2015 General Rate Case

Size: px
Start display at page:

Download "2015 General Rate Case"

Transcription

1 Application No.: Exhibit No.: Witnesses: A SCE-0, Vol. 0 R. Woods E. Takayesu (U -E) 01 General Rate Case ERRATA Transmission and Distribution (T&D) Volume System Planning Capital Projects Before the Public Utilities Commission of the State of California Rosemead, California November 01

2 SCE-0: Transmission and Distribution Volume 0-System Planning Capital Projects Table Of Contents Section Page Witness I. SYSTEM PLANNING CAPITAL PROJECTS...1 R. Woods E. Takayesu A. Introduction And Overview...1 B. C. D. Electric System Overview GRC Authorization and Recorded Costs... Planning Process Overview of Project Planning... Transmission Planning Processes... Generator Interconnection Process... Load Growth Planning Process... a) b) c) Development Of Peak Load Forecasts... Identification Of System Requirements...1 Development of Alternatives and Project Selection...1. Construction Licensing under G.O. -D...1 E. Transmission & Interconnection Planning Projects Grid Reliability Projects...1 (1) () () () BC/SJV RAS Expansion (Project #0)...0 Victor 0/ kv Substation (Project #0)...1 Rio Hondo 0/ kv Substation (Project #01)... East Kern Wind Resource Area (EKWRA) (Project #0)... -i-

3 SCE-0: Transmission & Distribution Volume 0 - System Planning Capital Projects List Of Figures (Continued) Figure Page Figure I-1 Capacitor Automation Program Capital Expenditures Recorded 00-01/Forecast WBS Element CET-PD-LG-CV (Constant 01 and Nominal $000)... Figure I-1 Circuit Automation Program Capital Expenditures Recorded 00-01/Forecast WBS Element CET-PD-OT-CI (Constant 01 and Nominal $000) s and CIT-00-OP-NS...0 Figure I-1 Substation Load Information Monitor Program Capital Expenditures Recorded 00-01/Forecast WBS Element CET-OT-OT-AT (Constant 01 and Nominal $000)...1 -x-

4 SCE-0: Transmission & Distribution Volume 0 - System Planning Capital Projects List Of Tables Table Page Table I-1 System Planning Capital Projects Expenditure Summary CPUC and FERC Jurisdictional (Nominal $000)... Table I- System Planning Capital Projects Expenditure Summary CPUC Jurisdictional (Nominal $000)... Table I- Operating Date Changes for Projects Included in 01 GRC to Current Forecast... Table I- Licensing and Exemption Status Distribution Substation Plan...1 Table I- Licensing and Exemption Status Subtransmission Lines Plan...1 Table I- Licensing and Exemption Status A-Bank Plan...1 Table I- Transmission & Interconnection Planning Projects Capital Expenditure Summary (Nominal $000)...1 Table I- Grid Reliability Projects Expenditure Summary CPUC and FERC Jurisdictional (Nominal $000)...0 Table I- Transmission System Generation Interconnection Projects Expenditure Summary CPUC and FERC Jurisdictional (Nominal $000)... Table I- Load Growth Planning Programs Capital Expenditure Summary (Nominal $000)... Table I- A-Bank Plan Capital Expenditure Summary (Nominal $000)... Table I-1 Subtransmission Lines Plan Capital Expenditure Summary (Nominal $000)... Table I-1 Subtransmission VAR Plan Capital Expenditure Summary (Nominal $000)... Table I-1 Distribution Substation Plan Capital Expenditure Summary (Nominal $000)... Table I-1 Land Held for Future Use Capital Expenditure Summary (Nominal $000)... Table I-1 Substation Equipment Replacement Program Capital Expenditure Forecast WBS Element CET-ET-LG-SU (Nominal $000)... Table I-1 DSP Circuit Work Capital Expenditures WBS Elements CET-ET-LG-PF and CET-ET-LG-CI (Nominal $000)... Table I-1 New Distribution Circuit Capital Expenditures WBS Elements CET-ET-LG- PF and CET-ET-LG-CI (Nominal $000)...0 Total Company -xi-

5 Substation Equipment Replacement Program (SERP). DSP Circuits. Distribution Plant Betterment. Distribution VAR Plan. Capacitor Automation Program. Circuit Automation Program. Substation Load Information Monitor Program (SLIM) The Generator Interconnection Program includes projects and capital expenditures driven by requests from generation project developers who choose to have SCE construct the facilities necessary to interconnect their projects to the SCE grid. The Added Facilities projects include projects SCE constructs when a load side customer requests non-standard service. These projects may include portions that are customer cost responsibility and portions that are rate payer funded. Total costs for these projects are shown below in Table I-1 and CPUC-jurisdictional costs are shown below in Table I-. Table I-1 System Planning Capital Projects Expenditure Summary CPUC and FERC Jurisdictional (Nominal $000) Line No. Project Category Prior Total 1 Transmission & Interconnection Planning Projects,0,0 1,0, 0, 1, 0,1,1,,0 Load Growth Planning Programs,0 1, 1, 1,1 0,0, 1,, System Improvement/Reinforcement Programs,0 1,,0, 1,1,,1 Generator Interconnection Program,,,,1,1,000 1, Added Facilities Projects 1,,,,0 1, 1,1,1 Total System Planning Capital Projects,, 1,, 1,1,, 1,1 1,1,0,,1 1,,,0 1,0,1,,, 1,1, 1,1,, 1,0 1,0,,

6 ,1 1,,,0 1,0,1, Table I- System Planning Capital Projects Expenditure Summary CPUC Jurisdictional (Nominal $000) Line No. Project Category Prior Total 1 Transmission & Interconnection Planning Projects,0,0, 1, 1,, Load Growth Planning Programs 0, 1,, 1,1,1, 1,,01 System Improvement/Reinforcement Programs,0 1,,0, 1,1,,1 Generator Interconnection Program,,,,1,1,000 1, Added Facilities Projects 1,,,,0 1, 1,1,1 Total System Planning Capital Projects 0,0,,,, 1,,,1 1 B. Electric System Overview 0,0 1,,,0,1 1,,,0 Figure I-1 below is a simplified diagram of our electric power system. It shows the flow of electricity from generating plants to end-use customers. I describe the system below. Figure I-1 Simplified System Diagram

7 () Valley C 00/ kv Substation (Project #00) Valley 00/ kv Substation is located in the city of Romoland and serves the areas of Glen Ivy, Lake Elsinore, Murrieta, Perris, Romoland, Sun City, Temecula, Winchester, and unincorporated areas of Riverside County. SCE has identified that the circuit breakers on the kv bus section at the Valley 00/ kv Substation exceed their short-circuit duty equipment rating. The project scope is to replace a total of sixteen kv circuit breakers at Valley 00/ kv Substation with higher short circuit duty rated units. The operating date is June 01 with a total project cost of $.0 million. 0 This project was included in SCE s 01 GRC filing with a December 0 operating date but was subsequently moved to June 01. There are no alternatives to this project. The proposed project is the only viable technical solution. () Ellis C 0/ kv Substation (Project #01) Ellis 0/ kv Substation is located in the city of Huntington Beach and serves communities in north Orange County. By 01, the A kv bus section at Ellis 0/ kv Substation is projected to exceed its capacity limit due to continuing load growth in the area. The project scope is to install a new 0 MVA transformer bank on the C kv bus section at Ellis 0/ kv Substation (thereby increasing total transformer capacity from 0 MVA to 1 MVA at the station), rearrange various kv subtransmission lines to permanently transfer four substations from the A kv bus section to the C kv bus section, and replace the north and south 0 kv buses with 1 kcmil ACSR. Without the project, the loading on the A kv bus section at Ellis 0/ kv Substation exceeded the substation s capacity limit in 0 under normal operating conditions. This project has been separated into two phases. Phase 1 includes the installation of a new 0 MVA transformer and the subtransmission lines rearrangement. Phase includes replacing the north and south 0 kv buses. This project was included in SCE s 01 GRC filing with a June 0 operating date but was subsequently moved to June 0 (Phase 1) and June 01 (Phase ) due to delays in acquiring the necessary permits to construct the project. Phase 1 had an operating date of June 0 and Phase has an operating date of July 01. The total project cost is $. million. 1 SCE has identified one alternative to this project to install a new 0 MVA transformer bank at Johanna 0/ kv Substation and construct approximately 1. miles of new 0 Refer to workpaper entitled Valley C 00/ kv Substation (Project #00). 1 Refer to workpaper entitled Ellis C 0/ kv Substation (Project #01). outage priority to the Del Amo-Ellis Loop-in Project needed due to SONGS shutdown. 1

8 kv subtransmission line to permanently transfer Gisler /1 kv Substation and Talbert /1 kv Substation from the Ellis kv system to the Johanna kv system. The total estimated cost of this alternative is $. million. The proposed project was selected as the least cost alternative. () Santiago 0/ kv Substation (Project #0) Santiago 0/ kv Substation is located in the city of Irvine and serves communities in south Orange County. By the end of 01, Santiago 0/ kv Substation is projected to approach its capacity limit due to continuing load growth in the area. The project scope is to install the existing spare 0 MVA transformer bank at Santiago 0/ kv Substation as a permanent unit (thereby increasing total transformer capacity from 0 MVA to 1 MVA at the station) and split the Santiago kv system. Without the project, the loading at Santiago 0/ kv Substation is projected to reach. percent of the substation s capacity limit by the end of 01 under normal operating conditions. The operating date is December 01 with a total project cost of $.01 million. This project was included in SCE s 01 GRC filing with a June 0 operating date but was subsequently moved to December 01 due to delays in acquiring the necessary permits to construct the project. SCE has identified one alternative to this project to install a new 0 MVA transformer bank at Viejo 0/ kv Substation, construct approximately 1. miles of new kv subtransmission line, and rebuild approximately.0 miles of existing kv subtransmission line to permanently transfer Borrego /1 kv Substation, Moulton /1 kv Substation, and Niguel /1 kv Substation from the Santiago kv system to the Viejo kv system. The total estimated cost of this alternative is $. million. The proposed project was selected as the least cost alternative. () La Cienega 0/ kv Substation (Project #0) La Cienega 0/ kv Substation is located in the city of Los Angeles and serves communities in west Los Angeles County. By 01, La Cienega 0/ kv Substation is projected to approach its capacity limit due to continuing load growth in the area. The project scope is to install a new 0 MVA transformer bank at La Cienega 0/ kv Substation (increasing total transformer capacity from 0 MVA to 0 MVA at the station) and upgrading the substation automation to SA. Without the project, the loading at La Cienega 0/ kv Substation is projected to reach. percent of the substation s capacity limit by 01 under normal operating conditions. This project is includes installing a new 0 MVA transformer bank and upgrading the substation automation Refer to workpaper entitled Santiago 0/ kv Substation (Project #0). in order to be more cost effective by designing and constructing project concurrent with other adjacent projects.

9 Table I-1 Distribution Substation Plan Capital Expenditure Summary Total Company (0% CPUC-Jurisdictional Nominal $000) Line Operating Project # Project Name No. Date Prior Total 1 0 Las Lomas /1 kv Substation Nov 01,1, ,1 0 Mascot /1 kv Substation Dec 01, , 0 Triton /1 kv Substation Apr 01,1, ,1 0 Pepper /1 kv Substation Jun 01,, ,1 00 El Sobrante /1 kv Substation Jun 01,1, , 0 Roadway /1 kv Substation Jun 01,, ,00 00 Bloomington /1 kv Substation Jun 01, , 00 Fillmore /1 kv Substation Jun 01,00 1, ,01 0 Devers /1 kv Substation Jun 01,, , 00 La Habra Project /1 kv Substation Jun 01,0, , 00 Estrella /1 kv Substation Jun 01 1,, , 1 0 Carodean /1 kv Substation Jun 01,0, , 1 0 Delano /1kV Substation Jun 01,00, ,0 1 0 Glen Avon /1 kv Substation Jun 01, ,0 1 0 Lampson /1 kv Substation Jun ,, , 1 01 Downs /1 kv Substation Jun 01,1, 1, , 1 0 Pebbly Beach 1/. kv Substation Jun , Del Amo Jr /1 kv Substation Jun ,1, - - -, 1 0 La Palma /1 kv Substation Jun 01,, , Lark Ellen /1 kv Substation Jun 01 1, 1, - - -, 1 00 Colonia /1 kv Substation Jun ,, - -, Canyon /1 kv Substation Jun 01 0, 1, 0 - -, 00 San Dimas /1 kv Substation Jun , 00 Orange /1 kv Substation Jun 01-1,0, - - 1,0 0 Lakeview /1 kv Substation Jun 01,0,0,,,0 -,0 00 Yokohl /1 kv Substation Jun 01,,00 0,, -,0 01 Banducci /1 kv Substation Jun 01,,0, 1,,1 -, 0 Greenhorn /. kv Substation Jun ,0 1, -, 0 Mainframe /.1 kv Substation Jun 01 -,, 1,,1 -, 0 01 Safari /1 kv Substation Jun ,, 1,0 -, 1 0 Circle City /1 kv Substation - Phase 1 Jun 01 -, 1,, -,1 0 Falcon Ridge /1 kv Substation Dec 01,1,,0,, -, Total Distribution Substation Plan 1,, 1,1 1,1 1, - 0, 1 The capital cost shown for each project in the table above is for work required inside the substation (e.g., the addition of a B-bank transformer), new distribution circuits associated with a B- bank transformer addition, and any telecommunications or right of way and land components of the project. The costs for the distribution circuits that are not associated B-bank transformer addition projects are aggregated and budgeted as a separate item entitled DSP Circuits and are included in this portion of my testimony for reference and justification purposes only. These circuit costs are discussed separately in the System Improvement/Reinforcements Program portion of my testimony. We have identified DSP projects with project costs equal to or greater than $1 million. A description and justification for each of these projects is provided below. The total cost for these projects is $0. million of which $. million is CPUC-jurisdictional cost forecast from 01 to 01.

10 Lakeview areas. The temporary Model Pole-Top /1 kv Substation 1 is projected to provide capacity to serve the load which is in excess of the capacity of Nuevo substation until Lakeview Substation is complete. Upon completion of the Lakeview Substation project, both Nuevo and Model P.T. Substations would be decommissioned. Lakeview Substation will provide capacity to serve the existing demand, as well as capacity to serve future developments, and provide enhanced reliability and operational flexibility to the Electrical Needs Area. The project scope is to construct a new substation consisting of two MVA, /1 kv transformer banks and four new 1 kv distribution circuits. Without the project, the loadings at Nuevo /1 kv Substation is projected to reach 1. percent of the substation s capacity limit by 01 under normal operating conditions. The operating date is June 01 with a total project cost of $.0 million. 1 This project was included in SCE s 01 GRC filing with a June 01 operating date but was subsequently moved to June 01 due to licensing delays. SCE has identified one alternative to this project to construct a new MVA, /1 kv substation in the Nuevo and Lakeview areas with four new 1 kv distribution circuits and three new kv distribution lines to feed the new substation. The alternative analysis was included in the PEA (Application A ) filed September 1, 0. The proposed project was selected because it satisfies all of the project objectives. The total estimated cost of this alternative is $.1 million. This alternative does not eliminate the need for Lakeview /1 kv Substation, but instead only defers the need by 1 years (from 01 to 0). This alternative does not adequately meet longterm projected electrical load requirements in the Nuevo and Lakeview areas. In addition, this alternative would result in reduced operating flexibility and reliability for the area as compared to the proposed project due to the considerably longer source lines needed to serve the substation (approximately twenty-five miles of kv lines to feed the /1 kv substation versus approximately three miles of kv lines to feed Lakeview /1 kv Substation). For these reasons, the proposed project was selected as the preferred alternative. () Yokohl /1 kv Substation (Project #00) Yokohl /1 kv Substation is a new planned substation to be located in the Yokohl Ranch area of the San Jacinto Valley. Yokohl Substation is planned to meet future load of Joaquin 1 Model Pole-Top /1 kv Substation is a temporary facility constructed as an interim measure to meet the immediate capacity needs in the Nuevo and Lakeview areas. 1 Refer to workpaper entitled Lakeview /1 kv Substation (Project #0). 0

11 Table I-1 Land Held for Future Use Capital Expenditure Summary (0% CPUC-Jurisdictional Nominal $000) Line Operating Project # Project Name No. Date Prior Total 1 0 Valley South Jun ,, -, 0 Circle City Substation Jun ,1 -,1 Total Other Transmission Planning Projects ,1,0-1, G. System Improvement/Reinforcement Programs seven The System Improvement/Reinforcement Programs include six categories in which projects are identified and cost forecasts are developed. Descriptions of these categories and forecasts are included below. 1. Substation Equipment Replacement Program (SERP) Blanket Budget Item, WBS Element CET-ET-LG-SU The Substation Equipment Replacement Program (SERP) evaluates the adequacy of substation terminal equipment and system protection equipment. Specifically, the SERP identifies substations where short-circuit duty levels exceed equipment ratings as well as system ground source requirements essential to the provision of safe, reliable service. Typical SERP projects include the replacement of circuit breakers with higher short-circuit duty rated units, 1 projects to reduce short circuit duty levels at substations, or the addition of ground banks for proper grounding under normal and contingency conditions. SERP projects are necessary for safe operation and to avoid equipment damage during normal, contingency, or faulted conditions. Figure I- below, shows recorded and forecast expenditures for SERP. 1 Short-Circuit Duty Abnormal current levels an electrical system will experience during faulted conditions, producing considerable thermal and mechanical stresses in electrical equipment.

12 Figure I-1 Circuit Automation Program Capital Expenditures Recorded 00-01/Forecast WBS Element CET-PD-OT-CI and CIT-00-OP-NS (0% CPUC-Jurisdictional Constant 01 and Nominal $000) s $1,000 $1,000 $,000 $,000 $,000 $,000 $,000 $ Nominal $,,0,0,,,000,1,0,1, Constant 01 $,1,1 1,,,,,00,00,00,00 Nominal $ Constant 01 $ Forecast 1. Substation Load Information Monitor Program, WBS CET-OT-OT-AT The Substation Load Information Monitor (SLIM) Program includes the work related to installation of equipment for substation load monitoring. This program will provide SCE with data to aid in circuit and substation transformer planning as well as improve real-time grid operations for substations that do not currently have substation automation systems. In 01 we plan to add load monitoring to ten substations and twenty per year thereafter through 01. Figure I-1 below, shows forecast expenditures for the SLIM Program. In 01 constant dollars, average forecast expenditures over the period are $1.0 million per year. 1 $, $,0 $,1 $, $,1 $, $, $, $, $,0 $, $, $1,1 $, $,1 $,0 $, $, $, $, 1 Refer to workpaper entitled Substation Load Information Monitoring Workpaper for additional detail. 0

13 SOUTHERN CALIFORNIA EDISON COMPANY QUALIFICATIONS AND PREPARED TESTIMONY OF ROBERT G. WOODS Q. Please state your name and business address for the record. A. My name is Robert G. Woods, and my business address is Three Innovation Way, Pomona, California, 1. Q. Briefly describe your present responsibilities at the Southern California Edison Company. A. I am the Director of Electric System Planning for the Engineering and Technical Service (E&TS) within Southern California Edison Company s Engineering and Technical Service (ET&S) organization. Electric System Planning is responsible for transmission, distribution, substation subtransmission planning, interconnection studies and customer support. Q. Briefly describe your educational and professional background. A. I hold a Bachelor of Science degree in Electrical Engineering from California State University of Long Beach. I joined Southern California Edison in 1 and have held a variety of planning, engineering, and management positions since. I have been in my current position since July, 0. Q. What is the purpose of your testimony in this proceeding? A. The purpose of my testimony in this proceeding is to sponsor Exhibit SCE-0, Volume, entitled Transmission and Distribution - System Planning Capital Projects as identified in the Table of Contents thereto. Q. Was this material prepared by you or under your supervision? A. Yes, it was. Q. Insofar as this material is factual in nature, do you believe it to be correct? A. Yes, I do. Q. Insofar as this material is in the nature of opinion or judgment, does it represent your best judgment? A. Yes, it does. Q. Does this conclude your qualifications and prepared testimony? A. Yes, it does. A-1

14 SOUTHERN CALIFORNIA EDISON COMPANY QUALIFICATIONS AND PREPARED TESTIMONY OF ERIK T. TAKAYESU Q. Please state your name and business address for the record. A. My name is Erik T. Takayesu, and my business address is Three Innovation Way, Pomona, California, 1. Q. Briefly describe your present responsibilities at the Southern California Edison Company. A. I am the Director of Electric System Planning within Southern California Edison Company s Transmission & Distribution (T&D) organization. Electric System Planning is responsible for planning the future needs of the distribution and transmission system, sponsoring projects that expand and reinforce the grid, and facilitating the interconnection of renewable distributed generation for meeting the corporate goals of safe, affordable and reliable delivery of energy to our customers.. Q. Briefly describe your educational and professional background. A. I hold a Bachelor of Science degree in Electrical Engineering from California State University of Long Beach, and a masters degree in Organizational Leadership From Gonzaga University. I joined Southern California Edison in and have held a variety of operational, planning, engineering, and management positions since. Prior to my current position I was the Principal Manager of Distribution Engineering. I have been in my current position since January, 01. Q. What is the purpose of your testimony in this proceeding? A. The purpose of my testimony in this proceeding is to sponsor Exhibit SCE-0, Volume, entitled System Planning Capital Projects. Q. Was this material prepared by you or under your supervision? A-1

15 1 A. No, Robert Woods was the initial sponsor of the testimony when it was submitted in November 01. I have reviewed the testimony and adopt the testimony as my own. Q. Insofar as this material is factual in nature, do you believe it to be correct? A. Yes, I do. Q. Insofar as this material is in the nature of opinion or judgment, does it represent your best judgment? A. Yes, it does. Q. Does this conclude your qualifications and prepared testimony? A. Yes, it does. A-

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: M. Flores B. Tolentino A (U -E) 01 General Rate Case ERRATA Transmission & Distribution (T&D) Volume 0 Substation Construction & Maintenance

More information

2018 General Rate Case Rebuttal Testimony

2018 General Rate Case Rebuttal Testimony Application No.: A.1-0-001 Exhibit No.: SCE-1, Vol. 0 Witnesses: A. Ayorinde (U -E) 01 General Rate Case Rebuttal Testimony Transmission & Distribution (T&D) Volume - Customer-Driven Programs Before the

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E For a Permit to Construct Electrical Facilities With Voltages

More information

2012 General Rate Case

2012 General Rate Case Application No.: Exhibit No.: SCE-0, Vol. 0 Part 0 & 0, Ch. I-II Witnesses: P. Arons K. Varnell (U -E) 01 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Part - Transmission

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: SCE-11 R. Lisbin (U 338-E) 2015 General Rate Case Compliance Before the Public Utilities Commission of the State of California Rosemead, California November 2013

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: SCE-1 J. P. Shotwell (U -E) 01 General Rate Case Testimony Regarding Accessibility Issues Developed Jointly By SCE and Center for Accessible Technology Before the

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Leatherneck

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Cerritos

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Eldorado-Lugo-Mohave

More information

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 System Planning Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: E. Takayesu (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume System Planning Before the Public Utilities Commission of

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witness: A.13-11-003 SCE-07, Vol. 04 D. Daigler C. Miller (U 338-E) 2015 General Rate Case ERRATA Safety, Security, & Compliance (SS&C) Volume 4 Corporate Security and Business

More information

2009 General Rate Case

2009 General Rate Case Application No.: Exhibit No.: SCE-0, Vol., Pt. Ch. I-IV Witness: A. Salinas (U -E) 00 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Capital Expenditures Part, Chapter I IV

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (APRIL 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Wendy al-mukdad, PE Utilities Engineer Grid Planning & Reliability Section, Energy Division California Public Utilities

More information

Rocky Mountain Power Docket No Witness: Rohit P. Nair BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Rohit P. Nair BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 16-035-36 Witness: Rohit P. Nair BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Rohit P. Nair March 2019 1 2 3 4 5 6

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 17-035-36 Witness: Kelcey A. Brown BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Kelcey A. Brown August 2017 1 2 3 4

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.-0- Exhibit No.: SCE-0, Vol. Witnesses: T. Reeves (U -E) 0 General Rate Case Transmission & Distribution (T&D) Volume - Other Costs, Other Operating Revenues Before the Public Utilities

More information

Valley-Ivyglen and Alberhill Transmission Line Projects

Valley-Ivyglen and Alberhill Transmission Line Projects Valley-Ivyglen and Alberhill Transmission Line Projects Final Environmental Impact Report City Council Meeting May 23, 2017 Valley-Ivyglen Project Construction of a new, single-circuit 115-kV subtransmission

More information

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

PacifiCorp Transmission Technical Workshop

PacifiCorp Transmission Technical Workshop PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

EU DONOR FUNDED SMART GRID PROGRAMME

EU DONOR FUNDED SMART GRID PROGRAMME EU DONOR FUNDED SMART GRID PROGRAMME 1 Historical Background Msunduzi Local Municipality is a local municipality in Umgungundlovu District Municipality, KwaZulu-Natal, South Africa. It encompasses the

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

(U 338-E) 2018 General Rate Case A Workpapers. 2nd ERRATA. RO- Taxes SCE-09 Volume 02, Chapter I-II

(U 338-E) 2018 General Rate Case A Workpapers. 2nd ERRATA. RO- Taxes SCE-09 Volume 02, Chapter I-II (U 338-E) 2018 General Rate Case A.16-09-001 Workpapers 2nd ERRATA RO- Taxes SCE-09 Volume 02, Chapter I-II September 2016 2 Workpaper / 2018 GRC Table I-1 Summary of Electric Plant Weighted Average Balances

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

LADWP POWER INFRASTRUCTURE PLAN

LADWP POWER INFRASTRUCTURE PLAN LADWP 2017-18 POWER INFRASTRUCTURE PLAN Introduction LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4 million

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION MPUC DOCKET NO. E-002, ET2/CN OAH DOCKET NO.

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION MPUC DOCKET NO. E-002, ET2/CN OAH DOCKET NO. Direct Testimony and Schedule STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION Eugene R. Kotz II IN THE MATTER OF THE APPLICATION FOR A CERTIFICATE OF NEED FOR THE HOLLYDALE 115 KV TRANSMISSION

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER07-1034-002 REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project )

Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project ) Unofficial Comment Form 1st Draft of PRC-005-3: Protection System and Automatic Reclosing Maintenance (Project 2007-17.2) Please DO NOT use this form for submitting comments. Please use the electronic

More information

(U 338-E) 2018 General Rate Case A Workpapers. T&D- Distribution Maintenance and Inspection SCE-02 Volume 04

(U 338-E) 2018 General Rate Case A Workpapers. T&D- Distribution Maintenance and Inspection SCE-02 Volume 04 (U 338-E) 2018 General Rate Case A.16-09- Workpapers T&D- Distribution Maintenance and Inspection SCE-02 Volume 04 September 2016 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 I. DISTRIBUTION

More information

THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS?

THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? Whitepaper authored by: Herbert Falk Senior Solutions Architect SISCO, Inc. herb@sisconet.com One of the major

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Advanced Protection and Control Technologies for T&D Grid Modernization

Advanced Protection and Control Technologies for T&D Grid Modernization Advanced Protection and Control Technologies for T&D Grid Modernization i-pcgrid Workshop San Francisco, CA March 31, 2016 Jeff Shiles, Principal Manager Protection & Automation Engineering Southern California

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

POWER INFRASTRUCTURE PLAN 2016

POWER INFRASTRUCTURE PLAN 2016 POWER INFRASTRUCTURE PLAN 2016 Introduction LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4 million people

More information

RE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line

RE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line Dominion Energy P.O. Box 26666, Richmond, VA 23261 DominionEnergy.com David J. DePippo Senior Counsel Direct: (804) 819-2411 Facsimile: (804) 819-2183 david.j.depippo@dominionenergy.com Via Email Ms. Anna

More information

December 9, 2011 Advice Letter 2613-E

December 9, 2011 Advice Letter 2613-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 9, 2011 Advice Letter 2613-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (APRIL 2011) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS Pursuant to Commission Decision ( D. ) 06-09-003, SCE hereby provides

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

G. Larry Clark Principal Engineer Power Delivery Alabama Power Company, A Southern Company

G. Larry Clark Principal Engineer Power Delivery Alabama Power Company, A Southern Company 2014 IEEE PES T&D Conference & Exposition Chicago, IL April 15, 2014 Panel Session: Technologies for Advanced Volt/VAR Control Implementation Volt/VAR Control as Part of an Integrated Distribution Management

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for Authority to Lease Available Land at Walnut Substation

More information

Notes to expenditure information provided by WE in support of the CPP earthquake readiness expenditure. Commissioned Assets

Notes to expenditure information provided by WE in support of the CPP earthquake readiness expenditure. Commissioned Assets Notes to expenditure information provided by WE in support of the CPP earthquake readiness expenditure Commissioned Assets Notes Capitalisation policy Consistent with IM 5.3.11, CPP capex, including for

More information

December 10, 2012 Advice Letter 2797-E

December 10, 2012 Advice Letter 2797-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 10, 2012 Advice Letter 2797-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

2018 General Rate Case. Operational Services (OS) Volume 3 Corporate Real Estate

2018 General Rate Case. Operational Services (OS) Volume 3 Corporate Real Estate Application No.: A.1-0- Exhibit No.: SCE-0, Vol. Witnesses: N. Desrocher A D. Bauder (U -E) 01 General Rate Case nd Errata Operational Services (OS) Volume Corporate Real Estate Before the Public Utilities

More information

TransWest Express and Gateway South

TransWest Express and Gateway South TransWest Express and Gateway South Co-developed by four leading entities: Arizona Public Service PacifiCorp National Grid Wyoming Infrastructure Authority Regional Stakeholder Meeting January 23, 2008

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

Transforming the Electric Grid

Transforming the Electric Grid Transforming the Electric Grid - ORNL s role in supporting DOE s mission January 6 th, 2005 Tom King Program Manager, Power Technologies Oak Ridge National Laboratory kingtjjr@ornl.gov 865-675-4390 Office

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 11 Grid Technology

2018 General Rate Case. Transmission & Distribution (T&D) Volume 11 Grid Technology Application No.: A.-0- Exhibit No.: SCE-0, Vol. Witnesses: D. Kim (U -E) 0 General Rate Case Transmission & Distribution (T&D) Volume Grid Technology Before the Public Utilities Commission of the State

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013

Chief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Mark W. Maher Chief Executive Officer Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Agenda WECC Overview WECC Strategic Planning Initiative Western Interconnection Synchrophasor

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

Local Area Studies Update - PACW Kevin Putnam

Local Area Studies Update - PACW Kevin Putnam Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton

More information

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO

More information

Power Infrastructure Plan

Power Infrastructure Plan Power Infrastructure Plan 2015 Introduction Background LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

Dominion Supplemental Projects

Dominion Supplemental Projects Dominion Supplemental Projects Transmission Expansion Advisory Committee October 11, 2018 Needs Need Number: DOM-2018-0017 Meeting Date: 10/11/2018 Process Stage: NEED Supplemental Project Driver: Customer

More information

INCREASING electrical network interconnection is

INCREASING electrical network interconnection is Blair, Steven Macpherson and Booth, Campbell and Turner, Paul and Turnham, Victoria (2013) Analysis and quantification of the benefits of interconnected distribution system operation. In: 5th International

More information

Smart Distribution Technology

Smart Distribution Technology Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications

More information

2009 SPP TransCanada Pipeline Study Report

2009 SPP TransCanada Pipeline Study Report 2009 SPP TransCanada Pipeline Study Report SPP Engineering Department, Planning Section PUBLISHED: 7/9/2009 LATEST REVISION: 7/9/2009 Copyright 2009 by Southwest Power Pool, Inc. All rights reserved. Table

More information

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Opening 2013/2014 Transmission Planning Process Stakeholder Meeting Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Yesterday s Agenda November 20 th Topic Opening Introduction

More information

PRC Coordination of Protection Systems for Performance During Faults

PRC Coordination of Protection Systems for Performance During Faults PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Powering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director

Powering the North West s Future: From DNO to DSO. Paul Bircham Commercial Strategy & Support Director Powering the North West s Future: From DNO to DSO Paul Bircham Commercial Strategy & Support Director 1 Introducing Electricity North West 5 million 2.4 million (45% of demand) 20,000 I&C (55% of demand)

More information

XXXXX XXXX Wind Generation Project

XXXXX XXXX Wind Generation Project A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Los Anseles W Department of 5* Water & Power

Los Anseles W Department of 5* Water & Power Los Anseles W Department of 5* Water & Power 3D RESOLUTION NO. BOARD LETTER APPROVAL DAVID H. WRIGHT MARCIE L. EDWARDS Chief Operating Officer General Manager DATE: May 26, 2016 SUBJECT: Lease Agreement

More information

February 25, Subject: Southern California Edison 2015 Annual Progress Report

February 25, Subject: Southern California Edison 2015 Annual Progress Report February 25, 2015 Mr. Tracy Rolstad, Chair WECC Technical Studies Subcommittee Avista Corp. 1411 East Mission Avenue Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff Salt Lake City, UT 84103-1114

More information

Unofficial Comment Form Project Disturbance Monitoring

Unofficial Comment Form Project Disturbance Monitoring Unofficial Comment Form Project 2007-11 Disturbance Monitoring Please DO NOT use this form for submitting comments. Please use the electronic form to submit comments on the Standard Authorization Request

More information

Minutes - Standing Policy Committee on Finance - April 9, 2015 REPORTS

Minutes - Standing Policy Committee on Finance - April 9, 2015 REPORTS Minutes - Standing Policy Committee on Finance - April 9, 2015 REPORTS Item No. 4 Water Supervisory Control and Data Acquisition (SCADA) Upgrade Financial Status Report No. 1 for the Period from November

More information

Washington City. September Capital Facilities Plan- Electrical

Washington City. September Capital Facilities Plan- Electrical Washington City Capital Facilities Plan- Electrical September 2007 Intermountain Consumer Professional Engineers, Inc. 1145 East South Union Avenue Midvale, Utah 84047 (801) 255-1111 TABLE OF CONTENTS

More information

DUKE ENERGY FLORIDA 2015 HURRICANE SEASON PREPARATION BRIEFING. Florida PSC Hurricane Preparedness Workshop March 18, 2015

DUKE ENERGY FLORIDA 2015 HURRICANE SEASON PREPARATION BRIEFING. Florida PSC Hurricane Preparedness Workshop March 18, 2015 Our hurricane restoration operational plan functioned well in 2004 and 2005. We continue to review it annually in an effort to make improvements. All lessons learned from past major storms and mid-level

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into the State of Competition Among Telecommunications Providers in California, and to Consider and Resolve

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE FORMULA ) RATE PLAN FILINGS OF OKLAHOMA GAS ) GAS AND ELECTRIC COMPANY ) DOCKET NO. -0-FR PURSUANT TO APSC DOCKET ) NO. -0-U ) Direct

More information

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006 Business Update Al Fohrer Chief Executive Officer Southern California Edison Company Merrill Lynch Power & Gas Conference September 2006 Forward-Looking Statement This presentation contains forward-looking

More information

Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE

Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Campus Electrical System Renewal, Reliability & Safety Presented by Andrew Hay, PE Key Factors of Resilient Electrical

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

THE INTERCONNECTION HANDBOOK

THE INTERCONNECTION HANDBOOK THE INTERCONNECTION HANDBOOK Southern California Edison Company Rev. 8 This document is controlled by the originating SCE T&D organization. When downloaded and printed, this document becomes UNCONTROLLED,

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D (.laps Lisa Malagon Leader Federal and State Compliance Mail Station 9704 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250- 5671 Elisa.Malagon@aps.com January 31, 2014 Docket Control Arizona Corporation

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information