XXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
|
|
- Gertrude Parks
- 5 years ago
- Views:
Transcription
1 XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation British Columbia Transmission Corporation, All rights reserved.
2 DISCLAIMER Scope and Limitations: This report was prepared by BCTC solely for the purposes described in this report, and is based on information available to BCTC as of the date of this report. Accordingly, this report is suitable only for such purposes, and is subject to any changes arising after the date of this report. Unless otherwise expressly agreed by BCTC, BCTC does not represent or warrant the accuracy, completeness or usefulness of this report, or any information contained in this report, for use or consideration by any third party, nor does BCTC accept any liability out of reliance by a third party on this report, or any information contained in this report, or for any errors or omissions in this report. Any use or reliance by third parties is at their own risk. 1
3 TABLE OF CONTENTS EXECUTIVE SUMMARY INTRODUCTION TERMS OF REFERENCE Designations SYSTEM STUDIES DESCRIPTION OF INTERCONNECTION FACILITIES Direct Assignment Facilities Transmission Tie to 1L Protection Facilities Control Centre Information Facilities Clowhom Substation Facilities Telecommunications Facilities Field Co-ordination Network Upgrade Facilities Transmission Line Upgrades to 1L Protection Control Telecommunications IMPLEMENTATION AND SCHEDULE COST ESTIMATES FOR FACILITIES Direct Assignments (DA) Facilities Network Upgrade (NU) Facilities... 9 Appendix A Documentation
4 EXECUTIVE SUMMARY This report contains a description and associated costs for the BCTC facilities that are necessary so that the Transmission System can accommodate the Bear Creek Hydro generation project near Sechelt, British Columbia. The interconnection facilities identified have been categorized as Direct Assignment or Network Upgrades. The cost estimate is summarized in the following table:. Direct Assignment (DA) $1,000K Network Upgrades (NU) $560K Total $1,560K (+GST) 3
5 1.0 INTRODUCTION XXXX (IPP) is proposing to develop a hydroelectric power generating facility and integrate it into the Transmission System near Sechelt BC. The IPP will generate a total of MW to be injected into the Transmission System at the BC Hydro Clowhom generating station (COM). The IPP facility consists of Upper Bear and Lower Bear, and a small 138kV substation and is collectively referred to as Bear Creek Hydro (BRK). Upper Bear will have one 13.8 kv generator rated at 13 MVA with a power factor of 0.9, and Lower Bear will have one 13.8 kv generator rated at 8.5 MVA with a power factor of 0.9. Maximum output from Upper Bear and Lower Bear are 11.7 MW and 7.65 MW respectively. The IPP will built a 7.5 km 138 kv overhead transmission line from Upper Bear to Lower Bear, and another 6.2 km 138 kv overhead transmission line from Lower Bear to an proposed 138kV substation within 200m of COM. The proposed in service date of the Bear Creek Hydro IPP is September The point of interconnection is the line side disconnect of BRK on line 1L44 at COM. This report contains a description and associated costs for the BCTC facilities that are necessary so that the Transmission System can accommodate the Bear Creek Hydro generation project. 4
6 2.0 TERMS OF REFERENCE On 12 April 2005, XXXX executed an Interconnection Impact Study and Facilities Study Agreement (Agreement) with BCTC. This report documents the Interconnection Facilities Study portion of the work described in the Agreement. The studies are based on the technical submission of XXXX attached in Schedule A of the Agreement. The Interconnection Impact Study is covered in a separate report (SPA ). Referenced Interconnection Facilities Study documentation is listed in Appendix A of this report. 2.1 Designations The following are BCTC operating designations used throughout this report: Item BC Hydro BC Transmission Corporation System Control Centre Lower Mainland Control Centre South Interior Control Centre Clowhom Substation Gibsons Substation Sechelt Substation Bear Creek Hydro Substation XXXX Operating Designation BCH BCTC SCC LMC SIC COM GIB SEC BRK XXXX 5
7 3.0 SYSTEM STUDIES 3.1 System Studies Results Power flow, short circuit, analytical, transient stability, protection, control, and telecommunications studies were performed to identify transmission system limitations for interconnecting the BRK generation project. Refer to the Interconnection Impact Study - Report No. SPA for details. 4.0 DESCRIPTION OF INTERCONNECTION FACILITIES The interconnection facilities identified have been categorized as Direct Assignment or Network Upgrades. 4.1 Direct Assignment Facilities Transmission Tie to 1L44 A 138kv 4-structure tap line to BRK from the COM switchyard, a distance of under 200m Protection Facilities Connect COM 1L44 line protection (new primary and standby) to BRK 138 kv CB CTs and initiate tripping of that breaker from COM 1L44 and T1 protection. Trip into COM T1 protection from breaker failure protection of BRK 138 kv CB. This will provide backup tripping for faults in the BRK installation Control Centre Information Facilities The following work will be required at LMC, SIC and SCC: Database and display work at LMC, SCC and SIC Commissioning at LMC, SIC and SCC Physical termination of D20 port at LMC Data link facilities from LMC to SCC and SCC to SIC Addition of the BRK generators to the Advanced Network Application system at SCC. Details of the required status and telemetry points are covered in the Project Interconnection Requirements. 6
8 4.1.4 Clowhom Substation Facilities Connection of the ground grid of COM to BRK via two size 9 ground wires acting as shield wires on the transmission tap to BRK Telecommunications Facilities A 4W circuit for DNP3.0 IED (SCADA) from Bear Creek to COM. The tone will interconnect at COM to LMC via BCH PLC and Microwave network. Installation of XXXX supplied FOTs equipment between BRK and COM Digital to analog conversion and DC power supply at COM to interface IPP equipment to powerline carrier Powerline carrier facilities between COM and GIB Note: the PLC wave trap at COM is to be connected to the SEC side of the BRK tap to 1L44, otherwise an additional trap must be provided by XXXX at BRK DACs equipment at LMC is required Field Co-ordination Provide Field Coordinator duties associated with the commissioning of BRK to the Transmission System in accordance with System Operating Order 1T-35. Refer to Section 13.1 of BCTC s 69 kv to 500 kv Interconnection Requirements for Power Generators" dated May Network Upgrade Facilities Transmission Line Upgrades to 1L44 Upgrade 1L44 COM to SCG and SCG to SEC to new summer ratings of 240 and 300 amps respectively Protection New primary and standby line protection at COM for 1L Control Add new telemetry for 1L44 and add BRK 52L status to RTU at COM. Add new line telemetry and status points to database and displays at LMC Telecommunications Provide dial-up facilities for SEL-203X via Globestar satellites services for line protection data access. 7
9 5.0 IMPLEMENTATION AND SCHEDULE If BCTC facilities work can proceed by 01 December 2005, BCTC will make reasonable efforts to complete the facilities and be ready for BRK synchronization by 30 September The implementation assumptions, which have been used in the schedule development, are the following: I. BCTC (and its contractors) would perform all work associated with the protection, control centre and telecommunications (excluding satellite) facilities. II. It is assumed that the 1L44 circuit will be de-energized during construction. XXXX is responsible to repay BC Hydro and other IPP(s) tapped on circuit 1L44 for any generation losses/costs incurred during construction. 6.0 COST ESTIMATES FOR FACILITIES All facilities identified for the connection have been categorized as Direct Assignment (DA) Facilities or Network Upgrade Facilities (NU). The following provides a breakdown of the costs. 6.1 Direct Assignments (DA) Facilities The costs for DA facilities, as described in Section 4.0, are summarized in the following table: Project Management $51K Study Work & Other Services $57K Transmission/Station Facilities $220K Protection Facilities $80K Control Centre Facilities $10K Telecommunications Facilities $490K Field Coordinator $11K Overhead $21K Subtotal $940K Contingency (6.6%) $60K DA Total $1,000K (+GST) 8
10 6.2 Network Upgrade (NU) Facilities Project Management $20K Study Work & Other Services $7.5K Transmission Facilities $303K Protection Facilities $83K Control Centre Facilities $17K Telecommunications Facilities $81.5K Overhead/IDC $18K subtotal $530K Contingency (6%) $30K NU Total $560K (+GST) 9
11 Appendix A Documentation The following drawings and notes are part of the project proposal submitted by XXXX. Subsequent revisions or new documents may supersede some of these documents. In such cases the latest issue is the governing document. The following table lists the data and other information from XXXX with respect to the Interconnection Facilities Study. 12 April 2005 Interconnection Impact Study and Facilities Study Agreement 1 March 2005 Generator Interconnection - Application 1 March 2005 ( dated Nov 2003) 1 March 2005 ( dated Nov 2003) Generator Equipment Statement ( GES) Transmission Entrance Equipment Statement (TEES) 13 May 2005 Supplement to the GES ( D. Marano to R. Hefflick regarding BRK G2 voltage) 7 July 2005 Supplement to the TEES ( D. Marano to G. Shtokalko regarding BRK transformer connections) 8 August 2005 Supplement to the GES ( D. Marano to R. Hefflick regarding BRK generator reactance data Rev 3 Nov. 30/04 Control Single One Line Diagram Figure 1 Rev A 2002 Figure 2 Rev A 2002 Substation Location Photo Sketch Substation Layout Preliminary Sketch 10
Studies Overview and Data Requirements. Robert Pan
Studies Overview and Data Requirements Robert Pan Outline 1. Introduction 2. BC Transmission System 3. BCTC Studies for Clean Power Call 4. Data Requirements for Interconnection Studies 5. Application
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationSystem Impact Study for Power Supply 400 MW Import on the EAL BCHA Path
System Impact Study for Power Supply 400 MW Import on the EAL BCHA Path Report No: NPP2000-21 September 13, 2001 Network Performance Planning Department T&D Engineering Executive Summary BC Hydro Power
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More informationGeneration Interconnection Impact Study Report. For. Interconnection Customer Q0022
Generation Interconnection Impact Study Report For Interconnection Customer Q0022 Prepared by: PacifiCorp Date: 10/29/2003 Generation Interconnection System Impact Study Report Interconnection Customer
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationGeneration, Transmission, and End User Facilities
Procedures for Interconnection of Generation, Transmission, and End User To the Grand River Dam Authority Transmission System Table of Contents GRDA/SPP Interaction... 3 Standards... 3 Generation... 3
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationINTERCONNECTION FACILITIES STUDY REPORT
INTERCONNECTION FACILITIES STUDY REPORT NORTHEAST WYOMING 250MW GENERATOR Prepared on Behalf of the Transmission Provider: Basin Electric Power Cooperative Transmission Black Hills Power Transmission December
More informationPG&E Transmission Interconnection Handbook
Table of Contents TABLE OF CONTENTS... 1 UPDATE HISTORY... UP-1 INTRODUCTION... IN-1 I-1. PURPOSE... IN-1 I-2. INTRODUCTORY DEFINITIONS... IN-1 I-3. HANDBOOK APPLICABILITY... IN-2 I-3.1. New Load, New
More informationB-1-1. Janet L. Fraser Director, Regulatory Affairs Phone: Fax:
B-- Janet L. Fraser Director, Regulatory Affairs Phone: 0-- Fax: 0-- E-mail: janet.fraser@bctc.com October 00 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission 00 Howe Street,
More informationENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, OUR TEAM OF PROFESSIONALS HAVE WORKED TOGETHER
smallhydro PRIME ENGINEERING LIMITED IS AN ELECTRICAL ENGINEERING AND SERVICES FIRM THAT SPECIALIZES IN HYDROELECTRIC POWER AND CONTROL SYSTEM DESIGN, IMPLEMENTATION AND MAINTENANCE. OUR TEAM OF PROFESSIONALS
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More informationPG&E Transmission Interconnection Handbook. Update Section Date Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug.
Update History PG&E Transmission Interconnection Hbook Added Figure G5-1 Simplified Flow Chart of Pre- Section G5 Aug. 11, 2004 Parallel/Parallel Test Procedure. Addition of F-35 GE device to Table G2-4
More informationRequests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure
Requests for Clarifications And Responses Order No. 754 Data Request The Study of Single Point of Failure Revised: July 12, 2013 Introduction The following information includes requests for clarification
More informationMONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES
MONITORING AND CONTROL REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITIES 1. Introduction Real time monitoring and control is necessary to ensure public and employee safety and to protect the integrity
More informationGeneration Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationGrid Interconnection of Renewable Generation
Grid Interconnection of Renewable Generation Randy Rismiller August 14, 2013 Generator Interconnection Rule Responsibility In the United States, the responsibility for establishing generator interconnection
More informationClean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008
Clean Power Call BC Transmission Corporation & BC Hydro Joint Information Session July 8, 2008 Agenda 1:30pm Welcome & Introduction Rohan Soulsby 1:40pm Transmission Interconnection Process I Ryan Hefflick
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationTSR A & B - FACILITIES STUDY REPORT
TSR-11-0502A & B - FACILITIES STUDY REPORT Transmission Service Request No. TSR-11-0502A&B 2 x 25 MW Wind Energy Generating Facilities From POI on Gladstone Walsenburg 230 kv Line to Ojo Substation 345
More informationReal-time Power System Operation. Energy Management Systems. Introduction
1 Real-time Power System Operation Energy Management Systems Introduction The time frame for Power Systems Operation varies from a few seconds to a week. To assist with the operation of the system, modern
More informationFeasibility Study on Load Flow and Short Circuit Project
Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November
More informationITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems
ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017
More informationPRC Coordination of Protection Systems for Performance During Faults
PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationTRANSMISSION ENGINEERING STANDARDS SUBSTATIONS
This standard was reviewed and approved by key managers on. Officer approval of this revision is not required. 1.0 SCOPE 1.1 This guide applies to the interconnection of a generating plant with the Oncor
More informationBC Hydro Proje t S openotes - 3
BC Hydro Proje t S openotes - 3 Cargill Grai Ter i al - Ne Su statio Re isio Consolidation of ScopeNotes from: Regional System Stations Planning Performance Planning Transmission Design Protection Planning
More informationSouth Tulsa Switch Automation Pilot
South Tulsa Switch Automation Pilot Presented by: Bret Goodwin, P.E., Distribution System Planning Supervisor AEP-Public Service Company of Oklahoma May 2010 SWEDE Conference Abstract for SWEDE, 2010 Title:
More informationQ44 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,
More informationPOWER SYSTEM DATA COMMUNICATION STANDARD
POWER SYSTEM DATA COMMUNICATION STANDARD PREPARED BY: AEMO Systems Capability VERSION: 2 EFFECTIVE DATE: 1 December 2017 STATUS: FINAL Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au
More informationFacilities Study for the Mora Line Transmission Project. Non-Tariff Facilities Study
Facilities Study for the Mora Line Transmission Project Non-Tariff Facilities Study November 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for
More informationCONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected Generation (DCG)]
Project Name: Kitchener-Wilmot Hydro Inc. 301 Victoria Street South Kitchener, Ontario, Canada N2G 4L2 Appendix F2: Form DG06 CONFIRMATION OF VERIFICATION EVIDENCE REPORT (COVER) [Distribution Connected
More informationInterconnection Feasibility Study Report GIP-IR377-FEAS-R1
Interconnection Feasibility Study Report GIP-IR377-FEAS-R1 Generator Interconnection Request 377 40 MW Wind Generating Facility Renfrew, NS Mar. 6, 2012 Control Centre Operations Nova Scotia Power Inc.
More informationGeneration Interconnection Feasibility Study Report
Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study
More informationOTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER
Parsons Brinckerhoff Associates OTAHUHU SUBSTATION DIVERSITY PROJECT: REVIEW OF THE CIRCUIT BREAKER CONFIGURATION PROPOSED BY TRANSPOWER A report prepared for 23 March 2007 Disclaimer Notice Report for
More informationSmall Generator Interconnection Tier 4 Facilities Study Report. Completed for. ( Interconnection Customer ) A Qualifying Facility Q0662
Small Generator Interconnection Tier 4 Facilities Study Report Completed for ( Interconnection Customer ) A Qualifying Facility Q0662 Proposed Interconnection Klamath Falls-Fishhole 69 kv line at approximately
More informationMarch 4, Mona Substation Line position & assoc relaying, communications & metering
700 N.E. Multnomah, Suite 550 Portland, OR 97232 March 4, 2004 Merrill Brimhall PacifiCorp Merchant 201 South Main, Suite 2200 Salt Lake City, Utah 84111 Dear Mr. Brimhall: PacifiCorp Transmission Systems
More informationDescription of the Application Process for Small Embedded Generators
Description of the Application Process for Small Embedded Generators This document describes the Application Process for Small Embedded Generators (as required under section 5.3.3A of the National Electricity
More informationUtility Interconnection. Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547
Utility Interconnection Highlights of the New Fast Track Process Proposed by FERC and Changes to IEEE 1547 1 4/16/2013 Agenda Review of Status of Distributed Energy Resources Standards Changes Review of
More informationFor further information, please contact Geoff Higgins at or by at
Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com February, 06 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission Sixth
More informationCAISO RIG Acceptance Test Procedure
CAISO RIG Acceptance Test Procedure TABLE OF CONTENTS 1.0 PURPOSE... 3 2.0 INTRODUCTION... 3 3.0 TEST PROCEDURE... 8 Market Services/ EDAS CAISO Public Revision History 1.0 PURPOSE The procedure is intended
More informationLarge Embedded Generators Register of Completed Projects
Large Embedded Generators Register of Completed Projects This document contains a description of the completed projects relating to the connection of Large Embedded Generators to the TasNetworks distribution
More informationFacility Connection Requirements. LST-FAC-001-PRO-Facility_Connection_Requirements
Facility Connection Requirements LST-FAC-001-PRO-Facility_Connection_Requirements Document Control Document Owner: Name: Mathew Gomes Title: Director of Development & System Planning Change History: The
More informationEvolution of Control for the Power Grid
Evolution of Control for the Power Grid Anjan Bose Washington State University Pullman, WA, USA PaiFest In Honor of Prof. M. A. Pai Urbana-Champaign, IL October 15, 2015 The Past (before 1960s) Hard
More informationRevision 6.0. Transmission Interconnection Guide
Revision 6.0 Transmission Interconnection Guide AMERICAN TRANSMISSION COMPANY Transmission Transmission Interconnection Guide Revision 6.0 December 15, 2017 American Transmission Company W234 N2000 Ridgeview
More informationTransmission Expansion Advisory Committee JCPL Supplemental Projects
Transmission Expansion Advisory Committee JCPL Supplemental Projects April 11, 2019 Needs Stakeholders must submit any comments within 10 days of this meeting in order to provide time necessary to consider
More information2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning
Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities
More informationTransmission Interconnection Handbook, Appendix F. System protection, generation interconnection, substation test, and telecommunication personnel
Utility Bulletin: TD-1013B-002 Publication Date: 07/03/2012 Rev: 0 Direct Transfer Trip (DTT) Telecommunication Options Summary Interconnection partners (customers) are requesting additional options for
More informationDesigning a new IEC substation architecture
Designing a new IEC 61850 substation architecture Gerrit Dogger Senior Product and Application Specialist Cooper Power Systems gerrit.dogger@cybectec.com Garry Tennese Station Integration Specialist Manitoba
More informationBC Hydro writes in compliance with Commission Order No. G-67-10, to provide its Report.
Tom A. Loski Chief Regulatory Officer Phone: 604-63-4046 Fax: 604-63-4407 bchydroregulatorygroup@bchydro.com November 0, 05 Ms. Erica Hamilton Commission Secretary British Columbia Utilities Commission
More informationSuperseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 Effective May 27, 2010 Effective December 3, 2011
Superseding SHEET NO. 34C-51 REVISED SHEET NO. 34C-51 INTERCONNECTION APPLICATION FOR ALL BUT UL1741 CERTIFIED INVERTER BASED SYSTEMS LESS THAN 10 KW In addition to the information provided below, a complete
More informationUpdate on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection
GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Update on the Gulf Cooperation Council (GCC) Electricity Grid System Interconnection by: Adnan Al-Mohaisen, GM, GCCIA S. Sud, V.P., SNC-Lavalin Power
More informationERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018
ERO Enterprise Registration Practice Guide: Distribution Provider directly connected Determinations Version 2: July 5, 2018 Purpose The purpose of this Practice Guide is provide a reference to be used
More informationREAL-TIME MONITORING DATA SPECIFICATION
REAL-TIME MONITORING DATA SPECIFICATION Version 1 December 9, 2016 Revision History Version Date Reviewer Revisions 1 11/1/16 Mansion Hudson Initial document 1 Contents 1. DOCUMENT REVIEW... 3 2. DEFINITIONS...
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationInformation Document PRC-001-AB3-1.1(ii) Protection System Coordination ID # RS
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationLecture 6 Substation Automation Systems
Lecture 6 Substation Automation Systems 1 Course map 2 Contents of the Lecture Part 1 Substation Automation Components & Architectures Substation Automation Functions Communication within the Substation
More informationSTCP22-1 Issue 003 Production of Models for GB System Planning
STCP22-1 Issue 003 Production of Models for GB System Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission
More informationProgress Report on the GCC Electricity Grid Interconnection in the Middle East
GULF COOPERATION COUNCIL INTERCONNECTION AUTHORITY Progress Report on the GCC Electricity Grid Interconnection in the Middle East by: Adnan Al-Mohaisen, GM, GCCIA Luc Chausse, Project Director, SNC-Lavalin
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationSTRATHCONA AREA TRANSMISSION UPGRADE PROJECT
STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a
More informationDESCRIPTION OF COST ALLOCATION METHODOLOGY
Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate
More informationCABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE Prepared by
CABLE AMPACITY PROGRAM (CYMECAP) STUDY: MANHOLE 2445 Prepared by BC HYDRO AUGUST 2008 Table of Contents Background... 2 Ductbank on South West... 3 Ampacities at Maximum... 3 at Recent Maximum Demands...
More informationAppendix I: LOAD OPERATING AGREEMENT
PG&E Transmission Interconnection Handbook Appendix I: LOAD OPERATING AGREEMENT Purpose The following agreement establishes operating responsibilities and associated procedures for communications between
More informationHow smart can the grid really be?
How smart can the grid really be? by Dale Pudney, HVT Power Systems and Luo Wei, NR Electric With the improvement of electronic communications and computing technology, it becomes possible to integrate
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: FINAL Approved for distribution
More informationHitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0027 Hardwired Back Up System
Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RO-ABWR-0027 Hardwired Back Up System RO TITLE: Hardwired Back Up System REVISION : 5 Overall RO Closure Date (Planned):
More informationTransmission Register PTO Admin User Manual. Version 1.0
Transmission Register PTO Admin User Manual Version 1.0 Table of Contents 1. INTRODUCTION... 3 1.1. Purpose...3 1.2. Scope...3 1.3. Definitions...3 2. COMPONENTS HOMEPAGE... 6 2.1. Find Components...6
More informationAPPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE:
APPLICATION No. To the ALBERTA ENERGY AND UTILITIES BOARD RE: New 240 kv Montana Alberta Tie Ltd. (MATL) Substation 120S and Reconfigure 240kV Transmission Line 923L AltaLink Management Ltd. 2611 3 rd
More informationImplementation of a Power Line Carrier solution to support anti-islanding protection and reduce interconnection costs for Distributed Generation
Implementation of a Power Line Carrier solution to support anti-islanding protection and reduce interconnection costs for Distributed Generation Jorge Valenzuela Cleveland, Oct 2017 Background NG Solar
More informationPower System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014
Power System Operating Incident Report Trip of Calvale No.2 275kV busbar and Calvale-Halys 8810 and 8811 transmission lines on 30 March 2014 PREPARED BY: Systems Capability DATE: 6 June 2014 STATUS: FINAL
More informationDistributed Generation Requirements Update
Distributed Generation Requirements Update Toronto Hydro has updated its real time monitoring and control requirements for Distributed Generation facilities. The latest version of the Distributed Generation
More informationLecture 5 Substation Automation Systems. Course map
Lecture 5 Substation Automation Systems 1 Course map 2 1 Contents of the Lecture Part 1 Substation Automation Components Substation Automation Functions Communication within the Substation (Intro) Part
More informationICX-CMOS-E-2006 Electrical / I&C Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS
102904-ICX-CMOS-E-2006 Electrical / I&C Engineer Holds a B. Sc. in Electronics & Electrical Communications Engineering and has over 9 years hands-on experience working in I&C field. Has extensive experience
More informationOncor Application for Interconnection of Distributed Generation
Oncor Application for Interconnection of Distributed Generation Operating Mode: Parallel Operation Longer than 100 milliseconds (07/11/2018) This application is for generator systems that synchronously
More informationUPDATES EPC Contract Signed August 2017
ACO SOLAR HV BOP PROJECT NUMBER 2655 Convalt Energy LLC MOEE Myanmar Power Generation, Substation UPDATES EPC Contract Signed August 2017 Convalt Energy LLC are developing a 300MW AC solar farm in Myanmar
More informationSuperseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 Effective May 27, 2010 Effective December 3, 2011
Superseding REVISED SHEET NO. 34D-8 REVISED SHEET NO. 34D-8 2. Initial Technical Review a. The following flowchart provides, for illustrative purposes, the major steps in the Initial Technical Review process:
More informationIMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO
IMS INTERFACE MARKET PROCEDURE NETWORK OPERATORS AND AEMO PREPARED BY: System Management (WA) DOCUMENT REF: SO_OP_WA_3805 VERSION: 1.0 EFFECTIVE DATE: 13/10/2017 STATUS: DRAFT FOR CONSULTATION Approved
More informationLONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL
LONG ISLAND POWER AUTHORITY INTERCONNECTION REQUIREMENTS FOR NEW DISTRIBUTED GENERATION GREATER THAN 300 KVA OPERATING IN PARALLEL WITH LIPA S RADIAL DISTRIBUTION SYSTEM Revised and Issued March 2003 I.
More informationBlackstart Hardware-in-the-loop Relay Testing Platform
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Blackstart Hardware-in-the-loop Relay Testing Platform R. LIU R. SUN M. TANIA Washington
More informationAwareness of the Situation
17/11/21 Situational Awareness UPDEA - Workshop Awareness of the Situation 25,623 Alarms in 8 ours 53 Alarms / min (average) 8% Are consequential Things 1 to keep in mind during a disturbance - Analog
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationSPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station
SPI PowerNet requirements for the non-contestable Interface Works at Deer Park Terminal Station SPI PowerNet Reference: ZD23 Version: 1.1 Issue date: 15 May 2014 Contents 1 Scope... 3 2 Deer Park Terminal
More informationJEA. Facility Connection Requirements
JEA Facility Connection Requirements April 2008 January 14 th, 2006 1/22 JEA Facility Connection Requirements TABLE OF CONTENTS 1.0 Introduction and Scope 1.1 Generation Facilities 1.2 Transmission Facilities
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationApproval...6. Current Revision...7. Introduction... 8 About PJM Manuals... 8 About This Manual... 8 Using This Manual...9
PJM Manual 07: PJM Protection Standards Revision: 3 Effective Date: May 24, 2018 Prepared by System Planning Division Transmission Planning Department PJM 2018 Table of Contents Table of Contents Approval...6
More informationSession Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power Transformers
Session Five: IEC61850 Based Process Bus Protection Solution for Remote Located Power 1. Abstract Dinesh Mithanthaya Design Manager, Horizon Power Higher capacity substation power transformers ( 5MVA),are
More informationSacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,
Sacramento Municipal Utility District SMUD May 10, 2010 1 SMUD Facts and Figures 900 Sq. Miles Service Area 585,500 Customers 1.4 million Area Population 10 Bulk Substations 473 Miles of Transmission Lines
More informationANCILLARY SERVICES BUSINESS MONITORING
ANCILLARY SERVICES BUSINESS MONITORING This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for
More informationCatching Falling Conductors in Midair Detecting and Tripping Broken Distribution Circuit Conductors at Protection Speeds
Catching Falling Conductors in Midair Detecting and Tripping Broken Distribution Circuit Conductors at rotection Speeds Karl Iliev San Diego Gas & Electric Company Eric Udren Quanta Technology, LLC Copyright
More informationSubstation SCADA Monitoring
Substation SCADA Monitoring Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Substations are a critical component
More informationExercise 2. Single Bus Scheme EXERCISE OBJECTIVE DISCUSSION OUTLINE. The single bus scheme DISCUSSION
Exercise 2 Single Bus Scheme EXERCISE OBJECTIVE When you have completed this exercise, you will be familiar with electric power substations using the single bus scheme with bus section circuit breakers.
More informationDesign Guidelines for SCADA & DSA
Design Guidelines for SCADA & 28 th February 2017 28 FEBRUARY 2017 ISSUE 4 PREPARED BY: PRINCIPAL ENGINEER SCADA & MANAGER AUTHORISED BY: MANAGER SECONDARY SYSTEMS DOCUMENT NUMBER: ISSUE 4 This plan is
More informationAUTOMATION OF POWER DISTRIBUTION USING SCADA
1 2 ABSTRACT In every substation certain measurements, supervision, control, operation and protection functions are necessary. Traditionally these functions were performed manually by system operator from
More informationNERC Event Analysis Update Webinar. Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016
NERC Event Analysis Update Webinar Hassan Hamdar Chair, Event Analysis Subcommittee October 20, 2016 Webinar Agenda ERO Event Analysis Process Update Lesson Learned Presentation from Entity ERO Lessons
More informationShabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India
SCADA in Transmission Line Shabnam Rukhsar Electrical Engineering Department, Anjuman College of Engineering and Technology.India ABSTRACT: Transmission line equivalent circuit parameters are often 25%
More informationPublic Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM
Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities
More information