Disturbance Monitoring and

Size: px
Start display at page:

Download "Disturbance Monitoring and"

Transcription

1 PRC R1 Notification Disturbance Monitoring and Reporting Requirements Compliance Spring Workshop May 10, 2017

2 Objectives This presentation will discuss: Requirement R1 Part 1.2 notifications Definition of Element Application of Bulk Electric System (BES) bus from Attachment 1 Notification requirements for transmission lines owned by an adjacent Transmission Owner (ATO) 2

3 PRC Disturbance Monitoring and Reporting Requirements Purpose: To have adequate data available to facilitate analysis of Bulk Electric System (BES) Disturbances. Effective Date: July 1, 2016 for R1 3

4 Requirement R1 R1. Each Transmission Owner (TO) shall: 1.1. Identify BES buses for which sequence of events recording (SER) and fault recording (FR) data is required by using the methodology in PRC-002-2, Attachment 1. 4

5 Requirement R1 (continued) R1. Each Transmission Owner (TO) shall: 1.2. Notify other owners of BES Elements connected to those BES buses, if any, within 90-calendar days of completion of Part 1.1, that those BES Elements require SER data and/or FR data. 5

6 Requirement R1 (continued) R1. Each Transmission Owner (TO) shall: 1.3. Re-evaluate all BES buses at least once every five calendar years in accordance with Part 1.1 and notify other owners, if any, in accordance with Part 1.2, and implement the re-evaluated list of BES buses as per the Implementation Plan. 6

7 Definition of Element Glossary of Terms Used in NERC Reliability Standards: Element Any electrical device with terminals that may be connected to other electrical devices such as a generator, transformer, circuit breaker, bus section, or transmission line. An Element may be comprised of one or more components. 7

8 Application of BES bus Attachment 1, Step 1: BES bus For the purposes of this standard, a single BES bus includes physical buses with breakers connected at the same voltage level within the same physical location sharing a common ground grid. These buses may be modeled or represented by a single node in fault studies. For example, ring bus or breaker-and-a-half bus configurations are considered to be a single bus. 8

9 Application Question? Is notification to the ATO required under R1 Part 1.2 for the situation described below: The TO identifies a BES bus for which SER and FR data is required under Part 1.1 of R1 The BES bus is a ring bus (or breaker-and-a-half) with multiple transmission lines, and one of the transmission lines is owned by an ATO The ATO owns the line conductor, which connects to a disconnect switch, owned by the TO The disconnect switch is connected to a bus section of the BES bus, and is connected in series with the transmission line 9

10 One Line Diagram Ring Bus Point of interconnection 10

11 Notification Requirement In this example: The ATO owns part of the transmission line The transmission line is a BES Element The transmission line is connected to the BES bus R1 Part Notify other owners of BES Elements connected to those BES buses, if any, within 90-calendar days of completion of Part 1.1, that those BES Elements require SER data and/or FR data. 11

12 Notification Requirement (continued) Therefore, the TO must notify the ATO within 90-calendar of identifying the BES bus in Part 1.1. Agreed to by all eight regions and NERC 12

13 Highlights A transmission line is an Element For PRC-002-2, ring bus and breaker-and-a-half bus configurations are considered to be a single BES bus Notification to ATOs is required, even if they only own the transmission line conductor 13

14 Questions? Scott Knewasser (813)

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Wksheet 1 PRC-002-2 Disturbance Moniting and Repting Requirements This section to be completed by the Compliance Enfcement Authity. Audit ID: Registered Entity: NCR Number: Compliance

More information

Mapping of Requirements from PRC (ii) to PRC Project System Protection Coordination

Mapping of Requirements from PRC (ii) to PRC Project System Protection Coordination Mapping of Requirements from PRC-001-1.1(ii) to PRC-027-1 Project 2007-06 System Protection Coordination Requirement in BOT Adopted PRC 001 1.1(ii) Action Taken Requirement or Language in Proposed PRC

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

Project Consideration of Commission Directives in Order No. 693

Project Consideration of Commission Directives in Order No. 693 Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action

Standard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action Mapping Document Mapping Document Showing of PRC-001-2 System Protection Coordination to PRC-027-1 Protection System Coordination for Performance During Faults Updated 10-31 to reflect changes made to

More information

FRCC Disturbance Monitoring Equipment Outage Reporting

FRCC Disturbance Monitoring Equipment Outage Reporting FRCC Disturbance Monitoring Equipment Outage FRCC-RE-OP-004-I Effective Date: May 30, 2018 Version: Inactive 3000 Bayport Drive, Suite 600 Tampa, Florida 33607-8410 (813) 289-5644 - Phone (813) 289-5646

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Wksheet 1 PRC-002-2 Disturbance Moniting and Repting Requirements This section to be completed by the Compliance Enfcement Authity. Audit ID: Registered Entity: NCR Number: Compliance

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered

More information

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project ) Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic

More information

Implementation Plan for COM-001-2

Implementation Plan for COM-001-2 Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.

More information

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010

NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission

More information

Transmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel

Transmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel Utility Bulletin: TD-1013B-002 Publication Date: 07/03/2012 Rev: 0 Direct Transfer Trip (DTT) Telecommunication Options Summary Interconnection partners (customers) are requesting additional options for

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR

More information

DRAFT Reliability Standard Audit Worksheet 1

DRAFT Reliability Standard Audit Worksheet 1 DRAFT Reliability Standard Audit Worksheet 1 PRC-025-2 Generator Relay Loadability This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR Number: Compliance

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered

More information

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES

Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Agenda Item 1 Administrative Items AQITF Chairman Jim McAvoy called the meeting to order at 9:00 p.m.

More information

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection

i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection 1 Process PG&E Order No. 754 Analysis Receive Bus List from Planning that Meet the Criteria in Table A Protection Computes Actual Clearing

More information

About Georgia Transmission Corporation (GTC)

About Georgia Transmission Corporation (GTC) About Georgia Transmission Corporation (GTC) Transmission-only, not-for-profit cooperative Formed in March 1997 from the restructuring of Oglethorpe Power Corporation (OPC) GTC provides network transmission

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013

Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013 Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

Offshore BMU Configuration

Offshore BMU Configuration BMU Configuration Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Steve Curtis : System Operator

More information

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

SECTION TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

SECTION TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS SECTION 264313 - TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and

More information

PRC System Protection Coordination Supplementary Reference

PRC System Protection Coordination Supplementary Reference PRC-001-2 System Protection Coordination Supplementary Reference Contents: Disclaimer... 2 Generator Protection Devices or Elements that May Require Coordination with Transmission or Distribution Protective

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

Standard EOP Disturbance Reporting

Standard EOP Disturbance Reporting A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment

More information

COM Communications and Coordination

COM Communications and Coordination COM-002-2 Communications and Coordination February 27, 2014 Lonnie Lindekugel ~ SPP Jim Nail ~ City of Independence INTRODUCTION NERC Reliability Standard COM-002-2 (Communications and Coordination) serves

More information

A. Introduction. B. Requirements and Measures

A. Introduction. B. Requirements and Measures A. Introduction 1. Title: Communications 2. Number: COM-001-3 3. Purpose: To establish Communication capabilities necessary to maintain reliability. 4. Applicability: 4.1. Functional Entities: 4.1.1. Transmission

More information

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number

Date adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (

More information

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4

More information

PRC 001 R6 & R7.3 TFO s Notification Requirement

PRC 001 R6 & R7.3 TFO s Notification Requirement PRC 001 R6 & R7.3 TFO s Notification Requirement Diagram Information: 4 Substation Buses: SB1 is Substation Bus 1, SB2 is Substation Bus 2, SB3 is Substation Bus 3, and SB4 is Substation Bus 4. Terminals:

More information

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The

More information

Project Protection System Misoperations

Project Protection System Misoperations Protection System Misoperations Please DO NOT use this form. Please use the electronic comment form at the link below to submit comments on the second draft of the PRC-004-3 standard for Protection System

More information

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015

Order No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015 Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee

More information

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan

Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table

More information

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014

NERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014 Request for Data or Information Protection System Misoperation Data Collection August 14, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 15 Table of

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

WHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION. Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District

WHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION. Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District WHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District 5 WHAT IS A BUS? All connections are at the same voltage. WHAT IS A BUS? All

More information

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1

Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Revision History Version Effective Date Summary of Revisions

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

Unofficial Comment Form Project Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays)

Unofficial Comment Form Project Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays) Project 2007-17.3 Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays) Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the

More information

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents

More information

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM April 13, 2007 LIPA Facility Connection Requirements TABLE OF CONTENT I. INTRODUCTION...1 II. REFERENCE

More information

SIRIUS Overload Relays. SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link

SIRIUS Overload Relays. SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link Integrated Motor Protection for High-Feature Applications SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link SIRIUS Overload Relays www.siemens.com/sirius SIRIUS 3RB24

More information

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities

Concept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting

More information

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018

ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used

More information

Revision 6.0. Transmission Interconnection Guide

Revision 6.0. Transmission Interconnection Guide Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview

More information

136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ]

136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ] 136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Parts 39.10 and 40 [Docket No. RM11-16-000] Transmission Relay Loadability Reliability Standard (September 15, 2011)

More information

GE Multilin technical note

GE Multilin technical note GE Digital Energy Multilin GE Multilin technical note Synchronizing multiple buses using common voltage measurements GE publication number: GET-8532 Copyright 2009 GE Multilin Synchronizing multiple buses

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 FAC-003-4 Transmission Vegetation Management. Registered Entity Name: Applicable Function(s): Applicable only for TO and GO Compliance Monitoring Method: RSAW Version:

More information

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013

Consideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013 Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

Power System Protection Training

Power System Protection Training Power System Protection Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Refresh your knowledge of

More information

Bulk Electric System Definition Changes and Reporting

Bulk Electric System Definition Changes and Reporting Bulk Electric System Definition Changes and Reporting June 12, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Overview BES Definition Change BES Definition Reference

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Transmission Register PTO Admin User Manual. Version 1.0

Transmission Register PTO Admin User Manual. Version 1.0 Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6

More information

SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link

SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link Integrated Motor Protection for High-Feature Applications siemens.com/sirius Answers for industry. SIRIUS 3RB24

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

BCM ULP Breaker Communication Module

BCM ULP Breaker Communication Module DOCA0152EN-00 BCM ULP Breaker Communication Module Firmware Version 4.1.9 Release Note 05/2018 The information provided in this documentation contains general descriptions and/or technical characteristics

More information

Unofficial Comment Form

Unofficial Comment Form Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting

More information

String monitoring with CMS - Circuit monitoring system Increased productivity and improved maintenance of PV systems

String monitoring with CMS - Circuit monitoring system Increased productivity and improved maintenance of PV systems S O L A R S T R I N G M O N I TO R I N G String monitoring with CMS - Circuit monitoring system Increased productivity and improved maintenance of PV systems Solar plant operators are constantly facing

More information

WON Security Guideline

WON Security Guideline WON Security Guideline Data Exchange Work Group October 7, 2015 155 rth 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WON Security Guideline 1 Table of Contents Purpose... 1 Background... 1 Security

More information

REAL-TIME MONITORING DATA SPECIFICATION

REAL-TIME MONITORING DATA SPECIFICATION REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...

More information

Disturbance Monitoring Standard Drafting Team August 7, p.m. 5 p.m. August 8, a.m. 5 p.m. August 9, a.m. noon

Disturbance Monitoring Standard Drafting Team August 7, p.m. 5 p.m. August 8, a.m. 5 p.m. August 9, a.m. noon Disturbance Monitoring Standard Drafting Team August 7, 2007 1 p.m. 5 p.m. August 8, 2007 8 a.m. 5 p.m. August 9, 2007 8 a.m. noon Florida Power and Light Offices 700 Universe Blvd. Juno Beach, Florida

More information

Multilin P30 Phasor Data Concentrator

Multilin P30 Phasor Data Concentrator Multilin P30 Phasor Data Concentrator Secure high performance Phasor Data Concentrator (PDC) for wide area monitoring and dynamic disturbance analysis KEY BENEFITS Reduce deployment and operation cost

More information

HPC-9DJ

HPC-9DJ Guideline General Application of Switching Devices on Distribution Networks Standard Number: HPC-2AA-07-0001-2012 Document Control Author Name: Anthony Seneviratne Position: Senior Standards Engineer Document

More information

OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER

OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER Parsons Brinckerhoff Associates OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER A report prepared for 23 March 2007 Disclaimer Notice Report for

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

State of Reliability Report 2013

State of Reliability Report 2013 State of Reliability Report 2013 Jessica Bian, Director of Performance Analysis Reliability Assessment and Performance Analysis (RAPA), NERC Risk Issues Steering Committee Meeting, July 11-12, 2013 State

More information

TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018

TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018 TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements FRCC Spring RE Workshop April 17-18, 2018 Objectives Background Reference Documents TOP-001-3 to TOP-001-4 Changes o R10 (TOP) Monitoring

More information

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document

CIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides

More information

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION

Exercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION Exercise 2 Single Bus Scheme EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with electric power substations using the single bus scheme with bus section circuit breakers.

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

SECTION SURGE PROTECTION DEVICES. A. Section includes Surge Protection Devices for low-voltage power, control, and communication equipment.

SECTION SURGE PROTECTION DEVICES. A. Section includes Surge Protection Devices for low-voltage power, control, and communication equipment. SECTION 26 43 00 SURGE PROTECTION DEVICES PART 1 - GENERAL 1.1 SUMMARY A. Section includes Surge Protection Devices for low-voltage power, control, and communication equipment. 1.2 DEFINITIONS A. ATS:

More information

Project Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018

Project Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018 Project 2017-01 Modifications to BAL-003-1.1 Frequency Response and Frequency Bias Setting Industry Webinar December 18, 2018 Administrative Items North American Electric Reliability Corporation (NERC)

More information

Electric Transmission Reliability

Electric Transmission Reliability 1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at

More information

NERC and Regional Coordination Update

NERC and Regional Coordination Update NERC and Regional Coordination Update Mark Kuras Sr. Lead Engineer, NERC and Regional Coordination Planning Committee April 7, 2016 NERC Standards Under Development Standards Project Activity Due Date

More information

NPCC Regional Reliability Reference Directory # 4 Bulk Power System Protection Criteria

NPCC Regional Reliability Reference Directory # 4 Bulk Power System Protection Criteria NPCC Regional Reliability Reference Directory # 4 Task Force on System Protection Revision Review Record: December 1 st, 2009 September 30 th, 2015 Adopted by the Members of the Northeast Power Coordinating

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Facility Connection Requirements

Facility Connection Requirements SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...

More information

Common Departures Interconnecting Facilities Requirements

Common Departures Interconnecting Facilities Requirements Welcome to our e-rew Express. In our last issue, we discussed the common departures on metering installation requirements. This time, we would like to discuss the common departures on the customer low

More information

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation

Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation 111 Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation Z. Gajić (ABB, Sweden) JP Wang / PW Gong / YS Xu (ABB China) ZX Zhou (CERPI, China) Summary Power utilities

More information

Miniature Circuit Breakers for Railway Applications

Miniature Circuit Breakers for Railway Applications Siemens AG 00 for Railway Applications BETA Low-Voltage Circuit Protection The miniature circuit breakers are used in fixed railway systems and rolling stock for protecting system components against overcurrent

More information

JEA. Facility Connection Requirements

JEA. Facility Connection Requirements JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities

More information

Blackstart Hardware-in-the-loop Relay Testing Platform

Blackstart Hardware-in-the-loop Relay Testing Platform 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Blackstart Hardware-in-the-loop Relay Testing Platform R. LIU R. SUN M. TANIA Washington

More information

Commission Testing Methods for Protection Systems

Commission Testing Methods for Protection Systems Commission Testing Methods for Protection Systems Tom Ernst GE Grid Solutions Ken Sletten Minnesota Power Abstract Commission testing should be designed to assure that the protection system is set and

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information