1 Scottish and Southern Electricity Net Who we are Our licence stipulates that we must develop and maintain an efficient, co-ordinated and economical system of electricity transmission. What is the difference between Transmission and Distribution? Other SSE Businesses Electricity Transmission is the transportation of electricity from generating plants to where it is required at centres of demand. Scottish Hydro Electric Transmission Plc (SHE Transmission) Scottish Hydro Electric Power Distribution Plc (SHEPD) Southern Electric Power Distribution (SEPD) The Electricity Transmission network, or grid, transports electricity at very high voltages through overhead wires, underground cables and subsea cables. The transmission network connects large scale generation, primarily renewables, to central and southern Scotland and the rest of Great Britain. We are part of Scottish and Southern Electricity Net, operating under licence as Scottish Hydro Electric Transmission Plc for the transmission The Electricity Distribution network is connected into the Transmission network but the voltage is lowered by transformers at electricity substations, and the power is then distributed to homes and businesses through overhead lines or underground cables. of electricity in the north of Scotland. In total we maintain about 5,000km of overhead lines and underground cables easily enough to stretch across the Atlantic from John O Groats all the way to Boston in the USA. Our network crosses some of the UK s most challenging terrain including circuits that are buried under the seabed, are located over 750m above sea level and up to 250km long. Overview of Transmission projects infrastructure Completed Under construction Potential development Advanced planning Shetland Orkney Gills Bay Dounreay Spittal Mybster The landscape and environment that contribute to the challenges we face also give the area a rich resource for renewable energy generation. There is a high demand to connect from new wind, hydro and marine generators which rely on Scottish and Southern Electricity Net to provide a physical link between the new sources of power and electricity users. Scottish and Southern Electricity Net is delivering a major programme of investment to ensure that the network is ready to meet the needs of our customers in the future. Isles Skye Mossford Beauly Lairg Fort William Dalmally Knocknagael Fort Augustus Loch Buidhe (Bonar Bridge) Denny Moray Firth Tomatin Perth Blackhillock Kintore Kincardine Peterhead Kintyre Hunterston Our responsibilities Arran As we are the only company that owns an electricity transmission network in the north of Scotland we are closely regulated by the energy regulator Ofgem. We are issued with a licence to operate and we must adhere to the terms of the licence. For this reason we operate on a very separate basis to other SSE businesses.

2 Project Overview Offshore Wind Farm Grid Connection We are the licensed owner of the electricity transmission network in the north of Scotland. Operating under license means that we have certain obligations that we must fulfil. These obligations include maintaining the existing network to ensure that the lights stay on and investing in the network to provide the infrastructure needed to allow generation developments to connect it. The transmission network gathers energy in from power stations, hydro-electric generation schemes and wind farms and carries it to areas where it is to be used. We work with the Transmission System Operator, National Grid, who is responsible for operating the transmission network across the whole of Great Britain, to make sure that power flows smoothly and reliably across our network. A request has been made to National Grid by the developer of Offshore Wind Farm to provide a connection to the transmission network. We are currently contracted to provide a connection running from the consented wind farm s onshore substation at Blackdog to the existing nearest point on the network at Dyce substation. ABERDEENSHIRE COUNCIL Kintore Dyce Offshore ABERDEEN CITY COUNCIL Location dismantling of Local Authority Boundary ( Option 3)

3 and 132 kv Steel Lattice to be re-conductored 132 kv to be dismantled Kintore to enable the Peripheral 132 kv Steel Lattice 132 kv Steel Lattice 132 kv Steel Lattice Steel Lattice line Laydown / Reproduced by Crown copy Ordn Project No: Dyce New Replacement Terminal ( 46a) Drawn by: 132 kv Steel Lattice 132 kv to be dismantled to be re-conductored 132 kv Steel Lattice 132 kv to be dismantled to be re-conductored New End Structure to replace Lattice 132 kvsteel to be dismantled to be re-conductored New End Structure to replace to 132 kv to be dismantled New End Structure replace 132 kv SteelSteel LatticeLattice to be re-conductored steel lattice tower to enable the Peripheral 132 kv Steel Lattice to be re-conductored 0 to to kv be dismantled be dismantled Crown copyright and database right 2015 all rights Laydown / Storage Area Project No: LT175 / 176 / 177 (SHEET 3 OF 3) LR /2.1.3 (Rev B) /2.1.2 (Rev B) Laydown / DrawnDyce by: LR Dyce Offshore LR /2.1.3 (Rev B) /2.1.3 (Rev B) Dyce New Replacement Terminal ( 46a) 132 kv Steel Lattice New Replacement Terminal to ( be re-conductored 46a) bstation w Replacement Terminal 132 kv to be dismantled ( 46a) End Structure to replace w Replacement TerminalNew steel lattice tower ( 46a) (SHEET 3 OF 3) Drawn by: Dyce Drawn by: OrdnanceNew Survey Licence number End EL Structure to replace Laydown/ Offshore Wind Farm Grid Connection Offshore Wind Farm Grid Connection (SHEET 3 OF 3) 132 kv to be removed StoneyhilltoWood enable the Peripheral Crown copyright and database right 2015 all rights Laydown / Crown copyright and database right 2015 all rights Ordnance Survey Licence number EL Laydown / Reproduced Storage Area by permission of Ordnance Survey on behalf of HMSO. Crown copyright and database right 2015 all rights Project No: LT175 / 176 / 177 Offshore Wind Farm Grid Connection 132 kv Laydown / Reproduced by permission of Ordnance Survey on behalf of HMSO. to enable the Peripheral Offshore Wind Farm Grid Connection Section of overhead already to enable theline THE PROPOSED DEVELOPMENT Peripheral to enable the 2 OF 3) Laydown / (SHEET Peripheral to enable the Peripheral Laydown / to enable the Peripheral 132 kv to be dismantled to enable the Peripheral 132 kv Steel Lattice to be re-conductored 132 kv Steel Lattice 132 kv to be dismantled to be re-conductored 132 kv Steel Lattice to be re-conductored ood 132 kv Steel Lattice to be re-conductored 132 kv 132 be dismantled kvto steel lattice tower132 kv to be removed New End Structure to replace to enable the 132 kv Peripheral 132 kv to enable the 132 kv to be removed Peripheral to be removed (Option 3) 132 kv Steel Lattice Crown copyright and database right 2015 all rights 132 kv New to be removed End Structure to replace No: LT175 / 176 / 177 Crown copyright and database right 2015 all rights Project Offshore Wind Farm Grid Connection New End Structur e to replace New End Structure Stoneyhill Wood Reproduced by permission of Ordnance Survey on behalf of HMSO. Laydown / Crown copyright and database right 2015 all rights Project No: LT175 / 176 / 177 to replace steel lattice tower (SHEET 1 OF 3) Stoneyhill Wood/ Offshore Wind Farm Grid Connection Laydown Storage Area Crown copyright and database all rights Projectright No:2015 LT175 / 176 / 177 Stoneyhill Wood Offshore Wind Farm Grid Connection Crown No: copyright and/database right 2015 all rights Project LT / 177 PROPOSED DEVELOPMENT Ordnance Survey Licence EL numberthe Offshore Wind Farm Grid Connection /2.1.1 (Rev B) Crown copyright and database right 2015 all rights Offshore Wind Farm Grid Connection (SHEET 2 OF 3) Crown copyright and database right 2015 all rights /2.1.2 (Rev B) Offshore Wind Farm Grid Connection Date: 26/10/2016 Drawn by: LR / 176 / 177 Crown copyright and database right 2015 all rights Project No: LT /2.1.2 (Rev B) Offshore Wind Farm Grid Connection

4 Overview of Works work for the project is due to commence in early 2017 with construction completion planned for Spring January 2017 Site mobilisation due to begin for both the cable and overhead line February 2017 Site mobilisation to commence for Dyce March 2017 start on both cable and overhead line The connection will involve: The installation of 7.6km of underground cable from Blackdog to 54 on the Dyce Stoneyhill overhead tower line, including a Horizontal Directional Drill (HDD) under the A90. Re-conductor 2km of the existing Dyce Stoneyhill overhead line. This will involve: Removal of two towers of the overhead line at Stoneyhill. Replacement of 54 with a new tower containing a End platform. Re-conductoring approximately 12km of the existing Dyce Kintore tower line between Dyce and Kintore substations. Reinforcement work within Dyce substation. The are being pursued under Permitted Development rights, meaning there are no planning consents required for the project. This will be confirmed with the relevant planning authorities prior to any work starting. The connection date we are working towards is 21 December The wind farm developer is constructing the new substation at Blackdog with associated cabling out to the wind farm. April 2017 start on Dyce April 2018 completion

5 Environmental Considerations Three route options were considered for the cable between Blackdog and Stoneyhill, with the preferred alignment shown on Board three. An Environmental Appraisal has been carried out along the preferred cable route and overhead lines between Stoneyhill and Kintore which focussed on: Ecology Landscape and Visual Archaeology Soils and Hydrology The purpose of these studies is to identify potential habitats for protected species, designated habitats and landscape areas and archaeological features. This information has been used to help refine the cable route and inform the Contractors of any constraints requiring mitigation. A small amount of commercial plantation tree felling will be required near Blackdog substation, but this will be kept to a minimum by routeing the cable along an existing firebreak. Pre-construction surveys for protected species will be undertaken prior to work starting in any area to ensure no breeding or rest sites are disturbed or destroyed. The Environmental Appraisal recommends a number of broad mitigation measures, which together with SHE Transmission s own protection plans, should ensure that the project does not pose any significant impacts or unacceptable levels of disturbance to any protected species. There are a number of scheduled monuments and listed buildings within 2.5km of the proposed, however none of them will be impacted by construction or adverse views following completion. There is also potential for unrecorded archaeological sites to be present along the cable route and care will be taken during installation to avoid disturbance or damage.

6 Feedback Thank you for taking the time to find out about our plans to connect the Community Liaison Manager Lesley Dow Offshore wind farm. The project is in the advanced development stage however we openly welcome comments and feedback to help us progress the project. If you wish to provide any feedback or comments, please either complete a feedback form or discuss your queries direct with a member of the project team. Information can also be posted out to you by our Community Liaison Manager upon request. can be submitted as follows: At the exhibition today: Complete a Comment Form and provide to a member of the project team. Online: Complete a Comment Form online by visiting the project webpage: By post: Complete a Form and post it to our Liaison Manager (details below). By Complete a Form and it to our Liaison Manager (details below). Download forms and all the information from today s event will also be available to download from the project website at: Request Information can also be posted out to you by our liaison manager upon request. Please make your comments as specific as possible in order to help us consider them in relation to our proposals. Lesley.dow@sse.com Lesley Dow SHE Transmission Inveralmond House 200 Dunkeld Road Perth PH1 3AQ Follow us Why not follow Scottish and Southern Energy Net on social media and keep up-to-date with all latest news and events? Find us on Facebook: SSEN Community Follow us on Bay Wind Farm Your Thank you for taking the time to attend this consultation event. In order to record your views and improve the effectiveness of our consultation, please complete this short feedback form. Please complete in BLOCK CAPITALS. (Please tick one box per question only) Q1 Has the requirement for the project been clearly explained? Yes No Unsure Q2 Have we explained our plans in a clear way? Yes No Unsure Q3 Do you have any comments on the plans presented by Scottish Hydro Electric Transmission? Q4 Do you have any further information that we need to be aware of? Q5 Can we provide any additional information at this stage? Please write in any further comments you would like to make about the engagement process as a whole. Full name Address Postcode Telephone If you would like to be kept informed of progress on the project please tick this box. If you would like your comments to remain anonymous please tick this box. Thank you for taking the time to complete this feedback form. Please hand your completed form in at the event or alternatively by one of the methods below: Post: Lesley Dow, SHE Transmission plc, Inveralmond House, 200 Dunkeld Road, Perth PH1 3AQ Lesley.dow@sse.com The feedback form and all information provided at the event can also be downloaded from the dedicated website: Any information given on the feedback form can be used and published anonymously as part of Scottish and Southern Electricity Net consultation report. By completing this feedback form you consent to Scottish and Southern Electricity Net using feedback for this purpose.

Finstown Substation - Orkney Project. Public Consultation July 2018

Finstown Substation - Orkney Project. Public Consultation July 2018 Finstown Substation - Orkney Project Public Consultation July 2018 Who we are We are Scottish and Southern Electricity Networks, operating under license as Scottish Hydro Electric Transmission plc (SHE

More information

South West Scotland Renewables Connection Project Environmental Statement Scoping Report Executive Summary

South West Scotland Renewables Connection Project Environmental Statement Scoping Report Executive Summary South West Scotland Renewables Connection Project Environmental Statement Scoping Report Executive Summary September 2007 EXECUTIVE SUMMARY Background This Environmental Impact Assessment (EIA) Scoping

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

New connections. You have a choice. It is your choice

New connections. You have a choice. It is your choice New connections You have a choice If you need a new connection in an area where we own the electricity network, did you know you had a choice? Just because we own the network, it does not mean you have

More information

Distribution Long Term Development Statement

Distribution Long Term Development Statement Distribution November 2017 SP Distribution for the years 2017/18 to 2021/22 Distribution for the years 2017/18 to 2021/22 The information used to compile this Statement is derived from SP Distribution

More information

MSVE CTMP - APPENDIX 3 SITE ACCESS POINTS & TRAFFIC ROUTES

MSVE CTMP - APPENDIX 3 SITE ACCESS POINTS & TRAFFIC ROUTES MSVE LT19 KNOCKNAGAEL TOMATIN 275KV REINFORCEMENT OVERHEAD LINE CTMP - APPENDIX 3 SITE ACCESS POINTS & TRAFFIC ROUTES CLIENT Management System Plan LT19-CTMP-A3 CTMP Appendix 3 - Site Access Points & Traffic

More information

SSE Wholesale Privacy Notice

SSE Wholesale Privacy Notice SSE Wholesale Privacy Notice About us What information do we need? Why do we need it? Legal bases for processing What do we do with it? Who do we share it with? How long will we keep it? Automated decision-making

More information

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,

More information

Consultation on: Queue Management. Consultation Period. Opens: 16 th February 2016

Consultation on: Queue Management. Consultation Period. Opens: 16 th February 2016 Consultation on: Queue Management Consultation Period Opens: 16 th February 2016 Closes: 16 th March 2016 SP Energy Networks SP Energy Networks provide power on behalf of supply companies through a network

More information

Southern Electric Power Distribution plc. Metering Point Administration Services Statement. Effective from 1st April Version 1.

Southern Electric Power Distribution plc. Metering Point Administration Services Statement. Effective from 1st April Version 1. Southern Electric Power Distribution plc Metering Point Administration Services Statement Effective from 1st April 2017 Version 1.0 Scottish and Southern Electricity Networks is a trading name of: Scottish

More information

Connecting and Managing Offshore Wind Danish Embassy - 4 th December 2012

Connecting and Managing Offshore Wind Danish Embassy - 4 th December 2012 Connecting and Managing Offshore Wind Danish Embassy - 4 th December 2012 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

STCP 04-1 Issue 005 Real Time Data Change Management

STCP 04-1 Issue 005 Real Time Data Change Management STCP 04-1 Issue 005 Real Time Data Change Management STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

Contractor Alliancing Sean Mooney Programme Manager

Contractor Alliancing Sean Mooney Programme Manager 1 Contractor Alliancing Sean Mooney Programme Manager Today s Agenda Introduction Background Contractor Alliancing The Process Alliance Electricity Alliance North (EAN) Optimise Water (LLP) JV Benefits

More information

ENMAX Generation Portfolio Inc.

ENMAX Generation Portfolio Inc. Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. September 5, 2017 Alberta Utilities Commission Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. Proceeding 22192 Application 22192-A002 September

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

REPORT. Public Information Days Feedback Summary 17 March March ScottishPower Renewables

REPORT. Public Information Days Feedback Summary 17 March March ScottishPower Renewables REPORT Public Information Days Feedback Summary 17 March 2018-25 March 2018 Client: ScottishPower Renewables Reference: I&BPB4842R000758F1.0 Revision: 1.0/Final Date: 10 May 2018 HASKONINGDHV UK LTD. Rightwell

More information

SSE Graduate Opportunities

SSE Graduate Opportunities SSE Graduate Opportunities We offer graduate development programmes across the following business areas. Click on each to take you to the page:- Networks Transmission Networks Distribution Enterprise Energy

More information

PARTICIPANT INVOLVEMENT PROGRAM

PARTICIPANT INVOLVEMENT PROGRAM ATTACHMENT 3 PARTICIPANT INVOLVEMENT PROGRAM Southern Alberta Transmission Reinforcement Amendment Needs Identification Document Approval Amendment 1.0 Participant Involvement Program From July to December

More information

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1

Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms. ABB Group May 22, 2009 Slide 1 Christian PAYERL, Poznan, 20 th May, 2009 ABB FACTS Grid connection of Wind Farms May 22, 2009 Slide 1 FACTS Applications Flexible AC Transmission Systems May 22, 2009 Slide 4 System Studies - Grid Codes

More information

MONITORING SOLUTIONS FOR Power & Utilities

MONITORING SOLUTIONS FOR Power & Utilities MONITORING SOLUTIONS FOR Power & Utilities SMART MONITORING SOLUTIONS FOR THE INTELLIGENT GRID Informed decision making from integrated monitoring at all points on the network and critical infrastructure

More information

Jenner Wind Energy Connection Needs Identification Document

Jenner Wind Energy Connection Needs Identification Document APPENDIX C AESO PIP Jenner Wind Energy Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From November 2015 to May 2016, the AESO conducted a participant involvement program

More information

FEED IN TARIFF APPLICATION FORM

FEED IN TARIFF APPLICATION FORM FEED IN TARIFF APPLICATION FORM You may not be eligible to register with us for the FIT scheme if you are not an SSE electricity customer. Please check your eligibility to join the Feed in Tariff (FIT)

More information

Feed-in Tariff Application Form

Feed-in Tariff Application Form Feed-in Tariff Application Form Once you ve completed all the details print off this form, sign it and return to us at Green Energy (UK) plc, Black Swan House, 23 Baldock Street, Ware, SG12 9DH. Scanned

More information

Heat meter User guide Sharky Heat Meters

Heat meter User guide Sharky Heat Meters Heat meter User guide Sharky Heat Meters 2 Heat meter user guide Contents Heat Meter 773 + 775 models 4 Understanding your meter 5 Understanding the displays on your meter 6 7 Contacting us 8 3 Sharky

More information

Oli Keinath OUR SOLUTIONS MY INFRASTRUCTURE. istockphoto: Global Stock. Turning Vision into Value.

Oli Keinath OUR SOLUTIONS MY INFRASTRUCTURE. istockphoto: Global Stock. Turning Vision into Value. Oli Keinath MY INFRASTRUCTURE OUR SOLUTIONS istockphoto: Global Stock 1 Our Vision HOCHTIEF is building the future. Along with our partners, we expand horizons, link people and organizations, create new

More information

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ]

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] DATE: April 8, 2013 REPORT NO. CD2013-040 TO: FROM: Chair and Members Committee of the Whole Community Services Gregory Dworak, General Manager Community Services 1.0 TYPE OF REPORT CONSENT ITEM [ ] ITEM

More information

Robin Hood Energy Feed-In Tariff Application Form

Robin Hood Energy Feed-In Tariff Application Form A not for profit company Robin Hood Energy Feed-In Tariff Application Form In order for us to pay the Feed-In Tariff (FIT), we need you to complete this application form fully. Simply fill in the form,

More information

Real-time Data Infrastructure Applied to the Monitoring of Renewables Assets

Real-time Data Infrastructure Applied to the Monitoring of Renewables Assets Real-time Data Infrastructure Applied to the Monitoring of Renewables Assets Presented by Aurélie Nasse, Operations Control Center Manager EDF EN Services Copyright 2011 OSIsoft, LLC Disclaimer The figures

More information

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS

More information

INVESTING IN SKELTON, SALTBURN & MARSKE

INVESTING IN SKELTON, SALTBURN & MARSKE INVESTING IN SKELTON, SALTBURN & MARSKE Powering the region We re Northern Powergrid, the company responsible for the electricity distribution network that keeps the lights on for 8 million customers across

More information

Proposal to Join the Locate Alliance Consortium and to Procure a Common Locate Service Provider Toronto Water and Transportation Services

Proposal to Join the Locate Alliance Consortium and to Procure a Common Locate Service Provider Toronto Water and Transportation Services STAFF REPORT ACTION REQUIRED Proposal to Join the Locate Alliance Consortium and to Procure a Common Locate Service Provider Toronto Water and Transportation Services Date: June 1, 2015 To: From: Wards:

More information

Benbow 397S Substation Upgrade Needs Identification Document

Benbow 397S Substation Upgrade Needs Identification Document APPENDIX C AESO PIP Benbow 397S Substation Upgrade Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to December 2015, the AESO conducted a Participant Involvement Program

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Well Operations Notification System WONS

Well Operations Notification System WONS Well Operations Notification System WONS Operator Quick Reference - Work Instructions Matthew Sharon (Oil and Gas Authority) 8/7/2016 This document provides detailed information on the use of the WONS

More information

Denmarks Cable Policy

Denmarks Cable Policy Denmarks Cable Policy Landsnet Annual meeting 2014 March 20th 2014 Jens Møller Birkebæk Director, International Affairs 1 About Energinet.dk 3 Interconnector capacity 3 Agenda Danish Cable Policy 1. Political

More information

Owner/Operator Forum 12 December

Owner/Operator Forum 12 December Owner/Operator Forum 12 December Steve Halsey DG Development Manager Today s Agenda Transition to DSO Breakout session What we do the role of the DNO Our vision Welcome and Introduction (DNO) Distribution

More information

Introduction. Quick Steps to Submission. How to Read the ROC Meter. Important Things to Note. Queries. Sample Table for Recording your Readings

Introduction. Quick Steps to Submission. How to Read the ROC Meter. Important Things to Note. Queries. Sample Table for Recording your Readings Meter Reading Guide Contents Introduction 1 Quick Steps to Submission 1 How to Read the ROC Meter 2 Important Things to Note 4 Queries 7 Sample Table for Recording your Readings 8 Introduction To be awarded

More information

Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018

Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps. Park Board Committee Meeting Monday, January 15, 2018 Metro Vancouver Stanley Park Water Supply Tunnel Public Engagement & Next Steps Park Board Committee Meeting Monday, January 15, 2018 Purpose To provide an update on Metro Vancouver s Stanley Park Water

More information

October 2017 INVESTING FOR THE FUTURE. NIE Networks summary business plans

October 2017 INVESTING FOR THE FUTURE. NIE Networks summary business plans October 2017 INVESTING FOR THE FUTURE NIE Networks summary business plans 2017-2024 Rasharkin cluster substation Who we are NIE Networks is the owner of the electricity transmission and distribution networks

More information

ASSET RISK MANAGEMENT Criticality Framework

ASSET RISK MANAGEMENT Criticality Framework ASSET RISK MANAGEMENT Criticality Framework 15 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D Preface This document has been prepared to

More information

Feed in Tariffs (FIT) Generator Application Form

Feed in Tariffs (FIT) Generator Application Form First Utility is part of the Feed in Tariff scheme and supports our own electricity customers. If your current electricity supplier is British Gas, E.ON, EDF Energy, Npower, Ovo Energy, Scottish Power,

More information

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network Tasmanian Networks Pty Ltd ABN 24 167 357 299 Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network (AS4777 Compliant) NG R PD 09 Version 2.0 July 2014 TABLE

More information

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY POLICY P-22 TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY Preamble It is recognized that while reliable and sophisticated telecommunication facilities are a benefit to the citizens of (CSRD),

More information

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Vancouver Community Information Open House March 9, About the Metro North Transmission Project Welcome Metro North Transmission Project Vancouver Community Information Open House March 9, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

Discussion Guide. Benvoulin Substation Project.

Discussion Guide. Benvoulin Substation Project. Discussion Guide Benvoulin Substation Project A Growing Region South Central Kelowna has experienced substantial growth over the last ten years. FortisBC is enhancing the electrical power supply system

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

Quotation Accuracy Scheme FOR SMALL CONNECTIONS. How to Challenge the Accuracy of your Quotation

Quotation Accuracy Scheme FOR SMALL CONNECTIONS. How to Challenge the Accuracy of your Quotation Quotation Accuracy Scheme FOR SMALL CONNECTIONS How to Challenge the Accuracy of your Quotation Contents 1. General Information... 3 2. Scope... 3 3. How to check the accuracy of your Quotation... 4 4.

More information

Contents. 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map

Contents. 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map Ranchtown Substation Project Open House Displays 08/16/2012 Contents 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map 2. Scope, Purpose and Need Existing Helotes

More information

Dumfries and Galloway Developer Forum. Welcome and Introduction. Gareth Hislop

Dumfries and Galloway Developer Forum. Welcome and Introduction. Gareth Hislop 6 th December 2017 Dumfries and Galloway Developer Forum Welcome and Introduction Gareth Hislop Dumfries and Galloway Forum Agenda Introduction Gareth Hislop NGET Update Julian Leslie Design Update Diyar

More information

Ells River Substation Telecommunication Tower

Ells River Substation Telecommunication Tower January 2013 Why are you receiving this project information package? We are advising neighbouring landholders, agencies and other interested parties about plans to construct the Ells River substation telecommunication

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

NETS SQSS Review of Requirement of Onshore Connection Facilities for Offshore Wind Farm Connections (GSR014) Working Group Report

NETS SQSS Review of Requirement of Onshore Connection Facilities for Offshore Wind Farm Connections (GSR014) Working Group Report NETS SQSS Review of Requirement of Onshore Connection Facilities for Offshore Wind Farm Connections (GSR014) Working Group Report January 2014 Executive Summary This document summarises the results of

More information

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document Decision 2014-271 Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014 The Alberta Utilities Commission Decision 2014-271: Alberta Electric System Operator

More information

In preparing this guidance document, consideration has been given to the following principles:

In preparing this guidance document, consideration has been given to the following principles: E.ON UK PLC CORPORATE RESPONSIBILITY REPORTING GUIDANCE This Reporting Guidance document supports the preparation and reporting of the following Customers and People Key Performance Indicators (KPIs) prepared

More information

POWER INFRASTRUCTURE PLAN 2016

POWER INFRASTRUCTURE PLAN 2016 POWER INFRASTRUCTURE PLAN 2016 Introduction LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4 million people

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2015 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2016 Introduction The

More information

Robin Hood Energy Feed-in Tariff Application Form

Robin Hood Energy Feed-in Tariff Application Form Robin Hood Energy Feed-in Tariff Application Form In order for us to pay the Feed-In Tariff (FIT), we need you to complete this application form fully. Simply fill in the form, sign it and return it to

More information

Kent Wind Energy Networking Event. Wednesday 26 th September

Kent Wind Energy Networking Event. Wednesday 26 th September Kent Wind Energy Networking Event Wednesday 26 th September Consortium partners Dong Energy is a leading offshore wind developer, having built around half of all offshore wind farms globally. (50%) E.ON

More information

Please let us know if you have any questions regarding this Policy either by to or by telephone

Please let us know if you have any questions regarding this Policy either by  to or by telephone Our Privacy Policy At Torbay Fishing we are committed to protecting and preserving the privacy of our customers when visiting us, visiting our website or communicating (electronically or verbally) with

More information

SECTION 106 ACTIVITIES ANNUAL REPORT

SECTION 106 ACTIVITIES ANNUAL REPORT SECTION 106 ACTIVITIES ANNUAL REPORT FOR THE YEAR ENDING DECEMBER 31, 2016 Metropolitan Washington Airports Authority 198 Van Buren Street, Suite 300 Herndon, Virginia 20170 JANUARY 2017 Introduction The

More information

STCP 18-3 Issue 006 TEC Changes

STCP 18-3 Issue 006 TEC Changes STCP 18-3 Issue 006 TEC Changes STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc. Scottish Hydro-Electric

More information

AEGIS 3 OS MasterMap module

AEGIS 3 OS MasterMap module AEGIS 3 OS MasterMap module The Advisory Unit Computers in Education 1 Copyright All rights reserved. No part of this manual may be reproduced or stored in a retrieval system other than by or for the purchaser,

More information

UE CONNECTION APPLICATION - POLE to PIT (Underground Electricity Supply)

UE CONNECTION APPLICATION - POLE to PIT (Underground Electricity Supply) Phone 1300 131 689 Business Hours 8:00AM 5:00PM United Energy ABN 70 064 651 029 Scan & Email undergroundsupply@ue.com.au Attn: Customer and Market Operations PO Box 449 Mount Waverley VIC 3149 Thank you

More information

ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE

ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE ELECTRICITY SUPPLY SYSTEMS OF THE FUTURE Rob Stephen President Cigre AFSEC conference March 2017 CIGRE Founded in 1921, CIGRE, the Council on Large Electric Systems, Our Mission:To be the world s foremost

More information

New Challenges for DSO

New Challenges for DSO New Challenges for DSO Johannes Brantl, Head of Assetmanagement, E.ON Bavaria IEA, Kassel, May 8th Power Grid of E.ON Bavaria Area MV-Grid 41.500 km² cables 23.000 km Overhead lines 21.400 km percentage

More information

In the Environment Court ENV-2011-CHC-090 Christchurch Registry. Under the Resource Management Act Meridian Energy Limited

In the Environment Court ENV-2011-CHC-090 Christchurch Registry. Under the Resource Management Act Meridian Energy Limited 1 In the Environment Court ENV-2011-CHC-090 Christchurch Registry Under the Resource Management Act 1991 and in the matter of direct referral of an application for resource consents by Meridian Energy

More information

UNDERGROUND HV SUBSTATION DESIGN

UNDERGROUND HV SUBSTATION DESIGN 3 for 2 Bundle Offer. SGD 2440 each for Team of 3! Topics Covered Underground Substations Overview Planning New Underground Substations S/S Design Overview Expert Course Faculty Leader In his 30 years

More information

Community Update. May 31, 2011

Community Update. May 31, 2011 Community Update May 31, 2011 Presented to: Leaside Community Presented by: Honourable Kathleen Wynne, Minister of Transportation Councillor Karen Stintz, Chair, Toronto Transit Commission Eglinton-Scarborough

More information

Beatrice Offshore Wind Farm

Beatrice Offshore Wind Farm X/JOBS/3019_/6docs/3019_WF_Ferry.indd SW W Viewpoint 15: Ferry Route 369731, 948678 19m above sea level 90, turbines occupy - 21 19.73km, T120 Location Plan - 1:500,000 scale Wireframe view S SW Viewpoint

More information

Guidance on submitting your annual ROC meter reading

Guidance on submitting your annual ROC meter reading Meter Reading Guide Guidance on submitting your annual ROC meter reading In order to be awarded ROCs from your system, it is essential for you to take your annual generation meter reading on Saturday 31st

More information

An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections

An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections An Introduction to the Operational Notification and Compliance Process Including

More information

TransWest Express Transmission Project Interregional Transmission Project Submittal

TransWest Express Transmission Project Interregional Transmission Project Submittal TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March

More information

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace.

Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace. Power delivery Demand for sustainable power is growing worldwide. Energy producers are broadening their offerings for a quickly evolving marketplace. Forward-thinking power grid design This evolution has

More information

South Hams Motor Club Our Privacy Policy. How do we collect information from you? What type of information is collected from you?

South Hams Motor Club Our Privacy Policy. How do we collect information from you? What type of information is collected from you? South Hams Motor Club Our Privacy Policy At South Hams Motor Club (SHMC) we are committed to protecting and preserving the privacy of our customers when attending our events, visiting our website or communicating

More information

GC0102 Mod Title: EU Connection Codes GB Implementation Mod 3

GC0102 Mod Title: EU Connection Codes GB Implementation Mod 3 Stage 01: Modification Proposal Grid Code GC0102 Mod Title: EU Connection Codes GB Implementation Mod 3 Purpose of Modification: This modification (3/4) will set out within the Grid Code the following

More information

Flexible Distributed Generation. FDG-A March Area (EPN) December 2016

Flexible Distributed Generation. FDG-A March Area (EPN) December 2016 Flexible Distributed Generation FDG-A March Area (EPN) December 2016 Principles of Flexible Distributed Generation A Flexible DG connection is a technical and commercial agreement where a generator is

More information

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton (February 2002) (Revised, January 2011) Council approval CW062-2011 (Revised, February 2011) revisions

More information

Danish Policy on Underground Cabling of HV lines. Anders H Kristensen Danish Energy Agency

Danish Policy on Underground Cabling of HV lines. Anders H Kristensen Danish Energy Agency Danish Policy on Underground Cabling of HV lines Anders H Kristensen Danish Energy Agency Background Local opposition to new overhead HV lines has always been strong, but the voice has been low The strength

More information

April 2010 Power Systems division A brief introduction. ABB Group August 25, 2011 Slide 1

April 2010 Power Systems division A brief introduction. ABB Group August 25, 2011 Slide 1 April 2010 Power Systems division A brief introduction August 25, 2011 Slide 1 Facts about ABB 117,000 employees in about 100 countries $32 billion in revenue (2009) Formed in 1988 merger of Swiss and

More information

NOT PROTECTIVELY MARKED SUPPLIER REGISTRATION FORM

NOT PROTECTIVELY MARKED SUPPLIER REGISTRATION FORM SUPPLIER REGISTRATION FORM Thank you for taking the time to complete the Horizon Supplier Registration form. Please contact suppliers@horizonnuclearpower.com if additional assistance is required. Highlighted

More information

Power Infrastructure Plan

Power Infrastructure Plan Power Infrastructure Plan 2015 Introduction Background LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4

More information

Public Notification Letter

Public Notification Letter 2000 Powell Street, Ste. 600 Emeryville, CA 94608 USA +1.510.452.8000 main +1.510.452.8001 fax Public Notification Letter To: Interested Parties From: SCS Global Services Date: 29 th of March 2016 Re:

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

SMR Deployment Enablers

SMR Deployment Enablers SMR Deployment Enablers Kris MacCrory Decision Analysis Services 2017 Energy Technologies Institute LLP - Subject to notes on page 1 Small Modular Reactor (SMR) Deployment Enablers Project Kris MacCrory

More information

BODY CORPORATE REGISTRATION Application form

BODY CORPORATE REGISTRATION Application form General Optical Council BODY CORPORATE REGISTRATION Application form Please read the attached guidance notes and complete the form in full. This form is for body corporates who wish to join the General

More information

Siemens HVDC & FACTS Innovations and Projects

Siemens HVDC & FACTS Innovations and Projects Siemens HVDC & FACTS Innovations and Projects EPRI Conference, October 2010 in Palo Alto Volker Hild, Jeff Vivian Bulk Power Transmission in China Selected HVDC Applications Page 2 Oct - 2010 Ultra HVDC

More information

PRIVACY POLICY QUICK GUIDE TO CONTENTS

PRIVACY POLICY QUICK GUIDE TO CONTENTS PRIVACY POLICY This privacy policy describes the policies and practices of Comodo Security Solutions, Inc. and Comodo Security Solutions Ltd. (collectively and individually referred to herein as "Comodo"),

More information

RE: Demand Side Unit (DSU) Congestion Issues and Next Steps in the Application Process

RE: Demand Side Unit (DSU) Congestion Issues and Next Steps in the Application Process 12 th March, 2015 Mr. Paul Brandon, Commission for Energy Regulation, The Exchange, Belgard Square North, Tallaght, Dublin 24, Ireland. Mr. Colin Broomfield, Utility Regulator, Queens House, 14 Queen Street,

More information

Technical Report REVISION SHEET. STUDSVIK UK LIMITED ENSREG Stress Tests : Final Report NO PROTECTIVE MARKING NO PROTECTIVE MARKING.

Technical Report REVISION SHEET. STUDSVIK UK LIMITED ENSREG Stress Tests : Final Report NO PROTECTIVE MARKING NO PROTECTIVE MARKING. STUDSVIK UK LIMITED ENSREG Stress Tests : Final Report REVISION SHEET Rev. Description Revised By Checked By Approved By A Original copy ER DS MM Studsvik Report Reference: TR_MRF021 Revision: Rev A Date:

More information

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km) nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Welcome Thank you for attending this community engagement on the Trans- Canada Highway 1 West Project, part of the Highway

More information

Boardman to Hemingway Project Advisory Team

Boardman to Hemingway Project Advisory Team Boardman to Hemingway Project Advisory Team Central Project Advisory Team Meeting 5 Tonight s Objectives Review progress of the Community Advisory Process and discuss next steps Present analysis of revised

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2118. Date ISDS Prepared/Updated: 03/07/2006 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC2118. Date ISDS Prepared/Updated: 03/07/2006 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 03/07/2006 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

Driving innova*on and knowledge

Driving innova*on and knowledge Driving innova*on and knowledge Presentation to Mer-Innovate SPARTA Paul Ellsmore Academic and Cross-Catapult Engagement Manager 29 th October 2014 Catapults: A long-term vision for innovation & growth

More information

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES

EBB PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES Network(s): Summary: ENGINEERING BULLETIN EBB 08-0061 PILOT FOR THE LIVE CONNECTION OF UNMETERED EQUIPMENT TO OVERHEAD LINES EPN, SPN This bulletin provides a framework for the pilot scheme for unmetered

More information

Optimizing wind farms

Optimizing wind farms Optimizing wind farms We are Uniper Your benefits We are a leading international energy company with operations in more than 40 countries and around 13,000 employees. We combine a balanced portfolio of

More information

Privacy Notice. What is personal data? Who we are. How the law protects you. How to Contact Us. Our Data Protection Officer

Privacy Notice. What is personal data? Who we are. How the law protects you. How to Contact Us. Our Data Protection Officer Privacy Notice Contents Privacy Notice Introduction... 3 People who have a Tenancy Agreement with us... 4 People who receive a Factoring Service... 6 People who have Shared Ownership or Shared Equity housing