ELECTRICAL DESIGN PRACTICE NOTE ELECTRICAL SYSTEM REQUIREMENTS

Size: px
Start display at page:

Download "ELECTRICAL DESIGN PRACTICE NOTE ELECTRICAL SYSTEM REQUIREMENTS"

Transcription

1 Approval Amendment Record Approval Date Version Description 12/02/ First Issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6

2 Table of Contents 1 Purpose Background The Issue The Requirement/Objective Attachments... 4 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 6

3 1 Purpose To require all parties proposing an addition or a change to the electrical systems to obtain a Systems Requirements document from the Head of Electrical/Engineering. 2 Background Projects and renewal works have been proposed without due consideration to the up stream and down stream implications of the impact on the wider electrical network. Examples include the proposal to install a new substation without early discussions with the supply companies resulting in delays and compromises to the final installation. There are now locations where the output of the traction substation is limited by the electrical protection settings and additional infrastructure will be required to operate the substation to its capacity. There are projects involving new substations where the scope of works specifically excludes changes to the electrical protection systems supplying the substations. Additional capacity has been installed in some systems without recognition that the fault carrying capacity of legacy equipment is exceeded. Compromises have been accepted in reticulation systems that have resulted in essential systems being dependent on a single electric supply. 3 The Issue The electrical networks, including substations, tiestations, 1500Vdc traction overhead and 22Kv transmission system are a system and all items associated with the system including capacity, voltage levels, fault protection, fault discrimination and redundancy under failure conditions require consideration BEFORE project or renewal scopes of works are locked down. The functional requirements as per Form MEMF also need to be included in the system documentation. Failure to address the electrical networks at the system level results in compromise with the potential to increase network risk. 4 The Requirement/Objective This Practice Note requires all persons developing projects or renewal works that impact the electrical system, to undertake a System Requirements Review (SRR), after the Preliminary Requirements Review (PRR) has been undertaken, in accordance with L3- PRJ-GDL-002 Engineering Management System Methodology. The SRR shall include a system requirements document produced and approved by the Head of Electrical/Engineering, such that the electrical network implications of the proposal are incorporated into the scope of works and potential network risks are removed. Note that the PRR stage requires a Final Impact Statement, Final Operation Statement and Project Brief, in accordance with Figures 1 and 2 of L3- PRJ-GDL-002, Attachment 1. The purchase of major electrical equipment such as rectifiers, rectifier transformers and substation high voltage circuit breakers shall not occur without a system requirements document and the consent of the Head of Electrical/Engineering. The advice from Head of Electrical /Engineering shall be written and incorporated into the project or renewal works documentation. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 6

4 Where the proposed works involve interaction with a supply company as determined by the Head of Electrical/Engineering, the advice shall include an agreement from the supply company to the principles of the project.` 5 Attachments PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 6

5 Concept Definition & Analysis Preliminary Definition & Detailed Qualification and Fabrication System Integration, T&C and Deployment HW development CDR Detailed Fabrication of HW Product to Qualified HW Product Preliminary System/HW Reqts Analysis and Definition HW Specification(s) Development Acceptance Review System Concept Requirements PRR SRR Concept X PDR CDR X TRR X T-20 T-12 T-5 System Integration and and Commissioning Handover/ Deployment CDR Critical Review CM Configuration Management DDR Detailed Review HW Hardware PDR Preliminary Review PRR Preliminary Requirements Review SRR System Requirements Review SW Software TRR Test Readiness Review WRR Works Readiness Review Mandatory, Formal Review Optional Review System/SW Reqts Analysis and Definition SW Specification(s) Development SW development Architectural (Preliminary) Detailed DDR SW Implementation, Unit, Integration & SW Product Occupation X Works Readiness Gate Formal Gate Functional Baseline Allocated (Development) Baseline Baseline Product Baseline Informal ( Engineering ) CM Formal CM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 6

6 Stakeholders Requirements Assessment ( SRA ) NPD, NAM, ENGINEERING, SAFETY PROPOSED APP Multiple Options POR & PIS Single, Final Option FOR & FIS Project Brief PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 6

MESP MODULAR SUBSTATION USER REQUIREMENTS

MESP MODULAR SUBSTATION USER REQUIREMENTS Engineering Specification Electrical Networks MODULAR SUBSTATION USER Version: 2 Issued: November 2015 Owner: Head of Engineering/Electrical Approved By: Head of Engineering/Electrical PRINTOUT MAY NOT

More information

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM

MESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V Version: 1 Issued: March 2014 Owner: Electrical Networks Asset

More information

Specification Voltage Limiting Device

Specification Voltage Limiting Device Engineering Specification Electrical Networks L1-CHE-SPE-152 Specification Voltage Limiting Device Version: 1 Issued: 20 th April 2018 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering,

More information

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP)

Title System Substation Commissioning Tests. Reference Number PCP 07 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title s Reference Number PCP 07 - (RIC Standard: EP 99 00 00 02 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

Switching Process and Rules Systems Operations Framework. Document Number:

Switching Process and Rules Systems Operations Framework. Document Number: Switching Process and Rules Systems Operations Framework Document Number: 4808076 TABLE OF CONTENTS 1. INTRODUCTION... 5 1.1 PURPOSE... 5 1.2 HIERARCHY... 5 2. PROCESSES... 7 2.1 SWITCHING OPERATOR AUTHORISATION

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

Title Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP)

Title Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP) Discipline Engineering Standard - NSW Category Electrical Title Reference Number POP 07 - (RIC Standard: EP 99 00 00 04 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

DESIGN PRACTICE NOTE NEGATIVE BUSBAR SHUNTS

DESIGN PRACTICE NOTE NEGATIVE BUSBAR SHUNTS Approval Amendment Record Approval Date Version Description 27/05/2013 1 Initial issue under MTM. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6 Table of Contents

More information

MTM Standards Induction for the Signal Design Roles

MTM Standards Induction for the Signal Design Roles MTM Standards Induction for the Signal Design Roles Version 1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW to be familiar

More information

PBS Aligned with IMS. David E Black, Structnet. Notice: Data on this page is controlled by restrictions listed on the title page

PBS Aligned with IMS. David E Black, Structnet. Notice: Data on this page is controlled by restrictions listed on the title page PBS Aligned with IMS Notice: Data on this page is controlled by restrictions listed on the title page 1 Defined Process Tasks Requirements & Architecture 1. Work Authorization Complete 2. Requirements

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

MTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES

MTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES SURGE PROTECTION IN SIGNAL Approval Amendment Record Approval Date Version Description 11/05/2016 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION

More information

ASSET RISK MANAGEMENT Criticality Framework

ASSET RISK MANAGEMENT Criticality Framework ASSET RISK MANAGEMENT Criticality Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to

More information

NOCN_Cskills Awards Level 1 Diploma in Construction and Civil Engineering Services (Construction)

NOCN_Cskills Awards Level 1 Diploma in Construction and Civil Engineering Services (Construction) NOCN_Cskills Awards Level 1 Diploma in Construction and Civil Engineering Services (Construction) Reference : 600/8622/1 Total Qualification Time (TQT) : 430 Credits : 43 Award Code : DIP079 Minimum Age

More information

MESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS

MESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS Engineering Specification Electrical Networks MESP 081000-01 TECHNICAL SPECIFICATION FOR SCADA CABLING IN Version: 1 Issued: March 2014 Owner: Electrical Networks Asset Manager Approved By: George Marulli

More information

Recording and Reporting of High Voltage and Low Voltage Switching

Recording and Reporting of High Voltage and Low Voltage Switching 1 SCOPE This document details the procedures to be adopted prior to, during, and on completion of Switching operations, and details the manner in which HV and LV Switching shall be recorded in order to

More information

QUIZ-MTM Standards Induction for the Signal Design Roles

QUIZ-MTM Standards Induction for the Signal Design Roles QUIZ-MTM Standards Induction for the Signal Design Roles Version 1.1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW

More information

MTM Standards Induction for the Signal Project Roles

MTM Standards Induction for the Signal Project Roles MTM Standards Induction for the Signal Project Roles Version 1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW to be

More information

ISSC is invited to consider the attached report and to support the proposal to change the priority order for the migration UEA web services.

ISSC is invited to consider the attached report and to support the proposal to change the priority order for the migration UEA web services. ISC11D005 Title: UEA Website Migration Author: Jonathan Richardson, Assistant Director, Corporate Information Services Date: 1 st November 2011 Circulation: ISSC 10 November 2011 Agenda: ISC11A001 Version:

More information

Description of the Application Process for Small Embedded Generators

Description of the Application Process for Small Embedded Generators Description of the Application Process for Small Embedded Generators This document describes the Application Process for Small Embedded Generators (as required under section 5.3.3A of the National Electricity

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

COMMUNICATION LINKS FOR SIGNALLING

COMMUNICATION LINKS FOR SIGNALLING Engineering Standard - Design Signalling & Operational Control Systems COMMUNICATION LINKS FOR SIGNALLING Version: 2 Issued: April 2016 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST

More information

LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE. Loughborough University (LU) Research Office SOP 1027 LU

LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE. Loughborough University (LU) Research Office SOP 1027 LU LOUGHBOROUGH UNIVERSITY RESEARCH OFFICE STANDARD OPERATING PROCEDURE Loughborough University (LU) Research Office SOP 1027 LU Process for Writing Study Protocols for NHS Research Sponsored by Loughborough

More information

Distribution Code Review Panel Protection Engineer assessment Working Group. Draft Document for

Distribution Code Review Panel Protection Engineer assessment Working Group. Draft Document for Distribution Code Review Panel Protection Engineer assessment Working Group Draft Document for Procedure for Assessment of Protection Relay Testing Engineers INTRODUCTION Electrical Protection system testing

More information

European Commission. Immigration Portal Development Case. Date: 08/06/2007 Version: 1.0 Authors: Revised by: Approved by: Public: Reference Number:

European Commission. Immigration Portal Development Case. Date: 08/06/2007 Version: 1.0 Authors: Revised by: Approved by: Public: Reference Number: EUROPEAN COMMISSION DIRECTORATE-GENERAL INFORMATICS Information systems Directorate European Commission Immigration Portal Development Case Date: 08/06/2007 Version: 1.0 Authors: Revised by: Approved by:

More information

Sapphire Wind Farm 330/33kV Substation

Sapphire Wind Farm 330/33kV Substation Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire

More information

NOCN_Cskills Awards Level 2 NVQ Diploma in Plant Operations (Construction) - In-shore Marine

NOCN_Cskills Awards Level 2 NVQ Diploma in Plant Operations (Construction) - In-shore Marine NOCN_Cskills Awards Level 2 NVQ Diploma in Plant Operations (Construction) - In-shore Marine Reference : 600/3638/2 Total Qualification Time (TQT) : 480 Credits : 48 Award Code : QUT862 Minimum Age : 16

More information

MTM Standards Induction for the Signal Maintain Roles

MTM Standards Induction for the Signal Maintain Roles MTM Standards Induction for the Signal Maintain Roles Version 1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW to be

More information

Transition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007

Transition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007 Data Center Operations Outsourcing Transition Plan Implementation: Final Page 1 of 15 DOCUMENT CONTROL SHEET Schedule/Exhibit Amendment Control Sheet Title of Amended Document: Section 4 Transition Plan

More information

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES Network(s): Summary: ENGINEERING BULLETIN EBB 08-0061 PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES EPN, SPN This bulletin provides a framework for the pilot scheme for unmetered

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

Information Technology Procedure IT 3.4 IT Configuration Management

Information Technology Procedure IT 3.4 IT Configuration Management Information Technology Procedure IT Configuration Management Contents Purpose and Scope... 1 Responsibilities... 1 Procedure... 1 Identify and Record Configuration... 2 Document Planned Changes... 3 Evaluating

More information

Appendix I: LOAD OPERATING AGREEMENT

Appendix I: LOAD OPERATING AGREEMENT PG&E Transmission Interconnection Handbook Appendix I: LOAD OPERATING AGREEMENT Purpose The following agreement establishes operating responsibilities and associated procedures for communications between

More information

Re-Forming the DoD Acquisition Process. A Systems Engineering Approach

Re-Forming the DoD Acquisition Process. A Systems Engineering Approach Re-Forming the DoD Acquisition Process A Systems Engineering Approach MR. STEVE WARD MR. CHRIS PERKINS DEPARTMENT OF THE AIR FORCE AERONAUTICAL SYSTEMS CENTER WRIGHT-PATTERSON AFB, OH 22 OCT 2007 DISCLAIMER

More information

Verified and validated

Verified and validated Verified and validated ABB has its own system verification and vaildation center STEPHAN GERSPACH, PETER WEBER When the IEC 61850 standard was introduced, ABB not only implemented it in its product portfolio,

More information

Engineering Recommendation G87 Issue

Engineering Recommendation G87 Issue PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation G87 Issue 2-2015 Guidelines for the Provision of Low Voltage Connections to Multiple Occupancy Buildings

More information

QUIZ-MTM Standards Induction for the Signal Project Roles

QUIZ-MTM Standards Induction for the Signal Project Roles QUIZ-MTM Standards Induction for the Signal Project Roles Version 1.1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW

More information

NOCN_Cskills Awards Level 3 Diploma in Site Carpentry (Construction)

NOCN_Cskills Awards Level 3 Diploma in Site Carpentry (Construction) NOCN_Cskills Awards Level 3 Diploma in Site Carpentry (Construction) Reference : 600/8604/X Total Qualification Time (TQT) : 1230 Credits : 123 Award Code : DIP058 Minimum Age : 16 Level : Level 3 Registration

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

1.0 Executive Summary

1.0 Executive Summary Statement of Work - 1 - Power and Cooling Assessment for Data Center Professional Services Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service

More information

CNAS-RC01. Rules for Accreditation of Certification Bodies

CNAS-RC01. Rules for Accreditation of Certification Bodies CNAS-RC01 Rules for Accreditation of Certification Bodies CNAS CNAS-RC01:2014 Page 1 of 25 Foreword... 2 1 Scope... 3 2 Reference Documents... 3 3 Terms and Definitions... 3 4 General... 5 5 Accreditation

More information

Minnesota DER Interconnection Process Kristi Robinson, P.E.

Minnesota DER Interconnection Process Kristi Robinson, P.E. Minnesota DER Interconnection Process Kristi Robinson, P.E. 6841 Power Lane SW Alexandria, Minnesota Tel 320.762.1697 Fax 320.762.1479 www.star-energy.com eee@star-energy.com Spring 2017: Petition made

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 60870-5-6 First edition 2006-03 Telecontrol equipment and systems Part 5-6: Guidelines for conformance testing for the IEC 60870-5 companion standards IEC 2006 Copyright - all

More information

National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION

National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION NSI 0 NATIONAL SAFETY INSTRUCTION INDEX Copyright National Grid plc 2016, all rights reserved. No part of this publication may

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

Getting Started with. SupportDesk. House-on-the-Hill Software Ltd. SupportDesk Green

Getting Started with. SupportDesk. House-on-the-Hill Software Ltd. SupportDesk Green Getting Started with SupportDesk House-on-the-Hill Software Ltd SupportDesk Green Software Copyright 1993-2007 House-On-The-Hill Software Ltd. All Rights Reserved. Manual Copyright 1993-2007 House-On-The-Hill

More information

Todmorden High School Job Description

Todmorden High School Job Description Todmorden High School Job Description Post Title: ICT Manager. Salary: SO2 ( 28,485-30,153) Hours: 37 hours, Full time Annual Leave: 30 days plus standard bank holidays. Holidays must be taken during school

More information

ProQual External Quality Assurance Qualifications. Level 4 Award in the External Quality Assurance of Assessment Processes and Practice

ProQual External Quality Assurance Qualifications. Level 4 Award in the External Quality Assurance of Assessment Processes and Practice ProQual External Quality Assurance Qualifications Level 4 Award in the External Quality Assurance of Assessment Processes and Practice Level 4 Certificate in Leading the External Quality Assurance of Assessment

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Qualification Specification. Skills for Engineering Level 1

Qualification Specification. Skills for Engineering Level 1 Qualification Specification Skills for Engineering Level 1 Version 1.0 (November 2016) Version 1.0 Page 1 of 22 This qualification specification covers the following qualifications: Qualification Title

More information

Huawei Railway Communication Service Solution Guide

Huawei Railway Communication Service Solution Guide Huawei Railway Communication Service Solution Guide Huawei Technologies Co., Ltd. Keywords Railway transport, service solution, subsystem, design,, solution implementation Abstract Huawei Railway Communication

More information

Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly

Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly Specification Electrical Networks L1-CHE-SPE-128 Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly Version: 1 Issued: February 2016 Owner: Head of Engineering - Electrical Approved

More information

CRITERIA FOR CERTIFICATION BODY ACCREDITATION IN THE FIELD OF RISK BASED INSPECTION MANAGEMENT SYSTEMS

CRITERIA FOR CERTIFICATION BODY ACCREDITATION IN THE FIELD OF RISK BASED INSPECTION MANAGEMENT SYSTEMS CRITERIA FOR CERTIFICATION BODY ACCREDITATION IN THE FIELD OF RISK BASED INSPECTION MANAGEMENT SYSTEMS Approved By: Executive: Accreditation: Mpho Phaloane Revised By: RBI STC Working Group Members Date

More information

AUTHORITY FOR ELECTRICITY REGULATION

AUTHORITY FOR ELECTRICITY REGULATION SULTANATE OF OMAN AUTHORITY FOR ELECTRICITY REGULATION SCADA AND DCS CYBER SECURITY STANDARD FIRST EDITION AUGUST 2015 i Contents 1. Introduction... 1 2. Definitions... 1 3. Baseline Mandatory Requirements...

More information

IECEx Guide Guidance for Applications from Service Facilities seeking IECEx Certification

IECEx Guide Guidance for Applications from Service Facilities seeking IECEx Certification IECEx Guide Guidance for Applications from Service Facilities seeking IECEx Certification INTERNATIONAL ELECTROTECHNICAL COMMISSION SCHEME FOR CERTIFICATION TO STANDARDS RELATING TO EQUIPMENT FOR USE IN

More information

Specification. Edexcel qualifications. Edexcel Level 3 Award in Reviewing Health and Safety Procedures in the Workplace(QCF)

Specification. Edexcel qualifications. Edexcel Level 3 Award in Reviewing Health and Safety Procedures in the Workplace(QCF) Specification Edexcel qualifications Edexcel Level 3 Award in Reviewing Health and Safety Procedures in the Workplace(QCF) For first registration December 2011 Edexcel, a Pearson company, is the UK s largest

More information

STCP Amendment Proposal Form

STCP Amendment Proposal Form STCP Amendment Proposal Form PA036 1. Title of Amendment Proposal STCP 09-2 Incorporation material currently within SPT SCS and making standard for both TOs. 2. Description of the Proposed Amendment (mandatory

More information

PROTERRA CERTIFICATION PROTOCOL V2.2

PROTERRA CERTIFICATION PROTOCOL V2.2 PROTERRA CERTIFICATION PROTOCOL V2.2 TABLE OF CONTENTS 1. Introduction 2. Scope of this document 3. Definitions and Abbreviations 4. Approval procedure for Certification Bodies 5. Certification Requirements

More information

PART IV GLOSSARY OF TERMS

PART IV GLOSSARY OF TERMS PART IV GLOSSARY OF TERMS Terms and Definitions For the purposes of this document, the following terms and definitions shall apply: PROCESS MANUAL FOR THE GFSI BENCHMARKING PROCESS V7.2 Introduction Purpose

More information

NASA Policy Directive

NASA Policy Directive NASA Policy Directive NPD 8820.2D Effective Date: July 02, 2013 Expiration Date: July 02, 2018 COMPLIANCE IS MANDATORY Subject: Design and Construction of Facilities Responsible Office: Facilities Engineering

More information

MESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR

MESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR 22 kv Version: 2 Issued: 19 th December 2016 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering - Electrical

More information

Chapter X Security Performance Metrics

Chapter X Security Performance Metrics DRAFT February 19, 15 BES Security s Working Group Page 1 of 7 Chapter X Security Performance s 1 3 3 3 3 0 Background The State of Reliability 1 report noted that the NERC PAS was collaborating with the

More information

EA-7/05 - EA Guidance on the Application of ISO/IEC 17021:2006 for Combined Audits

EA-7/05 - EA Guidance on the Application of ISO/IEC 17021:2006 for Combined Audits Publication Reference EA-7/05 EA Guidance on the Application of ISO/IEC 17021:2006 for Combined Audits PURPOSE This document has been prepared by a task force under the direction of the European Cooperation

More information

QUIZ-MTM Standards Induction for the Signal Maintain Roles Version 1.1, 2018

QUIZ-MTM Standards Induction for the Signal Maintain Roles Version 1.1, 2018 QUIZ-MTM Standards Induction for the Signal Maintain Roles Version 1.1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW

More information

EU DONOR FUNDED SMART GRID PROGRAMME

EU DONOR FUNDED SMART GRID PROGRAMME EU DONOR FUNDED SMART GRID PROGRAMME 1 Historical Background Msunduzi Local Municipality is a local municipality in Umgungundlovu District Municipality, KwaZulu-Natal, South Africa. It encompasses the

More information

1.0 Executive Summary. 2.0 Features and Benefits

1.0 Executive Summary. 2.0 Features and Benefits Table of Contents 1.0 EXECUTIVE SUMMARY 2.0 FEATURES AND BENEFITS 3.0 DETAILS OF SERVICE 4.0 Deliverable 5.0 Exclusions 6.0 SCOPE OF RESPONSIBILITY 7.0 PROJECT WORK DETAILS 8.0 ORDERING INFORMATION 9.0

More information

Solution Railway. tgood.com

Solution Railway. tgood.com Solution Railway tgood.com TGOOD Introduction TGOOD is the global leader in prefabricated electric power distribution solutions. It is the company that first comes to mind when cost-effective electric

More information

COURSE BROCHURE. ITIL - Expert Managing Across Lifecycle Training & Certification

COURSE BROCHURE. ITIL - Expert Managing Across Lifecycle Training & Certification COURSE BROCHURE ITIL - Expert Managing Across Lifecycle Training & Certification What is ITIL MALC? This ITIL training course brings together the full essence of a Lifecycle approach to service management,

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application

More information

e-ready Building Next Generation IT infrastructures ϕ The Cabling Partnership Mike Gilmore Managing Director, e-ready Building The Cabling Partnership

e-ready Building Next Generation IT infrastructures ϕ The Cabling Partnership Mike Gilmore Managing Director, e-ready Building The Cabling Partnership eready Building THE ONESTOP SHOP Telecommunications equipment and telecommunications cabling Specification for installation, operation and maintenance THE ONESTOPSHOP FOR INSTALLATION Q.A. Mike Gilmore

More information

Name of Regulated Qualification: BIIAB Level 4 Diploma In Professional Competence for IT and Telecoms Professionals (PROCOM) (QCF)

Name of Regulated Qualification: BIIAB Level 4 Diploma In Professional Competence for IT and Telecoms Professionals (PROCOM) (QCF) Name of Regulated Qualification: BIIAB Level 4 Diploma In Professional Competence for IT and Telecoms Professionals (PROCOM) (QCF) Level: 4 Ofqual Qualification number: 601/6521/2 What is the main purpose

More information

ELECTIVE INTERCONNECTION FACILITIES

ELECTIVE INTERCONNECTION FACILITIES Title: ELECTIVE INTERCONNECTION FACILITIES Business Practice Department: External Affairs Document No: BP-0506 v3.0 Issue Date: 12-15-2017 Previous Date: 12/11/2006 Contents 1 PURPOSE... 2 2 DEFINITIONS...

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 61850-5 First edition 2003-07 Communication networks and systems in substations Part 5: Communication requirements for functions and device models IEC 2003 Copyright - all rights

More information

Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A

Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A Chapter 5A Embedded Generation Information Pack United Energy s guide to the Embedded Generation connection process for of Chapter 5A Public Table of contents 1 Connection Framework... 3 2 Connection Types...

More information

Technical Data. Circuit Protection - Surge Protection Devices. Ver 1.0 CUSPD1110. Brief product description:

Technical Data. Circuit Protection - Surge Protection Devices. Ver 1.0 CUSPD1110. Brief product description: Technical Data Circuit Protection - Surge Protection Devices Ver 1.0 CUSPD1110 Brief product description: Surge Protection Device (SPD) protect against lightning surges and man made surges such as motors,

More information

Chroma-Q Color Web PSU 10-DMX. User Manual

Chroma-Q Color Web PSU 10-DMX. User Manual Chroma-Q Color Web PSU 10-DMX User Manual Version 1.1 September 2012 Warranty Statement Chroma-Q warrants to the original purchaser, with proof of purchase, that its delivered products shall be free from

More information

A specification proposed by JASPAR has been adopted for AUTOSAR.

A specification proposed by JASPAR has been adopted for AUTOSAR. Japan Automotive Software Platform and Architecture A specification proposed by JASPAR has been adopted for AUTOSAR. JASPAR General Incorporated Association 1. Introduction An RTE profile specification

More information

MEM31215 Certificate III in Engineering - Industrial Electrician

MEM31215 Certificate III in Engineering - Industrial Electrician MEM31215 Certificate III in Engineering - Industrial Electrician Release 2 MEM31215 Certificate III in Engineering - Industrial Electrician Modification History Release 2. MSAENV272B updated to MSMENV272.

More information

Global Specification Protocol for Organisations Certifying to an ISO Standard related to Market, Opinion and Social Research.

Global Specification Protocol for Organisations Certifying to an ISO Standard related to Market, Opinion and Social Research. CONTENTS i. INTRODUCTION 3 ii. OVERVIEW SPECIFICATION PROTOCOL DOCUMENT DEVELOPMENT PROCESS 4 1. SCOPE 5 2. DEFINITIONS 5 3. REFERENCES 6 4. MANAGEMENT STANDARDS FOR APPROVED CERTIFICATION BODIES 6 4.1

More information

Spillemyndigheden s Certification Programme. Instructions on Penetration Testing SCP EN.1.1

Spillemyndigheden s Certification Programme. Instructions on Penetration Testing SCP EN.1.1 SCP.04.00.EN.1.1 Table of contents Table of contents... 2 1 Objectives of the... 3 1.1 Scope of this document... 3 1.2 Version... 3 1.3 Applicability... 3 2 Certification... 4 2.1 Certification frequency...

More information

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014

Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014 Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014 2014 Electric Power Research Institute, Inc. All rights reserved. Meet the Challenge An Integrated Grid 2 Interconnected

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

External Assessment Specifications Document Curriculum. NQF Qualification Title Code

External Assessment Specifications Document Curriculum. NQF Qualification Title Code External Assessment Specifications Document Curriculum NQF Qualification Title Code Level 671101000 Occupational Certificate: Electrician 4 Name E-mail Phone Logo National Assessment Artisan Quality Moderation

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

IQ Level 4 Award in Understanding the External Quality Assurance of Assessment Processes and Practice (QCF) Specification

IQ Level 4 Award in Understanding the External Quality Assurance of Assessment Processes and Practice (QCF) Specification IQ Level 4 Award in Understanding the External Quality Assurance of Assessment Processes and Practice (QCF) Specification Regulation No: 600/5528/5 Page 1 of 15 Contents Page Industry Qualifications...

More information

Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY

Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Original Issue: September 2007 Prepared by: Lee Chan & Rob Rogerson This Revision: 0 October 2007 Date For Next Review:

More information

Critical Cyber Asset Identification Security Management Controls

Critical Cyber Asset Identification Security Management Controls Implementation Plan Purpose On January 18, 2008, FERC (or Commission ) issued Order. 706 that approved Version 1 of the Critical Infrastructure Protection Reliability Standards, CIP-002-1 through CIP-009-1.

More information

Microlok Data Design Records (Addressing, File Control, Checking, and FAT Testing)

Microlok Data Design Records (Addressing, File Control, Checking, and FAT Testing) Discipline: Engineering (Signalling) Category: Procedure Microlok Data Design Records (Addressing, File Control, Checking, and FAT Testing) ESD-05-11 Applicability ARTC Network Wide Primary Source Signal

More information

ENTSO-E connection network codes Implementation guidance documents. Joint DSO response paper

ENTSO-E connection network codes Implementation guidance documents. Joint DSO response paper ENTSO-E connection network codes Implementation guidance documents Joint DSO response paper August 2016 Dépôt légal: D/2016/12.105/45 Questionnaire Rate-of-change- of- frequency withstand capability (RoCoF)

More information

Advanced Validation Strategies for On-Board Satellite Software in the Galileo IOV Programme

Advanced Validation Strategies for On-Board Satellite Software in the Galileo IOV Programme Olivier Croatto, Michael Uemminghaus Garching, Oct. 7th, 2008 Advanced Validation Strategies for On-Board Satellite Software in the Galileo IOV Programme Astrium Proprietary Information Agenda 1 - Overview

More information

SUB-STATION CAPABILITY EPS AUSTRALIA. Suite 1702, Tower 2, 101 Grafton St, Bondi Junction NSW

SUB-STATION CAPABILITY EPS AUSTRALIA. Suite 1702, Tower 2, 101 Grafton St, Bondi Junction NSW EPS AUSTRALIA SUB-STATION CAPABILITY EPS is a recognised company specialising in Electrical, Instrumentation, Structural, Mechanical and Piping services. We have an appreciation for client and top tier

More information

Equipment Strategy For High Voltage Circuit Breakers

Equipment Strategy For High Voltage Circuit Breakers Current version: 23/05/2018 EXTERNAL USE Page 1 of 7 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References... 3 1.4 Defined terms... 3 1.5 Monitoring and compliance... 3

More information

SDG&E EPIC Program Overview

SDG&E EPIC Program Overview SDG&E EPIC Program Overview Presented by: Frank Goodman, SDG&E i-pcgrid Workshop March 30, 2018. All copyright and trademark rights reserved. Presentation overview SDG&E overview Project lists for three

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

Scheme Document. For more information or help with your application contact BRE Global on +44 (0) or

Scheme Document. For more information or help with your application contact BRE Global on +44 (0) or Page: Page 1 of 15 1. Introduction This certification scheme has been designed to promote sustainable production of construction products and materials. Responsible sourcing includes organisational management,

More information

TECHNICAL REPORT. Electromagnetic compatibility (EMC)

TECHNICAL REPORT. Electromagnetic compatibility (EMC) TECHNICAL REPORT IEC TR 61000-2-14 First edition 2006-12 Electromagnetic compatibility (EMC) Part 2-14: Environment Overvoltages on public electricity distribution networks IEC 2006 Copyright - all rights

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...

Disclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission... CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...

More information

PROFESSIONAL SERVICES

PROFESSIONAL SERVICES PROFESSIONAL SERVICES TELEPRESENCE CONSULTING 75% OF BUSINESS LEADERS BELIEVE THAT FACE-TO-FACE COLLABORATION IS CRITICAL. IT IMPROVES WORKFORCE PRODUCTIVITY, MAKES VIRTUAL TEAMS MORE EFFECTIVE AND SIGNIFICANTLY

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information