Disturbance Monitoring and
|
|
- Veronica Skinner
- 5 years ago
- Views:
Transcription
1 PRC R1 Notification Disturbance Monitoring and Reporting Requirements Compliance Spring Workshop May 10, 2017
2 Objectives This presentation will discuss: Requirement R1 Part 1.2 notifications Definition of Element Application of Bulk Electric System (BES) bus from Attachment 1 Notification requirements for transmission lines owned by an adjacent Transmission Owner (ATO) 2
3 PRC Disturbance Monitoring and Reporting Requirements Purpose: To have adequate data available to facilitate analysis of Bulk Electric System (BES) Disturbances. Effective Date: July 1, 2016 for R1 3
4 Requirement R1 R1. Each Transmission Owner (TO) shall: 1.1. Identify BES buses for which sequence of events recording (SER) and fault recording (FR) data is required by using the methodology in PRC-002-2, Attachment 1. 4
5 Requirement R1 (continued) R1. Each Transmission Owner (TO) shall: 1.2. Notify other owners of BES Elements connected to those BES buses, if any, within 90-calendar days of completion of Part 1.1, that those BES Elements require SER data and/or FR data. 5
6 Requirement R1 (continued) R1. Each Transmission Owner (TO) shall: 1.3. Re-evaluate all BES buses at least once every five calendar years in accordance with Part 1.1 and notify other owners, if any, in accordance with Part 1.2, and implement the re-evaluated list of BES buses as per the Implementation Plan. 6
7 Definition of Element Glossary of Terms Used in NERC Reliability Standards: Element Any electrical device with terminals that may be connected to other electrical devices such as a generator, transformer, circuit breaker, bus section, or transmission line. An Element may be comprised of one or more components. 7
8 Application of BES bus Attachment 1, Step 1: BES bus For the purposes of this standard, a single BES bus includes physical buses with breakers connected at the same voltage level within the same physical location sharing a common ground grid. These buses may be modeled or represented by a single node in fault studies. For example, ring bus or breaker-and-a-half bus configurations are considered to be a single bus. 8
9 Application Question? Is notification to the ATO required under R1 Part 1.2 for the situation described below: The TO identifies a BES bus for which SER and FR data is required under Part 1.1 of R1 The BES bus is a ring bus (or breaker-and-a-half) with multiple transmission lines, and one of the transmission lines is owned by an ATO The ATO owns the line conductor, which connects to a disconnect switch, owned by the TO The disconnect switch is connected to a bus section of the BES bus, and is connected in series with the transmission line 9
10 One Line Diagram Ring Bus Point of interconnection 10
11 Notification Requirement In this example: The ATO owns part of the transmission line The transmission line is a BES Element The transmission line is connected to the BES bus R1 Part Notify other owners of BES Elements connected to those BES buses, if any, within 90-calendar days of completion of Part 1.1, that those BES Elements require SER data and/or FR data. 11
12 Notification Requirement (continued) Therefore, the TO must notify the ATO within 90-calendar of identifying the BES bus in Part 1.1. Agreed to by all eight regions and NERC 12
13 Highlights A transmission line is an Element For PRC-002-2, ring bus and breaker-and-a-half bus configurations are considered to be a single BES bus Notification to ATOs is required, even if they only own the transmission line conductor 13
14 Questions? Scott Knewasser (813)
Unofficial Comment Form Project Disturbance Monitoring
Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Wksheet 1 PRC-002-2 Disturbance Moniting and Repting Requirements This section to be completed by the Compliance Enfcement Authity. Audit ID: Registered Entity: NCR Number: Compliance
More informationMapping of Requirements from PRC (ii) to PRC Project System Protection Coordination
Mapping of Requirements from PRC-001-1.1(ii) to PRC-027-1 Project 2007-06 System Protection Coordination Requirement in BOT Adopted PRC 001 1.1(ii) Action Taken Requirement or Language in Proposed PRC
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationPRC Coordination of Protection Systems for Performance During Faults
PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To
More informationProject Consideration of Commission Directives in Order No. 693
Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationStandard: PRC System Protection Coordination Requirement in Approved Standard Translation to New Standard or Other Action
Mapping Document Mapping Document Showing of PRC-001-2 System Protection Coordination to PRC-027-1 Protection System Coordination for Performance During Faults Updated 10-31 to reflect changes made to
More informationFRCC Disturbance Monitoring Equipment Outage Reporting
FRCC Disturbance Monitoring Equipment Outage FRCC-RE-OP-004-I Effective Date: May 30, 2018 Version: Inactive 3000 Bayport Drive, Suite 600 Tampa, Florida 33607-8410 (813) 289-5644 - Phone (813) 289-5646
More informationSupplemental Information
Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Wksheet 1 PRC-002-2 Disturbance Moniting and Repting Requirements This section to be completed by the Compliance Enfcement Authity. Audit ID: Registered Entity: NCR Number: Compliance
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered
More informationUnofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )
Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic
More informationImplementation Plan for COM-001-2
Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.
More informationNERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010
Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission
More informationTransmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel
Utility Bulletin: TD-1013B-002 Publication Date: 07/03/2012 Rev: 0 Direct Transfer Trip (DTT) Telecommunication Options Summary Interconnection partners (customers) are requesting additional options for
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR
More informationDRAFT Reliability Standard Audit Worksheet 1
DRAFT Reliability Standard Audit Worksheet 1 PRC-025-2 Generator Relay Loadability This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR Number: Compliance
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationInformation Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered
More informationSouthwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES
Southwest Power Pool AQ IMPROVEMENT TASK FORCE MEETING June 5, 2013, 9-11am Net Conference MINUTES Agenda Item 1 Administrative Items AQITF Chairman Jim McAvoy called the meeting to order at 9:00 p.m.
More informationi-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection
i-pcgrid Workshop 2014 PG&E Order No. 754 Analysis: Protection 1 Process PG&E Order No. 754 Analysis Receive Bus List from Planning that Meet the Criteria in Table A Protection Computes Actual Clearing
More informationAbout Georgia Transmission Corporation (GTC)
About Georgia Transmission Corporation (GTC) Transmission-only, not-for-profit cooperative Formed in March 1997 from the restructuring of Oglethorpe Power Corporation (OPC) GTC provides network transmission
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationApproval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9
PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6
More informationProposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time Study Models November 12, 2013
Proposal for Development and Use of Node- Breaker Topology Representations for Offline and Real-time November 12, 2013 Rationale Background Interconnection wide powerflow and dynamics cases are currently
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationOffshore BMU Configuration
BMU Configuration Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Steve Curtis : System Operator
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationSECTION TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS
SECTION 264313 - TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and
More informationPRC System Protection Coordination Supplementary Reference
PRC-001-2 System Protection Coordination Supplementary Reference Contents: Disclaimer... 2 Generator Protection Devices or Elements that May Require Coordination with Transmission or Distribution Protective
More informationDisclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...
More informationStandard EOP Disturbance Reporting
A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment
More informationCOM Communications and Coordination
COM-002-2 Communications and Coordination February 27, 2014 Lonnie Lindekugel ~ SPP Jim Nail ~ City of Independence INTRODUCTION NERC Reliability Standard COM-002-2 (Communications and Coordination) serves
More informationA. Introduction. B. Requirements and Measures
A. Introduction 1. Title: Communications 2. Number: COM-001-3 3. Purpose: To establish Communication capabilities necessary to maintain reliability. 4. Applicability: 4.1. Functional Entities: 4.1.1. Transmission
More informationDate adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number
Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (
More informationPG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.
Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4
More informationPRC 001 R6 & R7.3 TFO s Notification Requirement
PRC 001 R6 & R7.3 TFO s Notification Requirement Diagram Information: 4 Substation Buses: SB1 is Substation Bus 1, SB2 is Substation Bus 2, SB3 is Substation Bus 3, and SB4 is Substation Bus 4. Terminals:
More informationFacility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements
Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The
More informationProject Protection System Misoperations
Protection System Misoperations Please DO NOT use this form. Please use the electronic comment form at the link below to submit comments on the second draft of the PRC-004-3 standard for Protection System
More informationOrder No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015
Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee
More informationQuébec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan
Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table
More informationNERC Request for Data or Information: Protection System Misoperation Data Collection August 14, 2014
Request for Data or Information Protection System Misoperation Data Collection August 14, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com 1 of 15 Table of
More informationGeneration, Transmission, and End User Facilities
Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3
More informationWHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION. Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District
WHAT IS A BUS? FUNDAMENTALS OF BUS PROTECTION Kevin Wright Senior Protection Engineer Sacramento Municipal Utility District 5 WHAT IS A BUS? All connections are at the same voltage. WHAT IS A BUS? All
More informationGuidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1
Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Revision History Version Effective Date Summary of Revisions
More informationStudies Overview and Data Requirements. Robert Pan
Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application
More informationUnofficial Comment Form Project Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays)
Project 2007-17.3 Protection System Maintenance and Testing Phase 3 (Sudden Pressure Relays) Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the
More informationRequirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company
Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents
More informationBULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM
BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM April 13, 2007 LIPA Facility Connection Requirements TABLE OF CONTENT I. INTRODUCTION...1 II. REFERENCE
More informationSIRIUS Overload Relays. SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link
Integrated Motor Protection for High-Feature Applications SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link SIRIUS Overload Relays www.siemens.com/sirius SIRIUS 3RB24
More informationConcept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities
Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting
More informationERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018
ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used
More informationRevision 6.0. Transmission Interconnection Guide
Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview
More information136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts and 40. [Docket No. RM ]
136 FERC 61,187 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Parts 39.10 and 40 [Docket No. RM11-16-000] Transmission Relay Loadability Reliability Standard (September 15, 2011)
More informationGE Multilin technical note
GE Digital Energy Multilin GE Multilin technical note Synchronizing multiple buses using common voltage measurements GE publication number: GET-8532 Copyright 2009 GE Multilin Synchronizing multiple buses
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 FAC-003-4 Transmission Vegetation Management. Registered Entity Name: Applicable Function(s): Applicable only for TO and GO Compliance Monitoring Method: RSAW Version:
More informationConsideration of Issues and Directives Project Modeling Data (MOD B) October 7, 2013
Project 2010-03 Modeling Data (MOD B) October 7, 2013 Para 290. Project 2010-03 - Modeling Data The Commission directs public utilities, working through NERC, to modify the reliability standards MOD- 010
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationPower System Protection Training
Power System Protection Training Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Refresh your knowledge of
More informationBulk Electric System Definition Changes and Reporting
Bulk Electric System Definition Changes and Reporting June 12, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Overview BES Definition Change BES Definition Reference
More informationThis section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationTransmission Register PTO Admin User Manual. Version 1.0
Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6
More informationSIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link
SIRIUS 3RB24 Solid-State Overload Relays with Complete Starter Functionality via IO-Link Integrated Motor Protection for High-Feature Applications siemens.com/sirius Answers for industry. SIRIUS 3RB24
More informationSMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2
SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:
More informationBCM ULP Breaker Communication Module
DOCA0152EN-00 BCM ULP Breaker Communication Module Firmware Version 4.1.9 Release Note 05/2018 The information provided in this documentation contains general descriptions and/or technical characteristics
More informationUnofficial Comment Form
Generator Requirements at the Transmission Interface (Project 2010-07) Please DO NOT use this form to submit comments. Please use the electronic comment form to submit comments on the first formal posting
More informationString monitoring with CMS - Circuit monitoring system Increased productivity and improved maintenance of PV systems
S O L A R S T R I N G M O N I TO R I N G String monitoring with CMS - Circuit monitoring system Increased productivity and improved maintenance of PV systems Solar plant operators are constantly facing
More informationWON Security Guideline
WON Security Guideline Data Exchange Work Group October 7, 2015 155 rth 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WON Security Guideline 1 Table of Contents Purpose... 1 Background... 1 Security
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationDisturbance Monitoring Standard Drafting Team August 7, p.m. 5 p.m. August 8, a.m. 5 p.m. August 9, a.m. noon
Disturbance Monitoring Standard Drafting Team August 7, 2007 1 p.m. 5 p.m. August 8, 2007 8 a.m. 5 p.m. August 9, 2007 8 a.m. noon Florida Power and Light Offices 700 Universe Blvd. Juno Beach, Florida
More informationMultilin P30 Phasor Data Concentrator
Multilin P30 Phasor Data Concentrator Secure high performance Phasor Data Concentrator (PDC) for wide area monitoring and dynamic disturbance analysis KEY BENEFITS Reduce deployment and operation cost
More informationHPC-9DJ
Guideline General Application of Switching Devices on Distribution Networks Standard Number: HPC-2AA-07-0001-2012 Document Control Author Name: Anthony Seneviratne Position: Senior Standards Engineer Document
More informationOTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER
Parsons Brinckerhoff Associates OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER A report prepared for 23 March 2007 Disclaimer Notice Report for
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationState of Reliability Report 2013
State of Reliability Report 2013 Jessica Bian, Director of Performance Analysis Reliability Assessment and Performance Analysis (RAPA), NERC Risk Issues Steering Committee Meeting, July 11-12, 2013 State
More informationTOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018
TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements FRCC Spring RE Workshop April 17-18, 2018 Objectives Background Reference Documents TOP-001-3 to TOP-001-4 Changes o R10 (TOP) Monitoring
More informationCIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides
More informationExercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION
Exercise 2 Single Bus Scheme EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with electric power substations using the single bus scheme with bus section circuit breakers.
More informationWECC Criterion MOD-(11 and 13)-WECC-CRT-1.1
WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements
More informationSECTION SURGE PROTECTION DEVICES. A. Section includes Surge Protection Devices for low-voltage power, control, and communication equipment.
SECTION 26 43 00 SURGE PROTECTION DEVICES PART 1 - GENERAL 1.1 SUMMARY A. Section includes Surge Protection Devices for low-voltage power, control, and communication equipment. 1.2 DEFINITIONS A. ATS:
More informationProject Modifications to BAL Frequency Response and Frequency Bias Setting. Industry Webinar December 18, 2018
Project 2017-01 Modifications to BAL-003-1.1 Frequency Response and Frequency Bias Setting Industry Webinar December 18, 2018 Administrative Items North American Electric Reliability Corporation (NERC)
More informationElectric Transmission Reliability
1965 Northeast Blackout #1 History of NERC 1968 North American Electric Reliability Council (NERC) formed Voluntary compliance with reliability standards 2003 Northeast Blackout #2 2006 NERC accepted at
More informationNERC and Regional Coordination Update
NERC and Regional Coordination Update Mark Kuras Sr. Lead Engineer, NERC and Regional Coordination Planning Committee April 7, 2016 NERC Standards Under Development Standards Project Activity Due Date
More informationNPCC Regional Reliability Reference Directory # 4 Bulk Power System Protection Criteria
NPCC Regional Reliability Reference Directory # 4 Task Force on System Protection Revision Review Record: December 1 st, 2009 September 30 th, 2015 Adopted by the Members of the Northeast Power Coordinating
More informationSMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM
SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the
More informationFacility Connection Requirements
SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...
More informationCommon Departures Interconnecting Facilities Requirements
Welcome to our e-rew Express. In our last issue, we discussed the common departures on metering installation requirements. This time, we would like to discuss the common departures on the customer low
More informationVerification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation
111 Verification of Utility Requirements on Modern Numerical Busbar Protection by Dynamic Simulation Z. Gajić (ABB, Sweden) JP Wang / PW Gong / YS Xu (ABB China) ZX Zhou (CERPI, China) Summary Power utilities
More informationMiniature Circuit Breakers for Railway Applications
Siemens AG 00 for Railway Applications BETA Low-Voltage Circuit Protection The miniature circuit breakers are used in fixed railway systems and rolling stock for protecting system components against overcurrent
More informationJEA. Facility Connection Requirements
JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities
More informationBlackstart Hardware-in-the-loop Relay Testing Platform
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Blackstart Hardware-in-the-loop Relay Testing Platform R. LIU R. SUN M. TANIA Washington
More informationCommission Testing Methods for Protection Systems
Commission Testing Methods for Protection Systems Tom Ernst GE Grid Solutions Ken Sletten Minnesota Power Abstract Commission testing should be designed to assure that the protection system is set and
More informationJanuary 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.
California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California
More informationNERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum
Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission
More information