B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

Size: px
Start display at page:

Download "B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:"

Transcription

1 B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street, Sixth Floor Vancouver, BC VZ N Dear Ms. Hamilton: Re: British Columbia Transmission Corporation (BCTC) Application on Behalf of BC Hydro and Power Authority (BC Hydro) for a Certificate of Public Convenience and Necessity (CPCN) for the Vancouver City Central Transmission Substation Distribution Assets BC Hydro and Power Authority (BC Hydro) has authorized BCTC to seek Commission approval for the VCCT Substation Distribution Assets. Therefore, BCTC files amendments to the following pages of its Application, filed with the Commission on September 00, to incorporate an application for an order issuing a CPCN for the construction and operation of the VCCT Substation Distribution Assets. Application Pages: ES-,,,, -,, Appendices: Appendix A A Revised Draft Order granting BCTC a CPCN for the construction and operation of the VCCT Project except the Substation Distribution Assets A second Draft Order is included granting BC Hydro a CPCN for the construction and operation of the VCCT Substation Distribution Assets. For further information, please contact Gordon Doyle at 0--. Sincerely, Original signed by: Janet L. Fraser Director, Regulatory Affairs cc: Registered Intervenors Suite 00, Four Bentall Centre, 0 Dunsmuir Street PO Box 0, Vancouver, BC VX V

2 Executive Summary 0 for a more secure supply of current load, the need to ensure that load growth can be met, and the need to establish a new link between the north and south Metro systems. Orders Requested Pursuant to Sections and of the Utilities Commission Act, BCTC applies to the Commission for an order issuing a Certificate of Public Convenience and Necessity (CPCN) authorizing construction and operation of the VCCT Project except for the VCCT Substation Distribution Assets. BCTC also applies to the Commission on behalf of BC Hydro for a CPCN authorizing construction and operation of the VCCT Substation Distribution Assets. Vancouver City Central Transmission Project CPCN Application ES- Revised September 00 - Revised October

3 BC Transmission Corporation Introduction 0.0 INTRODUCTION This is an Application by British Columbia Transmission Corporation (BCTC) for two orders. Unless otherwise mentioned, where the term VCCT Project is used in this Application the term is referring to the entire project including the VCCT Substation Distribution Assets. On its own behalf, BCTC applies pursuant to Sections and of the Utilities Commission Act (the Act) for a Certificate of Public Convenience and Necessity (CPCN) for the Vancouver City Central Transmission Project (VCCT Project) except for the VCCT Substation Distribution Assets. On behalf of British Columbia Hydro and Power Authority (BC Hydro), BCTC also applies pursuant to Section and of the Act for a CPCN authorizing construction and operation of the related Substation Distribution Assets (SDA) components of the VCCT Project (the VCCT Substation Distribution Assets) as described in Section. of this Application.. Overview of the VCCT Project The VCCT Project is proposed to address three needs within the Metro Vancouver regional transmission system in the central part of the city of Vancouver. These needs are: 0 (a) significant load growth in the Mount Pleasant/South False Creek area and in adjacent service areas is forecast to exceed the capacity of existing substations serving those areas; (b) approximately 0 MVA of distribution load in the Mount Pleasant/South False Creek area is served by distribution duct banks that extend south from Murrin Substation which are approaching end of-life condition requiring replacement to secure continued reliable service. In addition, these distribution duct banks traverse through seismically unstable soil and would sustain significant damage in a seismic event; and (c) circuit L, a 0 kv underground circuit from Murrin Substation to Mainwaring Substation (MAN) is in a deteriorated condition approaching end- Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

4 BC Transmission Corporation Introduction of-life and for planning purposes has been zero-rated as of November 0. In the absence of circuit L, the transmission system in the south Metro area would not meet the normal system minus one element (N-) planning criterion.. Description of Preferred Solution The preferred solution to meeting the three needs is the VCCT Project, which would consist of a new substation in the Mount Pleasant area (the Mount Pleasant Substation or MPT ) connected by two new 0 kv circuits to Sperling Substation (SPG) and to Cathedral Square Substation (CSQ). Vancouver City Central Transmission Project CPCN Application -a Revised - September 00 - Revised October

5 BC Transmission Corporation Introduction (c) providing two new 0 kv underground transmission circuits to supply the new Mount Pleasant Substation which would replace the important function of circuit L of providing a link between the North and South Metro Vancouver transmission systems, allowing supply from the north to serve the south (and vice versa) during contingencies. 0 0 The proposed project provides a cost effective and reliable solution to meet the three identified needs... Description and Location of Substation The proposed Mount Pleasant Substation would be housed in a new building occupying a 0,000 square foot site at the corner of Alberta Street and West th Avenue in the City of Vancouver. The location of the proposed substation is currently zoned light industrial, and is within an area designated by the City as the Mount Pleasant Industrial Area. The conceptual design of the proposed Mount Pleasant Substation contemplates a staged development of the substation with transmission equipment and Substation Distribution Assets (SDA) installed over time as the electrical loads served by the substation increase... Location of Transmission Circuits The Mount Pleasant Substation would be connected by underground 0 kv transmission circuits to each of Sperling Substation, which is located at Arbutus Street and King Edward Avenue, and Cathedral Square Substation, which is located at Richards Street and Dunsmuir Avenue. The routes for the proposed transmission circuits are illustrated in Figure - above... Related ProjectOverview of the VCCT Substation Distribution Assets(SDA Facilities Included in Project) In this Application BCTC, on behalf of BC Hydro, also seeks an order issuing a CPCN for the VCCT Substation Distribution Assets, as described in Section. of this Application. The major components of the VCCT Substation Distribution Assets are: 0 (a) two 0/ kv, MVA (LV winding reconnectable to kv) step- down transformers; and Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

6 BC Transmission Corporation Introduction (b) two kv, MVA GIS feeder sections. In this Application BCTC is seeking approval of the transmission components of the VCCT Project. Certain associated SDA which are described for context in Section of this Application will be constructed in conjunction with the transmission infrastructure. However, no approval of the SDA portion of the project is sought in this Application. BCTC is aware of that British Columbia Utilities Commission (Commission) has expressed concerns about the practice of seeking separate approvals of Vancouver City Central Transmission Project CPCN Application -a Revised - September 00 - Revised October

7 BC Transmission Corporation Introduction 0 0 Transmission and SDA components for related projects. In its recent F00/0 BCTC Capital Plan Decision, issued July, 00, the Commission has directed BCTC to work with BC Hydro to either accept its proposal to have either BCTC or BC Hydro seek regulatory approval for the entire projects, including both transmission and SDA components, or develop an alternative resolution to the problem. In its Decision, the Commission directed BCTC and BC Hydro to provide its report within 0 days from the date of Decision, which would be on or about October,, 00. Given the timing of that report, BCTC will update this Application, if required, once it has been filed and further directions are made by the Commission, or if BC Hydro requests that BCTC seek approval of the related SDA assets on their behalf, as is their right under the SDA Service Level Agreement.. Orders Requested BCTC seeks two orders in this Application. Pursuant to Sections and of the Utilities Commission Act, BCTC applies to the Commission for an orders issuing a Certificate of Public Convenience and Necessity (CPCN) authorizing construction and operation of the VCCT Project, except the VCCT Substation Distribution Assets. BCTC also seeks, on behalf of BC Hydro, a CPCN authorizing the construction and operation of the VCCT Substation Distribution Assets as more fully described in Section of this Application. The information contained in this Application meets the information requirements set out in the Commission s Certificates of Public Convenience and Necessity CPCN Application Guidelines (the CPCN Guidelines ) issued March 00, and BCTC submits that the VCCT Project is required and in the public convenience and necessity. A ddraft Orders areis included as Appendix A to this Application.. Consistency with Utilities Commission Act The VCCT Project, as proposed in this Application, is consistent with the Utilities Commission Act. Section of the Utilities Commission Act provides a definition of Directive, page of July, 00 Decision pertaining to the F00/0 Transmission System Capital Plan Order No. G--0 Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

8 BC Transmission Corporation Introduction government s energy objectives. Subsection (.) requires the Commission to consider the Provincial government s energy objectives in deciding whether or not to issue a CPCN. Objective (d) in the definition of government s energy objectives is to encourage public utilities to develop adequate energy transmission infrastructure. Vancouver City Central Transmission Project CPCN Application -a Revised - September 00 - Revised October

9 Project Description PROJECT DESCRIPTIONS In Section, the need for development of the transmission system in the Mount Pleasant and central Vancouver area is described. In Section, alternative solutions are evaluated and a preferred solution, the VCCT Project, is identified. The purpose of this section is to describe the preferred solution, the VCCT Project, as proposed by BCTC.. VCCT Project Components and Infrastructure The proposed VCCT Project is comprised of an indoor substation and two underground 0 kv transmission circuits. The transmission circuits would provide supply to the proposed substation from the existing Sperling and Cathedral Square Substations in the City of Vancouver. As noted in Section, BCTC is seeking approval of the transmission components of the VCCT Project through this Application. The associated Substation Distribution Assets (SDA) that would be constructed in conjunction with the transmission infrastructure are described for context in Section. (Related Projects)., however, no approval of the SDA portion of the project is sought in this Application. BCTC is aware that the Commission has expressed concern about the practice of seeking separate approvals of Transmission and SDA components within related projects. In its recent F00/0 BCTC Capital Plan Decision, issued July, 00, the Commission has directed BCTC to work with BC Hydro to either accept its proposal to have either BCTC or BC Hydro seek regulatory approval for the entirety of a combined transmission/sda project, or develop an alternative resolution to the problem. In its Decision, the Commission directed BCTC and BC Hydro to provide its report within 0 days from the date of Decision, which would fall on or about October,, 00. Given that timing, BCTC would update the Application, if required, once that Report has been filed and upon acceptance of the recommendations made in it or further directions by the Commission. The transmission components of the VCCT Project are comprised of; Directive, page of July, 00 Decision pertaining to the F00/0 Transmission System Capital Plan Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

10 Project Description (a). km of 0 kv underground transmission circuits, duct banks and associated manholes connecting the proposed Mount Pleasant Substation to the existing Cathedral Square Substation; (b). km of 0 kv underground transmission circuits, duct banks and associated manholes connecting the proposed Mount Pleasant Substation to the existing Sperling Substation; (c) transmission terminations and associated 0 kv Gas Insulated Switchgear at Sperling Substation; 0 (d) transmission terminations and associated 0 kv Gas Insulated Switchgear at Cathedral Square Substation; (e) a new substation building together with transmission terminations and associated 0 kv Gas Insulated Switchgear; and (f) facilities in common between the transmission facilities and SDA facilities within the substation, which are considered transmission facilities under the SDA Asset Management Service Agreement between BCTC and BC Hydro. 0 The VCCT Substation Distribution Assets are described in Section. below... Substation The purpose of a distribution substation is to receive electricity at transmission voltage and transform the electricity to distribution voltage which can then be supplied to customers through distribution feeders. The proposed substation would be housed in a new building occupying a 0,000 square foot site at the corner of Alberta Street and West th Avenue in the City of Vancouver. BC Hydro has acquired property totaling,000 square feet. BC Hydro is in negotiations to acquire one additional lot of,000 square feet. The building would consist of one below ground level and two above ground levels which would house both transmission assets and SDA. A conceptual design layout of the substation and artists rendering of the building is provided in Appendix I and Appendix J respectively. The methods of construction, and accordingly the expected impacts on Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

11 Project Description the public from construction, of the substation building would be similar to conventional construction of any light industrial building. Vancouver City Central Transmission Project CPCN Application -a Revised - September 00 - Revised October

12 Project Description 0 The conceptual design of the proposed Mount Pleasant Substation contemplates a staged development of the substation with transmission equipment and SDA installed over time as the electrical loads which are served by the substation increase. The equipment to be included in the initial (F0) stage, which would provide MVA of distribution feeder capacity, is shown in Table -. Subsequent stages are shown in Table -, with conversion to kv when appropriate which would raise the ultimate distribution feeder capacity of the substation to 00 MVA. This Application concerns the transmission VCCT Project assets for the initial F0 stage. Subsequent stages would be included in future BCTC Transmission System Capital Plans, as appropriate, when loads and transmission needs justify these stages. Table -. Mount Pleasant Equipment Staging (Initial Stage) Equipment Description 0/ kv, MVA step-down transformer (LV winding reconnectable to kv) 0 kv GIS position ( transformers, transmission cables) kv, MVA GIS feeder section Quantity Table -. Mount Pleasant Equipment Staging (Stages Two - Six) Stage Equipment Description Station Capacity Two Add rd kv, MVA feeder section 00 MVA 00 Three Add rd 0 kv transformer Add rd 0 kv cable termination Add th and th 0 kv GIS positions Add th kv, MVA feeder section MVA 0 Four Add th kv, MVA feeder section MVA n/a Five Add th 0 kv cable termination Add th 0 kv GIS position MVA n/a Six Add th kv, MVA feeder section 00 MVA n/a Approx.Year The substation transmission facilities, including the building itself, are comprised of the following: Beyond 0-year planning horizon. Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

13 Project Description (a) a below grade cable tunnel through which the 0 kv transmission cables would enter the building; 0 (b) a 0 kv Gas Insulated Switchgear (GIS) hall located on the ground floor. This hall would house the 0 kv GIS to which the 0 kv transmission cables would terminate. Gas insulated switchgear is necessary rather than air insulated switchgear because of space constraints present for indoor substations that would generally not be present in an outdoor substation. At the initial stage of the substation development, the 0 kv GIS would include four positions; one each for the termination of the two 0 kv transmission circuits and one each for two transformers (SDA equipment). The substation conceptual design contemplates future addition of up to three more positions to allow for future termination of two additional 0 kv circuits and one additional transformer; (c) also on the ground floor would be a lay down area accessible from the rear of the building, a battery room, and station service rooms; and (d) on the second floor would be the mechanical room which would house the HVAC equipment and the control room which would house telecommunication and protection and control equipment. 0 The remainder of the bays/rooms of the substation would contain SDA equipment,. the approval of which is not the subject of this Application. The SDA equipment would include low voltage switchgear and current-limiting feeder reactors on the main level and basement level. At ground level SDA equipment would include 0 kv step-down transformers housed within transformer bays enclosed within concrete walls. The transformer bays were designed to provide the appearance that it is part of the entire enclosed substation building, while in fact being open to the air for ventilation purposes. On the second level would be a room for future installation of capacitor banks which would become necessary in subsequent stages of substation development as the load served by the substation increases. The transformers would be capable of stepping down the voltage from 0 kv to either. kv or kv depending on how the low voltage side of the transformers was connected. Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

14 . Project Cost Project Description 0 0 In Section, BCTC described the potential solutions based on a planning level estimate of -0%/+00%. Once the preferred solution, the VCCT Project, was identified BCTC refined the forecast accuracy to -%/+0%. The forecast project cost for the transmission assets for the VCCT Project is $ million. A further $ million would be incurred for SDA (which are not the subject of this Application). The total VCCT Project cost including both transmission assets and SDA is estimated to be $0 million, based on a -%/+0% forecast accuracy. The cost estimate considers all aspects of the VCCT Project including, consultation with public stakeholders and First Nations, regulatory, engineering, procurement, property acquisition, construction, environmental monitoring and mitigation, commissioning costs, BCTC corporate overhead, inflation and interest during construction (IDC). This cost estimate includes the cost for two transmission circuits, circuit terminations at Sperling, Cathedral Square and the proposed Mount Pleasant Substation, the Mount Pleasant substation building and the substation equipment installed in the first stage (F0) of substation development. Approximately % of the project cost is for the transmission facilities which are the subject of this application with the remainder for Substation Distribution Assets. A breakdown of the project costs is shown in Table -. Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

15 Project Description. Related ProjectsThe VCCT Substation Distribution Assets and Related Distribution System Development As discussed above, the installation of the SDA components of the ProjectVCCT Substation Distribution Assets are considered to be a related project that would take place simultaneously and in conjunction with the construction of the rest of the VCCT Project. The SDA Substation Distribution Assets are project is forecast to cost $. million and consists of the SDA equipment that would be installed in the Mount Pleasant Substation. The significant SDA equipment for this SDA project equipment includes: 0 (a) two 0/ kv, MVA (LV winding reconnectable to kv) step-down transformers; and (b) two kv, MVA GIS feeder sections. In addition, concurrent with and following the VCCT Project is, BC Hydro would construct distribution feeder duct banks in the city streets to house the distribution feeders which originate at Mount Pleasant Substation and begin to transfer Mount Pleasant/South False Creek load currently served by Murrin, Sperling and Mainwaring Substation to the new Mount Pleasant Substation. Vancouver City Central Transmission Project CPCN Application - Revised - September 00 - Revised October

16 Appendix A Draft Orders

17 WHEREAS: IN THE MATTER OF the Utilities Commission Act, R.S.B.C., Chapter and An Application by British Columbia Transmission Corporation for a Certificate of Public Convenience and Necessity for the Vancouver City Central Transmission Project BEFORE: (Panel members) Month XX, 00 O R D E R A. On September, 00, the British Columbia Transmission Corporation ("BCTC") applied (the Application ) to the British Columbia Utilities Commission (the Commission ) for a Certificate of Public Convenience and Necessity ( CPCN ) to construct and operate the Vancouver City Central Transmission Project (the VCCT Project) as described in this Application; and B. BCTC is proposing the VCCT Project as the preferred solution to: i) serve load growth in the Mount Pleasant/South False Creek area, ii) resolve reliability concerns associated with the end of life condition of the Main Street distribution duct banks being used to serve the Mount Pleasant/South False Creek area, and iii) resolve reliability concerns in view of the zero-rating of transmission circuit L.; and C. The VCCT Project has an estimated capital cost of approximately $0 million of which approximately $ million is for the VCCT Substation Distribution Assets and the remainder is for The VCCT Project excluding the Substation Distribution Assets (SDA) has an estimated capital cost of approximately $0 million, and includes the construction of a new Mount Pleasant substation and the construction of a new transmission line approximately km in length that follows the route described as Route Option B; and D. By Order No. G-xx-0, the Commission established a Written Public hearing process and Regulatory Timetable for the review of the Application; and E. The XXXX, XXX and XX intervened in the proceeding; and F. Submissions in the proceeding concluded with XXXX on XXXX xx, 00; and G. The Commission Panel has considered the Application and the evidence and submissions in the proceeding and has determined that the VCCT Project is in the public interest and that a CPCN be issued to BCTC for the VCCT Project for the reasons set out in the attached Reasons for Decision.

18 NOW THEREFORE pursuant to Sections and of the Utilities Commission Act the Commission orders as follows:. A Certificate of Public Convenience and Necessity is granted to BCTC for the entirety of the VCCT Project except the VCCT Substation Distribution Assets, all as described in the Application.. BCTC will file with the Commission quarterly progress reports on the VCCT Project schedule and costs, followed by a final report on project completion. DATED at the City of Vancouver, in the Province of British Columbia, this Month 00. day of BY ORDER Panel Chair

19 WHEREAS: IN THE MATTER OF the Utilities Commission Act, R.S.B.C., Chapter and An Application by British Columbia Transmission Corporation on behalf of British Columbia Hydro and Power Authority for a Certificate of Public Convenience and Necessity for the VCCT Substation Distribution Assets BEFORE: (Panel members) Month XX, 00 O R D E R A. On September, 00, the British Columbia Transmission Corporation ("BCTC") applied (the Application ) to the British Columbia Utilities Commission (the Commission ) for a Certificate of Public Convenience and Necessity ( CPCN ) to construct and operate the Vancouver City Central Transmission Project (the VCCT Project) as described in this Application; and B. BCTC is proposing the VCCT Project as the preferred solution to: i) serve load growth in the Mount Pleasant/South False Creek area, ii) resolve reliability concerns associated with the end of life condition of the Main Street distribution duct banks being used to serve the Mount Pleasant/South False Creek area, and iii) resolve reliability concerns in view of the zero-rating of transmission circuit L; and C. The VCCT Project has an estimated capital cost of approximately $0 million of which approximately $ million is for the VCCT Substation Distribution Assets; and D. On October. 00, BCTC amended the VCCT CPCN Application and applied to the Commission on behalf of BC Hydro and Power Authority ( BC Hydro ) for a CPCN to construct and operate the VCCT Substation Distribution Assets; and E. By Order No. G-xx-0, the Commission established a Written Public hearing process and Regulatory Timetable for the review of the Application; and F. The XXXX, XXX and XX intervened in the proceeding; and G. Submissions in the proceeding concluded with XXXX on XXXX xx, 00; and H. The Commission Panel has considered the Application and the evidence and submissions in the proceeding and has determined that construction and operation of the VCCT Substation Distribution Assets is in the public interest and that a CPCN be issued to BC Hydro for the VCCT Substation Distribution Assets for the reasons set out in the attached Reasons for Decision.

20 NOW THEREFORE pursuant to Sections and of the Utilities Commission Act the Commission orders as follows:. A Certificate of Public Convenience and Necessity is granted to BC Hydro for the construction and operation of the VCCT Substation Distribution Assets as described in the Application. DATED at the City of Vancouver, in the Province of British Columbia, this Month 00. day of BY ORDER Panel Chair

DARRYL CARTER &COMPANY Barristers & Solicitors

DARRYL CARTER &COMPANY Barristers & Solicitors Darryl Carter, a.c. (also of the California Bar) Mikle L. Carter Jennifer Wilkie DARRYL CARTER &COMPANY Barristers & Solicitors C11-1 103,10134-97 Avenue Grande Prairie, Alberta T8V7X6 Phone (780) 882-7296

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application

More information

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report.

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report. Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com November 0, 05 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

March 11, Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3

March 11, Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities Commission Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 B-1 Joanna Sofield Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com March 11, 2011 Ms. Erica M. Hamilton Commission Secretary British Columbia Utilities

More information

For further information, please contact Geoff Higgins at or by at

For further information, please contact Geoff Higgins at or by  at Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com February, 06 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth

More information

bcuc British Columbia Utilities Commission

bcuc British Columbia Utilities Commission January 26, 2018 bcuc British Columbia Utilities Commission Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

Re: FortisBC Inc. Customer Complaint Melody Farmer Boswell Power Surge and Incident Report

Re: FortisBC Inc. Customer Complaint Melody Farmer Boswell Power Surge and Incident Report LETTER NO. L 59 10 ERICA M. HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604)

More information

ENMAX Generation Portfolio Inc.

ENMAX Generation Portfolio Inc. Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. September 5, 2017 Alberta Utilities Commission Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. Proceeding 22192 Application 22192-A002 September

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project Welcome Metro North Transmission Project Vancouver Community Information Open House March 9, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,

More information

Discussion Guide. Benvoulin Substation Project.

Discussion Guide. Benvoulin Substation Project. Discussion Guide Benvoulin Substation Project A Growing Region South Central Kelowna has experienced substantial growth over the last ten years. FortisBC is enhancing the electrical power supply system

More information

The North American Electric Reliability Corporation ( NERC ) hereby submits

The North American Electric Reliability Corporation ( NERC ) hereby submits March 3, 2011 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 Re: North American Electric

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

Commission de l énergie de l Ontario NOTICE OF APPLICATION

Commission de l énergie de l Ontario NOTICE OF APPLICATION Ontario Energy Board Commission de l énergie de l Ontario EB-2007-0947 NOTICE OF APPLICATION Application by Hydro One Networks Inc. and Peterborough Distribution Inc. for Licence Amendments and Sale of

More information

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document Decision 2014-271 Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014 The Alberta Utilities Commission Decision 2014-271: Alberta Electric System Operator

More information

BC Hydro writes in compliance with Commission Order No. G-67-10, Directive 6, to provide its Report.

BC Hydro writes in compliance with Commission Order No. G-67-10, Directive 6, to provide its Report. Geoffrey Higgins Acting Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorygroup@bchydro.com May 12, 2015 Ms. Erica Hamilton Commission Secretary British Columbia Utilities

More information

UPDATES EPC Contract Signed August 2017

UPDATES EPC Contract Signed August 2017 ACO SOLAR HV BOP PROJECT NUMBER 2655 Convalt Energy LLC MOEE Myanmar Power Generation, Substation UPDATES EPC Contract Signed August 2017 Convalt Energy LLC are developing a 300MW AC solar farm in Myanmar

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities

More information

STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION

STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION In the Matter of the Application of Getty Wind Company, LLC for a Site Permit for a Large Wind Energy Conversion System in Stearns County, Minnesota In the

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY May 19, 2011 Community Meeting Metro Toronto Convention Centre North Building, Room 203B May 19 th, 2011, 4:30 p.m. to 7:30 p.m. Please sign in and complete a comment sheet Project team members are available

More information

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 13(2015)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 13(2015) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 13(2015) 1 IN THE MATTER OF the Electrical Power 2 Control Act, 1994, SNL 1994, Chapter E-5.1 (the 3

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

NOTICE OF APPLICATION AND HEARING FOR AN ELECTRICITY DISTRIBUTION RATE CHANGE Hydro One Remote Communities Inc.

NOTICE OF APPLICATION AND HEARING FOR AN ELECTRICITY DISTRIBUTION RATE CHANGE Hydro One Remote Communities Inc. Ontari o Energy Board Commission de l énergie de l Ontario EB-2008-0232 NOTICE OF APPLICATION AND HEARING FOR AN ELECTRICITY DISTRIBUTION RATE CHANGE Hydro One Remote Communities Inc. Hydro One Remote

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Vision Program Outline Georgia Institute of Technology Advanced Computing Technology Building Draft Program Vision Program Outline Issued April 2, 2001 I N T R O D U C T I O N Scope This document is a summary of the Vision Session

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting

More information

Reliance Infrastructure Limited

Reliance Infrastructure Limited Reliance Infrastructure Limited Reg. : H Block, 1 st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai 400 710 Website: www.rinfra.com PUBLIC NOTICE Objections / suggestions on Reliance Infrastructure

More information

EU DONOR FUNDED SMART GRID PROGRAMME

EU DONOR FUNDED SMART GRID PROGRAMME EU DONOR FUNDED SMART GRID PROGRAMME 1 Historical Background Msunduzi Local Municipality is a local municipality in Umgungundlovu District Municipality, KwaZulu-Natal, South Africa. It encompasses the

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

MFC Power General Partner Ltd.,

MFC Power General Partner Ltd., Decision 21950-D01-2016 Preferential Sharing of Records Between, MFC Power Limited Partnership, URICA Energy Real Time Ltd., and URICA Asset Optimization Ltd. October 12, 2016 Alberta Utilities Commission

More information

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities

FLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012 Item 23, Report No. 33, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan

More information

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17 Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11

More information

License Agreement with Rogers Communications Partnership for Use of Road Allowances

License Agreement with Rogers Communications Partnership for Use of Road Allowances CORPORATE REPORT NO: R160 COUNCIL DATE: SEPTEMBER 29, 2014 REGULAR COUNCIL TO: Mayor & Council DATE: September 23, 2014 FROM: Deputy City Engineer FILE: 5450-30 (Rogers) SUBJECT: License Agreement with

More information

Click on the links below to learn more about what we have been working on to serve you better.

Click on the links below to learn more about what we have been working on to serve you better. Click on the links below to learn more about what we have been working on to serve you better. Delivering value: Asset optimization and value engineering Maintaining reliability through security AltaLink's

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

BC OnLine. Site Registry User s Guide. Last Updated June 11, 2014

BC OnLine. Site Registry User s Guide. Last Updated June 11, 2014 BC OnLine Site Registry User s Guide Last Updated June 11, 2014 Copyright Copyright 2014 Province of British Columbia. All rights reserved. This user s guide is for users of the BC OnLine services who

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of December 12, 2015 DATE: December 1, 2015 SUBJECT: SP-84-U-15-1 USE PERMIT ASSOCIATED WITH A SITE PLAN for a telecommunications facility; located

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

Progress Report on the GCC Electricity Grid Interconnection in the Middle East

Progress Report on the GCC Electricity Grid Interconnection in the Middle East GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Progress Report on the GCC Electricity Grid Interconnection in the Middle East by: Adnan Al-Mohaisen, GM, GCCIA Luc Chausse, Project Director, SNC-Lavalin

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Vancouver Terminal Grain Storage Project. Feedback Form Inside. Community Engagement. October 1 19, 2012 PROJECT OV ERVIE W

Vancouver Terminal Grain Storage Project. Feedback Form Inside. Community Engagement. October 1 19, 2012 PROJECT OV ERVIE W Feedback Form Inside Vancouver Terminal Grain Storage Project Community Engagement October 1 19, 2012 PROJECT OV ERVIE W www.richardson.ca/news/vancouver-grain-terminal RICHARDSON INTERNATIONAL LIMITED

More information

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES P AGE 129 A-1 A-2 A-3 A-4 A-5 A-6 A-7 A-8 A-8 A-9 B-1 B-2 B-3 B-4 B-6 B-5 March 24, 2015 Scott Johnson Community

More information

City Hall Space Selection 15 Market Square. November 27, 2017

City Hall Space Selection 15 Market Square. November 27, 2017 City Hall Space Selection 15 Market Square November 27, 2017 Future City Hall Space Recommendation Recommendation Committee of the Whole recommends that Common Council approve the Offer to Amending Existing

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

Cereal Hudson. Tariffs. Anthony S. Campagiorni, Esq. Vice President, Regulatory & Governmental Affairs. Requested Revenue Increases

Cereal Hudson. Tariffs. Anthony S. Campagiorni, Esq. Vice President, Regulatory & Governmental Affairs. Requested Revenue Increases 1 Anthony S. Campagiorni, Esq. Vice President, Regulatory & Governmental Affairs P Power. Possibilities Cereal Hudson A FORTIS COMPANY July 28, 2017 Via Electronic Filing By Hand Honorable Kathleen Burgess,

More information

Content Copy Of Original

Content Copy Of Original Content Copy Of Original Ministry of the Environment and Climate Change Ministère de l Environnement et de l Action en matière de changement climatique Hydro One Networks Inc. 483 Bay St 14th Floor, South

More information

February 10, Via . Fiona McDougall Planner Development Services 8645 Stave Lake St Box 20 Mission, BC V2V 4L9. Dear Ms.

February 10, Via  . Fiona McDougall Planner Development Services 8645 Stave Lake St Box 20 Mission, BC V2V 4L9. Dear Ms. Cypress Land Services Telephone: 604.620.0877 Suite 120 736 Granville Street Facsimile: 604.620.0876 Vancouver, BC V6Z 1G3 Website : www.cypresslandservices.com V6Z 1G3 February 10, 2016 Fiona McDougall

More information

Physical Security Reliability Standard Implementation

Physical Security Reliability Standard Implementation Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,

More information

Approval of Navy Yard Chiller Joint Development Agreement

Approval of Navy Yard Chiller Joint Development Agreement Planning, Program Development and Real Estate Committee Item V B July 9, 2015 Approval of Navy Yard Chiller Joint Development Agreement Washington Metropolitan Area Transit Authority Board Action/Information

More information

HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION. Presentation to ANC 3E April 13, 2017

HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION. Presentation to ANC 3E April 13, 2017 HARRISON STREET SUBSTATION UPGRADE AND MODERNIZATION Presentation to ANC 3E April 13, 2017 1 PURPOSE AND NEED We are committed to providing reliable electric service to our customers. As part of this commitment,

More information

RE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line

RE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line Dominion Energy P.O. Box 26666, Richmond, VA 23261 DominionEnergy.com David J. DePippo Senior Counsel Direct: (804) 819-2411 Facsimile: (804) 819-2183 david.j.depippo@dominionenergy.com Via Email Ms. Anna

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E For a Permit to Construct Electrical Facilities With Voltages

More information

SHARED SERVICES COSTS

SHARED SERVICES COSTS SHARED SERVICES COSTS Page 1 of 15 TABLE OF CONTENTS 1. 2005-2007 SUMMARY...4 2. THE TRANSMISSION PROVIDER S MAIN SUPPLIERS...6 2.1 Technology Group...8 2.2 Shared Services Centre...10 2.3 Corporate Units...12

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information

DESCRIPTION OF COST ALLOCATION METHODOLOGY

DESCRIPTION OF COST ALLOCATION METHODOLOGY Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate

More information

Guidance: Operational Conditions Precedent (OCPs) September 2016 Version 1

Guidance: Operational Conditions Precedent (OCPs) September 2016 Version 1 Guidance: Operational Conditions Precedent (OCPs) September 2016 Version 1 Contents 1 Introduction 4 2 Operational Conditions Precedent requirements 4 3 Low Carbon Contracts Company Process 8 4 Supporting

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued April 23, 2015)

151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING. (Issued April 23, 2015) 151 FERC 61,066 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

Notification Form. Code of Practice for Soil Amendments

Notification Form. Code of Practice for Soil Amendments Notification Form for authorization to discharge waste under the Environmental Management Act Code of Practice for Soil Amendments FORM REFERENCE CODE: EPD-SAC-01.1 INSTRUCTIONS: The notification process

More information

Standard CIP-006-4c Cyber Security Physical Security

Standard CIP-006-4c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-4c 3. Purpose: Standard CIP-006-4c is intended to ensure the implementation of a physical security

More information

Ministry of Energy, Mines and Petroleum Resources. Guide to Acquiring Crown Petroleum and Natural Gas Tenures

Ministry of Energy, Mines and Petroleum Resources. Guide to Acquiring Crown Petroleum and Natural Gas Tenures Ministry of Energy, Mines and Petroleum Resources Guide to Acquiring Crown Petroleum and Natural Gas Tenures March 2018 1 Summary of Revisions Effective date Section Description March 2018 Reconfigured

More information

Community Design Guidelines Document (CDG)

Community Design Guidelines Document (CDG) Terms of Reference Community Design Guidelines Document (CDG) Block Plan Stage Supporting Document Required Created through the 2009 City of Brampton/BILD Development Process Review Project Revised Community

More information

Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements

Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Manual: Distribution Substation Manual (DSM) Section 1: Customer Supply Arrangements Standard Number: HPC-5DA-07-0001-2012 Document Control Author Name: Viswa Easwaran Position: Standards Engineer Document

More information

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008

Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick

More information

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx

12 Approval of a New PRESTO Agreement Between York Region and Metrolinx Clause 12 in Report No. 7 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on April 20, 2017. 12 Approval of a New PRESTO

More information

Reston Town Center North Development. Community Update

Reston Town Center North Development. Community Update Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ]

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] DATE: April 8, 2013 REPORT NO. CD2013-040 TO: FROM: Chair and Members Committee of the Whole Community Services Gregory Dworak, General Manager Community Services 1.0 TYPE OF REPORT CONSENT ITEM [ ] ITEM

More information

Cyber Security Reliability Standards CIP V5 Transition Guidance:

Cyber Security Reliability Standards CIP V5 Transition Guidance: Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible

More information

RESOLUTION NO. 14-R-

RESOLUTION NO. 14-R- RESOLUTION NO. 14-R- A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF MARION COUNTY, FLORIDA DIRECTING AND AUTHORIZING THE ACQUISITION OF SUBSTANTIALLY ALL OF THE REAL AND PERSONAL PROPERTY COMPRISING

More information

BOARD OF TRUSTEES THE CITY UNIVERSITY OF NEW YORK

BOARD OF TRUSTEES THE CITY UNIVERSITY OF NEW YORK BOARD OF TRUSTEES THE CITY UNIVERSITY OF NEW YORK COMMITTEE ON FACILITIES PLANNING AND MANAGEMENT AGENDA FOR MEETING November 19, 2018 I. ACTION ITEMS: A. Approval of the Minutes of the meeting of October

More information

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY POLICY P-22 TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY Preamble It is recognized that while reliable and sophisticated telecommunication facilities are a benefit to the citizens of (CSRD),

More information

E-HOUSE AND PREFABRICATED SUBSTATION SPECIALISTS COMPANY PROFILE. tgood.com. Energy. Fast.

E-HOUSE AND PREFABRICATED SUBSTATION SPECIALISTS COMPANY PROFILE. tgood.com. Energy. Fast. E-HOUSE AND PREFABRICATED SUBSTATION SPECIALISTS COMPANY PROFILE tgood.com Energy. Fast. Global leader in E-House and prefabricated substation solutions with the fastest assembly, delivery and installation

More information

User Guide. March 2017

User Guide. March 2017 User Guide March 2017 Alberta Utilities Commission efiling System User Guide Fifth Avenue Place Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Phone: 403-592-4500 Email: info@auc.ab.ca www.auc.ab.ca

More information

TRANSIT CENTER DISTRICT PLAN

TRANSIT CENTER DISTRICT PLAN TRANSIT CENTER DISTRICT PLAN Informational Presentation Planning Commission 04.19.2012 San Francisco Planning Department In partnership with: San Francisco Redevelopment Agency Transbay Joint Powers Authority

More information

NOTICE OF APPLICATION AND WRITTEN HEARING

NOTICE OF APPLICATION AND WRITTEN HEARING Ontario Energy Board Commission de l énergie de l Ontario EB-2012-0305 NOTICE OF APPLICATION AND WRITTEN HEARING Application by Hydro One Networks Inc. and Kitchener-Wilmot Hydro Inc. for Licence Amendments

More information

S T A F F R E P O R T

S T A F F R E P O R T S T A F F R E P O R T Meeting Date: 04 Jul 2017 To: Prepared By: Reviewed/Approved By: Department Report No: Subject: Corporate Strategic Plan: Mayor and Members of Council Lynn Phillips Tim Blake, Valerie

More information

SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS

SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS SECTION 5 -- EQUIPMENT LAYOUT & EQUIPMENT ENVIRONMENTS CONTENTS PAGE 1. GENERAL... 5-1 1.1. Introduction... 5-1 1.2. Equipment Layout Requirements... 5-1 2. EQUIPMENT FRAMES... 5-2 2.1. Introduction...

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Cerritos

More information

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended

Figure 1: Summary Status of Actions Recommended in June 2016 Committee Report. Status of Actions Recommended # of Actions Recommended Chapter 3 Section 3.05 Metrolinx Regional Transportation Planning Standing Committee on Public Accounts Follow-Up on Section 4.08, 2014 Annual Report In November 2015, the Standing Committee on Public

More information

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network Tasmanian Networks Pty Ltd ABN 24 167 357 299 Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network (AS4777 Compliant) NG R PD 09 Version 2.0 July 2014 TABLE

More information

Standard CIP-006-3c Cyber Security Physical Security

Standard CIP-006-3c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-3c 3. Purpose: Standard CIP-006-3 is intended to ensure the implementation of a physical security

More information

KEEPING YOU OUT IN FRONT

KEEPING YOU OUT IN FRONT URBACON DATA CENTRE SOLUTIONS KEEPING YOU OUT IN FRONT A next generation data centre in the core of downtown Toronto DOWNTOWN DATA CENTRE 281 FRONT STREET TORONTO, ON 1 2 X URBACON BUILDING GROUP 70 Lake

More information

MESP MODULAR SUBSTATION USER REQUIREMENTS

MESP MODULAR SUBSTATION USER REQUIREMENTS Engineering Specification Electrical Networks MODULAR SUBSTATION USER Version: 2 Issued: November 2015 Owner: Head of Engineering/Electrical Approved By: Head of Engineering/Electrical PRINTOUT MAY NOT

More information

PREFABRICATED SUBSTATIONS AND E-HOUSES. tgood.com. Energy, Fast!

PREFABRICATED SUBSTATIONS AND E-HOUSES. tgood.com. Energy, Fast! PREFABRICATED SUBSTATIONS AND E-HOUSES tgood.com Energy, Fast! Global leader in prefabricated substations and E-House systems PRODUCT OVERVIEW Fully integrated prefabricated substations and E-House systems.

More information

August 10, Sacramento County Planning and Community Development 827-7th Street Sacramento, CA Tricia Stevens, Principal Planner

August 10, Sacramento County Planning and Community Development 827-7th Street Sacramento, CA Tricia Stevens, Principal Planner August 10, 2010 Sacramento County Planning and Community Development 827-7th Street Sacramento, CA 95814 Attn: RE: Tricia Stevens, Principal Planner Conditional Use Permit Application Material / Justification

More information

Remote Real-Time Measurements of Voltage, Current and Energy

Remote Real-Time Measurements of Voltage, Current and Energy Remote Real-Time Measurements of Voltage, Current and Energy Chris Yakymyshyn Pam Hamilton Michael Brubaker yakymyshyn@fieldmetricsinc.com 727-319-0299 Slide 1 Outline Introduction FieldMetrics (FMI) Products

More information

Reliability & Resiliency in the US Capitol Region/Hardening the Grid One Year after Hurricane Sandy

Reliability & Resiliency in the US Capitol Region/Hardening the Grid One Year after Hurricane Sandy 1 Reliability & Resiliency in the US Capitol Region/Hardening the Grid One Year after Hurricane Sandy 2 Pepco D.C. Distribution System 260,000 Customers 175,000 Customers Supplied by Underground System

More information

March 4, 2011 VIA ELECTRONIC FILING

March 4, 2011 VIA ELECTRONIC FILING March 4, 2011 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: North American Electric Reliability Corporation,

More information