Introduction 2. I Documentation and Current Conditions Establishment Process 3. II Existing Public Safety Facilities Analysis 4

Size: px
Start display at page:

Download "Introduction 2. I Documentation and Current Conditions Establishment Process 3. II Existing Public Safety Facilities Analysis 4"

Transcription

1 TABLE of CONTENTS Introduction 2 I Documentation and Current Conditions Establishment Process 3 II Existing Public Safety Facilities Analysis 4 III Space Allocation, Co-location and Potential Site Location Analysis 8 IV Options 15 V Recommendations 17 VI Next Steps 19 Appendix A Stakeholder Interview Notes - Police - Fire - Emergency Management - Facilities Management Appendix B Profile of the Public Safety Departments November 9, 2011 (DRAFT) Page 1 of 20

2 INTRODUCTION In October 2009, the City Manager, representing the Public Safety Committee of the City of Winston-Salem proposed... to perform a needs assessment and space allocation study for the Public Safety operation (Emergency Management, Fire and Police) to identify current and future staffing levels and space allocation needs. This review is designed to facilitate comprehensive and long-term decisions about the use of all Public Safety facilities, including the Public Safety Center (PSC), the Beaty facility, the existing Emergency Management space at Smith Reynolds Airport and related auxiliary locations. The study will look at potential upfit and reuse options for these existing facilities. The analytical project team of Architectural Design Associates/Donald Eyberg Architects/Matrix Consulting Group was selected to perform this Study. These three tasks were established to address the needs Study: TASK 1 TASK 2 TASK 3 Conduct initial interviews with key stakeholders The project team will meet with the key stakeholders involved in the study. The focus of these interviews will be to identify key issues with existing facilities, space plans, (and) adjacencies. Document current facilities, spaces and utilization of that space The focus of this Task will be to document the current facilities and space utilized by the various Public Safety functions of the City. Document current staffing, deployment, operations and workload The project team will focus... on documenting key measures of staffing, deployment and workload facing each of the Public Safety departments. Following are our findings as we completed these three Tasks. Our charge for Phase One was to generate general observations relative to the Public Safety departments of the City of Winston- Salem. These will form guideposts as we move through the refining and detailing process of Phase Two to provide specific facility space planning, staffing recommendations and cost estimates. November 9, 2011 (DRAFT) Page 2 of 20

3 I - DOCUMENTATION and CURRENT CONDITIONS ESTABLISHMENT PROCESS The project team used a number of processes to establish all of the existing conditions that the study would need to address. 1. Facility tours: The Public Safety Center, Beaty Center, Emergency Management offices and Fire Stations 1, 7, 8, 9, 15, 16 and 17 were thoroughly toured to establish existing condition and usage. 2. Stakeholder leadership interviews: The leadership teams from Police, Fire and Emergency Management were interviewed to discuss current and future facility staffing needs. 3. Department head interviews: From each stakeholder group, department heads (captains, lieutenants, sergeants) were interviewed to establish staffing and operational specifics. 4. Public Safety Center analysis: The existing facility was analyzed to establish the current condition, utilization and to evaluate future utilization. 5. Beaty Center analysis: The existing facility was analyzed to establish the current condition, utilization and to evaluate future utilization. 6. Potential Public Safety Center locations: Three potential sites for a PSC were studied. These were the current PSC facility on North Cherry Street, the former Thomasville Furniture manufacturing facility across from the Beaty Center on North Patterson Avenue and the former Flak-T Bahnson facility on Lowery Street. A generic or unidentified site was also considered. The interview process was two-tiered. At the first level, the leaders of the three Public Safety departments were interviewed to establish the overall operational aspects of each department and how those operations would change in the future as they related to staffing, facilities availability and possible operational shifts (satellite precinct offices, population growth, etc.). The Stakeholder Interview Notes from these interviews are included in this Study as Appendix A. The second level of the process involved captains, lieutenants and sergeants in both the Police and Fire Departments, and staff in Emergency Management. They provided detailed information relative to staffing, organizational structure, roles, responsibilities, programs and service incidents and levels. The resultant document is the Profile of the Public Safety Departments and is included in this Study as Appendix B. November 9, 2011 (DRAFT) Page 3 of 20

4 II - EXISTING PUBLIC SAFETY FACILITIES ANALYSIS PUBLIC SAFETY CENTER ANALYSIS Facilities Management provided the original construction documents for the PSC for our review. Those were thoroughly studied and analyzed. This information was, along with the information gathered during our tour of the building, incorporated into our analysis. The current building was occupied in 1985 and contains approximately 60,000 square feet of total floor space on three floors. It is a steel frame building with glass and precast concrete exterior walls. It is situated at the corner of North Cherry Street and Eighth Street just north of downtown Winston-Salem. Several analysis points were found that affect the use and performance of the building: The PSC was fully occupied at the time of initial construction, with no expansions since. For comparison purposes, the population of Winston-Salem in 1985 was approximately 138,000 and has increased to 230,000 in 2009 (67% increase). Its land area was 70 square miles in 1985 and has increased to 133 square miles in 2010 (90% increase). There were 429 total police employees in 1985 and has increased to 706 in 2010 (65% increase). The PSC was built well before current day building codes or energy codes. Significant portions of the exterior shell are not insulated, and those areas that are insulated contain relatively small thicknesses of insulation typically found in buildings of that era. All of these combine to require significant energy consumption for the PSC as compared to newer buildings. The floor space efficiency ratios are typical as compared to other buildings of this use and type. Floor space efficiency ratios evaluate the amount of usable floor space against non-specific space. A ratio of 75% indicates that 25% of the floor area is used for toilets, stairs, mechanical rooms and corridors, leaving 75% for offices, conference rooms. work rooms and other spaces directly related to the use of the building. The first floor ratio is 66%, the second floor ratio is 71% and the third floor ratio is 77%. The first floor contains the mechanical equipment for the entire building. The roof construction consists of steel deck, insulation, lightweight concrete and builtup roofing membrane. This arrangement sandwiches the insulation in a position that precludes replacement. The roof membrane is currently scheduled for replacement. This process may add insulation to the top surface and increase the insulation effectiveness. The mechanical system in the PSC has outlived its normal life span. It struggles to adequately control the indoor environmental conditions, particularly during the hot humid summer months. This was observed during the tour and confirmed by the numbers of individual fans in the building and input from the occupants. An aggravating factor is the 15% to 20% more people working in the building than the system was designed to handle. This exacerbates cooling, humidity and healthy air flow issues. The age of the system results in very inefficient operation, both in terms of effectiveness and energy demand. Additionally, one central plant on the first floor serves the entire building. With no floor- November 9, 2011 (DRAFT) Page 4 of 20

5 by-floor system, the entire building is relying on the one system staying in operation. This also makes it impractical to replace the system while keeping the building in operation. The PSC lacks adequate electrical power supply. It was designed for a significantly smaller number of occupants. The electrical load that contemporary buildings demand now is also significantly higher than the PSC is capable of supplying. Electronic devices are in ever increasing use in offices, particularly in Police and Fire operations. This building struggles to supply that demand, affecting service performance of these two Departments. Computer connectivity is very low for a building of this type. Electrical upgrades have been added over the years, but there is still a need for greater capacity as these systems and needs have greatly increased in recent years. This issue mirrors the aspects of the electrical power supply stated above. The light fixtures are of the older inefficient type. They have old technology ballasts instead of newer, more efficient electronic types. The lamps that the fixtures use are also old technology lamps, resulting in both light output inefficiency and high energy demand of the fixtures. This affects both the energy performance of the building and the work efficiency of its users. Even though the PSC was built as a secure facility in 1985, security design issues for these types of buildings have changed dramatically over the past decade. The current security for the building only relates to public access. A PSC should be protected or hardened against a list of threats, both man-made and natural. Retrofitting this building to current day standards would be costly. Increasing the building s security is made more difficult by its closeness to the surrounding streets. In order to create a scenario where the building would be protected from vehicle-borne explosives, additional space (distance) is required between the building and the streets to safely divert the blast shock wave. The PSC is in a central location geographically. This facilitates convenient access by both employees and citizens. On the negative side, its location requires officers to travel to the center of Winston-Salem for roll-call, etc., regardless of their beat or precinct location. There is no automatic fire sprinkler system in the building. This is another component typically found in buildings of a high security value and is mandated in current building codes. Parking for the PSC is dispersed over several lots. None of the parking lots are secure and several are located across the adjacent streets. This is less than ideal from a safety perspective and from a security perspective. The PSC lacks accommodations for the physically challenged that conform to present day standards. North Carolina codes have been very proactive in this area over the years, but significant changes have occurred in the past 25 years that require easier access, accessible exits, more floor space, different types of spaces and new systems for communication, including information and way finding signage. The structure and exterior shell of the PSC are very sound, suggesting that a total renovation would be successful. This could extend its useful life by 25 to 40 years. This would involve relocating the building s occupants to other space, stripping the building down to the shell and constructing a complete renovation. November 9, 2011 (DRAFT) Page 5 of 20

6 BEATY CENTER ANALYSIS Schematic floor plans were provided for the recent building renovation for our review. Those were thoroughly studied and analyzed. This information was combined with the information gathered during our tour of the building and is incorporated into our findings. The building was built in 1956 as a Thomasville Furniture manufacturing facility and renovated as the Beaty Center in It contains approximately 145,000 gross square feet of floor space on two floors. Its construction consists of a steel frame building with brick masonry exterior walls. It is located on the west side of North Patterson Avenue near its intersection with Northwest Boulevard on a site totaling 7.9 acres. Several analysis points were found that affect the use and performance of the building: The Beaty Center was renovated to contain training space for the Police and Fire Departments, along with evidence processing and storage for Police. The Forsyth County Sheriff s Department will also soon begin to use the facility for evidence storage and processing. The facility offers a central location for these functions. During the recent renovation, several components of the building were upgraded. They include a new roof, previous skylight openings were closed, enhanced structural bracing and structural repairs, new mechanical and electrical systems, replacement windows, new secure entry, automatic fire sprinkler system and fire alarm system were added. Hazardous materials were removed from both the building and site. The facility was not hardened during the renovation and cannot supply space for an Emergency Operations Center (EOC). Additional upgrades would be required to meet EOC standards. Patterson Avenue is directly adjacent to the Beaty Center and could pose a vehicleborne security threat. Proximity of the building to the street cannot be changed, making resistance to these types of threats impossible. The building contains a large amount of open floor space for evidence storage and to allow expansion of current activities and/or insertion of related new activities in the future. The entire second floor is available, as are portions of the main floor and basement. Public Safety facilities not evaluated in this Study: Airport firing range Clemmons training and munitions facility (Kinnamon Road) Police Fleet management (Brookstown Avenue) Fire Fleet Management (Palmer Lane) Bike patrol offices (North Cherry Street downtown) Special Investigation Division, Enforcement Squad, Interdiction Squad and Crimestoppers lease space (North Point area). November 9, 2011 (DRAFT) Page 6 of 20

7 EMERGENCY MANAGEMENT OFFICES ANALYSIS Floor plans were not provided for these offices. This analysis is based on our tour of the building. The Emergency Management offices occupy a number of spaces in the north wing of Smith Reynolds Airport. There are five offices and one conference room. This functions acceptably on a day to day basis, but poses problems when an event initiates mobilization: Proper management of an event requires Emergency Management s presence in an Emergency Operations Center (EOC). Critical time can be lost during an emergency as personnel, support equipment and supplies have to relocate. The current space designated as an EOC is the auditorium on the third floor of the PSC. This space is not large enough for the total number of persons required to properly manage an emergency event. During a recent exercise, approximately 30 people participated. It was observed that the auditorium was at functional capacity. It can take as many as 60 people to adequately manage an emergency. There are also a minimal number of power and data outlets for the number of computers required. Other technologies that facilitate sharing of critical data among the emergency management team members is also lacking in the room. These include multiple screen projection capability and a PA system. The Smith Reynolds Airport is 3.6 miles from the PSC. The mobilization from Smith Reynolds Airport to the PSC requires approximately 4.5 hours to complete. This completion time involves moving the equipment and supplies required to manage the emergency from Smith Reynolds Airport to the PSC over clear streets in good weather conditions. This time would be much greater in the event of an emergency where streets could be blocked, weather conditions could be severe or exterior atmospheric conditions could be hazardous. This time would be better spent managing the initial hours of an emergency from a facility that is occupied by those required to handle the emergency. The PSC lacks a number of spaces required to adequately handle an emergency lasting more than one day. Among those are: kitchen, sleeping facilities, showers, bulk storage, collateral agency offices and time-out/de-compress space. Mobilization in the EOC can last several days and involve dozens of people requiring adequate support space. This mobilization also interferes with the normal operation of the Police Department. An emergency event requires them to hand over space normally dedicated to Police operations. In an actual emergency, this may not be intrusive, given that they are focusing more on the emergency. It is disruptive during the much-needed drills that are required to stay event-ready. November 9, 2011 (DRAFT) Page 7 of 20

8 III - SPACE ALLOCATION, CO-LOCATION AND POTENTIAL SITE LOCATION ANALYSIS SPACE ALLOCATIONS AND COMPARISONS As the current PSC is analyzed, a number of statistics can be directly derived. Those relate to city population, city land area and the number of police and fire employees served by the building. Basic to all of these is the building s date of occupancy (1985) and total size (60,000 square feet). City of Winston-Salem 1985 to 2009 comparison Residents Size Police Fire , Sq. Mi , Sq. Mi Over these 25 years, the population of Winston-Salem has grown by 67% and its land area has grown by 90%. The number of sworn Police officers per 1,000 residents has remained level over those 25 years at The number of Fire employees per 1,000 residents has also remained level over the period at 0.7. There have been no building additions to the Public Safety Center. That translates to approximately 60,000 square feet serving a total of 629 employees in 1985 and 1,049 employees in Additionally, discussions with Police, Fire and Facilities Management representatives indicate that the PSC was at capacity when originally occupied in Another factor indicative of the usage of the PSC is the ratio of square feet in the building to the total number of employees served. In 1985 that figure was 95.4 square feet per employee. In 2009 the figure was Relocating training, evidence processing and evidence storage to the Beaty Center improves the situation only slightly with just a few hundred square feet freed up. Another logical step would be to compare Winston-Salem with other similar cities. That is relatively easy to do when comparing population, land area and demographics. The four comparative cities noted do not contain any factors that alter their service levels such as resort status, costal location or major climatic differences. From these criteria, these cities are comparable: Residents Size Police & Fire Police Districts Birmingham, AL 230, SM 1, /1,000 4 Durham, NC 230, SM /1,000 6 Greensboro, NC 260, SM 1, /1,000 3 Lubbock, TX 226, SM /1,000 1 Winston-Salem, NC 230, SM 1, /1,000 1 The national average number of sworn Police officers per thousand residents is 3.0. The variations in the structure and size of each of the five cities make establishing direct comparisons very difficult. There is a wide variety of variables within the Public Safety November 9, 2011 (DRAFT) Page 8 of 20

9 Departments that affect office needs (number of employees, centralized versus de-centralized offices, service co-locations, department management structure, etc.). The parameters of this Study do not include direct establishment of space needs. That is reserved for Phase Two. It would be prudent to further analyze these cities as Phase Two progresses in order to draw whatever parallels exist within the service models and office spaces. This will provide additional check points in the space requirement establishment process as the full Public Safety Facility need emerges during Phase Two. CO-LOCATION ANALYSIS As the current situation demonstrates, the three Public Safety departments can function separately or together. During the design of the current PSC in the 1980 s, Winston-Salem operated on the Public Safety Officer concept, with a portion of Police and Fire personnel crosstrained and serving in both departments. Given that arrangement, it made sense for both departments to have offices in the same building. Winston-Salem suspended the Public Safety Officer concept in 1987 and returned to the traditional separate officer model. The only crossover function now is the need for the heads of both departments to meet together regularly for planning and information sharing. They could also share some meeting space. Accordingly, Police and Fire could occupy separate spaces. In emergency event situations, the most efficient arrangement is for Police, Fire and Emergency Management to be located together in the same building with the EOC. Some classroom oriented training functions could be provided in their respective offices, but most of those needs are now served through the Beaty Center. Fire prefers for some training to occur in Fire Stations to keep fire fighters dispersed in the community, facilitating response times if a fire call comes in during training. Driving training should not be located at either office location. The noises, smoke and smells generated during driving training are not conducive to a business/administrative environment. Fire suppression training also needs a free-standing facility at a remote location for obvious reasons. The Police Department is in the process of constructing a new firing range, while decommissioning and remediating the current range. This new location serves the need for a firing range. The former range will be used for munitions training, K-9 training and small amounts of munitions disposal and disablement. Both of these sites are large and accommodate these functions very well. The offices that the Police Department leases generally serve functions that need to be located away from the PSC for undercover operations and other reasons demanding anonymity or separation. The bicycle patrol offices are located strategic to their patrol area downtown and should remain there. The fleet management facilities for both Police and Fire could be located virtually anywhere in the County. These functions could also be a component of City Yard. Emergency Management demands a location near supportive spaces. It would benefit from being in the same building as the EOC for efficiency during an emergency event. This would also likely place Emergency Management in the same building as Police and Fire. This would be another benefit during emergencies and simulations. November 9, 2011 (DRAFT) Page 9 of 20

10 Police and Fire fleet management potential locations offer a number of possibilities. They are very specialized functions and are currently in separate locations. That arrangement can remain. They could be located in a new facility or merged into City Yard. In either case, these specialized functions should be staffed by separate personnel. SERVICE, PROGRAM AND DEMOGRAPHIC FACTORS AFFECTING SPACE ALLOCATIONS A possible service change that would affect the need for space would be a precinct office arrangement for Police. With the current central PSC, all patrol officers must travel to one location for shift change, roll call, booking, interviews, etc. This is very inefficient with respect to consumption of officer time, fuel consumption, vehicle wear and tear and service effectiveness. Opening precinct offices in the Police beat locations would move those functions out of the PSC for all but one or two beats. This would afford a higher degree of efficiency relative to officer travel time and vehicle fuel consumption, increase the service effectiveness by keeping officers in their beats longer and it would also reduce the demand for space in the current or new PSC. This could potentially provide a total reduction in space need in the PSC of 20% to 30%. It would also reduce the demand for parking at the PSC. Program changes would be difficult to predict. They could have both an increasing and decreasing affect on the need for floor space. Federal mandates could dictate a higher per capita ratio of sworn officers. The City could return to a Public Safety Officer concept, thereby changing the staffing dynamic, along with the related floor space needs. New, unknown threats could result in new types of officers, more officers, specialized space and new training methods. The policing functions of the City Police Department and the County Sheriff s Department could be merged into one Department. Charlotte-Mecklenburg is a local example. This would change staffing and the need for support space. Legal interpretations at the State level may open the possibility for City of Winston-Salem Police officers to serve local municipalities in place of the current arrangement staffed by County Sheriff s Deputies. Again, these are all difficult to predict. It is fairly easy to predict that the local population will grow. This will in turn require the Police and Fire departments to grow. This will be pushed in the Police department mostly by population growth to continue service levels. In the Fire department, annexation of land area will result in more fire stations to maintain acceptable response times. This is ongoing now with the recent completion of Station 20 and the bidding process for Station 19. Increases in the number of firefighters will increase the need for training space and office floor space for leadership positions. Just like predicting program changes, accurately predicting the rates of population and land area growth is difficult. What can accurately be predicted is that both will grow over time. The total number of Police employees has increased at precisely the same rate as population growth over the current 25-year life of the PSC. The total number of Fire employees has increased in a similar manner. November 9, 2011 (DRAFT) Page 10 of 20

11 POTENTIAL PUBLIC SAFETY CENTER OPTIONS AND LOCATIONS 1. Build a new PSC on North Patterson Avenue across from Beaty Center. This option involves the 11+ acres on the east side of North Patterson Avenue, directly across from the Beaty Center. This site represents the balance of the former Thomasville Furniture manufacturing facility. Other contiguous properties under different ownership are vacant and could possibly be added to the size of the original tract. All existing structures would be demolished and any prior soil contamination would be remediated. This site offers several positive benefits: A new PSC could be built apart from the existing PSC, allowing the current PSC to remain in operation. The new PSC on this site could benefit from hardened design elements and site design that could reduce blast impact from surrounding streets. The location directly across from the Beaty Center affords the possibility of secure transfer of evidence and property via an over-street walkway directly from the PSC to the Beaty Center. The location directly across from the Beaty Center affords the possibility of direct access to training classrooms via an over-street walkway directly from the PSC to the Beaty Center. This site represents a largely central location, much like the current location. The new PSC design could be programmed without the restraints of fitting into an existing facility. This site is large enough for a facility that can co-locate Police, Fire and Emergency Management in the same facility. Future expansion options can be accommodated into the facility design. This site provides a neighborhood Police presence for positive community relations. Secure and safe parking can be accommodated on this site. 2. Build a new PSC in an unidentified location. Another option is to seek a site that could provide the following: Access to major and/or minor thoroughfares. 7 to 10 acres of site area. Neighborhood presence. Sufficient distance from surrounding streets for blast resistance. Growth space for future needs. 3. Upfit a portion of the former Flak-T Bahnson building on Lowery Street. This former manufacturing site offers over 310,000 square feet of ground floor space on 36 acres near the intersection of US Hwy. 52 and Business I-40. Public safety space would have to be inserted into an existing facility, but this site offers ample space to manage a fit and provide expansion. Other City departments could share the space. The site has high accessibility to two major thoroughfares. Large open spaces to the south provide isolation for security. November 9, 2011 (DRAFT) Page 11 of 20

12 The proximity of US 52 on the north and the railroad on the south pose hazards related to accidents with potential chemical spills and other related exposures. This site provides driving training space for both Police and Fire. This site has very little or no neighborhood presence. 4. Renovate the PSC for use by Police and Fire. This option, after completion, would largely maintain the status quo. However, maintaining that position would not improve the overcrowding issues. In fact, giving the building more flexibility by adding heating and air conditioning units to each level would take floor space now dedicated to office and other uses. Replacing the central mechanical system requires vacating the entire building. That means temporary space would need to be in place for both Police and Fire for the duration of the renovation. A key component of that space would be adequate computer and connectivity technology to run a modern police and fire department for a city the size of Winston-Salem. Assuming these logistical factors would be acceptable, the building could be renovated once it was vacated. All interior elements would be demolished on each floor down to the exterior shell, floors and roof. Stair wells and elevator shafts would remain. The exterior concrete walls would be supplemented with new stud walls, an air infiltration barrier, insulation and gypsum board. Both the amount and continuity of the insulation would be improved and completed. This would also be the time to address building hardening as it relates to the building shell (walls, glass, etc.). Given the site and streets surrounding the building, there appears that little can be done to dramatically improve the building s blast resistance. Mechanical rooms could be added on the second and third floors, giving each floor its own mechanical system. Electrical capacity would be increased, as would data capability and connectivity. This would replicate the data and connectivity piece contained on the temporary space, requiring the purchase of these elements and equipment twice in an 18-month period. New high efficiency light fixtures would be added as well. An automatic fire sprinkler and suppression system would also be added. New toilets would be designed to be fully accessible, along with fixture counts to match the current North Carolina building code. Parking availability at the renovated Center would still be an issue, unless contiguous or nearby properties were acquired. The security and safety concern of the parking areas would need to be addressed as well during the renovation. This option seems to be very burdensome given the need to find functional, temporary space for both Police and Fire by requiring them to move two times in 18 months. The chances for success would be slightly improved if Fire were found a permanent space prior to the renovation. That still would require Police to be moved to temporary space and back again. Another factor that would contribute positively would be the Police precinct office concept. This would relocate space needs now assigned to the PSC to other locations, slightly reducing the space needed in the renovated PSC. The estimate of probable construction cost for renovating the PSC as described would be $15.0 million. This cost calculates to $250 per square foot and would involve everything in the November 9, 2011 (DRAFT) Page 12 of 20

13 building except for the structure and a portion of the exterior shell. The building glass would require replacement in order to enhance the hardness of the structure. Moving costs are not included in this figure and could total $50,000 to $100,000. Lease costs for the 18 month renovation period are also not included. Assuming 50,000 square feet of floor space would be adequate, the lease cost for the 18 month renovation period could range from $900,000 to $1.35 million, reflecting a per square foot price of $12 to $18 per square foot. 5. Renovate the PSC for use by other City of Winston-Salem Departments. Once a new PSC was constructed elsewhere, the current facility could be renovated largely as described above and occupied by other City departments. Any number of City departments that could benefit from being located in a facility like this would be candidates for moving. Those could include Inspections, Planning and others. This could improve access to these departments by their user groups, also provide growth space and satisfy co-location efficiencies for related departments. The estimate of probable construction cost for renovating the PSC as described would be $9.0 million, not including moving costs or any costs associated with temporary space(s). 6. Sell or transfer the PSC to another Owner. Once new facilities were completed for Police and Fire, the current PSC could be sold or transferred to another Owner. The list of interested government parties could include County, State or Federal Government entities for offices, Forsyth Technical Community College for instructional and office use, as well as private owners such as banks or small businesses. It could also be offered as leased office space for private companies or business incubator space. This option would deflect the renovation expenses, while potentially gaining income from the sale of the building. This option assumes the building would be sold or transferred as-is. No costs are associated with this option. In a sale of the building, it is anticipated that $1.0 million to $1.5 million of income would be generated. Lease options would involve some undetermined renovation expenses and unidentified lease income. Both of those can be assumed to be concurrent with buildings of similar type and final use. EMERGENCY OPERATIONS CENTER Emergency Management should be in a facility that can supply their need to mobilize without the distance issues posed by the current arrangement. This would eliminate the several hours now required to move and be ready to manage an event, allowing them to be ready immediately. This should be space directly adjacent to their day-today office space, providing sufficient space for Emergency Management training, exercises and actual event management. With Police, Fire and Emergency Management all near the EOC, their day-to-day interaction is greatly enhanced. Their immediate response to an emergency is also possible. The EOC also facilitates drills, exercises and training with minimal impact on normal, daily operations. The space can also be multi-functional for use by a number of City and County departments for training, meetings, etc. The facility should be: Approximately 12,000 square feet. November 9, 2011 (DRAFT) Page 13 of 20

14 Contain daily offices for Emergency Management and spaces required for emergencies, such as kitchen, showers, communications, collateral agencies, briefing rooms, secure rooms for elected officials and supply storage. Remotely located away from impact hazards, blast zone isolation, outside of flood prone areas and in an area unlikely to be affected by most emergencies and disasters. The site should be able to supply area for parking, tractor trailer storage and maneuvering, and additional temporary emergency facilities. The facility should be designed to hurricane impact standards. November 9, 2011 (DRAFT) Page 14 of 20

15 IV - OPTIONS As a result of the interviews, tours and analysis, several factors have been identified that affect Winston-Salem s Public Safety facilities: Police and Fire do not need to be in the same building for operational efficiencies, but it does make sense from an emergency management perspective. The PSC is over-utilized to the point of significant work inefficiency. Emergency Management should be located in an event-ready Emergency Operations Center. Fire lacks several structural training facilities, including driver training and fire suppression training. Logistically, it would be nearly impossible to renovate the PSC for Police use. A community Precinct office model for Police reduces the amount of PSC office space required. As a result of the Study, several options have been identified for consideration: Renovate the current PSC for Police and Fire. This option would require finding temporary space for both Departments that supplied their space and technology needs for approximately 18 months, moving them out of the PSC and back in once it was renovated. Both Departments could be located together in the same facility or in separate facilities. This option assumes the Police Precinct office model is adopted, reducing the space need for Police in the renovated PSC and offering growth room as a result. Renovate the current PSC for Police, Fire and Emergency Management. This option carries the requirements for Police and Fire noted above for moving out and back in. It also requires finding space in the current building for Emergency Management. A full space planning process would reveal the ability of the renovated PSC to offer enough space for all three Departments. Renovate the current PSC for Fire and other City Departments. This option would create renovated space in the current building for Fire, as well as space for other City Departments (Inspections, Planning, Public Works, Engineering, etc.). This option affords the possibility to co-locate Departments other than Police in the renovated PSC. A Department such as Inspections shares some functions with Fire and could benefit from a facility somewhat removed from City Hall for public access and employee efficiencies. Transfer or sell the PSC to another entity. The building is usable by other public agencies or marketable to private users. The current facility is capable of serving other City Departments, County agencies and even Federal agencies. It also offers a viable private office facility. Possibilities include corporate offices, main offices for a small bank, small data center, call center or a business incubator key-person location. Build a new PSC at the current North Cherry Street site. A new PSC would be built at the current site (with additional property acquisitions). The existing PSC would then be demolished. This option could locate all three Public Safety Departments in a new building on an enlarged North Cherry Street site. November 9, 2011 (DRAFT) Page 15 of 20

16 Build a new PSC on an unidentified site. Sites with existing buildings or bare sites could supply options for a new PSC. Locations would have to be identified and evaluated for size and location. Build a new PSC on North Patterson Avenue. The former Thomasville Furniture manufacturing facility site could provide the site for a new PSC. A direct connection to the Beaty Center could be provided via an over-street walkway for access to training and evidence transfer to storage. This site also offers the possibility of locating all three Departments on the same site. Acquire the former Bahnson site for upfit as a new PSC. This very large facility can be renovated for use by all three Public Safety Departments, while leaving space for growth or other City Departments. There is ample space in this existing facility for all three Departments as well as other Departments that could benefit from being in the same facility. Seek and build a site for driver training and fire suppression training. This function is currently unfulfilled and would be best served by a free-standing site with external buffer space. Smoke from training fires could hinder local traffic flow as drivers slow to view the activity. Driver training vehicle generate noise and sounds that should be isolated from adjacent areas. Merge vehicle outfitting and maintenance functions into City Yard space. These functions can be served in their current free-standing locations or merged into City Yard space. Continue to program and upfit space at the Beaty Center. This facility has recently undergone significant renovations to supply training space, evidence processing space and long-term evidence storage space. It is logical for those functions to remain in the Beaty Center and be allowed to grow in place, capitalizing on the investment made there. Upfit the second floor of the Beaty Center as an EOC. The second floor contains ample space for an EOC. Fire could be located there as well. Upfitting the building for these functions will limit its ability to provide long-term evidence processing and storage space. This could be mitigated through future additions to the Center. November 9, 2011 (DRAFT) Page 16 of 20

17 V RECOMMENDATIONS (A or B) Recommendation A. 1. Begin the negotiation, due-diligence and purchase process for the former Thomasville Furniture facility on North Patterson Avenue. This property is crucial to the concept of a unified PSC. Its location across from the Beaty Center makes it a logical choice for a Police headquarters facility. The site has a neighborhood presence, it is largely centrally located, it can be directly connected to the Beaty Center for secure evidence and property transfer and it is convenient to the Beaty Center for training. No other current site can offer these positive attributes. Once purchased, contracts can be awarded for demolition of the structures and clean-up of the site as required. 2. Establish 3 Community Police Precinct Offices. This will provide a broader, ongoing Police presence in the community and increase operational efficiency of the Department in terms of time and fuel consumption. Citizens also gain a higher degree of access to the Department, and the size of a new Public Safety Center can be reduced. Vacating the existing PSC also facilitates its total renovation at one time, as opposed to a floor-byfloor basis. 3. Program, design and construct a new PSC on the former Thomasville Furniture site to provide central space for Police, Fire and Emergency Management. Relocate Police and Fire from the current PSC and Emergency Management from Smith Reynolds Airport. All current additional Police and Fire spaces (bike patrol, firing range, Clemmons K-9 and munitions facility, fleet management and leased space) will remain in their current locations. The new PSC will contain an EOC. 4. Renovate the current PSC to accommodate other City Departments. Those would include Departments that would benefit from an enhanced public access arrangement. One example would be Building Inspections. This location would improve the ability for users of their services to access their offices and add efficiency to the Building Inspectors routine of travelling out to the community and back to the office. 5. Seek a site for Police and Fire driver training and Fire suppression training. Driver training could take place on a portion of the Bahnson site. Fire suppression training would best be located on an isolated site to provide visual and geographic buffers from surrounding uses and highways. 6. Continue the upfit process at the Beaty Center. This is the logical progression in a facility renovated to supply current and future space needs related to training, evidence processing and evidence storage, and to protect these elements over a long period of time. Other uses may be identified for portions of the space over time, but those should be secondary to the space required for the three core functions. PROJECTED COST OF RECOMMENDATION A: PSC Building only (80,000 $350/SF) - $28,000,000. Additional costs not included: Property acquisition and demolition, moving costs, existing PSC renovation cost for other City departments. November 9, 2011 (DRAFT) Page 17 of 20

18 Recommendation B. 1. Establish 3 Community Police Precinct Offices. This will provide a broader, ongoing Police presence in the community and increase operational efficiency of the Department in terms of time and fuel consumption. Citizens also gain a higher degree of access to the Department, and the size of a new Public Safety Center can be reduced. Vacating the existing PSC also facilitates its total renovation at one time, as opposed to a floor-byfloor basis. 2. Move Police and Fire out of the existing PSC and into temporary space at the Beaty Center. This move clears the way for the existing PSC to be completely renovated. The total renovation at one time retains a number of advantages over a floor-by-floor renovation. Security of the building is not compromised, and the public and staff are not subjected to safety issues inherent around a construction zone. The renovation costs are reduced by capitalizing on economies of scale in a larger construction project, as well as having each trade mobilize once for their work instead of once for each floor. Additional savings are realized by establishing a new Police Communications Center in the Beaty Center and keeping it in place there after the move back to the renovated PSC. This saves the cost of reproducing the Communications Center in the renovated PSC and frees floor space up in the renovated PSC as well. 3. Renovate the existing PSC. A vacated PSC allows it to be completely renovated and reprogrammed according to current-day Public Safety needs and building code requirements. The building exterior shell can be hardened, and the thermal envelope can be greatly improved for energy savings. New mechanical systems can be designed for each floor, facilitating future renovation needs. Public and staff safety can also be improved in the process. 4. Move Police, Fire and Emergency Management into the renovated PSC. With the establishment of the 3 Community Precinct Offices and the absence of communications in the building, the PSC can now provide adequate and growth space for all three departments. They can now begin to reap the benefits of being co-located within the same building. As stated above, they can also benefit from a re-programmed facility that provides space designed around current-day Public Safety standards. 5. Allow the Communications Center to remain in the Beaty Center. Keeping the communications center in Beaty capitalizes on the investment made to complete the move out of the PSC. It also frees up additional floor space in the PSC. 6. Continue the upfit process at the Beaty Center. This is the logical progression in a facility renovated to supply current and future space needs related to training, evidence processing and evidence storage, and to protect elements of evidence over a long period of time. Other uses may be identified for portions of the space over time, but those should be secondary to the space required for the programmed core functions. PROJECTED COST OF RECOMMENDATION B: Moving costs - $100,000; temporary space upfit at Beaty Center - $3,000,000; technology for Communications Center at Beaty Center - $1,000,000; PSC renovation (60,000 $250/SF) - $15,000,000 = $19,100,000 November 9, 2011 (DRAFT) Page 18 of 20

19 VI NEXT STEPS Completion of Phase Two will complete the Public Safety needs picture for the City of Winston- Salem, including total space requirements, establishment of Proposed Capital Projects, timelines and estimated construction costs. The space needs establishment process, or programming process, allows further detailed study of the space needs and adjacency needs for each Department. The proposed space requirements for each department can also be compared to the four similar cities noted in this Study as a means of tracking those space recommendations. Specifically, Phase Two will: 1. Analyze current staffing and deployment needs, given workloads and service level objectives, and determine future staffing needs. The steps in this Task analyze current staffing requirements in each public safety department. This step is critical given the need to project future facility requirements. This Task ensures that future projections are based on a strong foundation. The following approaches will be utilized: Utilize workload to calculate those functions (patrol, investigations, inspections, emergency dispatch) that are heavily dependent on the timing and volume of workload. Utilize other functions (geography, response time targets) for functions that are less strictly dependent on workload. Document staffing requirements for programs that are dependent on staff (emergency operations, public information officer, etc.) for the program in place but that are neither dependent on workload nor on performance targets. Following the development of these current staffing projections, planning and growth management information from the City will document the following: Annexation and other growth plans for the City over the planning period. Projections for population growth and changes in the City. Anticipated changes in service level objectives. Once these key factors have been documented, the following can then be established: Projections as to changes in population and resulting workload. A model that projects the required staffing and space needs for each. 2. Develop future space requirements, including consideration of adjacency and operational priorities. Following the development of the future staffing requirements for each of the public safety departments, the process will translate these findings into the following: November 9, 2011 (DRAFT) Page 19 of 20

20 Analyze current staffing and deployment needs given workloads and service level objectives, and determine future staffing needs. These will be assessed across all three Public Safety Departments. Draw comparisons and parallels between Winston-Salem and similar cities. Develop future space requirements, including consideration of adjacency and operational priorities. This will set space requirements for each Department and allow for future growth and known Department changes. Define the projects and their scope. Complete code reviews and project design programs. Establish estimates of construction costs. Develop recommendations for inclusion of the projects in future Capital Project Budgets. Completion of Phase Two will complete the Public Safety Needs picture, including total space requirements and estimated construction costs. Upon concurrence and/or direction from the Public Safety Committee and City Council, it is recommended that this team be authorized to proceed to Phase Two. This Public Safety Needs Assessment Study is a necessary step in a process that identifies the needs in all three Departments, defines proper project parameters, establishes priorities and establishes capital needs for several projects. This concludes Phase One of the Public Safety Needs Assessment Study for the City of Winston-Salem. November 9, 2011 (DRAFT) Page 20 of 20

CITY OF WINSTON-SALEM, NORTH CAROLINA Public Safety Needs Assessment Study Phase One EXECUTIVE SUMMARY

CITY OF WINSTON-SALEM, NORTH CAROLINA Public Safety Needs Assessment Study Phase One EXECUTIVE SUMMARY EXECUTIVE SUMMARY I. Documentation and Current Conditions Establishment Process II. Existing Public Safety Facilities Analysis III. Space Allocation, Co-Location and Potential Site Location Analysis IV.

More information

City Hall Space Selection 15 Market Square. November 27, 2017

City Hall Space Selection 15 Market Square. November 27, 2017 City Hall Space Selection 15 Market Square November 27, 2017 Future City Hall Space Recommendation Recommendation Committee of the Whole recommends that Common Council approve the Offer to Amending Existing

More information

M E M O R A N D U M. To: California State Lottery Commission Date: October 16, Item 9(c): Approval to Hire Project Management Consultant

M E M O R A N D U M. To: California State Lottery Commission Date: October 16, Item 9(c): Approval to Hire Project Management Consultant M E M O R A N D U M To: California State Lottery Commission Date: From: Joan M. Borucki Director Prepared By: Linh Nguyen Chief Deputy Director Subject: Item 9(c): Approval to Hire Project Management Consultant

More information

LAW ENFORCEMENT SUBSTATIONS NOVEMBER 17, 2015

LAW ENFORCEMENT SUBSTATIONS NOVEMBER 17, 2015 LAW ENFORCEMENT SUBSTATIONS NOVEMBER 17, 2015 TIMELINE Needs Assessments CMAG study (2009) identified/recommended Law Enforcement (LE) and Administration functions to centralize. Law Enforcement Needs

More information

Riverside Public Utilities Long Range Space Plan. Board of Public Utilities 12/07/12

Riverside Public Utilities Long Range Space Plan. Board of Public Utilities 12/07/12 Riverside Public Utilities Long Range Space Plan Board of Public Utilities 12/07/12 Long Term Goals Centralize staff location(s) for 650 positions Increase security for critical 24/7 operations Optimize

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

PUBLIC WORKS ORGANIZATIONAL CHART

PUBLIC WORKS ORGANIZATIONAL CHART PUBLIC WORKS ORGANIZATIONAL CHART C-108 Actual 2012-13 Adopted Year-End Estimated 2014-15 2015-16 PROGRAM EXPENSES/REVENUES Salaries & Benefits $ 1,725,030 $ 1,855,980 $ 1,676,130 $ 1,956,510 $ 1,979,470

More information

FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT

FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT Jack Strollo, Broker 500 S. Florida Avenue, Suite 420 Lakeland, Florida 33801 O. 863.683.3425 x103 C. 863.640.8238 jstrollo@resbroadway.com FOR SALE BANK OWNED OFFICE CENTRAL LAKELAND HISTORIC DISTRICT

More information

Corporate Security & Emergency Management Summary of Submitted 2015 Budget From Rates

Corporate Security & Emergency Management Summary of Submitted 2015 Budget From Rates Corporate Security & Emergency Management Summary of Submitted 2015 From Rates Service Expense 2014 2015 Revised Non Tax Revenue Net Tax Supported Expense Draft Non Tax Revenue Net Tax Supported Increase

More information

1.1 OVERVIEW OF THIS BOOK

1.1 OVERVIEW OF THIS BOOK 1 Introduction 1.1 OVERVIEW OF THIS BOOK Today s datacom (data and communications) facility managers and operators understand the importance of protecting their business critical data and information technology

More information

Municipal Service Park 3 December Consolidation of City services to one centralized complex

Municipal Service Park 3 December Consolidation of City services to one centralized complex Municipal Service Park 3 December 2010 Consolidation of City services to one centralized complex Overview: Operational Challenges and Opportunities South East Connector impacts Opportunities: The South

More information

AN EMERGENCY OPERATIONS CENTER FIELD STUDY HENRICO COUNTY, VIRGINIA. by Anna M. McRay

AN EMERGENCY OPERATIONS CENTER FIELD STUDY HENRICO COUNTY, VIRGINIA. by Anna M. McRay Notes on the Science of Extreme Situations, Paper No. 2 AN EMERGENCY OPERATIONS CENTER FIELD STUDY HENRICO COUNTY, VIRGINIA by Anna M. McRay Copyright 2002 by Anna M. McRay. All rights reserved. Permission

More information

GORE BUILDING. 238 N. Massachusetts Avenue, Lakeland, FL 33801

GORE BUILDING. 238 N. Massachusetts Avenue, Lakeland, FL 33801 GORE BUILDING 238 N. Massachusetts Avenue, Lakeland, FL 33801 CDB LOCATION REDEVELOPMENT PROJECT MUNN PARK HISTORIC DISTRICT INCENTIVES AVAILABLE ADJACENT PARKING INCLUDED BK698301 Phone: (863) 683-3425

More information

F O R S A L E F O R L E A S E

F O R S A L E F O R L E A S E F O R S A L E F O R L E A S E L E N O I R N C P O W E R E D S H E L L D A T A C E N T E R CALDWELL COUNTY LENOIR, NORTH CAROLINA Email: doug@five9sdigital.com Phone: 704.651.2210 Online: www.five9sdigital.com

More information

BUILDINGS AND FACILITIES

BUILDINGS AND FACILITIES EB-00-0 Exhibit C Tab Schedule Page of BUILDINGS AND FACILITIES FACILITIES AND ASSET MANAGEMENT OVERALL STRATEGY THESL s buildings and facilities (the facilities ) include operating centers (00 Commissioners,

More information

Property Maintenance & Operations Manual Training

Property Maintenance & Operations Manual Training Property Maintenance & Operations Manual Training Introduction to Property Operations Management and Building Security October 16, 2007 Property Maintenance & Operations Manual Training April 12, 2007

More information

U. S. Postal Service National Delivery Planning Standards A Guide for Builders and Developers

U. S. Postal Service National Delivery Planning Standards A Guide for Builders and Developers U. S. Postal Service National Delivery Planning Standards A Guide for Builders and Developers Table of Contents 1 Introduction... 3 2 Finding Your Growth Manager and USPS Online Resources... 4 2.1 Find

More information

BUSINESS CONTINUITY AND DISASTER RECOVERY ACROSS GOVERNMENT BOUNDARIES

BUSINESS CONTINUITY AND DISASTER RECOVERY ACROSS GOVERNMENT BOUNDARIES BUSINESS CONTINUITY AND DISASTER RECOVERY ACROSS GOVERNMENT BOUNDARIES Business Continuity and Disaster Recovery State of Utah NASCIO Awards 2009 1 BUSINESS CONTINUITY AND DISASTER RECOVERY ACROSS GOVERNMENT

More information

AMERICAN PKWY. FOR SALE CLASS A OFFICE HEADQUARTERS 4800 American Parkway, Madison, WI

AMERICAN PKWY. FOR SALE CLASS A OFFICE HEADQUARTERS 4800 American Parkway, Madison, WI FOR SALE CLASS A OFFICE HEADQUARTERS American Parkway, Madison, WI American Parkway Overview American Parkway is a Class A, 3-story, approximately 34,000 SF office building, within The American Center

More information

Capital Facilities and Equipment Plan

Capital Facilities and Equipment Plan Capital Facilities and Equipment Plan 2017-2021 Executive Summary and Purpose Responsible stewardship of the physical resources entrusted to us by our citizens is a core principle of Lacey Fire District

More information

Maximizing the University s Physical Assets (Part I): Facility Condition Assessment

Maximizing the University s Physical Assets (Part I): Facility Condition Assessment Maximizing the University s Physical Assets (Part I): Facility Condition Assessment Board of Regents Facilities and Operations Committee September 12, 2013 Agenda Program background Broadening our data

More information

RCMP Capital Improvements

RCMP Capital Improvements Prepared by: D. R. Duckworth, Corporate Services and Community Safety Director Improvements_BUS_1.docx Executive Summary This business case seeks approval for additional funding of $1,000,000 for capital

More information

EASTSIDE CITY OF BELLEVUE/ PRIVATE PRIVATE PRIVATE MULTI-PRIVATE MULTI-PRIVATE

EASTSIDE CITY OF BELLEVUE/ PRIVATE PRIVATE PRIVATE MULTI-PRIVATE MULTI-PRIVATE SITE COMPARISON CHART CITY Bellevue County Kirkland Kirkland Redmond ADDRESS 555 116th Ave. Lane 118th Ave. 14955 90th St. ACREAGE 5.6 10.7 7.5 5.5 7.2 to 11.6 ACRES ZONING COMMERCIAL LIGHT INDUSTRIAL

More information

Hurricane Florence Response and Recovery. October 18, 2018 Miles Lackey, Vice Chancellor of Business Affairs & CFO

Hurricane Florence Response and Recovery. October 18, 2018 Miles Lackey, Vice Chancellor of Business Affairs & CFO Hurricane Florence Response and Recovery October 18, 2018 Miles Lackey, Vice Chancellor of Business Affairs & CFO Event Impact Campus Grounds Approximately 400 downed trees Light poles Power lines Page

More information

Customer Service Center

Customer Service Center Facility Status B u d g e t, S i t e a n d F a c i l i t i e s O r g a n i z a t i o n O v e r v i e w F a c i l i t i e s S c o r e c a r d F a c i l i t y P l a n - S i t e P l a n, V i s i o n, M i

More information

Mountain Lakes Infrastructure Projects and Investments. January 2017

Mountain Lakes Infrastructure Projects and Investments. January 2017 Mountain Lakes Infrastructure Projects and Investments January 2017 Presentation & Discussion of: Birchwood & Island Beach Renovations Sunset Lake Dam Restoration/Rehabilitation Project Borough Hall Administrative

More information

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility

More information

Downtown Boise Multimodal Center

Downtown Boise Multimodal Center Treasure Valley High Capacity Transit Study Downtown Boise Multimodal Center Environmental Assessment June 2009 Prepared by the Federal Transit Administration and Valley Regional Transit. U.S. Department

More information

NOVEMBER department of transportation CONNECTICUT DEPARTMENT OF TRANSPORTATION. Statewide Computerized Traffic Signal Systems Needs Assessment

NOVEMBER department of transportation CONNECTICUT DEPARTMENT OF TRANSPORTATION. Statewide Computerized Traffic Signal Systems Needs Assessment department of transportation NOVEMBER 2015 CONNECTICUT DEPARTMENT OF TRANSPORTATION Statewide Computerized Traffic Signal Systems Needs Assessment EARLY DEPLOYMENT NEEDS ASSESSMENT-NOVEMBER 2015 The Connecticut

More information

After Action Report / Improvement Plan

After Action Report / Improvement Plan After Action Report Improvement Plan PSAP Paralysis A 911 Center COOP Drill June 24, 2015 Holmes County Emergency Management Department 1 Page ADMINISTRATIVE HANDLING INSTRUCTIONS 1. The title of this

More information

Increasing Distribution Demands: 5 Benefits of Modular Substations

Increasing Distribution Demands: 5 Benefits of Modular Substations Increasing Distribution Demands: 5 Benefits of Modular Substations ACHILA JAYASURIYA, SUBSTATION ENGINEER Substations play a critical role in the power industry. They support the transmission grid in moving

More information

DISASTER PREPAREDNESS IN THE COUNTY: IMPROVEMENTS NEEDED

DISASTER PREPAREDNESS IN THE COUNTY: IMPROVEMENTS NEEDED 2006-2007 SANTA CLARA COUNTY CIVIL GRAND JURY REPORT Summary DISASTER PREPAREDNESS IN THE COUNTY: IMPROVEMENTS NEEDED Disaster events that have occurred in Santa Clara County (County) have heightened interest

More information

Construct Chiller Plant, Phase I

Construct Chiller Plant, Phase I Page 1 of 6 Construct Chiller Plant, Phase I project 1 of 1 Virginia Polytechnic Institute and State University (208) General Information Project Type: New Construction Project Code: 17657 Start Year:

More information

26 th Street North and Old Dominion Drive Master Planning Task Force

26 th Street North and Old Dominion Drive Master Planning Task Force 26 th Street North and Old Dominion Drive Master Planning Task Force Presentation to Arlington Joint Facilities Advisory Commission October 24, 2018 Site Master Planning Task Force On September 2018, the

More information

Agenda Item No. AGENDA ITEM BRIEFING

Agenda Item No. AGENDA ITEM BRIEFING AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval to Amend the FY 2016-FY 2020 Texas A&M University

More information

Introduction. We are excited about the possibility of bringing Google Fiber to your city and look forward to working with you.

Introduction. We are excited about the possibility of bringing Google Fiber to your city and look forward to working with you. Introduction Over the last few years, gigabit Internet has moved from idea to reality, with dozens of communities working hard to build networks with speeds capable of supporting the future of the Internet.

More information

CITY OF JACKSONVILLE, FLORIDA

CITY OF JACKSONVILLE, FLORIDA FIRE AND RESCUE DEPARTMENT VISION: To move into the next century providing the finest in fire and emergency medical services by operating from modern facilities, utilizing the most effective vehicles,

More information

Critical Maintenance for Community Colleges bonded Health and Safety bonded Facilities Preservation bonded

Critical Maintenance for Community Colleges bonded Health and Safety bonded Facilities Preservation bonded Section Contents Five-Year Capital Plan FY 2017-18 through FY 2021-22 Project Funding Type Five-Year Plan Total ($ 000s) Critical Maintenance for Community Colleges bonded $235,000 Health and Safety bonded

More information

Environmental Impact Questionnaire

Environmental Impact Questionnaire Community Development Department 11 English Street Petaluma, CA 94952 Phone: 707-778-4301 Email: cdd@ci.petaluma.ca.us Web: www.cityofpetaluma.net/cdd Building Geographic Information Systems Housing Neighborhood

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline Georgia Institute of Technology Advanced Computing Technology Building Draft Program Vision Program Outline Issued April 2, 2001 I N T R O D U C T I O N Scope This document is a summary of the Vision Session

More information

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works

COUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works Item 7.3.5 Meeting date: August 13, 2018 Department: Prepared by: Reviewed by: SUBJECT: Engineering & Public Works COUNCIL REPORT George Elliott, P.Eng., Director of Engineering & Public Works Greg McClinchey,

More information

Pepperell Center Data Center Offering. Pepperell Center. Data Center Offering. Pepperell Mill Campus 40 Main Street Biddeford, Maine.

Pepperell Center Data Center Offering. Pepperell Center. Data Center Offering. Pepperell Mill Campus 40 Main Street Biddeford, Maine. Pepperell Center Data Center Offering Pepperell Mill Campus 40 Main Street Biddeford, Maine Page 1 Summer 2009 Table of Contents Project Summary... 3 History... 4 Location Viability... 5 Pepperell Center...

More information

SUMMIT TECHNOLOGY CAMPUS 777 NW BLUE PARKWAY I 850 NW CHIPMAN ROAD LEE S SUMMIT MO 64086

SUMMIT TECHNOLOGY CAMPUS 777 NW BLUE PARKWAY I 850 NW CHIPMAN ROAD LEE S SUMMIT MO 64086 SUMMIT TECHNOLOGY CAMPUS 777 NW BLUE PARKWAY I 850 NW CHIPMAN ROAD LEE S SUMMIT MO 64086 INFALLIBLE INFRASTRUCTURE. The Summit Technology Campus is comprised of two buildings totaling approximately 1,037,000

More information

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft

The Project Charter. Date of Issue Author Description. Revision Number. Version 0.9 October 27 th, 2014 Moe Yousof Initial Draft The Project Charter Project Title: VDI Data Center Design and Build Project Sponsor: South Alberta Data Centers Inc. (SADC Inc.) Project Customer: The City of Calgary Project Manager: Moe Yousof Document

More information

Building strong relationships within a jurisdiction by utilizing Geographic Information

Building strong relationships within a jurisdiction by utilizing Geographic Information Page 1 1. Program Overview Building strong relationships within a jurisdiction by utilizing Geographic Information Systems (GIS) resources is of obvious importance and essential. Relying upon those resources

More information

PREMIER DATA CENTER OPPORTUNITY ±64.31 ACRES OF LAND ENGLER BLVD AND HWY 212 Chaska, MN 55318

PREMIER DATA CENTER OPPORTUNITY ±64.31 ACRES OF LAND ENGLER BLVD AND HWY 212 Chaska, MN 55318 -$2.50/GROSS SF CLOVER PRESERVE DR PROPERTY HIGHLIGHTS + + Preliminary plat approved. Data center site, shovel ready + + 25MW service to the site via adjacent, double-ended substation with multiple feeds

More information

College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY through FY

College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY through FY Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan Request FY 2013-14 through FY 2017-18 Project Funding Type Total ($ 000s) Replacement of Unit Ventilation System

More information

Cisco Smart+Connected Communities

Cisco Smart+Connected Communities Brochure Cisco Smart+Connected Communities Helping Cities on Their Digital Journey Cities worldwide are becoming digital or are evaluating strategies for doing so in order to make use of the unprecedented

More information

Halifax Regional Municipality

Halifax Regional Municipality Halifax Regional Municipality Challenge Leverage existing IT infrastructure to design a high-definition surveillance system that helps protect corporate assets across the Halifax Regional Municipality

More information

Gold: points Platinum: 80+ points. Certified: points Silver: points

Gold: points Platinum: 80+ points. Certified: points Silver: points What is LEED? LEED, or Leadership in Energy & Environmental Design, is redefining the way we think about the places where we live, work and learn. As an internationally recognized mark of excellence, LEED

More information

2010 HURRICANE SEASON PREPARATION BRIEFING

2010 HURRICANE SEASON PREPARATION BRIEFING 2010 HURRICANE SEASON PREPARATION BRIEFING PSC Workshop May 17, 2010 Barbara Quinones, Director City of Homestead, Homestead Energy Services Today s Presentation System Overview Hurricane Experience Storm

More information

Five-Year Capital Plan Request FY through FY

Five-Year Capital Plan Request FY through FY Section Contents Five-Year Capital Plan Request FY 2015-16 through FY 2019-20 Project Funding Type Total ($ 000s) Critical Maintenance Seniors bonded $690,706 Health and Safety bonded Facilities Preservation

More information

Director of Public Works/City Engineer. Secretary. Word Processor. Streets and Facilities Supervisor. Traffic Signal Technician.

Director of Public Works/City Engineer. Secretary. Word Processor. Streets and Facilities Supervisor. Traffic Signal Technician. PUBLIC WORKS ORGANIZATIONAL CHART Director of Public Works/City Engineer Secretary Word Processor Transit Services Manager Fleet Services Supervisor Streets and Facilities Supervisor Principal Principal

More information

AGENDA ITEM # 1. CITY COUNCIL COMMUNICATION FORM

AGENDA ITEM # 1. CITY COUNCIL COMMUNICATION FORM AGENDA ITEM # 1. CITY COUNCIL COMMUNICATION FORM FROM: Joel Rae, Director of Public Safety (ext. 113) THROUGH: Deb Hinsvark, Interim City Manager (ext. 228) DATE: December 18, 2012 RE: Police and Fire

More information

4.11 PUBLIC SERVICES FIRE PROTECTION SERVICES REGULATORY FRAMEWORK. State Regulations PUBLIC SERVICES. California Building Code. California Fire Code

4.11 PUBLIC SERVICES FIRE PROTECTION SERVICES REGULATORY FRAMEWORK. State Regulations PUBLIC SERVICES. California Building Code. California Fire Code 4.11 This chapter describes public services provided in Walnut Creek and evaluates the potential impacts to public services that could result from development of the proposed Project. An Initial Study

More information

ANCHORAGE POLICE DEPARTMENT

ANCHORAGE POLICE DEPARTMENT ANCHORAGE POLICE DEPARTMENT Department Goal The goal of the Anchorage Police Department for the - Capital Improvement Budget/Program is to provide adequate equipment, facilities and communications systems

More information

RSI DISTRIBUTION CENTER 1,000,000 SF CLASS A INDUSTRIAL FACILITY WITH 13+ YEAR NNN LEASE 838 LINCOLN COUNTY PARKWAY LINCOLNTON, NC CHARLOTTE MSA

RSI DISTRIBUTION CENTER 1,000,000 SF CLASS A INDUSTRIAL FACILITY WITH 13+ YEAR NNN LEASE 838 LINCOLN COUNTY PARKWAY LINCOLNTON, NC CHARLOTTE MSA RSI DISTRIBUTION CENTER 1,000,000 SF CLASS A INDUSTRIAL FACILITY WITH 13+ YEAR NNN LEASE 838 LINCOLN COUNTY PARKWAY LINCOLNTON, NC CHARLOTTE MSA EXECUTIVE SUMMARY THE INVESTMENT OPPORTUNITY 1,000,000 SF

More information

2017 Capital Improvement Budget Police Department

2017 Capital Improvement Budget Police Department 2017 Capital Improvement Budget Police Department (in thousands) Projects Bonds State Federal Other Total APD Headquarters Campus Perimeter Security Project 500 - - - 500 APD Investigation Interview Room

More information

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association

VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association VTA s BART Silicon Valley Phase II Extension Project San Jose Downtown Association August 24, 2017 THANK YOU! San Jose Downtown Association for inviting us & San Jose First United Methodist Church for

More information

Energy Action Plan 2015

Energy Action Plan 2015 Energy Action Plan 2015 Purpose: In support of the Texas A&M University Vision 2020: Creating a Culture of Excellence and Action 2015: Education First Strategic Plan, the Energy Action Plan (EAP) 2015

More information

Cedar Rapids ITS Deployment Project

Cedar Rapids ITS Deployment Project Cedar Rapids ITS Deployment Project Concept of Operations July 29, 2011 Table of Contents Section 1 Introduction Purpose Goal of ITS Deployments Section 2 Needs Assessment General Background Stakeholders

More information

Request Conditional Use Permit (Colleges & Universities, public or private) Staff Planner Ashby Moss

Request Conditional Use Permit (Colleges & Universities, public or private) Staff Planner Ashby Moss Applicant & Property Owner Public Hearing July 13, 2016 City Council Election District Bayside Agenda Item 9 Request Conditional Use Permit (Colleges & Universities, public or private) Staff Planner Ashby

More information

Heavy Industrial / Corporate Office Campus

Heavy Industrial / Corporate Office Campus Heavy Industrial / Corporate Office Campus -Priced at: $80 Sq.Ft. -131,040 square feet (+/-) -8.8 Acres (+/-) -18 Megawatt Electrical Service -500,000 Gallons per-day Water Service 1270 SE Monmouth Cutoff

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

Appendix 2. Capital Funding Source Summary Table of Contents

Appendix 2. Capital Funding Source Summary Table of Contents Capital Source Summary Table of Contents 2016 Corporate Services APP 2-3 Mayor and Council APP 2-5 Office of the Chief Administrative Officer APP 2-5 Office of the Chief Operating Officer APP 2-5 Planning

More information

PREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT

PREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT PREPARED STATEMENT OF ERNEST R. FRAZIER, SR., ESQ. AMTRAK, CHIEF OF POLICE AND SECURITY DEPARTMENT HOUSE TRANSPORTATION & INFRASTRUCTURE SUBCOMMITTEE ON RAILROADS Oversight Hearing on Railroad Security

More information

Mission Statement & Company Overview

Mission Statement & Company Overview STP_SOLUTIONS_Services_Brochure 13/09/2011 14:22 Page 1 SPECIALISTS IN PROVIDING NATIONWIDE WORKSPACE SOLUTIONS OFFICE REFURBISHMENT DATA CENTRES / DISASTER RECOVERY SITES ELECTRICAL & MECHANICAL INSTALLATIONS

More information

City Reso-A Requests FY 2018 (City Council and Borough Presidents)

City Reso-A Requests FY 2018 (City Council and Borough Presidents) Section Contents College Statement and Statistics Campus Site Map Five-Year Capital Plan FY 2017-18 through FY 2021-22 Project Funding Type Five-Year Plan Total ($ 000s) Replacement of Unit Ventilation

More information

Hazard Management Cayman Islands

Hazard Management Cayman Islands Hazard Management Cayman Islands Strategic Plan 2012 2016 Executive Summary HMCI strategic plan outlines the agency s outlook in the next five years and illustrates the main strategies as goals that will

More information

Facilities Department Town of Duxbury, MA

Facilities Department Town of Duxbury, MA Facilities Department Town of Duxbury, MA FY18 Capital Project Request Presentation To The Board of Selectmen, Finance, & Fiscal Advisory Committee s Duxbury Senior Center November 14, 2016 Prepared and

More information

Inland Real Estate Commercial Brokerage, Inc Butterfield Road, Oak Brook, IL CALL FOR OFFERS

Inland Real Estate Commercial Brokerage, Inc Butterfield Road, Oak Brook, IL CALL FOR OFFERS CALL FOR OFFERS ACQUIRE SIGNIFICANTLY BELOW APPRAISED VALUE Offering Brochure For further information contact: Paul Montes Sr. Vice President 630-954-4446 montes@inlandgroup.com Eric Spiess Sr. Vice President

More information

Critical Infrastructure Assessment

Critical Infrastructure Assessment Critical Infrastructure Assessment Everyday the products and services that support our standard of living flow, almost seamlessly, to and from our homes, communities, and government. Making this possible

More information

Scoping Notice. For a new North Kaibab. Inter-agency Office Complex

Scoping Notice. For a new North Kaibab. Inter-agency Office Complex Scoping Notice For a new North Kaibab United States Department of Agriculture Inter-agency Office Complex North Kaibab Ranger District Kaibab National Forest Forest Service Coconino County, Arizona Section

More information

Appendix M. Lifeline Sector Coordination

Appendix M. Lifeline Sector Coordination Appendix M. Lifeline Sector Coordination Regional Water Supply Resiliency Project Phase 2 Summary Report July 2018 This page intentionally left blank. Regional Water Supply Resiliency Project Phase 2 Summary

More information

Feasibility of Establishing a Toner Cartridge Refilling Station

Feasibility of Establishing a Toner Cartridge Refilling Station STAFF REPORT August 8, 2005 To: From: Subject: Administration Committee Treasurer Feasibility of Establishing a Toner Cartridge Refilling Station Purpose: The purpose of this report is to respond to the

More information

S T A F F R E P O R T

S T A F F R E P O R T S T A F F R E P O R T Meeting Date: 04 Jul 2017 To: Prepared By: Reviewed/Approved By: Department Report No: Subject: Corporate Strategic Plan: Mayor and Members of Council Lynn Phillips Tim Blake, Valerie

More information

Library Board of Directors / Board of County Commissioners 21 May 2015

Library Board of Directors / Board of County Commissioners 21 May 2015 Library Board of Directors / Board of County Commissioners 21 May 2015 1 2 Acknowledgements Group 4 Architecture, Research, and Planning Carson Block Consulting Joan Frye Williams Collins Noteis and Associates

More information

IV.I.1 Police Protection

IV.I.1 Police Protection 1. INTRODUCTION This section of the Draft EIR discusses police protection within the project area. Sources of information used in the preparation of this section include: coordination with the Los Angeles

More information

David Griffin MOCKINGBIRD & I-35 DALLAS, TEXAS

David Griffin MOCKINGBIRD & I-35 DALLAS, TEXAS IN THE AREA: AERIAL River Bend is a unique real estate opportunity in the core of Dallas. With its convenient location near Dallas Love Field and the University of Texas Southwestern Medical District,

More information

Kentucky Wireless Information Network Service (Ky-WINS)

Kentucky Wireless Information Network Service (Ky-WINS) 2006 NASCIO Recognition Awards Nomination Category: Information Communications Technology (ICT) Innovations Kentucky Wireless Information Network Service (Ky-WINS) Kentucky State Police Kentucky has implemented

More information

Centre Lionel E. Lalonde Centre (Emergency & Protective Services Centre)

Centre Lionel E. Lalonde Centre (Emergency & Protective Services Centre) (Emergency & Protective Services Centre) Priorities Committee Meeting Wednesday, March 21 st 2007 Presented By: Tim P. Beadman Acting General Manager of Emergency Services - and - Richard Dixon Facilities

More information

FY Janette Pell Department Director. Information and Communications Technology. Administration and Finance

FY Janette Pell Department Director. Information and Communications Technology. Administration and Finance FY 2018 19 Janette Pell Department Director Administration and Finance Capital Projects Facilities and Real Estate Management Fleet Operations Information and Communications Technology Purchasing, Surplus

More information

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development

Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Planning, Program Development and Real Estate Committee Item V- B September 11, 2014 Approval to Negotiate and Execute a Term Sheet for the Navy Yard Chiller Site Joint Development Washington Metropolitan

More information

York Regional Police. 20-Year Facilities Master Plan. Final Report

York Regional Police. 20-Year Facilities Master Plan. Final Report York Regional Police 20-Year Facilities Master Plan Final Report Chris Polden January 25, 2017 2 Contents Introduction ORH Methodology Sector Policing Future Unit Requirement Station Location Optimization

More information

Platte County Courthouse Remodel Phase I Project

Platte County Courthouse Remodel Phase I Project Platte County Courthouse Remodel Phase I Project 1 Background The courthouse is in its 100th year of use and is in need of updates and space re-purposing to take us through another 100 years of serving

More information

WAREHOUSE / DISTRIBUTION EXPERIENCE

WAREHOUSE / DISTRIBUTION EXPERIENCE WAREHOUSE / DISTRIBUTION EXPERIENCE BERRY WHOLESALE DRUGS Walter Knestrick Contractor, Inc. The warehouse space includes a partial mezzanine with administrative offices and staff support areas. The mezzanine

More information

APPROVED WORK ZONE TRAFFIC CONTROL TRAINING GUIDELINES TRAINING PROVIDERS / COURSES FOR CONTRACTORS / SUBCONTRACTORS

APPROVED WORK ZONE TRAFFIC CONTROL TRAINING GUIDELINES TRAINING PROVIDERS / COURSES FOR CONTRACTORS / SUBCONTRACTORS APPROVED WORK ZONE TRAFFIC CONTROL TRAINING GUIDELINES TRAINING PROVIDERS / COURSES FOR CONTRACTORS / SUBCONTRACTORS The South Carolina Department of Transportation will require work zone traffic control

More information

Stryker Center Concept

Stryker Center Concept Stryker Center Concept 1/13 Background Information Evolution of Williamsburg s City Square (See Figure I) City government offices moved to N. Boundary St. from S. England Street in the early 1930s to make

More information

Campus Team Report - October 2,

Campus Team Report - October 2, Campus Team Report - October 2, 2016 - Campus Team Members Craig Rudd, Cornerstone Board Jinjer Menge, Cornerstone Board Clark Anderson, Finance Team Mike Soper, Cornerstone Church Teresa Johnson, Cornerstone

More information

Management Update: Storage Management TCO Considerations

Management Update: Storage Management TCO Considerations IGG-09172003-01 C. Stanley Article 17 September 2003 Management Update: Storage Management TCO Considerations CIOs, asset managers, data center managers and business managers should be aware of the total

More information

EMERGENCY SUPPORT FUNCTION (ESF) 13 PUBLIC SAFETY AND SECURITY

EMERGENCY SUPPORT FUNCTION (ESF) 13 PUBLIC SAFETY AND SECURITY EMERGENCY SUPPORT FUNCTION (ESF) 13 PUBLIC SAFETY AND SECURITY PRIMARY AGENCY: SUPPORT AGENCIES: Savannah-Chatham Metropolitan Police Department Armstrong-Atlantic Campus Police Department Bloomingdale

More information

2019 Capital Improvement Plan 2018 Adopted vs 2019 Request Executive CIP 2017 Adopted CIP

2019 Capital Improvement Plan 2018 Adopted vs 2019 Request Executive CIP 2017 Adopted CIP Police Department Capital Improvement Plan Project Summary Agency Priority # Light Bar Replacement Project 1 45,000 47,225 - - - - # North Police Station 4-100,000 - - - - # Police Building Improvements

More information

Downtown Lakeland Office Space For Lease

Downtown Lakeland Office Space For Lease Jack Strollo, Broker 100 S. Kentucky Avenue, Suite 290 Lakeland, Florida 33801 Office 863.683.3425 x103 Cell/Text 863.640.8238 www.resbroadway.com jstrollo@resbroadway.com Downtown Lakeland Office Space

More information

A Strong Response Before, During and After. Hurricane Sandy. West Penn Power, Penelec and Met-Ed

A Strong Response Before, During and After. Hurricane Sandy. West Penn Power, Penelec and Met-Ed A Strong Response Before, During and After Hurricane Sandy West Penn Power, Penelec and Met-Ed January 10, 2013 FirstEnergy s Presence in Pennsylvania Erie Towanda New Castle Easton Greensburg Johnstown

More information

COMMERCIAL SITE AT GENERATION PARK

COMMERCIAL SITE AT GENERATION PARK COMMERCIAL SITE AT GENERATION PARK 77.9 Acre Site on Lockwood Road Generation Park Location Map Close Proximity to Major Destinations & Transportation Corridors Generation Park Features 4,000-acre master-planned

More information

White Paper: Data Center Capacity Management Provides New Business Opportunities & Efficiency at State-of-the-Art One Wilshire June 8, 2017

White Paper: Data Center Capacity Management Provides New Business Opportunities & Efficiency at State-of-the-Art One Wilshire June 8, 2017 White Paper: Data Center Capacity Management Provides New Business Opportunities & Efficiency at State-of-the-Art One Wilshire June 8, 2017 As operators have demanded increasing levels of power density

More information

Supplemental Details - Capital Funding Source Summary Cap Fund Cap Fund Cap Fund - 21

Supplemental Details - Capital Funding Source Summary Cap Fund Cap Fund Cap Fund - 21 Supplemental Details - Capital Source Summary 2018 Cap Fund - 2 2019 Cap Fund - 12 2020 Cap Fund - 21 Brampton Public Library Automation Software & Hardware Upgrades Brampton Library - 4 Corners BramWest

More information

BLUE RIBBON Facilities

BLUE RIBBON Facilities BLUE RIBBON 2015 Facilities FACILITY PRIORITIES Police Administration Addition $4,484,864 Relocation of Fire Station 3 $4,829,683 (Does not include land purchase) City Hall Basement/Conference/Training/Emergency

More information

HOTEL RESILIENT Plan ahead stay ahead. With support from the German Government through

HOTEL RESILIENT Plan ahead stay ahead. With support from the German Government through HOTEL RESILIENT Plan ahead stay ahead With support from the German Government through WHAT CAN GO WRONG WILL GO WRONG Murphy s Law More than 40% of hotels do not reopen after large disasters FEMA 2010

More information

KCTCS Facilities Support Services and Capital Projects

KCTCS Facilities Support Services and Capital Projects KCTCS Facilities Support Services and Capital Projects Responsible for the management of KCTCS facilities, equipment, and property, the mission of KCTCS Facilities Support Services and Capital Projects

More information