1 Project Presentation April, 2017
2 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern California Edison s Colorado River Substation (Blythe, CA) Permitting agencies: Bureau of Land Management ( BLM ), Arizona Corporation Commission ( ACC ), California Public Utilities Commission ( CPUC ) Enables variety of renewable energy development and integration, system economics and reliability benefit to the electric consumers in AZ and CA Commercial Operation: May 2020 Entire cost will be paid by ratepayers of California Independent System Operators ( CAISO )
3 Project Ownership CAISO selected DCR Transmission LLC ( DCRT ) as project sponsor, July 2015 DCRT: Joint venture led by Starwood Energy Group Global Inc. (Private equity company specializing in investing in energy infrastructure projects in North America) Project awarded to DCRT under cost cap, specified project specifications and strict project completion date requirement When completed: o Ten West will be under operational control of CAISO and transmission capacity will become a part of CAISO network o DCRT will become Participating Transmission Owner with CAISO and achieve a Utility status with the CPUC o Transmission Revenue Requirement ( TRR ) will be approved by Federal Energy Regulatory Commission ( FERC ) and collected by CAISO from its customers based upon CAISO rules
4 Project Purpose, Need & Benefits Establish new reliable/economic transmission interconnection between two critical transmission hubs in AZ and CA to strengthen regional transmission system reliability, improve operational flexibility and increase transmission system efficiency by decreasing congestion Benefits o Facilitate development of new renewable energy resources and renewable energy zones o Provide Load Serving Entities (LSE) in CA and AZ access to efficient, cost effective renewable resources o Provide economic benefits to ratepayers within CAISO Controlled Grid as well as AZ ratepayers o Improve regional collaboration and provide improved access to diverse cost effective, environmentally friendly resources, thereby enhancing renewable integration o Promote regional economic development
5 Major Regulatory Requirements ACC (and Arizona Siting Committee) will issue Certificate of Environmental Compatibility ( CEC ) BLM is lead federal agency for National Environmental Policy Act ( NEPA ) process o Preparation of Plan of Development ( POD ) o Preparation of draft and final Environmental Impact Statement ( EIS ) o Issue final Record of Decision (ROD) CPUC leads California Environmental Quality Act ( CEQA ) process (EIS will serve as CEQA Equivalent Document) CPUC will issue Certificate of Public Convenience and Necessity ( CPCN )
6 Project Proposed Route Alternatives Segments
7 Project Schedule Project awarded by CAISO July, 2015 Stakeholder Outreach July, 2015 May 2020 Right of Way / Land Acquisition October 2015 February 2019 BLM Issues Draft EIS October 2017 Engineering and Construction January 2018 May 2020 BLM Issues Final EIS May 2018 CPUC accepts EIS as CEQA Equivalent Document; Issues CPCN September 2018 ACC/Siting Committee issue CEC March 2018 Other Fed/State/Local Permits/Consultations September 2018 March 2019
8 Stakeholder Outreach & Engagement Launched October 2015: Broad Early Often (200+ briefings, presentations, mailings, website, factsheet, contact list, open houses, 800#) Stakeholders include: Cooperating Agencies, elected officials (local/state/federal), landowners, off highway vehicle users, environmental groups, community organizations, economic development entities, military, industry, and Native American Tribes Focus on populated areas: La Paz County (Town of Quartzsite, Ehrenberg), Riverside County (City of Blythe) and Maricopa County (Tonopah, Harquahala) DCRT is committed to continuing public outreach activities and working in collaboration with all key stakeholders throughout development and construction phase
9 Contact 844 Ten West ( )
Presentation to Local/State/Federal Agency Mtg November 10, 2015
Presentation to Local/State/Federal Agency Mtg November 10, 2015 Summary Proposed 114 mile 500 kv transmission project that will connect with Delaney Substation near Palo Verde Nuclear Generating Station,
More informationFrom: Laura Manz, Vice President of Market & Infrastructure Development
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional
More informationDelaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation
Steve Rutty Director, Grid Assets Lou Fonte Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Lead Engineer, Grid Assets September 3, 2014 Transmission Planning
More informationNorth Gila-Imperial Valley #2 Transmission Project
North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------
More informationTransWest Express Transmission Project Interregional Transmission Project Submittal
TransWest Express Transmission Project 2016 2017 Interregional Transmission Project Submittal Submittals to California Independent System Operator, WestConnect and Northern Tier Transmission Group March
More informationPhysical Security Reliability Standard Implementation
Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,
More informationISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO
ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call
More informationAmerican Transmission Company U.P. Energy Summit
American Transmission Company U.P. Energy Summit John Flynn Vice President Strategic Planning & Business Development October 26, 2011 Helping to keep the lights on, businesses running and communities strong
More informationSUNZIA SOUTHWEST TRANSMISSION PROJECT PROJECT UPDATE NEW MEXICO RETA David Getts General Manager SouthWestern Power Group
SUNZIA SOUTHWEST TRANSMISSION PROJECT David Getts General Manager SouthWestern Power Group PROJECT UPDATE NEW MEXICO RETA 8.22.12 SouthWestern Power Group Independent developer of utility-scale generation
More informationDowntown Boise Multimodal Center
Treasure Valley High Capacity Transit Study Downtown Boise Multimodal Center Environmental Assessment June 2009 Prepared by the Federal Transit Administration and Valley Regional Transit. U.S. Department
More informationCompetitive Solicitation Process Enhancements. Status Update / Issue Paper
Competitive Solicitation Process Enhancements Status Update / Issue Paper October 7, 2014 Table of Contents 1 Introduction... 3 2 Stakeholder process... 4 3 Background on the competitive solicitation process...
More informationPublic Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM
Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities
More informationTransmission Infrastructure By Public-Private Model
Portfolio Media, Inc. 648 Broadway, Suite 200 New York, NY 10012 www.law360.com Phone: +1 212 537 6331 Fax: +1 212 537 6371 customerservice@portfoliomedia.com Transmission Infrastructure By Public-Private
More informationATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n
RFP P5413 Contract No. 200703566 Work Order No. -07 ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n Prepared for: Metropolitan Atlanta Rapid Transit Authority Prepared by: DMJM Harris/JJG Joint
More informationEnergy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan
Energy Imbalance Market: PacifiCorp Stakeholder and Tariff Revision Plan Document Version 1.9 Date Updated: January 17, 2014 The following document outlines PacifiCorp s Stakeholder and Tariff Revision
More informationRegional Centers Framework Update. Regional Project Evaluation Committee March 24, 2017
Regional Centers Framework Update Regional Project Evaluation Committee March 24, 2017 Overview Background Project Overview and Previous Board Direction Overview of Stakeholder Working Group Report Process
More informationWarrenton Wheeler Gainesville 230kV Reliability Project
Warrenton Wheeler Gainesville 230kV Reliability Project February 28, 2013 Key Messages Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have been working together to address three
More informationMemorandum. This memorandum requires Committee action.
California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure
More informationReston Town Center North Development. Community Update
Reston Town Center North Development Community Update May 31, 2017 1 Presentation Agenda Project Overview Site and Current Property Ownerships Development Plan/Grid of Streets Proposed Ownership Comprehensive
More informationOffice of Indian Energy Policy and Programs
DOE OFFICE OF INDIAN ENERGY Office of Indian Energy Policy and Programs NETWIG January 2016 Sarai Geary, Program Manager, Office of Indian Energy Office of Indian Energy Policy and Programs MISSION To
More informationHistory of NERC December 2012
History of NERC December 2012 Timeline Date 1962-1963 November 9, 1965 1967 1967-1968 June 1, 1968 July 13-14, 1977 1979 1980 Description Industry creates an informal, voluntary organization of operating
More informationSECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS
SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES PROOF OF SERVICE NOTICE TO COMMUNITY ORGANIZATIONS PUBLIC NOTICE NOTICE IN UTILITY BILLS NOTICE OF OWNERS OF PROPERTY
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for the California Solar Initiative, the Self-Generation Incentive
More informationHistory of NERC January 2018
History of NERC January 2018 Date 1962 1963 The electricity industry created an informal, voluntary organization of operating personnel to facilitate coordination of the bulk power system in the United
More informationStem Beach Solar 1041 Application
Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project
More informationWestern Interconnection
Transmission Planning in the Western Interconnection Supporting Resource Development NWCC/NCSL Transmission Policy Institute Byron Woertz, Senior Project Manager Denver, CO June 17, 2010 Overview A Few
More informationHistory of NERC August 2013
History of NERC August 2013 Timeline Date 1962 1963 November 9, 1965 1967 1967 1968 June 1, 1968 July 13 14, 1977 1979 Description The electricity industry creates an informal, voluntary organization of
More informationITC HOLDINGS, CORP. Edison Electric Institute 9
ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER07-1034-002 REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)
More informationNVTC Data Center and Cloud Infrastructure Committee
NVTC Data Center and Cloud Infrastructure Committee Powering Virginia's High-Tech Economy and Preparing a Smarter Energy Grid for Future Growth Featured Presenters: October 25, 2017 Karen Jackson, Secretary
More informationHLG Briefly. HLG was established on March 6, 2015 during the 46 th Session of the UN Statistical Commission
HLG Briefly Activity of the High-Level Group for Partnership, Coordination and Capacity Building for Statistics for Agenda 030 on Sustainable Development (HLG) HLG was established on March 6, 015 during
More informationJuly 26, Dear Mr. Millar:
July 26, 2012 Mr. Neil Millar Executive Director Infrastructure Development California Independent System Operator Corporation 250 Outcropping Way Folsom, CA 95630 Dear Mr. Millar: As you are aware, Clean
More informationJohn P Buechler NYISO Executive Regulatory Policy Advisor. NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY
Eastern Interconnection Planning Collaborative Update John P Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY November 30, 2010
More informationFebruary 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426
California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California
More informationUnlocking Private Sector Financing for Alternative Fuel Vehicles and Fueling Infrastructure. Presentation to EIS 2013 April 8, 2013
+ Unlocking Private Sector Financing for Alternative Fuel Vehicles and Fueling Infrastructure Presentation to EIS 2013 April 8, 2013 + NASEO and the State Energy Offices (SEOs) Membership includes the
More informationBenbow 397S Substation Upgrade Needs Identification Document
APPENDIX C AESO PIP Benbow 397S Substation Upgrade Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to December 2015, the AESO conducted a Participant Involvement Program
More informationTransWest Express and Gateway South
TransWest Express and Gateway South Co-developed by four leading entities: Arizona Public Service PacifiCorp National Grid Wyoming Infrastructure Authority Regional Stakeholder Meeting January 23, 2008
More informationBalance of Power in the Hudson Valley
1 Balance of Power in the Hudson Valley Chris Hogan, NYSDEC Major Project Management Unit May 3, 2017 2 Objective Provide an overview of the various state and federal processes by which energy projects
More informationMountain West Transmission Group. Tim Vigil RT Merchant Manager Western Area Power Administration
Mountain West Transmission Group Tim Vigil RT Merchant Manager Western Area Power Administration Mountain West Transmission Group* Basin Electric Power Cooperative (BEPC) Black Hills Energy s three electric
More informationMountain West Transmission Group. WECC MIC Update October 17, 2017
Mountain West Transmission Group WECC MIC Update October 17, 2017 Agenda Overview Mountain West Activities Mountain West Analyses Mountain West Next Steps 2 Mountain West Overview 3 What is the Mountain
More informationSoutheast Florida Regional Climate Change Compact Update. Broward Climate Change Task Force February 16, 2017
Southeast Florida Regional Climate Change Compact Update Broward Climate Change Task Force February 16, 2017 Overview Recent Activities RCAP Update Forthcoming Efforts Regional Resilience Projects Summit
More informationDraft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission
The following White Paper proposes a draft methodology for determining the incremental amount of transfer capability that would be the basis for the quantity of Merchant Transmission CRRs to be allocated
More informationBoardman to Hemingway Project Advisory Team
Boardman to Hemingway Project Advisory Team Central Project Advisory Team Meeting 5 Tonight s Objectives Review progress of the Community Advisory Process and discuss next steps Present analysis of revised
More informationElectricity Sub-Sector Coordinating Council Charter FINAL DISCUSSION DRAFT 7/9/2013
Electricity Sub-Sector Coordinating Council Charter FINAL DISCUSSION DRAFT 7/9/2013 Purpose and Scope The purpose of the Electricity Sub-Sector Coordinating Council (ESCC) is to facilitate and support
More informationThe Blue Line Extension
The Blue Line Extension NORTH CAROLINA JOINT TRANSPORTATION OVERSIGHT COMMITTEE Presented by Carolyn Flowers CATS Chief Executive Officer Raleigh, NC February 10, 2012 Overview Charlotte Area Transit System
More informationState and Local Partners for a Clean and Green California
State and Local Partners for a Clean and Green California Statewide Energy Efficiency Collaborative Conference, Sacramento, California Mark Ferron California Public Utilities Commission June 20, 2013 1
More informationDallas City Council August 2, Jody Puckett, Assistant City Manager (I) City Manager s Office
Trinity Parkway Alternative 3C Dallas City Council August 2, 2017 Jody Puckett, Assistant City Manager (I) City Manager s Office Presentation Overview Provide background on Trinity Parkway Alternative
More informationContractor Alliancing Sean Mooney Programme Manager
1 Contractor Alliancing Sean Mooney Programme Manager Today s Agenda Introduction Background Contractor Alliancing The Process Alliance Electricity Alliance North (EAN) Optimise Water (LLP) JV Benefits
More informationOPPD Board Committee Meeting April 13, 2017 Transmission Right of Way Acquisition & Routing, Siting and Public Involvement Stakeholder Engagement
OPPD Board Committee Meeting April 13, 2017 Transmission Right of Way Acquisition & Routing, Siting and Public Involvement Stakeholder Engagement Process and Condemnation Update Right-of-Way Easement
More informationInteroperability and Standardization: The NIST Smart Grid Framework
Interoperability and Standardization: The NIST Smart Grid Framework GridWeek Asia George W. Arnold, Eng.Sc.D. National Coordinator for Smart Grid Interoperability National Institute of Standards and Technology
More informationElectric Program Investment Charge Joint IOU Stakeholder Webinar
Electric Program Investment Charge Joint IOU Stakeholder Webinar Second Triennial Investment Plan Cycle February 21, 2014 A Survey of California s Energy Goals Electric Systems Face Fundamental Changes
More informationCyber Security Reliability Standards CIP V5 Transition Guidance:
Cyber Security Reliability Standards CIP V5 Transition Guidance: ERO Compliance and Enforcement Activities during the Transition to the CIP Version 5 Reliability Standards To: Regional Entities and Responsible
More informationArizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D
(.laps Lisa Malagon Leader Federal and State Compliance Mail Station 9704 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250- 5671 Elisa.Malagon@aps.com January 31, 2014 Docket Control Arizona Corporation
More informationBike Sharing Feasibility Study and Implementation Plan 2012
Source: Nice Ride (Twin Cities MN) Source: Capital Bikeshare (Washington, DC) City of Cleveland Bike Sharing Feasibility Study and Implementation Plan 2012 November 20, 2013 Toole Design Group BrownFlynn,
More informationIntroduction to the NYISO
Introduction to the NYISO Power Control Center Guilderland, NY July 21, 2011 1 Today s Topics NYISO History NYISO Roles & Governance NYISO Markets Building Reliability Emerging Trends 2 Evolution of the
More informationHetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process
California Independent System Operator & Hetch Hetchy Water and Power of the City and County of San Francisco Joint Transmission Planning Base Case Preparation Process This is a living document. Please
More informationCOUNCIL REPORT. Item Meeting date: August 13, 2018 Engineering & Public Works
Item 7.3.5 Meeting date: August 13, 2018 Department: Prepared by: Reviewed by: SUBJECT: Engineering & Public Works COUNCIL REPORT George Elliott, P.Eng., Director of Engineering & Public Works Greg McClinchey,
More informationGDOT PowerPoint Title Page MMPT. Technical Committee April 6, 2010
GDOT PowerPoint Title Page MMPT Technical Committee April 6, 2010 Introduction Senate Bill 200, enacted in May2009, revamped existing P3 enabling legislation This new legislative direction provides an
More informationDiscussion Guide. Benvoulin Substation Project.
Discussion Guide Benvoulin Substation Project A Growing Region South Central Kelowna has experienced substantial growth over the last ten years. FortisBC is enhancing the electrical power supply system
More informationBay Area Regional Bicycle Share Pilot Project. Karen Schkolnick, BAAQMD SPUR Evening Forum: Bike Sharing Around the Bay June 25, 2013
Bay Area Regional Bicycle Share Pilot Project Karen Schkolnick, BAAQMD SPUR Evening Forum: Bike Sharing Around the Bay June 25, 2013 1 Overview Pilot Project Background and Goals Roadmap, Regional Process
More informationClick to edit Master title style Click to edit Master title style
Southwest Chief & Front Range Passenger Rail Commission Overview for Transportation Legislative Review Committee November 2, 2017 Presented by: Sal Pace Jacob Riger, AICP November 2, 2017 FIRST WE WERE
More informationWORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES
Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS
More informationCorridor Management Committee. January 12, 2017
Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major
More informationAddressing Challenges Through Interconnection Wide
Addressing Challenges Through Interconnection Wide Transmission Analysis High Plains Regional Transmission Summit November 3, 2009 David A. Whiteley, Whiteley BPS Planning Ventures LLC 2 Challenge and
More informationTERMS OF REFERENCE. Scaling-up Renewable Energy Program (SREP) Joint Mission. Lesotho
TERMS OF REFERENCE Scaling-up Renewable Energy Program (SREP) Joint Mission September 27-29, 2017 Lesotho 1 SUMMARY 1. Mission objectives. The main objective of the Joint Mission ( the Mission ) is to
More informationNORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY. SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance
NORTH COUNTY CORRIDOR EXPRESSWAY TRANSPORTATION AUTHORITY ITEM: 6B SUBJECT: Jacobs Engineering Contract; Task Order #2 and Task Order #3 Acceptance Jacobs Engineering has completed Task 1 with amendment
More informationMunitions Response Site Prioritization Protocol
Munitions Response Site Prioritization Protocol Module 2. Stakeholder Involvement April 2007 April 2007 0 Outline Introduction Stakeholders Defined Protocol Requirements Conducting Stakeholder Involvement
More informationInitiation of Periodic Regional Reviews: Region 1 Project Update
Section 368 Energy Corridors Energy Policy Act of 2005 Initiation of Periodic Regional Reviews: Region 1 Project Update James Gazewood, National Project Manager BLM Washington Office Section 368 West-wide
More informationEPA Near-port Community Capacity Building: Tools and Technical Assistance for Collaborative Solutions
EPA Near-port Community Capacity Building: Tools and Technical Assistance for Collaborative Solutions Sabrina Johnson, Project Lead EPA Office of Transportation & Air Quality presented at Southeast Diesel
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Eldorado-Lugo-Mohave
More informationGreen California Summit. Paul Clanon Executive Director California Public Utilities Commission April 19, 2011
Green California Summit Paul Clanon Executive Director California Public Utilities Commission April 19, 2011 1 Presentation Overview What is Smart Grid Why Smart Grid California s Commitment to Smart Grid
More informationWestern States Power Crisis EPRI White Paper - An Overview -
Western States Power Crisis EPRI White Paper - An Overview - Dejan J. Sobajic July, 2001 Western States Power Crisis.1 Origins of the White Paper The roots of the document go back to several discussions
More informationPLANNING COMMISSION JUNE 7, 2018 PUBLIC HEARING
PLANNING COMMISSION JUNE 7, 2018 PUBLIC HEARING SUBJECT: MUNICIPAL CODE AMENDMENT TO UPDATE TITLE 10, VEHICLES AND TRAFFIC, AND TITLE 19, ZONING ORDINANCE, WEST HOLLYWOOD MUNICIPAL CODE TO AMEND THE TRANSPORTATION
More informationDulles Area Transportation Association
Dulles Area Transportation Association February 8, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Scope Multimodal improvements
More informationCalifornia Energy Efficiency Strategic Plan
California Energy Efficiency Strategic Plan Paula Gruendling Regulatory Analyst California Public Utilities Commission 1 September 17, 2014 Presentation Overview California Energy Efficiency Strategic
More informationTHE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9
THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental
More informationCouncil of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013
Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility
More informationUpdates and Modifications to Report
QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision
More informationTHE SOUTHERN GATEWAY MANAGED LANES PROJECT. Public Meetings Summer 2015 June 23, June 25, July 7, July 9
THE SOUTHERN GATEWAY MANAGED LANES PROJECT Public Meetings Summer 2015 June 23, June 25, July 7, July 9 History & Background Began in 2001 as a Major Investment Study (MIS), Schematic, and Environmental
More informationSUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17
Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11
More informationWritten Testimony of Rick Gonzales Senior Vice President and Chief Operating Officer New York Independent System Operator
Assembly Standing Committee on Energy Kevin A. Cahill, Chairman Assembly Standing Committee on Corporations, Authorities and Commissions James F. Brennan, Chairman Assembly Standing Committee on Cities
More informationSRP Ten Year Transmission Plan
2018 SRP Ten Year Transmission Plan 2018-2027 Prepared for the Arizona Corporation Commission January 2018 Docket No. E-00000D-17-0001 Page1 Page1 Table of Contents 1. Introduction... 1 2. Planning Organizations...
More informationGrid Security & NERC
Grid Security & NERC Janet Sena, Senior Vice President, Policy and External Affairs Southern States Energy Board 2017 Associate Members Winter Meeting February 27, 2017 Recent NERC History Energy Policy
More informationExpanding Transmission Capacity: Options and Implications. What role does renewable energy play in driving transmission expansion?
Expanding Transmission Capacity: Options and Implications What role does renewable energy play in driving transmission expansion? Beth Soholt Director, Wind on the Wires bsoholt@windonthewires.org Office:
More informationHigh Level Group on Interconnections for South-West Europe. Progress Report (March - December 2015)
High Level Group on Interconnections for South-West Europe Progress Report (March - December 2015) I - Introduction This Progress Report provides information on the state-of-play and milestones achieved
More informationPacifiCorp Transmission Energy Gateway Update. John Cupparo Vice President, Transmission January 2010
PacifiCorp Transmission Energy Gateway Update John Cupparo Vice President, Transmission January 2010 Topics Overview and current status Rightsizing Challenges and opportunities Summary 2 Energy Gateway
More informationOPUC Workshop March 13, 2015 Cyber Security Electric Utilities. Portland General Electric Co. Travis Anderson Scott Smith
OPUC Workshop March 13, 2015 Cyber Security Electric Utilities Portland General Electric Co. Travis Anderson Scott Smith 1 CIP Version 5 PGE Implementation Understanding the Regulations PGE Attended WECC
More informationDOE OFFICE OF INDIAN ENERGY Program Overview May 5, Chris Deschene, Director
DOE OFFICE OF INDIAN ENERGY Program Overview May 5, 2017 Chris Deschene, Director Reality of 567 Federally Recognized Tribes Staggering gaps between Indian Country and the rest of the U.S. American Indian
More informationBuilding Energy Programs: A New Blueprint for Success
Building Energy Programs: A New Blueprint for Success State Workshop on Innovations in Energy Efficiency Policy: East and South February 19, 2014 Chapel Hill, NC Kara Saul Rinaldi National Home Performance
More informationNortheast Coordinated System Plan and Other Interregional Activities
Northeast Coordinated System Plan and Other Interregional Activities IPSAC10 November 6, 2009 Michael I. Henderson and John Buechler Background on Interregional Planning Order 890 requires regional coordination
More informationCommission for Environmental Cooperation (CEC) Sponsored Workshop on Environmental Assistance Programs and Resources for Automotive OEMs and Suppliers
Commission for Environmental Cooperation (CEC) Sponsored Workshop on Environmental Assistance Programs and Resources for Automotive OEMs and Suppliers Ben Vickery Senior Technical Analyst NIST MEP September
More informationMarch 21, 2016 MEMORANDUM FOR THE HEADS OF EXECUTIVE DEPARTMENTS AND AGENCIES. Building National Capabilities for Long-Term Drought Resilience
This document is scheduled to be published in the Federal Register on 03/25/2016 and available online at http://federalregister.gov/a/2016-06901, and on FDsys.gov March 21, 2016 MEMORANDUM FOR THE HEADS
More informationChief Executive Officer. Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013
Mark W. Maher Chief Executive Officer Pacific Northwest Utilities Conference Committee Portland, Oregon March 8, 2013 Agenda WECC Overview WECC Strategic Planning Initiative Western Interconnection Synchrophasor
More informationSEAWALL EARTHQUAKE SAFETY & DISASTER PREVENTION PROGRAM
SEAWALL EARTHQUAKE SAFETY & DISASTER PREVENTION PROGRAM Port Jurisdiction Historic shoreline Presentation to the Port Commission March 13, 2018 Photo Michael Macor SEAWALL EARTHQUAKE SAFETY & DISASTER
More informationDecember 10, Statement of the Securities Industry and Financial Markets Association. Senate Committee on Banking, Housing, and Urban Development
December 10, 2014 Statement of the Securities Industry and Financial Markets Association Senate Committee on Banking, Housing, and Urban Development Hearing Entitled Cybersecurity: Enhancing Coordination
More informationWHO-ITU National ehealth Strategy Toolkit
WHO-ITU National ehealth Strategy Toolkit Context and need for a National Strategy A landscape of isolated islands of small scale applications unable to effectively communicate and to share information
More informationBROADBAND STATUTES AND RECENT LEGISLATION
kslegres@klrd.ks.gov 68-West Statehouse 300 SW 10th Ave. Topeka, Kansas 66612-1504 (785) 296-3181 January 15, 2019 kslegislature.org/klrd BROADBAND STATUTES AND RECENT LEGISLATION Statutes Forty-three
More informationDecision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement
Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,
More informationLive Webinar: Best Practices in Substation Security November 17, 2014
Live Webinar: Best Practices in Substation Security November 17, 2014 1 Agenda & Panelists Welcome & Introduction - Allan Wick, CFE, CPP, PSP, PCI, CBCP Enterprise Security Manager-CSO Tri-State Generation
More informationPrepared Testimony of. Bohdan R. Pankiw. Chief Counsel Pennsylvania Public Utility Commission. before the
Prepared Testimony of Bohdan R. Pankiw Chief Counsel Pennsylvania Public Utility Commission before the Pennsylvania Senate Consumer Protection and Professional Licensure Committee and Pennsylvania Senate
More information