ISC(JNMC)(2016)132. Fibre Network - Connecting Cambridgeshire
|
|
- Osborn Carr
- 5 years ago
- Views:
Transcription
1 ISC(JNMC)(2016)132 Fibre Network - Connecting Cambridgeshire Project proposal to connect AstraZeneca locations to the existing University of Cambridge fibre optic network JH/RPC 17/03/2016
2 1. Project outline An exploratory piece of work to evaluate the opportunity to connect AstraZeneca s various Cambridgeshire based facilities to the existing GBN (Granta Backbone Network), to enable the fast and transparent transfer of data between AstraZeneca sites, collaborating institutions and access to national and international network resources via Janet. AstraZeneca have provided a number of locations that they would wish to be connected via the University fibre optic network (specifications detailed later in this document). The proposed extensions are based upon the following presumptions: (a) All sites will be connected via a physically diverse ring for resilience purposes. (b) Costs provided are indicative at this stage. Dependent upon urgency of connectivity, prices may vary to include additional contract labour to assist in implementation. Conversely, if extensions to the network (specifically the Milton Road Science Park) can be aligned with proposed City Council redevelopment, implementation costs would reduce. (c) All prices are excluding VAT. (d) The costs are broken down into four discrete projects, each of which may be permitted in isolation. Page 2 of 9
3 2. Central Cambridge locations (a) Hills Road location to the existing GBN network on the guided busway (b) Cancer Research UK (CBC) is already connected to the GBN (c) Implementing the connection of the AstraZeneca building (CBC) to the existing GBN fibre From To Distance Price p/m Ancillary Total Hills Rd Hills Rd 790m 100 None 79,000 CRUK AstraZeneca (CBC) - - None - CBC AstraZeneca (CBC) - - 5,000 5,000 84,000 See appendix Cambridge Science Park (Milton Road) (a) AstraZeneca, Cambridge Science Park, Milton Road From To Distance Price p/m Ancillary Total Chesterton Rd Milton 3,370m 120 None 404,000 Science Park Histon Rd Milton Science Park 4,130m 120 None 495, ,600 See appendix 2. Page 3 of 9
4 4. Connecting the long-term southern Cambridgeshire sites Extending the existing network to the following sites: (a) AstraZeneca, Babraham Institute (b) AstraZeneca, Granta Park (c) Wellcome Genome Campus (Hinxton) From To Distance Price p/m Ancillary Total CBC Babraham 6,130m 65 None 398,450 Institute Babraham Granta Park 3,720m 65 SED - 100k 341,800 Institute Granta Park Wellcome 7,390m 65 None 480,350 Genome Campus Wellcome Genome Campus Cambridge 14,290m 90 SED - 150k 1,436,100 2,656,700 See appendix Connecting all of the southern Cambridgeshire sites Extending the existing network to the following sites: (a) AstraZeneca, Babraham Institute (b) AstraZeneca, Granta Park (c) Wellcome Genome Campus (Hinxton) (d) AstraZeneca, Melbourn Science Park (e) AstraZeneca, Chesterford Research Park From To Distance Price p/m Ancillary Total CBC Babraham 6,130m 65 None 398,450 Institute Babraham Granta Park 3,720m 65 SED - 100k 341,800 Institute Granta Park Gt 9,270m 65 None 602,550 Chesterford Gt Chesterford Wellcome 6,420m 65 None 417,300 Genome Campus Wellcome Melbourn 15,690m 65 SED - 150k 1,169,850 Genome Campus Melbourn Cambridge 16,200m 65 SED - 150k 1,203,000 4,132,950 See appendix 4. Page 4 of 9
5 6. Existing connected sites available to GBN customers Connection to the GBN will not only provide direct fibre connectivity between those locations, but also to the existing GBN customers and partners. In total there are over 180 discrete organisations, departments and Colleges that connect to the GBN, of which we would anticipate the following being a list of parties that we believe AstraZeneca may wish to collaborate with: (a) Janet and Janet services ( (b) GEANT via Janet ( (c) Cambridge Biomedical Campus (i) MRC Laboratory of Molecular Biology (ii) CRUK (iii) School of Clinical Medicine (UoC) (iv) Cambridge Institute of Medical Research (v) Addenbrooke s Hospital (NHS) (vi) Cambridge Institute of Public Health (vii) Institute of Metabolic Science (NHS & UoC) (d) Tennis Court Road/Downing Site (Cambridge) (i) School of Biological Sciences (UoC) (ii) The Gurdon Institute (Wellcome Trust, CRUK, UoC) (iii) Cambridge Systems Biology Centre (UoC) (e) West Cambridge Data Centre (UoC) (f) MRC Cognition and Brain Sciences Unit 7. GBN Specification Subject to negotiation, the GBN installs standard telecommunications specification: (a) 90mm ducting (not shared with BT or Virgin Media) (b) Minimum of 144 core (72 pair) OS2 steel taped armoured fibre (c) Presentation within locations as per customer specification i.e. FC/UPC, LC/UPC etc. (d) Dark fibres can be provided either between AstraZeneca sites or between AstraZeneca and another customer on the GBN. (e) Whilst lit circuits for routed data traffic is monitored for service availability, dark fibre is not visible to the Network service department and service monitoring would need to be performed in collaboration with the customers. 8. Capital and operational expenditure The GBN is an asset owned by the Collegiate University. The operation and expansion of this network is self-funding but not for profit. It would be anticipated that the GBN would recover the costs of extension over a reasonable period of time, although whether this is through a capital implementation charge or recurrent operational (lease) charges is open to negotiation. All proceeds from the GBN are re-invested into the service to either extend its reach or improve resilience. Page 5 of 9
6 9. Appendixes Appendix 1 - Central Cambridge locations Page 6 of 9
7 Appendix 2 - Cambridge Science Park (Milton Road) Page 7 of 9
8 Appendix 3 - Connecting the long-term southern Cambridgeshire sites Page 8 of 9
9 Appendix 4 - Connecting all of the southern Cambridgeshire sites Page 9 of 9
INTRODUCTION OUR SERVICES
INTRODUCTION OUR SERVICES Conduct aims to revolutionise the South African telecommunications market by building a trusted, open-access, optical network in the last mile. We deploy carrier neutral, dark
More informationOracle Database 12c at Wellcome Trust Sanger Institute (WTSI)
Oracle Database 12c at Wellcome Trust Sanger Institute (WTSI) Oracle Open World - 2013 Kalyan Kallepally Principal Database Administrator About Me Working as Principal Database Administrator at Wellcome
More informationTHE REGIONAL MUNICIPALITY OF YORK
THE REGIONAL MUNICIPALITY OF YORK Committee of the Whole Report of the Executive Director, Corporate and Strategic Planning ECONOMIC DEVELOPMENT ACTION PLAN UPDATE - YORK REGION BROADBAND STRATEGY PROGRESS
More informationNORTH WEST Super-fast Broadband Strategy Condition 21 November 2012
NORTH WEST Super-fast Broadband Strategy Condition 21 November 2012 November 2012 North West Cambridge Development Site Wide Strategy Superfast Broadband Site Wide Strategy for Superfast Broadband Contents
More information... u. Clear. Creative. Communications. Gamma Results 2017
- - -,.:, : ::=-: amma... u Clear. Creative. Communications. Gamma Results 2017 Gamma is a rapidly growing technology based provider of advanced communication services to the UK business market A UK based
More informationGigabit West Sussex. Report to Cabinet. Executive Summary. Recommendations. Reasons for Recommendations. Background Papers
Report to Cabinet 21 st September 2017 By the Cabinet Member for Finance & Assets DECISION REQUIRED Not Exempt Gigabit West Sussex Executive Summary This report explains the reasons why the Council should
More informationMcClelland Report. John McClelland CBE, June 2011
McClelland Report 2 The public sector is lagging where it should be and there is an opportunity to capture a multiplicity of benefits in radically changing how ICT is adopted and deployed and in how it
More informationSMART. Investing in urban innovation
SMART Investing in urban innovation What Smart Belfast? Belfast has ambitious plans for the future. Building on our economic revival, we want to make our city an outstanding place to live, work and invest.
More informationRepowering Downtown Austin
Repowering Downtown Austin Downtown Then and Now Downtown Skyline 2000 Downtown Skyline in 2018 2 Downtown Customers Residential Customers 15,000 - Population of Downtown Residents 946 - Condo Units Under
More informationDATA CENTRE & COLOCATION
DATA CENTRE & COLOCATION RISING DEMAND FOR HOSTED SERVICES When it comes to hosted IT infrastructure, organisations are looking for highly resilient, highly available and highly scalable facilities at
More informationBT CNSP - new solutions for health and social care
BT CNSP - new solutions for health and social care The Health and Social Care Network (HSCN) will provide a reliable and efficient way for health and social care organisations to access and exchange information.
More informationCambridge South East Transport Study: Summary Report of Consultation Findings
Produced by the Cambridgeshire Research Group Cambridge South East Transport Study: Summary Report of Consultation Findings Version May Cambridgeshire Research Group is the brand name for Cambridgeshire
More informationGÉANT IP Service Description. High Performance IP Services to Support Advanced Research
GÉANT IP Service Description High Performance IP Services to Support Advanced Research Issue Date: 1 November 2017 GÉANT IP Overview The GÉANT IP service provides high-bandwidth, international Internet
More informationThe Cambridge Bio-Medical-Cloud An OpenStack platform for medical analytics and biomedical research
The Cambridge Bio-Medical-Cloud An OpenStack platform for medical analytics and biomedical research Dr Paul Calleja Director of Research Computing University of Cambridge Global leader in science & technology
More informationBLACKSBURG. electronic village. Community Network Development Guidelines. Technical Report April, An outreach effort of
BLACKSBURG electronic village Community Network Development Guidelines Technical Report 2001-01 April, 2001 An outreach effort of A university putting knowledge to work For more information, contact: Dr.
More informationGuelph Police Service
Guelph Police Service The Guelph Police Service provides policing services to the City of Guelph and has an authorized complement of 196.5 police officers and 89.42 civilians. We serve our community by
More informationDemand Aggregation. For Attracting a Private Partner or Cost Justifying Your Own Fiber Build. BBC Summit - Austin, TX - April 6, 2014
Demand Aggregation For Attracting a Private Partner or Cost Justifying Your Own Fiber Build BBC Summit - Austin, TX - April 6, 2014 1 Your Panel Mike Smeltzer Urbana-Champaign Big Broadband - UC2B University
More information/ Lot 1 Standard Service Offer Data Access Services Service Offer RM1045-L1-SSO Pinacl
/ Lot 1 Standard Service Offer Data Access Services Service Offer RM1045-L1-SSO-00002-Pinacl Standard Service Offer - Connectivity MPLS with Cloud Service Provider Connectivity MPLS (Multiprotocol Label
More informationFlexible HPC for Bio-informatics. Peter Clapham
Flexible HPC for Bio-informatics Peter Clapham Overview Overview of the Sanger Institute How our data flow works today New scientific demands Private cloud deployment Transitional and future challenges
More informationDISTRICT OF MUSKOKA COUNCIL PRESENTATION RE: CONNECT TO INNOVATE HIGH SPEED FIBRE OPTIC APPLICATION
DISTRICT OF MUSKOKA COUNCIL PRESENTATION RE: CONNECT TO INNOVATE HIGH SPEED FIBRE OPTIC APPLICATION CHRIS LITSCHKO, CEO LAKELAND HOLDING LTD. (LAKELAND ENERGY/NETWORKS) March 20, 2017 OPPORTUNITY: Connect
More informationREPUBLIC OF IRAQ COMMUNICATIONS AND MEDIA COMMISSION
REPUBLIC OF IRAQ COMMUNICATIONS AND MEDIA COMMISSION CONSULTATION DOCUMENT METHODOLOGY FOR FIXED AND MOBILE BU-LRIC MODELS OCTOBER 2015 INTRODUCTION The Communications and Media Commission regulates termination
More information3. Authorize budget changes as outlined in the Financial Impacts and Budget Actions section of this report.
City Council Report To: From: Mayor and City Council City Council Meeting: March 1, 2016 Agenda Item: 3.B Jory Wolf, Chief Information Officer, Information Systems Department, Broadband Subject: Digital
More informationRequest for Information. Services, Operations, and Maintenance of City-Built Fiber Optic Network. City of Westminster
Request for Information for Services, Operations, and Maintenance of City-Built Fiber Optic Network City of Westminster Issued: April 12, 2013 1 Table of Contents I. Introduction... 3 II. Project Background...
More informationADDENDUM # 7 RFP DARK FIBER OPTIC CABLE INFRASTRUCTURE LEASE
September 25, 2013 (emailed to all proposers on this date) ADDENDUM # 7 RFP 021402 DARK FIBER OPTIC CABLE INFRASTRUCTURE LEASE Please note the following answers to questions that were asked prior to the
More informationPage 1. Agenda Item 5
Page 1 Agenda Item 5 Background The Boultham Railway Loop area was once a hive of industry. Site of Spike Island; the testing facility for the first Tank; Once the largest production facility for aircraft
More informationSYSTEMS INTEGRATORS: THREE S A CLOUD INFOPAPER
SYSTEMS INTEGRATORS: THREE S A CLOUD INFOPAPER Introduction There is one thing that people can bet their mortgages on, and that is that technology won t stand still. For Systems Integrators (SI s) whose
More informationPresentation to Tendring Business Leaders - 17 July 2017
Presentation to Tendring Business Leaders - 17 July 2017 Colchester: competing in a digital future Places have to compete Colchester has significant potential for economic growth Significant opportunity
More informationPlease find attached a presentation to be delivered this week by PIPE Networks (ASX:PWK) Managing Director Bevan Slattery.
ACN 099 104 122 17 May 2006 ASX Announcement Investor Presentation - 1 st Anniversary of IPO Please find attached a presentation to be delivered this week by PIPE Networks (ASX:PWK) Managing Director Bevan
More informationYork Telecom Network (YTN) The Possibilities Presentation to Broadband Advisory Taskforce
York Telecom Network (YTN) The Possibilities Presentation to Broadband Advisory Taskforce February 3, 2016 Name of Presentation Agenda 1. Story of YTN Recap 2. Spectrum of s Broadband Network 3. Case Studies
More information08 November Jisc s global reach. Dr Esther Wilkinson, Head of international Dr Baoyu Wang, International services manager
08 November 2017 Jisc s global reach Dr Esther Wilkinson, Head of international Dr Baoyu Wang, International services manager Overview» Jisc structure and strategy» Jisc international» Jisc network and
More informationME6 CITYSENSE BUSINESS CASE
ME6 CITYSENSE BUSINESS CASE MAP OF RUSSIAN FEDERAL DISTRICTS 8 1 4 2 5 6 7 Potential number of LED 3 luminaires in districts and their total anticipated cost () 1 Central Federal District including Moscow
More informationDEVELOPER, INVESTOR AND MANAGER OF LOGISTICS SPACE. gazeley.com
DEVELOPER, INVESTOR AND MANAGER OF LOGISTICS SPACE gazeley.com DELIVERING EXCEPTIONAL SERVICE TO A GROWING WORLD-CLASS COMMUNITY OF CUSTOMERS FOR 30 YEARS ABOUT US We are a leading developer, investor,
More informationNetwork Services BT Internet Connect
Contents 1. 2. Network Services Customer responsibilities 3. Network Services General 4. Domain Name Registration 5. Service Management Boundary 6. Defined Terms Network Services Where the Customer selects
More informationDell helps you to simplify IT
Dell helps you to simplify IT Workshops the first step Reduce desktop and data centre complexity. Improve productivity. Innovate. Dell IT Consulting Services New Edition 2010 Introduction How can you protect
More information1 Introduction Introduction to structure Explorers Organisation Explorer Mini Explorer... 7
1 Introduction... 2 1.1 Introduction to structure... 3 2 Explorers... 5 2.1 Organisation Explorer... 5 2.2 Mini Explorer... 7 2.2.1 To maintain existing data... 8 2.2.2 Amending or entering new details...
More informationHelping us all live better lives. Easier, healthier, smarter and longer.
The Biosphere Newcastle is a specialist facility tailored to the commercialisation of life sciences and innovation, research and development in the North East of England s regional and economic capital.
More informationThe safe share project John Chapman, Deputy head, information security, Jisc
John Chapman, Deputy head, information security, Jisc What: a pilot project enabling the secure exchange of data collected by Government and the NHS using an encrypted overlay over the Janet network to
More informationJLCIMT. OSCIO Broadband Initiative. 11 May 2017
JLCIMT. OSCIO Broadband Initiative 11 May 2017 A Plan to Work Together where we are today 2 Leverage economies of scale to get more for our current funding 700 sites on the planned network statewide, 585
More informationNetworks & Data Centres
Networks & Data Centres A very brief introduction ITSS Induction MT 2017 www.it.ox.ac.uk contact@it.ox.ac.uk Henryk Glogowski Head of Networks & Data Centres IT Services September 2017 (V1.1.0) Outline
More informationGÉANT Plus Service Description. High Performance Cost-effective Connectivity
GÉANT Plus Service Description High Performance Cost-effective Connectivity Issue Date: 1 November 2017 GÉANT Plus Overview The GÉANT Plus service is offered on the GÉANT network to all GÉANT National
More informationThe IBMS: 2016 and beyond
The IBMS: 2016 and beyond Ian Sturdgess IBMS President Pathology Services Manager West Hertfordshire Hospitals NHS Trust Institute of Biomedical Science The professional body for the biomedical science
More informationOPEN Networks - Future Worlds Consultation
ENA Open Networks Future Worlds Consultation OPEN Networks - Future Worlds Consultation Developing change options to facilitate energy decarbonisation, digitisation and decentralisation Executive Summary
More informationFederal Funding for Broadband Access & Adoption: New Policy, New Market Dynamics
Federal Funding for Broadband Access & Adoption: New Policy, New Market Dynamics 38th Annual PURC Conference February 3, 2011 Bridget Duff Broadband Education Consultants, LLC Introduction New Broadband
More informationTechnology Update. Tim Kidd, Executive Director Jisc Technologies 25/05/2016 Jisc Update 1
Technology Update Tim Kidd, Executive Director Jisc Technologies Tim.Kidd@jisc.ac.uk 25/05/2016 Jisc Update 1 Google Akamai 100Gbit/s BTnet Netflix 10Gbit/s AQL 3G 1Gbit/s BBC Bogons Init7 Globelynx Microsoft
More informationCalifornia s Public Libraries and CENIC: Frequently Asked Questions
Leading the Way to Tomorrow s Internet The Corporation for Education Network Initiatives in California California s Public Libraries and CENIC: Frequently Asked Questions What is CENIC? CENIC, the Corporation
More informationHuawei European Research University Partnerships. Michael Hill-King European Research Institute, Huawei
Huawei European Research University Partnerships Michael Hill-King European Research Institute, Huawei Next 20 30 Years: The World Will Become Intelligent All things Sensing All things Connected All things
More informationGÉANT Open Service Description. High Performance Interconnectivity to Support Advanced Research
GÉANT Open Service Description High Performance Interconnectivity to Support Advanced Research Issue Date: 1 November 2017 GÉANT Open Exchange Overview Facilitating collaboration has always been the cornerstone
More informationProject Summary. June 15, Local Government School District Collaboration. VoIP Telephone System (Voice over Internet Protocol)
June 15, 2005 Project Summary Local Government School District Collaboration VoIP Telephone System (Voice over Internet Protocol) Through the support and vision of City Council and the Trustees of School
More informationHABERSHAM COUNTY BOARD OF COMMISSION EXECUTIVE SUMMARY
HABERSHAM COUNTY BOARD OF COMMISSION EXECUTIVE SUMMARY SUBJECT: County Dark Fiber Expansion Project DATE: March 7, 2017 (X) RECOMMENDATION ( ) POLICY DISCUSSION BUDGET INFORMATION: ( ) STATUS REPORT ANNUAL
More informationCASE STUDY ALDER HEY CHILDREN S HOSPITAL - CCTV. Challenge. Solution. Axis Mini Domes Internal & External PTZ Zoom. Benefits.
Challenge A leader and pioneer in specialist health care for children, Alder Hey has 270 beds, 16 digitally enhanced operating theatres, treating over 270,000 children every year, covering an area of 51,000
More informationOneUConn IT Service Delivery Vision
OneUConn IT Service Delivery Vision The University s Academic Vision establishes a foundation and high expectations for excellence in research, teaching, learning, and outreach for all of UConn s campuses.
More informationHSCN Technical & Security working group
Technical & Security working group Interconnectivity Peering Blueprint DRAFT Work In Progress Marco Dellarole - Accenture Keith Smith Virgin Media London June 16, 2016 Objectives of this deck This deck
More informationGuidance is provided below as to what information each municipality should consider providing to the potential Respondents to the RFQ.
S:\SHAREDAT\Broadband\StateGig Project Key Docs\RFQ Docs 091514\RFQ Addendum instructions for munis 120114.docx Guidance is provided below as to what information each municipality should consider providing
More informationBT Locate Affordable, local, secure data centres
BT Locate Affordable, local, secure data centres We invest heavily in developing products and technologies that will provide you with the very best solutions for your company. Email clientreception@bt.com
More informationDevelopment of a National Broadband Strategy Project. Addendum No. 1 to Phase 2 report
Development of a National Broadband Strategy Project Addendum No. 1 to Phase 2 report Prepared by Setics SA ICT Consultants (Pty) Ltd Progressus Corporation For Botswana Communications Regulatory Authority
More informationThe Corporation of the City of Nelson. Fibre Update Report June 15, 2015
The Corporation of the City of Nelson Fibre Update Report June 15, 2015 1 Path to 2040 Broadband networks support the City s Path to 2040 Sustainability Strategy Principles: Prosperity (increased productivity
More informationComet modular traffic management system. Traffic Solutions
Comet modular traffic management system Traffic Solutions The scalable, modular design of the Comet system allows users to invest in a system initially addressing a particular need, whilst allowing future
More informationEUMEDCONNECT3 and European R&E Developments
EUMEDCONNECT3 and European R&E Developments David West DANTE 17 September 2012 INTERNET2 Middle SIG, Abu Dhabi The Research and Education Network for the Mediterranean Covering GEANT Other regional network
More informationOceansgate Plymouth University
Oceansgate Plymouth University Feb 2018 Patrick Hartop Head of City Deal patrick.hartop@plymouth.gov.uk Gareth Simmons Strategic Projects Director gareth.simmons@plymouth.gov.uk Why is this so important
More informationCity of Rancho Cucamonga Fiber Optic Master Plan
City of Rancho Cucamonga Fiber Optic Master Plan History January 2016: City Council authorized Magellan Advisors to perform a fiber optic feasibility study Spring 2016 to Spring 2017: Researched and evaluated:
More informationTelecom NZ Limited - List of Charges
International Leased-Circuit Services This section gives the charges for all Telecom International Private Leased Services available from New Zealand and Scott Base to other countries. All International
More informationThese Leased Lines Specific Terms and Conditions of Supply are to be read in conjunction with our General Terms and Conditions of Supply.
Leased Lines Specific Terms and Conditions 1 DEFINITIONS These Leased Lines Specific Terms and Conditions of Supply are to be read in conjunction with our General Terms and Conditions of Supply. All definitions
More informationFire Safety Awareness Training Workstation Assessment
Health and Safety Guidance Note Fire Safety Awareness Training Workstation Assessment - Guidance and Help (Ref: QMUL_HS_166) Table of Contents Fire Safety Awareness Training (QMPlus)... 3 First Time Login...
More informationOpen Exchange Policy
23-01-2014 Open Exchange Policy Date of Issue: 23 Jan 2014 Document Code: GN3PLUS13-1439-12 Authors: DANTE Product Management Description: Outlines the purpose and governance of the GÉANT Open Exchange
More informationport Ager1da March 3, 2014 TO: Honorable Mayor and City Council FROM: Department of Information Technology
Ager1da port TO: FROM: SUBJECT: Honorable Mayor and City Council Department of Information Technology AUTHORIZATION TO ENTER INTO A CONTRACT WITH ARNOLD AND WALTERS TELECOMMUNICATIONS CONSULTANTS FOR FIBER
More informationGÉANT Open Service Description. High Performance Interconnectivity to Support Advanced Research
GÉANT Open Service Description High Performance Interconnectivity to Support Advanced Research Issue Date: 20 July 2015 GÉANT Open Exchange Overview Facilitating collaboration has always been the cornerstone
More informationNetwork Disaggregation at a World Leading Internet Exchange Point (IXP) Richard Petrie LINX CTO
Network Disaggregation at a World Leading Internet Exchange Point (IXP) Richard Petrie LINX CTO What is an Internet Exchange Point (IXP) What is an Internet Exchange Point (IXP) Service Providers Content
More informationNextgen Group Overview Destination Digital-Geraldton. 16 th October 2013
Nextgen Group Overview Destination Digital-Geraldton 16 th October 2013 WHAT WE DO We transport, house and secure critical data for Australian industry and government CORE BUSINESS STRATEGY Specialised
More informationAPPLICATION FOR DARK FIBRE OPTIC SERVICE
Suite 101, 310 Ward Street, Nelson, BC V1L 5S4 Phone: (250) 352-5511 Fax: (250) 352-2131 Website: http://www.nelson.ca/ APPLICATION FOR DARK FIBRE OPTIC SERVICE FOR OFFICE USE: APPLICATION # DATE OF APPLICATION:
More informationFY 2016 Results Presentation. 29 August 2016
FY 2016 Results Presentation 29 August 2016 RIGHT INDUSTRY, RIGHT REGION INTERNATIONAL NETWORK HONG KONG LOS ANGELES INTERNATIONAL NETWORK (AS OF JUNE 2016) SINGAPORE Legend BRISBANE Metro Fibre Existing
More informationAn introduction to MPLS IPVPN. TTB PRES MPLS IPVPN DIRECT v2.indd 1 25/08/ :48
An introduction to MPLS IPVPN TTB PRES MPLS IPVPN DIRECT v2.indd 1 25/08/2016 09:48 How it works TTB PRES MPLS IPVPN DIRECT v2.indd 2 25/08/2016 09:48 Supports high volume data transfer Consolidates voice
More informationConnecting Cambridgeshire Delivering a Digital Connectivity Strategy for Cambridgeshire and Peterborough
Connecting Cambridgeshire Delivering a Digital Connectivity Strategy for Cambridgeshire and Peterborough 2018-2022 5 G W I F I P L A N S I C A C C E S S S M A R T FULL FIBRE PUBLIC ACCESS WIFI 5G PLANS
More information1 Introduction to structure Explorers Organisation Explorer Mini Explorer... 5
1 Introduction to structure...1 2 Explorers...3 2.1 Organisation Explorer... 3 2.2 Mini Explorer... 5 2.2.1 To maintain existing data... 6 2.2.2 Amending or entering new details... 6 3 Post and Position
More informationResilience Planning in San Francisco
Resilience Planning in San Francisco 2 Developed policies and infrastructure to mitigate and recover from disasters Expanded definition of resilience: Responding to disasters Systemic crises like economic
More informationA Long and Successful Public-Private Partnership. Town of Gilbert AZ and Severn Trent Services
A Long and Successful Public-Private Partnership Town of Gilbert AZ and Severn Trent Services 9 October 2012 ICMA Annual Conference Solutions Track Presented by: Patrick Banger and Martin Kane Our discussion
More informationExtract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017
Extract From Economic Development Task Force Meeting EDTF#02-17 held April 12, 2017 Agenda Item 10.1 Scheduled Business 7. Funding for The Richmond Hill Centre for High-Tech Business Development (Staff
More informationMilestone at The University of Nottingham A Case Study
Milestone at The University of Nottingham A Case Study Chris Tadman Data Centres Team Leader Information Services Aim Where we were Where we needed to be Why we went with Milestone Problems and how we
More informationNorth Carolina Research and Educa3on Network
North Carolina Research and Educa3on Network 2 What can you do with a gig @ home? Stream without buffering at least 5 high- defini3on videos (1080p) at the same 3me and s3ll have enough bandwidth to email
More information1. The site should consist of the following six pages, to be completed and ready for uploading by <date specified by tutor>:
OCR ITQ LEVEL 2 UNIT 81: WEBSITE SOFTWARE ASSESSMENT: BRADGATE PARK FITNESS PROGRAMME SCENARIO: You are employed as a member of the Web Design Team of Leicestershire County Council and regularly receive
More information4net Technologies. Fixed Voice and Data Services V
4net Technologies Fixed Voice and Data Services V1.02-1115 Fixed Voice and Data Services Every business needs network services. However, they can be a considerable overhead, often poorly managed by providers
More informationCapabilities Statement. CITEC 317 Edward Street Brisbane, QLD
Capabilities Statement CITEC 317 Edward Street Brisbane, QLD 4000 info@citec.com.au 07 3222 2555 For over 50 years we have provided technology infrastructure, business solutions and support to state government
More informationKuh-ke-nah Network and Services Page 1 - April 2005
Kuh-ke-nah Network and Services Page 1 - April 2005 The map of Canada shows the urban sites with video conferencing connections and facilities that now have Quality of Service (QoS) for their video and
More informationEMCOR UK - NETWORK SERVICES NETWORK SERVICES
NETWORK SERVICES EMCOR UK is a leader in integrated facilities management. We help our customers drive differentiation through our knowledge of network services. Making our customers lives easier CS-EMCOR-17
More informationE-rate Program Applicant Training. Eligible Services. September November Universal Service Administrative Company. All rights reserved.
E-rate Program Applicant Training Eligible Services September November 2016 Overview FY2017 Eligible Services List (ESL) Category One Broadband Voice Services Category Two Internal Connections Managed
More informationComprehensive Energy Management & Utility Master Plan
Comprehensive Energy Management & Utility Master Plan OVERVIEW University of Utah & Health Science Campus Overview Campus Transformation Value Drivers and Challenges Integrated Energy Planning Approach
More informationData Center RFP Template
Request for Proposal Data Center RFP Template 1 Table of Contents Corporate Profile 3 Building/Property 5 Data Center Space 6 Electrical Specifications 6 Cooling Specifications 7 Network Services 8 Data
More informationFleur Tariffs October 2017
Fleur Tariffs October 2017 1. Line rental Our standard line rental is 15.50 per month. However should you wish to pay 12 months upfront, you will benefit from a 10% discount so you ll pay 167.40 instead
More informationSubmission for Approval of Business Operation Plan for the Fiscal Year Ending March 31, 2015
This English text is a translation of the Japanese original. The Japanese original is authoritative. February 28, 2014 Submission for Approval of Business Operation Plan for the Fiscal Year Ending March
More informationCabinet (Resources) Panel 16 January 2018
Cabinet (Resources) Panel 16 January 2018 Report title Decision designation Cabinet member with lead responsibility Corporate Plan priority Key decision In forward plan Wards affected Accountable Director
More informationWestern Illinois University Quad Cities Facilities. Consolidated Fiscal-Year 2012 Annual Report and Fiscal-Year 2013 Planning Document
Mission statement: Western Illinois University Quad Cities Facilities Consolidated Fiscal-Year 2012 Annual Report and Fiscal-Year 2013 Planning Document Submitted by: William Brewer University Architect
More informationSTRUCTURED CABLING UK WIDE SERVICES
STRUCTURED CABLING UK WIDE SERVICES Page 1 STRUCTURED CABLING UK WIDE SERVICES Contents 4 Section 1: Cabling Overview 5 Section 2: Our Partners 6 Section 3: Innovation 7 Section 4: Managed Services 8 Section
More informationStrategic Choices for 5-digit Dialing at Harborview
Strategic Choices for 5-digit Dialing at Harborview Capital Improvement Council February 27, 2006 D. Scott Mah Assistant Vice President, C&C Service Delivery & Support Computing & Communications Current
More informationCelebrating UTSA s National Leadership. Cybersecurity and the. Biosciences. June 5, 2018
Celebrating UTSA s National Leadership Cybersecurity and the Biosciences June 5, 2018 San Antonio s National Leadership in Biomedical Research & Development San Antonio has 3,300+ MDs and PhDs and more
More informationGrid BT. The evolution toward grid services. EU Grid event, Brussels May Piet Bel Grid Action Team
Grid Computing @ BT The evolution toward grid services EU Grid event, Brussels May 31 05 Piet Bel Grid Action Team Agenda BT Why Grid? What is BT doing? Evolution of Grid Services Q & A 2 Forward-looking
More informationResearch requirements for a Future JANET
Research requirements for a Future JANET 2012/13 and beyond David Salmon - JANET(UK) 40G & 100G slides from Rob Evans JANET(UK) Copyright JNT Association 2009 MSN Cosener s 2009 1 Overview Where are we
More informationThe Engineering Department recommends that Council: 1. Receive this Corporate Report for information purposes.
Corporate NO: R038 Report COUNCIL DATE: MARCH 12, 2007 REGULAR COUNCIL TO: Mayor & Council DATE: March 8, 2007 FROM: General Manager, Engineering FILE: 5420-00 SUBJECT: Street Lighting Copper Wire Theft
More informationSIN 510 Issue 1.1 August 2016
SIN 510 Issue 1.1 August 2016 Suppliers' Information Note For The BT Network Openreach Time Division Multiplex (TDM) Backhaul Bearer Service Service & Interface Description Each SIN is the copyright of
More informationElite Construction Inc.
Elite Construction Inc. www.eliteconstructioninc.com Elite Construc 02 ction Inc. CB CONSTRUCTION 4 CONSTRUCTION Elite Construction Inc. University Avenue Courthouse Eglinton Grand Even Vaughan, Ont.-based
More informationGigabit Ethernet Wireless Backhaul and Mobile Solution for. The City of Temple, Texas. Alan DeLoera, Director of Technology City of Temple, Texas
Gigabit Ethernet Wireless Backhaul and Mobile Solution for The City of Temple, Texas Alan DeLoera, Director of Technology City of Temple, Texas Located in Central Texas 60,000 residents Area of 70 square
More informationTo be an active partner, always ready to improve by working with others
Title of Report: Prepared By: Sponsor: Action Required: Statement of Assurance/Readiness Preparedness to Major Incidents Ben Cockerill, Emergency Planning Officer Kevin O Leary, Deputy Director of Operations
More information