COM Communications and Coordination
|
|
- Kimberly Armstrong
- 5 years ago
- Views:
Transcription
1 COM Communications and Coordination February 27, 2014 Lonnie Lindekugel ~ SPP Jim Nail ~ City of Independence
2 INTRODUCTION NERC Reliability Standard COM (Communications and Coordination) serves an important purpose by requiring users, owners and operators to implement the necessary communications and coordination among Registered Entities. 2
3 Why do we care? Mistakes DO happen! EPRI study of 400 switching mishaps 19% due to communication failures. Study of dispatchers at 18 utilities 18% operator errors due to communication issues. Recommendation 26 of the 2003 Blackout Report. 3
4 Purpose: To ensure Balancing Authorities, Transmission Operators and Generator Operators have adequate communications and that these communications capabilities are staffed and available for addressing a realtime emergency condition. To ensure communications by operating personnel are effective. Applicability: Reliability Coordinators (RCs) Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators (GOPs) 4
5 Common NERC Terms and Definitions Reliability Directive: A communication initiated by a Reliability Coordinator, Transmission Operator, or Balancing Authority where action by the recipient is necessary to address an Emergency or Adverse Reliability Impact. 1 NERC Glossary of Terms. Retrieved from: Emergency: Any abnormal system condition that requires automatic or immediate manual action to prevent or limit the failure of transmission facilities or generation supply that could adversely affect the reliability of the Bulk Electric System. Adverse Reliability Impact: The impact of an event that results in frequencyrelated instability; unplanned tripping of load or generation; or uncontrolled separation or cascading outages that affects a widespread area of the Interconnection. 5
6 COM includes the following requirements: R1. Each Transmission Operator, Balancing Authority, and Generator Operator shall have communications (voice and data links) with appropriate Reliability Coordinators, Balancing Authorities, and Transmission Operators. Such communications shall be staffed and available for addressing a real-time emergency condition. R1.1. Each Balancing Authority and Transmission Operator shall notify its Reliability Coordinator, and all other potentially affected Balancing Authorities and Transmission Operators through predetermined communication paths of any condition that could threaten the reliability of its area or when firm load shedding is anticipated. R2. Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall issue directives in a clear, concise, and definitive manner; shall ensure the recipient of the directive repeats the information back correctly; and shall acknowledge the response as correct or repeat the original statement to resolve any misunderstandings. 6
7 Evaluating COM Requirement 1: R1. Each Transmission Operator, Balancing Authority, and Generator Operator shall have communications (voice and data links) with appropriate Reliability Coordinators, Balancing Authorities, and Transmission Operators. Such communications shall be staffed and available for addressing a real-time emergency condition. Analysis: Requirement 1, Part 1, describes which entities need communications (voice and data links) with other applicable entities by the use of the word appropriate. The TOPs, BAs and GOPs should have clear knowledge of who their RCs, BAs and TOPs are and should be able to identify the voice and data links between the entities through observation of the communication channels on the system operator s desk and/or by diagrams depicting the communication paths. Analysis: Requirement 1, Part 2, describes that TOPs, BAs and GOPs are required to have personnel available through their communications channels to address real-time emergency conditions. 7
8 Evaluating COM Requirement 1.1: R1.1 Each Balancing Authority and Transmission Operator shall notify its Reliability Coordinator, and all other potentially affected Balancing Authorities and Transmission Operators through predetermined communication paths of any condition that could threaten the reliability of its area or when firm load shedding is anticipated. Analysis: Sub-requirement 1.1 is event-driven and describes the communications required by the BAs and TOPs to notify their RC (and other potentially affected BAs and TOPs) of any condition that could threaten the reliability of their area through predetermined communication paths or in any situation in which firm load shedding is anticipated. 8
9 Evaluating COM , Requirement 2: R2. Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall issue directives in a clear, concise, and definitive manner; shall ensure the recipient of the directive repeats the information back correctly; and shall acknowledge the response as correct or repeat the original statement to resolve any misunderstandings. Analysis: Part 1: shall issue directives in a clear, concise, and definitive manner; Part 2: shall ensure the recipient of the directive repeats the information back correctly; Part 3: shall acknowledge the response as correct or repeat the original statement to resolve any misunderstandings. 9
10 The key objectives of this application guide are: To ensure BAs, TOPs and GOPs have adequate communication capabilities. To ensure BAs, TOPs and GOPs have communications (voice and data links) with their appropriate RCs, BAs, TOPs and GOPs. To ensure that entities are staffed for addressing real-time emergencies. To ensure communications by operating personnel are effective. Clarify terminology. Provide examples of proper communications in order to meet the requirements of the COM Standard. Provide examples of adequate communication capabilities (voice and data links) available for addressing real-time emergency conditions. 10
11 Questions 11
Standard COM-002-2a Communications and Coordination
A. Introduction 1. Title: Communication and Coordination 2. Number: COM-002-2a 3. Purpose: To ensure Balancing Authorities, Transmission Operators, and Generator Operators have adequate communications
More informationStandards Authorization Request Form
Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.
More informationCOM Interpersonal Communications Capabilities
COM-001-3 Interpersonal Communications Capabilities 1 Background In the FERC Notice of Proposed Rulemaking (NOPR) for COM-001-2, the Commission asked for comments on whether the standard should be modified
More informationUnofficial Comment Form Project Operating Personnel Communications Protocols COM-002-4
Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Please DO NOT use this form. Please use the electronic comment form to submit comments on the proposed draft COM 002 4 (Operating
More informationProject Posting 8 Frequently Asked Questions Guide
Project 2007-02 Posting 8 Frequently Asked Questions Guide General Questions 1. What were the inputs that drove the development of posting 8 of Project 2007-02? The NERC Board of Trustees November 7 th,
More informationProject Consideration of Commission Directives in Order No. 693
Project 2009-02 Consideration of Commission Directives in Order Order P 905-906 Further, consistent with the NOPR, the Commission directs the ERO to modify IRO-002-1 to require a minimum set of tools that
More informationStandard TOP Transmission Operations
A. Introduction 1. Title: Transmission Operations 2. Number: TOP-001-34 3. Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection
More informationGuidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1
Guidelines for Submitting NERC Reliability Standards Required Documents to the SPP Reliability Coordinator and the SPP Balancing Authority Version 1 Revision History Version Effective Date Summary of Revisions
More informationNERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM September 6, 2013
NERC Management Response to the Questions of the NERC Board of Trustees on Reliability Standard COM-003-1 September 6, 2013 At the August 14-15, 2013 meeting of the Board of Trustees ( Board ) of the North
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 CIP-002-5.1 Cyber Security BES Cyber System Categorization This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity: NCR
More informationCOM Operating Personnel Communications Protocols. October 31, 2013
COM-002-4 Operating Personnel Communications Protocols October 31, 2013 Agenda Introductory Remarks: Mark Lauby Project 2007 02 Background COM 002 4 Requirements Implementation Plan Compliance VSL/VRF
More informationImplementation Plan for COM-001-2
Defined Terms in the NERC Glossary The RC SDT proposes the following new definitions: Interpersonal Communication: Any medium that allows two or more individuals interact, consult, or exchange information.
More informationA. Introduction. B. Requirements and Measures
A. Introduction 1. Title: Communications 2. Number: COM-001-3 3. Purpose: To establish Communication capabilities necessary to maintain reliability. 4. Applicability: 4.1. Functional Entities: 4.1.1. Transmission
More informationStandard COM Communication and Coordination
A. Introduction 1. Title: Communication and Coordination 2. Number: COM-002-3 3. Purpose: To ensure Emergency communications between operating personnel are effective. 4. Applicability 4.1. Reliability
More informationSouthwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September
Southwest Power Pool Independent Coordinator of Transmission RELIABILITY PLAN for Entergy in the Southeastern Electric Reliability Council September 23, 2009 TABLE OF CONTENTS INTRODUCTION A. RESPONSIBILITIES
More informationUnofficial Comment Form Project Operating Personnel Communications Protocols COM Operating Personnel Communications Protocols
Project 2007-02 Operating Personnel Communications Protocols COM-002-4 Operating Personnel Communications Protocols Please DO NOT use this form. Please use the electronic comment form to submit comments
More informationStandards Authorization Request Justification
Standards Authorization Request Justification Project 2009-02 Real-time Monitoring and Analysis Capabilities NERC Report Title Report Date 1 of 30 3353 Peachtree Road NE Suite 600, North Tower Atlanta,
More informationViolation Risk Factor and Violation Severity Level Justification Project Modifications to CIP-008 Cyber Security Incident Reporting
Violation Risk Factor and Justification Project 2018-02 Modifications to CIP-008 Cyber Security Incident Reporting This document provides the standard drafting team s (SDT s) justification for assignment
More informationOfficial Comment Form Reliability Guideline: Generating Unit Operations During Complete Loss of Communications
Official Comment Form Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Please use this form to submit comments on the proposed Reliability Guideline: Generating
More informationTOP-010-1(i) Real-time Reliability Monitoring and Analysis Capabilities
A. Introduction 1. Title: Real-time Reliability Monitoring and Analysis Capabilities 2. Number: TOP-010-1(i) 3. Purpose: Establish requirements for Real-time monitoring and analysis capabilities to support
More informationViolation Risk Factor and Violation Severity Level Justifications Project Modifications to CIP Standards
Violation Risk Factor and Violation Severity Level Justifications Project 2016-02 Modifications to CIP Standards This document provides the standard drafting team s (SDT s) justification for assignment
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Wksheet 1 EOP-008-2 Loss of Control Center Functionality This section to be completed by the Compliance Enfcement Authity. Audit ID: Registered Entity: NCR Number: Compliance
More informationReliability Coordinator Procedure PURPOSE... 1
No. RC0550 Restriction: Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 1.1.1. CAISO RC... 2 1.1.2. RC Working Groups... 2 1.1.3. Operationally Affected Parties... 2 1.1.4. RC Oversight Committee...
More informationChapter X Security Performance Metrics
DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the
More informationprimary Control Center, for the exchange of Real-time data with its Balancing
A. Introduction 1. Title: Reliability Coordination Monitoring and Analysis 2. Number: IRO-002-5 3. Purpose: To provide System Operators with the capabilities necessary to monitor and analyze data needed
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 CIP-012-1 Cyber Security Communications between Control Centers This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered Entity:
More informationPeak Reliability. Reliability Coordinator Data Request and Specifications for Data Provision
Table of Contents I. Purpose... 2 II. Introduction... 2 III. Peak Roles and Responsibilities... 2 IV. Applicability and Obligations... 3 V. Questions and Comments... 6 VI. Data Request Spreadsheet... 6
More informationStandard Authorization Request Form
Standard Authorization Request Form Title of Proposed Standard: Project 2009-02: Real-time Reliability Monitoring and Analysis Capabilities Original Request Date: June 4, 2009 Revised Date: January 15,
More informationNERC and Regional Coordination Update
NERC and Regional Coordination Update Mark Kuras Sr. Lead Engineer, NERC and Regional Coordination Planning Committee April 7, 2016 NERC Standards Under Development Standards Project Activity Due Date
More informationTOP/IRO Standards. RC Users Group January 21, Vic Howell Manager, Operations Engineering Support
TOP/IRO Standards RC Users Group January 21, 2016 Vic Howell Manager, Operations Engineering Support Saad Malik Manager, Real-Time Operations Engineering New/Revised TOP & IRO Standards November 19, 2015,
More informationProject , COM Operating Personnel Communications Protocols Rationale and Technical Justification
Project 2007-02, COM-002-4 Operating Personnel Communications Protocols Rationale and Technical Justification Posting 8: Background and Justification for COM-002-4 Requirements The purpose of the proposed
More informationProposed Convention for Numbering of NERC Reliability Standards Draft September 9, 2004
Proposed Convention for ing of NERC Reliability s Draft September 9, 2004 Introduction The Version 0 Drafting Team proposes to initiate a new convention for numbering NERC reliability standards concurrent
More informationDate adopted/approved 02/08/2013 Custodian (entity responsible for maintenance and upkeep) Data Exchange Work Group. Web URL: Previous name/number
Document name Category Guideline for WECC Operations Network Node: Responsibilities and Procedures ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other (
More informationERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018
ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used
More information2017 MRO Performance Areas and an Update on Inherent Risk Assessments
MIDWEST RELIABILITY ORGANIZATION 2017 MRO Performance Areas and an Update on Inherent Risk Assessments Adam Flink, Risk Assessment and Mitigation Engineer November 16, 2016 Improving RELIABILITY and mitigating
More informationDisturbance Monitoring and
PRC-002-2 R1 Notification Disturbance Monitoring and Reporting Requirements Compliance Spring Workshop May 10, 2017 Objectives This presentation will discuss: Requirement R1 Part 1.2 notifications Definition
More informationNew Brunswick 2018 Annual Implementation Plan Version 1
New Brunswick Energy and Utilities Board Reliability Standards, Compliance and Enforcement Program New Brunswick 2018 Annual Implementation Plan Version 1 December 28, 2017 Table of Contents Version History...
More informationNovember 9, Revisions to the Violation Risk Factors for Reliability Standards IRO and TOP
!! November 9, 2016 VIA ELECTRONIC FILING Jim Crone Director, Energy Division Manitoba Innovation, Energy and Mines 1200-155 Carlton Street Winnipeg MB R3C 3H8 RE: Revisions to the Violation Risk Factors
More informationComment Form for 1 st Draft of Standard for Backup Facilities (Project )
Comment Form for 1 st Draft of Standard for Backup Facilities (Project 2006-04) Please use this form to submit comments on the 1 st draft of the standards for Backup Facilities (Project 2006-04). Comments
More informationTitle. Critical Infrastructure Protection Getting Low with a Touch of Medium. CanWEA Operations and Maintenance Summit 2018.
Critical Infrastructure Protection Getting Low with a Touch of Medium Title CanWEA Operations and Maintenance Summit 2018 January 30, 2018 George E. Brown Compliance Manager Acciona Wind Energy Canada
More informationSupplemental Information
Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationProject Physical Security Directives Mapping Document
Document Background In Order No. 802 (final order on CIP-014-1 Physical Security), issued on November 20, 2014, FERC directed NERC to remove the term widespread from Reliability Standard CIP-014-1 or,
More informationTOP for Transmission Operators
Meeting Title Date TOP-001-4 for Transmission Operators Compliance Team Lead, Keith Smith Background Effective July 1, 2018 Replaces currently effective TOP-001-3 Modified to address reliability concerns
More informationWON Security Guideline
WON Security Guideline Data Exchange Work Group October 7, 2015 155 rth 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WON Security Guideline 1 Table of Contents Purpose... 1 Background... 1 Security
More information151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued April 23, 2015)
151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.
More informationTOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements. FRCC Spring RE Workshop April 17-18, 2018
TOP-001 v3 and v4 Monitoring Non-BES and Data Exchange Requirements FRCC Spring RE Workshop April 17-18, 2018 Objectives Background Reference Documents TOP-001-3 to TOP-001-4 Changes o R10 (TOP) Monitoring
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationStandard EOP Disturbance Reporting
A. Introduction 1. Title: Disturbance Reporting 2. Number: EOP-004-1 3. Purpose: Disturbances or unusual occurrences that jeopardize the operation of the Bulk Electric System, or result in system equipment
More informationProject Cyber Security - Order No. 791 Identify, Assess, and Correct; Low Impact; Transient Devices; and Communication Networks Directives
Project 2014-02 - Cyber Security - Order No. 791 Identify, Assess, and Correct; Low Impact; Transient Devices; and Communication Networks Directives Violation Risk Factor and Justifications The tables
More information5. Effective Date: The first day of the first calendar quarter after applicable regulatory approval.
Introduction 1. Title: IROL and SOL Mitigation in the ERCOT Region 2. Number: IRO-006-TRE-1 3. Purpose: To provide and execute transmission loading relief procedures that can be used to mitigate SOL or
More informationNERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016
NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons
More informationNB Appendix CIP NB-0 - Cyber Security Recovery Plans for BES Cyber Systems
This appendix establishes modifications to the FERC approved NERC standard CIP-009-6 for its specific application in New Brunswick. This appendix must be read with CIP-009-6 to determine a full understanding
More informationPhysical Security Reliability Standard Implementation
Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationNB Appendix CIP NB-0 - Cyber Security Personnel & Training
This appendix establishes modifications to the FERC approved NERC standard CIP-004-5.1 for its specific application in New Brunswick. This appendix must be read with CIP-004-5.1 to determine a full understanding
More informationStandard Development Timeline
CIP-002-6 Cyber Security BES Cyber System Categorization Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the
More informationQuébec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan Annual Implementation Plan
Québec Reliability Standards Compliance Monitoring and Enforcement Program Implementation Plan 2017 Annual Implementation Plan Effective Date: January 1, 2017 Approved by the Régie: December 1, 2016 Table
More informationCity of Grand Island Tuesday, February 28, 2017 Council Session
City of Grand Island Tuesday, February 28, 2017 Council Session Item G-6 #2017-50 - Approving Transmission Services Agreement with Nebraska Public Power District Staff Contact: Tim Luchsinger, Stacy Nonhof
More informationReliability Standard Audit Worksheet 1
Reliability Standard Audit Worksheet 1 PRC-004-3 Protection System Misoperation Identification and Correction This section to be completed by the Compliance Enforcement Authority. Audit ID: Registered
More informationCIP-014. JEA Compliance Approach. FRCC Fall Compliance Workshop Presenter Daniel Mishra
CIP-014 JEA Compliance Approach FRCC Fall Compliance Workshop Presenter Daniel Mishra Acronyms & Terminologies DHS Department of Homeland Security JEA It s not an acronym JSO Jacksonville Sheriff's Office
More informationNERC Overview and Compliance Update
NERC Overview and Compliance Update Eric Ruskamp Manager, Regulatory Compliance August 17, 2018 1 Agenda NERC Overview History Regulatory Hierarchy Reliability Standards Compliance Enforcement Compliance
More informationNERC and Regional Coordination Update. Operating Committee Preston Walker January 9, 2018
NERC and Regional Coordination Update Operating Committee Preston Walker January 9, 2018 Standards Project Action End Date Project 2017-07 Standards Alignment with Registration NERC Standards Under Development
More informationAgenda Event Analysis Subcommittee Conference Call
Agenda Event Analysis Subcommittee Conference Call October 23, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security
More informationPath Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor
Path Operations post WECC TOP 007 Rob Witham, WAPA RMR TSS Supervisor May 10, 2017 ISAS Salt Lake City, UT WECC Standard TOP 007 WECC 1a Title: System Operating Limits Purpose: To limit instances where
More informationBulk Electric System Definition Changes and Reporting
Bulk Electric System Definition Changes and Reporting June 12, 2014 Greg Sorenson, PE Senior Compliance Engineer gsorenson.re@spp.org 501.688.1713 Overview BES Definition Change BES Definition Reference
More informationOctober 2, CIP-014 Report Physical Security Protection for High Impact Control Centers Docket No. RM15-14-
October 2, 2017 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: CIP-014 Report Physical Security Protection for High Impact Control Centers
More informationTable of Contents. TOP TOP BA Data Request and Specification Guidelines. Operating Procedure
No. 3140 Table of Contents Purpose... 2 Responsibilities... 2 2. Scope/Applicability... 4 2.1 Background... 4 2.2 Scope / Applicability... 4 3. Detail... 5 3.1... 5 Introduction... 5 3.2 Data Specification
More informationStandards Authorization Request Form
Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.
More informationProcedure For NPCC Bulk Electric System Asset Database
Procedure For NPCC Bulk Electric System Asset Database Compliance Procedure 09 (CP-09) Revision 2 Table of Contents 1. Introduction and Purpose... 3 2. Responsibilities... 3 3. Overview... 3 4. Asset Database...
More informationCIP Cyber Security Critical Cyber Asset Identification. Rationale and Implementation Reference Document
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document NERC Cyber Security Standards Drafting Team for Order 706 December 2010 This document provides
More informationAgenda Event Analysis Subcommittee Conference Call
Agenda Event Analysis Subcommittee Conference Call August 14, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security
More informationCIP Physical Security What to Expect
CIP-014-2 Physical Security What to Expect March 28, 2017 Kevin Perry Director, Critical Infrastructure Protection Jeff Rooker Lead Compliance Engineer 1 Purpose To identify and protect Transmission stations
More informationDER Data Collection Guideline. Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017
DER Data Collection Guideline Rich Hydzik, DER Subgroup Lead ERSWG Meeting November 6, 2017 Since the August 3, 2017, Meeting Data Collection Guideline has been through two rounds of comment from DER Subgroup
More informationReliability Coordinator Procedure
No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...
More informationConcept White Paper. Concepts for Proposed Content of Eventual Standard(s) for Project : Real-Time Monitoring and Analysis Capabilities
Concept White Paper Concepts for Proposed Content of Eventual Standard(s) for Project 2009-02: Real-Time Monitoring and Analysis Capabilities Real-time Monitoring and Analysis Capabilities Standard Drafting
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationNERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010
Transmission Relay Loadability FERC Order 733 Project 2010-1313 NERC Relay Loadability Standard Reliability Standards Webinar November 23, 2010 Project Overview 2 Standards Involved PRC-023-2 Transmission
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationAvailable Transfer Capability Definitions and Determination
Available Transfer Capability Definitions and Determination A framework for determining available transfer capabilities of the interconnected transmission networks for a commercially viable electricity
More informationRELIABILITY OF THE BULK POWER SYSTEM
RELIABILITY OF THE BULK POWER SYSTEM Jim Burley, VP of Compliance, Mitigation and Standards October 26, 2011 Promoting RELIABILITY and Mitigating RISKS to the Bulk Power System Context In the Beginning-2003
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationWide Area Measurements & Control Systems
The 8 th Electric Power Control Centers Workshop June 5-8, 2005, Les Diablerets, Switzerland Wide Area Measurements & Control Systems NERC Security Coordinators and Interregional Security Network Nodes
More informationAgenda Event Analysis Subcommittee Conference Call
Agenda Event Analysis Subcommittee Conference Call September 11, 2013 11:00 a.m. 1:00 p.m. Eastern Ready Talk Conference Call and Web Meeting Information: Dial-In: 1-866-740-1260 Access Code: 6517175 Security
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE PENNSYLVANIA PUBLIC UTILITY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Physical Security Reliability : Standard : Docket No. RD14-15-000 COMMENTS OF THE PENNSYLVANIA PUBLIC UTILITY COMMISSION I. INTRODUCTION On
More informationERS Canada Service Guide. Version
ERS Canada Service Guide Version 2017.03.13 Contents 1. Introduction... 1 2. Service Features... 1 2.1. Call Flow... 1 2.2. Service Components... 1 2.3. Service Specifications... 2 2.4. Maintenance and
More informationBritish Columbia Utilities Commission Reliability Standards with Effective Dates adopted in British Columbia
Page 1 of 15 British Columbia Utilities Reliability Standards with s adopted in British Columbia BAL-001-2 Standard Real Power Balancing Control Performance R-14-16 July 1, 2016 BAL-002-1 1 Disturbance
More informationCIP Cyber Security Personnel & Training
A. Introduction 1. Title: Cyber Security Personnel & Training 2. Number: CIP-004-6 3. Purpose: To minimize the risk against compromise that could lead to misoperation or instability in the Bulk Electric
More informationIndividual William H. Chambliss, Operating Committee Virginia State Corporation Commission
or group. (77 Responses) Name (51 Responses) Organization (51 Responses) Group Name (26 Responses) Lead Contact (26 Responses) IF YOU WISH TO EXPRESS SUPPORT FOR ANOTHER ENTITY'S COMMENTS WITHOUT ENTERING
More informationGrid Security & NERC. Council of State Governments. Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016
Grid Security & NERC Council of State Governments The Future of American Electricity Policy Academy Janet Sena, Senior Vice President, Policy and External Affairs September 22, 2016 1965 Northeast blackout
More informationCIP Cyber Security Configuration Change Management and Vulnerability Assessments
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationPRC Coordination of Protection Systems for Performance During Faults
PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To
More informationCyber Threats? How to Stop?
Cyber Threats? How to Stop? North American Grid Security Standards Jessica Bian, Director of Performance Analysis North American Electric Reliability Corporation AORC CIGRE Technical Meeting, September
More informationDRAFT. Cyber Security Communications between Control Centers. March May Technical Rationale and Justification for Reliability Standard CIP-012-1
DRAFT Cyber Security Communications between Control Centers Technical Rationale and Justification for Reliability Standard CIP-012-1 March May 2018 NERC Report Title Report Date I Table of Contents Preface...
More informationMethods for Establishing IROLs Task Force
Methods for Establishing IROLs Task Force Progress Update Ryan D. Quint Senior Manager, Advanced Analytics and Modeling OC/PC Joint Meeting March 7, 2017 Background MEITF kicked off in December to: Address
More informationGrid Security & NERC
Grid Security & NERC Janet Sena, Senior Vice President, Policy and External Affairs Southern States Energy Board 2017 Associate Members Winter Meeting February 27, 2017 Recent NERC History Energy Policy
More informationrequirements in a NERC or Regional Reliability Standard.
CIP 002 5.1 Cyber Security BES Cyber System Categorization A. Introduction 1. Title: Cyber Security BES Cyber System Categorization 2. Number: CIP 002 5.1 3. Purpose: To identify and categorize BES Cyber
More informationImplementation Plan. Project CIP Version 5 Revisions 1. January 23, 2015
Implementation Plan Project 2014-02 CIP Version 5 Revisions January 23, 2015 This Implementation Plan for the Reliability Standards developed as part of Project 2014 02 CIP Version 5 Revisions replaces
More informationDisclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...
More informationOrder No Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request. September, 2015
Order No. 754 Assessment of Protection System Single Points of Failure Based on the Section 1600 Data Request System Protection and Control Subcommittee (SPCS) and System Modeling and Analysis Subcommittee
More information