for EBCx alone may be difficult Ongoing O&M Regular preventative maintenance Staff training M&V approaches Selecting the variables to meter and monitor Data management Balancing technical rigor with cost Documentation & Reporting Sufficiently defining the baseline Tracking performance Keeping up with facility changes
27 ESPC Excellent Vehicle for EBCx Persistence Persistence of savings Long term contract - O&M and R&R issues are major concerns for both Requirement for M&V - Provides contractor an on-going connection to project - Leverage M&V activities to ensure persistence» Often the missing element for EBCx projects
28 EISA 2007 High Performance Federal Buildings S 431 & S 432: Increases energy conservation goals Defines commissioning, recommissioning & retrocommissioning Enhances energy reporting requirements Mandates EE & EBCx opportunities assessed 25% of facilities per year, each facility at east every 4 years Excludes most facilities < 50K sq ft and all <25k Implementation within 2 years Web-based tracking cost & savings M&V of project savings Facility benchmarking
29 EISA 2007 Interpretation EBCx Requirements Assess re/retrocommissioning measures: Step 1: Initial Assessment Conduct facility walk-through - 4 to 8 hours Comprehensive data collection & analysis - Is equipment operating to spec and design intent Step 2: Detailed Re/Retrocommissioning Evaluation Efforts take from 1 to 4 days Identify operations & maintenance optimizations Capital improvements may be identified
30 EISA 2007 ESPC Related S : ESPC authorization made permanent Removes sunset provision of 2016 Removes requirements for congressional notification Allows financing flexibility Appropriated funds allowed Prevents agencies from limiting ESPC lengths Agency retains all savings Study non-building applications for ESPC
31 Conclusions Incorporating EBCx with ESPCs improves both processes Results in deeper, more comprehensive projects Importance of scoping EBCx opportunities Persistence of EBCx measures enhanced with ESPC M&V facilitates ongoing commissioning activities New legislation is facilitating EBCx at Federal facilities ESPC is most likely avenue for EBCx implementation
32 AIA Quality Assurance Portland Energy Conservation, Inc is a registered provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members are available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
33 Thank you! Lia Webster Portland Energy Conservation Inc.
Critical Facilities Existing Building Commissioning (EBCx)
Critical Facilities Existing Building Commissioning (EBCx) Tony DiLeonardo LEED AP, CxA President Wick Fisher White Tracey Jumper CCP President Jump Start Building Commissioning, LLC AIA Quality Assurance
More informationDOE Energy Savings Performance Contracts (ESPCs) and ESPC ENABLE
Session: Third-Party Financing Options DOE Energy Savings Performance Contracts (ESPCs) and ESPC ENABLE Doug Culbreth Oak Ridge National Laboratory August 11, 2016 Rhode Island Convention Center Providence,
More informationESPC Overview. Definition and Need. Program Description. Questions and Answers. Curt Murdock & Rod Bridgeman August 6
Energy Savings Performance Contracting (ESPC) US Army Corps of Engineers Engineering and Support Center, Huntsville Curt Murdock, Energy Branch Chief Curt.e.murdock@usace.army.mil Roderick Bridgeman, Mechanical
More informationDoing More with Less: Maintaining, Operating, and Improving your BMS. Bernard Keister, V PE Senior Engineer Guttmann & Blaevoet Consulting Engineers
Doing More with Less: Maintaining, Operating, and Improving your BMS Bernard Keister, V PE Senior Engineer Guttmann & Blaevoet Consulting Engineers AIA Quality Assurance Learning Objectives 1. Develop
More informationGSA Deep Energy Retrofit Program
Public Private Partnerships GSA Deep Energy Retrofit Program Kinga Porst Hydras U.S. General Services Administration August 15, 2017 Tampa Convention Center Tampa, Florida GSA Portfolio 376 million square
More informationIT Transformation Through ESPCs
June 27, 2013 IT Transformation Through ESPCs Restricted Siemens AG 2013. All rights reserved. siemens.com/answers Contents Integration of IT with Facilities ESPCs as Related to Data Centers Measurement
More informationPresentation. Guaranteed Energy Savings Performance Project
Presentation Guaranteed Energy Savings Performance Project Greg Spiro, PE, CEM, LEED-AP Georgia Institute of Technology Senior Mechanical Engineer Facilities Design & Construction 470-351-9867151 6th Street
More informationDriving Proactive Facility Operations with Automated HVAC Diagnostics
Driving Proactive Facility Operations with Automated HVAC Diagnostics Turn HVAC Data into Actionable Information AKA Monitoring Based Commissioning Ongoing Commissioning Automated Fault Detection & Diagnostics
More informationBest Practices in Existing Building Commissioning
Best Practices in Existing Building Commissioning Carl E. Lundstrom, P. E., CCP Federal Solutions Manager E M C Engineers, Inc. Subsidiary of Eaton Corporation FEDERAL UTILITY PARTNERSHIP WORKING GROUP
More informationKentucky Community and Technical College System ESPC Initiative
Kentucky Community and Technical College System ESPC Initiative Energy Services Coalition Conference August 24, 2016 Presented by: Billie Hardin KCTCS Sustainability Project Manager OVERVIEW KCTCS Background
More informationTrack 11, Session 4 -- Campus Utility Distribution Systems
Track 11, Session 4 -- Campus Utility Distribution Systems ESCO Contract Vehicle approaches to implement VA requirements at VISN 21 Steven T. Smith, Senior Director, Engineering Federal Energy Systems
More informationCommercial Retro-Commissioning Program Manual for 2016 SECTION 1
Commercial Retro-Commissioning Program Manual for 2016 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.
More informationRetro-Commissioning of Data Centers
Retro-Commissioning of Data Centers Agenda Unique traits of Data Centers (DCs) Benefits of Retro-Cx DCs Suitable candidates for Retro-Cx Phases of Retro-Cx Additional considerations for DCs 2 Unique Traits
More informationA Case Study in Fuel Cell Market Transformation
A Case Study in Fuel Cell Market Transformation Potential Opportunities for Fuel Cell Power at DOE Germantown Data Center * : The Pros and Cons of Energy Savings and Service Agreements Amy Manheim Market
More informationWORKSHOP REPORT; 360 PERSPECTIVE ON DEEP ENERGY RETROFITS
EXECUTIVE SUMMARY WORKSHOP REPORT; 360 PERSPECTIVE ON DEEP ENERGY RETROFITS IMAGE COURTESY OF SHUTTERSTOCK Contact: Cara Carmichael (ccarmichael@rmi.org) Kinga Porst (kinga.porst@gsa.gov) 1 EXECUTIVE SUMMARY
More informationEnergy Action Plan 2015
Energy Action Plan 2015 Purpose: In support of the Texas A&M University Vision 2020: Creating a Culture of Excellence and Action 2015: Education First Strategic Plan, the Energy Action Plan (EAP) 2015
More informationEnergy Solutions for Buildings
Energy Solutions for Buildings Making energy safe, reliable, efficient, productive and green Make the most of your energy SM 1 Solutions to enable and sustain energy savings Technology is crucial to make
More informationUESCs and VA s Performance Contracting Program Lara Spader Department of Veterans Affairs August 17, 2017
What the Government Needs from the Utility UESCs and VA s Performance Contracting Program Lara Spader Department of Veterans Affairs August 17, 2017 Tampa Convention Center Tampa, Florida Agenda Resiliency
More informationEffective energy management services for all your needs
Effective energy management services for all your needs Discover our complete services offer Make the most of your energy sm Energy Challenge Supply Costs Sustainability Pressures Demand Efficiency When
More informationESC Conference: Energy Savings and Performance-Based Contracting Investment Initiative Update. Timothy D. Unruh PhD, PE, CEM.
ESC Conference: Energy Savings and Performance-Based Contracting Investment Initiative Update July 29, 2014 Timothy D. Unruh PhD, PE, CEM Program Manager DOE FEMP 1 Energy Efficiency and Renewable Energy
More informationEnergy Performance Tracking: Tools and Best Practices
Energy Performance Tracking: Tools and Best Practices Hannah Friedman, PE Technical Research Director Dave Moser, PE Senior Engineer Mark Effinger, Engineer Portland Energy Conservation, Inc. AIA Quality
More informationMetering Best Practices: A Guide to Achieving Utility Resource Efficiency Greg Sullivan PE, LEED AP Principal Engineer Efficiency Solutions
Metering Best Practices: A Guide to Achieving Utility Resource Efficiency Greg Sullivan PE, LEED AP Principal Engineer Efficiency Solutions AIA Quality Assurance Learning Objectives: 1. Present the importance
More informationRetro-Cx Program at Air National Guard Bases Civil Engineering Technical Service Center (CETSC) Presenter: Kurt Blemel ARCADIS/Malcolm Pirnie May 11,
Retro-Cx Program at Air National Guard Bases Civil Engineering Technical Service Center (CETSC) Presenter: Kurt Blemel ARCADIS/Malcolm Pirnie May 11, 2011 CETSC Initiative Description Utilize industry
More informationMaintaining Efficiency using Your Building Controls and Automation
Session: Building Controls and Automation Maintaining Efficiency using Your Building Controls and Automation Carl E. Lundstrom, PE, CCP Dewberry Design Builders Inc. August 10, 2016 Rhode Island Convention
More informationENERGY EFFICIENCY FINANCE
ENERGY EFFICIENCY FINANCE Energy Efficiency Indicator Survey and PACE 1 Copyright 2011 Johnson Controls, Inc. JOHNSON CONTROLS 140,000 Employees Multi-industry Founded 1885 Building Efficiency Creating
More informationAgenda. What would a 30% reduction in energy use do for your budget? The next generation of energy and infrastructure projects in MI
What would a 30% reduction in energy use do for your budget? The next generation of energy and infrastructure projects in MI Presented by: Scott Mason 1 Agenda Traditional energy efficiency Next generation
More informationAnnual Report for the Utility Savings Initiative
Report to the North Carolina General Assembly Annual Report for the Utility Savings Initiative July 1, 2016 June 30, 2017 NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY http://portal.ncdenr.org Page
More informationDLA Energy Panel: Energy Resiliency and Assurance
DLA Energy Panel: Energy Resiliency and Assurance U.S. Air Force Office of Energy Assurance Mr. Shawn Bennett, Senior Advisor 12 April 2017 Installation Energy Is Mission Critical AVIATION ~5,517 Aircraft
More informationFt Worth Data Center Power Metering for Real Time PUE Calculation. Scope of Work
Ft Worth Data Center Power Metering for Real Time PUE Calculation Scope of Work Prepared for the General Services Administration By Lawrence Berkeley National Laboratory Rod Mahdavi December 13, 2010 Executive
More informationEnergy Performance Contracting
Energy Performance Contracting December 2017 Outlines Section One: Jonson Controls as an Energy Service Company (ESCO) Reasons behind investment in Energy Efficiency Section Two: Funding Options of Energy
More informationComEd Retro-Commissioning and Monitoring-Based Commissioning
ComEd Retro-Commissioning and Monitoring-Based Commissioning Rick Tonielli Sr. Program Manager C O N F I D E N T I A L Territory profile ComEd is an electric delivery company providing service to 3.8 million
More informationwhere we are, where we could be, how we can get there. 12/14/2011
Central Plant Optimization ASHRAE National Capitol Chapter - PES Wednesday, Nov 7, 2011 Dave Klee, LEED AP Director, Optimized Building Solutions Johnson Controls, Inc. 1 1 J o http://www.johnsoncontrols.com/cpo
More informationCommissioning In Healthcare
Commissioning In Healthcare Joseph Lorino, PE, LEED AP, NewYork-Presbyterian Hospital Evan Wyner, PE, CCP, Strategic Building Solutions 21 st National Conference on Building Commissioning AIA Quality Assurance
More informationUtility Energy Service Contracts (UESCs)
Session: Third Party Funding Options Utility Energy Service Contracts (UESCs) Karen Thomas National Renewable Energy Laboratory (NREL) August 11, 2016 Rhode Island Convention Center Providence, Rhode Island
More informationContinuous Energy Improvement. The Pepco C&I Energy Savings Plan Perspective April 12, 2011
Continuous Energy Improvement The Pepco C&I Energy Savings Plan Perspective April 12, 2011 Pepco Holdings, Inc. Services over 1.9 million customers in DE, DC, MD, and NJ 3 regulated electric utility companies
More informationExisting Building Commissioning Guidelines (ASHRAE Guidelines 0.2 & 1.2) Mark F. Miller, PE, CCP Principal - Strategic Building Solutions, LLC
Existing Building Commissioning Guidelines (ASHRAE Guidelines 0.2 & 1.2) Mark F. Miller, PE, CCP Principal - Strategic Building Solutions, LLC Overview ASHRAE Guidelines for EBCX Best Practices General
More informationTurnkey. Government Facilities. energy solutıons MECHANICAL AND CONTROL SYSTEM EXPERTISE
Government Facilities Turnkey energy solutıons An SBA Approved 8(a) Mentor-Protégé Program Participant and GSA Schedule Holder MECHANICAL AND CONTROL SYSTEM EXPERTISE Specialized expertise in energy mandates
More informationHow Big Data Analytics Helps Hotels Improve Maintenance and Comfort, and Save Energy
How Big Data Analytics Helps Hotels Improve Maintenance and Comfort, and Save Energy Critical facility management drivers are impacting all industries Sustainability Big Data/Cloud Open Building Systems
More informationTrends in Data Center Energy Efficiency
Trends in Data Center Energy Efficiency Presented by: Todd Boucher Better Building by Design 2012 1 Efficiency Vermont is a Registered Provider with The American Institute of Architects Continuing Education
More informationMonitoring-Based Commissioning (MBCx) Early Results from a Portfolio of University Campus Projects
2006 National Conference on Building Commissioning Early Results from a Portfolio of University Campus Projects Karl Brown Deputy Director, California Institute for Energy and Environment University of
More informationInstructions for Participating in ASHRAE s. Commissioning Process Management Professional (CPMP) Certification Program
Instructions for Participating in ASHRAE s Commissioning Process Management Professional (CPMP) Certification Program Effective date: 10/06/2009 Related Resources Resources available to help prepare for
More informationHPE Energy Efficiency Certification Service
Data sheet HPE Energy Efficiency Certification Service HPE Technology Consulting As power consumption and heat generation in the data center increase due to information explosion, big data, e-commerce,
More informationENERGY SAVINGS PERFORMANCE CONTRACTING
ENERGY SAVINGS PERFORMANCE CONTRACTING SAVES ENERGY, SAVES TAXPAYER MONEY, CREATES JOBS SPEAKERS: Tuesday, January 14, 2014 3:00 PM 4:00 PM Jennifer Schafer, Executive Director, Federal Performance Contracting
More informationCybersmart Buildings: Securing Your Investments in Connectivity and Automation
Cybersmart Buildings: Securing Your Investments in Connectivity and Automation Jason Rosselot, CISSP, Director Product Cyber Security, Johnson Controls AIA Quality Assurance The Building Commissioning
More informationPlease comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. Provider Name: Lean Construction
More informationThe Three Big Questions in the Energy World (and Why They All Have the Same Answer)
The Three Big Questions in the Energy World (and Why They All Have the Same Answer) Paul W. Birkeland Copyright 2014 Global Strategic Energy All rights reserved. 1 To Join the Workshop Text PAULBIRKELAN946
More informationA GROWING CONCERN BUILT ENVIRONMENT
THE FEDERAL GOVERNMENT OF CANADA: IT ENERGY USE - A GROWING CONCERN ecoenergy EXPERIENCES FROM THE BUILT ENVIRONMENT Liz Westbrook-Trenholm Senior Officer, Buildings Division Office of Energy Efficiency
More informationCertified Commissioning Technician (CxT) Application
1518 K Street NW Washington, DC 20005 Tel: (202) 737-7775 Fax: (202) 638-4833 Email: info@commissioning.org Website: www.commissioning.org Certified Commissioning Technician () Application First Name Middle
More informationThe challenge is that BAS are often very complex with 1000s of data points to review. EMS Optimization Software
EMS Optimization Software Often immediate energy savings can be achieved with proper set points, sequencing, scheduling and fault detection of the Building Automation System (BAS). The challenge is that
More informationCenterPoint Energy Retro-Commissioning Program Application
CenterPoint Energy Retro-Commissioning Program Application CenterPoint Energy Retro-Commissioning Program is offered to Commercial and Industrial customers in our service territory to enhance their facility
More informationIT Governance ISO/IEC 27001:2013 ISMS Implementation. Service description. Protect Comply Thrive
IT Governance ISO/IEC 27001:2013 ISMS Implementation Service description Protect Comply Thrive 100% guaranteed ISO 27001 certification with the global experts With the IT Governance ISO 27001 Implementation
More informationBuilding the Future. Energy Efficiency on Campus Real World Data. ERRAPPA Spill Prevention and Emergency Response/Contingency Plans 7/27/2017
CLICK Click TO EDIT to edit MASTER Master TITLE title STYLE style Energy Efficiency on Campus Real World Data Building the Future APPA/PCAPPA/BayAPPA 2017: Annual Conference and July Exhibition 21, 2017
More informationEnergy efficiency at scale:
Energy efficiency at scale: Virtual energy assessment technologies are uniquely powerful for saving energy in building portfolios Large portfolios of commercial buildings can benefit greatly from new virtual
More informationMDCSystems. MICHAEL A. BAKER, P.E., M.S.E.M. Consulting Engineer
MDCSystems Providing Expert Solutions for Projects Worldwide MICHAEL A. BAKER, P.E., M.S.E.M. Consulting Engineer Education Drexel University, M.S., Engineering Management, Technology Assessment Brown
More informationViewpoint from the Energy Related
Viewpoint from the Energy Related Associations Viewpoint from the Energy Related Associations Steve Kiesner, Moderator Edison Electric Institute August 16, 2017 Tampa Convention Center Tampa, Florida Speakers
More informationNational Service Center
UNITED TECHNOLOGIES CARRIER CORPORATION National Service Center MAXIMIZING PERFORMANCE AND LONGEVITY OF INDUSTRIAL CHILLERS Protection, Performance and Peace of Mind Because industrial chillers serve large
More informationA New Paradigm for Retrocommissioning: Moving Building Science to Green Collar Trades
A New Paradigm for Retrocommissioning: Moving Building Science to Green Collar Trades Presented by: Keith Forsman,PE Pacific Gas & Electric Company August 17, 2010 .From Building Science to Green Collar
More informationCECIP 18 GWH3. 16KMTCO 2 e 4 ABOUT CECIP CALTECH ENERGY CONSERVATION INVESTMENT PROGRAM ANNUAL REPORT 2014 ABOUT CALTECH INVESTED TO DATE
CECIP CALTECH ENERGY CONSERVATION INVESTMENT PROGRAM ANNUAL REPORT 2014 ABOUT CECIP Caltech s green revolving fund, CECIP, combines finance, engineering and operations to implement energy conservation
More informationFinal Benchmarking Policy and Procedures
Final Benchmarking Policy and Procedures Strategic Plan Task 3.1.1 Deliverable 2.2.3 Funded by Southern California Edison Company Local Government Strategic Plan Strategies Program 2013 2015 Program Period
More informationSession 6: Data Center Energy Management Strategies
Session 6: Data Center Energy Management Strategies Data Center Energy Use and Opportunities: Applying Best Practices to meet Executive Order Requirements Dale Sartor, PE Lawrence Berkeley National Laboratory
More informationAir Force Civil Engineer Energy Savings Performance Contracts (ESPC) Playbook
2017 Air Force Civil Engineer Air Force Civil Engineer Energy Savings Performance Contracts (ESPC) Playbook 1 P age This Playbook is an electronic document. The only valid version is the latest version
More informationSouthern California Edison s RCx Programs
Southern California Edison s RCx Programs Mugi Lukito (Southern California Edison) California Commissioning Collaborative Meeting November 6, 2008 1 California Long Term Energy Efficiency Strategic Plan
More informationGet The Respect You Deserve With Credentials From APWA
Get The Respect You Deserve With Credentials From APWA Accreditation Certified Public Fleet Professional Certified Public Infrastructure Inspector Certified Stormwater Manager The Credentialing Department
More informationComprehensive Energy Management & Utility Master Plan
Comprehensive Energy Management & Utility Master Plan OVERVIEW University of Utah & Health Science Campus Overview Campus Transformation Value Drivers and Challenges Integrated Energy Planning Approach
More informationBeverly D. Grappone Hall Certified LEED Silver Home of NHTI s State-of-the Art Nursing Simulation Center
Beverly D. Grappone Hall Certified LEED Silver Home of NHTI s State-of-the Art Nursing Simulation Center Project: Beverly D. Grappone Hall Facility Size: 30,500 sq. ft. Location: Concord, New Hampshire
More informationEnvironment, Energy Security, and Sustainability Symposium and Exhibition (E2S2)
Environment, Energy Security, and Sustainability Symposium and Exhibition (E2S2) Heidi Anne Kaltenhauser Optimizing Building Performance through Integrated Design June 17, 2010 1 CTC is an independent,
More informationEfficiency Works Business: 2017 Rebates & Goals. January 17, 2017
Efficiency Works Business: 2017 Rebates & Goals January 17, 2017 Platte River Power Authority provides electricity to Estes Park, Fort Collins, Longmont, and Loveland Substation Generation Coal / Natural
More informationFactsheet. Power Generation Service Energy efficiency in power generation and water
Factsheet Power Generation Service Energy efficiency in power generation and water Opportunity identification Opportunity identification overview The opportunity identification phase of Industrial Energy
More informationPrecision Controls of Indianapolis
Precision Controls of Indianapolis For nearly 30 years, Precision Controls of Indianapolis has excelled at process controls, HVAC controls, HVAC and mechanical services, and instrument calibration. An
More informationPLAYBOOK. How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy
PLAYBOOK F O R C H A N G E How Do You Plan to Grow? Evaluating Your Critical Infrastructure Can Help Uncover the Right Strategy The world is becoming more digital every day. The demand for feature-rich,
More informationIncreased Cooling Demand Means More Energy Saving Opportunities. Wednesday, May 25 th, 2016
Increased Cooling Demand Means More Energy Saving Opportunities Wednesday, May 25 th, 2016 AIA Provider: Colorado Green Building Guild Provider Number: 50111120 Increased Cooling Demand Means More Energy
More informationHVAC&R Technical Requirements for The Commissioning Process. Charles E Dorgan, PE, PhD, CxAP Professor Emeritus University of Wisconsin - Madison
HVAC&R Technical Requirements for The Commissioning Process Charles E Dorgan, PE, PhD, CxAP Professor Emeritus University of Wisconsin - Madison Guideline 1-2007 Purpose of this presentation is: to assist
More informationEngineering and Design Services Mechanical HVAC Plumbing Electrical Chemical/Process Structural Instrumentation
Commissioning Profile + Services About Us Established in 1965, DEDC is a privately owned, full-service multidisciplined engineering and design firm. We offer in-house expertise in mechanical HVAC, electrical,
More informationSetting New Standards for Ultra High Performance HVAC
Setting New Standards for Ultra High Performance HVAC WHITE PAPER What if your commercial HVAC system could operate as efficiently in 10 years as it did on the day it was commissioned? What if you could
More informationMetering and Energy Retrofits for the GSA
Metering and Energy Retrofits for the GSA 2012 Rocky Mountain Chapter ASHRAE Technical Conference Leadership in HVAC&R April 20 th, 2012 Juan Moreno and Christian Marsh-Frydenlund 1 1 Agenda Project Overview
More informationAchieving Operational Excellence
Achieving Operational Excellence Energy Efficient Operations in a Shrinking Budget Environment 2010 Energy/Facilities Connections Conference Innovative Approaches for a New Decade DID YOU KNOW? Nine out
More informationExploring the Maturity of Risk Management Process in Government: An Integrated ERM Model at the U.S. Department of Education
Exploring the Maturity of Risk Management Process in Government: An Integrated ERM Model at the U.S. Department of Education FEDERAL STUDENT AID ENTERPRISE RISK MANAGEMENT GROUP Cynthia Vitters 1. ERM
More informationSecurity and Privacy Governance Program Guidelines
Security and Privacy Governance Program Guidelines Effective Security and Privacy Programs start with attention to Governance. Governance refers to the roles and responsibilities that are established by
More informationEngineered Energy Solutions An Overview. Controls, Automation and Energy Conservation
Engineered Energy Solutions An Overview Controls, Automation and Energy Conservation Engineered Energy Solutions Independent Control System Integration and Engineering Firm specializing in the energy efficient
More informationLEAN SIX SIGMA APPROACH TO ENERGY EFFICIENCY PROJECTS ENERGY EFFICIENCY NOW: PUTTING THE PIECES OF THE PUZZLE TOGETHER
LEAN SIX SIGMA APPROACH TO ENERGY EFFICIENCY PROJECTS ENERGY EFFICIENCY NOW: PUTTING THE PIECES OF THE PUZZLE TOGETHER PRESENTER Christopher Hodgin, P.E., CEM, LEED-AP, CCCA State of Alaska Department
More informationHigh Performance Begins Here
High Performance Begins Here NEBB Certified Firms, Professionals and Technicians have access to a vast array of training and education from industry experts. These resources, along with the stringent certification
More informationDR and EE Standards for SCE Buildings
Design & Engineering Services DR and EE Standards for SCE Buildings Prepared by: Design & Engineering Services Customer Service Business Unit Southern California Edison December 2011 Acknowledgements Southern
More informationWashington Headquarters Services Defense Facilities Directorate
Washington Headquarters Services Defense Facilities Directorate Meeting Executive Order 13514 Federal Leadership in Environmental, Energy, and Economic Performance Crystall Merlino, LEED AP Engineering
More informationDEFENSE ACQUISITION REVIEW JOURNAL
DEFENSE ACQUISITION REVIEW JOURNAL 78 Report Documentation Page Form Approved OMB No. 0704-0188 Public reporting burden for the collection of information is estimated to average 1 hour per response, including
More informationCommission for Environmental Cooperation (CEC) Sponsored Workshop on Environmental Assistance Programs and Resources for Automotive OEMs and Suppliers
Commission for Environmental Cooperation (CEC) Sponsored Workshop on Environmental Assistance Programs and Resources for Automotive OEMs and Suppliers Ben Vickery Senior Technical Analyst NIST MEP September
More informationSCORE/CitySmart: Lessons from the Institutional Sector. September 22, 2015 ACEEE National Conference on Energy Efficiency as a Resource
SCORE/CitySmart: Lessons from the Institutional Sector September 22, 2015 ACEEE National Conference on Energy Efficiency as a Resource Why should institutional customers be targeted? What has worked in
More informationExecutive Summary. Zuma Engineering and Research. Data Center Virtualization Assessment. Service Description
Executive Summary is firmly planted in the Green Computing movement by providing independent auditing of Information Technology (IT) data centers to assist with optimizing performance and reducing their
More informationART CENTER AND SATELLITE PLANT
CSU The California State University Office of Audit and Advisory Services CONSTRUCTION California State University, Bakersfield ART CENTER AND SATELLITE PLANT Audit Report 15-09 May 7, 2015 EXECUTIVE SUMMARY
More informationMacDill AFB Energy Center
MacDill AFB Energy Center Thanks for Joining Us Doug Bushing Global Energy Director, CBRE Kevin Kushman CEO, Blue Pillar Rick Hofstetter PowerLogic Specialist, Schneider Electric MACDILL AFB ENERGY CENTER
More informationLeveraging Building Automation Systems to support ongoing commissioning
Leveraging Building Automation Systems to support ongoing commissioning Building Automation Systems Introduction Show me the money Critical components Building Automation System Architectures Protocols
More informationProfessional Certification in the Commissioning Industry. Mike Eardley, PE, CCP Director of Commissioning services Cannon Design
Professional Certification in the Commissioning Industry Mike Eardley, PE, CCP Director of Commissioning services Cannon Design AIA Quality Assurance The Building Commissioning Association is a Registered
More informationFederal Data Center Consolidation Initiative (FDCCI) Workshop III: Final Data Center Consolidation Plan
Federal Data Center Consolidation Initiative (FDCCI) Workshop III: Final Data Center Consolidation Plan August 10, 2010 FDCCI Agenda August 10 th, 2010 1. Welcome Katie Lewin GSA Director Cloud Computing
More informationE e n rgy g y St S ud u y y Pr P og o r g ams December 2011
Energy Study Programs December 2011 1 Agenda Energy Study Programs Overview Recommissioning Engineering Studies Data Center Studies Custom Rebates What makes a good energy study? 2 Energy Study Program
More information1st IEF-EU Energy Day Preceding the 7th IEA-IEF-OPEC Symposium on Energy Outlooks 14 February 2017
1st IEF-EU Energy Day Preceding the 7th IEA-IEF-OPEC Symposium on Energy Outlooks 14 February 2017 Naif ALRagass Director General Assistant for Technical Affairs The Saudi Energy Efficiency Center (SEEC)
More informationThis Is Not Your Father's ESPC
This Is Not Your Father's ESPC Monday, June 9, 2014 1:15 pm 2:30 pm, Hidalgo Presented by: Hope Davis, Director, Massachusetts Division of Capital Asset Management & Maintenance Russ Katherman, Engineering
More informationOverview of the Re:fit Programme
Overview of the Re:fit Programme Delivering savings in the public sector Vicky Kingston Project Director Vicky.kingston@local.gov.uk +447876 594 041 The Re:fit Framework Introducing Re:fit Re:fit allows
More informationThis Is Not Your Father's ESPC
, Hidalgo Presented by: Hope Davis, Director, Massachusetts Division of Capital Asset Management & Maintenance Russ Katherman, Engineering Manager, Montana Architecture & Engineering Division Dick Mink,
More informationDeploying High Efficiency Outdoor Lighting: Regional Streetlight Procurement Program (RSLPP)
Deploying High Efficiency Outdoor Lighting: Regional Streetlight Procurement Program (RSLPP) Michael Fuller President, Keystone Lighting Solutions RSLPP Technical Advisor and Owner s Agent August 21 st,
More informationMay Hands-on Guidance. Measurable Results. SUPPLIER EFFICIENCY PROGRAM
May 2015 Hands-on Guidance. Measurable Results. SUPPLIER EFFICIENCY PROGRAM REACHING OUTSIDE OUR WALLS WHAT A scalable education and training platform that helps suppliers reduce their energy use and costs
More informationSRP Energy Efficiency Program Update SWEEP Regional Energy Efficiency Workshop
SRP Energy Efficiency Program Update SWEEP Regional Energy Efficiency Workshop November 13, 2008 1 Objectives of SRP Energy Efficiency (EE) Programs Reduce/defer generation resource needs Meet SRP s Sustainable
More information