1 Decision Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014

2 The Alberta Utilities Commission Decision : Alberta Electric System Operator Needs Identification Document Application No Facility Application Application No Proceeding No September 24, 2014 Published by The Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 The Alberta Utilities Commission Calgary, Alberta Alberta Electric System Operator Needs Identification Document Decision Applications No and No Facility Application Proceeding No Introduction and background 1. The Alberta Electric System Operator (AESO) filed a needs identification document (NID) as Application No with the Alberta Utilities Commission (AUC or the Commission) on June 25, 2014, pursuant to Section 34 of the Electric Utilities Act, regarding the need to construct facilities for a customer connection in the Fort Hills area. 2. The development described in the NID would include the following components: a) the construction of the Secord 2005S substation, b) the alteration of transmission line 9L32, and c) the construction of approximately 2.2 kilometres of two single-circuit 24-kilovolt (kv) transmission lines (635PL and 635PL9-1001) connecting Secord 2005S substation to Fort Hills 505S substation. 3. Pursuant to Section 35 of the Electric Utilities Act, the AESO directed ATCO Electric Ltd. (ATCO) to submit a facility application to the AUC to meet the first two components of the NID identified above. 4. ATCO filed Application No (the facility application) with the AUC on June 26, 2014, pursuant to Section 14 of the Hydro and Electric Energy Act, for approval to construct Secord 2005S substation, to alter and salvage a portion of existing transmission line 9L32; and, pursuant Section 15 of the Hydro and Electric Energy Act, to operate the Secord 2005S substation. 5. Pursuant to Section 15.4 of the Hydro and Electric Energy Act, the AESO and ATCO requested that the Commission consider the need application and the facility application jointly. The Commission considered the applications jointly as Proceeding No On July 29, 2014, the Commission issued information requests to ATCO. ATCO responded to the information requests on August 15, On August 11, 2014, the Commission issued a notice of applications for Proceeding No. 3317, with a deadline date of August 29, 2014 to file submissions. The notice was sent to market participants, landowners, companies and agencies within 800 metres of the proposed AUC Decision (September 24, 2014) 1

4 Alberta Electric System Operator and development. The notice was also distributed electronically to market participants and published on the AUC website. No objections to the applications were received. 8. On June 4 and July 7, 2014, Fort Hills Energy Corporation (Fort Hills) filed, Applications No and No for approval of transmission lines designated as 635PL and 635PL (the transmission lines). The transmission lines would be used to connect Fort Hills 505S substation to Secord 2005S substation. The Fort Hills applications are presently under consideration by the Commission in Proceeding No Discussion NID application 9. The AESO stated that the proposed facilities would be required to supply Fort Hills load and future industrial electric load in the same area. 10. The AESO requested the assistance of ATCO in conducting a participant involvement program respecting the need of the proposed transmission facilities. Facility application 11. To meet two components of the need identified in the AESO s NID, ATCO proposed to construct the Secord 2005S substation and alter 240-kV transmission line 9L32 to connect Secord 2005S substation to the Alberta Interconnected Electric System. 12. The Secord 2005S substation would be located in the northwest quarter of Section 6 and the southwest quarter of Section 7 of Township 97, Range 10, west of the Fourth Meridian. There would be five 240-kV circuit breakers in the proposed substation within a 96-metre by 356-metre fenced area. 13. ATCO proposed to decommission and salvage approximately 305 metres of the existing transmission line 9L32 just outside of Secord 2005S substation bisecting the transmission line into two segments. 14. The segment of existing transmission line 9L32 between Joslyn 849S substation and Secord 2005S substation would continue to be operated as 9L32. The other segment of the transmission line between Secord 2005S substation and McClelland 957S substation would be renumbered as 9L101. Transmission lines 9L32 and 9L101 would both be terminated at Secord 2005S substation. 15. The cost of the project was estimated to be approximately $21 million and was classified as a participant-related cost, paid for by Fort Hills Energy Corporation. 16. ATCO indicated that the equipment to be installed in the substation would not produce continuous noise; therefore, a noise impact assessment was not prepared. 2 AUC Decision (September 24, 2014)

5 Alberta Electric System Operator and 17. The proposed Secord 2005S substation site was selected for the following reasons: a) it is adjacent to existing linear disturbances, b) it is close to an existing access road to Fort Hills mine expansion, c) it is in the vicinity of the Fort Hills 505S substation, and d) it would avoid the Athabasca River valley, and key wildlife and biodiversity zones, resulting in reduction of overall impacts on stakeholders and the surrounding environment. 18. The substation site is forested and non-forested industrially developed Crown land within the Lower Athabasca Regional Plan (LARP). ATCO stated that the proposed substation development is consistent with the LARP requirements. 19. ATCO submitted that it conducted a joint participant involvement program for both the needs and facility applications that included all occupants, landowners, companies, agencies within 800 metres of the proposed facilities. ATCO submitted that it received no objections or concerns about the proposed facilities. 20. ATCO stated that the proposed substation development would adhere to the Alberta Environment and Sustainable Resource Development environmental protection guidelines. 21. ATCO stated that the Regional Municipality of Wood Buffalo is the municipal authority pursuant to the Municipal Government Act. The proposed facilities are exempt from Part 17 of the Municipal Government Act with respect to subdivision and development approvals. 22. ATCO submitted that it received Historical Resources Act clearance from Alberta Culture on May 29, ATCO indicated that it would provide structure design details to NAV Canada following completion of the transmission line design. ATCO also stated that, if required, it would apply to Transport Canada for Aeronautical Obstruction Clearance and would comply with the Aeronautics Act. 3 Findings 24. After a review of the applications filed by the AESO and ATCO, the Commission finds that the applications meet the information requirements stipulated in AUC Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments (AUC Rule 007). 25. Because no interested party has demonstrated that the AESO s assessment of the need for the proposed facilities is technically deficient or not in the public interest, the Commission approves the needs identification document application pursuant to Section 38(e) of the Transmission Regulation. 26. The Commission finds that the facility application for the proposed substation and transmission line alterations proposed by ATCO satisfy the need as identified by the AESO NID. AUC Decision (September 24, 2014) 3

6 Alberta Electric System Operator and 27. The Commission recognizes that a participant involvement program was completed, and that there are no outstanding objections or concerns with the applications. The Commission finds that the participant involvement program meets the requirements of AUC Rule 007. The Commission notes that there were no objections in response to the notice of applications. 28. The Commission relies on ATCO s commitments that the relevant sections of the Alberta Environmental Protection and Enhancement Act, the Environmental Protection Guidelines for transmission lines and other relevant regulations and guidelines will be complied with. 29. The Commission acknowledges that the project is within the Lower Athabasca Regional Plan area and is satisfied that the project is in accordance with the requirements of the LARP. 30. The Commission considers that the technical, siting and environmental aspects of the facilities, as specified in AUC Rule 007, have been met. 31. Given the considerations discussed above, the Commission finds the proposed project to be in the public interest pursuant to Section 17 of the Alberta Utilities Commission Act. 4 Decision 32. Pursuant to Sections 34 of the Hydro and Electric Energy Act, the Commission approves the needs identification application and grants the AESO the approval set out in Appendix 1 Needs Identification Document Approval No. U September 24, Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission approves the facility application and grants to ATCO: Permit and Licence No. U September 24, 2014, to construct and operate the Secord 2005S substation as set out in Appendix 2. Permit and Licence No. U September 24, 2014, to alter and operate 240-kV transmission line 9L32 set as set out in Appendix 3. Permit and Licence No. U September 24, 2014, to alter and operate 240-kV transmission line 9L101 as set out in Appendix 4. Approval No. U September 24, 2014, to salvage a portion of transmission line 9L32 as set out in Appendix The appendices will be distributed separately. Dated on September 24, The Alberta Utilities Commission (original signed by) Anne Michaud Commission Member 4 AUC Decision (September 24, 2014)

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application

More information

ENMAX Generation Portfolio Inc.

ENMAX Generation Portfolio Inc. Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. September 5, 2017 Alberta Utilities Commission Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. Proceeding 22192 Application 22192-A002 September

More information

Ells River Substation Telecommunication Tower

Ells River Substation Telecommunication Tower January 2013 Why are you receiving this project information package? We are advising neighbouring landholders, agencies and other interested parties about plans to construct the Ells River substation telecommunication

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP)

AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP) APPENDIX B AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP) Sunnybrook and Livock Substation Modifications Needs Identification Document 1.0 Participant Involvement Program From May 2015 to August 2015, the

More information

Benbow 397S Substation Upgrade Needs Identification Document

Benbow 397S Substation Upgrade Needs Identification Document APPENDIX C AESO PIP Benbow 397S Substation Upgrade Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to December 2015, the AESO conducted a Participant Involvement Program

More information

MFC Power General Partner Ltd.,

MFC Power General Partner Ltd., Decision 21950-D01-2016 Preferential Sharing of Records Between, MFC Power Limited Partnership, URICA Energy Real Time Ltd., and URICA Asset Optimization Ltd. October 12, 2016 Alberta Utilities Commission

More information

PARTICIPANT INVOLVEMENT PROGRAM

PARTICIPANT INVOLVEMENT PROGRAM ATTACHMENT 3 PARTICIPANT INVOLVEMENT PROGRAM Southern Alberta Transmission Reinforcement Amendment Needs Identification Document Approval Amendment 1.0 Participant Involvement Program From July to December

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

Jenner Wind Energy Connection Needs Identification Document

Jenner Wind Energy Connection Needs Identification Document APPENDIX C AESO PIP Jenner Wind Energy Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From November 2015 to May 2016, the AESO conducted a participant involvement program

More information

Vegreville Office Telecommunication Tower Replacement

Vegreville Office Telecommunication Tower Replacement Project Need and Details March 2012 If approved, the proposed Vegreville Office Telecommunication Tower Replacement will be located on the current tower site at 6502-55 Avenue in the Town of Vegreville.

More information

User Guide. March 2017

User Guide. March 2017 User Guide March 2017 Alberta Utilities Commission efiling System User Guide Fifth Avenue Place Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Phone: 403-592-4500 Email: info@auc.ab.ca www.auc.ab.ca

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

Project Data Update Package Instruction Manual (PDUP-IM)

Project Data Update Package Instruction Manual (PDUP-IM) Project Data Update Package Instruction Manual (PDUP-IM) Date: April 11, 2018 Prepared by: Reviewed by: Approved by: Khalid Rafiq, P. Eng. Modelling Engineer, Transmission Project Delivery Christopher

More information

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

Environmental Impact Questionnaire

Environmental Impact Questionnaire Community Development Department 11 English Street Petaluma, CA 94952 Phone: 707-778-4301 Email: cdd@ci.petaluma.ca.us Web: www.cityofpetaluma.net/cdd Building Geographic Information Systems Housing Neighborhood

More information

CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA

CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA SEPTEMBER 19, 2012 AT 9:00 AM FIRST FLOOR, ORTH CO FERE CE ROOM CITY HALL 10205 98 STREET ATTE DEES Councillor J. Croken L. Coulter

More information

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton (February 2002) (Revised, January 2011) Council approval CW062-2011 (Revised, February 2011) revisions

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

CIP Standards Development Overview

CIP Standards Development Overview CIP Standards Development Overview CSSDTO706 Meeting with FERC Technical Staff July 28, 2011 Objectives Historical Timeline CIP-002-4 CIP-005-4 CIP Version 5 2 Project 2008-06 Overview FERC Order 706 SDT

More information

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES PROOF OF SERVICE NOTICE TO COMMUNITY ORGANIZATIONS PUBLIC NOTICE NOTICE IN UTILITY BILLS NOTICE OF OWNERS OF PROPERTY

More information

Ministry of Energy, Mines and Petroleum Resources. Guide to Acquiring Crown Petroleum and Natural Gas Tenures

Ministry of Energy, Mines and Petroleum Resources. Guide to Acquiring Crown Petroleum and Natural Gas Tenures Ministry of Energy, Mines and Petroleum Resources Guide to Acquiring Crown Petroleum and Natural Gas Tenures March 2018 1 Summary of Revisions Effective date Section Description March 2018 Reconfigured

More information

EBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston

EBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston EBR Application for Review Request to Review Environmental Compliance Approval Cruickshank Construction Limited Elginburg Quarry, Kingston Decision Summary EBRO File No.: 16EBR001.R Issue: The Ministry

More information

Balance of Power in the Hudson Valley

Balance of Power in the Hudson Valley 1 Balance of Power in the Hudson Valley Chris Hogan, NYSDEC Major Project Management Unit May 3, 2017 2 Objective Provide an overview of the various state and federal processes by which energy projects

More information

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax: B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: 0-- E-mail: janet.fraser@bctc.com October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street,

More information

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator

Written Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator Assembly Standing Committee on Energy Kevin A. Cahill, Chairman Assembly Standing Committee on Corporations, Authorities and Commissions James F. Brennan, Chairman Assembly Standing Committee on Cities

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Downtown Boise Multimodal Center

Downtown Boise Multimodal Center Treasure Valley High Capacity Transit Study Downtown Boise Multimodal Center Environmental Assessment June 2009 Prepared by the Federal Transit Administration and Valley Regional Transit. U.S. Department

More information

Standard CIP Cyber Security Security Management Controls

Standard CIP Cyber Security Security Management Controls A. Introduction 1. Title: Cyber Security Security Management Controls 2. Number: CIP-003-4 3. Purpose: Standard CIP-003-4 requires that Responsible Entities have minimum security management controls in

More information

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY May 19, 2011 Community Meeting Metro Toronto Convention Centre North Building, Room 203B May 19 th, 2011, 4:30 p.m. to 7:30 p.m. Please sign in and complete a comment sheet Project team members are available

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

Standard CIP Cyber Security Critical Cyber Asset Identification

Standard CIP Cyber Security Critical Cyber Asset Identification Standard CIP 002 1 Cyber Security Critical Cyber Asset Identification Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed

More information

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES P AGE 129 A-1 A-2 A-3 A-4 A-5 A-6 A-7 A-8 A-8 A-9 B-1 B-2 B-3 B-4 B-6 B-5 March 24, 2015 Scott Johnson Community

More information

NOTICE OF APPLICATION AND WRITTEN HEARING

NOTICE OF APPLICATION AND WRITTEN HEARING Ontario Energy Board Commission de l énergie de l Ontario EB-2012-0305 NOTICE OF APPLICATION AND WRITTEN HEARING Application by Hydro One Networks Inc. and Kitchener-Wilmot Hydro Inc. for Licence Amendments

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF SEPTEMBER 25, 2012 Item 23, Report No. 33, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan

More information

Alberta Reliability Standards Compliance Monitoring Program. Version 1.1

Alberta Reliability Standards Compliance Monitoring Program. Version 1.1 Version 1.1 Effective: January 14, 2011 Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Applicability... 1 4. Definitions... 1 5. Compliance Monitoring Overview... 2 6. Monitoring Tools... 1

More information

Baseline Bridge Crossing. Priorities Committee Meeting

Baseline Bridge Crossing. Priorities Committee Meeting Baseline Bridge Crossing Priorities Committee Meeting June 14, 2016 1 Unparalleled Asset Footprint Largest Energy Infrastructure Company in North America Over 12,000 employees in Canada and the U.S. $18.2

More information

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ]

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] DATE: April 8, 2013 REPORT NO. CD2013-040 TO: FROM: Chair and Members Committee of the Whole Community Services Gregory Dworak, General Manager Community Services 1.0 TYPE OF REPORT CONSENT ITEM [ ] ITEM

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Interpretations for the SFI Standards and Rules. January 2017

Interpretations for the SFI Standards and Rules. January 2017 Interpretations for the SFI 2015-2019 Standards and Rules January 2017 Official SFI Standard Interpretations contained in this document are auditable requirements 1 Table of Contents Table of Contents...

More information

Revisions to the Right-of-Way Management Ordinance for Wireless Providers Implementing SB1004

Revisions to the Right-of-Way Management Ordinance for Wireless Providers Implementing SB1004 Revisions to the Right-of-Way Management Ordinance for Wireless Providers Implementing SB1004 Economic Development & Housing Committee August 21, 2017 Don Knight, Senior Assistant City Attorney Rick Galceran,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E For a Permit to Construct Electrical Facilities With Voltages

More information

Content Copy Of Original

Content Copy Of Original Content Copy Of Original Ministry of the Environment and Climate Change Ministère de l Environnement et de l Action en matière de changement climatique Hydro One Networks Inc. 483 Bay St 14th Floor, South

More information

Budget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017

Budget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017 2017-18 Budget Review Process (BRP) Preliminary List of Business Initiatives Stakeholder Meeting April 10, 2017 Purpose / Agenda The purpose of this presentation is to: Provide stakeholders with a BRP

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Eldorado-Lugo-Mohave

More information

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY

TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY POLICY P-22 TELECOMMUNICATION FACILITIES SITING AND CONSULTATION POLICY Preamble It is recognized that while reliable and sophisticated telecommunication facilities are a benefit to the citizens of (CSRD),

More information

Exhibit 25.A. June 2, [First Name] [Last Name] [Suffix] [Address_1] [Address_2] [City], [State] [Zip]

Exhibit 25.A. June 2, [First Name] [Last Name] [Suffix] [Address_1] [Address_2] [City], [State] [Zip] June 2, 2017 [First Name] [Last Name] [Suffix] [Address_1] [Address_2] [City], [State] [Zip] Application of Pedernales Electric Cooperative, Inc. to Amend its Certificate of Convenience and Necessity for

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

ENVIRONMENTAL ASSESSMENT WORKSHEETS EAW Comment Deadline: June 17, 2009

ENVIRONMENTAL ASSESSMENT WORKSHEETS EAW Comment Deadline: June 17, 2009 Next Publication: June 1, 2009 Vol. 33, No.10 Submittal Deadline: May 22, 2009 Project Title: ENVIRONMENTAL ASSESSMENT WORKSHEETS EAW Comment Deadline: June 17, 2009 Project Title: Pierce Butler Route

More information

DESCRIPTION OF COST ALLOCATION METHODOLOGY

DESCRIPTION OF COST ALLOCATION METHODOLOGY Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate

More information

Self-Certification Tutorial. Version 1.0 April 2013

Self-Certification Tutorial. Version 1.0 April 2013 Version 1.0 April 2013 The PLAN At the end of this tutorial, you will be able to: 1. Describe the purposes of Self-Certification 2. Identify deadlines 3. Describe the use of the Self-Certification template

More information

BC OnLine. Site Registry User s Guide. Last Updated June 11, 2014

BC OnLine. Site Registry User s Guide. Last Updated June 11, 2014 BC OnLine Site Registry User s Guide Last Updated June 11, 2014 Copyright Copyright 2014 Province of British Columbia. All rights reserved. This user s guide is for users of the BC OnLine services who

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

SUBSTATION PERMITTING & SITING

SUBSTATION PERMITTING & SITING SYMPOSIUM SUBSTATION PERMITTING & SITING September 27, 2017 Sheraton Denver Downtown Hotel Denver, CO TAG US #EUCIEvents FOLLOW US @EUCIEvents EUCI is authorized by IACET to offer 0.8 CEUs for the symposium

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON ENTERED MAY 05 2nl1 In the Matter of BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON CP 1503 CP 1465 ZA YO GROUP, LLC and ZA YO BANDWIDTH, LLC ORDER Application to Transfer a Certificate of Authority to

More information

CITY OF KIRKLAND TRAFFIC IMPACT ANALYSIS GUIDELINES

CITY OF KIRKLAND TRAFFIC IMPACT ANALYSIS GUIDELINES CITY OF KIRKLAND TRAFFIC IMPACT ANALYSIS GUIDELINES SEPA TRANSPORTATION CONCURRENCY - ROAD IMPACT FEES Introduction Revised February 2004 These guidelines describe how to prepare a traffic study, or Traffic

More information

CHARTER TOWNSHIP OF ALLENDALE, OTTAWA COUNTY, MICHIGAN WIRELESS COMMUNICATION FACILITIES APPLICATION

CHARTER TOWNSHIP OF ALLENDALE, OTTAWA COUNTY, MICHIGAN WIRELESS COMMUNICATION FACILITIES APPLICATION CHARTER TOWNSHIP OF ALLENDALE, OTTAWA COUNTY, MICHIGAN WIRELESS COMMUNICATION FACILITIES APPLICATION This application is to be completed in compliance with Article 25 of the Charter Township of Allendale

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

CAW Clean Wind Energy Project

CAW Clean Wind Energy Project Prepared by: M.K. Ince and Associates Ltd. September 19, 2012 Amended March 11, 2013 Table of Contents 1 INTRODUCTION... 1 2 PURPOSE... 1 3 COMPLAINT RESPONSE PROTOCOL... 1 3.1 COMPLAINT INITIATION...

More information

Unique Well Identifiers. General Description

Unique Well Identifiers. General Description Appendix 2 Unique Well Identifiers General Description The unique well identifier (UWI) is the standard well identification that was developed for the petroleum industry by the Geoscience Data Committee

More information

What is Integrated Land Management?

What is Integrated Land Management? What is Integrated Land Management? What is ILM? ILM is the strategic, planned way of doing business ILM is the approach ILM promotes the responsible use of public land ILM is about managing the impact

More information

Application for Variance in a Regional Plan

Application for Variance in a Regional Plan Form (LUS-O2) Land Use Secretariat 9th floor, Centre West Building 10035 108 Street Edmonton, AB T5J 3E1 TEL: 780-644-7972 or Toll Free Rite Line at: 310-0000 FAX: 780-644-1034 Alberta Land Stewardship

More information

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km) nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Welcome Thank you for attending this community engagement on the Trans- Canada Highway 1 West Project, part of the Highway

More information

Rules on Standards for Requesting and Exchanging Site-Specific Historic Usage Information for Retail Electricity and Natural Gas Markets

Rules on Standards for Requesting and Exchanging Site-Specific Historic Usage Information for Retail Electricity and Natural Gas Markets Rule 010 Rules on Standards for Requesting and Exchanging Site-Specific Historic Usage Information for Retail Electricity and Natural Gas Markets This rule was approved by the Alberta Utilities Commission

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

Quest Carbon Capture and Storage Project. Appendix J Public Consultation Activities

Quest Carbon Capture and Storage Project. Appendix J Public Consultation Activities Quest Carbon Capture and Storage Project Appendix J: Public Consultation Activities Appendix J Public Consultation Activities Shell Canada Limited Appendix J: Public Consultation Activities Quest Carbon

More information

Re: Filing of Windstream's Comments to Notice of Proposed Rulemaking; Case No. NNTRC

Re: Filing of Windstream's Comments to Notice of Proposed Rulemaking; Case No. NNTRC New Mexico Office of External Affairs 1660 Old Pecos Trail- Suite D Santa Fe; NM 87505 1:505.9559700 f:505.955.9699 windstream September 19, 2011 Executive Director Navajo Nation Telecommunications Regulatory

More information

(a) Discourages obtrusive Telecommunication Facilities within or adjacent to Residential Areas, Heritage Areas and Environmentally Sensitive Areas;

(a) Discourages obtrusive Telecommunication Facilities within or adjacent to Residential Areas, Heritage Areas and Environmentally Sensitive Areas; POLICY NUMBER: C471C REFERENCE: ADOPTED BY: City Council City Council 1997 07 15 C471A January 23, 2013 City Council 1998 07 07 C471A SUPERSEDES: City Council 2006 05 09 C471B C471B PREPARED BY: Sustainable

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

RCMP Support / Bylaw Services Department

RCMP Support / Bylaw Services Department RCMP Support / Bylaw Services Department business plan 2012-2014 TABLE OF CONTENTS 1. Our Services 1.1 Our Mandate 1.2 Lines of Business 2. Accomplishments 3. Implementing Sustainability 3.1 Strategy 1

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

Stakeholder Engagement Summary Report

Stakeholder Engagement Summary Report Stakeholder Engagement Summary Report South Shore Corridor Project 1. INTRODUCTION 1.1 Project Overview Port Metro Vancouver s South Shore Trade Area is of critical importance to Canadian trade. One of

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

CITY OF TORONTO TELECOMMUNICATION TOWER AND ANTENNA PROTOCOL (Industry Canada Local Land-use Authority Consultation)

CITY OF TORONTO TELECOMMUNICATION TOWER AND ANTENNA PROTOCOL (Industry Canada Local Land-use Authority Consultation) Attachment 1: Approved Telecommunications Protocol (Adopted by City Council - March 3, 4 and 5, 2008) CITY OF TORONTO TELECOMMUNICATION TOWER AND ANTENNA PROTOCOL (Industry Canada Local Land-use Authority

More information

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path

System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power

More information

Standards Authorization Request Form

Standards Authorization Request Form Standards Authorization Request Form When completed, email this form to: sarcomm@nerc.com NERC welcomes suggestions to improve the reliability of the bulk power system through improved reliability standards.

More information

South West Scotland Renewables Connection Project Environmental Statement Scoping Report Executive Summary

South West Scotland Renewables Connection Project Environmental Statement Scoping Report Executive Summary South West Scotland Renewables Connection Project Environmental Statement Scoping Report Executive Summary September 2007 EXECUTIVE SUMMARY Background This Environmental Impact Assessment (EIA) Scoping

More information

Connecticut Department of Department of Administrative Services and the Broadband Technology Opportunity Program (BTOP) 8/20/2012 1

Connecticut Department of Department of Administrative Services and the Broadband Technology Opportunity Program (BTOP) 8/20/2012 1 Connecticut Department of Department of Administrative Services and the Broadband Technology Opportunity Program (BTOP) 8/20/2012 1 Presentation Overview What is BTOP? Making BTOP work for our state What

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

ELECTRONIC ASSIGNMENTS PROCEDURES GUIDE. June 2006

ELECTRONIC ASSIGNMENTS PROCEDURES GUIDE. June 2006 ELECTRONIC ASSIGNMENTS PROCEDURES GUIDE June 2006 June 2006 1 INTRODUCTION... 3 1.1 WHAT ARE ELECTRONIC ASSIGNMENTS?... 3 2 OVERVIEW... 4 3 GETTING STARTED... 5 3.1 NEW CLIENT OR EXISTING CLIENT?... 5

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Guidance of NOP Certification system Page 1/8

Guidance of NOP Certification system Page 1/8 Page 1/8 I. Introduction A. Regulation Since October 21, 2002, The USDA implemented its organic regulations for the production, labeling, and inspection of organic products: the National Organic Program

More information

Gatekeeper and Notice Requirements For Direct Electronic Access and Routing Arrangements

Gatekeeper and Notice Requirements For Direct Electronic Access and Routing Arrangements Rules Notice Technical UMIR Please distribute internally to: Institutional Legal and Compliance Senior Management Trading Desk Contact: Naomi Solomon Senior Policy Counsel, Market Regulation Policy Telephone:

More information

Appendix A Existing Surface Utilities

Appendix A Existing Surface Utilities Appendix A Existing Surface Utilities PRELIMINARY INFRASTRUCTURE STUDY PROPOSED DUSEL SITE GILES COUNTY, VIRGINIA Prepared for: Kimballton Deep Underground Science and Engineering Laboratory Kimballton

More information

Schools and Libraries (E-rate) Program FCC Form 473 User Guide

Schools and Libraries (E-rate) Program FCC Form 473 User Guide Schools and Libraries (E-rate) Program FCC Form 473 User Guide 1 Universal Service Administrative Company FCC Form 473 (SPAC) User Guide TABLE OF CONTENTS Contents Purpose of FCC Form 473... 3 Before You

More information

DARRYL CARTER &COMPANY Barristers & Solicitors

DARRYL CARTER &COMPANY Barristers & Solicitors Darryl Carter, a.c. (also of the California Bar) Mikle L. Carter Jennifer Wilkie DARRYL CARTER &COMPANY Barristers & Solicitors C11-1 103,10134-97 Avenue Grande Prairie, Alberta T8V7X6 Phone (780) 882-7296

More information

Prepared Testimony of. Bohdan R. Pankiw. Chief Counsel Pennsylvania Public Utility Commission. before the

Prepared Testimony of. Bohdan R. Pankiw. Chief Counsel Pennsylvania Public Utility Commission. before the Prepared Testimony of Bohdan R. Pankiw Chief Counsel Pennsylvania Public Utility Commission before the Pennsylvania Senate Consumer Protection and Professional Licensure Committee and Pennsylvania Senate

More information

European Code of Conduct on Data Centre Energy Efficiency

European Code of Conduct on Data Centre Energy Efficiency EUROPEAN COMMISSION DIRECTORATE-GENERAL JOINT RESEARCH CENTRE Institute for Energy and Transport Renewable Energy Unit European Code of Conduct on Data Centre Energy Efficiency Introductory guide for applicants

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of December 12, 2015 DATE: December 1, 2015 SUBJECT: SP-84-U-15-1 USE PERMIT ASSOCIATED WITH A SITE PLAN for a telecommunications facility; located

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Cerritos

More information

SITE DESCRIPTION. Vicinity

SITE DESCRIPTION. Vicinity SITE DESCRIPTION Vicinity The Montrose Shopping Center is located in the northeast quadrant of the intersection of Randolph Road and Rockville Pike (MD 355). The existing building (formally known as the

More information

Georgia: Power Transmission Enhancement Project financed by Asian Development Bank (ADB)

Georgia: Power Transmission Enhancement Project financed by Asian Development Bank (ADB) Asian Development Bank Project Number: 2974-GEO Georgia: Power Transmission Enhancement Project financed by Asian Development Bank (ADB) Bi-Annual Land Acquisition and Resettlement Plan, November 2013

More information

RECORD OF PRE-APPLICATION MEETING FOR THE PROPOSED SANRAL PROJECT TO WIDEN THE N3 (AND PORTION OF N2) BETWEEN DURBAN AND PIETERMARITZBURG

RECORD OF PRE-APPLICATION MEETING FOR THE PROPOSED SANRAL PROJECT TO WIDEN THE N3 (AND PORTION OF N2) BETWEEN DURBAN AND PIETERMARITZBURG RECORD OF PRE-APPLICATION MEETING FOR THE PROPOSED SANRAL PROJECT TO WIDEN THE N3 (AND PORTION OF N2) BETWEEN DURBAN AND PIETERMARITZBURG Date: 25 th July 2016 Location: Department of Environmental Affairs,Environmental

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information