1 Capital Plan Prioritization Using Asset Management Strategies PNCWA Webinar April 22, 2010 Marc W. Yarlott, P.E.
2 Mission for Asset Management International Infrastructure Management Manual NAMS-- 2
3 EPA 10 Steps
4 Condition Assessment What shape is it in? Criticality How important is it? How much life is left? Capital Plan Life Cycle Costing How much will it cost to maintain? How much will it cost to replace?
5 What is a Relative Criticality Analysis? Analysis on a System Level Ranked Relative to Other Plant Systems Analysis of the Relative Criticality of the Assets Being Maintained Where Relative Criticality is a Function of: Consequence of Failure Likelihood of Failure 5
6 How to Complete a Criticality Analysis Define the List of Systems that Provide 100% Asset Coverage Group Workshop Setting (Ops., Maint., Management) For Each System Prepare a List of Worst Case Failure Scenario Descriptions Example: Influent Pump System Stops Pumping and Sewage Backs-up In Basements For Each Scenario Provide Rankings on a Standardized Scale to Quantify Consequence and Likelihood 6
7 Criticality Analysis Ranking Consequence Areas Ranked for Each System s Failure Scenarios Safety Capacity Environmental Operating Costs Stakeholder Collateral Damages Ranked As: Unacceptable Major Undesirable Minor 7
8 Criticality Analysis Answers the question how important is it? 5(High) Consequence 4 2 (Low) Aggressive Monitoring Program Sample Monitoring Immediate Work Aggressive Monitoring Program (Low) (High) Probability
9 Relative Criticality
10 Condition Assessment Answers the question what shape is it in?
11 High-level Condition Assessment Tool
12 Condition Assessment Standards Vibration Score Rating Condition Description Stress Description
13 Life Cycle Analysis Answers the questions how much life is left? What has/will it cost to maintain, and what will it cost to replace? Incorporating: Asset Expected Life Cycle (years) Maintenance Cost Trending and Forecasting Estimated Replacement Value
14 Practical Life of Asset Data
15 Life-Cycle Summary Objective Assets at End of Life - In Poor Condition - Important Capital Plan
16 Condition Assessment Results Life Range Criticality - >10 Years Years Years Years Years + >10 Years Asset Description Remaining Life, Yr Condition (5=good,1=bad) Comments PUMP #1 WEST 16TH WS-0010P W/S CIP 201 PUMP #2 WEST 16TH WS-00140P W/S CIP 201 FLOW MATCHER - RAW SEWAGE RSR1 WS-01160SC W/S CIP 2011 FLOW MATCHER - RAW SEWAGE RSR2 WS-01170SC W/S CIP 2011 GATE - SLUICE #2 INFLUENT W WS W/S -1.7 Cont. Rebuild Thru Maint. 5yr VALVE GROUP RAW SEWAGE PUMPING SYSTEM W/S -2.7 Cont. Repair Thru Maint. 5yr PUMP SUMP WEST 16TH WS-00150P W/S -2.7 CIP 201 PUMP STATION WEST 16TH WS W/S CIP 201 FLUME - PARSHALL INFLUENT SOUTH W/S -2.7 Not Expected to Replace in 5yr FLUME - PARSHALL INFLUENT WEST W/S Not Expected to Replace in 5yr
17 Assessment Summary 450 Count of Assets Criticality 5 Criticality Criticality 2 Criticality Past Life by +10 Years Past Life by Years Past Life by +0-5 Years Remaining Life of +0-5 Years Remaining Life Remaining Life of Years of +10 Years Criticality 5 Criticality Criticality Criticality 1 Count of Assets Condition (5=Good)
18 Capital vs. Maintenance Decisions Repair or Replace? Asset Description Remaining Life Condition Rating (5=good,1=bad) Criticality PUMP #1 LG FRITO-LAY PUMP STATION PUMP #2 LG FRITO-LAY PUMP STATION PUMP #1 LG INDUSTRIAL PUMP STATION W/S PUMP #2 LG-0010 INDUSTRIAL PUMP STATION W/S PUMP # LG INDUSTRIAL PUMP STATION W/S Corrective Costs (Past 4 Yrs) Preventative Costs (Past 4 Yrs) Replacement Costs PUMP #1 LG FRITO-LAY PUMP STATION $ 740 $ 272 $ 15,000 PUMP #2 LG FRITO-LAY PUMP STATION $ 5,42 $ 154 $ 15,000
19
20 Resources EPA Asset Management Scrapbook PNCWA Asset Management Committee Newsletter marc@wllcamg.com WEF Operations Magazine WE&T, April 2010, Factoring Condition Assessment and Asset Management Into Capital Planning QUESTIONS????
21 Abstract With limited funds, it is more important then ever to invest capital for the maximum benefit. Asset Management provides a framework to evaluate and prioritize capital investments by combining condition assessment, expected asset life, and criticality to identify the highest priority repair and replacements. Veolia Water North America (VWNA) has been developing and using a variety of methods to refine the approach to developing a capital plan in accordance with their asset management program. While the ultimate objective is to have a statistically significant projection of expected asset life based on data from the computerized maintenance management system (CMMS), a much simpler program has been developed to establish a baseline for small water and wastewater plants or projects with little CMMS history. The presentation will cover the steps taken to develop a baseline Asset Management Capital Investment Plan including: Determining Criticality using the Relative Criticality Analysis Developing Condition Assessment standards with measurable criteria Using industry standards for expected useful life to project remaining life Sorting and prioritizing asset replacements using the Criticality, Condition, and Expected Remaining Life for Capital Investment Planning. Gresham Story Start somewhere and go broad Gresham Criticality ranking done, then needed condition ranking to each asset in 6 months. Now Asking more questions. How much is spent, etc Gresham - Decision between R&R and Capital Plan Vancouver Frito Lay Using Condition/Criticality to filter results to prioritize the capital plan list Vancouver Maintenance vs. Capital how to take the data and now use it to make decisions. Pivot tables
Asset Management and. Your Name
Asset Management and Criticality: Creative Solutions Novato for our Facilities Environment Your Name Veolia Veolia Water Water North North America America October June 27th, 2010 2014 Mission for Asset
More informationThe City of St. Petersburg (City) initiated
FWRJ Remote Facility Condition Inspections and Subsequent Integration into the City of St. Petersburg s Asset Management Program Laura Baumberger, Robert Labrie, and Rebecca Overacre The City of St. Petersburg
More informationGetting Started with Stormwater Asset Management
Getting Started with Stormwater Asset Management Fall Conference Broken Arrow, OK September 17, 2018 Trey Shanks CFM, IAM, PACP ts@freese.com Asset management roadmap STEP 4 Risk Based Analysis STEP 3
More informationPresented by Joe Burns Kentucky Rural Water Association July 19, 2005
Infrastructure Security for Public Water and Wastewater Utilities Presented by Joe Burns Kentucky Rural Water Association July 19, 2005 Public Health Security and Bioterrorism Preparedness and Response
More informationCity of Denton s Proactive Approach to Asset Management featuring InfoMaster & Cityworks
City of Denton s Proactive Approach to Asset Management featuring InfoMaster & Cityworks Presentation Scope Why asset management Software tools used in Denton asset management plan Detail discussion of
More informationTreatment Facility Asset Management and Risk Based Assessment. NE Texas WEAT Biennial Conference May 7, 2014
Treatment Facility Asset Management and Risk Based Assessment NE Texas WEAT Biennial Conference May 7, 2014 Asset Management What is? A set of processes to minimize infrastructure life cycle costs at an
More informationAsset Management Made Easy. AWWA-PNWS Section Conference April 2018
Asset Management Made Easy AWWA-PNWS Section Conference April 2018 1 Agenda Asset Management basics Asset Management at SPU A few case studies 2 Definitions Asset management A process for maintaining a
More informationAn Update on Security and Emergency Preparedness Standards for Utilities
An Update on Security and Emergency Preparedness Standards for Utilities Linda P. Warren, Launch! Consulting Safety and Security in the Workplace March 28, 2013 Overview 1 Review of AWWA Standards in Water
More informationRESILIENT UTILITY COALITION OF SOUTH FLORIDA
RESILIENT UTILITY COALITION OF SOUTH FLORIDA RUC MISSION The Resilient Utility Coalition seeks to advance utility infrastructure resiliency efforts in South Florida and provide essential value to its members
More informationIdentifying Critical Infrastructure Through the Use of Hydraulic Modeling to Support Asset Management
Identifying Critical Infrastructure Through the Use of Hydraulic Modeling to Support Asset Management James P. Cooper, Prof. Engineer, Cert. Operator Acknowledgements Lisa Gresehover Kimberly Six Karem
More informationSewer System Capital Budget Process
Sewer System Capital Budget Process Presentation to New Castle County Council Department of Special Services Committee Meeting Jason P. Zern, P.E. Operations Engineer March 1, 2016 1 Outline Review Asset
More informationTraverse City Asset Management Plan
Utilities and Public Services Larry LaCross, GISP, Asset Management/GIS Analyst Traverse City Department of Public Services Introduction About Traverse City (TC) TC Assets Department of Public Services
More informationA CMMS CASE STUDY: NEXGEN BOOSTS MAINTENANCE EFFICIENCY AND LABOR PRODUCTIVITY FOR CMSA
A CMMS CASE STUDY: NEXGEN BOOSTS MAINTENANCE EFFICIENCY AND LABOR PRODUCTIVITY FOR CMSA ABOUT CMSA Operational since 1985, the Central Marin Sanitation Agency (CMSA) operates the largest wastewater treatment
More informationPERSPECTIVES ON A J100 VULNERABILITY ASSESSMENT OUTCOMES AND LESSONS LEARNED BY MINNEAPOLIS WATER AUGUST 2016
PERSPECTIVES ON A J100 VULNERABILITY ASSESSMENT OUTCOMES AND LESSONS LEARNED BY MINNEAPOLIS WATER AUGUST 2016 Mr. Glen Gerads, Director of Minneapolis Water Mr. Andrew Ohrt, PE, Arcadis Agenda What is
More informationService Plan for Infrastructure Engineering
Service Plan for Infrastructure 2016-2019 Capital Regional District Date submitted: Revised: August 14, 2017 Table of Contents 1 Overview... 1 1.1 Division & Service Summary... 1 1.2 Organization Chart...
More informationPursuing Excellence in Asset Management
Agenda Number 4. Pursuing Excellence in Asset Management Taking it to the next level Greg Ramon, Assistant General Manager Maintenance Administration June 5, 2014 Asset Management History 1985 to 2003:
More informationElectric Load Growth Q2 Update. Chad Rissman- Director of Engineering and Asset Management & Andy Wendell Director of Customer Services April,
Electric Load Growth Q2 Update Chad Rissman- Director of Engineering and Asset Management & Andy Wendell Director of Customer Services April, 2 2018 1 Updates Informational, no action required Discussions
More informationExecutive summary. Natural disasters including bushfires, floods, storms and cyclones have destructive and devastating consequences for Australia
Natural disasters including bushfires, floods, storms and cyclones have destructive and devastating consequences for Australia The impacts of these disasters to businesses, properties and people have been
More informationProject Life Cycle Support (SCADA)
Project Life Cycle Support (SCADA) Texas Association of Clean Water Agencies Garland, TX March 26, 2010 Yehuda Morag CH2M HILL, Austin TX WBG030410171936AUS Agenda Introduction to SCADA Utility Managers
More informationAnnual Report for the Utility Savings Initiative
Report to the North Carolina General Assembly Annual Report for the Utility Savings Initiative July 1, 2016 June 30, 2017 NORTH CAROLINA DEPARTMENT OF ENVIRONMENTAL QUALITY http://portal.ncdenr.org Page
More informationTransmission Resiliency & Security
Transmission Resiliency & Security Response to High Impact Low Frequency Threats Richard Lordan, PE Senior Technical Executive NCSL-NARUC Energy Risk & Critical Infrastructure Protection Workshop May 25,
More informationALBEMARLE COUNTY SERVICE AUTHORITY
ALBEMARLE COUNTY SERVICE AUTHORITY AGENDA ITEM EXECUTIVE SUMMARY AGENDA TITLE: Strategic Plan Process STAFF CONTACT(S)/PREPARER: Gary O Connell, Executive Director AGENDA DATE: September 20, 2018 ACTION:
More informationReliability Excellence (RE)
Reliability Excellence (RE) Taking it to the next level Greg Ramon May 1, 2014 Asset Management History 1985 to 2003: Reactive Maintenance Reactive fix it when it breaks 2003 to 2012: Maintenance Excellence
More informationMassachusetts Water Resources Authority FY17 Proposed Capital Improvement Budget
Massachusetts Water Resources Authority FY17 Proposed Capital Improvement Budget December 16, 2015 FY17 Proposed CIP Fix it First MWRA continues to focus on Asset Protection and Long Term Redundancy initiatives;
More informationFacility Condition Assessments
Facility Condition Assessments City Council Work Session: July 1, 2014 Department of Public Works Introduction Andrew Clough, Director, Public Works Phil Harrington, Deputy Director, Public Works Lorin
More informationAnnie Vanrenterghem Raven, PhD, Principal, infraplan, LLC, New York, NY. Kurt Vause, Engineering Director, AWWU, Anchorage, Alaska
Annie Vanrenterghem Raven, PhD, Principal, infraplan, LLC, New York, NY Kurt Vause, Engineering Director, AWWU, Anchorage, Alaska infraplan Introduction Analytical? Analytical Program What does it take?
More informationSouth Dakota Utah Wyoming Needs and Challenges Funding assistance Training Federal program enhancements Exercises
STATE, LOCAL, TRIBAL, AND TERRITORIAL GOVERNMENT COORDINATING COUNCIL REGIONAL CONSORTIUM COORDINATING COUNCIL Regional Overview of Critical Infrastructure Programs Region Snapshot Region VIII The State,
More informationBaltimore City Department of Public Works
Baltimore City Department of Public Works Bureau of Water and Wastewater WHEN IT BREAKS, IT POURS January 16, 2014 Presentation Outline Overview of Baltimore Water System Light Street Main Break Asset
More informationRockwell Automation ODVA Annual Meeting
Rockwell Automation ODVA Annual Meeting Copyright 2011 Rockwell Automation, Inc. All rights reserved. Topics Industrial Energy Management: Industrial GreenPrint Business Drivers Enabling Solutions Copyright
More informationInfrastructure and Asset Management. and Asset Management
Infrastructure and Asset Management 18/09/2015 Emad Elbeltagi 1 W elcome to Infrastructure and Asset Management 18/09/2015 Emad Elbeltagi 2 1 About Emad Elbeltagi Structure and delivery Assessment Course
More informationSecurity Master Planning to Protect Water Resources Lara Kammereck John Saunders May 1, 2015
Security Master Planning to Protect Water Resources Lara Kammereck John Saunders May 1, 2015 Who is Cascade Water Alliance? Joined together in 1999 350,000 residents 20,000 businesses City of Bellevue
More informationMaximizing the University s Physical Assets (Part I): Facility Condition Assessment
Maximizing the University s Physical Assets (Part I): Facility Condition Assessment Board of Regents Facilities and Operations Committee September 12, 2013 Agenda Program background Broadening our data
More information5 Servicing Capacity Assignment for Aurora, East Gwillimbury and Newmarket
Clause 5 in Report No. 11 of Committee of the Whole was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on June 28, 2018. 5 Servicing Capacity Assignment
More informationNEORSD s Model-Based Approach to Support Regulatory Compliance of a CSO Consent Decree and NPDES Permit
NEORSD s Model-Based Approach to Support Regulatory Compliance of a CSO Consent Decree and NPDES Permit Advanced Seminar on GIS-Centric Applications for Utility Planning & Operations Ohio Innovyze User
More informationCanadian Infrastructure Report Card
Chris McNally, P.Eng. Presentation to the Institute of Intergovernmental Relations June 2015 Project Sponsors: 1 The Problem According to Statistics Canada, the Gross stock of core public infrastructure
More informationMaster Plan for the Port of New York and New Jersey: A Road Map for the Next 30 Years
Master Plan for the Port of New York and New Jersey: A Road Map for the Next 30 Years **Hatch: Please provide images used on GID presentation title page. Also please provide replace image of 1 WTC with
More informationProcuring New Infrastructure for Canada s Municipalities
1 V E R K I M I C H A E L T U N T E N G - H E E N A N B L A I K I E L L P C A R D I F F 2 2 O C T O B E R, 2 0 1 3 Procuring New Infrastructure for Canada s Municipalities Public-Private-Partnerships and
More informationThe J100 RAMCAP Method
The J100 RAMCAP Method 2012 ORWARN Conference Kevin M. Morley, PhD Security & Preparedness Program Manager AWWA--Washington, DC Water is Key to Daily Life Potable drinking water Sanitation Public Health
More informationSTATE BROADBAND ACTION PLAN MAY 2015 Nevada Economic Development Conference PREPARED BY CONNECT NEVADA AND THE NEVADA BROADBAND TASK FORCE
STATE BROADBAND ACTION PLAN MAY 2015 Nevada Economic Development Conference PREPARED BY CONNECT NEVADA AND THE NEVADA BROADBAND TASK FORCE PLAN STRUCTURE I INTRODUCTION Background History of the Project
More informationRegional TSM&O Vision and ITS Architecture Update
Regional TSM&O Vision and ITS Architecture Update Progress Update Transportation Coordinating Committee April 5, 2019 Task List (2018 2020) 1. Develop a Regional TSM&O Vision 2. Document Current TSM&O
More informationEnergy Action Plan 2015
Energy Action Plan 2015 Purpose: In support of the Texas A&M University Vision 2020: Creating a Culture of Excellence and Action 2015: Education First Strategic Plan, the Energy Action Plan (EAP) 2015
More informationWELCOME TO A SILVER JACKETS WEBINAR ON:
WELCOME TO A SILVER JACKETS WEBINAR ON: Flood Vulnerability Assessment for Critical Facilities For audio, call 877-336-1839 Access code: 8165946 Security Code: 4567 MOLLY WOLOSZYN Extension Climate Specialist
More informationMinimum Support Needed for a Reliable SCADA System
Minimum Support Needed for a Reliable SCADA System Speaker Bio Jeff Miller, PE, ISI ENV SP Dewberry Automation Manager MEP Service Line Raleigh, NC 22 years experience in Electrical / Instrumentation &
More informationFACILITIES CAPITAL. FY 2007 Appropriation $98,554,760 FY 2008 Estimate $105,429,240 FY 2009 Estimate $128,000,000
FACILITIES CAPITAL FY 2007 Appropriation $98,554,760 FY 2008 Estimate $105,429,240 FY 2009 Estimate $128,000,000 STRATEGIC GOAL: ENHANCED MANAGEMENT EXCELLENCE Federal Resource Summary by Performance Objective
More informationFederal Railroad Administration Southeast Regional Rail Planning Study
Federal Railroad Administration Southeast Regional Rail Planning Study Stakeholder Group Workshop 3 Orlando, Florida Next Steps Sunserea Dalton, CH2M March 1, 2017 Next Steps Provide input on Workshop
More informationRevenue Management as a Customer Service. Ed Hackney
Revenue Management as a Customer Service Ed Hackney About Ed 14 years with SUEZ and United Water Revenue Management Operational Technology Engineering IT 2 Internet Startups 2 Big 4 consultancies BS Rutgers
More informationCapital Planning & Financing
Capital Planning & Financing Lifelines Council Brian Strong, Director of Capital Planning City and County of San Francisco November 17, 2011 Capital Planning Discussion San Francisco Capital Plan Overview
More informationChapter 18 SaskPower Managing the Risk of Cyber Incidents 1.0 MAIN POINTS
Chapter 18 SaskPower Managing the Risk of Cyber Incidents 1.0 MAIN POINTS The Saskatchewan Power Corporation (SaskPower) is the principal supplier of power in Saskatchewan with its mission to deliver power
More informationREPORT TO COUNCIL City of Sacramento
REPORT TO COUNCIL City of Sacramento 915 I Street, Sacramento, CA 95814-2604 www. CityofSacramento.org 14 Consent November 10, 2009 Honorable Mayor and Members of the City Council Agreement: Supervisory
More informationJo-Anna Wood WHO Global Observatory for ehealth: research and resources for use in Australia HIC 2016
Jo-Anna Wood B.Comm, MA, CHIA Chair HISA Victoria Committee WHO Global Observatory for ehealth: research and resources for use in Australia Prepared by The Checkley Group www.checkley.com.au INTRODUCTION
More informationUSERS CONFERENCE Copyright 2016 OSIsoft, LLC
HRSD - Bringing Time and Space Together for Operational Awareness in Waste Water Presented by Kimberly Peterson, Data Analysis Manager, HRSD Clay Wise, Chief of IT Operations & Support, HRSD Agenda Outline
More informationContractor Alliancing Sean Mooney Programme Manager
1 Contractor Alliancing Sean Mooney Programme Manager Today s Agenda Introduction Background Contractor Alliancing The Process Alliance Electricity Alliance North (EAN) Optimise Water (LLP) JV Benefits
More informationSENATE, No STATE OF NEW JERSEY. 217th LEGISLATURE INTRODUCED DECEMBER 12, 2016
SENATE, No. STATE OF NEW JERSEY th LEGISLATURE INTRODUCED DECEMBER, 0 Sponsored by: Senator STEPHEN M. SWEENEY District (Cumberland, Gloucester and Salem) Senator LINDA R. GREENSTEIN District (Mercer and
More informationSANITATION PROJECTS. Current Year Project Future Year Project. 2 10" to 14" Sewerline Rehab (Various Locations - Not Mapped)
SANITATION PROJECTS Sanitation projects represent three categories of capital improvements: facilities replacement projects, sewerline replacement projects, and capital projects to expand or upgrade the
More informationLabs21 Sub-Metering Guidelines for Laboratory Facilities
DRAFT OUTLINE 6-17-10 Note: This draft outline is only a strawman to facilitate discussion. It is expected that it will be revised based on stakeholder review and input. Please provide comments using track
More informationGMLC Grid Analysis and Design for Energy and Infrastructure Resilience in New Orleans, LA
GMLC 1.3.11 - Grid Analysis and Design for Energy and Infrastructure Resilience in New Orleans, LA ROBERT JEFFERS, SANDIA NATIONAL LABORATORIES April 18-20, 2017 Sheraton Pentagon City Arlington, VA Security
More informationDEVELOPMENT OF OPERATIONAL MANUALS. Jason Whittaker. Goulburn Valley Water
DEVELOPMENT OF OPERATIONAL MANUALS Paper Presented by : Jason Whittaker Author: Jason Whittaker, Technical Officer, Goulburn Valley Water 67 th Annual Water Industry Engineers and Operators Conference
More informationDraft Water Master Plan Capital Improvement Program
Draft Water Master Plan Capital Improvement Program December 17, 2014 Tualatin Valley Water District Water Master Plan Today s meeting: Water Master Planning and CIP overview Origin of the Draft Level
More informationJohn P Buechler NYISO Executive Regulatory Policy Advisor. NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY
Eastern Interconnection Planning Collaborative Update John P Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental and Regulatory Affairs Advisory Group Meeting Albany, NY November 30, 2010
More informationPractical IT Research that Drives Measurable Results OptimizeIT Strategic Planning Bundle
Practical IT Research that Drives Measurable Results OptimizeIT Strategic Planning Bundle Info-Tech Research Group 1 An IT Strategy must lay out a roadmap and budget for investment to establish the systems,
More informationAGENDA ITEM EXECUTIVE SUMMARY
202 AGENDA ITEM EXECUTIVE SUMMARY Agenda Item: Presenter & Title: Wastewater Treatment Plant SCADA System and Fiber Optic Communication System Upgrades Richard Babica, Director of Public Works Date: May
More information2017 IESALC FALL TECHNOLOGY MEETING
2017 IESALC FALL TECHNOLOGY MEETING CONDUCTING AIRFIELD LIGHTING ASSESSMENTS TO IDENTIFY FUTURE CAPITAL IMPROVEMENT PROJECTS HYATT REGENCY DALLAS OCTOBER 22 26 2017 PRESENTED BY MARK A. MORLEY, P.E., RCDD
More informationPinellas County. Business Technology Services. BTS Board Meeting April 19, 2018
Pinellas County Business Technology Services BTS Board Meeting April 19, 2018 Agenda 1. Call to Order (Commissioner Welch, Chair) 2. Designation of Voting Members (Commissioner Welch, Chair) 3. Action
More informationCritical Infrastructure Assurance BC s s Lower Mainland
Critical Infrastructure Assurance BC s s Lower Mainland A Status Update to EPICC 2008 February EPICC 1 When It All Goes Wrong Everyone, help me! http://www.koreatimes.co.kr/upload/news/cartoon(66).jpg
More informationBALTIMORE UTILITY ASSET MANAGEMENT DIVISION
BALTIMORE UTILITY ASSET MANAGEMENT DIVISION Baltimore City s Asset Management Program Sustainable Best Management Practices in Transportation Workshop July 16, 2013 Rudy S. Chow, P.E. Bureau Head Alfred
More informationOUR FINAL ASSURANCE PLAN FOR PR19
OUR FINAL ASSURANCE PLAN FOR PR19 Contents 1 2 3 4 5 6 7 8 Introduction and background Our governance structure for PR19 What information needs assuring? Forms of assurance Our risk assessment process
More informationFLORIDA STATE UNIVERSITY MASTER PLAN 10 Utilities
UTILITIES ELEMENT NOTE: Unless otherwise noted, the goals, objectives and policies contained in this element shall guide development of the Main Campus and Southwest Campus in Tallahassee as well as the
More informationNext Generation Telemetry Systems Improve Utility Effectiveness
Improve Utility Effectiveness 2016 NC AWWA-WEA Spring Conference Asheville, North Carolina 1:40pm Monday April 18 th, 2016 Presented by Jeff M. Miller, PE, ENV SP Authored by Jeff M. Miller, PE, ENV SP
More informationPhysical Security Reliability Standard Implementation
Physical Security Reliability Standard Implementation Attachment 4b Action Information Background On March 7, 2014, the Commission issued an order directing NERC to submit for approval, within 90 days,
More informationFY Bay Area UASI Risk and Grants Management Program Update. November 14, 2013
FY 2013-2014 Bay Area UASI Risk and Grants Management Program Update November 14, 2013 Overview FY 2013 Bay Area UASI Risk and Grants Management Program May 2013 December 2013 Data Management Analysis
More information2015 HDR, all rights reserved.
2015 HDR, all rights reserved. An Alternative to HEC-GEORAS: Overview & Comparison of AutoCAD River & Flood Analysis Module Ron Branyon, PE, CFM George Doubleday, EIT, CFM Brandon Hilbrich, PE, CFM TFMA
More informationCity of San Antonio Utilizing Advanced Technologies for Stormwater System Mapping and Condition Assessments
City of San Antonio Utilizing Advanced Technologies for Stormwater System Mapping and Condition Assessments Prepared for: 2017 ESRI Users Conference Prepared by Noelle Gaspard, PE, GISP, CFM July 12,2017
More informationSoutheast Florida Regional Climate Change Compact Update. Broward Climate Change Task Force February 16, 2017
Southeast Florida Regional Climate Change Compact Update Broward Climate Change Task Force February 16, 2017 Overview Recent Activities RCAP Update Forthcoming Efforts Regional Resilience Projects Summit
More informationFog Computing Design Principles for Industrial IoT Applications. Sudhanshu Gaur Director, Industrial IoT R&D Hitachi America, Ltd.
Fog Computing Design Principles for Industrial IoT Applications Sudhanshu Gaur Director, Industrial IoT R&D Hitachi America, Ltd. IoT Trends & Challenges More data from more sources helps businesses make
More informationCDIA Strategies for Sustaining and Up-scaling Interventions in Viet Nam
Regional Workshop on Integrated Resource Management in Asian Cities: The Urban Nexus Da Nang, Viet Nam 25-27 June 2014 CDIA Strategies for Sustaining and Up-scaling Interventions in Viet Nam by Joy Bailey,
More informationSP Energy Networks Business Plan
SP Energy Networks 2015 2023 Business Plan Updated March 2014 Annex 132kV Substation Plant Strategy SP Energy Networks 29 March 2014 March 2014 Issue Date Issue No. Document Owner Amendment Details 17th
More informationThe standard base asset life used in the renewal programme and asset valuation for facility assets (major components) are shown in the table below:
7.3.6 Facilities Background Plant is defined as asset components that pump, store or treat water. Key components include: Pumping stations - pumping of water to within the reticulation Treatment plants
More informationA Regional Water Utility and the Private Sector Defining a Partnership for Infrastructure Delivery
A Regional Water Utility and the Private Sector Defining a Partnership for Infrastructure Delivery Carmel Krogh Director Shoalhaven Water Shoalhaven City Council Shoalhaven City Council Structure Asset
More informationMigration towards a technology supported integrated network management model
Migration towards a technology supported integrated network management model Gonzalo Reyes B. Engineering, Planning and Tariff Management Manager ESSBIO - NUEVOSUR May 2017 CHILEAN WATER UTILITY SECTOR
More informationAtlantic Coast Service Center
Atlantic Coast Service Center Robert W. Pearson, PE Senior Forensic Civil/Structural Engineer 704-533-3250 rpearson@uis-usa.com EDUCATION: Virginia Tech Blacksburg, Virginia Bachelor of Science in Civil
More informationDepartment of Defense Installation Energy Program
Department of Defense Installation Energy Program Ms. Lisa A. Jung Deputy Assistant Secretary of Defense, Installation Energy Office of Assistant Secretary of Defense Energy, Installations & Environment
More informationDepartment of Management Services REQUEST FOR INFORMATION
RESPONSE TO Department of Management Services REQUEST FOR INFORMATION Cyber-Security Assessment, Remediation, and Identity Protection, Monitoring, and Restoration Services September 3, 2015 250 South President
More informationCommittee on Water and Task Force on Innovation
Committee on Water and Task Force on Innovation Using IIoT to Drive Business Insights John Kuchmek American Water Krishna Kumar App Orchid WHO WE ARE We are the largest and most geographically diverse
More informationArcGIS in the Cloud. Andrew Sakowicz & Alec Walker
ArcGIS in the Cloud Andrew Sakowicz & Alec Walker Key Takeaways How to Identify Organizational Strategy & Priorities Esri s Cloud Offerings A Broad Spectrum Successfully Executing Your Strategy The Cloud
More informationSM05: Risk Analysis: A Comparison in Quantifying Asset Values, Threats, Vulnerabilities and Risk. Doug Haines Haines Security Solutions 9 April 2013
SM05: Risk Analysis: A Comparison in Quantifying Asset Values, Threats, Vulnerabilities and Risk Doug Haines Haines Security Solutions 9 April 2013 The Broad Picture Learning Objectives Know the differences
More informationIndustrial Energy Efficiency
ABB Global Consulting, APW 2011, Orlando Industrial Energy Efficiency Metals Industry Case Study April 19, 2011 Slide 1 Introduction ABB Global Consulting Products Capability Industrial Energy Efficiency
More informationContents. Critical Analysis Assessing Vulnerability October, Overview/Purpose of Criticality Analysis Criticality Analysis
Critical Analysis Assessing Vulnerability October, 2016 Murray, Smith & Associates, Inc. Washington APWA Conference Spokane, WA 1 Contents Overview/Purpose of Criticality Analysis Criticality Analysis
More informationValue & Risk in the New Energy Era: Rethinking Asset Investment Decisions
Value & Risk in the New Energy Era: Rethinking Asset Investment Decisions June 15, 2017 etsinsights.com 1 Value & Risk in the New Energy Era: Rethinking Asset Investment Decisions June 15, 2017 Agenda
More informationUsing Metrics to Gain Management Support for Cyber Security Initiatives
Using Metrics to Gain Management Support for Cyber Security Initiatives Craig Schumacher Chief Information Security Officer Idaho Transportation Dept. January 2016 Why Metrics Based on NIST Framework?
More informationBremner Transformer Station and Cable Tunnel PROGRESS OF THE CLASS ENVIRONMENTAL ASSESSMENT STUDY
May 19, 2011 Community Meeting Metro Toronto Convention Centre North Building, Room 203B May 19 th, 2011, 4:30 p.m. to 7:30 p.m. Please sign in and complete a comment sheet Project team members are available
More information3/2/2010. SCADA Defined. What They re Generally Best At (Although All Systems Vary) Three Levels of SCADA Systems
SCADA Data Mining and IT Needs to Improve Plant Operation and Downtime AWEA Wind Power Asset Management Workshop Adopted for Wind Power Management class http://www.icaen.uiowa.edu/~ie_155/ by Andrew Kusiak
More informationDISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY ATTACHMENT A A-1: BACKGROUND AND CONTRACTOR QUALIFICATIONS A-2: SCOPE OF WORK
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY ATTACHMENT A A-1: BACKGROUND AND CONTRACTOR QUALIFICATIONS A-2: SCOPE OF WORK GOODS AND SERVICES CONTRACTS Page 1 of 5 RFP 16-PR-DEM-33 Comprehensive All-Hazards
More informationUnderstanding Holistic Effects of Cyber Events on Critical Infrastructure
Understanding Holistic Effects of Cyber Events on Critical Infrastructure Shane Cherry Infrastructure Analysis and Technology Development National and Homeland Security Directorate March 20, 2018 INL/CON-17-42513
More informationManaging Energy at Your Small Drinking Water System A Workshop Series for New Hampshire Utilities
Managing Energy at Your Small Drinking Water System A Series for New Hampshire Utilities 2 08/24/16 Lincoln Town Hall, Lincoln, NH Facilitator David R. Tucker This program is made possible under a cooperative
More informationNear-port Community Capacity Building Toolkit for Effective EJ Stakeholder Engagement
Near-port Community Capacity Building Toolkit for Effective EJ Stakeholder Engagement Sabrina Johnson, Project Lead EPA Office of Transportation & Air Quality presented at 2016 Urban Waters Federal Partnership
More informationEPA Near-port Community Capacity Building: Tools and Technical Assistance for Collaborative Solutions
EPA Near-port Community Capacity Building: Tools and Technical Assistance for Collaborative Solutions Sabrina Johnson, Project Lead EPA Office of Transportation & Air Quality presented at Southeast Diesel
More informationInfrastructure Resilience in Northland. Northland Lifelines Group October 2008
Infrastructure Resilience in Northland Northland Lifelines Group October 2008 NLG what have we achieved so far? Priority utility sites and routes Lifeline utility protocols and debriefs following events
More informationFacilities Master Plan Toronto Public Library Board Consultation
STAFF REPORT INFORMATION ONLY Facilities Master Plan Toronto Public Library Board Consultation Date: May 28, 2018 20. To: From: Toronto Public Library Board City Librarian SUMMARY The purpose of this report
More informationEvaluation of Jackson and Saylor Sanitary Sewer Lift Station During July 23-24, 2010 Storm Event. Presented by:
City of Elmhurst Evaluation of Jackson and Saylor Sanitary Sewer Lift Station During July 23-24, 2010 Storm Event Christopher B. Burke Engineering, Ltd. Presented by: Christopher B. Burke, PhD, PE, D.WRE,
More informationNERC History, Mission and Current Issues Southern States Energy Board. October 16, 2011
NERC History, Mission and Current Issues Southern States Energy Board October 16, 2011 Electricity Vital to America 2 RELIABILITY ACCOUNTABILITY Risk Curve with Actual Events Severity ( Log Base 10) 2003
More information