CROW Outage Scheduler Web GUI Tutorial

Size: px
Start display at page:

Download "CROW Outage Scheduler Web GUI Tutorial"

Transcription

1 CROW Outage Scheduler Web GUI Tutorial 9/14/2011 SPP Operations Engineering

2 Revision History Date or Version Number Author Change Description Comments 06/22/2011 Derek Hawkins Initial Draft Draft for review by Jason and Neil. 6/28/2011 Version 1.1 6/30/2011 Version 1.2 7/22/2011 Version 1.3 9/14/2011 Version 1.4 Derek Hawkins Updates based on initial reviews by the project team. For review and post to members. Derek Hawkins Screenshot updates Updates correspond to CROW ver Derek Hawkins Additions: Outage Statuses Outage Flags User Role Setup Jason Smith Clarification of tables reference from Appendix 12. Clarification on Planned End Time of Forced outages. Corrected max lead time for forced generation outages to match Appendix 12. Updated screenshots to reflect button move in GUI. Requests from members during the ITE testing phase. CROW Outage Scheduler Web GUI Tutorial 2

3 Table of Contents Revision History...2 Introduction to CROW...4 Outage Coordination Methodology Tables...4 Outage Priorities... 4 Outage Request Types... 5 Outage Causes... 6 Outage Statuses... 7 Outage Flags... 8 Facility Naming Conventions...9 Fundamental Model Characteristics... 9 Naming Conventions... 9 User Role Setup...11 OPS1 versus CROW...12 CROW Web Interface...13 Login Navigation Useful Navigation Hints Outage Submissions...18 New Request (Forced)...18 New Request (Un-forced)...23 Changing an Existing Request (Forced)...27 Changing an Existing Request (Un-forced)...29 CROW Outage Scheduler Web GUI Tutorial 3

4 Introduction to CROW Southwest Power Pool s CROW outage scheduler will be used by members of SPP to submit and coordinate transmission and generation outages. The SPP CROW application replaces the GEN_S and TRAN_S applications that have resided in SPP s OPS1 portal. CROW allows greater flexibility in order to meet each individual company s business needs related to outage coordination. Access to the transmission and/or generation information of each entity in the SPP CROW system is fully configurable based on each individual user account. Outage Coordination Methodology Tables All of the following tables are referenced from SPP Criteria Appendix 12: Outage Coordination Methodology. Outage Priorities Transmission Outage Priorities Priority Definition Minimum Lead Time Planned Equipment is known to be operable with little risk of leading to a forced outage. As required for preventive maintenance, troubleshooting, repairs that are not viewed as urgent, system improvements such as capacity upgrades, the installation of additional facilities, or the replacement of equipment due to obsolescence. Discretionary Equipment is known to be operable with little risk of leading to a forced outage; however the timeline for submission of Planned outage priority has passed. Discretionary outages are required to be submitted at least 2 calendar days in advance. Due to the shorter lead time, this outage priority has increased risk of being denied based upon higher priority outage requests. Opportunity Lead time may be very short or zero. An outage that can be taken None due to changed system conditions (i.e. Generator suddenly offline for forced outage allows transmission work to be done). Operational Equipment is removed from service for operational reasons such None as voltage control, constraint mitigation as identified in an operating procedure, etc. Urgent Equipment is known to be operable, yet carries an increased risk of a forced outage or equipment loss. The equipment remains in service until maintenance crews are ready to perform the work. Emergency Equipment is to be removed from service by operator as soon as None possible because of safety concerns or increased risk to grid security. 7 Days None Maximum Lead Time 2 Days 7 Days 7 Days None 2 Hours 48 Hours 2 Hours Forced Equipment is out of service at the time of the request. None 1 Hour Figure 1: Transmission Outage Priorities CROW Outage Scheduler Web GUI Tutorial 4

5 Generation Outage/Derate Priorities Priority Definition Minimum Lead Time Maximum Lead Time Planned Equipment is known to be operable with little risk of leading 2 Days None to a forced outage. As required for preventive maintenance, troubleshooting, repairs that are not viewed as urgent, system improvements such as capacity upgrades, the installation of additional facilities, or the replacement of equipment due to obsolescence. Urgent Equipment is known to be operable, yet carries an increased 24 Hours 7 Days risk of a forced outage or equipment loss. The equipment remains in service until maintenance crews are ready to perform the work. Emergency Equipment is to be removed from service by operator as None 24 Hours soon as possible because of safety concerns or increased risk to grid security. Forced Equipment is out of service at the time of the request. None None Figure 2: Generation Outage Priorities Outage Request Types Transmission Outage Types Outage Request Type Out of Service (OOS) Normally Open (NO) Informational (INF) Hot Line Work (HLW) General System Protection (GSP) Definition Equipment is out of service. Equipment is normally out of service and is identified as normally open in the SPP regional models. Normally Open request type is used to close (place in service) a normally open facility. Used for outage events that are not covered by one of the other Outage Equipment Request Types. Not an out of service event. Work is being performed on live or energized equipment. Work is being performed on protection systems. Requestor shall specifically identify protection systems out of service and any modification to operation or behavior of system contingencies. Figure 3: Transmission Outage Types Modeling Assumptions SDX = Open EMS = Open SDX = Closed EMS = Closed None Informational Only None Informational Only None Informational Only Generation Outage/Derate Types Request Type Out of Service Derate Definition Modeling Assumption Generator or Resource is out of service. SDX = offline EMS = offline Generator or Resource maximum capability is lowered from SDX = online, with new lower normal operation. A new maximum capability is required PMAX to be submitted with each Outage Request Type of Derate. EMS = online, with new lower PMAX Figure 4: Generation Outage/Derate Types CROW Outage Scheduler Web GUI Tutorial 5

6 Outage Causes Transmission Outage Causes Reason Definition Maintenance & Construction Outages to facilitate repair, maintain, or upgrade of facility related equipment. This includes clearances to perform vegetation management. Does not include outages to support Maintenance & Construction of other facilities. Those should be submitted as Voltage or SOL Mitigation. Third Party Request Non-transmission facility related requests for clearance or work such as highway construction. Voltage Mitigation Operation of facilities to preserve or correct Bulk Electric System voltage. SOL Mitigation (Thermal) Operation of facilities to preserve or correct Bulk Electric System thermal loading issues. Weather/Environmental/Fire Outages caused by wind, ice, snow, fire, flood, etc. All weather or (excluding Lightning) environmental causes excluding lightning strikes. Lightning Outages caused by direct or indirect Lightning strikes. Foreign Interference (including Outages caused by blown debris, bird droppings, kites, falling conductors, contamination) airplanes, etc. Vandalism/Terrorism/Malicious Outages resulting from known or suspected vandalism, terrorism, or other Acts malicious acts. Equipment Failure Outages resulting from failure of facility related equipment. Imminent Equipment Failure Operation of facilities due to expected imminent facility rated equipment failure. Protection System Failure Operation of facilities due to failure or undesired operation of the facility including Undesired Operations protection systems. Vegetation Outages resulting from contact with vegetation. This does not include outages due to clearances required to perform vegetation management which should be submitted as Maintenance & Construction. This does not include vegetation blown into rights of way or into contact with facilities which should be submitted as Foreign Interference. BES Condition (Stability, Outages resulting from Bulk Electric System conditions such as islanding, Loading) cascading outages, sudden thermal loading due to other contingencies, transient stability conditions, etc. Unknown Operation of facilities due to an unknown reason. Most forced outages will be submitted with an initial reason of Unknown. Once the actual reason for the operation is known, the outage requestor should update the outage request. SPP Staff will follow up after some time to determine the actual outage reason for any outages which still have a reason of Unknown submitted. Other Operation of facilities due to a reason not listed here. Figure 5: Transmission Outage Reasons CROW Outage Scheduler Web GUI Tutorial 6

7 Generation Outage/Derate Causes Reason Equipment Failure Imminent Equipment Failure BES Reliability Loss of Interconnection BES Stability Fuel Supply Regulatory/Safety/En vironmental Unknown Routine Generator Maintenance Supporting Transmission Outage BES Reliability Excess Capacity/Economic Outage Statuses Status Proposed Submitted Study Definition Failure in station generation, prime mover, or other equipment has occurred. Does not include failure of GSU transformers or interconnection facilities. Does include equipment related to fuel delivery considered a part of the resource (such as a coal mill). Expected failure in station generation, prime mover, or other equipment. Does not include failure of GSU transformers or interconnection facilities. Does include equipment related to fuel delivery considered a part of the resource (such as a coal mill). Removal from service or limitation to preserve or correct Bulk Electric System reliability issues either through action of a Special Protection System, runback scheme, or as mitigation of another reliability event. Failure in interconnection equipment such as GSU transformers or other interconnection facilities. Does not include loss of synchronization due to stability or islanding type events. Removal from service or limitation due to Bulk Electric System stability issues. Includes loss of synchronization due to transient stability and/or islanding issues. Removal from service or limitation due to fuel supply interruption. Does not include local equipment failures related to fuel supply. Includes loss of gas pressure due to offsite issue, coal supply exhaustion, lack of headwater issues for hydro, etc. Removal from service or limitation due to Regulatory/Safety/Environmental restrictions such as emission limits, OSHA, NRC, or other regulatory body limitations. Includes damage caused by weather including but not limited to lightning, flood, earthquake, etc. This may also include limitations to hydro due to low dissolved oxygen in tail water or to control downstream flooding. The default Forced Outage/Derate reason will be pre-populated with Unknown at the time of submittal. Either during the initial outage submittal or at a later time, the Unknown reason must be changed to reflect the actual experienced issue. Removal from service or limitation in order to perform repair or inspection of generation equipment. Removal from service or limitation in order to support a scheduled transmission outage. Removal from service or limitation to preserve or correct a Bulk Electric System reliability issue. Removal from service or limitation due to seasonal or system capacity need. This includes peaker units not expected to be used during winter months. Figure 6: Generation Outage/Derate Reasons Definition The outage request has been saved in the outage scheduler system and remains under the full revision control until the outage is entered into a Submitted state by the requestor. If the requestor does not move a proposed request to the submitted status within 30 days of the planned start date, the outage is automatically Withdrawn. Proposed outage request status dates DO NOT qualify for outage queuing in conflict resolution. Proposed outage requests are not provided to external systems such as NERC SDX/IDC or SPP s EMS. The outage request has been submitted into the outage scheduler system and is ready for review by SPP. The outage requestor does not possess revision control of the outage in this status. A revision request may be submitted to SPP regarding an outage in Submitted status. Outage requests in this state are provided to external systems such as NERC SDX/IDC or SPP s EMS. SPP will change the status type to Study once the active study process begins. Outage CROW Outage Scheduler Web GUI Tutorial 7

8 Preliminary Approved Approved Implemented Completed requests in this state are provided to external systems such as NERC SDX/IDC or SPP s EMS. Outage requests with Preliminary Approved status have been approved based on long lead studies and may need additional analysis closer to the planned start date or finalization of an Operating Guide. Once the restudy is complete or final opguide posted, the outage status is changed to Approved. Outage requests in this state are provided to external systems such as NERC SDX/IDC or SPP s EMS. Approved state indicates SPP has completed the study process and the outage request is ready for implementation. Outage requests in this state are provided to external systems such as NERC SDX/IDC or SPP s EMS. Once the outage request actual start time has been entered, signifying that the outage has begun, the outage status is changed to Implemented. Outage requests in this state are provided to external systems such as NERC SDX/IDC or SPP s EMS. Once the outage request actual end time has been entered, signifying that the outage has ended, the outage status is changed to Completed. Outage requests in this state are NO LONGER provided to external systems such as NERC SDX/IDC or SPP s EMS. Outage Flags Transmission Outage Flags Flag Perm. FG Element MTE Op Guide JOA Tie Line Definition This flag will be set when the equipment is determined to be an element of a permanent flowgate. Major Transmission Element This flag is set for the following equipment: All transmission facilities rated at 230kV or above. All tie lines, 60kV and above. All facilities, monitored and contingent elements, associated with flowgates Other facilities specified by the Transmission Operator or the Reliability Coordinator as having a major impact on the Bulk Electric System or that affect the capability and reliability of generating facilities (backup station power, etc). If the request has an operating guide associated with the outage then this flag will be set. Joint Operating Agreement This flag will be set for equipment identified as those that outages must be coordinated with MISO/TVA per our Joint Operating Agreements with those entities. This flag is set when the To and From stations are operated by different companies. Generation Outage Flags Flag Black Start JOU Definition This flag will be set for units that have been designated as black start units. Joint Owned Unit This flag is set for units that are owned by multiple companies. CROW Outage Scheduler Web GUI Tutorial 8

9 Facility Naming Conventions Fundamental Model Characteristics All bulk electric system equipment in the model in SPP CROW will be associated with a Station. For purposes of the SPP CROW project, a Station will be defined as all the bulk electric system equipment located at a geographic location. For the initial implementation of SPP CROW, the types of bulk electric system equipment that will be included in the model will be Units, Lines, and Transformers. Other types of bulk electric system equipment may be included in later upgrades to the SPP CROW system. Units and Transformers will be associated with (attached to) a Station in the CROW model. A Line will connect two Stations in the model. Each Line will be listed in CROW as equipment under both stations it connects to. Naming Conventions Stations Each Station will be given a single common name. This common name will be the name most often used collectively by transmission owners, transmission operators, and reliability coordinators when referring to a station. Station names should be spelled out completely. If station names contain a direction to distinguish between two stations, the direction will follow the actual station name. Directions can be used as an integral part of the station name. If two stations within the SPP Reliability Coordination area have the same name, the station operator s abbreviated name with be added. Station Name Examples NW Texarkana Northwest Texarkana (Preferred) East Fayetteville, South Fayetteville Fayetteville East, Fayetteville South (Preferred) Hugo WFEC Hugo AEP From these common names, a 12 character limited station name abbreviation will also be determined. If the full station name is 12 characters or less, the full name and abbreviated name will be the same. An appropriate abbreviation of this common name will be critical as station abbreviations are used frequently in CROW in place of the full station name. CROW Outage Scheduler Web GUI Tutorial 9

10 Equipment The SPP CROW system allows for three discreet names for each individual piece of bulk electric system equipment; Lines, Transformers, and Units. These are an SPP EMS NAME, COMMON NAME, and an ALTERNATE NAME. SPP will determine the SPP EMS NAME for each piece of equipment by its associated EMS equipment. The equipment Owner/Operator and SPP will collaborate to determine the most appropriate COMMON NAME. ALTERNATE NAMES can be set by the equipment Owner/Operator. Lines Each transmission line s Common Name will be the combination of a From Station name and a To Station name along with the voltage level. Circuit ID numbers will only be used in cases of double circuits or uncommon equipment configurations. The From and To stations will be placed in alphabetical order to form the line names. Line Common Name Examples Northwest Texarkana Lydia 345kV Lydia Northwest Texarkana 345kV (Preferred) Transformers Each transformer common name will be the common name of the station at which it is located along with the high and low side voltage levels. Circuit ID numbers will only be used in cases of double circuits or uncommon equipment configurations. Directions can be used in place of circuit ID numbers to distinguish transformers of the same high and low side voltage level at the same station. Transformer Common Name Examples Northwest Texarkana North 345/138kV Northwest Texarkana South 345/138kV CROW Outage Scheduler Web GUI Tutorial 10

11 User Role Setup The CROW system allows the flexibility to meet each individual company s business needs related to the access of transmission and/or generation information of each entity. The system is fully configurable based on each individual user account. SPP will work with each user to determine the appropriate access and review authority to preserve code of conduct integrity. The graphic below outlines the user role model that SPP will follow. Transmission and Reliability roles have the capability to view or submit outages for all types of equipment within its company. Generation and Marketing roles are only able to view or submit outages for Units within its company. Please note that individual users can be set up with read-only access or full outage submittal privileges. Southwest Power Pool Balancing Authority A TOP A GOP A IPP C Balancing Authority B TOP B GOP B TOP D Company A Trans. Reliability Role Company A Generation Marketing Role Company C Generation Marketing Role Company B Trans. Reliability Role Company B Generation Marketing Role Company D Trans. Reliability Role TOP A Lines TOP A XFMRs GOP A Units IPP C Units TOP B Lines TOP B XFMRs GOP B Units TOP D Lines TOP D XFMRs CROW Equipment CROW Outage Scheduler Web GUI Tutorial 11

12 OPS1 versus CROW SPP is replacing the Transmission and Generation Outage Scheduler applications on OPS1 with a new application by Equinox Software called the CROW Outage Scheduler. CROW will allow varying levels of granularity within companies and NERC registered entities. Individual Generator Operators (GOP s) within a BA or TOP may also be configured to provide outage requests independent of other entities within the larger entity. SPP will work with each user to determine the appropriate access and review authority to preserve code of conduct integrity. CROW simply replaces the TRANS and GENS outage submission functionality in OPS1. All other valid applications on OPS1 such as CPS, Hourly Load, Load Forecast, Load and Capability, Reports, etc. are not impacted nor replaced by the CROW Outage Scheduler. Important Differences between OPS1 and CROW The historical limitations in OPS1 did not allow much granularity in separation of different entities data, so submission on a Balancing Authority level was required. The CROW system allows the flexibility to meet each individual company s business needs related to the access of transmission and/or generation information of each entity. The system is fully configurable based on each individual user account. Currently in OPS1, station names are listed in an abbreviated form. With CROW s flexibility, SPP will use complete names to reduce opportunities for confusion. SPP has attempted to collaborate with the members in order to compile an agreed upon list of common station names. Generation derates will be handled differently in CROW from what is currently in OPS1. Generation derates in CROW will become the unit s new Pmax. An OPS1 generation derate was the amount that the unit was derated by. Example Unit 1 derated from a Pmax of 600 MW to 400 MW: CROW derate = 400 MW OPS1 derate = 200 MW Required Fields: OPS1 1. Start Time 2. End Time 3. Outage Priority (Maintenance or Forced) CROW 1. Start Time 2. End Time 3. Outage Priority 4. Outage Type 5. Outage Cause 6. Recall Time (or Unrecallable) CROW Outage Scheduler Web GUI Tutorial 12

13 CROW Web Interface The following section will address logging in to the SPP CROW Web application as well as basic navigation procedures and settings configurations. Login Upon accessing the PROD CROW URL ( the user will be asked to select the certificate that was provided for member access. Once selected, the Outage Request Index screen will be displayed. Note that only a small set of equipment will be available in ITE CROW for beta testing purposes. Figure 7: Select certificate provided for access. Navigation Upon logging in to CROW Web the user will notice three tabs for navigation. The primary tabs that are common to all screens are Operations Reports, Outage Requests, and Options. Navigating between the primary tabs will populate secondary tabs specific to the current screen. Figure 8: Primary tabs common to all screens. CROW Outage Scheduler Web GUI Tutorial 13

14 1. Operations Reports a. CROW has the ability to allow users to define custom reports. These reports can be set up to view one time online or ed to the user. It also allows for users to subscribe to reports and receive those reports via on a user specified time basis. Figure 9: Operations Reports Tab CROW Outage Scheduler Web GUI Tutorial 14

15 2. Outage Requests Home a. This is the default Home screen that shows the Outage Request Index. b. The index only shows equipment that the user profile has been configured to have access to. c. This index can also be filtered using the Date/Time fields or the available drop down lists. To apply the filters, the user must click. d. New outage requests will be submitted here using the button. e. Outage request summaries can be viewed for previously submitted outages by double-clicking the request in the index. f. CROW allows the user to. This will open an Excel window containing all of the outage requests that are being displayed in the Outage Request Index. Figure 10: Outage Requests Tab displaying the Outage Request Index CROW Outage Scheduler Web GUI Tutorial 15

16 3. Options a. The Options tab allows users to configure the SPP CROW Web application to meet their specific business needs. b. Users can change time zones, naming conventions, and request outage approval/denial notifications via . Figure 11: CROW Administrative Options Screen CROW Outage Scheduler Web GUI Tutorial 16

17 Useful Navigation Hints Buttons: Figure 12: Navigation buttons available from the Request Summary, Request Details/Approval, and Attachments screens. Back Returns to the previous screen. Export Opens a Word document containing the outage request details. Duplicate Displays a new Request Summary screen with the fields completed using the same data from the outage request that was selected to duplicate. Home Returns the user to the Outage Request Index screen. CROW Outage Scheduler Web GUI Tutorial 17

18 Outage Submissions The primary focus of SPP members will be outage submission. The following sections will detail new outage submissions as well as modifications to previously submitted outage request. The outage submission process will differ depending on the priority selected. For this guide, two types of priorities will be considered: forced and un-forced. All priorities excluding forced have a similar submission process; therefore, this tutorial will only cover that process once. New Request (Forced) 1. The first step in submitting a new outage is to click the New Outage Request button from the Outage Request Index screen. CROW Outage Scheduler Web GUI Tutorial 18

19 2. Step one creates a new screen under the Outage Request primary tab that displays the Request Summary tab. This is the screen where equipment will be added and outage request criteria will be completed. The first step from this screen will be to click Add in order to select the equipment that is being submitted. Select Add CROW Outage Scheduler Web GUI Tutorial 19

20 3. After selecting Add, the Select Circuits/Equipment window appears. This window allows the user to select the equipment using the drop down lists. Once the equipment is highlighted, click OK to return to the Request Summary screen noting that the equipment has been added to the Equip. Requested table. CROW Outage Scheduler Web GUI Tutorial 20

21 4. For this example we have chosen a Forced outage with the outage cause Unknown. (If upon further investigation the cause is discovered, then CROW allows for the outage request to be modified with the updated information. This is addressed in the next section.) We can now Implement the outage request. It is important to note that since this is a Forced outage, the only option is to Implement the outage since it should have already started. The default Planned End Time for a Forced Priority Outage is approximately 24 hours in the future. The Planned End Time can be updated later as more information about the Forced outage is known. 5. Since this is a Forced outage, a new window is displayed that allows the user to log the actual outage start time before completing the implementation. CROW Outage Scheduler Web GUI Tutorial 21

22 6. Upon successful implementation, the application returns to the Request Summary with a notification in green that the outage submission was completed successfully. When the outage is in this state, the user has the option to Request Change to the outage, Save any changes made to the outage, or Complete the outage by entering the time when equipment was returned to service. The outage request will also appear in the Outage Request Index. CROW Outage Scheduler Web GUI Tutorial 22

23 7. If the outage request conflicts with an existing outage request, the user will receive the following error indicating the existing outage request. 8. Users should utilize the Request Change button to update the Planned End time or Outage Cause for submitted outages. New Request (Un forced) 1. This example will consider a Planned outage to demonstrate the process for submitting unforced outages. Begin by clicking New Outage Request from the Outage Request Index page. CROW Outage Scheduler Web GUI Tutorial 23

24 2. Step one creates a new screen under the Outage Request primary tab that displays the Request Summary tab. From here equipment will be added and outage request criteria will be completed. The first step from this screen will be to click Add in order to select the equipment that is being submitted. Select Add 3. After selecting Add, the Select Circuits/Equipment window appears allowing the user to select the equipment using the drop down lists. Once the equipment is highlighted, click OK to return to the Request Summary screen noting that the equipment has been added to the Equip. Requested table. CROW Outage Scheduler Web GUI Tutorial 24

25 CROW Outage Scheduler Web GUI Tutorial 25

26 4. Once the equipment has been added to the request, the Outage Priority should be selected. This example specifies a Planned outage priority that will be Continuously out of service for the time span indicated. Also, a Min. Recall Time of 2 hours has been selected signifying that it would take at least 2 hours to return this equipment to service if directed to do so. After selecting Maintenance and Construction for the Outage Cause, notice that Planned outage requests offer the ability to Save Proposed outage request or Submit the outage request. Clicking Submit sends the outage request to SPP for analysis. Save Proposed requests are not visible to SPP and do not have a secured queue date. 5. Upon submittal, a green notification will be displayed at the top of the Outage Request Index page if the outage request was completed successfully. CROW Outage Scheduler Web GUI Tutorial 26

27 Changing an Existing Request (Forced) 1. To modify an existing outage request, or to notify SPP that the outage has ended by updating the Planned End Time, start by locating the outage in the Outage Request Index and doubleclicking the request. Notice that when the Request Summary screen is displayed that the fields are grayed-out indicating that they cannot be changed from this page. 2. Click Request Change to display a new Request Summary that will allow the fields to be changed. For this example, the outage cause will be updated from Unknown to Equipment Failure. CROW Outage Scheduler Web GUI Tutorial 27

28 3. Next, Submit the change insuring that a green notification is received. 4. The change request can be viewed in the Change Requests tab. 5. This outage request can no longer be modified until SPP staff has updated the approval status of the change request. CROW Outage Scheduler Web GUI Tutorial 28

29 Changing an Existing Request (Un forced) 1. To modify an existing outage request, start by locating the outage in the Outage Request Index and double-clicking the request. For this example, the outage request has been Preapproved by SPP. The CROW Web indicates a change in outage request status by highlighting the request in the Outage Request Index. 2. Notice that when the Request Summary screen is displayed that the fields are grayed-out indicating that they cannot be changed from this page. The Outage Status field is also red indicating that this field has been modified. CROW Outage Scheduler Web GUI Tutorial 29

30 3. There are two options with a Planned request that is in the Pre-Approved status: Request Change or Request Cancel. Click Request Change to display a new Request Summary that allows the fields to be modified. Note that change requests can only be submitted prior to the outage request reaching the implemented status. The Planned end date will be changed for this example. CROW Outage Scheduler Web GUI Tutorial 30

31 4. Next, Submit the change insuring that a green notification is received. This request has now been sent to SPP for analysis. CROW Outage Scheduler Web GUI Tutorial 31

32 5. CROW also allows the user to export the revision history of the outage request into an Excel spreadsheet by clicking. The following window would be displayed. CROW Outage Scheduler Web GUI Tutorial 32

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

Reliability Coordinator Procedure

Reliability Coordinator Procedure No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...

More information

Member Impacting Project Overview

Member Impacting Project Overview Member Impacting Overview Page 1 of 7 Table of Contents PR20090027 - Outage Scheduler Table of Contents... 2 Version Control... 2 Document Purpose... 2 Executive Summary... 3 Business Impact... 3 Technical

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 FAC-003-4 Transmission Vegetation Management. Registered Entity Name: Applicable Function(s): Applicable only for TO and GO Compliance Monitoring Method: RSAW Version:

More information

edart Quick Reference Guide

edart Quick Reference Guide edart Quick Reference Guide Revision: 05 Effective Date: 08/16/2017 PJM 2017 Prepared by edart Project Team Table of Contents Table of Contents... 2 Revision History... 6 About the Quick Reference Guide...

More information

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Revision History Version Effective Date Summary of Revisions

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision

Peak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision Table of Contents I. Purpose... 2 II. Introduction... 2 III. Peak Roles and Responsibilities... 2 IV. Applicability and Obligations... 3 V. Questions and Comments... 6 VI. Data Request Spreadsheet... 6

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Reliability Coordinator Procedure PURPOSE... 1

Reliability Coordinator Procedure PURPOSE... 1 No. RC0550 Restriction: Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 1.1.1. CAISO RC... 2 1.1.2. RC Working Groups... 2 1.1.3. Operationally Affected Parties... 2 1.1.4. RC Oversight Committee...

More information

Outage Coordination External Workshop. Jason Ausmus Manager, Operations Planning

Outage Coordination External Workshop. Jason Ausmus Manager, Operations Planning Outage Coordination External Workshop Jason Ausmus Manager, Operations Planning Outage Coordination Course 8 total CEHs for this course To get the CEHs, you will need to: o Be present for the entire class

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016

NERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons

More information

Transmission Register PTO Admin User Manual. Version 1.0

Transmission Register PTO Admin User Manual. Version 1.0 Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6

More information

Transmission Service Reference Manual. May 08, 2017

Transmission Service Reference Manual. May 08, 2017 Transmission Service Reference Manual May 08, 2017 Revision History Revision History Date or Version Number April 29, 2015 Version 1.0 May 08, 2017 Version 2.0 Author Shari Brown Julie Gerush Change Description

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

STCP22-1 Issue 003 Production of Models for GB System Planning

STCP22-1 Issue 003 Production of Models for GB System Planning STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission

More information

BESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2

BESNet User Manual. Exception Request Preparation for Registered Entities. June 29, 2014 Version 1-2 Table of Contents BESNet User Manual Exception Request Preparation for Registered Entities June 29, 2014 Version 1-2 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

RPS Quick Reference Guide

RPS Quick Reference Guide The RPS Quick Reference Guide was designed to help users navigate through the Renewable Energy Facility Application Tracking System while highlighting important notes and features. Table of Contents Logging

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Outage Scheduler User's Guide

Outage Scheduler User's Guide GUIDE 10 Outage Scheduler User's Guide September 2016 Version: 3.0 Revision Date: 09/13/2016 This document was prepared by: Scheduling, Energy Market Operations New York Independent System Operator 10

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

NERC Overview and Compliance Update

NERC Overview and Compliance Update NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately in congestion management procedures.

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Standard EOP Disturbance Reporting

Standard EOP Disturbance Reporting A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment

More information

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (

More information

Standard INT Dynamic Transfers

Standard INT Dynamic Transfers Standard INT-004-3.1 Dynamic Transfers A. Introduction 1. Title: Dynamic Transfers 2. Number: INT-004-3.1 3. Purpose: To ensure Dynamic Schedules and Pseudo-Ties are communicated and accounted for appropriately

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Bulk Electric System Definition Changes and Reporting

Bulk Electric System Definition Changes and Reporting Bulk Electric System Definition Changes and Reporting June 12, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Overview BES Definition Change BES Definition Reference

More information

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September

Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September 23, 2009 TABLE OF CONTENTS INTRODUCTION A. RESPONSIBILITIES

More information

ereliability Tracker Software Leader User Guide

ereliability Tracker Software Leader User Guide ereliability Tracker Software Leader User Guide Revision Date: 10/15/2014 Table of Contents Introduction... 2 Log-in/Create an Account... 2 Types of Users and Permissions... 2 Functions... 3 Home... 3

More information

Checklist for Submission to Utility

Checklist for Submission to Utility Simplified Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource (DER) to the Utility s distribution system through the Simplified Process

More information

REAL-TIME MONITORING DATA SPECIFICATION

REAL-TIME MONITORING DATA SPECIFICATION REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support

TOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support TOP/IRO Standards RC Users Group January 21, 2016 Vic Howell Manager, Operations Engineering Support Saad Malik Manager, Real-Time Operations Engineering New/Revised TOP & IRO Standards November 19, 2015,

More information

Chapter X Security Performance Metrics

Chapter X Security Performance Metrics DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the

More information

Electric Transmission Reliability

Electric Transmission Reliability 1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted By Company Date Submitted Shannon Eddy (shannon@consciousventuresgroup.com) Rachel Gold (Rachel@consciousventuresgroup.com) Large-scale Solar Association (LSA) December

More information

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

CIP Cyber Security Configuration Change Management and Vulnerability Assessments

CIP Cyber Security Configuration Change Management and Vulnerability Assessments Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Regulatory Impacts on Research Topics. Jennifer T. Sterling Director, Exelon NERC Compliance Program

Regulatory Impacts on Research Topics. Jennifer T. Sterling Director, Exelon NERC Compliance Program Regulatory Impacts on Research Topics Jennifer T. Sterling Director, Exelon NERC Compliance Program The 2003 Blackout On August 14, 2003, an electric power blackout affected large portions of the Northeast

More information

Implementation Plan for COM-001-2

Implementation Plan for COM-001-2 Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.

More information

Internal Controls Evaluation (ICE) Tony Eddleman, P.E. NERC Compliance Manager Nebraska Public Power District

Internal Controls Evaluation (ICE) Tony Eddleman, P.E. NERC Compliance Manager Nebraska Public Power District Internal Controls Evaluation (ICE) Tony Eddleman, P.E. NERC Compliance Manager Nebraska Public Power District 2 Topics NPPD Overview Reliability Controls NPPD Internal Control Evaluation (ICE) Sample Controls

More information

Standard COM-002-2a Communications and Coordination

Standard COM-002-2a Communications and Coordination A. Introduction 1. Title: Communication and Coordination 2. Number: COM-002-2a 3. Purpose: To ensure Balancing Authorities, Transmission Operators, and Generator Operators have adequate communications

More information

Published: December 15, 2016 Revised: December 15, 2016

Published: December 15, 2016 Revised: December 15, 2016 Market Participant Guide: SPP 2017 Congestion Hedging Published: December 15, 2016 Revised: December 15, 2016 Revision History Chart Version Revised By Description of Modifications Revision Date 1.0 Congestion

More information

Published: December 15, 2017 Revised: December 15, 2017

Published: December 15, 2017 Revised: December 15, 2017 Market Participant Guide: SPP 2018 Congestion Hedging Published: December 15, 2017 Revised: December 15, 2017 Revision History Chart Version Revised By Description of Modifications Revision Date 1.0 Congestion

More information

Comment Form for 1 st Draft of Standard for Backup Facilities (Project )

Comment Form for 1 st Draft of Standard for Backup Facilities (Project ) Comment Form for 1 st Draft of Standard for Backup Facilities (Project 2006-04) Please use this form to submit comments on the 1 st draft of the standards for Backup Facilities (Project 2006-04). Comments

More information

2016 Fall ITO Stakeholder Meeting. Topics in Operations

2016 Fall ITO Stakeholder Meeting. Topics in Operations 2016 Fall ITO Stakeholder Meeting Topics in Operations 11/17/2016 TOP-003-3 Requirement R1. Each Transmission Operator shall maintain a documented specification for the data necessary for it to perform

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

Entity Registration: CFRs

Entity Registration: CFRs Entity Registration: CFRs End User Guide: Registered Entities December 12 th, 2017 1 Table of Contents 1 Overview... 3 1.1 Entity Registration Overview... 3 1.2 CFR Overview... 3 1.2.1 CFR States... 3

More information

New Brunswick 2018 Annual Implementation Plan Version 1

New Brunswick 2018 Annual Implementation Plan Version 1 New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...

More information

A. Introduction 1. Title: 2. Number: 3. Purpose: 4. Applicability: 4.1. Functional Entities: Balancing Authority Distribution Provider

A. Introduction 1. Title: 2. Number: 3. Purpose: 4. Applicability: 4.1. Functional Entities: Balancing Authority Distribution Provider The Background, VRF/VSLs, and Guidelines and Technical Basis Sections have been removed for this informal posting. The Project 2016-02 is seeking comments around the concept of the Requirement/Measure

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

Interconnection Application

Interconnection Application Interconnection Application Member interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

Project Tracking and Cost Estimation Tool PR

Project Tracking and Cost Estimation Tool PR Project Tracking and Cost Estimation Tool PR20120007 Member Test Plan MAINTAINED BY Cary Frizzell PUBLISHED: May 22, 2012 Copyright 2012 by Southwest Power Pool, Inc. All rights reserved. 1. OVERVIEW...

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1

DRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1 DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...

More information

Model Parts and Assembly. Jay Britton Britton Consulting LLC

Model Parts and Assembly. Jay Britton Britton Consulting LLC Model Parts and Assembly Jay Britton Britton Consulting LLC jay.britton@comcast.net WG13 Ref Model for a Network Analysis Case Physical Network Model Parts Repository Full Model Parts Incremental Model

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50 BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T - 50 VOLTAGE STABILITY OPERATING LIMITS AND PROCEDURES FOR USING THE REAL TIME VOLTAGE STABILITY APPLICATION (RTVSA) Supercedes 7T-50 dated 02 May

More information

Standard INT Interchange Authority Distributes Arranged Interchange

Standard INT Interchange Authority Distributes Arranged Interchange Standard INT-005-2 Authority Distributes A. Introduction 1. Title: Authority Distributes 2. Number: INT-005-2 3. Purpose: To ensure that the implementation of between Source and Sink Balancing Authorities

More information

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities

TOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities A. Introduction 1. Title: Real-time Reliability Monitoring and Analysis Capabilities 2. Number: TOP-010-1(i) 3. Purpose: Establish requirements for Real-time monitoring and analysis capabilities to support

More information

Project Posting 8 Frequently Asked Questions Guide

Project Posting 8 Frequently Asked Questions Guide Project 2007-02 Posting 8 Frequently Asked Questions Guide General Questions 1. What were the inputs that drove the development of posting 8 of Project 2007-02? The NERC Board of Trustees November 7 th,

More information

Evaluate & Triage a Service Request UFR Page 1 of 7

Evaluate & Triage a Service Request UFR Page 1 of 7 Page 1 of 7 Purpose: The triage of a Service Request (SR) submitted for a facility When: UFR has been notified by email that a Service Request has been submitted via the web Who: Unit Facility Representative

More information

CIP Cyber Security Personnel & Training

CIP Cyber Security Personnel & Training A. Introduction 1. Title: Cyber Security Personnel & Training 2. Number: CIP-004-6 3. Purpose: To minimize the risk against compromise that could lead to misoperation or instability in the Bulk Electric

More information

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting

More information

Disturbance Monitoring and

Disturbance Monitoring and PRC-002-2 R1 Notification Disturbance Monitoring and Reporting Requirements Compliance Spring Workshop May 10, 2017 Objectives This presentation will discuss: Requirement R1 Part 1.2 notifications Definition

More information

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Agenda Item 1 Administrative Items AQITF Chairman Jim McAvoy called the meeting to order at 9:00 p.m.

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

Standards Authorization Request Justification

Standards Authorization Request Justification Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

Geomagnetic Disturbances

Geomagnetic Disturbances Geomagnetic Disturbances Managing Risk to the North American Power Grid Mark Olson, Reliability Standards Developer Worcester Polytechnic Institute Energy Symposium September 25, 2013 About NERC The North

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

Training Manual for CB Area Good Inside Portal

Training Manual for CB Area Good Inside Portal Training Manual for CB Area Good Inside Portal www.utzcertified.org Table of Contents Module 0: Introduction to the CB Area... 2 Module 1: Introduction to the Requests area... 7 Module 2: Introduction

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM Version 1.2 May 28, 2009 Transmission Planning Department Revisions Rev. No. Date Description By Approval 1.0 8/10/06

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Standard TOP Transmission Operations

Standard TOP Transmission Operations A. Introduction 1. Title: Transmission Operations 2. Number: TOP-001-34 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection

More information

Critical Cyber Asset Identification Security Management Controls

Critical Cyber Asset Identification Security Management Controls Implementation Plan Purpose On January 18, 2008, FERC (or Commission ) issued Order. 706 that approved Version 1 of the Critical Infrastructure Protection Reliability Standards, CIP-002-1 through CIP-009-1.

More information

Misoperations Information Data Analysis System (MIDAS)

Misoperations Information Data Analysis System (MIDAS) Misoperations Information Data Analysis System (MIDAS) End User Guide June 2016 NERC Report Title Report Date I Table of Contents Preface... iii Chapter 1 Reporting Obligations...1 Entities Obligated to

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Essential Reliability Services and the Evolving Bulk-Power System -- Primary Frequency Response ) ) ) Docket No. RM16-6-000 SUPPLEMENTAL

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Introduction. Lesson 1 Access and Basic Navigation

Introduction. Lesson 1 Access and Basic Navigation Introduction Hello and Welcome to PRA s etmf Basics for External Users This tutorial is designed to provide you with a basic overview of PRA s etmf 3 System that you will be using to access your Trial

More information

Essential Reliability Services NERC Staff Report

Essential Reliability Services NERC Staff Report Essential Reliability Services NERC Staff Report Mark Lauby, Senior Vice President and Chief Reliability Officer Annual Meeting of the National Conference of State Legislators August 20, 2014 About NERC

More information