1 QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision ( D. ) , SCE hereby provides this quarterly report on the status of transmission and generation interconnection projects. Relevant information on the construction status, approval status and the purpose of the project (in the form requested by Energy Division) is provided in the attached tables. Modifications from the previous report are highlighted in gray. Cancelled projects are highlighted in green and new projects are highlighted in yellow. Project cost information has already been provided to the Energy Division under Public Utilities Code Section 583 and is therefore not included in the table. Updates and Modifications to Report SCE has made the following updates and modifications from the October 2016 Quarterly Report: OVERALL CHANGES New projects submitted into the 1 st Quarter 2017 filing: No new projects submitted this quarter. Projects removed from 1 st Quarter 2017 filing (projects are removed from the AB970 Report four quarters after they are operational, incorporated into another project, or cancelled): Project No. 35 East Kern Wind Resource Area 66kV (formerly Antelope Bailey Windhub) Project No. 102 New Primm 220kV Substation Project No. 116 San Onofre 220 kv Switchyard Separation from SONGS PROJECT UPDATES Project No. 41 HDPP RAS Expansion Planned In-Service Date: 6/1/2017 Project No. 58 Tehachapi Renewable Transmission Project Project Estimated Cost Cost Range ($M): 2,300M-2,400M PIN 5243: o Capacity/Voltage Level: 500kV PIN 6438:

2 PIN 6439: PIN7553: Project No. 59 North of Magunden Redundant BCT Upgrade Planned In-Service Date: 3/31/2017 Project No. 64 Lugo Sub Install new 500kV CBs for AA Banks Notes: Issue ATP 2017 Project No. 82 Mesa 500 kv Substation Planned In-Service Date: 6/1/2021 Project Estimated Cost Project No. 86 Colorado River 230kV Substation - #2 AA Bank and Modification to the Colorado River Corridor RAS Planned In-Service Date: 12/1/2019 Project No. 105 New SCE-Owned Eldorado 220 kv Switchyard and 500/220 kv AA Transformer Bank Planned In-Service Date: 07/31/2016 Project No. 113 Victor Loop-in Project Approval Status CPUC: Exempt Project No. 114 Eldorado-Lugo-Mohave Upgrade Project Name: Eldorado-Lugo-Mohave Upgrade (Added Upgrade to title) Project Description: This project involves the upgrade of the existing 500 kv Series Capacitors at Eldorado and Lugo on the Eldorado-Lugo 500 kv T/L to 3,300A continuous rating, as well as a new Series Capacitor rated at 3,300A in the vicinity of Pisgah Substation (midline capacitor). The project will also involve the upgrade of the existing 500 kv Series Capacitors at Lugo and Mohave on the Lugo-Mohave 500 kv T/L to 3,300A continuous rating as well as a new Series Capacitor rated 3,300A in the vicinity of Pisgah Substation (midline capacitor). In addition, the existing line termination positions at Eldorado, Lugo, and Mohave substations will be upgraded with higher rated equipment (circuit breakers, disconnects, and associated terminal equipment). The objective of this project is to increase deliverability of generation from the Eldorado area into the LA Basin by increasing the compensation level of the 500 kv transmission lines from 35% to 70%. This project was approved as part of the and CAISO Transmission Plan. 2

3 Project No. 115 Lugo-Mohave Series Capacitor Upgrade Project Status: Cancelled-Transferred as part of work associated with PIN Project No. 117 Lugo -Victorville RAS Project Name: Lugo -Victorville RAS (Added RAS to title) Purpose & Benefit: To prevent overloads on the jointly owned Lugo-Victorville 500 kv T/L Project No. 119 Santiago Synchronous Condenser Planned In-Service Date: 6/1/2018 Project No. 120 Eldorado-Mohave & Eldorado-Moenkopi 500 kv Line Position Swap Purpose & Benefit: Project is to remediate thermal overloads on the Lugo-Victorville 500kV T/L caused by adjacent transmission circuit contingency. This project would eliminate the WECC Category C5 adjacent circuit transmission corridor contingency of the Eldorado-Lugo and Eldorado-Mohave 500kV T/Ls. Project No. 123 Eagle Mountain Reactor Project Location: Eagle Mountain 220/161 kv Generation Interconnection Projects Updated Item to reflect that the project is operational and the associated interconnection facilities and network upgrades are in service. This project will be removed from the report during the 2nd Quarter 2017 update. Updated Item to reflect that the project is operational and the associated interconnection facilities and network upgrades are in service. This project will be removed from the report during the 2nd Quarter 2017 update. Updated Item to reflect that the project is operational and the associated SCE affected system facilities are in service. This project will be removed from the report during the 2nd Quarter 2017 update. Updated Item to reflect the project has a later Planned In-Service Date. Updated Item to reflect the project is operational and the associated interconnection facilities and network upgrades are in service with the exception of the SPS. Updated Item to reflect that the project is operational and the associated SCE affected system facilities are in service. This project will be removed from the report during the 2nd Quarter 2017 update. Updated Item to reflect the project has a later Planned In-Service Date. 3

4 Updated Item to reflect that the interconnection agreement was terminated by the Interconnection Customer. This project will be removed from the report in the 2nd Quarter 2017 update. Respectfully submitted, GARY CHEN /s/ Gary Chen By: Gary Chen Attorney for SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California Telephone: (626) January 3,

5 CERTIFICATE OF SERVICE I hereby certify that, pursuant to the Commission s Rules of Practice and Procedure, I have this day served a true copy of QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION AND GENERATION INTERCONNECTION PROJECTS on all parties identified on the attached service list(s). Service was effected by one or more means indicated below: Transmitting the copies via to all parties who have provided an address. First class mail will be used if electronic service cannot be effectuated. Executed this 3rd day of January, 2017, at Rosemead, California. /s/ Norman L. Goss Norman L. Goss Legal Administrative Assistant SOUTHERN CALIFORNIA EDISON COMPANY 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (APRIL 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (JANUARY 2015) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Eldorado-Lugo-Mohave

More information

Updates and Modifications to Report

Updates and Modifications to Report QUARTERLY COMPLIANCE REPORT (APRIL 2011) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS Pursuant to Commission Decision ( D. ) 06-09-003, SCE hereby provides

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Leatherneck

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for Authority to Lease Available Land at Walnut Substation

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER07-1034-002 REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E For a Permit to Construct Electrical Facilities With Voltages

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

February 25, Subject: Southern California Edison 2015 Annual Progress Report

February 25, Subject: Southern California Edison 2015 Annual Progress Report February 25, 2015 Mr. Tracy Rolstad, Chair WECC Technical Studies Subcommittee Avista Corp. 1411 East Mission Avenue Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff Salt Lake City, UT 84103-1114

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ERRATA TO SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) REPLY TO PROTESTS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ERRATA TO SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) REPLY TO PROTESTS BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Certificate of Public Convenience and Necessity

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Cerritos

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

Memorandum. This memorandum requires Committee action.

Memorandum. This memorandum requires Committee action. California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure

More information

North Gila-Imperial Valley #2 Transmission Project

North Gila-Imperial Valley #2 Transmission Project North Gila-Imperial Valley #2 Transmission Project WECC 2015 Annual Progress Report Submitted by: Southwest Transmission Partners, LLC. ISSUED: March 4, 2015 Table of Contents I. Introduction---------------------------------------------------------------

More information

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

July 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities

More information

2012 General Rate Case

2012 General Rate Case Application No.: Exhibit No.: SCE-0, Vol. 0 Part 0 & 0, Ch. I-II Witnesses: P. Arons K. Varnell (U -E) 01 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Part - Transmission

More information

Decision on the 2012/2013 ISO Transmission Plan

Decision on the 2012/2013 ISO Transmission Plan Decision on the 2012/2013 ISO Transmission Plan Neil Millar Executive Director, Infrastructure Development Board of Governors Meeting General Session March 20-21, 2013 Approving the plan means approving

More information

Interconnection and Transmission

Interconnection and Transmission Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection

More information

December 10, 2012 Advice Letter 2797-E

December 10, 2012 Advice Letter 2797-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 10, 2012 Advice Letter 2797-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In The Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for Authority to Lease Certain Fiber Optic Cables to CELLCO

More information

Appendix 1 Interconnection Request INTERCONNECTION REQUEST

Appendix 1 Interconnection Request INTERCONNECTION REQUEST Appendix 1 Interconnection Request INTERCONNECTION REQUEST NO HARD COPY REQUIRED FOR INTERCONNECTION REQUESTS SUBMITTED ELECTRONICALLY VIA RIMS 5 Provide one hard copy of this completed form pursuant to

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PREHEARING CONFERENCE STATEMENT OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PREHEARING CONFERENCE STATEMENT OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into the November 2018 Submission of Southern California Edison Risk Assessment and Mitigation Phase I.18-11-006

More information

2018 General Rate Case

2018 General Rate Case Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: M. Flores B. Tolentino A (U -E) 01 General Rate Case ERRATA Transmission & Distribution (T&D) Volume 0 Substation Construction & Maintenance

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY'S (U 338-E) NOTICE OF COMMUNICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY'S (U 338-E) NOTICE OF COMMUNICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Investigation into the November 2018 Submission of Southern California Edison Risk Assessment and Mitigation Phase. I.18-11-006

More information

November 14, 2008 Advice Letter 2265-E

November 14, 2008 Advice Letter 2265-E STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 November 14, 2008 Advice Letter 2265-E Akbar Jazayeri Vice President, Regulatory Operations

More information

Public Service Company of New Mexico

Public Service Company of New Mexico Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder

More information

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way

October 30, Secretary. above. that. attached. Folsom, CA. 250 Outcropping Way California Independent System Operator October 30, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan

Quarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability

More information

Project Presentation April, 2017

Project Presentation April, 2017 Project Presentation April, 2017 Background and Summary Proposed 114 mile, series compensated 500 kv transmission line project Connects Arizona Public Service s Delaney Substation (Tonopah, AZ) to Southern

More information

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013

Opening. 2013/2014 Transmission Planning Process Stakeholder Meeting. Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Opening 2013/2014 Transmission Planning Process Stakeholder Meeting Tom Cuccia Sr. Stakeholder Engagement and Policy Specialist November 20-21, 2013 Yesterday s Agenda November 20 th Topic Opening Introduction

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: A.1--00 SCE-0, Vol. 0 R. Woods E. Takayesu (U -E) 01 General Rate Case ERRATA Transmission and Distribution (T&D) Volume System Planning Capital Projects Before

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA NOTICE OF EX PARTE COMMUNICATION OF SOUTHERN CALIFORNIA EDISON COMPANY (U338-E)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA NOTICE OF EX PARTE COMMUNICATION OF SOUTHERN CALIFORNIA EDISON COMPANY (U338-E) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E) for Approval of Green Energy Programs. Application No. 18-09-015 NOTICE OF

More information

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document

Alberta Electric System Operator Secord 2005S Substation Needs Identification Document Decision 2014-271 Alberta Electric System Operator Needs Identification Document Facility Application September 24, 2014 The Alberta Utilities Commission Decision 2014-271: Alberta Electric System Operator

More information

149 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER APPROVING STIPULATION AND CONSENT AGREEMENT

149 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER APPROVING STIPULATION AND CONSENT AGREEMENT 149 FERC 61,157 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, and Tony Clark. Western Area Power Administration Desert

More information

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014

January 30, Docket Nos. ER and ER Interconnection Queue Quarterly Progress Report, Q4 2014 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 January 30, 2015 Re: California

More information

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process

Hetch Hetchy Water and Power of the City and County of San Francisco. Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Hetch Hetchy Water and Power of the City and County of San Francisco Joint Transmission Planning Base Case Preparation Process This is a living document. Please

More information

Joint Transmission Planning Base Case Preparation Process

Joint Transmission Planning Base Case Preparation Process California Independent System Operator & Southern California Edison Joint Transmission Planning Base Case Preparation Process NERC Reliability Standard MOD-032-1 Version 1.2 August 31, 2017 INTENTIONALLY

More information

Transmission Register PTO Admin User Manual. Version 1.0

Transmission Register PTO Admin User Manual. Version 1.0 Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6

More information

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO

ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

ITC HOLDINGS, CORP. Edison Electric Institute 9

ITC HOLDINGS, CORP. Edison Electric Institute 9 ITC HOLDINGS, CORP. Company Background: ITC Holdings, Corp. is in the business of investing in electricity transmission infrastructure as a means to improve electric reliability, connect renewable energy

More information

Standard CIP Cyber Security Critical Cyber As s et Identification

Standard CIP Cyber Security Critical Cyber As s et Identification A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification

More information

THE INTERCONNECTION HANDBOOK

THE INTERCONNECTION HANDBOOK THE INTERCONNECTION HANDBOOK Southern California Edison Company Rev. 8 This document is controlled by the originating SCE T&D organization. When downloaded and printed, this document becomes UNCONTROLLED,

More information

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006

Business Update. Al Fohrer Chief Executive Officer Southern California Edison Company. Merrill Lynch Power & Gas Conference September 2006 Business Update Al Fohrer Chief Executive Officer Southern California Edison Company Merrill Lynch Power & Gas Conference September 2006 Forward-Looking Statement This presentation contains forward-looking

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

CenterPoint Energy P O Box 1700 Houston, TX

CenterPoint Energy P O Box 1700 Houston, TX CenterPoint Energy P O Box 1700 Houston, TX 77251-1700 IF YOU ARE APPLYING FOR DISTRIBUTED GENERATION, PLEASE FOLLOW THE INSTRUCTIONS IN THE PARAGRAPHS BELOW. YOU WILL NEED TO COMPLETE AND SIGN AND THEN

More information

SRP Ten Year Transmission Plan

SRP Ten Year Transmission Plan 2018 SRP Ten Year Transmission Plan 2018-2027 Prepared for the Arizona Corporation Commission January 2018 Docket No. E-00000D-17-0001 Page1 Page1 Table of Contents 1. Introduction... 1 2. Planning Organizations...

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

Full Network Model Scope for FNM DB2017Q4

Full Network Model Scope for FNM DB2017Q4 Transmission Projects PG&E SCE 1. Cooley Landing BK2, 115/60 kv Transformer Replacement (Formerly Resource ID P.07237), phase # 1 2. Cortina #3 60kV Line Reconductoring, phase # 1 3. Dyer Summit Wind Repower

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: SCE-1 J. P. Shotwell (U -E) 01 General Rate Case Testimony Regarding Accessibility Issues Developed Jointly By SCE and Center for Accessible Technology Before the

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS?

THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? Whitepaper authored by: Herbert Falk Senior Solutions Architect SISCO, Inc. herb@sisconet.com One of the major

More information

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005

Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency. Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Phasor Technology Research Road Map to Improve Grid Reliability and Market Efficiency Presented to TAC on April 5, 2005 and PAC on April 22, 2005 Background Power Grid has evolved from a vertically integrated

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

March 1, 2013 Advice Letter 2840-E

March 1, 2013 Advice Letter 2840-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor March 1, 2013 Advice Letter 2840-E Akbar Jazayeri Vice President, Regulatory Operations P O Box

More information

The ESP Handbook. Chapter 2 Enrolling in Direct Access An Overview. Version 5.0 December 1, 2011

The ESP Handbook. Chapter 2 Enrolling in Direct Access An Overview. Version 5.0 December 1, 2011 The ESP Handbook Chapter 2 Enrolling in Direct Access An Overview Version 5.0 December 1, 2011 Chapter 2: Enrolling in Direct Access An Overview Providing Direct Access Services in the SCE Service Territory:

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION HORUS Central Valley Solar 1, LLC ) HORUS Central Valley Solar 2, LLC ) ) v. ) Docket No. EL16-104-000 ) California Independent

More information

December 9, 2011 Advice Letter 2613-E

December 9, 2011 Advice Letter 2613-E STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor December 9, 2011 Advice Letter 2613-E Akbar Jazayeri Vice President, Regulatory Operations P O

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (NOT CONSOLIDATED) And Related Matters. Application Application

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (NOT CONSOLIDATED) And Related Matters. Application Application BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for Development of Distribution Resources Plans Pursuant to Public

More information

2012 Grid Assessment Results CAISO Stakeholder Meeting September 26-27, 2012

2012 Grid Assessment Results CAISO Stakeholder Meeting September 26-27, 2012 2012 Grid Assessment Results CAISO Stakeholder Meeting September 26-27, 2012 2006 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Agenda Introduction 2012 Grid Assessment

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E) for Approval of Its 2018-2020 Triennial Investment Plan for the Electric Program

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) )

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Promote Policy and Program Coordination and Integration in Electric Utility Resource Planning. Order Instituting

More information

Introduction to Generation Availability Data System (GADS) Wind Reporting

Introduction to Generation Availability Data System (GADS) Wind Reporting Introduction to Generation Availability Data System (GADS) Wind Reporting Registration and Reporting Fundamentals Donna Pratt, Performance Analysis Manager-Data Analytics NERC Webinar April 26, 2017 Topics

More information

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments

Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Wendy al-mukdad, PE Utilities Engineer Grid Planning & Reliability Section, Energy Division California Public Utilities

More information

RTDS Simulation and Testing of a Remedial Action Scheme at Southern California Edison

RTDS Simulation and Testing of a Remedial Action Scheme at Southern California Edison RTDS Simulation and Testing of a Remedial Action Scheme at Southern California Edison Allison Auld*, Joshua Park*, Anthony Johnson*, Marc Desjardine, and Rudi Wierckx *Southern California Edison, Westminster,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Develop a Successor to Existing Net Energy Metering Tariffs Pursuant to Public Utilities Code Section 2827.1,

More information

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011

Western DSW Planning St k er eeti ting (Western OATT Attachment P) June 9, 2011 Western DSW Planning Stakeholder Meeting (Western OATT Attachment P) June 9, 2011 Agenda: 1. Welcome and Introductions of Attendees 2. Planning Process 3. Interconnection Requests 4. Comments/questions

More information

Small Hydro Regulatory and Permitting Requirements California

Small Hydro Regulatory and Permitting Requirements California Small Hydro Regulatory and Permitting Requirements California Lon W. House, Ph.D. 530.409.9702 Water & Energy Small Hydro Regulatory and Compliance FERC QF, Small Hydro License or Exemption EIA Generator

More information

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation

Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Steve Rutty Director, Grid Assets Lou Fonte Delaney - Colorado River 500 kv Transmission Line Project Phase 3 Competitive Solicitation Lead Engineer, Grid Assets September 3, 2014 Transmission Planning

More information

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM

Public Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES

SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES Per the SAAS Accreditation Agreement and SAAS Procedure 200, all accredited CBs are required to report a written list of all certifications granted every three

More information

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 18, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 18, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application

ATCO Electric Ltd. Dawes Substation and Telecommunications Tower Project Facility Application Decision 2014-039 Dawes Substation and Telecommunications Tower Project Facility Application February 19, 2014 The Alberta Utilities Commission Decision 2014-039: Dawes Substation and Telecommunications

More information

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS

SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES NOTICE TO COMMUNITY ORGANIZATIONS NOTICE IN UTILITY BILLS SECTIONS II - VIII QUANTITY, FORM, AND FILING REQUIREMENTS APPLICATION FILING FEES PROOF OF SERVICE NOTICE TO COMMUNITY ORGANIZATIONS PUBLIC NOTICE NOTICE IN UTILITY BILLS NOTICE OF OWNERS OF PROPERTY

More information

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER

July 30, Q2 Quarterly Report on Progress in Processing Interconnection Requests; Docket No. ER California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 July 30, 2010 Re: Q2 Quarterly

More information

SOUTHERN CALIFORNIA EDISON COMPANY

SOUTHERN CALIFORNIA EDISON COMPANY SOUTHERN CALIFORNIA EDISON COMPANY COMPLIANCE PROCEDURES IMPLEMENTING FERC ORDER 717C STANDARDS OF CONDUCT Version 1.2 Updated June 14, 2017 Purpose: To provide Southern California Edison s (SCE) overall

More information

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company

Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company Requirements for Data for Power System Modeling and Analysis (MOD-032-1) Arizona Public Service Company December 29, 2016 APS Requirements for Data for Power System Modeling and Analysis Table of Contents

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service ) Docket No. ER Company )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service ) Docket No. ER Company ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Arizona Public Service ) Docket No. ER14-2430 Company ) COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION The California

More information

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

ATC Zone 2 Projects Update U.P. Energy Summit

ATC Zone 2 Projects Update U.P. Energy Summit ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project

More information

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D

Arizona Public Service Company Ten-Year Transmission System Plan Docket No. E-00000D (.laps Lisa Malagon Leader Federal and State Compliance Mail Station 9704 PO Box 53999 Phoenix, Arizona 85072-3999 Tel 602-250- 5671 Elisa.Malagon@aps.com January 31, 2014 Docket Control Arizona Corporation

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) NOTICE OF EX PARTE COMMUNICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) NOTICE OF EX PARTE COMMUNICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application Of Southern California Edison Company (U 338-E) For Authority To Increase Its Authorized Revenues For Electric Service In 2018,

More information

RFP Attachment 13. January 2010

RFP Attachment 13. January 2010 PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

Studies Overview and Data Requirements. Robert Pan

Studies Overview and Data Requirements. Robert Pan Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application

More information

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement

Decision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Edison Company (U 338-E) for Approval of the Results of Its 2016 Energy Storage and Distribution Deferral

More information

2015 General Rate Case

2015 General Rate Case Application No.: Exhibit No.: Witnesses: SCE-11 R. Lisbin (U 338-E) 2015 General Rate Case Compliance Before the Public Utilities Commission of the State of California Rosemead, California November 2013