APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

Size: px
Start display at page:

Download "APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:"

Transcription

1 APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd rd Avenue S.E. Calgary, Alberta T2A 7W7 December 13, 2006

2

3 TABLE OF CONTENTS 1. EXECUTIVE SUMMARY APPLICATION EXISTING PERMITS AND LICENCES AESO DIRECT ASSIGNMENT PROPOSED DEVELOPMENT DESCRIPTION OF PROPOSED FACILITIES MATL 120S SUBSTATION Substation Site Major Items of Equipment Protection Land Rights TRANSMISSION LINE 923L AND 940L Physical Details GENERAL PROTECTION AND COMMUNICATION SITE SELECTION PUBLIC CONSULTATION LANDOWNERS CONTACTED AGENCY REFERRAL AGENCIES CONTACTED STEPS IN AGENCY REFERRAL AGENCY CONCERNS ENVIRONMENTAL MANAGEMENT PROJECT SCHEDULE PROJECT COST...9 i

4

5 APPENDICES Appendix A Alberta Electric System Operator (AESO) Documents Direct Assignment Letter Appendix B 120-SLD SITE06 Single Line Diagram Single Line Diagram MATL 120S Substation Site Plan - MATL 120S Substation Appendix C D1 Map1 Mapping Project Area Map Air Photo Map AEUB Project Location map Appendix D Public Consultation Materials Stakeholder Information Package ii

6 i

7 APPLICATION TO THE ALBERTA ENERGY AND UTILITIES BOARD RE: NEW 240 kv MATL SUBSTATION 120S 1. EXECUTIVE SUMMARY Montana Alberta Tie Ltd. (MATL) is moving forward with plans to construct a 240 kv transmission line between Alberta and Montana. The proposed 240 kv transmission line will connect to the Alberta Electric System at a new substation designated as MATL substation 120S. The proposed substation will be located northeast of the City of Lethbridge in the NE W4M where it will be connected to Alta Link s 240 kv transmission line 923L via an in/out configuration. This will involve construction of two new spans of 240 kv transmission line. AltaLink and MATL will own separate segments of the 120S substation. Stakeholders have been contacted and there have been no objections received. The proposed in-service date for the MATL substation 120S is December 7, 2007, with a proposed construction start date of September 7, APPLICATION AltaLink Management Ltd. (AltaLink) hereby makes application to the Alberta Energy and Utilities Board (the Board), pursuant to Sections 14, 15 and 18 of the Hydro and Electric Energy Act (Alberta), being Chapter H-16 of the Revised Statutes of Alberta, 2000, for Permits, Licences, Directions, Orders, and all other laws and regulations as may be necessary to permit AltaLink to: a) construct the AltaLink portion of the new 240 kv substation designated MATL 120S; b) reconfigure existing 240 kv transmission line 923L in and out of 120S substation; c) redesignate the existing portion of 240 kv transmission line 923L, as 940L between North Lethbridge substation 370S and the new MATL substation 120S; 1

8 d) connect AltaLink s segment of the MATL substation 120S to MATL s segment of substation 120S located in NE W4; e) operate these facilities. The work and facilities covered by this Application will: be constructed in accordance with the approvals granted by the Board pursuant to this Application; comply with the Safety Codes Act; comply with the Hydro and Electric Energy Act; comply with the Electric Utility Act; comply with the Radio and Communications Ac;, and be inspected and declared safe for operation under the authority of a properly qualified professional engineer before being energized. Upon completion, AltaLink will provide the Board with a statement that it has been so constructed and inspected and will indicate the nominal voltage level. 3. EXISTING PERMITS AND LICENCES AltaLink Management Ltd. is the holder of the following permit and licence: U for 240 kv transmission line 923L 4. AESO DIRECT ASSIGNMENT This project has been direct assigned to AltaLink by the AESO. See the attached letter from the AESO in Appendix A. 2

9 5. PROPOSED DEVELOPMENT Single Line Diagram 120-SLD06 in Appendix B shows the proposed initial system development of the MATL substation 120S, with the AltaLink and MATL portions of the substation defined. Air Photo MAP1 in Appendix C shows the location of the proposed MATL substation 120S and the two new portions of 240 kv transmission lines. The proposed substation will be located adjacent to existing 240 kv double circuit transmission line 923/924L. 6. DESCRIPTION OF PROPOSED FACILITIES 6.1. MATL 120S Substation Substation Site The proposed MATL substation 120S will be located in NE ¼ of section W4M. (Lat , Long ) See Site Plan 120-SITE06 in Appendix B for details Major Items of Equipment Upon completion of this project, the AltaLink portion of the new MATL substation 120S will contain the following major items of equipment: kv circuit breakers See Single Line Diagram 120-SLD06, in Appendix B for the electrical representation of the proposed substation Protection Install, set, and commission breaker failure protection for each of the three 240 kv breakers in the new substation. On the 240 kv 940L line to North Lethbridge 370S, install, set, and commission A and B distance line protection. On the 240 kv 923L line to West Brooks substation 28S and Langdon substation 102S, install, set, and commission A and B distance line protection. Install, set and commission A and B low-impedance bus differential protection on the 240 kv bus to which the MATL facility is to be connected. 3

10 Land Rights MATL has an agreement in place to purchase approximately 20 acres of land in NE W4 for the proposed substation. This land transfer will be completed once the subdivision application is approved by the local municipal authority. AltaLink will obtain an easement from MATL for AltaLink s portion of the MATL substation 120S and the new transmission lines Transmission line 923L and 940L Transmission circuit 923L will be altered to facilitate an in/out arrangement into the MATL substation 120S. The amount of new transmission line required to connect into the substation will be two spans of about 350 metres and about 100 metres from the existing line into and out of the substation. The portion of existing transmission line from North Lethbridge Substation 370S to MATL substation 120S will be re-designated as 940L Physical Details conductor 2 x 477 kcmil (bundled conductor) span length 350 metres 6.3. General Protection and Communication As part of this project, minor modifications to the protection and control systems will be carried out at North Lethbridge substation 370S and West Brooks substation 28S. 7. SITE SELECTION The site selection for the MATL substation was completed by MATL. MATL negotiated a land purchase agreement with the landowner for the substation site. The proposed location of MATL substation 120S is shown on Air Photo Map1 and Project Area Map D1 in Appendix C and on Site Plan 120-SITE06 in Appendix B. 4

11 The proposed location of the MATL substation: is adjacent to a road, which provides good access for construction, operation and maintenance; is adjacent to existing 240 kv transmission line 923/924L, which minimizes the length of new transmission line required; has no objections from landowners located within 800 m (1/2 mile) of the proposed substation site; has no objections from agency stakeholders. 8. PUBLIC CONSULTATION AltaLink carried out a stakeholder consultation process with local and government agencies and landowners. All concerns raised by stakeholders during the consultation process were addressed. AltaLink has received no objections to the proposed MATL substation 120S Landowners Contacted The landowner mailing list was developed through a title search of all properties within 800 meters of the proposed MATL substation site. "Landowners" includes all owners of land, occupants, renters and businesses located on those properties. There are four landowners located within 800 meters of the proposed substation site. All the landowners have been informed about this project. An information package (attached in Schedule D) describing the project was mailed to all the landowners. The landowners were later contacted by telephone to confirm they had received the information package and to answer any questions. Additional information was sent out to the landowners as requested. Prior to AltaLink contacting the landowners, MATL staff had extensive discussions with the same landowners regarding the proposed transmission line and substation site location. The focus of these discussions regarded the location of the transmission line 5

12 and the need for a substation adjacent to the existing 240 kv transmission line 923/924L. MATL offered to purchase land in NW W4 but was not successful in obtaining these lands. MATL subsequently made an offer to the land owner in NE W4M, and was successful. When AltaLink contacted these landowners to discuss AltaLink s involvement in the project, they were very familiar with the need to construct the substation. Steps in Landowner Contacts October, 2006 Landowner Referral October and November, 2006 Landowner Consultation Information packages were mailed to all landowners identified through land title searches. All landowners within 800 meters of the proposed substation site were contacted by telephone. Landowners did not have any concerns with the proposed project. 9. AGENCY REFERRAL The proposed site for MATL substation 120S was the subject of correspondence and discussion with the agencies and companies listed below. AltaLink has received no objections from these agencies regarding the proposed substation Agencies Contacted Agency Name Alberta Community Development, Alberta Sustainable Resource Development, Wildlife Management County of Lethbridge TELUS Communication Inc Navigation Canada Agency Contact Barry Newton Barry.newton@gov.ab.ca Kim Morton Kim.morton@gov.ab,.ca Rob Singleton r.singleton@county.lethbridge.ab.ca Dwayne Schultz Dwayne.Schultz@TELUS.COM General Manager Airport Operations (GMAO) NAV CANADA Land Use Office West roej@navcanada.ca 6

13 Agency Name Transport Canada Agency Contact Aerodromes and Air Navigation 9.2. Steps in Agency Referral October, 2006 Agency Referral Information packages were sent to agencies. (regular mail or e- mail) 9.3. Agency Concerns Agency Concern Mitigation Alberta Sustainable Resource Development, Wildlife Management No work on grassland areas during the period of April 15 to mid-july. The substation site is on cultivated lands and grasslands should not be impacted by AltaLink. Telus Provision of Ground Potential Rise data of the MATL substation. The information will be provided once the substation design has been completed. 7

14 10. ENVIRONMENTAL MANAGEMENT AltaLink s contractor personnel, tools, equipment and procedures are required to meet the environmental health and safety requirements of all laws and regulations of the jurisdiction in which the work takes place. This includes procedures and practices that follow Alberta Environment guidelines for right of way clearing, construction, reclamation, and subsequent activities as described in the Information Letter Environmental Protection Guidelines for Electrical Transmission Lines (C&R/IL/95-2). Impacts are managed through utilizing appropriate procedures for vegetation management, spill response, and stream crossings. AltaLinks contractors will follow Alberta Environment Guidelines for all creek and river crossings. AltaLink s contractors are expected to use approved single trail access routes and construction practices and equipment that minimize rutting, compaction, soil disturbance, and preservation of topsoil and sub-soil structures. Ongoing operational impacts are managed through procedures for accessing rights-of-ways, landowner access procedures, vegetation management procedures, spill response procedures and maintenance inspection procedures. 11. PROJECT SCHEDULE REQUESTED APPROVAL: August 24, 2007 CONSTRUCTION START: September 7, 2007 COMMISSIONING: December 7,

15 12. PROJECT COST The estimated cost for the MATL substation 120S project is as follows: Project Totals Percentage of Rounded Numbers Total Estimate Material Transmission Component Total Transmission Line Cost 435,000 5% Survey 10,000 <1% Right of Way Acquisition 10,000 <1% Right of Way Preparation 45,000 <1% Sub total 500,000 6% Substation Equipment Transformers & Switchgears 850,000 9% Site Preparation & Survey 500,000 5% Building 180,000 2% Protection/Telecontrol (including Metering & Settings) 580,000 6% Switchyard Bus Work, Foundation & Superstructures 820,000 9% SCADA 70,000 1% Land 10,000 <1% Sub total 3,010,000 33% AltaLink Regulatory (Siting) 40,000 <1% Prelim Engineering & Design 60,000 <1% Supervision (Project Mgmt., Field Insp., Eng Reviews, Commissioning) 190,000 2% Overhead (E&S) 600,000 7% AFUDC 60,000 1% Sub total 950, % Contractor Engineering Procurement Construction & Management (EPCM) Detail Engineering & Design 1,050,000 11% Procurement 140,000 1% Construction Labor 2,630,000 29% Project management 920,000 10% Sub total 4,740,000 51% TOTAL 9,200, % This estimate is within a +20/-10% cost variance and the entire cost will be borne by MATL. 9

16 This Application has been reviewed by the undersigned, who is a registered Engineering Technologist under The Engineering, Geological and Geophysical Professions Act of Alberta. All communication regarding this Application should be directed to Conrad Journault at or at conrad.journault@altalink.ca or John Rohrich at or at john.rohrich@altalink.ca Dated at the City of Calgary in the Province of Alberta this 13 th day of December AltaLink Management Ltd., By its agent John Rohrich, R.E.T., Manager of Siting AltaLink Management Ltd rd Avenue SE Calgary, Alberta T2A 7W7 10

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document Decision 2014-271 Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014 The Alberta Utilities Commission Decision 2014-271: Alberta Electric System Operator

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,

More information

Benbow 397S Substation Upgrade Needs Identification Document

Benbow 397S Substation Upgrade Needs Identification Document APPENDIX C AESO PIP Benbow 397S Substation Upgrade Needs Identification Document 1.0 Participant Involvement Program (PIP) From June to December 2015, the AESO conducted a Participant Involvement Program

More information

ENMAX Generation Portfolio Inc.

ENMAX Generation Portfolio Inc. Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. September 5, 2017 Alberta Utilities Commission Decision 22192-D01-2017 ENMAX Generation Portfolio Inc. Proceeding 22192 Application 22192-A002 September

More information

PARTICIPANT INVOLVEMENT PROGRAM

PARTICIPANT INVOLVEMENT PROGRAM ATTACHMENT 3 PARTICIPANT INVOLVEMENT PROGRAM Southern Alberta Transmission Reinforcement Amendment Needs Identification Document Approval Amendment 1.0 Participant Involvement Program From July to December

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L September 15, 2017 Alberta Utilities Commission Decision 22769-D01-2017 Transmission Lines 138-1.80L and 138-1.81L Proceeding 22769 Application

More information

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT

STRATHCONA AREA TRANSMISSION UPGRADE PROJECT STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a

More information

Stem Beach Solar 1041 Application

Stem Beach Solar 1041 Application Stem Beach Solar 1041 Application September 18 th, 2018 By: Stem Beach Solar LLC, Invenergy LLC 1401 17 th Street, Ste 1100 Denver, Colorado 80202 For: Pueblo County Agenda 1. About Invenergy 2. Project

More information

AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP)

AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP) APPENDIX B AESO PARTICIPANT INVOLVEMENT PROGRAM (PIP) Sunnybrook and Livock Substation Modifications Needs Identification Document 1.0 Participant Involvement Program From May 2015 to August 2015, the

More information

Jenner Wind Energy Connection Needs Identification Document

Jenner Wind Energy Connection Needs Identification Document APPENDIX C AESO PIP Jenner Wind Energy Connection Needs Identification Document 1.0 Participant Involvement Program (PIP) From November 2015 to May 2016, the AESO conducted a participant involvement program

More information

Ells River Substation Telecommunication Tower

Ells River Substation Telecommunication Tower January 2013 Why are you receiving this project information package? We are advising neighbouring landholders, agencies and other interested parties about plans to construct the Ells River substation telecommunication

More information

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES PROOF OF SERVICE NOTICE TO COMMUNITY ORGANIZATIONS PUBLIC NOTICE NOTICE IN UTILITY BILLS NOTICE OF OWNERS OF PROPERTY

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of December 12, 2015 DATE: December 1, 2015 SUBJECT: SP-84-U-15-1 USE PERMIT ASSOCIATED WITH A SITE PLAN for a telecommunications facility; located

More information

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS

Information Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES

WORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS

More information

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:

B-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax: B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: 0-- E-mail: janet.fraser@bctc.com October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street,

More information

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY

SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY SOUTHERN COMPANY DISTRIBUTION INTERCONNECTION POLICY Inverter Based Generators 25 kw and This document contains the interconnection requirements for inverter based generators, 25 kw and smaller, that operate

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Contents. 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map

Contents. 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map Ranchtown Substation Project Open House Displays 08/16/2012 Contents 1. Routing and Siting Process Routing and Siting Process Highlights Timeline Constraints Map 2. Scope, Purpose and Need Existing Helotes

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ]

DATE: April 8, 2013 REPORT NO. CD TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] DATE: April 8, 2013 REPORT NO. CD2013-040 TO: FROM: Chair and Members Committee of the Whole Community Services Gregory Dworak, General Manager Community Services 1.0 TYPE OF REPORT CONSENT ITEM [ ] ITEM

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS

More information

MFC Power General Partner Ltd.,

MFC Power General Partner Ltd., Decision 21950-D01-2016 Preferential Sharing of Records Between, MFC Power Limited Partnership, URICA Energy Real Time Ltd., and URICA Asset Optimization Ltd. October 12, 2016 Alberta Utilities Commission

More information

INFRASTRUCTURE ELECTRIC UTILITY CAPITAL IMPROVEMENT PROJECTS DRAFT

INFRASTRUCTURE ELECTRIC UTILITY CAPITAL IMPROVEMENT PROJECTS DRAFT INFRASTRUCTURE ELECTRIC UTILITY CAPITAL IMPROVEMENT PROJECTS 2014-2023 DRAFT November 5, 2012 Project Costs Infrastructure - Electric Utility F - 2 City of Lethbridge Infrastructure - Electric Utility

More information

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES

APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES APPENDIX E: DRAFT INITIAL STUDY/MITIGATED NEGATIVE DECLARATION COMMENT LETTERS AND RESPONSES P AGE 129 A-1 A-2 A-3 A-4 A-5 A-6 A-7 A-8 A-8 A-9 B-1 B-2 B-3 B-4 B-6 B-5 March 24, 2015 Scott Johnson Community

More information

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum

NERC Transmission Availability Data System (TADS): Element Identifier Data Submission Addendum Transmission Availability Data System (TADS) Element Identifier Data Submission Addendum May 28, 2013 3353 Peachtree Road NE NERC Transmission Availability Data System (TADS): Element Identifier Data Submission

More information

CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA

CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA CITY OF GRA DE PRAIRIE SUBDIVISIO A D DEVELOPME T APPEAL BOARD AGE DA SEPTEMBER 19, 2012 AT 9:00 AM FIRST FLOOR, ORTH CO FERE CE ROOM CITY HALL 10205 98 STREET ATTE DEES Councillor J. Croken L. Coulter

More information

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network

Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network Tasmanian Networks Pty Ltd ABN 24 167 357 299 Guideline for the Connection of Micro Embedded Generators to the TasNetworks Distribution Network (AS4777 Compliant) NG R PD 09 Version 2.0 July 2014 TABLE

More information

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km)

Ministry of Transportation and Infrastructure jurisdiction (337 km) Federal Parks Canada jurisdiction (103 km) nfrastructure jurisdiction (337 km) HGHWAY 1 KAMLOOPS TO ALBERTA FOUR-LANNG PROGRAM Welcome Thank you for attending this community engagement on the Trans- Canada Highway 1 West Project, part of the Highway

More information

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities

More information

Corridor Management Committee. January 12, 2017

Corridor Management Committee. January 12, 2017 Corridor Management Committee January 12, 2017 1 Today s Topics Chair s Remarks 2017 Project Activity Overview Updated Corridor Flyover Video: Preview 2017 Meeting Schedule 2 3 Chair s Update 2016 Major

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Electric Utility Facility Connection Requirements

Electric Utility Facility Connection Requirements City of Coffeyville Municipal Light and Power Electric Utility Facility Connection Requirements Approved: Date: Version Date Change Tracking Reviewer/Editor 1.0 June, 2010 Original document. Steve McGie

More information

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton

Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton Protocol and Guideline for Establishing Wireless Telecommunication Facilities Within City of Brampton (February 2002) (Revised, January 2011) Council approval CW062-2011 (Revised, February 2011) revisions

More information

Environmental Monitoring Report. Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project. Semiannual Report January June 2016

Environmental Monitoring Report. Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project. Semiannual Report January June 2016 Environmental Monitoring Report Semiannual Report January June 2016 Loan 2671 & Grant 0218-KGZ: Power Sector Improvement Project Prepared by OJSC National Electric Grid of Kyrgyzstan for the Kyrgyz Republic

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

Sapphire Wind Farm 330/33kV Substation

Sapphire Wind Farm 330/33kV Substation Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire

More information

Baseline Bridge Crossing. Priorities Committee Meeting

Baseline Bridge Crossing. Priorities Committee Meeting Baseline Bridge Crossing Priorities Committee Meeting June 14, 2016 1 Unparalleled Asset Footprint Largest Energy Infrastructure Company in North America Over 12,000 employees in Canada and the U.S. $18.2

More information

Small Hydro Regulatory and Permitting Requirements California

Small Hydro Regulatory and Permitting Requirements California Small Hydro Regulatory and Permitting Requirements California Lon W. House, Ph.D. 530.409.9702 Water & Energy Small Hydro Regulatory and Compliance FERC QF, Small Hydro License or Exemption EIA Generator

More information

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report.

BC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report. Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com November 0, 05 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission

More information

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662 Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately

More information

Variance Project Black Flag Attachments:

Variance Project Black Flag Attachments: Variance 15-01 Project Black Flag Attachments: 1. Locator 2. VAR 15-01 Staff report 3. Variance Exhibit 4. Applicant s Statement E Lookout Dr N Plano Rd 1402 E. Lookout Dr. N Greenville Ave Woodglen Dr

More information

Description of the Application Process for Small Embedded Generators

Description of the Application Process for Small Embedded Generators Description of the Application Process for Small Embedded Generators This document describes the Application Process for Small Embedded Generators (as required under section 5.3.3A of the National Electricity

More information

Budget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017

Budget Review Process (BRP) Preliminary List of Business Initiatives. Stakeholder Meeting April 10, 2017 2017-18 Budget Review Process (BRP) Preliminary List of Business Initiatives Stakeholder Meeting April 10, 2017 Purpose / Agenda The purpose of this presentation is to: Provide stakeholders with a BRP

More information

Vegreville Office Telecommunication Tower Replacement

Vegreville Office Telecommunication Tower Replacement Project Need and Details March 2012 If approved, the proposed Vegreville Office Telecommunication Tower Replacement will be located on the current tower site at 6502-55 Avenue in the Town of Vegreville.

More information

Re: FortisBC Inc. Customer Complaint Melody Farmer Boswell Power Surge and Incident Report

Re: FortisBC Inc. Customer Complaint Melody Farmer Boswell Power Surge and Incident Report LETTER NO. L 59 10 ERICA M. HAMILTON COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604)

More information

Practice Guidelines from Other Canadian Jurisdictions. The Association of Professional Engineers and Geoscientists of Alberta (

Practice Guidelines from Other Canadian Jurisdictions. The Association of Professional Engineers and Geoscientists of Alberta ( Jan, 2017 Practice Guidelines from Other Canadian Jurisdictions Jurisdiction Guideline Name Main Discipline Revision Date Comments The Association of Professional and of Alberta (www.apega.ca) Authenticating

More information

Document C0. Use for:

Document C0. Use for: Date: July 27, 2015 Document C0 Use for: Connection of Electric Generation that will operate with an Open Transition (Category 1) between the Ameren System and the Generator or operate with a Synchronized

More information

Applicant Type (Conditional Use Permit, Variance, Tract Map, etc.): Applicant: Address: Phone(s): Fax:

Applicant Type (Conditional Use Permit, Variance, Tract Map, etc.): Applicant: Address: Phone(s): Fax: ENVIRONMENTAL QUESTIONNAIRE City of Twentynine Palms Community Development Department 6136 Adobe Road Twentynine Palms, CA 92277 (760) 367-6799 Fax (760) 367-5400 29palms.org : Please complete each statement

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

Instructions for Applying for Consultants Competitive Negotiation Act (CCNA) Certification with Palm Beach County (PBC)

Instructions for Applying for Consultants Competitive Negotiation Act (CCNA) Certification with Palm Beach County (PBC) Instructions for Applying for Consultants Competitive Negotiation Act (CCNA) Certification with Palm Beach County (PBC) In accordance with the Consultants Competitive Negotiation Act (CCNA), Florida Statutes

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Environmental Impact Questionnaire

Environmental Impact Questionnaire Community Development Department 11 English Street Petaluma, CA 94952 Phone: 707-778-4301 Email: cdd@ci.petaluma.ca.us Web: www.cityofpetaluma.net/cdd Building Geographic Information Systems Housing Neighborhood

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

UPDATES EPC Contract Signed August 2017

UPDATES EPC Contract Signed August 2017 ACO SOLAR HV BOP PROJECT NUMBER 2655 Convalt Energy LLC MOEE Myanmar Power Generation, Substation UPDATES EPC Contract Signed August 2017 Convalt Energy LLC are developing a 300MW AC solar farm in Myanmar

More information

Unified Development Code. Public Workshop No. 3 November 7, 2017

Unified Development Code. Public Workshop No. 3 November 7, 2017 Unified Development Code Public Workshop No. 3 November 7, 2017 Purpose of the Project 2 The overall goal of the project is to bring together the County s Land Development Regulations (Chapter 74 of the

More information

User Guide. March 2017

User Guide. March 2017 User Guide March 2017 Alberta Utilities Commission efiling System User Guide Fifth Avenue Place Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Phone: 403-592-4500 Email: info@auc.ab.ca www.auc.ab.ca

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

TELECOMMUNICATIONS ACCESS POLICY 2011

TELECOMMUNICATIONS ACCESS POLICY 2011 TELECOMMUNICATIONS ACCESS POLICY 2011 The Vice Chancellor and Principal, as delegate of the Senate of the University of Sydney, adopts the following policy. Dated: 31 January 2011 Signature: Name: Michael

More information

Solid Waste Association of North America (SWANA)

Solid Waste Association of North America (SWANA) Manitoba Operator Certification Solid Waste Association of North America (SWANA) SWANA NLC Solid Waste Association of North America Non-profit organization Over 8,000 members 45 Chapters in US, Canada,

More information

VERIZON TELEPHONE COMPANIES TARIFF FCC NO.

VERIZON TELEPHONE COMPANIES TARIFF FCC NO. Director-Tariffs 1st Revised Page 19-1 600 Hidden Ridge Cancels Original Page 19-1 Irving, Texas 75038 Issued: September 28, 2001 Effective: October 13, 2001 1 (A) INTERCONNECTION BETWEEN COLLOCATED SPACES

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

MESP MODULAR SUBSTATION USER REQUIREMENTS

MESP MODULAR SUBSTATION USER REQUIREMENTS Engineering Specification Electrical Networks MODULAR SUBSTATION USER Version: 2 Issued: November 2015 Owner: Head of Engineering/Electrical Approved By: Head of Engineering/Electrical PRINTOUT MAY NOT

More information

Dealing With a Disaster and Its Effect on the Utility Operation

Dealing With a Disaster and Its Effect on the Utility Operation Nashville Electric Service Dealing With a Disaster and Its Effect on the Utility Operation UTA Fall Conference Florence, Alabama October 12-14, 2011 Outline Who We Are Typical Emergency Response Challenges

More information

MANITOBA LANDFILL OPERATOR CERTIFICATION PROGRAM SUSTAINABLE DEVELOPMENT

MANITOBA LANDFILL OPERATOR CERTIFICATION PROGRAM SUSTAINABLE DEVELOPMENT MANITOBA LANDFILL OPERATOR CERTIFICATION PROGRAM MANITOBA SUSTAINABLE DEVELOPMENT 2017 TABLE OF CONTENTS FOREWORD... 3 Landfill Operator Certification Program Overview... 4 DEFINITIONS... 5 1.0 PROGRAM

More information

Guidelines for Certification under the Airside Driving Qualification Scheme for Specialized Ground Services Equipment

Guidelines for Certification under the Airside Driving Qualification Scheme for Specialized Ground Services Equipment Guidelines for Certification under the Airside Driving Qualification Scheme for Specialized Ground Services Equipment Issued by Airport Authority Hong Kong 29 December 2014 It is the responsibility of

More information

WN U-60 Original Sheet No. 152

WN U-60 Original Sheet No. 152 WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H

More information

Standard CIP-006-4c Cyber Security Physical Security

Standard CIP-006-4c Cyber Security Physical Security A. Introduction 1. Title: Cyber Security Physical Security of Critical Cyber Assets 2. Number: CIP-006-4c 3. Purpose: Standard CIP-006-4c is intended to ensure the implementation of a physical security

More information

Breaking New Ground Georgia s Education and Training Certification Requirements for Persons Involved with Land Disturbing Activity

Breaking New Ground Georgia s Education and Training Certification Requirements for Persons Involved with Land Disturbing Activity Breaking New Ground Georgia s Education and Training Certification Requirements for Persons Involved with Land Disturbing Activity Cory Rayburn Erosion and Sediment Control Specialist Georgia Soil & Water

More information

Click on the links below to learn more about what we have been working on to serve you better.

Click on the links below to learn more about what we have been working on to serve you better. Click on the links below to learn more about what we have been working on to serve you better. Delivering value: Asset optimization and value engineering Maintaining reliability through security AltaLink's

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

REVISION HISTORY DATE AMENDMENT DESCRIPTION OF AMENDMENT

REVISION HISTORY DATE AMENDMENT DESCRIPTION OF AMENDMENT REVISION HISTORY DATE AMENDMENT DESCRIPTION OF AMENDMENT IFC SERVICE DESCRIPTION 17 OCTOBER 2016 Page 1 of 9 SERVICE DESCRIPTION 2-14: INTERNATIONAL FALCON CONNECTION SERVICE (IFC Service) 1. THE SERVICE

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 FAC-003-4 Transmission Vegetation Management. Registered Entity Name: Applicable Function(s): Applicable only for TO and GO Compliance Monitoring Method: RSAW Version:

More information

AURA BOCA COLONNADE Project #RW

AURA BOCA COLONNADE Project #RW LWDD Board Workshop 03/06/2018 - Agenda Item #3 AURA BOCA COLONNADE Project #RW-18-0027 March 6, 2018 Nicole Smith, Right-of-Way Coordinator SITE Looking East from Congress Avenue Congress Avenue L-42

More information

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY

Bremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY May 19, 2011 Community Meeting Metro Toronto Convention Centre North Building, Room 203B May 19 th, 2011, 4:30 p.m. to 7:30 p.m. Please sign in and complete a comment sheet Project team members are available

More information

Bulletin Installation of solar photovoltaic systems Rules , , , , and

Bulletin Installation of solar photovoltaic systems Rules , , , , and Bulletin 64-5-0 Installation of solar photovoltaic systems Rules 64-060, 64-200, 64-214, 84-020, 84-024 and 84-030 Scope (1) Introduction (2) Disconnecting means (a) Disconnecting means for solar photovoltaic

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

California Code of Regulations TITLE 21. PUBLIC WORKS DIVISION 1. DEPARTMENT OF GENERAL SERVICES CHAPTER 1. OFFICE OF THE STATE ARCHITECT

California Code of Regulations TITLE 21. PUBLIC WORKS DIVISION 1. DEPARTMENT OF GENERAL SERVICES CHAPTER 1. OFFICE OF THE STATE ARCHITECT California Code of Regulations TITLE 21. PUBLIC WORKS DIVISION 1. DEPARTMENT OF GENERAL SERVICES CHAPTER 1. OFFICE OF THE STATE ARCHITECT SUBCHAPTER 2.5. VOLUNTARY CERTIFIED ACCESS SPECIALIST PROGRAM Program

More information

Office of the City Auditor 2014 Third Quarter Activity Report November 25, 2014

Office of the City Auditor 2014 Third Quarter Activity Report November 25, 2014 2014 Third Quarter Activity Report November 25, 2014 This page is intentionally blank. 1. Audit Plan Progress Monitoring Bylaw 16097, Audit Committee Bylaw, Section 5 states that the Committee assists

More information

ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n

ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n RFP P5413 Contract No. 200703566 Work Order No. -07 ATLANTA BELTLINE A g e n cy C o o r d i n at i o n P l a n Prepared for: Metropolitan Atlanta Rapid Transit Authority Prepared by: DMJM Harris/JJG Joint

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

SERVICE TERMS AND SLA FOR LEASE OF DARK FIBER

SERVICE TERMS AND SLA FOR LEASE OF DARK FIBER SERVICE TERMS AND SLA FOR LEASE OF DARK FIBER Dark Fiber Lease. These are the service terms and service level agreement for the lease of Global Crossing Dark Fiber which apply to the provision of Dark

More information

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17

SUBJECT: PRESTO operating agreement renewal update. Committee of the Whole. Transit Department. Recommendation: Purpose: Page 1 of Report TR-01-17 Page 1 of Report TR-01-17 SUBJECT: PRESTO operating agreement renewal update TO: FROM: Committee of the Whole Transit Department Report Number: TR-01-17 Wards Affected: All File Numbers: 465-12, 770-11

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER Supports Item No. 2 P&E Committee Agenda September 20, 2007 ADMINISTRATIVE REPORT Report Date: August 31, 2007 Author: Gordon Foy Phone No.: 604.873.7306 RTS No.: 06810 VanRIMS No.: Meeting

More information

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)] Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected

More information

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

STATE OF MINNESOTA DEPARTMENT OF ADMINISTRATION METROPOLITAN MOSQUITO CONTROL DISTRICT ORDER FINDINGS OF FACT

STATE OF MINNESOTA DEPARTMENT OF ADMINISTRATION METROPOLITAN MOSQUITO CONTROL DISTRICT ORDER FINDINGS OF FACT STATE OF MINNESOTA DEPARTMENT OF ADMINISTRATION TARGETED GROUP DESIGNATION FOR METROPOLITAN MOSQUITO CONTROL DISTRICT FINDINGS OF FACT, CONCLUSIONS AND ORDER FINDINGS OF FACT 1. Minn. Stat. 16C.16, subd.

More information

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013

Council of State Governments. Takoma Langley Transit Center Purple Line Project Briefing. October 28, 2013 Council of State Governments Takoma Langley Transit Center Purple Line Project Briefing October 28, 2013 Takoma Langley Transit Center Purpose and Need Provide a safe, attractive and efficient facility

More information

1.0 Executive Summary

1.0 Executive Summary Statement of Work - 1 - Power and Cooling Assessment for Data Center Professional Services Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details of Service

More information

Internal Audit Follow-Up Report. Multiple Use Agreements TxDOT Office of Internal Audit

Internal Audit Follow-Up Report. Multiple Use Agreements TxDOT Office of Internal Audit Internal Audit Follow-Up Report Multiple Use Agreements TxDOT Office of Internal Audit Objective Assess the status of corrective actions for high risk Management Action Plans (MAPs) previously communicated

More information

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update

LC 67 PacifiCorp s Compliance Filing New Wind and Transmission Projects Quarterly Update October 30, 2018 VIA ELECTRONIC FILING Public Utility Commission of Oregon 201 High Street SE, Suite 100 Salem, OR 97301-3398 Attn: Filing Center RE: LC 67 PacifiCorp s Compliance Filing New Wind and Transmission

More information

Balance of Power in the Hudson Valley

Balance of Power in the Hudson Valley 1 Balance of Power in the Hudson Valley Chris Hogan, NYSDEC Major Project Management Unit May 3, 2017 2 Objective Provide an overview of the various state and federal processes by which energy projects

More information

SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality,

SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality, SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality, integrity, and innovation. Our mission is to offer the safest,

More information