Siemens Experience with Plant Level Control Modeling

Size: px
Start display at page:

Download "Siemens Experience with Plant Level Control Modeling"

Transcription

1 1 Siemens Experience with Plant Level Control Modeling 14PESGM0540 Yuriy Kazachkov Joergen Nygaard Nielsen Robert J. Nelson Jay Senthil July 30 th, 2014 IEEE PES GM Washington DC

2 Conceptual Diagram Showing Participants of the Plant Vlt Voltage Control 2 Plant Voltage Controller POI Transformer LTC MV On-Grid SVC Local Voltage Controllers

3 3 Wind Plant Voltage Controller with no System SVC Voltage control mode with a droop of 1 to 6%. Siemens default droop value is 4% typical for overseas project (UK) Voltage control mode with zero droop but with the dead band of 0.5 to 2%

4 4 Example of coordination between PVC and SVC To avoid fighting g between the SVC and the PVC, the latter cannot operate at zero slope but will rather operate with a slope setting of 0.5% to 1% SVC on continuous control provides inductive reactive power at voltage levels above 103% system voltage by staying on the slope up to its inductive limit. At and below 103% system voltage, there is no contribution of reactive power from the SVC until the voltage falls to 97% system voltage, and then the maximum capacitive output will be injected into the network. (Example is from a specific project. In most cases PVC should regulate lt 1 p.u. voltage).

5 Generic Wind Farm Voltage Controller 5

6 The PSS E Model for the Siemens Generic Wind Farm Vlt Voltage Controller Three control paths: PCC voltage, Reactive power, and Power factor 6 Inputs PCC voltage, power and reactive power enter the delay blocks emulating communication lines from measuring sensors to controllers. The output of the controller Uwt_Ref is formed from the delayed output of a PI controller of the selected control path. Central voltage controller broadcastsnew references to the turbines every 150 ms. At initialization, voltage reference Uwt_Ref is calculated as an average terminal voltage of all supervised WTGs. Averaging causes some initial movement of local WTG controllers if initial terminal voltages (load flow) of WTGs are different. Takes about 6 seconds for the system to resettle. 10 seconds is normally ample time preceding a disturbance for a dynamic simulation.

7 Examples of commissioning tests of the Siemens voltage plant controllers 1 7 This plot was derived in the course of commissioning tests at the plant with a very weak interconnection (SCR was about 1.35). The red is the set point voltage, the blue is the actual voltage. The weak system insures good control of voltage, despite a 4% reactive droop setting.

8 Examples of commissioning tests of the Siemens voltage plant controllers 2 8 This is typical for the UK applications. Tap position of the POI transformer was changed in a multi step pattern. The plant controller was trying to regulate the POI voltage on a 4% droop line. One can see the POI voltage (red) and the reactive power response (green).

9 Examples of commissioning tests of the Siemens voltage plant controllers 3 9 This test was performed at a relatively small wind farm connected to a strong system in the U.S. Voltage reference (red) was changed step wise. The command to local controls followed this change (blue). However the voltage of the strong interconnection (green) was relatively insensitive to plant reactive output.

10 SWT4: Generic PSS E Model for Siemens Wind Turbine Series 1 10 Includes: Converter Module Electrical Control Module Voltage Plant Controller supervising up to 50 WTGs Frequency Plant Controller supervising up to 50 WTGs (in progress)

11 SWT4: Generic PSS E Model for Siemens Wind Turbine Series 2 11 The model was tested for the system with 4 aggregated WTG units.

12 SWT4: Generic PSS E Model for Siemens Wind Turbine Series 3 12 PCC Voltage (blue) and a Command to Local Controls (red) Reactive Power of Each of Four Units as a Response to Step Change in GWFVC Voltage Reference

13 Conversion of the Plant Controller Model of the Renewable Energy Generic Standard dmodel to Multi Unit Application 1 The standard Generic Renewable Plant Control Model REPCAU1 is designed to interact with the local control of the single equivalent (aggregated) unit. Its block diagram shows two paths, one controlling a WTG active power and another controlling a WTG reactive power. Pref and Qref1 are respective commands from the PlantControllers to local controllers. 13

14 Conversion of the Plant Controller Model of the Renewable Energy Generic Standard Model to Multi Unit Application 2 14 The REPCAU1 standard model has been upgraded with the capability to supervise multiple (up to 150) WTGs, typical for modern wind plants. The dynamics of the standard model were left intact [5]. The upgraded model has a provision for identifying active WTGs supervised by the Plant Controller. At initialization, the Plant Controller collects the active and reactive power outputs of all on line WTGs, sums them up to get the total WTGs active and reactive power and divide them by a number of on line WTGs to calculate the initial average WTG active and reactive powers. These quantities will be used to initialize the state variables of active and reactive power paths of the Plant Controller.

15 Conversion of the Plant Controller Model of the Renewable Energy Generic Standard dmodel to Multi Unit Application 3 15 Simultaneously, the Plant Controller model stores the differences between initial average and initial active and reactive powers for each WTG. In the course of the dynamic simulation the outputs of both paths change depending on a disturbance and have to be transferred to local WTGs controllers as respective active and reactive power commands. To avoid initial movement, at eachintegration step these commandsaresummedare summed up with the stored differences between initial average and initial active and reactive powers for each WTG.

16 16 The updated REPCMU1 plant controller

17 Test system with 10 WTGs supervised by a Plant Controller 17

18 18 No PVC, +2% Step in System Voltage System voltage (black) change is followed by POI voltage change (red). The WTG voltage (blue) is kept constant by local control. POI reactive power flow (pink) drops as a consequence of the local controls action.

19 Documentation of the Upgraded REPCMU1 Renewable Energy Plant Controller Model 19 MISC OTHER MODELS Model lrepcmu1 Model linstance 1: I C O N S C O N S ST A T E S V A R S Tfltr Kp Ki Tft Tfv Vfrz Rc Xc Kc emax emin dbd1 dbd2 QMAX QMIN Kpg Kig tp fdbd1 fdbd2 femax femin Pmax Pmin Tg Ddn Dup VCFlag: 1 RefFlag: 1 Ffag: 0 WTG BUS # MID WTG BUS # MID WTG BUS # MID 1 ' 1 ' 2 ' 1 ' 3 ' 1 ' 4 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 '... 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' 0 ' 1 ' Bus Number for Voltage Control (if 0 local control): 100 Branch FROM bus number: 30 TO bus number: 100 Branch circuit ID: T1

20 Testing of the Upgraded REPCMU1 Renewable Energy Plant Controller Model 1 20 POI Voltage (red) and Command from the Plant Controller (blue) as a Response to Step Wise Change in Plant Controller Voltage Reference (black)

21 Testing of the Upgraded REPCMU1 Renewable Energy Plant Controller Model 2 21 WTGs Active Powers as a Response to Step Wise Change in Plant WTGs Active Powers as a Response to Step Wise Change in Plant Controller Frequency Reference (black)

22 22 with PVC, +2% Step in System Voltage System voltage (black) jumps up by 2%. POI voltage (red) stays constant due to PVC. Local WTG voltage (blue) drops following the command from the PVC to local controllers. The POI reactive power flow (pink) drops to accommodate change in local voltages.

23 PVC with Line Drop Compensation, +2% in System Vlt Voltage V100 vs Q Xc= V100 V100 vs Q Xc= V100

24 24 PVC and the System SVC Sfault=1200 MVA PVC here SVC here Continuously controlled SVC is simulated by the standard d SVSMO1U2 model

25 PVC and System SVC, +2% in System Voltage Droops of both thpvc and SVC =0 25 QSVC recovers because VPOI is the same as initially Voltages of POI and SVC bus get back

26 PVC and System SVC, +2% in System Voltage Line drop compensation of PVC XC=4%, SVC droop=4% 26 Because V100 increased SVC output drops Voltages of POI and SVC bus increased

27 27 References 1. Wind Power in Power System, p.s, 2nd Edition, Edited by Thomas Ackerman, Wiley, 2012, section WECC Wind Power Plant Dynamic Modeling Guide, prepared by WECC Renewable Energy Modelling Task Force, March 2014, Draft 3. WECC PV Power Plant Dynamic Modeling Guide, prepared by WECC Renewable Energy Modelling Task Force, April 2014, Draft 4. Comparison of WPP models in IEC CDV and WECC. Generic block structure of WPP, presented by Poul Ejnar Sorensen, Technical University of Denmark, Feldkirch, Denmark, Pouyan Pourbeik, Model Specifications and Testing for the 2 nd Generation Wind Turbine Generator Models, WECC REMTF Workshop, Salt Lake City, UT, June 2014

28 28 Acknowledgment Authors acknowledge financial support from Sandia National Laboratory in conversion of the plant controller model of the renewable energy generic standard model to multi unit unit application

Update on REPC_B Model

Update on REPC_B Model Update on REPC_B Model Pouyan Pourbeik WECC MVWG Meeting March, 206 206 Electric Power Research Institute, Inc. All rights reserved. REPC_A (existing plant controller) 2 206 Electric Power Research Institute,

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

FACTS and HVDC for Grid Connection of Large Wind Farms

FACTS and HVDC for Grid Connection of Large Wind Farms David Larsson Power-Gen Europe 2005 Milan, Italy FACTS and HVDC for Grid Connection of Large Wind Farms www.abb.com/facts FACTS Agenda Wind Generators Response to Grid Faults PICTURE JPG-FORMAT WEB OPTIMIZED

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

ISO New England Data Modeling Requirements

ISO New England Data Modeling Requirements A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda

More information

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1 Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms May 22, 2009 Slide 1 FACTS Applications Flexible AC Transmission Systems May 22, 2009 Slide 4 System Studies - Grid Codes

More information

Wind Farm Volt/VAR Control Using a Real-Time Automation Controller

Wind Farm Volt/VAR Control Using a Real-Time Automation Controller Wind Farm Volt/VAR Control Using a Real-Time Automation Controller Michael Thompson, Tony Martini, and Nicholas Seeley Schweitzer Engineering Laboratories, Inc. Published in Wide-Area Protection and Control

More information

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547

Utility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of

More information

Wind Plant Systems Grid Integration Plant and Turbine Controls SCADA

Wind Plant Systems Grid Integration Plant and Turbine Controls SCADA GE Energy Wind Plant Systems Grid Integration Plant and Turbine Controls SCADA Mahesh Morjaria Manager, Wind Plant Systems Platform Adopted for Wind Power Management class http://www.icaen.uiowa.edu/ edu/~ie_155/

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Comparison of Shunt Facts Devices for the Improvement of Transient Stability of Two Machine

More information

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2

SMUD Model Data Requirements & Reporting Procedures MOD VERSION 1.2 SMUD Model Data Requirements & Reporting Procedures MOD-032-1 VERSION 1.2 NOVEMBER 10, 2015 1 TABLE OF CONTENTS INTRODUCTION... 2 1.1 Purpose... 2 1.2 Audience... 3 1.3 Process Overview... 3 Figure 1-1:

More information

Power System Network Simulator (PSNsim)

Power System Network Simulator (PSNsim) The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment

More information

The Drive To Transactive Energy

The Drive To Transactive Energy The Drive To Transactive Energy Building the Enabling Network for DER Participation Leveraging the IEEE 1547 based Grid Interconnection for Transactive Energy Services Presented By: Paul Heitmann Businovation,

More information

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents

More information

Enhancing the Grid Compliance of Wind Farms by Means of Hybrid SVC

Enhancing the Grid Compliance of Wind Farms by Means of Hybrid SVC Enhancing the Grid Compliance of Wind Farms by Means of Hybrid SVC P. Vuorenpää, Student Member, IEEE, and P. Järventausta Abstract--Despite reactive power control capability of the modern wind turbine

More information

A Svc Light Based Technique for Power Quality Improvement for Grid Connected Wind Energy System

A Svc Light Based Technique for Power Quality Improvement for Grid Connected Wind Energy System IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331, Volume 7, Issue 5 (Sep. - Oct. 2013), PP 52-58 A Svc Light Based Technique for Power Quality Improvement

More information

Mehr Spannungsqualität im Netz mit SVC PLUS. Improvement in Voltage Quality for Power Systems with SVC PLUS

Mehr Spannungsqualität im Netz mit SVC PLUS. Improvement in Voltage Quality for Power Systems with SVC PLUS Mehr Spannungsqualität im Netz mit SVC PLUS Improvement in Voltage Quality for Power Systems with SVC PLUS M. Claus D. Retzmann K. Uecker A. Zenkner 1 10-2009 E T PS SL/Re General Features of VSC* FACTS

More information

PLUS Technology for Large Scale Renewable Energy Integration

PLUS Technology for Large Scale Renewable Energy Integration PLUS Technology for Large Scale Renewable Energy Integration ASIA CLEAN ENERGY FORUM 2015 Manila 15-19 June, 2015 P. Thepparat*, M. Haeusler, V. Hild, B. Rutrecht, K. Uecker Vers. 8-4-00 Energy Management

More information

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB2 INTRODUCTION TO SLIDER BINARY (*.sld) FILES

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB2 INTRODUCTION TO SLIDER BINARY (*.sld) FILES SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB2 INTRODUCTION TO SLIDER BINARY (*.sld) FILES Power Systems Simulations Colorado State University PURPOSE: The purpose of this lab is to introduce

More information

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models

DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models DRAFT Reliability Guideline: Modeling Distributed Energy Resources in Dynamic Load Models Problem Statement With the proliferation of distributed energy resources (DER), Transmission Planners must adapt

More information

Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool. Eleanor Ewry

Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool. Eleanor Ewry Using WECC Composite Load Model and PowerWorld Time Step Simulation Tool Eleanor Ewry Engineer October 21, 2014 Overview Introduction to Composite Load Model Introduction to Time Step Simulation (TSS)

More information

Smart Energy Systems Laboratory. Overview. Department of Energy Technology Aalborg University

Smart Energy Systems Laboratory. Overview. Department of Energy Technology Aalborg University Smart Energy Systems Laboratory Overview Department of Energy Technology Aalborg University 1 Background SmartC2Net, EU FP7 ( 4.9M), 2012 2015 www.smartc2net.eu Mission: To develop, implement and validate

More information

Chapter 3 MODELING OF SHUNT FACTS DEVICES. The Shunt FACTS Devices are used for voltage control and

Chapter 3 MODELING OF SHUNT FACTS DEVICES. The Shunt FACTS Devices are used for voltage control and 44 Chapter 3 MODELING OF SHUNT FACTS DEVICES 3.0 Introduction The Shunt FACTS Devices are used for voltage control and power flow control, but these are good at for voltage control. These are not in a

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

System Studies for American Transmission Co. s Benson Lake SVC Project

System Studies for American Transmission Co. s Benson Lake SVC Project Helping to keep the lights on, businesses running and communities strong System Studies for American Transmission Co. s Benson Lake SVC Project Adam Manty, Transmission Planning Engineer, ATC Outline Introduction

More information

Static Var Compensator: Effect of Fuzzy Controller and Changing Membership Functions in its operation

Static Var Compensator: Effect of Fuzzy Controller and Changing Membership Functions in its operation International Journal of Electrical Engineering. ISSN 0974-2158 Volume 6, Number 2 (2013), pp. 189-196 International Research Publication House http://www.irphouse.com Static Var Compensator: Effect of

More information

Hybrid STATCOM / SVC Workgroup 15 th May 2014

Hybrid STATCOM / SVC Workgroup 15 th May 2014 Hybrid STATCOM / SVC Workgroup 15 th May 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Dynamic Load Models in PowerWorld Simulator

Dynamic Load Models in PowerWorld Simulator Dynamic Load Models in PowerWorld Simulator Jamie Weber (weber@powerworld.com) Director of Software Development 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com

More information

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines

Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines Modeling and Simulation of Static VAR Compensator Controller for Improvement of Voltage Level in Transmission Lines 1 B.T.RAMAKRISHNA RAO, 2 N.GAYATRI, 3 P.BALAJI, 4 K.SINDHU 1 Associate Professor, Department

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

HVDC Control and Protection Testing Using the RTDS Simulator

HVDC Control and Protection Testing Using the RTDS Simulator HVDC Control and Protection Testing Using the RTDS Simulator Yong-Beum Yoon, Tae-Kyun Kim, Seung-Tae Cha Power System Research Laboratory, Korea Electric Power Research Institute, Korea Abstract: Many

More information

Electric Access System Enhancement (EASE)

Electric Access System Enhancement (EASE) Electric Access System Enhancement (EASE) Robert Sherick T-D Operations Interface Working Group More Than Smart August 2 nd, 2017 1 AGENDA ENERGISE Program EASE Project Objectives Approach Expected Outcomes

More information

Photovoltaik ON GRID / OFF GRID

Photovoltaik ON GRID / OFF GRID Photovoltaik ON GRID / OFF GRID BST the flexible training system from for building automation based on real components. BST mobile practical safe elabo-ts.com Photovoltaic Off Grid System DC Hybrid AC

More information

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI 621213 EE-2401 POWER SYSTEM OPERATION AND CONTROL UNIT-III REACTIVE POWER VOLTAGE CONTROL TWO MARKS: 1. What are the sources of reactive power? How it is

More information

Introduction to new ABB STATCOM portfolio Power Grid Integration FACTS

Introduction to new ABB STATCOM portfolio Power Grid Integration FACTS INNOVATION DAY AT CERN, MAY 10 TH 2017 Introduction to new ABB STATCOM portfolio Power Grid Integration FACTS Bjoern Oedegard, Principal Engineer System & Power Electronics FACTS Flexible AC Transmission

More information

Developing a Roadmap for A Smart(er) and Strong Transmission Grid

Developing a Roadmap for A Smart(er) and Strong Transmission Grid Developing a Roadmap for A Smart(er) and Strong Transmission Grid By: Navin Bhatt Manager, Advanced Transmission Studies & Technologies American Electric Power (AEP) PSERC 2009 Summer Workshop Breckenridge,

More information

Transient Stability Improvement in Transmission System Using SVC with fuzzy logic Control

Transient Stability Improvement in Transmission System Using SVC with fuzzy logic Control Transient Stability Improvement in Transmission System Using SVC with fuzzy logic Control Aashutosh Khasdeo Assistant Professor, Dept of Electrical & Electronics Engineering, LNCT Bhopal, MP, India ---------------------------------------------------------------------***---------------------------------------------------------------------

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Monitoring and Controlling Energy Efficiency of Photovoltaic Installations

Monitoring and Controlling Energy Efficiency of Photovoltaic Installations Monitoring and Controlling Energy Efficiency of Photovoltaic Installations Features System Current and voltage supervision of solar panels Control of switching states Sources Shunt and inductive sensors

More information

Voltage control in MV and LV grid Distributed automation solution. Sami Repo Tampere University of Technology, Finland Coordinator of IDE4L project

Voltage control in MV and LV grid Distributed automation solution. Sami Repo Tampere University of Technology, Finland Coordinator of IDE4L project 1 Voltage control in MV and LV grid Distributed automation solution Sami Repo Tampere University of Technology, Finland Coordinator of IDE4L project 2 Content IDE4L project Problem of voltage control in

More information

PUBLICLY AVAILABLE SPECIFICATION

PUBLICLY AVAILABLE SPECIFICATION IEC/IEEE/PAS 63547 PUBLICLY AVAILABLE SPECIFICATION Edition 1.0 2011-09 Interconnecting distributed resources with electric power systems INTERNATIONAL ELECTROTECHNICAL COMMISSION PRICE CODE V ICS 29.240.99

More information

National Load Despatch Centre Power System Operation Corporation

National Load Despatch Centre Power System Operation Corporation Module on Procedure for Data Collection National Load Despatch Centre Power System Operation Corporation Background Algorithms/ Processes AC Load flow and transmission losses Slack bus determination- Average

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

The current state of the electrical grid And the technologies that will enable its transformation

The current state of the electrical grid And the technologies that will enable its transformation ABB POWER GRIDS The current state of the electrical grid And the technologies that will enable its transformation IEEE POWER & ENERGY SOCIETY - SUBSTATIONS COMMITTEE May 7-11 th Agenda State of the Industry

More information

Western Interconnection

Western Interconnection Transmission Planning in the Western Interconnection Supporting Resource Development NWCC/NCSL Transmission Policy Institute Byron Woertz, Senior Project Manager Denver, CO June 17, 2010 Overview A Few

More information

Successful deployment of the OP4500 at CONECTA S.A.

Successful deployment of the OP4500 at CONECTA S.A. Successful deployment of the OP4500 at CONECTA S.A. 1. Challenges and reasons to purchase a real-time simulation platform CONECTA is an integrated company offering monitoring, protection and control solutions

More information

An Inrush Current Elimination Technique for Line-Interactive UPS Systems During Switching-in of an Auxiliary Load While Feeding a Main Load

An Inrush Current Elimination Technique for Line-Interactive UPS Systems During Switching-in of an Auxiliary Load While Feeding a Main Load An Inrush Current Elimination Technique for Line-Interactive UPS Systems During Switching-in of an Auxiliary Load While Feeding a Main Load Syed Sabir Hussain Bukhari*, Byung-il Kwon *, Thomas A. Lipo

More information

THE ENEL SMART GRID TEST SYSTEM: A REAL-TIME DIGITAL SIMULATOR-BASED INFRASTRUCTURE

THE ENEL SMART GRID TEST SYSTEM: A REAL-TIME DIGITAL SIMULATOR-BASED INFRASTRUCTURE THE ENEL SMART GRID TEST SYSTEM: A REAL-TIME DIGITAL SIMULATOR-BASED INFRASTRUCTURE Gianluca Sapienza Gianpatrizio Bianco Giorgio Di Lembo Enel Distribuzione Italy Enel Distribuzione Italy Enel Distribuzione

More information

Prospects of the new SVC with modular Multilevel Voltage Source Converter

Prospects of the new SVC with modular Multilevel Voltage Source Converter SB4 Colloquium 2011 Prospects of the new SVC with modular Multilevel Voltage Source Converter Marcos Pereira Martin Pieschel Ralf Stoeber Brisbane Australia, 19-21 October 2011 Siemens AG 2011 Energy Sector

More information

SmartNet Pilots: The demonstration of the different TSO-DSO coordination schemes and market structures

SmartNet Pilots: The demonstration of the different TSO-DSO coordination schemes and market structures Smart TSO-DSO interaction schemes, market architectures and ICT Solutions for the integration of ancillary services from demand side management and distributed generation The Global Forum Electricity Ancillary

More information

Power System Studies. The Power of Trust. The Future of Energy.

Power System Studies. The Power of Trust. The Future of Energy. The Power of Trust. The Future of Energy. POWER SYSTEM ANALYSIS Consulting studies to investigate system events and optimize power system performance In todays competitive and rapidly changing operating

More information

Developing a Dynamic Smart Grid Model

Developing a Dynamic Smart Grid Model European Association for the Development of Renewable Energies, Environment and Power Quality (EA4EPQ) International Conference on Renewable Energies and Power Quality (ICREPQ 12) Santiago de Compostela

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

Integrated Energy Networks enabled by Digitalization Siemens AG 2015 siemens.com

Integrated Energy Networks enabled by Digitalization Siemens AG 2015 siemens.com Prof. Dr.-Ing. Michael Weinhold, CTO Siemens Energy Management Berlin, 14. Dezember 2015 Integrated Energy Networks enabled by Digitalization siemens.com The world of our customers is changing From centralized

More information

ELECTRIC POWER SYSTEM

ELECTRIC POWER SYSTEM FUNDAMENTAL CHANGES TO THE ELECTRIC POWER SYSTEM POST-2018 BY MARK SIIRA, ComRent International This article gives a glimpse of some significant changes that will occur in electric power system testing

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

Venteea - A Smart Grid demonstrator for the DRES integration on the MV distribution networks.

Venteea - A Smart Grid demonstrator for the DRES integration on the MV distribution networks. Venteea - A Smart Grid demonstrator for the DRES integration on the MV distribution networks www.venteea.fr/en/ Agenda Quick Overview of VENTEEA project MV Distribution State Estimator (DSE) L éolien 8,1

More information

April 2010 Power Systems division A brief introduction. ABB Group August 25, 2011 Slide 1

April 2010 Power Systems division A brief introduction. ABB Group August 25, 2011 Slide 1 April 2010 Power Systems division A brief introduction August 25, 2011 Slide 1 Facts about ABB 117,000 employees in about 100 countries $32 billion in revenue (2009) Formed in 1988 merger of Swiss and

More information

CIGRE STUDY COMMITTEE C4 BRANDON PETERSON SOUTH AFRICAN MEMBER SC C4 7 AUGUST 2017

CIGRE STUDY COMMITTEE C4 BRANDON PETERSON SOUTH AFRICAN MEMBER SC C4 7 AUGUST 2017 CIGRE STUDY COMMITTEE C4 BRANDON PETERSON SOUTH AFRICAN MEMBER SC C4 7 AUGUST 2017 1 WHERE SC C4 FITS IN A1 Rotating electrical machines A2 Transformers A3 High voltage equipment B1 Insulated cables B2

More information

Transient Stability Improvement of Long Transmission Line System by Using SVC

Transient Stability Improvement of Long Transmission Line System by Using SVC Transient Stability Improvement of Long Transmission Line System by Using SVC Dr.Tarlochan Kaur 1 and Sandeep Kakran 2 1 Associate Professor, EED, PEC University of Technology, Chandigarh, India 2 Assistant

More information

An Integrated Platform for Increased FLEXIbility in smart TRANSmission grids with STORage Entities and large penetration of Renewable Energy Sources

An Integrated Platform for Increased FLEXIbility in smart TRANSmission grids with STORage Entities and large penetration of Renewable Energy Sources An Integrated Platform for Increased FLEXIbility in smart TRANSmission grids with STORage Entities and large penetration of Renewable Energy Sources Project presentation This project has received funding

More information

February 25, Subject: Southern California Edison 2015 Annual Progress Report

February 25, Subject: Southern California Edison 2015 Annual Progress Report February 25, 2015 Mr. Tracy Rolstad, Chair WECC Technical Studies Subcommittee Avista Corp. 1411 East Mission Avenue Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff Salt Lake City, UT 84103-1114

More information

Collector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co.

Collector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co. Collector System Design Considerations for Wind Farms Sean Carr Ernst Camm S&C Electric Co. 1 Overview Challenges in wind farm collector systems Design considerations for collector systems Summary The

More information

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4

More information

IEC TC88/PT25 Meeting 5th-6th September Welcome to Copenhagen

IEC TC88/PT25 Meeting 5th-6th September Welcome to Copenhagen IEC TC88/PT25 Meeting 5th-6th September 2001 Welcome to Copenhagen Time Schedule Day 1 10:00 Kick-off 12:30 Lunch 17:00 Meeting breaks 19:30 Visit and dinner at Tivoli Day 2 9:00 Meeting continues 12:30

More information

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY

LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY LAB1 INTRODUCTION TO PSS/E EE461: POWER SYSTEMS COLORADO STATE UNIVERSITY PURPOSE: The purpose of this lab is to introduce PSS/E. This lab will introduce the following aspects of PSS/E: Introduction to

More information

PSS SINCAL Hosting Capacity Analysis. IEEE PES General Meeting 2017 Chicago - July 16-21, 2017

PSS SINCAL Hosting Capacity Analysis. IEEE PES General Meeting 2017 Chicago - July 16-21, 2017 PSS SINCAL Hosting Capacity Analysis IEEE PES General Meeting 2017 Chicago - July 16-21, 2017 usa.siemens.com/digitalgrid Advantages at a Glance Maximal Hosting Capacity Analysis or How much Distributed

More information

OPTIMAL LOCATION OF SVC USING BENEFIT FACTORS TO IMPROVE THE VOLTAGE PROFILE IN POWER SYSTEMS

OPTIMAL LOCATION OF SVC USING BENEFIT FACTORS TO IMPROVE THE VOLTAGE PROFILE IN POWER SYSTEMS European International Journal of Science and Technology Vol. 4 No. 2 February, 2015 OPTIMAL LOCATION OF SVC USING BENEFIT FACTORS TO IMPROVE THE VOLTAGE PROFILE IN POWER SYSTEMS IRENE N. MUISYO a, KEREN

More information

SVC FOR MAINTAINING OF POWER QUALITY IN THE FEEDING GRID IN CONJUNCTION WITH AN ELECTRIC ARC FURNACE IN A STEEL PLANT

SVC FOR MAINTAINING OF POWER QUALITY IN THE FEEDING GRID IN CONJUNCTION WITH AN ELECTRIC ARC FURNACE IN A STEEL PLANT SVC FOR MAINTAINING OF POWER QUALITY IN THE FEEDING GRID IN CONJUNCTION WITH AN ELECTRIC ARC FURNACE IN A STEEL PLANT Rolf GRÜNBAUM Danilo DOSI Leonardo RIZZANI ABB Power Technologies AB - Sweden ABB Power

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC

Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC Study of Transient Stability Improvement of IEEE 9-Bus System by using SVC Rathnasagar Rangu 1, Poonam Upadhyay 2 1 PG Student, VNR VJIET, Hyderabad, India 2 Professor, VNR VJIET, Hyderabad, India Abstract

More information

List of Communication Requirements within Microgrid

List of Communication Requirements within Microgrid Project Milestone Report Microgrid Positioning www.ugrip.eu MILESTONE M4.2. List of Communication Requirements within Microgrid Project Acronym ugrip Project Number 229 Funding Scheme Project Start Date

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, 2018 1:00 p.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 1:00-1:10 Stakeholder Process and Schedule Kristina Osborne

More information

Simulation and Analysis of Static Var Compensator with Matlab

Simulation and Analysis of Static Var Compensator with Matlab The International Journal Of Engineering And Science (IJES) Volume 4 Issue 12 Pages PP -07-11 2015 ISSN (e): 2319 1813 ISSN (p): 2319 1805 Simulation and Analysis of Static Var Compensator with Matlab

More information

Reactive Power Control and Transmission Line Loss Reduction with Realization of FACT Controller

Reactive Power Control and Transmission Line Loss Reduction with Realization of FACT Controller International Journal of Electronics Engineering Research. ISSN 0975-6450 Volume 9, Number 8 (2017) pp. 1297-1310 Research India Publications http://www.ripublication.com Reactive Power Control and Transmission

More information

Large Embedded Generators Register of Completed Projects

Large Embedded Generators Register of Completed Projects Large Embedded Generators Register of Completed Projects This document contains a description of the completed projects relating to the connection of Large Embedded Generators to the TasNetworks distribution

More information

Performance analysis of FACTS devices in steady state power flow

Performance analysis of FACTS devices in steady state power flow Performance analysis of FACTS devices in steady state power flow VELAMURI SURESH 1, SREEJITH.S 2 1 Research Scholar, 2 Associate Professor School of Electrical engineering, VIT University Vellore, INDIA

More information

Power System Enterprise Solution

Power System Enterprise Solution Power System Enterprise Solution ETAP is the most comprehensive analysis platform for the design, simulation, operation, control, optimization, and automation of generation, transmission, distribution,

More information

Joint Transmission Planning Base Case Preparation Process

Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Southern California Edison Joint Transmission Planning Base Case Preparation Process NERC Reliability Standard MOD-032-1 Version 1.2 August 31, 2017 INTENTIONALLY

More information

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements

Identify and understand the operation of common bus. After this presentation you will be able to: Identify common bus arrangements Introduction to Bus Protection By Matt Horvath, P.E. November 6, 2018 Electrical Buses Physical and Electrical Junction A bus is a critical element of a power system, as it is the point of convergence

More information

ADINE EU DEMONSTRATION

ADINE EU DEMONSTRATION ADINE EU DEMONSTRATION PROJECT OF ACTIVE DISTRIBUTION NETWORK Sami Repo Tampere University of Technology Finland Distributed Generation DG Increased DG penetration is expected New products New connection

More information

Control, Protection, and Realtime Simulation of Microgrids

Control, Protection, and Realtime Simulation of Microgrids Large-scale Integration of Distributed Energy Resources: Control, Protection, and Realtime Simulation of Microgrids Amir Etemadi etemadi@gwu.edu US China Smart Grid Workshop May 16, 2014 Nanjing, China

More information

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

Artificial Neural Network Controller With Static VAR Compensator to Improve Transient Stability for A Grid Connected Distributed Generation System

Artificial Neural Network Controller With Static VAR Compensator to Improve Transient Stability for A Grid Connected Distributed Generation System nternational Journal of Applied Sciences, Engineering and Management SSN 2320 3439, Vol. 07, No. 02, March 2018, pp. 01 05 Artificial Neural Network Controller With Static VAR Compensator to mprove Transient

More information

Demonstration Test Bed for Advanced Control Systems

Demonstration Test Bed for Advanced Control Systems Demonstration Test Bed for Advanced Control Systems Christopher R Clarke Senior Engineer SCE Advanced Technology June 22, 2016 1 Advanced Distribution Control Systems Introduction of customer adoption

More information

2009 E09PS E09PS E09PS E09PS E09PS E09PS38 IEEE 2009 E09PS39 E09PS40 E09PS41 E09PS42 E09PS43 IEEE 2008 E09PS44

2009 E09PS E09PS E09PS E09PS E09PS E09PS38 IEEE 2009 E09PS39 E09PS40 E09PS41 E09PS42 E09PS43 IEEE 2008 E09PS44 1 CODE IEEE TRANSACTION POWER SYSTEM YEAR E09PS32 E09PS01 E09PS02 E09PS03 E09PS04 E09PS05 E09PS06 E09PS07 E09PS08 E09PS09 E09PS10 E09PS11 E09PS12 E09PS13 E09PS14 E09PS15 E09PS16 E09PS17 E09PS18 E09PS19

More information

Model of Photovoltaic Generation During Cloudy Days

Model of Photovoltaic Generation During Cloudy Days Model of Photovoltaic Generation During Cloudy Days Dionysios C. Aliprantis, Chengrui Cai Iowa State University Sandia National Laboratory June 11, 2012 Outline Motivation Literature review on cloud pattern

More information

ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE

ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE Rob Stephen President Cigre AFSEC conference March 2017 CIGRE Founded in 1921, CIGRE, the Council on Large Electric Systems, Our Mission:To be the world s foremost

More information

UNDERGROUND HV SUBSTATION DESIGN

UNDERGROUND HV SUBSTATION DESIGN 3 for 2 Bundle Offer. SGD 2440 each for Team of 3! Topics Covered Underground Substations Overview Planning New Underground Substations S/S Design Overview Expert Course Faculty Leader In his 30 years

More information

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017

Power System Resilience & Reliability. Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 Power System Resilience & Reliability Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 28, 2017 NERC, Reliability, & Resilience NERC has addressed reliability

More information

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68

p. 1 p. 9 p. 26 p. 56 p. 62 p. 68 The Challenges and Opportunities Faced by Utilities using Modern Protection and Control Systems - Paper Unavailable Trends in Protection and Substation Automation Systems and Feed-backs from CIGRE Activities

More information

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM

CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM 52 CHAPTER 4 FACTS CONTROLLERS FOR OPTIMIZATION OF POWER SYSTEM 4.1 INTRODUCTION Flexible AC Transmission System (FACTS) controllers have been used in power systems with the objective of improving system

More information

Static var compensator (SVC) applications for improving transmission system performance

Static var compensator (SVC) applications for improving transmission system performance ABB Automation & Power World: April 18-21, 2011 WPS-141-1B Static var compensator (SVC) applications for improving transmission system performance ABB Inc. April 21, 2011 Slide 1 WCS-120-1 Static Var Compensator

More information

POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER

POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER POWER FACTOR CORRECTION USING SVC WITH FUZZY LOGIC CONTROLLER Puranik Sahu 1, Arun Pachori 2 1 puranik1987@gmail.com Abstract: To transmit or distribute fixed amount of power at fixed voltage, the conductor

More information

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group

SUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group SUNZIA SOUTHWEST TRANSMISSION PROJECT David Getts General Manager SouthWestern Power Group PROJECT UPDATE NEW MEXICO RETA 8.22.12 SouthWestern Power Group Independent developer of utility-scale generation

More information

GRIDCON itap ON-LOAD TAP-CHANGER FOR DISTRIBUTION GRIDS. POWER QUALITY

GRIDCON itap ON-LOAD TAP-CHANGER FOR DISTRIBUTION GRIDS. POWER QUALITY GRIDCON itap ON-LOAD TAP-CHANGER FOR DISTRIBUTION GRIDS. POWER QUALITY GRIDCON itap ECONOMICALLY INTEGRATING RENEWABLE ENERGIES INTO THE GRID. RUNNING INDUSTRIAL PROCESSES STABLY WHILE OPTIMIZING ENERGY

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

System Engineering, IT/OT Integration and the Smart Grid. Steve Apps Pr.Eng SAIEE Associate Director EON Consulting, South Africa

System Engineering, IT/OT Integration and the Smart Grid. Steve Apps Pr.Eng SAIEE Associate Director EON Consulting, South Africa System Engineering, IT/OT Integration and the Smart Grid Steve Apps Pr.Eng SAIEE Associate Director EON Consulting, South Africa South African grid: large and complex Line (kv) Length (km) 765 1,859 533

More information