1 Approval Amendment Record Approval Date Version Description 27/05/ Initial issue under MTM. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6
2 Table of Contents 1. Purpose Scope Abbreviations and Acronyms Definitions and Responsibilities References and Legislation Background The Issue The Requirement Type Approval MTM Requirements Related Documents Appendices...5 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 6
3 1. Purpose The purpose of this document is to clearly define MTM requirements for negative busbar shunts that provide connection points for substation electrical load metering and electrolysis mitigation and to ensure all future substation designs are compliant. 2. Scope The contents of this document is to be incorporated into all substation design works requiring the installation or replacement of negative busbar shunts. 3. Abbreviations and Acronyms A Amps dc Direct Current ma Milli Amps MTM Metro Trains Melbourne mv Milli Volts MW Megawatts PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 6
4 4. Definitions and Responsibilities The following are to note and comply with the terms of this Design Practise Note; Substation Designers o To incorporate requirements into all new designs Project Managers o To ensure requirements are incorporated into all design scope of works. Electrical Network Staff Network Asset Managers Substation Design Reviewers Substation Design Approvers 5. References and Legislation Nil 6. Background Recent design and construction of new substations has seen a variety of different sizes and types of negative busbar shunts proposed for use. Scope of Works documentation does not address MTM s requirements for negative busbar shunt. This is unacceptable for ongoing maintenance and or replacement by Network Asset Management staff. 7. The Issue Substation staff has difficulties connecting testing equipment to non-standard negative busbar shunts. Substation staff is unable to provide replacement parts for non-standard negative busbar shunt. Design Practise Note has been developed to ensure standardisation of components being incorporated in Substation designs and for spares needed for maintenance purposes this 8. The Requirement All future substation design work is to incorporate the contents of this Design Practise note. Any variation to this requirement will require a signed waiver. 9. Type Approval Type Approval is not required where the design complies with this Design Practice note and complies with existing type approved equipment currently in service. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 6
5 10. MTM Requirements As of the date of this document the following standards will apply; For a Single Rectifier Unit Substation of 3.0 MW or less. Continuous Rating 3000 A dc Shunt Ratio 150 mv for 3000 A dc (per rectifier) Accuracy 1% Physical Size and Holes as per Standard Drawing STD_E0107 (attached) Where a substation is to have more than one rectifier MTM shall be consulted for technical direction. 11. Related Documents VRIOG 10.3 Substation Design Standard VRIOG 10.4 Substation Construction Standard 12. Appendices Appendix 1 - Standard Drawing Traction Substation Shunt Negative Busbar STD_E0107 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 6
6 Appendix 1 Standard Drawing, STD_E0107 (for guide only, refer to DMS for latest standard drawing). PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 6
MTM DESIGN PRACTICE NOTE 110V AC SURGE PROTECTION IN SIGNAL EQUIPMENT ROOMS AND TRACKSIDE ZONE BOXES
SURGE PROTECTION IN SIGNAL Approval Amendment Record Approval Date Version Description 11/05/2016 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION
More informationCOMMUNICATION LINKS FOR SIGNALLING
Engineering Standard - Design Signalling & Operational Control Systems COMMUNICATION LINKS FOR SIGNALLING Version: 2 Issued: April 2016 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST
More informationMESP TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V DC TRACTION SYSTEM
Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR A RECTIFIER UNIT CONTROL & PROTECTION SYSTEM FOR USE IN THE 1500V Version: 1 Issued: March 2014 Owner: Electrical Networks Asset
More informationMESP TECHNICAL SPECIFICATION FOR SCADA CABLING IN SUBSTATIONS
Engineering Specification Electrical Networks MESP 081000-01 TECHNICAL SPECIFICATION FOR SCADA CABLING IN Version: 1 Issued: March 2014 Owner: Electrical Networks Asset Manager Approved By: George Marulli
More informationMESP MODULAR SUBSTATION USER REQUIREMENTS
Engineering Specification Electrical Networks MODULAR SUBSTATION USER Version: 2 Issued: November 2015 Owner: Head of Engineering/Electrical Approved By: Head of Engineering/Electrical PRINTOUT MAY NOT
More informationSpecification Voltage Limiting Device
Engineering Specification Electrical Networks L1-CHE-SPE-152 Specification Voltage Limiting Device Version: 1 Issued: 20 th April 2018 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering,
More informationRemotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly
Specification Electrical Networks L1-CHE-SPE-128 Remotely Operable 1500V DC Disconnector & Short-Circuit Switch Assembly Version: 1 Issued: February 2016 Owner: Head of Engineering - Electrical Approved
More informationMTM Standards Induction for the Signal Maintain Roles
MTM Standards Induction for the Signal Maintain Roles Version 1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW to be
More informationMESP TECHNICAL SPECIFICATION FOR 22 kv METAL ENCLOSED SWITCHGEAR
Engineering Specification Electrical Networks TECHNICAL SPECIFICATION FOR 22 kv Version: 2 Issued: 19 th December 2016 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering - Electrical
More informationMTM Standards Induction for the Signal Project Roles
MTM Standards Induction for the Signal Project Roles Version 1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW to be
More informationMTM Standards Induction for the Signal Design Roles
MTM Standards Induction for the Signal Design Roles Version 1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW to be familiar
More informationQUIZ-MTM Standards Induction for the Signal Maintain Roles Version 1.1, 2018
QUIZ-MTM Standards Induction for the Signal Maintain Roles Version 1.1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW
More informationEDS MW AND MVAR TRANSDUCER CONNECTION
Document Number: EDS 05-5001 Network(s): Summary: ENINEERIN DESIN STANDARD EDS 05-5001 MW AND MVAR TRANSDUCER CONNECTION EPN, LPN, SPN This standard details the convention to be used when wiring MW and
More informationQUIZ-MTM Standards Induction for the Signal Project Roles
QUIZ-MTM Standards Induction for the Signal Project Roles Version 1.1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW
More informationTECHNICAL SPECIFICATION FOR A 1500V DC SWITCHGEAR ASSEMBLY
Engineering Specification Electrical TECHNICAL SPECIFICATION FOR A 1500V DC SWITCHGEAR ASSEMBLY Version: 2 Issued: October 2017 Owner: Chief Engineer Approved By: Phil Ellingworth Chief Engineer PRINTOUT
More informationManual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide
Manual: Distribution Substation Manual (DSM) Section 4: Equipment Installation Guide Standard Number: HPC-5DA-07-0004-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document
More informationQUIZ-MTM Standards Induction for the Signal Design Roles
QUIZ-MTM Standards Induction for the Signal Design Roles Version 1.1, 2018 Applicant Name: RSW number It is a requirement of the MTM Signals, CS&C, and Project Competency Management system for all RSW
More informationL1-CHE-SPE-303 ELECTRICAL AND ELECTRONIC COMPONENTS (RATINGS AND CONSTRUCTION REQUIREMENTS)
Engineering Specification Signalling L1-CHE-SPE-303 ELECTRICAL AND ELECTRONIC COMPONENTS (RATINGS AND CONSTRUCTION REQUIREMENTS) Version: 1 ENGINEERING SPECIFICATION ELECTRICAL AND ELECTRONIC COMPONENTS
More informationELECTRICAL DESIGN PRACTICE NOTE ELECTRICAL SYSTEM REQUIREMENTS
Approval Amendment Record Approval Date Version Description 12/02/2015 1 First Issue PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 6 Table of Contents 1 Purpose...
More informationManual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements
Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Standard Number: HPC-5DA-07-0001-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document
More informationTitle Substations - Base Safety & Operating Standards. Reference Number POP 07 - (RIC Standard: EP SP)
Discipline Engineering Standard - NSW Category Electrical Title Reference Number POP 07 - (RIC Standard: EP 99 00 00 04 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards
More informationEngineering Recommendation G87 Issue
PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation G87 Issue 2-2015 Guidelines for the Provision of Low Voltage Connections to Multiple Occupancy Buildings
More informationANCILLARY SERVICES BUSINESS MONITORING
ANCILLARY SERVICES BUSINESS MONITORING This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for
More informationPRICE BID T Sub : Supply of various measuring panel meters.
PRICE BID T - 3746 Sub : Supply of various measuring panel mets. Description : Supply of various measuring panel mets. Refence No. : T 3746 Urja RFQ No. : 25929 SCHEDULE B (Price Bid) Sr. No. Description
More informationDistribution Substation Manual (DSM) Section 6: Miscellaneous
Distribution Substation Manual (DSM) Section 6: Miscellaneous Standard Number: HPC-5DA-07-0006-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document Owner Name: Justin
More informationRelevant Electrical Standards (RES) Grid Code Review Panel January 2014
Relevant Electrical Standards (RES) Grid Code Review Panel January 2014 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same
More informationFedRAMP Plan of Action and Milestones (POA&M) Template Completion Guide. Version 1.1
FedRAMP Plan of Action and Milestones (POA&M) Template Completion Guide Version 1.1 September 3, 2015 FedRAMP Plan of Action & Milestones (POA&M) Template Completion Guide v1.1 September 3, 2015 Document
More informationFedRAMP Plan of Action and Milestones (POA&M) Template Completion Guide. Version 1.2
FedRAMP Plan of Action and Milestones (POA&M) Template Completion Guide Version 1.2 October 21, 2016 FedRAMP POA&M Template Completion Guide v1.1 September 1, 2015 Document Revision History Date Description
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationManual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements
Manual: Distribution Substation Manual (DSM) Section 5: Substation Fire Protection Requirements Standard Number: HPC-5DA-07-0005- Document Control Author Name: Viswa Easwaran Position: Standards Engineer
More informationEnvironmental Control and Monitoring (Draft)
Next Generation Adaptive Optics System Environmental Control and Monitoring (Draft) April 10, 2009 VersionV1.0 Prepared By Jason Chin 2 of 11 REVISION HISTORY Revision Date Author (s) Reason for revision
More informationVP ELECTRONIQUE MASSY
Rev: 86-653/1 Date: 28 Oct 08 2008 Voltech Instruments. All rights reserved. Contents 1 What is Standby Power? 2 Why is standby power important? 3 Which appliances consume standby power? 4 How to measure
More informationFREQUENCY RESPONSE MONITORING (ANCILLARY SERVICES BUSINESS MONITORING)
FREQUENCY RESPONSE MONITORING (ANCILLARY SERVICES BUSINESS MONITORING) This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors
More informationTitle Power Supply Units for Signalling Equipment - DC (Regulated & Filtered) Units. Reference Number SPS 30 - (RIC Standard: SC SP)
Discipline Engineering Standard - NSW Category Signalling Title Power Supply Units for Signalling Equipment - DC (Regulated & Filtered) Units Reference Number SPS 30 - (RIC Standard: SC 09 10 07 00 SP)
More informationData Warehouse Risk Assessment (GDPR)
Data Warehouse Risk Assessment (GDPR) The new data protection law is effective from 25.05.2018. Individuals will have more control of their personal data and organisations will have to implement a risk
More informationTransition Plan. Data Center Operations Outsourcing. Implementation: Final. Ref: TR0007
Data Center Operations Outsourcing Transition Plan Implementation: Final Page 1 of 15 DOCUMENT CONTROL SHEET Schedule/Exhibit Amendment Control Sheet Title of Amended Document: Section 4 Transition Plan
More informationAC Immune DC Track Circuits Set-Up, Test and Certification
Discipline: Engineering (Signalling) Category: Standard AC Immune DC Track Circuits Set-Up, Test and Certification SES 02 Applicability New South Wales RIC (NSW CRN) Primary Source RIC Standard SC 07 41
More informationEngineering Document Control
Division / Business Unit: Function: Document Type: Enterprise Services All Disciplines Procedure Engineering Document Control Applicability ARTC Network Wide SMS Publication Requirement Internal / External
More informationSTCP 04-3 Issue 005 Real Time Data Provision
STCP 04-3 Issue 005 Real Time Data Provision STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationCONDITIONS OF SERVICE
3.4 UNMETERED CONNECTIONS This section pertains to the conditions of service and supply of electrical energy for unmetered connections. Unmetered connections are categorized as equal to GS < 50 kw class
More informationCompany Directive STANDARD TECHNIQUE : NC2D/2. Relating to Specification of Connection Assets
Company Directive STANDARD TECHNIQUE : NC2D/2 Relating to Specification of Connection Assets Policy Summary This document describes the procedure to be followed for specification and approval where a customer
More informationGuidance Document. UNC Modification Proposals Guidance for Proposers
Guidance Document UNC Modification Proposals Guidance for Proposers Guidance Document Page 1 of 7 Version 0.1 Introduction This document is the UNC Modification Guidance Document referenced in the Uniform
More informationAnnexure: B INFORMATION. Responsible Executive Manager: Division/Unit Responsible for Formulation: Writer/s: Date + Number of Revision: Review Date:
PROTOCOL FOR THE INSTALLATION OF TELECOMMUNICATION INFRASTRUCTURE IN THE KRUGER NATIONAL PARK Reference Ref: Number: 17/Pr/KNP/pro/telecom mast/vs2 (02-11) INFORMATION Responsible Executive Manager: Mr
More informationIndependent Connections Provider (ICP) Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure
Independent Connections Provider () Unmetered Connections (UMC) Jointing to Services (UJ2S) Procedure Owner Name Title Neil Clarke Head of Highway Services Signature Date 16 August 2018 Authoriser Name
More informationDisclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...
More informationSTANDARD OPERATING PROCEDURE SOP 815. Clinical Data Management System LOCKING AND UNLOCKING THE DATABASE. Joint Research Office
STANDARD OPERATING PROCEDURE SOP 815 Clinical Data Management System LOCKING AND UNLOCKING THE DATABASE Version 2.1 Version date 19/06/2017 Effective date 08/08/2017 Number of pages 6 Review date June
More informationEnergy Energy Networks. Networks Association. Association. Insert presentation title here. The Voice of the Networks
The Voice of the Networks Energy Energy Networks Networks Association Association Open Networks Project Workstream 1 Product 12 (Update Section 12.3) Insert presentation title here Name Position Date Context
More informationDESIGN PRACTICE NOTE AXLE COUNTER RESET
Approval Amendment Record Approval Date Version Description 09/09/2015 1 Initial issue 01/02/2016 2 Updated with issue of Works Instruction & Signal Engineering comments 31/08/2017 3 Updates with Standard
More informationPower System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014
Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014 PREPARED BY: Systems Capability DATE: 6 June 2014 STATUS: FINAL
More informationAudit Report. Association of Chartered Certified Accountants (ACCA)
Audit Report Association of Chartered Certified Accountants (ACCA) 26 August 2015 Contents 1 Background 1 1.1 Scope 1 1.2 Audit Report and Action Plan Timescales 2 1.3 Summary of Audit Issues and Recommendations
More informationAUTHORITY FOR ELECTRICITY REGULATION
SULTANATE OF OMAN AUTHORITY FOR ELECTRICITY REGULATION SCADA AND DCS CYBER SECURITY STANDARD FIRST EDITION AUGUST 2015 i Contents 1. Introduction... 1 2. Definitions... 1 3. Baseline Mandatory Requirements...
More informationL1-CHE-SPE-274 VITAL RELAY - MINIATURE PLUG-IN
Engineering Specification Signalling L1-CHE-SPE-274 VITAL RELAY - MINIATURE PLUG-IN Version: 1 ENGINEERING SPECIFICATION VITAL RELAY - MINIATURE PLUG-IN L1-CHE-SPE-274 Version: 1 Effective from: 1 st July
More informationSector Vision for the Future of Reference Standards
The Group of Representative Bodies (GRB) The Sector Forum Rail (SFR) Sector Vision for the Future of s Brussels, 13 th July 2018 Sector Vision for Future of s 13 th July 2018 Page 1 of 6 Scope of position
More informationFIELDS OF ACTIVITY OF STUDY COMMITTEES
FIELDS OF ACTIVITY OF STUDY COMMITTEES A 1 A 2 A 3 BB1 BB2 BB3 BB4 BB5 C 1 C 2 C 3 C 4 C 5 C 6 D 1 D 2 Rotating Electrical Machines Economics, design, construction, test, behaviour and materials for turbine
More informationIT Security Standard Operating Procedure
IT Security Standard Operating Procedure Notice: This document has been made available through the Police Service of Scotland Freedom of Information Publication Scheme. It should not be utilised as guidance
More informationDEEP SEA ELECTRONICS PLC
DEEP SEA ELECTRONICS PLC DSE2133 DSEnet RTD / Thermocouple Input Expansion Module Operator Manual Document number 057-140 Author : Anthony Manton DSE2131 DSEnet RTD / Thermocouple Input Expansion Module
More informationDC Track Circuits Set-Up, Test and Certification
Discipline: Engineering (Signalling) Category: Standard DC Track Circuits Set-Up, Test and Certification SES 01 Applicability New South Wales CRIA (NSW CRN) Primary Source RIC Standard SC 07 41 00 01 WI
More informationModel User Manual Revision E 04/29/99. OEM Gaging System. Part Number R01
04/29/99 Model 3800 OEM Gaging System User Manual Revision E Part Number 028585-R01 Information in this document is subject to change without notice. No part of this document may be reproduced or transmitted
More informationAwareness of the Situation
17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog
More informationPRODUCT SPECIFICATION
SIM Card Connector, Hinged Type, 6 Pin, SMT, 1.85mm Profile. Page 1 SIM Card Connector, Hinged Type, 6 Pin, SMT, 1.85mm Profile. Page 2 1.0 SCOPE. This specification covers performance, tests and quality
More informationGuide for the application of the CR NOI TSI
European Railway Agency According to Framework Mandate C(2007)3371 final of 13/07/2007 Reference in ERA: ERA/GUI/07-2011/INT Version in ERA: 1.01 Date: 03 December 2013 Document prepared by Document type:
More informationStandard Setting and Revision Procedure
Better Cotton Initiative Standard Setting and Revision Procedure BCI-PRO-01 (V2-0) EN Title: Document reference code: Standard Setting and Revision Procedure BCI-PRO-01-V2 Approval : BCI Council, January
More informationGeneration Interconnection Feasibility Study Report
Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study
More informationBC-9000 Field Calibration Procedure CF1_FIELDCAL_BC9000 Revised 03/16/2013
BC-9000 Field Calibration Procedure CF1_FIELDCAL_BC9000 Revised 03/16/2013 INTRODUCTION: The BC-9000 Battery Charger will recharge12 and 24 volt lead-acid and nickel cadmium batteries. Battery charging
More informationDPM Bi-directional Digital DC Power Meter with built-in USB data logger & adapter External shunt model. User Manual
DPM-3321 Bi-directional Digital DC Power Meter with built-in USB data logger & adapter External shunt model User Manual Bi-Directional DC Power Meter with built-in USB data logger & adapter. The new DPM-3321
More informationApril 2010 Power Systems division A brief introduction. ABB Group August 25, 2011 Slide 1
April 2010 Power Systems division A brief introduction August 25, 2011 Slide 1 Facts about ABB 117,000 employees in about 100 countries $32 billion in revenue (2009) Formed in 1988 merger of Swiss and
More informationFedRAMP JAB P-ATO Vulnerability Scan Requirements Guide. Version 1.0
FedRAMP JAB P-ATO Vulnerability Scan Requirements Guide Version 1.0 May 27, 2015 Document Revision History Date Version Page(s) Description Author May 27, 2015 1.0 All Initial Version C. Andersen June
More informationDelimited. Interfaced. Readable. Modifiable. Verifiable. Prioritized* Endorsed
15 quality goals for requirements Justified Correct Complete Consistent Unambiguous Feasible Abstract Traceable Delimited Interfaced Readable Modifiable Verifiable Prioritized* Endorsed Marked attributes
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationSTCP Amendment Proposal Form
STCP Amendment Proposal Form PA036 1. Title of Amendment Proposal STCP 09-2 Incorporation material currently within SPT SCS and making standard for both TOs. 2. Description of the Proposed Amendment (mandatory
More informationElectronic Devices. Special Purpose Diodes. Chapter Three. Dr. Hisham Alrawashdeh
Electronic Devices Chapter Three Special Purpose Diodes Dr. Hisham Alrawashdeh Chapter Three Special Purpose Diodes Introduction Chapter 2 was devoted to general-purpose and rectifier diodes, which are
More informationPOLICY STATEMENT. eportfolio Policy: Policy to support the eportfolio and practitioner engagement.
POLICY STATEMENT eportfolio Policy: Policy to support the eportfolio and practitioner engagement. Purpose The OTBNZ is responsible for ensuring that all practitioners on its Register are fit and competent
More informationPRODUCT SPECIFICATION
SIM Card Connector, Hinged Type, 8 Pin, SMT, 1.50mm Profile. Page 1 SIM Card Connector, Hinged Type, 8 Pin, SMT, 1.50mm Profile. Page 2 1.0 SCOPE. This specification covers performance, tests and quality
More informationAgenda Item 6: Public Sector Measurement
Agenda Item 6: Public Sector Measurement David Watkins, Task Force Chair Dave Warren, Principal, and Edwin Ng, Principal IPSASB Meeting Washington D.C., USA March 12 15, 2019 Page 1 Proprietary and Copyrighted
More informationWeb Room Booking Procedure
Academic Registrars Department Web Room Booking Procedure Contents Introduction / Background... 1 Scope / Purpose... 1 Definitions... 2 How to Start... 2 How to Choose a Room... 4 Choosing a Room... 6
More informationGlobal Water Instrumentation, Inc.
Instrumentation, Inc. 11390 Amalgam Way Gold River, CA 95670 T: 800-876-1172 Int l: (916) 638-3429, F: (916) 638-3270 Display: EZ100 11/12/04-1 - Congratulations on your purchase of the EZ100 Display.
More informationCOMMITTEE FOR PROPRIETARY MEDICINAL PRODUCTS (CPMP) GUIDELINE ON REQUIREMENTS FOR PLASMA MASTER FILE (PMF) CERTIFICATION
The European Agency for the Evaluation of Medicinal Products Evaluation of Medicines for Human Use London, 26 February 2004 COMMITTEE FOR PROPRIETARY MEDICINAL PRODUCTS (CPMP) GUIDELINE ON REQUIREMENTS
More informationOFFICIAL COMMISSIONING OF SECURITY SYSTEMS AND INFRASTRUCTURE
Title of document ONR GUIDE COMMISSIONING OF SECURITY SYSTEMS AND INFRASTRUCTURE Document Type: Unique Document ID and Revision No: Nuclear Security Technical Assessment Guide CNS-TAST-GD-4.4 Revision
More informationPART 4 Test Item File
PART 4 Test Item File Principles of Electric Circuits, 8e (Floyd) Chapter 1: Quantities and Units 1) The unit of measurement for conductance is the coulomb. (True/False) 2) Kilo equals 1,000 times the
More information1. Project Description
Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal
More informationCardiff University Security & Portering Services (SECTY) CCTV Code of Practice
Cardiff University Security & Portering Services (SECTY) CCTV Code of Practice Document history Author(s) Date S Gamlin 23/05/2018 Revision / Number Date Amendment Name Approved by BI annual revision Date
More information1.7 The Policy sets out the manner by which the University will respond to Subject Access Requests.
1 Introduction 1.1 Article 15 of the General Data Protection Regulations (GDPR) provides individuals (Data Subjects) with the right to access personal information so that they are fully informed of the
More informationEDS SCADA NUMBERING SYSTEM
Document Number: EDS 05-9007 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 05-9007 SCADA NUMBERING SYSTEM This standard describes the system for numbering SCADA wiring within switchgear
More informationReliability Coordinator Procedure PURPOSE... 1
No. RC0550 Restriction: Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 1.1.1. CAISO RC... 2 1.1.2. RC Working Groups... 2 1.1.3. Operationally Affected Parties... 2 1.1.4. RC Oversight Committee...
More informationEVAL-INAMP-62RZ/82RZ/82RMZ
Evaluation Boards for the AD620 Series and and the AD8220 Series Instrumentation Amplifiers EVAL-INAMP-62RZ/82RZ/82RMZ FEATURES 3 generic, easy-to-use PC boards Support several related in-amp products
More informationOperational Equipment Power and Environment Standard
Operational Equipment Power and Environment Standard Contents 1 Scope -3 2 Invitation to Tender Response -3 3 Generic Requirements for Equipment Environment -3 3.1 Environmental Conditions -3 3.2 Specific
More informationEDS LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES
Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-0150 LONDON 33KV DISTRIBUTION NETWORK DESIGN AND CUSTOMER SUPPLIES LPN This standard provides guidelines for the development of the 33kV distribution
More informationISO 9001 CERTIFIED. 607 NW 27th Ave Ocala, FL Phone: (352) or Fax: (352) OPERATION MANUAL. Total System Manager
ISO 9001 CERTIFIED Phone: (352) 629-5020 or 800-533-3569 Fax: (352)-629-2902 Total System Manager PAGE 1 of 17 1. REVISION LOG... 2 2. SYSTEM OVERVIEW... 3 2.1. SCOPE... 3 2.2. FEATURES... 3 3. OPERATIONAL
More informationBC-5000 Field Calibration Procedure 55 AMP
BC-5000 Field Calibration Procedure 55 AMP CF1_FIELDCAL Revised 9/8/2012 INTRODUCTION: SCOPE: The BC-5000 Battery Capacity Analyzer will perform automatic capacity testing of 12 and 24 volt lead-acid batteries.
More informationAS 7708:2016. Open Consultation. Signals Earthing and Surge Protection. Draft for Comment. Train Control Systems Standard
Train Control Systems Standard This Australian Standard AS 7708 was prepared by a RISSB Development Group consisting of representatives from the following organisations: Click here to enter the organisations
More informationNetwork Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY
Network Asset Design Standard HV SUBSTATION FEEDER EXIT CIRCUITS ISOLATION POLICY Original Issue: September 2007 Prepared by: Lee Chan & Rob Rogerson This Revision: 0 October 2007 Date For Next Review:
More informationQuick Network Block QNB-1-B. User Manual
Quick Network Block QNB-1-B User Manual Issue 1.14 Battery Connection - up to 8/16 Amps of load can be delivered to the connected instruments in two separately fused banks for redundancy (8 or 16 Amp options
More informationInformation Security Controls Policy
Information Security Controls Policy Version 1 Version: 1 Dated: 21 May 2018 Document Owner: Head of IT Security and Compliance Document History and Reviews Version Date Revision Author Summary of Changes
More informationISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management
INTERNATIONAL STANDARD ISO/IEC 27005 First edition 2008-06-15 Information technology Security techniques Information security risk management Technologies de l'information Techniques de sécurité Gestion
More informationWP195 Capacity Market and CFD Metered Data
WP195 Capacity Market and CFD Metered Data EMRS Working Practice Public Version: 4.0 Date: 6 December 2017 Table of Contents Change Amendment Record 3 1. Introduction 4 1.1 Scope and Purpose 4 1.2 Main
More informationProduct certification scheme requirements. Solar Photovoltaic Modules
Page 1 of 5 1. Introduction This document identifies the evaluation and assessment requirements and practices for the purposes of certification and listing of Solar Photovoltaic (PV) modules. Certification
More informationAccessibility Policy and Multi-Year Accessibility Plan for Enterprise Holdings
Accessibility Policy and Multi-Year Accessibility Plan for Enterprise Holdings In 2005, the Ontario Government set the goal of a barrier-free Ontario for people with disabilities by creating the Accessibility
More informationPRODUCT SPECIFICATION
DC Power Jack, Thru-Hole, Horizontal, w/locating Pegs, Ø2.00mm Page 1 DC Power Jack, Thru-Hole, Horizontal, w/locating Pegs, Ø2.00mm Page 2 1.0 SCOPE. DC Power Jack, Thru-Hole, Horizontal, w/locating Pegs,
More informationISO New England Operating Procedure No. 18 Metering And Telemetering Criteria (OP-18)
ISO New England Operating Procedure No. 18 Metering And Telemetering Criteria (OP-18) Effective Date: October 5, 2015 REFERENCES: ISO New England Market Rules and Procedures ISO New England Operating Procedure
More information