PAC World Conference IEC A to Z Implementation in a Nutshell

Size: px
Start display at page:

Download "PAC World Conference IEC A to Z Implementation in a Nutshell"

Transcription

1 PAC World Conference 2016 IEC A to Z Implementation in a Nutshell Topics #: Authors' names: 4. Standardization and harmonization of system models 10. IEC 61850, tools, applications and benefits 27. Engineering of protection, automation and control systems Patrick Ducret, Yannick Thiessoz, Jörg Reuter Authors' affiliation: Romande Energie SA, Infoteam SA, Helinks LLC Country: Switzerland address: patrick.ducret@romande-energie.ch 1

2 IEC A to Z Implementation in a Nutshell Contents Abstract Motivation IEC Data Model and Signal mapping End to End Engineering Standardization Process Tools and Products Conclusion Outlook Figure 1: Aspects of the IEC adaptation project... 4 Figure 2: Romande Energie Process Signals... 4 Figure 3 Signal Mapping... 5 Figure 4: End to End Engineering... 6 Figure 5: Example of Mapping of Protocols and Network Control Center Data... 6 Figure 6 Library Element and Content... 7 Figure 7: Standardization Process and Project Engineering Process... 8 Figure 8 Project Engineering Process... 9 Figure 9: Tools and Products Figure 10 Illustration of System Configuration Tool

3 Abstract Romande Energie SA, DSO in Switzerland, has successfully optimized its engineering process adopting the IEC top down process. Their solution emphasizes standardization and engineering automation for System specification o Single line diagram o Signal lists o Address allocation o HMI and NCC configuration System Configuration o Network configuration o Horizontal/vertical communication configuration (end to end engineering) Documentation The purpose of this paper is to show the steps it took to introduce this new way of working, and the resulting benefits for different project use cases: retrofit, maintenance and extension of existing substations. A concrete example explains the process from the specification to the implementation and the usage of tools. The paper will also show the benefits of the standardisation and opportunities for the future. 1. Motivation Romande Energie Group is the leading electricity distributor in Western Switzerland. It supplies more than 300,000 end-customers directly in approximately 300 municipalities in the cantons of Vaud, Valais, Fribourg and Geneva. Its core business lines are the generation, distribution and marketing of power together with energy services. Romande Energie recognized in 2008 that intelligent communication and standardized data modelling as it is provided by IEC has the potential to decrease wiring, engineering and maintenance costs by improving at the same time functionality and security of their substations. Their evaluation of IEC showed us that the task of adopting IEC is not an easy one. Romande Energy identified the key success factors for this endeavor: IEC Data Model and Signal mapping: Mastering IEC and building an IEC Data Model for their applications and signals. End to End Engineering: Extending the technological scope of the project beyond IEC By including the signal flow from the primary process up to the Station HMI and Network Control Center communication, they intended to create a seamless integration of all signal engineering tasks. This is what Romande Energy calls End to End Engineering Process: The conventional Electrical Schema Drawing oriented processes needed to be revised. This implied changes in the interfaces of departments (Drawing, Protection Control) and put new requirements on the qualification of the engineering teams. HR related challenges were not to be underestimated. 3

4 Standardization: Once the process and related data were defined, typical solutions could be extracted and placed into solution libraries. Using solution libraries was expected to drastically decrease engineering times and improve the quality of the delivered systems. Tools: The complexity of the engineering task and the need for standardization could not be mastered without appropriate tool support. Tool integration needed to happen from the process level tools up to the HMI configuration tools. Figure 1: Aspects of the IEC adaptation project 2. IEC Data Model and Signal mapping Romande Energie used to work with signal lists, wiring and protection schemes as well as functional descriptions, control schemes and IED specifications Figure 2: Romande Energie Process Signals shows an example of non IEC signal definitions. Figure 2: Romande Energie Process Signals Romande Energie decided to use IEC Functional Naming. This implicated to create an IEC model of our substations. They had to map and adapt their naming rules and structures to meet the SCL schema (Substation Section of SCL schema, IEC Part 6). 4

5 Once the structures in place, they used these structures to create a signal list with unique and IED independent signal names. Identifying the proper IEC Data Attributes for existing signals turned out to be a real challenge. On one side a deep know how of the Logical Nodes and Data Attribute semantics was needed in order to identify the corresponding IEC Data Object and Attribute, on the other side they needed to resolve semantic conflicts between the RE control & protection philosophy and the semantics of the standard. Overcoming this led us to define a nonnegligible amount of GGIOs. Things became not easier when it turned out that also among the IED manufacturers and IED implementations the use of IEC semantics followed often different principles. Thus they could not define a device independent RE model and ended up by creating IED specific IEC signal mappings. This showed later to be a good decision. Once IED specific IEC61850 mappings were added to the Templates, configuring the IEC communication structures (Data Sets and Control Blocks) was performed by a single mouse click.. Figure 3 Signal Mapping The tables in Figure 3 are showing the mapping principle. The left part represents the Romande Energie Signal as it was used in conventional substations. The middle part shows the IED independent mapping and the right part gives an example of mapping to a particular IED Type. The type is identified by String F101 in the IED Name field. Please observe the differences of the IEC representation between the middle part and the right part. The IED independent representation has no IED Name, no Logical Device and no Logical Node instance number. The IED specific representation uses these values in order to identify a specific instance inside the IED. The example is straight forward and simple. As mentioned before, there were manifold mapping problems to be solved. Digging into these would largely stretch the scope of this paper. Part of the evaluation activities was a project to prove this concept by implementing an interchangeability use case. Romande Energie showed that it was possible to replace a device of one manufacturer by a similar device from another. Because all the engineering templates were using part 1 and 2 of the table above it was just a matter of exchanging part 3 for a new IED, press the build application button of the IEC System Tool (see: Tools and Products), upload the new configuration file and restart the system. 5

6 3. End to End Engineering IEC mapping is a crucial element of the SAS engineering process, but it is not everything. Configuring the communication gateway, defining the IEC104 or 101 communication addresses and engineering the HMI are also important elements. Romande Energies vision was to include all these steps in the process and cover them with a set of well integrated tools. This approach is called End to End Engineering. Figure 4: End to End Engineering The modelling work was extended to include all aspects of a signal needed to realize the End to End Engineering. Figure 5 shows how the 104 protocol is included as well as data for the Network Control Center. Figure 5: Example of Mapping of Protocols and Network Control Center Data Similar mappings exist for the Station HMI. In this paper we are showing the conceptual mapping using Excel. Substation engineers all over the world are using similar lists for similar engineering tasks. The difference however is, that we designed the lists very strictly following the IEC data model and prepared them in a way that appropriate tools can import these lists and automate the engineering work. 6

7 4. Standardization Standardization requires the definition of reusable elements from the model. These reusable elements can be used as building blocks for projects. It is important to find the right granularity for the building blocks. Romande Energie decided to define Function Types and Bay Types. Figure 3 Signal Mapping shows the set of signals for a typical Disconnector Function. Figure 6 Library Element and Content The System Configuration Tool is used to draw the Single Line. The disconnector Q9 in the Single Line is associated with the library element Disconnector Function. (Figure 1) The library element Disconnector Function contains all the information for the End to End Engineering. The System Configuration Tool creates and exports with a high degree of automation consistently all configuration files needed for the project. The Romande Energie Signal Identification and the Wiring Information is used for documentation purposes. The Romande Energie Signal Identification also serves as unique identifier for a signal. The IEC Mapping information, together with ICD or IID files is used to create the IEC SCD file including Data Sets and Control Blocks for Client Server and GOOSE communication. The 104 addresses, routing information and texts are used to create the Gateway configuration files and finally the NCC related information supports the Network control system setup. The Function Types are used to assemble the next higher library element, which is the Bay Type. Typical Bay Types are Feeder -, Transformer -, and Bus Coupler bays. By instantiating a Bay Type the complete End to End Engineering information can be instantiated. Powerful deep copy operations in the System Configuration Tool give another boost to engineering efficiency. 7

8 5. Process We cannot afford inventing the wheel multiple times. That is why Romande Energie continuously performs the concept and standard development work independently of the ongoing substation automation projects. (Standard Design). After the initial effort of developing the End to End templates they are now in the maintenance phase for the engineering standards. This includes two major activities: 1. Incorporate feedback from projects into the End to End Library 2. Performing IED qualifications to adapt to new products on the market. Figure 7: Standardization Process and Project Engineering Process Basically the project engineering process for a new SAS system needs 3 inputs: Single Line Diagram End to End Templates ICD, IID or even SCD files The Single Line Diagram defines the IEC structure of the system. These structures are used to allocate functions and to create hierarchical names for all elements of the projects. (IEDs, signals, variable replacement for HMI texts ). The elements of the End to End Templates are applied based on the structure of the Single Line. The IEDs are brought into the project based on prequalified ICD files. Depending on the IED Type also entire SCD files are added to the project. In this case the SCD file contains the IED instances, but no communication configuration. Using the information from the templates the SCD tool now creates the configuration files for the different devices. Outputs of this process step are: An SCD file with the IEC communication configuration. This SCD file is then loaded into the vendor tools (ICT) in order to setup the IEDs compliant to the system configuration. A configuration file for the Gateway and HMI configuration tool. 8

9 A Signal list for as build documentation 6. Tools and Products Figure 8 Project Engineering Process The concept of End to End Engineering requires a seamless integration of tools and products. Romande Energy is a member of a consortium of utilities which have developed and currently own the StreamX platform. StreamX is a modular set of products and tools with the following components: Multi-protocol, IT security hardened IEC software gateway (StreamBridge) SCADA System specific for power applications (StreamView, StreamBrain) Centralized data management and integrated engineering tools for all components except IEDs (StreamTools) Integrated IEC System Configuration Tool (StreamDesign). StreamX has been developed and is maintained by Infoteam SA (Switzerland). IEC provides a very important contribution with the System Configuration Language (SCL) which allows the exchange of (engineering) data between tools and devices from different vendors. By including a third party IEC System Configuration Tool StreamX allows a seamless integration of IEC with the gateway and HMI engineering. The third party System Configuration tool is provided by HELINKS LLC. (Switzerland). 9

10 Figure 9: Tools and Products Figure 10 illustrates the work with the System Configuration Tool. In the center we see the Single Line of a bay template. It is used to create the substation and add the End to End Data to the system. The lower part shows the IEC Network and IEDs and the right part indicates the export files. All related engineering data and files are centrally stored and submitted to version control. 7. Conclusion Figure 10 Illustration of System Configuration Tool Tools and processes as described are currently used by Romande Energie. They have realized the expected cost reduction for new substations based on reduced wiring costs and improved engineering processes. Key factors for the increased engineering efficiency are: The use of standardized End to End Engineering Templates. 10

11 Seamless tool integration Usage of the End to End Templates guaranties a harmonized design. Similar substations result in similar automation solutions. The central data management and central versioning ensure availability and correctness of the engineering data. These are key factors to efficient maintenance and easy extensibility of the substation automation systems. However, there are open points remaining which still represent challenges: A better integration of HW design, network design and IED wiring. IED Software life cycle management. Load and update status of IED configurations and firmware. Release management for IED Tools. Integration of test activities (test planning, test execution, test documentation) 8. Outlook Intended future activities are: Improvement of the IED qualification process in terms of acceptance criteria and qualification test procedures. Including IEC ED2 in the End to End Engineering Templates. Definition of new test procedures for projects and implementing them in the test processes. 11

Engineering Approach for the End User in IEC applications

Engineering Approach for the End User in IEC applications 21, rue d Artois, F-75008 PARIS D2/B5-115 CIGRE 2010 http : //www.cigre.org Engineering Approach for the End User in IEC 61850 applications N. NIBBIO M. GENIER C. BRUNNER Romande Energie SA SIG UTInnovation

More information

Substation Configuration Language. Summary August 2006

Substation Configuration Language. Summary August 2006 Substation Configuration Language Summary August 2006 CONFIGURATION SCL Format Defined in IEC 61850 Part 6 Four different file types System Specification Description (SSD) power system functions Substation

More information

Experiences with conformance test procedures for IEC Edition 2 System and IED configuration tools

Experiences with conformance test procedures for IEC Edition 2 System and IED configuration tools Experiences with conformance test procedures for IEC 61850 Edition 2 System and IED configuration tools Peter KREUTZER, ABB Switzerland Ltd, Switzerland Bas MULDER, DNV GL, The Netherlands Stephan GERSPACH,

More information

IEC Engineering Process and Multi-Vendor System Configuration Tools Reduce Engineering Costs of Substation Automation Projects

IEC Engineering Process and Multi-Vendor System Configuration Tools Reduce Engineering Costs of Substation Automation Projects IEC 61850 Engineering Process and Multi-Vendor System Configuration Tools Reduce Engineering Costs of Substation Automation Projects Adam Gauci, P.Eng. Schneider Electric North America Summary Abstract...

More information

IEC Test Equipment Requirements

IEC Test Equipment Requirements OMICRON K02 03 20060309 IEC 61850 Test Equipment Requirements Dr. Alexander Apostolov K02 03 20060309 Page: 1 Intelligent Substation Automation Systems OMICRON K02 03 20060309 Page: 2 Intelligent Sensor

More information

COMMUNICATION NETWORKS. FOX615/612 TEGO1 IEC GOOSE Proxy Gateway interface module.

COMMUNICATION NETWORKS. FOX615/612 TEGO1 IEC GOOSE Proxy Gateway interface module. COMMUNICATION NETWORKS FOX615/612 TEGO1 IEC 61850 GOOSE Proxy Gateway interface module. 2 FOX615/612 TEGO1 IEC 61850 GOOSE GATEWAY INTERFACE MODULE INTRODUCTION 3 FOX615/612 multiplexing platform. Enabling

More information

InFusion SOFTWARE Product Specifications

InFusion SOFTWARE Product Specifications InFusion SOFTWARE Product Specifications Substation Automation Configuration for ArchestrA IDE BACKGROUND The IEC 61850 standard for communications in substations allows the development of multifunctional

More information

SCL Manager An Engineering & Configuration tool based on IEC

SCL Manager An Engineering & Configuration tool based on IEC 6000 SCL Manager An Engineering & Configuration tool based on IEC61850 www.kalkitech.com About Kalkitech Kalki Communication Technologies Limited (Kalkitech) is a technology based company founded in 1998,

More information

Trends, Lessons and Benchmarks

Trends, Lessons and Benchmarks Trends, Lessons and Benchmarks Dr. Alexander Apostolov Disclaimer: The person making this presentation is not responsible for what he says because he has no clue what he is talking about Questions What

More information

IEC standard update

IEC standard update IEC 61850 standard update Christoph Brunner, Switzerland IEC 61850 Europe Conference Amsterdam September 27 28, 2017 Content IEC 61850 parts beyond Ed 1 scope Ongoing work related to IEC 61850 Improving

More information

IEC SCL - MORE THAN INTEROPERABLE DATA EXCHANGE BETWEEN ENGINEERING TOOLS

IEC SCL - MORE THAN INTEROPERABLE DATA EXCHANGE BETWEEN ENGINEERING TOOLS IEC 61850 SCL - MORE THAN INTEROPERABLE DATA EXCHANGE BETWEEN ENGINEERING TOOLS Wolfgang Wimmer ABB Baden, Switzerland wolfgang.wimmer@ch.abb.com Abstract The IEC 61850 SCL language for Substation Configuration

More information

Efficient Secondary System Configuration Process Utilizing Centralized Substation Functions

Efficient Secondary System Configuration Process Utilizing Centralized Substation Functions Efficient Secondary System Configuration Process Utilizing Centralized Substation Functions Jani Valtari ABB Oy Distribution Automation, Pekka Verho Tampere University of Technology Country: Finland E-mail

More information

Integrating IEC & IEEE 1815 (DNP3)

Integrating IEC & IEEE 1815 (DNP3) Integrating IEC 61850 & IEEE 1815 (DNP3) Andrew West Regional Technical Director, SUBNET Solutions, Inc. SUMMARY North America has a mature electric power grid. The majority of grid automation changes

More information

Overview and Application

Overview and Application IEC 61850 Overview and Application Who am I? Rich Hunt Market Development Leader GE Grid Solutions Over 25 years in the power systems industry At GE for 10 years (almost) Member of IEEE PSRC, U.S. Representative

More information

SIPROTEC 5 V7.8 Protection, automation and monitoring for digital substations

SIPROTEC 5 V7.8 Protection, automation and monitoring for digital substations SIPROTEC 5 V7.8 Protection, automation and monitoring for digital substations siemens.com/siprotec5 SIPROTEC 5 Table of content Introduction New functions of V7.8 SIPROTEC 5 - the core of Digital Substation

More information

ENTSO-E IST Evaluation of export capabilities

ENTSO-E IST Evaluation of export capabilities it4power LLC, Chollerstrasse 3, 6300 Zug, Switzerland Phone: +41 41 712 1984 Fax: +41 41 712 1983 info@it4power.com ENTSO-E IST Evaluation of export capabilities Author Christoph Brunner Released [Name,

More information

Substation Automation based on IEC Claes Rytoft ABB Power Systems

Substation Automation based on IEC Claes Rytoft ABB Power Systems Substation Automation based on IEC 61850 Claes Rytoft ABB Power Systems BayNetworks Development of SA SA conventional MMI / Control Board NCC SA with interbay bus NCC SA with interbay & process bus NCC

More information

Lecture 6 Substation Automation Systems

Lecture 6 Substation Automation Systems Lecture 6 Substation Automation Systems 1 Course map 2 Contents of the Lecture Part 1 Substation Automation Components & Architectures Substation Automation Functions Communication within the Substation

More information

Experience with IEC based Systems

Experience with IEC based Systems Klaus-Peter Brand April 2006 Experience with IEC 61850 based Systems ABB - 1 - IEC61850 Experience Content IEC 61850 Experience with Systems ABB University Switzerland - 2 - First experiences Experience

More information

Pushing the limits. ABB product development based on the IEC standard

Pushing the limits. ABB product development based on the IEC standard Pushing the limits ABB product development based on the IEC 61850 standard JANNE STARCK, STEVEN A. KUNSMAN Since the publication of the first edition in 2004, the IEC 61850 communication standard has practically

More information

COLLABORATE TO WIN. 03/31/2017 Digital Substation Turning IEC61850 features into benefits. Peter Rietmann, Program Manager Digital Substation NA

COLLABORATE TO WIN. 03/31/2017 Digital Substation Turning IEC61850 features into benefits. Peter Rietmann, Program Manager Digital Substation NA COLLABORATE TO WIN 03/31/2017 Digital Substation Turning IEC61850 features into benefits Peter Rietmann, Program Manager Digital Substation NA Increasing Reliability Higher functional integration and process

More information

RULES DRIVEN PROJECT SPECIFICATION IN THE CONTEXT OF IEC BASIC APPLICATION PROFILES

RULES DRIVEN PROJECT SPECIFICATION IN THE CONTEXT OF IEC BASIC APPLICATION PROFILES RULES DRIVEN PROJECT SPECIFICATION IN THE CONTEXT OF IEC 61850 BASIC APPLICATION PROFILES Camille BLOCH Mayank SHARMA Michael HAECKER Schneider Electric - France Schneider Electric - India Schneider Electric

More information

How smart can the grid really be?

How smart can the grid really be? How smart can the grid really be? by Dale Pudney, HVT Power Systems and Luo Wei, NR Electric With the improvement of electronic communications and computing technology, it becomes possible to integrate

More information

/ Charlie Hsu, Sales, PSAC, Power System Division, TWABB, June.2013 IEC The Approach and the Standard. ABB Group July 1, 2013 Slide 1

/ Charlie Hsu, Sales, PSAC, Power System Division, TWABB, June.2013 IEC The Approach and the Standard. ABB Group July 1, 2013 Slide 1 / Charlie Hsu, Sales, PSAC, Power System Division, TWABB, June.2013 IEC 61850 The Approach and the Standard July 1, 2013 Slide 1 Agenda Introduction & revolution The key issues for IEC 61850 Logical Nodes

More information

EP A1 (19) (11) EP A1 (12) EUROPEAN PATENT APPLICATION. (43) Date of publication: Bulletin 2008/40

EP A1 (19) (11) EP A1 (12) EUROPEAN PATENT APPLICATION. (43) Date of publication: Bulletin 2008/40 (19) (12) EUROPEAN PATENT APPLICATION (11) EP 1 976 218 A1 (43) Date of publication: 01..2008 Bulletin 2008/40 (21) Application number: 07374.8 (1) Int Cl.: H04L 29/06 (2006.01) H02J 13/00 (2006.01) G06F

More information

Designing a new IEC substation architecture

Designing a new IEC substation architecture Designing a new IEC 61850 substation architecture Gerrit Dogger Senior Product and Application Specialist Cooper Power Systems gerrit.dogger@cybectec.com Garry Tennese Station Integration Specialist Manitoba

More information

Connected Grid Design Suite-Substation Workbench Release 1.0: Frequently Asked Questions (FAQ)

Connected Grid Design Suite-Substation Workbench Release 1.0: Frequently Asked Questions (FAQ) Connected Grid Design Suite-Substation Workbench Release 1.0: Frequently Asked Questions (FAQ) Revised June 12, 2013 Online Part Number: Cisco Systems, Inc. www.cisco.com Questions: Questions: Introduction

More information

SPECIFICATIONS FOR SCL(SUBSTATION CONFIGURATION LANGUAGE) MANAGER WITH HYDRO DATA MODELS A. GENERAL SPECIFICATIONS

SPECIFICATIONS FOR SCL(SUBSTATION CONFIGURATION LANGUAGE) MANAGER WITH HYDRO DATA MODELS A. GENERAL SPECIFICATIONS A. GENERAL SPECIFICATIONS A.1 General Conformance: The SCL (Substation Configuration Language) Manager configuration utility tool provided by the vender for configuring an IED( Intelligent Electronic Device)

More information

B. Project life cycle II. SPECIFICATIONS A. Specification of functionality

B. Project life cycle II. SPECIFICATIONS A. Specification of functionality 2 Being a comprehensive standard, IEC 61850 also covers design aspects, protocol requirements, testing guidelines, etc. In order to exploit its full benefits in any specific case, its application requires

More information

IMPACT OF IEC ON SYSTEM ENGINEERING, TOOLS, PEOPLE- WARE, AND THE ROLE OF THE SYSTEM INTEGRATOR

IMPACT OF IEC ON SYSTEM ENGINEERING, TOOLS, PEOPLE- WARE, AND THE ROLE OF THE SYSTEM INTEGRATOR IMPACT OF IEC 61850 ON SYSTEM ENGINEERING, TOOLS, PEOPLE- WARE, AND THE ROLE OF THE SYSTEM INTEGRATOR Karlheinz Schwarz, SCC schwarz@scc-online.de 1 Introduction The crucial focus of IEC 61850 is the provision

More information

Copyright 2017 SUBNET Solutions Inc.

Copyright 2017 SUBNET Solutions Inc. Unified Configuration & Documentation Applying a unified configuration and documentation approach to the engineering and operation of multi-vendor multi-edition IEC 61850 systems SUBNET Solution Inc. Overview

More information

Nicolás Vidal, CLABB System Data Manager SDM600. See the unseen from a new perspective

Nicolás Vidal, CLABB System Data Manager SDM600. See the unseen from a new perspective Nicolás Vidal, CLABB System Data Manager SDM600 See the unseen from a new perspective See the unseen from a new perspective A comprehensive software solution for automatic management of service and cyber

More information

IEC meets Industrial IT

IEC meets Industrial IT IEC 61850 meets Industrial IT Lars Andersson, Klaus-Peter Brand, Petra Reinhardt The international electrical engineering community is continuously creating new global standards. These are not only important

More information

THE MODELING APPROACH OF IEC

THE MODELING APPROACH OF IEC Modeling interoperable protection and control devices for substation automation according to IEC 61850 Klaus-Peter Brand 1, Wolfgang Wimmer 2 Switzerland Summary The standard IEC 61850 Communication Networks

More information

User Manual.

User Manual. User Manual www.gridsoftware.com Table of Contents SCL Matrix Overview...4 1. Startup Screen...5 2. Ribbon...7 2.1. Home...8 2.2. Engineering Process...9 2.3. Add...10 2.4. Import/Export...11 3. Projects...12

More information

The Impact of the coming Standard IEC61850 on the Life-cycle of Open Communication Systems in Substations

The Impact of the coming Standard IEC61850 on the Life-cycle of Open Communication Systems in Substations The Impact of the coming Standard IEC61850 on the Life-cycle of Open Communication Systems in Substations Lars Andersson, Klaus-Peter Brand, Wolfgang Wimmer ABB Power Automation Ltd, Switzerland Abstract

More information

A Collation & Analysis Methodology for Substation Event Data via a Web Interface (supporting COMTRADE, GOOSE & MMS Data Sources from Multiple Vendors)

A Collation & Analysis Methodology for Substation Event Data via a Web Interface (supporting COMTRADE, GOOSE & MMS Data Sources from Multiple Vendors) 1 A Collation & Analysis Methodology for Substation Event Data via a Web Interface (supporting COMTRADE, GOOSE & MMS Data Sources from Multiple Vendors) Abstract Author: Bruce Mackay Email Address: bruce.mackay@concogrp.com

More information

IEC61850 TaskForce - Punch List*

IEC61850 TaskForce - Punch List* ISSUE N Category Description Edition Chapter Kind? WG10 comments WG10 action plan 1 Tool interoperability Free interpretation of the SCL file structure makes exchanges of files almost impossible without

More information

Jim McGhee, Utility Market Manager, RuggedCom Inc.

Jim McGhee, Utility Market Manager, RuggedCom Inc. First Practical Experience with IEEE 1588 High Precision Time Synchronization in High Voltage Substation with IEC 61850 Process Bus Jim McGhee, Utility Market Manager, RuggedCom Inc. (JimMcGhee@RuggedCom.com)

More information

EXPERIENCE WITH IEC IN THE REFURBISHMENT OF AN IMPORTANT EUROPEAN 380 KV SUBSTATION. Switzerland

EXPERIENCE WITH IEC IN THE REFURBISHMENT OF AN IMPORTANT EUROPEAN 380 KV SUBSTATION. Switzerland 21, rue d Artois, F-75008 PARIS B5-109 CIGRE 2006 http : //www.cigre.org EXPERIENCE WITH IEC 61850 IN THE REFURBISHMENT OF AN IMPORTANT EUROPEAN 380 KV SUBSTATION S. LAEDERACH* 1, W. BAASS 2, K.P. BRAND

More information

ClearView SCADA Benefits

ClearView SCADA Benefits ReLab Software s ClearView SCADA is a true out-of-the-box solution with all the components necessary for deployment in substation automation and control room applications. ClearView is built for the time

More information

Standards Are Not Enough! Challenges of Interoperability. A. ESHPETER SUBNET Solutions Inc. Canada

Standards Are Not Enough! Challenges of Interoperability. A. ESHPETER SUBNET Solutions Inc. Canada 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Standards Are Not Enough! Challenges of 61850 Interoperability A. ESHPETER SUBNET Solutions

More information

Impact of IEC communication protocol on substation automation systems

Impact of IEC communication protocol on substation automation systems International Journal of Research in Advanced Engineering and Technology ISSN: 2455-0876; Impact Factor: RJIF 5.44 www.engineeringresearchjournal.com Volume 2; Issue 5; September 2016; Page No. 49-53 Impact

More information

POWER GRIDS. We are bridging the gap. Enabling Digital Substations.

POWER GRIDS. We are bridging the gap. Enabling Digital Substations. POWER GRIDS We are bridging the gap. Enabling Digital s. 2 A B B D i g i ta l S u b s tat i o n s ABB s Digital provides customers in the utility sector with unmatched control and efficiency. The digital

More information

Structured Design of Substations Automation Systems according to IEC 61850

Structured Design of Substations Automation Systems according to IEC 61850 Structured Design of Substations Automation Systems according to IEC 61850 Pedro F. M. Dias Instituto Superior Técnico, Lisbon, Portugal J.L. Pinto de Sá Abstract - This work deals with the development

More information

RELEASE NOTE. Integrated Engineering Tool IET600 Ver. 5.3 Feature Pack 4

RELEASE NOTE. Integrated Engineering Tool IET600 Ver. 5.3 Feature Pack 4 RELEASE NOTE Integrated Engineering Tool IET600 Ver. 5.3 Feature Pack 4 2 IET600 VER. 5.3 FP4 RELEASE NOTE IET600 Ver. 5.3 FP4 Release Note Dear Reader, We are pleased to announce the release of IET600

More information

Global Synchronized Phasor Measurement Standards

Global Synchronized Phasor Measurement Standards Global Synchronized Phasor Measurement Standards Vahid Madani and Farnoosh Rahmatian March 30, 2011 i-pcgrid Workshop 2011 Phasor Measurement System GPS Timing standards IEEE 1588 PTP C37.238 Profile Communication

More information

ADVANCED SIMULATION OF IEDS. Thomas Schossig. OMICRON electronics GmbH, Klaus, Austria; TESTING

ADVANCED SIMULATION OF IEDS. Thomas Schossig. OMICRON electronics GmbH, Klaus, Austria; TESTING ADVANCED SIMULATION OF IEDS Thomas Schossig OMICRON electronics GmbH, Klaus, Austria; thomas.schossig@omicronenergy.com ABSTRACT IEC 61850 is the established standard for substation communication. Since

More information

C I R E D 22 nd International Conference on Electricity Distribution Stockholm, June 2013

C I R E D 22 nd International Conference on Electricity Distribution Stockholm, June 2013 C I R E D 22 nd International Conference on Electricity Distribution Stockholm, 0-3 June 203 Paper 399 PROTECTION OPERATION ANALYSIS IN SMART GRIDS Alexander Apostolov OMICRON electronics - USA alex.apostolov@omicronusa.com

More information

////// SUBSTATIONS. Control command and local Scada

////// SUBSTATIONS. Control command and local Scada ////// SUBSTATIONS Control command and local GENERAL INFORMATION The solution provided by Sécheron for local control and monitoring of traction substations is a significant step in supporting operations

More information

Development of an Intelligent Station HMI in IEC Based Substation

Development of an Intelligent Station HMI in IEC Based Substation Journal of Electrical Engineering & Technology, Vol. 4, No.1, pp. 13~18, 2009 13 Development of an Intelligent Station HMI in IEC 61850 Based Substation Seong-Jeong Rim, Sheng-Wu Zeng* and Seung-Jae Lee**

More information

Communication in Substations with IEC Simple Communication Test with IEC Johannes Bruss, Siemens AG, E D EA PRO LM Siemens AG 2008

Communication in Substations with IEC Simple Communication Test with IEC Johannes Bruss, Siemens AG, E D EA PRO LM Siemens AG 2008 Communication in Substations with IEC 61850 Simple Communication Test with IEC61850 Johannes Bruss, Siemens AG, E D EA PRO LM As a first example, it has to be checked in a simple way that the communication

More information

Grid Automation Controller COM600 How it fits into the Smart Grid?

Grid Automation Controller COM600 How it fits into the Smart Grid? ABB Oy Distribution Automation Grid Automation Controller How it fits into the Smart Grid? May 27, 2014 Slide 1 1MRS756763 E Content Technical Presentation May 27, 2014 Slide 2 Description Grid Automation

More information

Application and Research of Integrated Model Between Substation and Dispatch Center

Application and Research of Integrated Model Between Substation and Dispatch Center International Conference on Energy, Power and Electrical Engineering (EPEE 2016) Application and Research of Integrated Model Between Substation and Dispatch Center Ning Jiang1, Lin Li1, Ning Kang1, Guodong

More information

PSSS/PSAC Engineering, Muhammad Adil, Substation Automation Systems. ABB Group October 29, 2014 Slide 1

PSSS/PSAC Engineering, Muhammad Adil, Substation Automation Systems. ABB Group October 29, 2014 Slide 1 PSSS/PSAC Engineering, Muhammad Adil, 30-10-2014 Substation Automation Systems October 29, 2014 Slide 1 CONTENT INTRODUCTION IEC61850 ABB s BAY LEVEL SOLUTIONS ABB s STATION LEVEL SOLUTIONS ABB s AS A

More information

RELEASE NOTE. Integrated Engineering Tool IET600 Ver. 5.3 Feature Pack 3

RELEASE NOTE. Integrated Engineering Tool IET600 Ver. 5.3 Feature Pack 3 RELEASE NOTE Integrated Engineering Tool IET600 Ver. 5.3 Feature Pack 3 2 IET600 VER. 5.3 FP3 RELEASE NOTE IET600 Ver. 5.3 FP3 Release Note Dear Reader, We are pleased to announce the release of IET600

More information

Digital Substation Unrestricted Siemens AG 2017 siemens.com/digital-substation

Digital Substation Unrestricted Siemens AG 2017 siemens.com/digital-substation Digital Substation A Substation Why Should We Make It Digital? Adopt new business models Time to operation Quality assurance Business agility Avoid outages Investment security Ensuring grid availability

More information

OfprintofarticleinPACWorld,Spring2008

OfprintofarticleinPACWorld,Spring2008 OfprintofarticleinPACWorld,Spring2008 47 identification has non standardized parts. The logical device name as a manufacturer / organisation related structuring is completely free within some syntactical

More information

IEDScout. Versatile software tool for working with IEC devices

IEDScout. Versatile software tool for working with IEC devices IEDScout Versatile software tool for working with IEC 61850 devices One software tool for working with all IEC 61850 IEDs Examine IEC 61850 devices IEDScout is an ideal tool for protection and substation

More information

ABB Automation & Power World: April 18-21, 2011 IEC connectivity, networking and state-of-the-art Relion protection/control technologies

ABB Automation & Power World: April 18-21, 2011 IEC connectivity, networking and state-of-the-art Relion protection/control technologies ABB Automation & Power World: April 18-21, 2011 IEC 61850 connectivity, networking and state-of-the-art Relion protection/control technologies ABB Inc. April 20, 2011 Slide 1 Overview IEC61850 Basics What

More information

Lecture 5 Substation Automation Systems. Course map

Lecture 5 Substation Automation Systems. Course map Lecture 5 Substation Automation Systems 1 Course map 2 1 Contents of the Lecture Part 1 Substation Automation Components Substation Automation Functions Communication within the Substation (Intro) Part

More information

Abstract. Randy Kimura GE Digital Energy

Abstract. Randy Kimura GE Digital Energy Substation Automation Hybrid Randy Kimura GE Digital Energy Abstract IEC 61850 is revolutionizing the integration of protection and control through the introduction of new concepts and technologies. Deploying

More information

Eandis IEC61850 Next steps. 27 September 2017

Eandis IEC61850 Next steps. 27 September 2017 Eandis IEC61850 Next steps Eandis in the Energy market Regulator CREG / VREG Producers Electricity Import Natural Gas Elia Distribution Grid Operator Fluxys Suppliers Customers 2 HS Eandis Network: TS

More information

System Engineer Configures IEC Gateway to DNP3 Substation

System Engineer Configures IEC Gateway to DNP3 Substation 1 Description of Function 1.1 Function Name System Configures to DNP3 System Configures to DNP3 1.2 Function ID DNP3-IEC6850-2 1.3 Brief Description Given DNP-XML Device Profiles for a substation automation

More information

Response to the. ESMA Consultation Paper:

Response to the. ESMA Consultation Paper: Response to the ESMA Consultation Paper: Draft technical standards on access to data and aggregation and comparison of data across TR under Article 81 of EMIR Delivered to ESMA by Tahoe Blue Ltd January

More information

Leverage substation gateway hardware to host a substation HMI and reduce costs

Leverage substation gateway hardware to host a substation HMI and reduce costs White Paper WP912003EN New Issue COOPER POWER SERIES Leverage substation gateway hardware to host a substation HMI and reduce costs Traditional substation human-machine interfaces (HMIs) are primarily

More information

Applications and Industry Activities

Applications and Industry Activities Applications and Industry Activities Christoph Brunner Switzerland The Contents of IEC 61850, Edition 1 System Aspects Part 1: Introduction and Overview Part 2: Glossary Part 3: General Requirements Part

More information

CASE STUDY. Wind Farm in Mexico Completes First Successful IEC Application With Multivendor Interoperability

CASE STUDY. Wind Farm in Mexico Completes First Successful IEC Application With Multivendor Interoperability CASE STUDY La Venta II Wind Farm Oaxaca, Mexico Wind Farm in Mexico Completes First Successful IEC 61850 Application With Multivendor Interoperability Comisión Federal de Electricidad (CFE) is Mexico s

More information

Hugo E. Meier, Heidelberg, Germany, June 2014 Integrator Partner Seminar2014 Substation automation trends

Hugo E. Meier, Heidelberg, Germany, June 2014 Integrator Partner Seminar2014 Substation automation trends Hugo E. Meier, Heidelberg, Germany, June 2014 Integrator Partner Seminar2014 Substation automation trends Substation automation trends Contents Product Portfolio Trends in substation automation Cyber Security

More information

AMA ServerSim-G Server-Simulator for IEC Data Sheet

AMA ServerSim-G Server-Simulator for IEC Data Sheet Server-Simulator for IEC 61850 Data Sheet November 2013 1 Introduction The AMA-61850-ServerSim-G offers you the capability to test client type systems, like RTUs, substation HMI or SCADA systems, using

More information

SDG&E s EPIC Demonstration Projects on Emerging Communication Standards. IEC Europe 2017 Conference. Frank Goodman, SDG&E EPIC Program Manager

SDG&E s EPIC Demonstration Projects on Emerging Communication Standards. IEC Europe 2017 Conference. Frank Goodman, SDG&E EPIC Program Manager SDG&E s EPIC Demonstration Projects on Emerging Communication Standards Frank Goodman, SDG&E EPIC Program Manager IEC 61850 Europe 2017 Conference September 26-28, 2017 2017 San Diego Gas & Electric Company.

More information

Substation automation products. MicroSCADA Pro for substation automation

Substation automation products. MicroSCADA Pro for substation automation Substation automation products for substation automation Perfect control anywhere, anytime is an investment for today and tomorrow. Start, for instance, with monitoring or gateway functionality and integrate

More information

ROCON RPC 116. SUBSTATION AUTOMATION Central unit for substation automation

ROCON RPC 116. SUBSTATION AUTOMATION Central unit for substation automation RPC 116 Central unit for substation automation RPC 116 offers an overall concept for substation system automation at Bay Level, Station Level and Control Center Level. RPC 116 is an embedded unit, which

More information

I E C E N G I N E E R I N G P R O C E S S I N O F F S H O R E W I N D F A R M S

I E C E N G I N E E R I N G P R O C E S S I N O F F S H O R E W I N D F A R M S IEC 61850 ENGINEERING PROCESS IN OFFSHORE WIND FARMS Saeed Nemati 27 September 2017 IEC 61850 2 IEC 61850 in Offshore Wind Farms About Dong Energy Main Business Units Bioenergy & Thermal Power Distribution

More information

Mapping the Substation Configuration Language of IEC to ArchiMate

Mapping the Substation Configuration Language of IEC to ArchiMate Mapping the Substation Configuration Language of IEC 61850 to ArchiMate Johan König, Kun Zhu, Lars Nordström, Mathias Ekstedt, Robert Lagerström Industrial Information and Control Systems, Royal Institute

More information

Smart Commissioning. White Paper January 2019

Smart Commissioning. White Paper January 2019 is a technology-enabled approach for streamlining the commissioning of field instrumentation connected to a DeltaV Distributed Control System (DCS) or Safety Instrumented System (SIS). It reduces the effort

More information

ABB Group April 19, 2011 Slide 1

ABB Group April 19, 2011 Slide 1 Alejandro Schnakofsky, NAM Applications and Tech Support Manager Simplifying substation control engineering by using an IEC 61850 based Relion solution April 19, 2011 Slide 1 Overview IEC61850 Basics What

More information

Program. 5 Day IEC Seminar and Training. XXXX Automation & Information Systems XXXX

Program. 5 Day IEC Seminar and Training. XXXX Automation & Information Systems XXXX , 2010 Program 5 Day IEC 61850 Seminar and Training XXXX Automation & Information Systems XXXX 18.-22.01.2010 Notes: 1. Questions and discussions during and after each presentation are expected and welcome.

More information

Experience with a Digital Substation Pilot in North Ame rica

Experience with a Digital Substation Pilot in North Ame rica Experience with a Digital Substation Pilot in North Ame rica Wojciech Szela, Edward Gdowik PECO Harsh Vardhan, R. Ramlachan GE Grid Solutions 2018 Texas A&M Protective Relaying Conference IEC MDS 61850

More information

Grid Automation Products. MicroSCADA Pro Substation automation applications.

Grid Automation Products. MicroSCADA Pro Substation automation applications. Grid Automation Products Substation automation applications. 2 Substation automation applications Automate, control and optimize your operations. is an investment for today and tomorrow. Start, for instance,

More information

IEC61850 Maintenance approach. 2017, September the 27 th

IEC61850 Maintenance approach. 2017, September the 27 th IEC61850 Maintenance approach 2017, September the 27 th Javier Figuera Pozuelo (Madrid, 1976) has been working in the Spanish TSO (Red Eléctrica de España) since 2.001. First, as a Protection and Control

More information

Digitizing copper Defining key elements to ensure a successful integration from concept to maintenance

Digitizing copper Defining key elements to ensure a successful integration from concept to maintenance Alejandro Schnakofsky, ABB Inc. Digitizing copper Defining key elements to ensure a successful integration from concept to maintenance Abstract in this paper, IEC61850 GOOSE message is presented as a vehicle

More information

ECE Supervisory Control & Critical Infrastructure Systems IEC Presented by Jake Groat Slides by Rick Liposchak, P.E.

ECE Supervisory Control & Critical Infrastructure Systems IEC Presented by Jake Groat Slides by Rick Liposchak, P.E. ECE444-544 Supervisory Control & Critical Infrastructure Systems IEC 61850 Presented by Jake Groat Slides by Rick Liposchak, P.E. 17 April 2018 What will we cover? Lecture 1- IEC 61850 Why IEC 61850? What

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 6850-6 First edition 2004-03 Communication networks and systems in substations Part 6: Configuration description language for communication in electrical substations related

More information

MicroSCADA Pro Substation automation applications.

MicroSCADA Pro Substation automation applications. G R I D AUTO M ATI O N PRO D U C T S Substation automation applications. ABB Oy Finland Power Grids Grid Automation P.O. Box 614 FI-65101 Vaasa, Finland Phone: +358 10 22 21999 (Customer Support Center)

More information

What are the issues and challenges during testing (focus on maintenance testing)

What are the issues and challenges during testing (focus on maintenance testing) Secure and Efficient Testing of IEC 61850-Based Protection and Control Systems Agenda What are the issues and challenges during testing (focus on maintenance testing) Requirements for testing IEC 61850-based

More information

IEC conference Amsterdam 2017

IEC conference Amsterdam 2017 IEC 61850 conference Amsterdam 2017 Substation to Control Centre (and more) Bas Mulder Consultant, DNV GL René Troost Grid Strategist, Stedin 1 Stedin and IEC 61850 Stedin adopted IEC 61850 in 2007 as

More information

DIGITAL SUBSTATION IEC ENTSO-E ACTION PLAN TO IMPROVE IEC DATA MODELS AND ENGINEERING PROCESS

DIGITAL SUBSTATION IEC ENTSO-E ACTION PLAN TO IMPROVE IEC DATA MODELS AND ENGINEERING PROCESS ENTSO-E ACTION PLAN TO IMPROVE IEC 61850 DATA MODELS AND ENGINEERING PROCESS DIGITAL SUBSTATION IEC 61850 Moscow, The Russian Federation, 3. October 2017 INTRODUCTION ENTSO-E at a glance Page 3 ENTSO-E

More information

IEEE 1588v2 Time Synchronization in Energy Automation Applications Case Studies from China

IEEE 1588v2 Time Synchronization in Energy Automation Applications Case Studies from China IEEE 1588v2 Time Synchronization in Energy Automation Applications Case Studies from China Real Time Communications Symposium Munich, January 2012 Maciej Goraj maciejgoraj@ruggedcom.com 1 Who is RuggedCom?

More information

Standard profiles key to high interoperability

Standard profiles key to high interoperability Standard profiles key to high interoperability Heiko Englert, Siemens AG, Germany Patrick Lhuillier, RTE, France #GridInterop Theses to be verified Achieving Interoperability is a matter of effort There

More information

OrionLX. An Overview of the OrionLX Product Line

OrionLX. An Overview of the OrionLX Product Line OrionLX TM An Overview of the OrionLX Product Line The Best Substation Automation Platform Out There Is in Here The OrionLX Family of Substation Automation Platforms perform an expanding array of automation

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD 61850-7-1 First edition 2003-07 Communication networks and systems in substations Part 7-1: Basic communication structure for substation and feeder equipment Principles and models

More information

Synchrophasor Standards and Guides

Synchrophasor Standards and Guides Synchrophasor Standards and Guides PSTT and IEEE PSRC Vahid Madani, Ken Martin, and Damir Novosel NASPI General Meeting February 23, 2011 Ft. Worth, TX Presentation Standards & guides related to synchrophasors

More information

An Insight into IEC Protocol mplementation with ERLPhase new generation Devices

An Insight into IEC Protocol mplementation with ERLPhase new generation Devices An Insight into IEC 61850 Protocol mplementation with ERLPhase new generation Devices IEEE Winnipeg January 25, 2011 Dr. Krish Narendra, PhD VP Technology and Quality ERLPhase Power Technologies Ltd. All

More information

Smart Commissioning. White Paper February 2018

Smart Commissioning. White Paper February 2018 Smart Commissioning Smart Commissioning is a technology-enabled approach for streamlining the commissioning of field instrumentation connected to a DeltaV Distributed Control System (DCS) or Safety Instrumented

More information

ProField-GW Description

ProField-GW Description ProField-GW Description 1/28 ProField-GW Description Version: 200/2012.11.20 Edited: Donka Zoltán, Attila Székely 2011 Budakalász Szentendrei u 1-3. Web: www.prolan-power.hu All rights reserved. Copyright

More information

IEC 61850: From Paper to Operation

IEC 61850: From Paper to Operation IEC 61850: From Paper to Operation Dr. Alexander Apostolov AREVA T&D Automation XVIII SNPTEE Curitiba, Brazil, 19 October 2005 Introduction IEC 61850 is now an approved international standard It allows

More information

IEC Edition 2. From substation automation to power utility automation

IEC Edition 2. From substation automation to power utility automation IEC 61850 Edition 2 From substation automation to power utility automation KLAUS-PETER BRAND, WOLFGANG WIMMER The final part of IEC 61850 Edition 1 Communication Networks and Systems in Substation Automation

More information

Challenges and Solutions for GOOSE Traffic Monitoring

Challenges and Solutions for GOOSE Traffic Monitoring Transforming the world of energy using open standards Ralph Mackiewicz SISCO, Inc. 6605 19½ Mile Road Sterling Heights, MI 48314-1408 USA Tel: +1-586-254-0020 x103 Fax: +1-586-254-0053 Mob: +1-586-260-2571

More information

Amsterdam 27 September 2017 David MacDonald

Amsterdam 27 September 2017 David MacDonald Operations & Maintenance facilitating condition based and predictive maintenance to support cost-efficient operation and maximum life-cycle of next generation IEC 61850 systems Amsterdam 27 September 2017

More information