Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility

Size: px
Start display at page:

Download "Small Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility"

Transcription

1 Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010

2 TABLE OF CONTENTS 1.0 DESCRIPTION OF THE PROJECT SCOPE AND OBJECTIVE OF THE STUDY FACILITIES ANALYSIS ASSUMPTIONS POINT OF INTERCONNECTION SCOPE OF WORK INTERCONNECTION CUSTOMER S COLLECTOR SUBSTATION INTERCONNECTION DISTRIBUTION CIRCUIT POINT OF INTERCONNECTION SUBSTATION COMMUNICATION SPECIFICATIONS [PAST THE POINT OF INTERCONNECTION] COST ESTIMATE SCHEDULE PARTICIPATION BY AFFECTED SYSTEMS APPENDICES SGIQ0314 Page 2 December 29, 2010

3 1.0 DESCRIPTION OF THE PROJECT ( Interconnection Customer ) has proposed the interconnection of 20 MW of new solar generation to PacifiCorp s ( Distribution Provider ) 34.5-kV transmission system located in Iron County, Utah. The solar project will consist of twenty (40) 500 kw photovoltaic panels for a total output of 20 MW. The panels will grouped into to strings and will be bundled into groups of 4 panels per 480V to 34.5-kV step-up transformer. The requested commercial operation date has been moved to the fourth quarter of 2011, or by December 31, Interconnection Customer will operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Distribution Provider has assigned the project Q SCOPE AND OBJECTIVE OF THE STUDY The objective of the Facilities Study is to: Specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study(s). Identify: (1) The electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters, and other station equipment. (2) The nature and estimated cost of the Transmission Provider s Interconnection Facilities and Upgrades necessary to accomplish the interconnection. (3) An estimate of the time required to complete the construction and installation of such facilities. 3.0 FACILITIES ANALYSIS ASSUMPTIONS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change. For study purposes there are two separate queues: o Transmission Service Queue: to the extent practical, all network upgrades that are required to accommodate active transmission service requests and are expected to be in-service on or after the Interconnection Customer s requested in-service date for the Project will be modeled in this study. o Generation Interconnection Queue: when relevant, interconnection facilities associated with higher queue interconnection requests will be modeled in this study. However, network upgrades required to provide delivery will only be modeled for projects which have requested network resource integration service only or qualified facility status. No generation will be simulated from any higher SGIQ0314 Page 3 December 29, 2010

4 queued project unless a commitment has been made to obtain transmission service. The Interconnection Customer s request for interconnection service in and of itself does not convey transmission service. This study assumes the Project will be integrated into Transmission Provider s system at the agreed upon and/or proposed point of interconnection. Generator tripping may be required for certain outages. All facilities will meet or exceed the minimum WECC, NERC, and Transmission Provider performance and design standards 4.0 POINT OF INTERCONNECTION The proposed generation facility is to be interconnected, through ten (10) 2000/2250 kva kv to 480-V step-up transformers. The customer has requested to interconnect to Distribution Provider s 34.5-kV Transmission system at West Cedar substation. Figure 1 below, contains a simplified oneline of the proposed generation facility. Figure 1: Simplified One line Diagram of System SGIQ0314 Page 4 December 29, 2010

5 5.0 SCOPE OF WORK 5.1 INTERCONNECTION CUSTOMER S COLLECTOR SUBSTATION The following outlines the design, procurement, installation, and ownership of equipment that is needed for the Interconnection Customer s Collector Substation. WORK TO BE COMPLETED BY THE INTERCONNECTION CUSTOMER Engineer, procure, and construct all facilities required for the Interconnection Customer s collector substation except for those facilities/components indicated as supplied by the Distribution Provider. The Interconnection Customer shall submit, on forms provided by the Distribution Provider, information specific to equipment designed, purchased, and installed by the Interconnection Customer that will be owned and maintained by the Distribution Provider. The completed forms are to be returned to the Distribution Provider s project manager or designated representative. Install a 34.5-kV circuit breaker at the collector substation for connection to the 34.5-kV, 1.1 mile long radial distribution line. The Distribution Provider will review the Interconnection Customers specifications for the breaker to ensure compatibility with the Distribution Providers control and protection schemes. Prior to back feed the Interconnection Customer must arrange distribution voltage retail meter service for electricity consumed by the project and arrange back up station service for power that will be drawn from the transmission or distribution line when the Project is not generating. The Interconnection Customer must call the PCCC Solution Center to arrange this service. Install a relay panel provided by the Distribution Provider in the collector substation. This panel will contain the Distribution Provider s owned and maintained line relays that will function with the line relays installed at the point of interconnection substation for high speed protection of the Interconnection Customer s 34.5kV radial distribution line. The detection and isolation of faults on the 34.5-kV collector system beyond the Interconnection Customer s collector substation 34.5-kV bus will be the responsibility of the Interconnection Customer. Faults on that system will need to be detected and cleared in ten cycles or less. Design, procure, and install, the fiber optic cable, splice boxes, and termination panels for the fiber optic link between the collector substation and the point of interconnection substation. The Distribution Provider will own and maintain the fiber optic system after commissioning. Design, procure, install, own, and maintain the battery backed up power source for the fiber optic communications system. Terminate all field Input/Output connections required to provide data and control in accordance with safe system operation and in compliance with the Interconnection Agreement. Terminate the fiber cable installed between the collector substation and the point of interconnection substation in fiber patch panels and perform continuity and final testing to ensure installation meets specifications and standards provided by the Distribution Provider. SGIQ0314 Page 5 December 29, 2010

6 Design, procure, install, own, and maintain a data concentrator and digital communication circuit using DNP-3.0 protocol. The data concentrator will bridge the data from the generation facility s control system to an existing fiber node at the West Cedar substation. This data will then be transmitted to the Distribution Provider s system control center over the existing fiber network. Design, procure, install, own, and maintain a remote combination Input/Output module and interface to the point of interconnection substation SCADA RTU. The following data is required to be provided to the point of interconnection substation from the Interconnection Customer s substation: Analogs: 52-1 Real Power 52-1 Reactive Power 52-2 Real Power 52-2 Reactive Power Auxiliary Real Power Auxiliary Reactive Power Status: 34.5-kV breakers WORK TO BE COMPLETED BY THE DISTRIBUTION PROVIDER Supply all specifications required for the Distribution Provider s equipment to facilitate design of the collector substation. Perform final checkout and testing/commissioning of the interconnecting line protection/control and communications systems in the collector substation. Design, procure, install, own and maintain a new fiber node and multiplexer to communicate with the existing fiber node in the Distribution Provider s Point of Interconnection substation. Design, procure, own, and maintain a relay panel that will be installed by the Interconnection Customer in the collector substation. This panel will function with the line relays installed at the point of interconnection substation for current differential line protection of the Interconnection Customer s radial transmission line. 5.2 INTERCONNECTION DISTRIBUTION CIRCUIT The following outlines the design, procurement, installation, testing and ownership of equipment for Distribution Provider s Distribution Circuit. WORK TO BE COMPLETED BY THE INTERCONNECTION CUSTOMER Engineer, procure, construct, own and maintain the 1.1-mile 34.5-kV interconnecting tie line between the point of interconnection substation and the Interconnection Customer s collector substation. The last transmission line structure located adjacent to the Distribution Provider s point of interconnection SGIQ0314 Page 6 December 29, 2010

7 substation shall be constructed to Distribution Provider s standards and be one of the following structures; TG 242, TG 251, or TG 252. Engineer, procure, and construct all OPGW/ADSS fiber optic cable (48 count, single mode) and associated equipment from the collector substation to the termination panel inside the point of interconnection substation to support usage of a current line differential relay system that will be used to detect faults the radial interconnection line as well as other relay and operational data communications. WORK TO BE COMPLETED BY THE DISTRIBUTION PROVIDER Supply specifications for Distribution Provider equipment to facilitate the design of the Interconnection Customer s take-off structure. Review the Interconnection Customer s take off structure adjacent to the Distribution Provider s point of interconnection substation to ensure proper clearance and tension. Supply specifications to the Interconnection Customer for the installation of the Distribution Provider s fiber optic cable. Own and maintain all OPGW and ADSS fiber optic cable after final acceptance and checkout by the Distribution Provider. 5.3 POINT OF INTERCONNECTION SUBSTATION The following scope outlines the design, procurement, installation, and ownership of equipment that is needed for the interconnection of the proposed generation facility. In the existing line position, designated as the future capacitor bank position, installation of the additional switches, circuit breaker, bus work and all other equipment/material required will be needed to allow for the interconnection of the Interconnection Customer s generation facility into the West Cedar substation. WORK TO BE COMPLETED BY THE INTERCONNECTION CUSTOMER Design, procure, install, own, and maintain one (1) - 3 conduit with 2 interducts from the Interconnection Customer s last radial transmission line structure located adjacent to the point of interconnection substation to the fence line of the point of interconnection substation. This conduit will join with Distribution Provider installed conduits from the fence to the fiber termination panel inside the point of interconnection substation. Furnish and install the Distribution Provider s ADSS fiber into the point of interconnection control house and terminate the fiber optic cable in the fiber termination patch panels. The fiber patch panels will be owned and maintained by the Distribution Provider; and the Distribution Provider will make the final connection between the patch panel and the end use equipment. Perform end to end checkout of the installed fiber optic cable circuitry between the patch panels at the Interconnection Customer collector substation and the point of interconnection substation and provide optical time-domain reflectometer test traces to the Distribution Provider. Final checkout and SGIQ0314 Page 7 December 29, 2010

8 acceptance shall be in accordance with the Distribution Providers standards and specifications. WORK TO BE COMPLETED BY THE DISTRIBUTION PROVIDER Engineer, procure, construct, own and maintain a new 34.5kV line position to allow for the connection of the Q0314 project into the West Cedar substation. The following is a list of the major equipment required: One (1) 72.5-kV, 2000A, breaker Two (2) 34.5-kV, 2000A, TPST, double side break, manually operated switches One (1) 34.5-kV, 2000A, TPST, vertical break manually operated switch Three (3) 30-kV, MCOV surge arresters Three (3) 34.5-kV metering units Design, procure, install, own and maintain protective relays to detect faults on the 34.5-kV system. A current differential line protection system will be used for this line. The line relays will communicate over the fiber optic communications system installed on the Interconnection Distribution Circuit. In addition to the line protective relaying, a relay used for under/over voltage and over/under frequency protection of the system will be installed at West Cedar substation. If the voltage, magnitude or frequency, is outside of the normal operation range this relay will trip open the tie breaker at West Cedar substation. Design, procure, install own and maintain the point of interconnection revenue metering system including instrument transformers, meter panels, junction boxes, secondary meter control cable, and all other metering equipment to complete the system. The metering design package will include two revenue quality meters, test switches, and all digital and analog data terminated at a metering interposition block. One meter will be designated a primary meter and be used for SCADA data that includes bidirectional KWh quantities, and instantaneous MW, MVAr and per phase voltage data. The second or backup meter will be used for MW data sent to the alternate control center. Because the instrument transformers are a long lead time item, the Interconnection Customer has the option to procure them to the Distribution Provider s specification if desired. Design, procure, modify, own and maintain the existing fiber node equipment in the West Cedar substation. Design, procure, install, own and maintain a GE D20 RTU and make all input/output connections from the patch panel to the end use equipment. The following data is required from the West Cedar substation: Analogs: Net Generation Real Power Net Generator Reactive Power Accumulator Pulses: Interchange metering kwh SGIQ0314 Page 8 December 29, 2010

9 Supply a dialup phone line for retail sales metering and generational accounting via the MV-90 translation system. This may be provided by utilizing the digital communications system. Perform final checkout and point to point testing/commissioning of the communications, metering, and protection and control systems for the interconnection of the proposed generation project. 5.4 COMMUNICATION SPECIFICATIONS [PAST THE POINT OF INTERCONNECTION] The following scope outlines the design, procurement, installation and ownership of equipment that is needed to support the required communications past the point of interconnection. WORK TO BE COMPLETED BY THE DISTRIBUTION PROVIDER Design, procure, install, own and maintain additional multiplex equipment at the Cedar City Service Center, Scipio Pass Communications site, and Salt Lake Control Center. 6.0 COST ESTIMATE The following estimate represents only scopes of work that will be performed by the Transmission Provider. Costs for any work being performed by the Interconnection Customer are not included. West Cedar Substation $ 1,405,000 Installation of a new line position. Transmission Line $ 26,000 Connection of the customer tap line to Transmission Provider s system. Customer Substation $ 374,000 Equipment required for protection and control and communications. Cedar City Service Center $ 46,000 Equipment required for communications. Scipio Pass Communications Site $ 63,000 Equipment required for communications. Salt Lake Control Center $ 27,000 Equipment required for communications. Total Project $ 1,941,000 Note: This estimate is as accurate as possibly given the level of detailed study that has been completed to date and approximates the costs incurred by Distribution Provider to SGIQ0314 Page 9 December 29, 2010

10 interconnecting this generator to Distribution Provider s electrical distribution system. The Interconnection Customer will be responsible for all actual costs, regardless of the estimated costs communicated to or approved by the Interconnection Customer. 7.0 SCHEDULE Please note that the schedule is driven by the date that the Small Generator Interconnect Agreement is signed. If the signed agreement is not received by that date there will be, at a minimum, a day for day slip in the entire schedule. Changes in this date affect the entire schedule. The requested commercial operation date has been moved to the fourth quarter of 2011, or by December 31, Please note that the following schedule does not support the requested in-service date of December 31, Initiating task Date Execute interconnection agreement & provide financial security 02/01/2011 Engineering & procurement commences 04/01/2011 Engineering design completed 09/30/2011 Field construction commences 12/01/2011 Generator step-up transformer receives back feed power 07/31/2012 Generation testing 08/01/2012 Commercial operation 09/10/ PARTICIPATION BY AFFECTED SYSTEMS No Affected Systems were identified in relation to this Interconnection Request. 9.0 APPENDICES Appendix 1: Higher Priority Requests SGIQ0314 Page 10 December 29, 2010

11 APPENDIX 1: HIGHER PRIORITY REQUESTS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are identified below. If any of these requests are withdrawn, the Distribution Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change. Transmission/Generation Interconnection Queue Requests considered: No higher priority transmission service and/or generator interconnection requests have been identified. SGIQ0314 Page 1 December 29, 2010

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation

Small Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016

More information

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662

Small Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662 Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately

More information

Small Generator Interconnection System Impact Study Report. Completed For Q0047

Small Generator Interconnection System Impact Study Report. Completed For Q0047 Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

More information

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )

Revised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer ) Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original

More information

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022

Generation Interconnection Impact Study Report. For. Interconnection Customer Q0022 Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer

More information

Small Generator Interconnection System Impact Study Report. Completed for Q0373

Small Generator Interconnection System Impact Study Report. Completed for Q0373 Small Generator Interconnection Completed for Q0373 Proposed Interconnection To the Existing Q0006 500kV substation on the 13.8kV side of the bus July 7, 2011 TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING

More information

REAL-TIME MONITORING DATA SPECIFICATION

REAL-TIME MONITORING DATA SPECIFICATION REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...

More information

March 4, Mona Substation Line position & assoc relaying, communications & metering

March 4, Mona Substation Line position & assoc relaying, communications & metering 700 N.E. Multnomah, Suite 550 Portland, OR 97232 March 4, 2004 Merrill Brimhall PacifiCorp Merchant 201 South Main, Suite 2200 Salt Lake City, Utah 84111 Dear Mr. Brimhall: PacifiCorp Transmission Systems

More information

TSR A & B - FACILITIES STUDY REPORT

TSR A & B - FACILITIES STUDY REPORT TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection

More information

INTERCONNECTION FACILITIES STUDY REPORT

INTERCONNECTION FACILITIES STUDY REPORT INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December

More information

PG&E Transmission Interconnection Handbook

PG&E Transmission Interconnection Handbook Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New

More information

SOUTH TEXAS ELECTRIC COOPERATIVE, INC.

SOUTH TEXAS ELECTRIC COOPERATIVE, INC. SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection

More information

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems

ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017

More information

Feasibility Study on Load Flow and Short Circuit Project

Feasibility Study on Load Flow and Short Circuit Project Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November

More information

ATTACHMENT I: Generator Interconnection Procedures (GIP)

ATTACHMENT I: Generator Interconnection Procedures (GIP) ATTACHMENT I: Generator Interconnection Procedures (GIP) Section 1. Application 1.1 Applicability 1.1.1 The objective of this GIP is to implement the requirements for Generating Facility interconnections

More information

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY

High-Reliability Fault-Clearing System solution. Application Guide. Outdoor Distribution (15.5 kv through 38 kv) S&C ELECTRIC COMPANY S&C Remote Supervisory V ista Outdoor Distribution (15.5 kv through 38 kv) Electric utility customers are increasingly concerned about the frequency and duration of outages they are experiencing, and are

More information

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS

TRANSMISSION ENGINEERING STANDARDS SUBSTATIONS This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor

More information

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM

SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM SMALL GENERATING FACILITY PRE-APPLICATION REPORT REQUEST FORM 1. Instructions By completing this request form, an Interconnection Customer may request a preapplication report from the NYISO regarding the

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection

More information

1. Project Description

1. Project Description Page No: 1 of 16 1. Project Description 1.1 Introduction This document outlines protection, monitoring and control requirements for the shared network assets associated with establishment of Tarrone Terminal

More information

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service

ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service Improvement and Power District Original Sheet No. F-1 ATTACHMENT F Form of Service Agreement for Wholesale Network Integration Transmission Service 1.0 This Form of Service Agreement for Wholesale Network

More information

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Rocky Mountain Power Exhibit RMP (RTL-1) Docket No Witness: Rick T. Link BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH Exhibit RMP (RTL-1) BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Direct Testimony of Rick T. Link May 31, 2017 Pre-Issuance Bidders Conference Presentation

More information

COGENERATION INTERCONNECTION REQUIREMENTS. Parallel Operation of Connecting Parties Generation

COGENERATION INTERCONNECTION REQUIREMENTS. Parallel Operation of Connecting Parties Generation COGENERATION INTERCONNECTION REQUIREMENTS Parallel Operation of Connecting Parties Generation Cogeneration Interconnection Requirements (ID 195440).docx 1 (This page left blank intentionally) Cogeneration

More information

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281

Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection

More information

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure

Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification

More information

Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards

Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards Attachment H: Small Generator (10 MW and below) Technical Requirements and Standards Scope Attachment H: Small Generator (10 MW and Below) Technical Requirements and Standards The PJM Small Generator Interconnection

More information

IntelliTeam II Automatic Restoration System

IntelliTeam II Automatic Restoration System No system is too complex to automate with... IntelliTeam II Automatic Restoration System Introduced in 1997, the IntelliTeam Automatic Restoration System was the first product of its kind. Using peer-to-peer

More information

Generation, Transmission, and End User Facilities

Generation, Transmission, and End User Facilities Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3

More information

JEA. Facility Connection Requirements

JEA. Facility Connection Requirements JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities

More information

SECTION ELECTRIC METERING

SECTION ELECTRIC METERING SECTION 26 27 13 ELECTRIC METERING SPEC WRITER NOTES: Use this section only for NCA projects Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable

More information

Generation Interconnection Feasibility Study Report

Generation Interconnection Feasibility Study Report Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study

More information

Synchronous switching of distribution sub networks

Synchronous switching of distribution sub networks Synchronous switching of distribution sub networks Paul Stergiou ConEdison USA Manuel P Pimenta, - ConEdison USA Sergio A Rodriguez ConEdison USA Thomas Horan ConEdison USA Andre Smit- Siemens Industry

More information

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station

SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet Reference: ZD23 Version: 1.1 Issue date: 15 May 2014 Contents 1 Scope... 3 2 Deer Park Terminal

More information

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM

BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM BULK POWER SYSTEM FACILITY AND END USER INTERCONNECTION REQUIREMENTS TO THE LIPA TRANSMISSION SYSTEM April 13, 2007 LIPA Facility Connection Requirements TABLE OF CONTENT I. INTRODUCTION...1 II. REFERENCE

More information

Q44 Generation Interconnection

Q44 Generation Interconnection A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,

More information

Electric Utility Facility Connection Requirements

Electric Utility Facility Connection Requirements City of Coffeyville Municipal Light and Power Electric Utility Facility Connection Requirements Approved: Date: Version Date Change Tracking Reviewer/Editor 1.0 June, 2010 Original document. Steve McGie

More information

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 22, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. California Independent System Operator Corporation January 22, 2013 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: California

More information

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning

2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities

More information

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study

XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation

More information

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL

LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL DISTRIBUTION SYSTEM Revised and Issued March 2003 I.

More information

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.

The Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is

More information

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5

SPECIFIC INTERCONNECTION PROTECTION REQUIREMENTS... 5 Central Hudson Gas & Electric Corporation (CHG&E) Interconnection Protection Requirements for Distributed Generators of Greater than 300 kva Connected in Parallel with the CHG&E Electrical Delivery System

More information

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1

Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.

More information

Specification Voltage Limiting Device

Specification Voltage Limiting Device Engineering Specification Electrical Networks L1-CHE-SPE-152 Specification Voltage Limiting Device Version: 1 Issued: 20 th April 2018 Owner: Chief Engineer Approved By: Andrew Russack Head of Engineering,

More information

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS STATE OF MINNESOTA DISTRIBUTED GENERATION INTERCONNECTION TABLE OF CONTENTS Foreword 2 1. Introduction 3 2. References 6 3. Types of Interconnections 7 4. Interconnection Issues and Technical Requirements

More information

Supplemental Information

Supplemental Information Retirement of NPCC Directory# 3 Supplemental Information On April 1, 2015, NPCC Directory# 3 was retired upon the effective date of PRC-005-2 Protection System Maintenance which is subject to a 12 year

More information

Network Configuration Document Selection for New Substations Framework

Network Configuration Document Selection for New Substations Framework Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...

More information

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers

Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power 1. Abstract Dinesh Mithanthaya Design Manager, Horizon Power Higher capacity substation power transformers ( 5MVA),are

More information

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study

Western Spirit Clean Line Project. Non Tariff Interconnection Facilities Study Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean

More information

Flexible High-Speed Load Shedding Using a Crosspoint Switch

Flexible High-Speed Load Shedding Using a Crosspoint Switch Flexible High-Speed Load Shedding Using a Crosspoint Switch Will Allen and Tony Lee Schweitzer Engineering Laboratories, Inc. Published in Wide-Area Protection and Control Systems: A Collection of Technical

More information

It is acceptable to place all required information in the main element (such as G4010) and delete the sub-elements provided in this template.

It is acceptable to place all required information in the main element (such as G4010) and delete the sub-elements provided in this template. 6. ENGINEERING SYSTEMS REQUIREMENTS G40 SITE ELECTRICAL UTILITIES SYSTEMS REQUIREMENTS SITE ELECTRICAL UTILITIES TEMPLATE 02/18 Instructions for using this template: There are template files for each UNIFORMAT

More information

High and Medium Voltage Substation Design, Testing and Maintenance. KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel.

High and Medium Voltage Substation Design, Testing and Maintenance. KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel. Training Course : High and Medium Voltage Substation Design, Testing and Maintenance Training Course For One Week In KSA, Jeddah, Holiday Inn Jeddah Gateway Hotel Which Be Held As Under Details : Tel.

More information

Facility Connection Requirements

Facility Connection Requirements SEMINOLE ELECTRIC COOPERATIVE, INC. Facility Connection Requirements BULK ELECTRIC SYSTEM FACILITIES Facility Connection Requirements Page 1 of 19 Table of Contents 1. GENERAL CONNECTION REQUIREMENTS...

More information

WN U-60 Original Sheet No. 152

WN U-60 Original Sheet No. 152 WN U-60 Original Sheet No. 152 Table of Contents INTERCONNECTION WITH ELECTRIC GENERATORS 1) Introduction Sheet 152-A 2) Attachments Sheet 152-A 3) Definitions Sheet 152-B 4) Applicability Sheet 152-H

More information

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1

WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements

More information

Electric T&D Capacity, Reliability, UG Asset Bulletin

Electric T&D Capacity, Reliability, UG Asset Bulletin UTILITY OPERATIONS FOR IMMEDIATE RELEASE Date: 11/01/04 Title: Check all appropriate boxes X Electric T&D Capacity, Reliability, UG Asset Bulletin Secondary Spot Network System Requirements for Distributed

More information

Real-time Power System Operation. Energy Management Systems. Introduction

Real-time Power System Operation. Energy Management Systems. Introduction 1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern

More information

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER

ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study

Facilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study Facilities Study for the Mora Line Transmission Project Non-Tariff Facilities Study November 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for

More information

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document

Western Area Power Administration (WAPA) Transmission System Network Upgrades Policy Document Western Area Power Administration (WAPA) Transmission System Policy Document This Business Practice documents the Western Area Power Administration (WAPA) policy, as implemented by WAPA s Power System

More information

WON Security Guideline

WON Security Guideline WON Security Guideline Data Exchange Work Group October 7, 2015 155 rth 400 West, Suite 200 Salt Lake City, Utah 84103-1114 WON Security Guideline 1 Table of Contents Purpose... 1 Background... 1 Security

More information

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM

TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM TECHNICAL REQUIREMENTS FOR INTERCONNECTION TO THE BLACK HILLS POWER TRANSMISSION SYSTEM Version 1.2 May 28, 2009 Transmission Planning Department Revisions Rev. No. Date Description By Approval 1.0 8/10/06

More information

Chapter 2 State Estimation and Visualization

Chapter 2 State Estimation and Visualization Chapter 2 State Estimation and Visualization One obvious application of GPS-synchronized measurements is the dynamic monitoring of the operating conditions of the system or the dynamic state estimation

More information

Power System Network Simulator (PSNsim)

Power System Network Simulator (PSNsim) The PSNsim is hardware simulator that simulates all parts of power system from generation to utilization. The PSNsim is a scaled down model of the real power system that provides an experimental environment

More information

An Innovative Approach to Implementing SCADA into the Industrial Environment

An Innovative Approach to Implementing SCADA into the Industrial Environment Feature An Innovative Approach to Implementing SCADA into the Industrial Environment by Lynn Hamrick and David Charles ESCO Energy Services ESCO Energy Services Company recently implemented a Supervisory,

More information

AUTOMATION OF POWER DISTRIBUTION USING SCADA

AUTOMATION OF POWER DISTRIBUTION USING SCADA 1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from

More information

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW

Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW Level 2, 3 and 4 Interconnection Application for Certified, Inverter Based Generating Facilities Not Greater than 2MW The Customer Generator applicant ("Applicant") hereby makes application to the T &

More information

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]

CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)] Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected

More information

Revision 6.0. Transmission Interconnection Guide

Revision 6.0. Transmission Interconnection Guide Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution

More information

Local Area Studies Update - PACW Kevin Putnam

Local Area Studies Update - PACW Kevin Putnam Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton

More information

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:

APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd

More information

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.

PG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4

More information

Grid Interconnection of Renewable Generation

Grid Interconnection of Renewable Generation Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection

More information

Medium Voltage Metal-Enclosed Power Capacitor Banks

Medium Voltage Metal-Enclosed Power Capacitor Banks 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Medium Voltage Metal-Enclosed Power Capacitor Banks General Northeast Power System s (NEPSI's) medium

More information

From: Laura Manz, Vice President of Market & Infrastructure Development

From: Laura Manz, Vice President of Market & Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional

More information

ISO New England Data Modeling Requirements

ISO New England Data Modeling Requirements A U G U S T 1 5, 2 0 1 6 B O S T O N, M A ISO New England Data Modeling Requirements Renew Northeast Meeting Al McBride D I R E C T O R, T R A N S M I S S I O N S T R A T E G Y & S E R V I C E S Agenda

More information

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements

Facility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The

More information

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO

IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved

More information

Smart Distribution Technology

Smart Distribution Technology Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications

More information

SECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE

SECTION APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE SECTION 16262 - APPENDIX B SFC DOCUMENT SUBMITTAL SCHEDULE PART 1 - GENERAL 1.01 RELATED SECTIONS A. Section 01300 Submittals B. Section 16262 Static Frequency Converter C. Section 16262A Appendix A SFC

More information

Digital substations. Introduction, benefits, offerings

Digital substations. Introduction, benefits, offerings Digital substations Introduction, benefits, offerings Outline What is a digital substation? Benefits of digital substations ABB offering for digital substations Substation evolution June 26, 2017 Slide

More information

Exelon Energy Delivery Interconnection Guidelines for Generators Greater than 2 MVA and Less than or equal to 20 MVA

Exelon Energy Delivery Interconnection Guidelines for Generators Greater than 2 MVA and Less than or equal to 20 MVA Exelon Energy Delivery Interconnection Guidelines for Generators Greater than 2 MVA and Less than or equal to 20 MVA Original 10-31-2006 1 Table of Contents DEFINITIONS...3 RESPONSIBILITIES OF THE GIC...5

More information

California lndependent System Operator Corporation Compliance Filing Docket No. ER

California lndependent System Operator Corporation Compliance Filing Docket No. ER The Woshington Harbour 3000 K Street, N.W., Suite 300 Washington, D.C. 20007-51 16 Phone 202.424.7500 Fox 202.424.7647 January 3l.2005 The Honorable Magalie R. Salas Secretary Federal Energy Regulatory

More information

Collector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co.

Collector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co. Collector System Design Considerations for Wind Farms Sean Carr Ernst Camm S&C Electric Co. 1 Overview Challenges in wind farm collector systems Design considerations for collector systems Summary The

More information

LCRA Transmission Services Corporation. Facility Connection Requirements

LCRA Transmission Services Corporation. Facility Connection Requirements LCRA Transmission Services Corporation Facility Connection Requirements April 2017 Table of Contents 1.0 INTRODUCTION... 3 2.0 Facility Connection Requirements... 3 2.1 Summary of Basic Interconnection

More information

SEL-487B. A Powerful Solution for Busbar Differential Protection. Bus Differential and Breaker Failure Relay

SEL-487B. A Powerful Solution for Busbar Differential Protection. Bus Differential and Breaker Failure Relay Bus Differential and Breaker Failure Relay A Powerful Solution for Busbar Differential Protection Features and Benefits Select the for the differential protection of busbar systems with up to 18 terminals.

More information

How smart can the grid really be?

How smart can the grid really be? How smart can the grid really be? by Dale Pudney, HVT Power Systems and Luo Wei, NR Electric With the improvement of electronic communications and computing technology, it becomes possible to integrate

More information

THE INTERCONNECTION HANDBOOK

THE INTERCONNECTION HANDBOOK THE INTERCONNECTION HANDBOOK Southern California Edison Company Rev. 8 This document is controlled by the originating SCE T&D organization. When downloaded and printed, this document becomes UNCONTROLLED,

More information

Sapphire Wind Farm 330/33kV Substation

Sapphire Wind Farm 330/33kV Substation Signature projects: Projects: Project Edison AusNet Sapphire Wind Farm 330/33kV Substation TransGrid Zinfra constructed 330/33kV substation and transmission line as part of the cut in works for the Sapphire

More information

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical

.2 Section General Commissioning (Cx) Requirements. .3 Section Common Work Requirements - Electrical Issued for Review Section 26 28 16.01 Air Circuit Breakers Page 1 of 7 PART 1 GENERAL 1.1 GENERAL.1 This specification serves to define requirements for a replacement of low voltage circuit breaker of

More information

This webinar brought to you by the Relion product family

This webinar brought to you by the Relion product family This webinar brought to you by the Relion product family Relion. Thinking beyond the box. Designed to seamlessly consolidate functions, Relion relays are smarter, more flexible and more adaptable. Easy

More information

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids Enrico Ragaini (ABB Low Voltage Products), Alexandre Oudalov (ABB Corporate Research), ISGT Europe 2012, Berlin Microgrids: Building Blocks of the Smart Grid Adaptive Protection Schemes for Microgrids

More information

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9

Approval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9 PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6

More information

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011

Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011 Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 INTERCONNECTION APPLICATION FOR ALL BUT UL1741 CERTIFIED INVERTER BASED SYSTEMS LESS THAN 10 KW In addition to the information provided below, a complete

More information

WESTERN AREA POWER ADMINISTRATION Meter Policy

WESTERN AREA POWER ADMINISTRATION Meter Policy WESTERN AREA POWER ADMINISTRATION Table of Contents 1. Purpose... 4 2. Scope... 4 3. General Requirements... 5 4. WAPA-Owned Facilities... 6 5. Customer-Owned Facilities... 7 6. New Boundary Meter Installations...

More information

Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium

Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium Our Power & Control line of Business offers solutions that safely distribute power to your home or business. Our product range includes Low/Medium Voltage Panels and Enclosures designed and built with

More information