New Resource Implementation & Market Modeling

Size: px
Start display at page:

Download "New Resource Implementation & Market Modeling"

Transcription

1 New Resource Implementation & Market Modeling Resource Interconnection Fair February 24, 2016 Page 1

2 Topics Discuss the New Resource Implementation (NRI) process. Structure and timeline for any resource required to or electing to participate in the CAISO commercial market. Review requirements to incorporate projects into the ISO energy market (Full Network Model) Including all expansions, like increasing MW outputs after study processes are complete, or changing fuel mixes. Review requirements for Qualifying Facilities (QFs) and conversions with expiring agreements. Page 2

3 Interconnection Process Map You are here The New Resource Implementation (NRI) process ensures that all ISO requirements are completed: For initial synchronization, or To declare that a resource for commercial operation QF and other types of conversions Resources seeking wholesale market participation, but not required to complete the ISO interconnection process, will start with NRI processes. Examples could include: Distribution-connected resources, QF and other types of conversions Page 3

4 Modeling and Contracts Implementation Group EDAS NRI EDAS: Energy Data Acquisition Systems MPAI MCI ERM ERM: Energy Resource Management FNM: Full Network Model FNM MPAI: Market Participant Asset Implementation NRI: New Resource Implementation Operations Energy Management Outage Planning Outage Coordination Operational Readiness Queue Management Regulatory Contract Management Meter Data Acquisition Transmission Planning Congestion Rights VER Forecasting Page 4

5 Function of the Bucket and File naming System Buckets represent a group of required submittals Buckets represent NRI checklist items that must be accepted (not merely received) by the respective bucket due date Buckets dates are derived by working backward from the sync, QF completion, or conversion date reminders are sent if a bucket deliverables have not been accepted File Naming (of attachments) Filenames are specifically designed for automated identification Ensure files are routed to the appropriate business unit for reviews and acceptabnce Automatically checks off the bucket item when accepted. Page 5

6 Tips for success: NRI document submission Review the NRI Guide and Checklist Start the NRI process early and submit documents before bucket dates Include your CAISO Project number (e.g. 16GEN1234) One project per Multiple attachments per per project are okay sender must be listed on the Project Details Form Follow the file naming convention in the NRI Guide Please read the responses from NRI We are here to help - ask questions! Page 6

7 Live, learn, and love your buckets. Accurate documents submitted well ahead of bucket deadline: Inaccurate documents submitted at the last minute without reviewing requirements in advance of submission: Page 7

8 Buckets timeline and recent process changes NRI deliverables are collected in 6 buckets As of Feb. 24, 2016, the number of buckets shrank, however: More deliverables are associated with Bucket 1, and Bucket 1 now collects what used to be collected in Buckets 1 & 2 Page 8

9 Getting Started First step of the NRI process: Submit a Project Details Form no less than 7 months in advance of your estimated initial sync, QF, or conversion date Your project will be assigned a NRI project number Example: 16GEN1234 Use the Project Details Form to update: Project Description Initial Sync, QF, or conversion date addresses (to designate recipient of project progress reports and to allow an authorized user to submit documentation to NRI) Page 9

10 Bucket 1: Full Network Model Preparation Deliverables are required to: Create a Market Resource ID Essential for participation in the ISO market; Satisfy requirements for Direct Telemetry (if applicable). Bucket 1 items include: Copy of executed two-party Interconnection Agreement Issued For Construction (IFC), single-line, & three-line drawings Communication Block Diagram, Network Application information, Other itesm (See NRI checklist and guide for complete listing) For wind projects only: Submit Site Information document and Topographical map Page 10

11 Bucket 2: Regulatory Contracts, Forecasting Information and Model Testing Initiate the applicable ISO Regulatory Contracts The type of contracts required for a project depends on the project type (New resource, QF, Dynamic, etc.). RegulatoryContracts@caiso.com for questions about specific contract types. Submit the initial Generator Resource Data Template (GRDT) Resource characteristics recorded in the GRDT are necessary for preliminary modeling of the resource. Meter Configuration Worksheet For Initial set up the meter(s) in the meter polling system For solar projects only Submit Site Information document and Topographical map Page 11

12 Bucket 3: Market Preparation Bucket 3 Deliverables: Regulatory contracts fully executed Final GRDT submitted The Interconnection Customer (IC) submits a copy of the SC Selection Letter The SC signs the SC Acceptance Letter, routes to the IC, and the IC submits A resource cannot synchronize or participate in the ISO markets without an SC association. Page 12

13 Bucket 3: Market Preparation (cont.) Bucket 3 Deliverables (cont): Control & Protection documentation If directly connected to CAISO transmission (projects with an ISO Queue Number) Final Meter and Remote Intelligent Gateway (RIG) requirements: Pre-testing confirmed, Schedule end-to-end test with CAISO Submit signed security agreement(s) Page 13

14 Bucket 4: Trial Operations Approval, or a Resource Requesting Sync, QF Transition or Conversion For New Construction Buckets 1-3 are completed Testing Completed Must provide connected utility approval letter WebOMS Outage for test energy Send NRI Request to Sync with subject line in specific format: e.g. 14GEN1234 Request for Initial Synchronization Still to do: Complete Buckets 5 and 6 For QF or Conversions Buckets 1-3 are completed Testing completed IC and SC coordinate transition of settlement data Send NRI Request to Sync with subject line in specific format: e.g. Request for QF Conversion for (Project Name) 14GEN1234 Telemetry error free for 72 hours Final Metering Documents & Meter Data Validation Certificate of Compliance issued by ISO Hurray! You re Done with NRI Page 14

15 Bucket 5: Trial Operations (After Sync & Before COD) During Trial Operations: SCs must follow Operating Procedure 5320 Metering and telemetry data are monitored to ensure data quality meets CAISO standards 72 uninterrupted hours of error-free telemetry required Final metering documents are reviewed and accepted, and validation is completed. Then, a Certificate of Compliance will be issued. Trial Operations biggest show stoppers: Final metering documentation issues MET station problems Page 15

16 Bucket 6: Commercial Operation Date (COD) or Commercial Operation for Markets (COM) Process for declaring commercial operation after Trial Operations is complete: Commercial Operations Date (COD) Commercial Operation for Markets (COM) IC: Request COD IC: Request COM IC: Sends to NRI requesting COD. IC: Sends to NRI requesting COM and subject line in specific format. e.g. COD Request accompanies request with COM implementation plan. Approval for [Project Name] 14GEN12 subject line in specific format. e.g. COM Request Approval for [Project Name] 14GEN1234 SC: follow Operating Procedure 5320 SC: follow Operating Procedure 5320 ISO: 72 hours monitoring of metering and telemetry ISO: 72 hours monitoring of metering and telemetry data ensure data quality meets CAISO standards. data ensure data quality meets CAISO standards. ISO: Internal business units confirm that the market, ISO: Internal business units confirm that the market, operational readiness, real-time and the UDC or PTO operational readiness, real-time and the UDC or PTO is ready. is ready. NRI: sends an to the IC that provides a declaration date for the commercial operations date. NRI: will send an to the IC that provides a declaration date for the first commercial operations for market. Page 16

17 Bucket 6: Commercial Operation Date (COD) or Commercial Operation for Markets (COM) Commercial Operations Date (COD) No equivalent action for COD No equivalent action for COD No equivalent action for COD No equivalent action for COD Commercial Operation for Markets (COM) IC Actions, for each declaration: 1. Attach and a COM declaration letter before 9am for same day declaration, or for a later date, but no sooner than the date stated in the ISO If changed, attach an updated COM plan to the same . SC: Updates WebOMS outage by following Operating Procedure NRI: sends an confirming the increase. This process is repeated until you ve reached the full COD amount. Page 17

18 Bucket 6: Commercial Operation Date (COD) and Commercial Operation for Markets (COM) Commercial Operations Date (COD) NRI: No futher action required IC Action: Attach and a COD declaration letter before 9am for same day declaration, but no sooner than the date stated in the above. NRI: sends an confirming the declaration Hurray you re done with NRI!!!! Commercial Operation for Markets (COM) NRI: No futher action required IC Action: Attach and a COD declaration letter before 9am for same day declaration, but no sooner than the date stated in the above. NRI: sends an confirming the declaration Hurray you re done with NRI!!!! Page 18

19 Recent or upcoming changes to the NRI Process Revisions to Bucket System filing dates (effective Feb 24, See earlier slide) Meter Site Verification Sheet (MSVS) RIMS5 POC and User Provisioning RIMS5 user interface (late summer 2016) Project Details Form (Version 9) Updated NRI Guide, Checklist and Website Page 19

20 Resources NRI Checklist and Guide New Resource Implementation webpage: NRI Checklist: NRI Guide: Project Details Form: Page 20

21 Thank you! If you have any further questions regarding the NRI process, please send them to Page 21

Resource Interconnection Management System (RIMS) Quick Start Guide

Resource Interconnection Management System (RIMS) Quick Start Guide Resource Interconnection Management System (RIMS) Quick Start Guide New Resource Implementation (NRI) Starting a New Project, Document Submission, and Project Information Updates for: Solar Wind/Wind Repower

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Emilee Plouff, Contract Negotiation and Regulatory Contracts Joanne Bradley, Queue Management March 6, 2018 Interconnection Process

More information

Agreements and Queue Management

Agreements and Queue Management Agreements and Queue Management Infrastructure Contracts and Management Joanne Bradley, Queue Management Shoukat Ansari, Contract Negotiation PJ Topping, Regulatory Contracts February 27, 2019 Interconnection

More information

Agreements & Queue Management

Agreements & Queue Management Agreements & Queue Management Resource Interconnection Fair February 24, 2016 Page 1 Interconnection Process Map You are here Page 2 Topics 1. Generator Interconnection Agreement (GIA) 2. Affected Systems

More information

Small Hydro Regulatory and Permitting Requirements California

Small Hydro Regulatory and Permitting Requirements California Small Hydro Regulatory and Permitting Requirements California Lon W. House, Ph.D. 530.409.9702 Water & Energy Small Hydro Regulatory and Compliance FERC QF, Small Hydro License or Exemption EIA Generator

More information

Table of Contents. Purpose. Certification of Metering Facilities. Procedure No Version No. 1.4 Effective Date 2/14/2018. Operating Procedure

Table of Contents. Purpose. Certification of Metering Facilities. Procedure No Version No. 1.4 Effective Date 2/14/2018. Operating Procedure No. 5710 Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 3 2.1 Background... 3 2.2 Scope / Applicability... 3 3. Detail... 3 3.1 Certifying Metering Facilities... 3 3.1.1

More information

Operations ISO Version: 1.6. Effective Date: 8/02/2018. Fieldwork Guide. Fieldwork Guide

Operations ISO Version: 1.6. Effective Date: 8/02/2018. Fieldwork Guide. Fieldwork Guide REVISION HISTORY VERSION NO. (Must match header) DATE REVISED BY DESCRIPTION 1.0 6/6/2016 EDAS Created Document 1.1 6/29/2016 EDAS Updates to include all Meter Work and instruction 1.2 8/29/2016 EDAS Included

More information

Operations ISO Version: 1.2. Communication Block Diagram Requirements Effective Date: 082/07/2017. Checklist

Operations ISO Version: 1.2. Communication Block Diagram Requirements Effective Date: 082/07/2017. Checklist Checklist REVISION HISTORY VERSION NO. DATE REVISED DESCRIPTION (Must match header) BY 1.1 07/03/2017 Created Document 1.2 08/07/2017 RLS Removed watermark. No technical changes. Contents Purpose... 4

More information

Meter Configuration and RIG Details Checklist

Meter Configuration and RIG Details Checklist Meter Configuration and RIG Details Checklist REVISION HISTORY VERSION NO. (Must match header) DATE REVISED BY DESCRIPTION 1.0 2/25/2015 MU Created Document 1.1 8/16/2016 MU Updated requirements in conjunction

More information

RIMS: Transmission Implementation Module

RIMS: Transmission Implementation Module RIMS: Transmission Implementation Module Resource Interconnection Management System (RIMS) Functional Enhancements Radha Madrigal Training and Readiness February 13, 2018 The information contained in these

More information

User Access Administrator (UAA) Form and Access to Resource Interconnection Management System (RIMS 5)

User Access Administrator (UAA) Form and Access to Resource Interconnection Management System (RIMS 5) User Access Administrator (UAA) Form and Access to Resource Interconnection Management System (RIMS 5) Massih Ahmadi 11/28/2017

More information

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012

CAISO Metering & Telemetry Requirements. Jeremy Laundergan - Director, EnerNex November 8, 2012 CAISO Metering & Telemetry Requirements Jeremy Laundergan - Director, EnerNex November 8, 2012 Background and Overview Both federal and state regulatory authorities are advocating the participation of

More information

1. Responsibilities. Settlement Quality Meter Data (SQMD) Plan Submission & Approval Process (External) Operating Procedure

1. Responsibilities. Settlement Quality Meter Data (SQMD) Plan Submission & Approval Process (External) Operating Procedure Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 3 2.1 Background... 3 2.2 Scope / Applicability... 3 3. Detail... 4 3.1 SQMD Plan Imposed by the CAISO Tariff... 4 3.1.1

More information

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

Expanding Metering and Telemetry Options Technical Stakeholder Initiative Expanding Metering and Telemetry Options Technical Stakeholder Initiative April 24, 2013 Todays Agenda Time Topic Presenter 10:00 10:10 Opening Comments/Introductions Khaled Abdul-Rahman 10:10 10:20 Stakeholder

More information

EIM Entity Readiness Criteria May 6, 2015

EIM Entity Readiness Criteria May 6, 2015 EIM Entity Readiness Criteria May 6, 2015 FERC Directive Regarding Readiness Criteria We therefore direct CAISO to submit a compliance filing within 60 days of issuance of this order, to revise the EIM

More information

Checklist for Submission to Utility

Checklist for Submission to Utility Simplified Interconnection Application Persons interested in applying for the interconnection of a distributed energy resource (DER) to the Utility s distribution system through the Simplified Process

More information

Section 10 of BPM for TPP- Generator modeling webinar

Section 10 of BPM for TPP- Generator modeling webinar Section 10 of BPM for TPP- Generator modeling webinar Songzhe Zhu, Irina Green, Riddhi Ray, Mudita Suri Market and Infrastructure Development September 11, 2018 Presentation overview Overview of PRR 1067

More information

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 July 30, 2010 Re: Q2 Quarterly

More information

Expanding Metering and Telemetry Options Technical Stakeholder Initiative

Expanding Metering and Telemetry Options Technical Stakeholder Initiative Expanding Metering and Telemetry Options Technical Stakeholder Initiative August 28th, 2013 9:00 a.m. 12:00 p.m. (Pacific Time) Web Conference Information Web Conference Information Web Address (URL):

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted By Company Date Submitted Shannon Eddy (shannon@consciousventuresgroup.com) Rachel Gold (Rachel@consciousventuresgroup.com) Large-scale Solar Association (LSA) December

More information

Resource Adequacy Pre-Market Simulation Training Workshop

Resource Adequacy Pre-Market Simulation Training Workshop Resource Adequacy Pre-Market Simulation Training Workshop Focusing on the following initiatives: Reliability Services Initiative (RSI) Capacity Procurement Mechanism (CPM) Replacement October 21, 2015

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 977 METERING PROTOCOL ORIGINAL VOLUME NO. III Original Sheet No. 978 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE MP 1.1 Objective

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

ENTSO-e Operational Security Network Code. OS Code Objectives. Update for JESG meeting 20 th Feb 2013

ENTSO-e Operational Security Network Code. OS Code Objectives. Update for JESG meeting 20 th Feb 2013 ENTSO-e Operational Security Network Code Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. OS

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information

CAISO RIG Acceptance Test Procedure

CAISO RIG Acceptance Test Procedure CAISO RIG Acceptance Test Procedure TABLE OF CONTENTS 1.0 PURPOSE... 3 2.0 INTRODUCTION... 3 3.0 TEST PROCEDURE... 8 Market Services/ EDAS CAISO Public Revision History 1.0 PURPOSE The procedure is intended

More information

SREC Registration Program (SRP) FAQs Updated

SREC Registration Program (SRP) FAQs Updated SREC Registration Program (SRP) FAQs Updated 03.03.16 SRP Program Changes Q. What changes are being made to the 2016 NJ SREC Solar Registration Program? A. There are two (2) important changes the Program.

More information

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, :00 p.m. 4:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Webconference November 12, 2018, 2018 1:00 p.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 1:00-1:10 Stakeholder Process and Schedule Kristina Osborne

More information

Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative. Revised Scope and Schedule

Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative. Revised Scope and Schedule Energy Storage and Distributed Energy Resources (ESDER) Stakeholder Initiative Revised Scope and Schedule June 25, 2015 Table of Contents 1 Introduction... 3 2 Background... 3 3 Stakeholder process...

More information

FNM Expansion Training Webinar

FNM Expansion Training Webinar FNM Expansion Training Webinar Cynthia Hinman Lead Client Trainer August 11, 2014 The information contained in these materials is provided for general information only and does not constitute legal or

More information

Generator Interconnection Process. Wholesale Transmission Overview

Generator Interconnection Process. Wholesale Transmission Overview 1 Generator Interconnection Process Wholesale Transmission Overview 2 This presentation summarizes the FERC-approved Generator Interconnection Procedures (GIP) in Appendix Y of the California Independent

More information

Market Participant User Guide ISO Reliability Requirements Application (IRR UI)

Market Participant User Guide ISO Reliability Requirements Application (IRR UI) Market Participant User Guide ISO Reliability Requirements Application (IRR UI) Version 1 Last Revised: November 21, 2011 ISO Public 1 of 84 Table of Contents 1. Introduction... 5 1.1 Resource Adequacy

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: January 30, 2019 Re: Decision on

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 727 METERING PROTOCOL FIRST REPLACEMENT VOLUME NO. II Original Sheet No. 728 METERING PROTOCOL Table of Contents MP 1 OBJECTIVES, DEFINITIONS AND SCOPE

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

BPM Change Management Meeting

BPM Change Management Meeting BPM Change Management Meeting August 22, 2017 Julia Payton BPM Change Management Process BPM_CM@caiso.com Agenda BPM Change Management Meeting, August 22, 2017 Topic Introduction/meeting overview Discussion

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Ben Kaun, bkaun@epri.com, 650-855-2208 EPRI 9/24/14 Please use this template to provide your comments on the presentation and discussion

More information

Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6

Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6 Supervisory Control and Data Acquisition (SCADA) Performance Criteria Transmission Maintenance Procedure No. 6 Version 3 Effective Date 10/17/2017 Approved by: Transmission Maintenance Coordination Committee

More information

SCS FSC Chain-of-Custody Guidance for Certification of Multiple Sites FSC-STD V2-1

SCS FSC Chain-of-Custody Guidance for Certification of Multiple Sites FSC-STD V2-1 2000 Powell Street, Ste. 600 Emeryville, CA 94608 USA +1.510.452.8000 main +1.510.452.8001 fax www.scsglobalservices.com SCS FSC Chain-of-Custody Guidance for Certification of Multiple Sites FSC-STD-40-003

More information

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting

Contingency Reserve Sharing; Ancillary Services Market. Presented to the JCM Joint Stakeholder Meeting Contingency Reserve Sharing; Ancillary Services Market Presented to the JCM Joint Stakeholder Meeting 1 Agenda Products and Nature of Current Services Contingency Reserve Sharing Group (CRSG) Agreement

More information

Resource Adequacy Pre-Market Simulation Training and Settlements Workshop

Resource Adequacy Pre-Market Simulation Training and Settlements Workshop Resource Adequacy Pre-Market Simulation Training and Settlements Workshop Focusing on the following initiatives: Reliability Services Initiative (RSI) Capacity Procurement Mechanism (CPM) Replacement Commitment

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

9 February 2017 Part 6 distributed generation applications. Ron Beatty Principal advisor

9 February 2017 Part 6 distributed generation applications. Ron Beatty Principal advisor 9 February 2017 Part 6 distributed generation applications Ron Beatty Principal advisor 1031043 1 EMBEDDED GENERATION TRENDS Fuel type Embedded generation ICP Installed identifiers capacity in MW % of

More information

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER

WELCOME. Draft Energy Storage Roadmap. Draft Matrix Stakeholder Call. November 3, 2014 San Francisco SAFER, SMARTER, GREENER WELCOME Draft Energy Storage Roadmap Draft Matrix Stakeholder Call November 3, 2014 San Francisco SAFER, SMARTER, GREENER Alignment of Proposed Actions to Storage Configuration and Use Cases Robert Anderson,

More information

Interconnection Application

Interconnection Application Interconnection Application Member interested in applying for the interconnection of a distributed energy resource to the Utility s distribution system through the Fast Track or Study Processes are to

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information

Annual Industry Consultation

Annual Industry Consultation nd Annual Industry Consultation Proposed revisions to the Balancing Services Adjustment Data Methodology Statement Procurement Guidelines System Management Action Flagging Methodology Statement Balancing

More information

Interconnection Re-MAT September 11, 2013

Interconnection Re-MAT September 11, 2013 Interconnection Re-MAT September 11, 2013 2013 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Distribution System Interconnection Processes Rule 21 - Governed by CPUC Wholesale

More information

Demand Response User Guide DRRS Enhancement Market Simulation. Version 1.0 August 18, 2016

Demand Response User Guide DRRS Enhancement Market Simulation. Version 1.0 August 18, 2016 Demand Response User Guide DRRS Enhancement Market Simulation Version 1.0 August 18, 2016 Table of Contents INTRODUCTION... 5 Purpose... 5 Definitions... 6 DEMAND RESPONSE PROVIDER (DRP)... 10 Executing

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections

An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections An Introduction to the Operational Notification and Compliance Process Including Timescales for New Generation Connections An Introduction to the Operational Notification and Compliance Process Including

More information

ISO-NE Demand response season preparation webinar

ISO-NE Demand response season preparation webinar ISO-NE Demand response 2017 season preparation webinar agenda What you need to know Program information recap Market history and expectations Up-to-date information Curtailment plans Communications drill

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Project Data Update Package Instruction Manual (PDUP-IM)

Project Data Update Package Instruction Manual (PDUP-IM) Project Data Update Package Instruction Manual (PDUP-IM) Date: April 11, 2018 Prepared by: Reviewed by: Approved by: Khalid Rafiq, P. Eng. Modelling Engineer, Transmission Project Delivery Christopher

More information

Forced and Planned Outage Substitution, RAAIM Pre-Calc

Forced and Planned Outage Substitution, RAAIM Pre-Calc Forced and Planned Outage Substitution, RAAIM Pre-Calc RSI 2017 Training January 17, 2018 1:00PM The information contained in these materials is provided for general information only and does not constitute

More information

Self-Certification Tutorial. Version 1.0 April 2013

Self-Certification Tutorial. Version 1.0 April 2013 Version 1.0 April 2013 The PLAN At the end of this tutorial, you will be able to: 1. Describe the purposes of Self-Certification 2. Identify deadlines 3. Describe the use of the Self-Certification template

More information

The NYISO shall assign a Queue Position based upon the date and time of receipt of the

The NYISO shall assign a Queue Position based upon the date and time of receipt of the 30.4 Queue Position 30.4.1 General The NYISO shall assign a Queue Position based upon the date and time of receipt of the valid Interconnection Request; provided that, if the sole reason an Interconnection

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

IATF Transition Strategy Presenter: Cherie Reiche, IAOB

IATF Transition Strategy Presenter: Cherie Reiche, IAOB IATF 16949 Transition Strategy Presenter: Cherie Reiche, IAOB IATF 16949 Transition Strategy IATF 16949 transition strategy was presented at the IATF global stakeholder conference in Rome, Italy in April

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Specific topics covered in this brief include:

Specific topics covered in this brief include: April 2008 Summary Welcome to the Fifteenth National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 28, 2008, Transmission Update conference

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

GUIDE TO CERTIFICATION

GUIDE TO CERTIFICATION GUIDE TO CERTIFICATION December 2017 *Note this document is temporary, and the content will soon appear on peer.gbci.org, at the latest November 30, 2015.* CONGRATULATIONS ON YOUR DECISION TO PURSUE PEER

More information

Table of Contents. Purpose. Meter Data Acquisition and Processing Procedure. Procedure No Version No. 1.3 Effective Date 2/14/2018

Table of Contents. Purpose. Meter Data Acquisition and Processing Procedure. Procedure No Version No. 1.3 Effective Date 2/14/2018 Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 3 2.1 Background... 3 2.2 Scope / Applicability... 3 3. Detail... 3 3.1 ISOMEs Interrogation... 3 3.2 ISOMEs Validation...

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

Settlement Files Publication Contingency Provisions

Settlement Files Publication Contingency Provisions Files Publication Contingency Provisions VERSION 2.0: AUGUST 30, 2016 Table of Contents 1 Introduction... 3 1.1 Revision History... 3 1.2 Related Documents... 3 1.3 Document Purpose and Scope... 3 2 Statement

More information

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements

Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements Screening Procedures for Access to ISO Register of Transmission Facilities and Entitlements In accordance with the Federal Energy Regulatory Commission (FERC) order issued on January 24, 2003 (as modified

More information

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009

Midwest ISO Overview - ATC Customer Meeting. February 26, 2009 Midwest ISO Overview - ATC Customer Meeting February 26, 2009 Agenda Overview January 2009 Dashboard Module E RAR Timeline Questions 2 Overview January was characterized by seasonal cold temperatures,

More information

Reliability Coordinator Procedure

Reliability Coordinator Procedure No. Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/ Applicability... 2 2.1. Background... 2 2.2. Scope... 2 2.3. Applicability... 3 3. Detail... 3 3.1. Format and Security Protocols...

More information

July 26, Dear Mr. Millar:

July 26, Dear Mr. Millar: July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 Dear Mr. Millar: As you are aware, Clean

More information

APPENDIX LETTER CODE DESCRIPTION Appendix D2 Scheduled ENROL/ 3PENR

APPENDIX LETTER CODE DESCRIPTION Appendix D2 Scheduled ENROL/ 3PENR APPENDIX D1. Customer Notifications Overview This Overview identifies the system-generated notification letters that are sent out based on customer status in the Electric Choice enrollment cycle. For each

More information

IRB RESEARCH REPOSITORY COMPLIANCE PROGRAM: Repository Protocols and FAQs

IRB RESEARCH REPOSITORY COMPLIANCE PROGRAM: Repository Protocols and FAQs IRB RESEARCH REPOSITORY COMPLIANCE PROGRAM: Repository Protocols and FAQs Compliance Deadline: August 31, 2011 Kathryn Schuff, MD, MCR Andrea Johnson, JD IRB Co-Chair Regulatory Specialist, ORIO Agenda

More information

Standard COM-002-2a Communications and Coordination

Standard COM-002-2a Communications and Coordination A. Introduction 1. Title: Communication and Coordination 2. Number: COM-002-2a 3. Purpose: To ensure Balancing Authorities, Transmission Operators, and Generator Operators have adequate communications

More information

Warrenton Wheeler Gainesville 230kV Reliability Project

Warrenton Wheeler Gainesville 230kV Reliability Project Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three

More information

Energy Storage and Distributed Energy Resources Phase 2. Customer Partnership Group March 27, p.m. 2 p.m. (Pacific Standard Time)

Energy Storage and Distributed Energy Resources Phase 2. Customer Partnership Group March 27, p.m. 2 p.m. (Pacific Standard Time) Energy Storage and Distributed Energy Resources Phase 2 Customer Partnership Group March 27, 2018 1 p.m. 2 p.m. (Pacific Standard Time) Agenda Item Project Schedule Update New Baseline Requests - Submittal

More information

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process

Order No Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Order No. 1000 Compliance Filing Related to Interconnection Issues Proposed Transmission Interconnection Process Thinh Nguyen Manager, Interconnection Projects New York Independent System Operator Joint

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents Appendix M... 2 Dynamic Scheduling Protocol (DSP)... 2 1. DYNAMIC SCHEDULES OF IMPORTS TO THE CAISO BALANCING AUTHORITY AREA... 2 1.2 Contractual Relationships... 2 1.3 Communications,

More information

Market Simulation Early 2016 Release

Market Simulation Early 2016 Release Market Simulation Early 2016 Release Christopher McIntosh Lead Market Simulation Coordinator Early 2016 Release Market Simulation Phase 1 November 30 th, 2015 Agenda Early 2016 Market Simulation Initiatives

More information

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission The following White Paper proposes a draft methodology for determining the incremental amount of transfer capability that would be the basis for the quantity of Merchant Transmission CRRs to be allocated

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan

Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision

More information

Solar*Rewards Community MN Application Manual

Solar*Rewards Community MN Application Manual Solar*Rewards Community MN Application Manual Version 2.0 February 2018 Contents 1. Introduction... 4 2. Application Form: Submission and Validation - Submitting Application Form... 5 2.1. Overview...

More information

Customer Inquiry, Dispute & Information (CIDI) User Guide

Customer Inquiry, Dispute & Information (CIDI) User Guide U S E R G U I D E CALIFORNIA ISO Customer Inquiry, Dispute & Information (CIDI) User Guide Revision History Version Date Description By 1.0 04/26/10 CIDI initial user guide Latisha Collins 1.1 04/27/10

More information

Business Practice Manual Change Management Meeting

Business Practice Manual Change Management Meeting Business Practice Manual Change Management Meeting Name Chris Kirsten Date February 26, 2013 Web Address: https://www.webmeeting.att.com Meeting Number: 5114682337 Access code: 9842446 Teleconference Dial-in

More information

Entergy Arkansas, Inc. Transition Plan Technical Conference #1

Entergy Arkansas, Inc. Transition Plan Technical Conference #1 Entergy Arkansas, Inc. Transition Plan Technical Conference #1 May 5, 2010 1 Why Technical Conferences? Complex subject matter Venue for stakeholders to develop an awareness and understanding of the issues

More information

FY2016 FCC Form 470 and Competitive Bidding

FY2016 FCC Form 470 and Competitive Bidding and Competitive Bidding Slide 1 Table of Contents Topic Page The E-Rate Process 3 Making a Plan 5 The Basics 11 Filing a Form 470 21 Form Actions 25 Form 470 Section One: Basic Information 29 Form 470

More information

IATF Transition Strategy Presenter: Mrs. Michelle Maxwell, IAOB

IATF Transition Strategy Presenter: Mrs. Michelle Maxwell, IAOB IATF 16949 Transition Strategy Presenter: Mrs. Michelle Maxwell, IAOB IATF 16949 Transition Strategy IATF 16949 transition strategy was presented at the IATF global stakeholder conference in Rome, Italy

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM)

Business Practice Manual For. Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM) Business Practice Manual For Generator Interconnection and Deliverability Allocation Procedures (GIDAP) BPM) Version 1.0 Last Revised: June 176July 26, 2013 Approval History Approval Date: MM DD YYYY07/26/2013

More information

GUIDANCE: INSTALLED CAPACITY & FINAL INSTALLED CAPACITY Version 1

GUIDANCE: INSTALLED CAPACITY & FINAL INSTALLED CAPACITY Version 1 GUIDANCE: INSTALLED CAPACITY & FINAL INSTALLED CAPACITY Version 1 Contents 1. Introduction 3 2. Installed Capacity 3 3. Final Installed Capacity 5 Low Carbon Contracts Company Ltd Guidance: Installed Capacity

More information

E-rate Program Applicant Training Fiber Options

E-rate Program Applicant Training Fiber Options E-rate Program Applicant Training Fiber Options September November 2016 Agenda 1. Identifying Eligible Fiber Services and Charges 2. Requesting Proposals for Fiber Options 3. Selecting the Most Cost-Effective

More information

Guidance version control

Guidance version control Guidance version control Guidance version control Contents v2.0 2 v3.0 3 v4.0 4 v5.0 6 v6.0 8 v7.0 9 v8.0...12 v9.0...13 National Grid EMR Delivery Body Page 1 v2.0 Slide 79 If the CMU is new and you want

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

ecampus Submission Process

ecampus Submission Process ecampus Submission Process Progress Report Submission, and Installment Submission & Feedback 1 All Progress Reports and Installment Submissions are found on the Assignments Page. 2 Individual assignments

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

ONCOR INFRASTRUCTURE DEVELOPMENT

ONCOR INFRASTRUCTURE DEVELOPMENT ONCOR INFRASTRUCTURE DEVELOPMENT Ellen Buck Presentation to Leadership North Texas March 27, 2015 ONCOR: 100 YEARS AND COUNTING Largest Texas regulated utility More than 3,000 employees 10 million living

More information