2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning
|
|
- Rosamond Pearson
- 5 years ago
- Views:
Transcription
1 Application No.: Exhibit No.: Witnesses: A.1-0- SCE-0, Vol. 0 R E. Takayesu A (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume R System Planning Before the nd Errata Public Utilities Commission of the State of California Rosemead, California September, 01
2 1 DER solutions will meet the current need associated with one or more of the projects, SCE will refund the balance to customers. However, should the projects be determined to be needed at or sooner than expected due to increased load growth not met by DERs, then SCE will have recovered the revenue requirements associated with these expenditures as part of this request. IV. $,1 $,1 CAPITAL EXPENDITURE FORECASTS SCE is forecast to spend $, million in total capital expenditures from 01 00, of which $,1 million is CPUC-jurisdictional. Table IV- shows the total company (FERC and CPUCjurisdictional) capital expenditure summary and Table IV- shows the CPUC-jurisdictional capital expenditures only. SCE s System Planning work is managed through four primary categories: =, 01=,0 01=, 01=,0 00=, Total=1,1 1. Transmission & Interconnection Planning Projects, described in Section A;. Distribution & Subtransmission Planning Programs and Projects, described in Section B;. System Improvement Programs, described in Section C; and. Customer-Requested Projects, described in Section D. Table IV- System Planning Capital Expenditure Summary 01 (Total Company Nominal $000) 01=,01 01=, 01=1,0, 01=, 00=0, Total=,1,1 Note that the cost recovery for the DERs will not be collected through the GRC. 0 Refer to WP SCE-0 T&D-Vol., Book A, pp. (Tables IV- and IV-). 1 The following capital expenditures for projects with operating dates prior to 01 are not included in the table above: $1. M in 01, $.M in 01, and $.M in 01. Refer to WP SCE-0 T&D-Vol., Book A, pp. (In-Service Projects with CapEx in this GRC). -0-
3 01=, 01=,0 01=, 01=,0 00=, Total=1,1 Table IV- System Planning Capital Expenditure Summary (CPUC-Jurisdictional Nominal $000) 01=,1 01=, 01=,1 A. Transmission & Interconnection Planning Projects 01=, As described in the Transmission & Interconnection Planning Process Section III.A, SCE s 00=0,01 Total=,1,0 Transmission & Interconnection Planning Projects fall into three categories: (1) Grid Reliability Projects needed to support grid reliability; () Transmission System Generation Interconnection Projects needed to interconnect individual generation customers; and () Policy-driven Projects must support state and federal policy to deliver energy to SCE s transmission system. While the majority of work for these transmission projects fall under FERC-jurisdiction, some of these projects include components under CPUC jurisdiction such as upgrades to the underlying subtransmission system or equipment supporting telecommunications, automation, and controls. Both the total project and CPUC-jurisdictional forecast expenditures for these three project categories are shown in Table IV- and Table IV- respectively. The total company cost for all three categories of transmission work is $1,0. million. The CPUC-jurisdictional cost for these projects is $01. million. The tables also include the Generation Interconnection RAS, which has no forecast CPUC-jurisdictional capital expenditures and will not be discussed further in this testimony. Id. See SCE-0, Vol. 1 for SCE s methodology for separating capital expenditures between FERC and CPUC jurisdiction. -1-
4 SCE in 01, the analysis performed in reviewing how DERs impact the distribution system found that clustered DERs will drive more upgrades. 0 The study assumed. percent 1 of the allocated DERs were generating during minimum loading for each distribution circuit, versus 0 percent as often considered for impact studies. By comparing the forecast power flow to the rated capacity of the circuit conductors, the study identified approximately 1 circuit-miles of cable and conductor requiring replacement from on SCE s kv, 1 kv, and 1 kv distribution circuits. Of the circuit-miles, 1 circuit-miles will be overhead conductor and 1 circuit-miles will be underground cable. The total estimated cost to replace miles of overhead conductor and underground cable due to DER exceeding loading limits is approximately $. million (nominal dollars) from The forecast expenditures driven by load growth represent our baseline forecast for distribution circuit upgrades for The expenditure was reduced by $. million to account for energy storage pilots planned to meet distribution needs. 1 Last, forecast expenditure for DER driven upgrades are added to the cost for These three aspects were combined to develop the final expenditure for this category. We forecast capital expenditures to increase by approximately $.0 million per year (in constant 01 dollars) from compared to historical expenditures; as referenced before, 0 expenditure was omitted from the comparison due to changes in accounting. From SCE expects to slowly increase spending in this category to better utilize existing distribution asset capacity and address needs on the kv system.. New Distribution Circuits, WBS Element CET-ET-LG-CI As part of our DSP Program, SCE identifies new distribution circuits as part of three types of projects: new substation projects, substation capacity increase projects, and projects with unique drivers. Figure IV-1 shows the historical 0 costs for these three categories of new distribution circuits while future expenditure only includes standalone circuit projects. This is due to recent accounting changes to avoid overlap in capital expenditure requests. New distribution circuits are required to provide new capacity outside the substation fence in areas where multiple distribution circuits in the same geographical region are expected to exceed capacity; to serve new residential or 0 The Impact of Localized Energy Resources on SCE s Distribution and Transmission System, SCE, May Refer to WP SCE-0 T&D-Vol., Book A, pp. 1 (DER Driven Circuit Upgrades Methodology). Id. Refer to WP SCE-0 T&D-Vol., pp. (Cost of Overhead Conductor Rebuilds). 1 See SCE-0 T&D-Vol. Distributed Energy Storage Integration (DESI) Pilot Program. --
5 approximately a quarter mile from the Mono Lake Fault line and has antiquated equipment that is vulnerable to significant earthquakes. The scope of the project includes a complete rebuild of the substation to current reliability and seismic standards. This includes rebuilding the kv and kv switchracks, replacing the. kv switchrack with a 1 kv switchrack, installing two MVA / kv transformers, and installing two MVA /1 kv transformers. Upon completion of rebuilding Lee Vining Substation, the Cain Ranch./1 kv substation will be decommissioned and the existing. kv circuit currently served from Lee Vining Substation will require a new 1/. kv pole top. This will allow SCE to continue serving customers from the same. kv distribution circuit. The operating date is June 01 with a total project cost of $. million. SCE has identified one alternative for this project. The alternative is to eliminate the kv facilities at Lee Vining / kv substation which requires upgrades to subtransmission lines and neighboring Lundy /1 kv substation. The scope of work at Lee Vining / kv substation includes converting the substation from //. kv to a /1 kv substation, rebuilding the kv switchrack, installing two MVA /1 kv transformers, replacing the low voltage switchrack from. kv to 1 kv, and reconfigure distribution circuitry. The scope of work at Lundy /1 kv substation includes replacing the existing kv switchrack with a kv switchrack, install two MVA /1 kv transformers, and install one MVA /. kv transformer to interconnect existing hydroelectric generation. The subtransmission line work includes replacing approximately. miles of conductor and poles converting both Lee Vining-Lundy No.1 and Lee Vining-Lundy No. from kv to kv and tie in a new subtransmission line to feed temporary / kv transformation while the Lee Vining / kv substation rebuild construction is completed. The total estimated cost for the alternative is $1. million. The preferred project was selected because it is the most cost effective solution.. kv Programs The kv Programs include the conversion or elimination of substations and circuits to address equipment obsolescence, overloads, and reliability. Table IV-1 below shows the total capital forecast for kv Programs. --
6 (1) Santa Barbara County Reliability Project (Project #01) The Goleta-Santa Clara No. 1 and No. 0 kv transmission lines serve Goleta 0/ kv Substation, which serves approximately,000 metered customers in the city of Santa Barbara and surrounding communities. The Goleta-Santa Clara No. 1 and No. 0 kv Transmission Lines are approximately miles long, run on a common steel tower over hilly terrain subject to mudslides during rainy conditions, and are the sole source to Goleta 0/ kv Substation. During the preparation for El Nino in 01, this system received considerable attention from the community and third parties concerned about the potential reliability issues raised if a major landslide occurs that could jeopardize the integrity of the transmission lines, threatening the reliability of service to the Santa $. (DR CUE-DR- Barbara area. Q1) The project scope is to rebuild approximately. miles of existing /0 copper conductor kv subtransmission line connecting the Goleta kv System and the Santa Clara kv System with higher capacity rated Aluminum Conductor Steel Reinforced conductor. Rebuilding this kv subtransmission line will allow approximately two-thirds of the load served by Goleta 0/ kv Substation to be safely and reliably transferred to the neighboring Santa Clara 0/ kv Substation during an outage of the Goleta-Santa Clara No. 1 and No. 0 kv Transmission Lines. The operating date is December 01 with a total project cost of $1. million. This project was included in SCE s 01 GRC filing with a June 01 operating date and in the 01 GRC with a June 01 operating date, but was subsequently moved to December 01 due to the CPUC requiring that the project go through licensing. The CPUC issued SCE a Permit to Construct in Decision D (D.1--00) on November, 01. SCE identified one alternative to this project to construct a new 0 mile 0 kv transmission line from Santa Clara 0/ kv Substation to Goleta 0/ kv Substation. The alternative analysis can be found in the PEA (Application A filed October, 01). The total estimated cost of this alternative is $. million. SCE s proposed project is expected to cost $. million and was selected as the lower-cost alternative. () Base Case Reconductor/Recable Projects Of the remaining 1 subtransmission line reconductor/recable projects, six are needed to correct forecast normal base case overloads. These include the Vestal-Mariposa kv Line, the Vestal-Columbine-Delano-Earlimart kv Line, and the La Cienega Beverly Culver kv Line which correct both Base Case and Likely Contingency violations. In addition, normal Base --
7 Table IV-0 Subtransmission VAR Plan Capital Expenditure Summary (CPUC-Jurisdictional Nominal $000) Line Project Operating Project Name No. No. Date Prior Total 1 0 Projects with CPUC-jurisdictional cost < $M 1,00 1,0 1,0 1,0 1,, Total Subtransmission VAR Plan 1,00 1,0 1,0 1,0 1,, 1 C. System Improvement Programs The System Improvement Programs include three categories in which expenditure forecasts are developed: 1) Substation Equipment Replacement Program, ) Distribution VAR Plan, and ) the Substation Monitoring Program. These programs include evaluation and identification of equipment near or at the limit of its protection level, supplying sufficient reactive power to the distribution electrical system, and installing monitoring systems at substations to enable the retrieval of substation 01=1,1 loading and underground cable temperature data. SCE explains how these System Improvement 01=0, 01=,0 Programs are planned in Section III.C. Brief descriptions of these categories and forecasts are included 01=, below. 00=1,1 Total=1, Table IV-1 System Improvement Programs Capital Expenditure Summary (CPUC-Jurisdictional Nominal $000) 1. Substation Equipment Replacement Program, WBS Element CET-ET-LG-SU The Substation Equipment Replacement Program (SERP) covers forecast expenditures 01=, 01=,0 1 for work required to replace substation equipment identified to exceed their protection ratings to 01=, 1 interrupt fault current. SCE has identified substation circuit breakers projected to exceed short circuit 01=,0 00=, duty interrupting capabilities. Circuit breakers attempting to interrupt fault current that exceed ratings Total=1,1 1 have the potential to cause catastrophic failure resulting in prolonged outages. Leaving these breakers in 1 1 Line No. Program/Project Category Total 1 Substation Equipment Replacement Program 1, 1, 0, 1,0, 1, Distribution VAR Plan,,1,,1,1, Substation Monitoring Programs Total System Improvement,1,,1,0 0,0 1,1 service jeopardizes worker safety proposing the potential scenario where a catastrophic failure occurs when work is being performed in the substation. The only alternative option to replacing circuit breakers Refer to WP SCE-0 T&D-Vol., Book A, pp. 0 (Table IV-1). --
8 1 is to split the substation bus. This can reduce short circuit duty at circuit breakers at the bus being split. However, this solution can only be accomplished at subtransmission substations and not available for distribution substations. Splitting the bus at a distribution substation incorporates risk of not providing enough fault current to operate circuit breakers. In addition, the option of splitting a subtransmission substation bus is usually not a cost effective solution compared to replacing circuit breakers. More details on how SCE plans for this category is explained in Section III.C.1. SCE analyzed historical cost data to develop unit costs for circuit breaker replacements in this category. The unit cost was applied to our forecast units to develop our annual expenditure forecast. Table IV- provides the unit cost, unit count, and annual expenditure forecast for circuit breaker replacements in each voltage class for the SERP category. Table IV- Substation Equipment Replacement Program Capital Expenditure Forecast 1 WBS Element CET-ET-LG-SU (CPUC-Jurisdictional Nominal $000) kv CBs to Replace 1 kv Unit Cost $ $ $ $ $0 Subtotal $, $, $1,1 $1, $, kv CBs to Replace 1 1 kv CBs to Replace kv CBs to Replace kv Unit Cost $1 $1 $1 $1 $1 1 kv Unit Cost $1 $1 $1 $1 $1 1 kv Unit Cost $1 $1 $1 $1 $1 Subtotal $,0 $1, $1,0 $1, $1, Total $1, $1, $0, $1,0 $, 1 1 Figure IV- below, shows 0 01 recorded and forecast expenditures for SERP. From 0 01, our SERP expenditures averaged $. million per year (in constant 01 dollars). The total cost for the SERP over the forecast period is $1. million (in nominal dollars), or an average of $. million per year (in constant 01 dollars) in the period. Refer to WP SCE-0 T&D-Vol., pp. 1 1 (Cost of Circuit Breaker Replacements). 1 Refer to WP SCE-0 T&D-Vol., Book A, pp. 0 (Table IV-1). --
9 1 is to split the substation bus. This can reduce short circuit duty at circuit breakers at the bus being split. However, this solution can only be accomplished at subtransmission substations and not available for distribution substations. Splitting the bus at a distribution substation incorporates risk of not providing enough fault current to operate circuit breakers. In addition, the option of splitting a subtransmission substation bus is usually not a cost effective solution compared to replacing circuit breakers. More details on how SCE plans for this category is explained in Section III.C.1. SCE analyzed historical cost data to develop unit costs for circuit breaker replacements in this category. The unit cost was applied to our forecast units to develop our annual expenditure forecast. Table IV- provides the unit cost, unit count, and annual expenditure forecast for circuit breaker replacements in each voltage class for the SERP category. Table IV- Substation Equipment Replacement Program Capital Expenditure Forecast 1 WBS Element CET-ET-LG-SU (CPUC-Jurisdictional Nominal $000) kv CBs to Replace 1 kv Unit Cost $ $ $ $ $0 Subtotal $, $,0 $,01 $1, $1, kv CBs to Replace 1 1 kv CBs to Replace kv CBs to Replace kv Unit Cost $1 $1 $1 $1 $1 1 kv Unit Cost $1 $1 $ $ $1 1 kv Unit Cost $1 $1 $ $ $1 Subtotal $,0 $1, $1,0 $1,1 $1, Total $1,1 $0, $,0 $, $1,1 Figure IV- below, shows 0 01 recorded and forecast expenditures 1 for SERP. From 0 01, our SERP expenditures averaged $. million per year (in constant 01 1 dollars). The total cost for the SERP over the forecast period is $1. million (in nominal dollars), or an average of $. million per year (in constant 01 dollars) in the period. Refer to WP SCE-0 T&D-Vol., pp. 1 1 (Cost of Circuit Breaker Replacements). 1 Refer to WP SCE-0 T&D-Vol., Book A, pp. 0 (Table IV-1). -- A
10 Nominal 01=1,1 01=0, 01=,0 01=, 00=1,1 Figure IV- Substation Equipment Replacement Program (SERP) Expenditures WBS Element CET-ET-LG-SU Recorded 0-01/Forecast (CPUC-Jurisdictional Constant 01 and Nominal $000) Constant 01$ 01=1,0 01=1, 01=,0 01=, 00=, In 01, SCE analyzed the short circuit duties at existing substations against the ratings of the circuit breakers. This analysis prioritized circuit breaker replacements based on percentage of overstress to mitigate safety risks. The result was the development of a plan to address projected overstressed distribution breakers and 1 overstressed subtransmission breakers in years The forecast expenditures are displayed in Figure IV-. The evolving state of both the transmission and distribution systems has resulted in increased Short Circuit Duty levels across the SCE system. SCE views this as an issue important to system safety and reliability and accommodating DERs. 1 SCE is increasing the total distribution and subtransmission level breaker replacements compared to historical replacements to help facilitate DER expansion and maintain safety and reliability of the electrical system as it evolves.. Distribution VAR Plan, WBS Element CET-PD-LG-NC Distribution capacitor banks supply reactive power (VAR) to the distribution system to maintain acceptable power factor and suitable voltage to serve customers. Reactive power demand increases as load continues to increase on the system. Distribution capacitors are connected along the 1 Refer to WP SCE-0 T&D-Vol., Book A, pp. 1 (DER Driven Circuit Upgrades Methodology). --
2015 General Rate Case
Application No.: Exhibit No.: Witnesses: A.1--00 SCE-0, Vol. 0 R. Woods E. Takayesu (U -E) 01 General Rate Case ERRATA Transmission and Distribution (T&D) Volume System Planning Capital Projects Before
More information2018 General Rate Case
Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: M. Flores B. Tolentino A (U -E) 01 General Rate Case ERRATA Transmission & Distribution (T&D) Volume 0 Substation Construction & Maintenance
More information2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 System Planning
Application No.: A.1-0- Exhibit No.: SCE-0, Vol. 0 Witnesses: E. Takayesu (U -E) 01 General Rate Case Transmission & Distribution (T&D) Volume System Planning Before the Public Utilities Commission of
More informationMemorandum. This memorandum requires Committee action.
California Independent System Operator Corporation Memorandum To: ISO Operations Committee From: Dariush Shirmohammadi, Director of Regional Transmission - South Armando Perez, VP, Planning & Infrastructure
More informationFunding California Investor Owned Utilities Smart Grid Technologies & Deployments
Funding California Investor Owned Utilities Smart Grid Technologies & Deployments Wendy al-mukdad, PE Utilities Engineer Grid Planning & Reliability Section, Energy Division California Public Utilities
More information2012 General Rate Case
Application No.: Exhibit No.: SCE-0, Vol. 0 Part 0 & 0, Ch. I-II Witnesses: P. Arons K. Varnell (U -E) 01 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Part - Transmission
More informationWORKPAPERS TO PREPARED DIRECT TESTIMONY OF DAVID BUCZKOWSKI ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY BEFORE THE PUBLIC UTILITIES
Application of SOUTHERN CALIFORNIA GAS ) COMPANY for authority to update its gas ) requirement and base rates ) effective January 1, 2019 (U 904-G) ) Application No. 17-10- Exhibit No.: (SCG-11-CWP) WORKPAPERS
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) )
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E For a Permit to Construct Electrical Facilities With Voltages
More information2018 General Rate Case
Application No.: A.-0- Exhibit No.: SCE-0, Vol. Witnesses: T. Reeves (U -E) 0 General Rate Case Transmission & Distribution (T&D) Volume - Other Costs, Other Operating Revenues Before the Public Utilities
More informationNotes to expenditure information provided by WE in support of the CPP earthquake readiness expenditure. Commissioned Assets
Notes to expenditure information provided by WE in support of the CPP earthquake readiness expenditure Commissioned Assets Notes Capitalisation policy Consistent with IM 5.3.11, CPP capex, including for
More informationISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO
ISO Responses to Questions about the Memorandum of Understanding between Valley Electric Association and the ISO The following Q & A is based on questions raised by stakeholders on an ISO conference call
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E for a Permit to Construct Electrical Facilities With Voltages
More informationThe Narragansett Electric Company. d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No Testimony of. Todd G. Kopoyan, P.E.
d/b/a National Grid (Rhode Island Reliability Project) RIPUC Dkt. No. 0 Testimony of Todd G. Kopoyan, P.E. February 0, 00 0 0 INTRODUCTION Q. Please state your name and business address. A. My name is
More informationEU DONOR FUNDED SMART GRID PROGRAMME
EU DONOR FUNDED SMART GRID PROGRAMME 1 Historical Background Msunduzi Local Municipality is a local municipality in Umgungundlovu District Municipality, KwaZulu-Natal, South Africa. It encompasses the
More informationSmall Generator Interconnection Facilities Study Report. Completed for Q0314 ( Interconnection Customer ) A Qualified Facility
Small Generator Interconnection Completed for Q0314 ( Interconnection Customer ) A Qualified Facility Proposed Interconnection PacifiCorp s 34.5-kV West Cedar Substation December 29, 2010 TABLE OF CONTENTS
More information2009 General Rate Case
Application No.: Exhibit No.: SCE-0, Vol., Pt. Ch. I-IV Witness: A. Salinas (U -E) 00 General Rate Case Transmission And Distribution Business Unit (TDBU) Volume Capital Expenditures Part, Chapter I IV
More informationSacramen Sacr t amen o t Municipal Utility Dis t Dis rict t SMUD May Ma 10,
Sacramento Municipal Utility District SMUD May 10, 2010 1 SMUD Facts and Figures 900 Sq. Miles Service Area 585,500 Customers 1.4 million Area Population 10 Bulk Substations 473 Miles of Transmission Lines
More information2018 General Rate Case Rebuttal Testimony
Application No.: A.1-0-001 Exhibit No.: SCE-1, Vol. 0 Witnesses: A. Ayorinde (U -E) 01 General Rate Case Rebuttal Testimony Transmission & Distribution (T&D) Volume - Customer-Driven Programs Before the
More informationSmall Generator Interconnection System Impact Study Report. Completed For Q0047
Small Generator Interconnection Completed For Q0047 Proposed Interconnection PacifiCorp s Existing Goshen Rigby 69 kv Line March 7, 2005 1.0 Description of the Generation Facility Q0047 ( Interconnection
More informationLADWP POWER INFRASTRUCTURE PLAN
LADWP 2017-18 POWER INFRASTRUCTURE PLAN Introduction LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4 million
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER07-1034-002 REPLY BRIEF OF SOUTHERN CALIFORNIA EDISON COMPANY (March 19, 2009)
More informationFrom: Laura Manz, Vice President of Market & Infrastructure Development
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Laura Manz, Vice President of Market & Infrastructure Development Date: May 8, 2009 Re: Decision for Conditional
More informationSmart Distribution Technology
Smart Distribution Technology Presentation Agenda Alabama Power Company, A Southern Company Distribution Automation Supervisory Control And Data Acquisition (SCADA) Multiple Address System (MAS) communications
More informationAdvanced Protection and Control Technologies for T&D Grid Modernization
Advanced Protection and Control Technologies for T&D Grid Modernization i-pcgrid Workshop San Francisco, CA March 31, 2016 Jeff Shiles, Principal Manager Protection & Automation Engineering Southern California
More informationSupplemental Testimony on Safety-Related Spending
Application No.: Exhibit No.: Witnesses: A.16-09-001 SCE-16 S. Menon (U 338-E) Supplemental Testimony on Safety-Related Spending Before the Public Utilities Commission of the State of California Rosemead,
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: May 21, 2014 Re: Decision on interconnection
More informationBEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION
BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE FORMULA ) RATE PLAN FILINGS OF OKLAHOMA GAS ) GAS AND ELECTRIC COMPANY ) DOCKET NO. -0-FR PURSUANT TO APSC DOCKET ) NO. -0-U ) Direct
More informationSmall Generator Interconnection Facilities Study Report. Completed for. ( Interconnection Customer ) Proposed Interconnection Pavant substation
Small Generator Interconnection Facilities Study Report Completed for ( Interconnection Customer ) Proposed Interconnection Pavant substation Original report dated February 17, 2016 Revised March 11, 2016
More information2018 General Rate Case. Operational Services (OS) Volume 3 Corporate Real Estate
Application No.: A.1-0- Exhibit No.: SCE-0, Vol. Witnesses: N. Desrocher A D. Bauder (U -E) 01 General Rate Case nd Errata Operational Services (OS) Volume Corporate Real Estate Before the Public Utilities
More information2018 General Rate Case. Transmission & Distribution (T&D) Volume 11 Grid Technology
Application No.: A.-0- Exhibit No.: SCE-0, Vol. Witnesses: D. Kim (U -E) 0 General Rate Case Transmission & Distribution (T&D) Volume Grid Technology Before the Public Utilities Commission of the State
More informationATC Zone 2 Projects Update U.P. Energy Summit
ATC Zone 2 Projects Update U.P. Energy Summit Brett French Regional Manager of External Relations Michigan October 16, 2012 Helping to keep the lights on, businesses running and communities strong Project
More informationRCP2 Portfolio Overview Document
RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016
More informationDESCRIPTION OF COST ALLOCATION METHODOLOGY
Filed: September, 00 EB-00-00 Exhibit G Schedule Page of 0 DESCRIPTION OF COST ALLOCATION METHODOLOGY.0 INTRODUCTION This schedule provides an overview of the cost allocation methodology used to allocate
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Eldorado-Lugo-Mohave
More informationINTERCONNECTION FACILITIES STUDY REPORT
Interconnection Request No. TI-08-0312 INTERCONNECTION FACILITIES STUDY REPORT Prepared by Tri-State Generation and Transmission Association, Inc. 1 of 7 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
More informationSub Regional RTEP Committee Mid-Atlantic First Energy MAAC
Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC September 21, 2018 Penelec Transmission Zone Need Number: PN-2018-001 Consider upgrading transmission line equipment (switches, conductor, splices,
More informationTHE INTERCONNECTION HANDBOOK
THE INTERCONNECTION HANDBOOK Southern California Edison Company Rev. 8 This document is controlled by the originating SCE T&D organization. When downloaded and printed, this document becomes UNCONTROLLED,
More informationLocal Area Studies Update - PACW Kevin Putnam
Transmission Planning Attachment K Q5 Public Input Meeting Local Area Studies Update - PACW Kevin Putnam March 23, 2017 Hermiston-Pendleton-Enterprise Study Finding Report Jerry Vang PAGE 3 Hermiston-Pendleton
More informationWECC Criterion MOD-(11 and 13)-WECC-CRT-1.1
WECC Criterion MOD-(11 and 13)-WECC-CRT-1.1 A. Introduction 1. Title: Steady State and Dynamic Data Requirements 2. Number: MOD-(11 and 13)-WECC-CRT-1.1 3. Purpose: To establish the consistent data requirements
More informationPreparing for the Dynamic Grid of Future
Preparing for the Dynamic Grid of Future Peter Hoffman, P.E. Duke Energy, Grid Solutions Engineering & Technology POWERING LIVES & COMMUNITIES Environmental Stewardship Reliable Service Affordable Rates
More informationTHE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS?
THE ANATOMY OF A CENTRALIZED REMEDIAL ACTION SYSTEM: WHAT CAN BE DONE IN 50 MILLISECONDS? Whitepaper authored by: Herbert Falk Senior Solutions Architect SISCO, Inc. herb@sisconet.com One of the major
More informationDemonstration Test Bed for Advanced Control Systems
Demonstration Test Bed for Advanced Control Systems Christopher R Clarke Senior Engineer SCE Advanced Technology June 22, 2016 1 Advanced Distribution Control Systems Introduction of customer adoption
More informationXXXX. Bear Creek Hydro Generation Project. Interconnection Facilities Study
XXXX Bear Creek Hydro Generation Project Interconnection Facilities Study Report No. SPA 2005-33 August 2005 System Planning (Lower Mainland & Vancouver Island) British Columbia Transmission Corporation
More informationSHARED SERVICES - INFORMATION TECHNOLOGY
Updated: February, 00 EB-00-0 Exhibit D Page of SHARED SERVICES - INFORMATION TECHNOLOGY.0 INTRODUCTION 0 Information Technology ( IT ) refers to computer systems (hardware, software and applications)
More informationRevised Generation Interconnection Impact Study Report. For. Queue Position 31 ( Interconnection Customer )
Revised Generation Interconnection Impact Study Report For Queue Position 31 ( Interconnection Customer ) September 22, 2004 1 Generation Interconnection System Impact Study Report I. Revision of Original
More informationPublic Service Company of New Mexico
Public Service Company of New Mexico Open Transmission Planning Meeting November 2, 2017 Albuquerque, NM INTRODUCTION Public Stakeholder Meeting Order 890 Objective to improve transparency and stakeholder
More informationSE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality,
SE Engineering, PC strives to be a leader in the power system engineering field by providing our customers with the highest level of quality, integrity, and innovation. Our mission is to offer the safest,
More informationGeneration Interconnection Feasibility Study Report
Project 76 Generation Interconnection Feasibility Study Report December 21, 2007 Electric Transmission Planning Table of Contents Table of Contents... 2 Executive Summary... 3 Network Resource Interconnection
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities: Cerritos
More informationHIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM
HIGH LEVEL REQUIREMENTS OF FAST SIMULATION AND MODELLING SUITE OF TOOLS FOR FUTURE SELF-HEALING DISTRIBUTION POWER SYSTEM A. Valenti* I Bel ** S. Lee *EDF **EPRI E2I ConEdison France USA USA arnaud.valenti@edf.fr
More information(U 338-E) 2018 General Rate Case A Workpapers. T&D- Distribution Maintenance and Inspection SCE-02 Volume 04
(U 338-E) 2018 General Rate Case A.16-09- Workpapers T&D- Distribution Maintenance and Inspection SCE-02 Volume 04 September 2016 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 I. DISTRIBUTION
More informationUpdates and Modifications to Report
QUARTERLY COMPLIANCE REPORT (JANUARY 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision
More informationJuly 1, 1999 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Donald A. Fellows, Jr. Manager of Revenue and Tariffs July 1, 1999 (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Notice of Proposed Construction of Facilities
More informationGenerator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281
Generator Interconnection Impact Study Report Pamlico County, NC 200 MW Wind Farm Queue #281 June 6, 2012, Inc. PURPOSE The purpose of this impact study is to assess the impacts of a wind farm interconnection
More informationStatus and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014
Status and Next Steps NARUC Electricity Committee Hank Courtright, Senior VP July 15, 2014 2014 Electric Power Research Institute, Inc. All rights reserved. Meet the Challenge An Integrated Grid 2 Interconnected
More informationG. Larry Clark Principal Engineer Power Delivery Alabama Power Company, A Southern Company
2014 IEEE PES T&D Conference & Exposition Chicago, IL April 15, 2014 Panel Session: Technologies for Advanced Volt/VAR Control Implementation Volt/VAR Control as Part of an Integrated Distribution Management
More informationSTRATHCONA AREA TRANSMISSION UPGRADE PROJECT
STRATHCONA AREA TRANSMISSION UPGRADE PROJECT September 2017 ProjeCt InFormation You are receiving this information because you are a landowner, resident, business owner, or occupant of property near a
More informationKEDS DSO Development Plan. George Karagutoff, KEDS CEO Prishtina, Kosovo 20 March, 2018
KEDS DSO Development Plan George Karagutoff, KEDS CEO Prishtina, Kosovo 20 March, 2018 1 INVESTMENTS AT A GLANCE KEDS begun its operations after the successful unbundling of Distribution and Supply business
More informationFeasibility Study on Load Flow and Short Circuit Project
Feasibility Study on Load Flow and Short Circuit Project 101813-01 Prepared by: Transmission Planning Department Cleco Corporation, Inc. 2180 St. Landry Hwy P.O. Box 70 St. Landry, LA 71367 Final November
More informationInterconnection and Transmission
Interconnection and Transmission Gary L. Brown, P.E. Director of Energy Development Gary@ZGlobal.biz 916-985-9461 Kevin Coffee Energy Management Committee Meeting Irvine, California August 26, 2015 Interconnection
More informationUpdates and Modifications to Report
QUARTERLY COMPLIANCE REPORT (APRIL 2017) OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) REGARDING STATUS OF TRANSMISSION PROJECTS AND GENERATION INTERCONNECTION PROJECTS Pursuant to Commission Decision
More informationNetwork Configuration Document Selection for New Substations Framework
Network Configuration Document Selection for New Substations Current version: 20/06/2018 EXTERNAL USE Page 1 of 14 Table of contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 References...
More informationInmate Population Forecast and Analysis Update for Minnehaha County South Dakota. Bill Garnos
Inmate Population Forecast and Analysis Update for Minnehaha County South Dakota January 8, 2014 Bill Garnos Jail Consultant First Meeting August 2013 Consultant Background and Previous Studies Overview
More informationPublic Service Company of New Mexico. Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM
Public Service Company of New Mexico Public Transmission Planning Meeting March 2, 2017 Albuquerque, NM Agenda Introduction Agenda Additions Stakeholder Process PNM 10-Year Plan Development Regional Activities
More informationStandard CIP Cyber Security Critical Cyber As s et Identification
A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification
More information2015 General Rate Case
Application No.: Exhibit No.: Witnesses: SCE-11 R. Lisbin (U 338-E) 2015 General Rate Case Compliance Before the Public Utilities Commission of the State of California Rosemead, California November 2013
More informationToronto Hydro-Electric System Limited EB Exhibit G1 Tab 1 Schedule 1 ORIGINAL Page 1 of 15 SMART GRID PLAN
EB-00-0 Exhibit G Tab Schedule Page of 0 SMART GRID PLAN INTRODUCTION This Exhibit presents THESL s plans for development of the smart grid in keeping with the Green Energy and Green Economy Act, 00 (
More informationDevelopment trends in Substation Design
Development trends in Substation Design on behalf of SC B3 Hans-Erik Olovsson Convenor Activity Area 1 (AA1) «Substation concepts and development» hans-erik.olovsson@se.abb.com 1 Agenda Evolution of primary
More information2015 General Rate Case
Application No.: Exhibit No.: Witnesses: SCE-1 J. P. Shotwell (U -E) 01 General Rate Case Testimony Regarding Accessibility Issues Developed Jointly By SCE and Center for Accessible Technology Before the
More informationLos Anseles W Department of 5* Water & Power
Los Anseles W Department of 5* Water & Power 3D RESOLUTION NO. BOARD LETTER APPROVAL DAVID H. WRIGHT MARCIE L. EDWARDS Chief Operating Officer General Manager DATE: May 26, 2016 SUBJECT: Lease Agreement
More informationITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems
ITC Facility Connection Requirements for Generation, Transmission and End-User Facilities Connected to the ITC Holdings Transmission Systems Category: Planning Type: Policy Eff. Date/Rev. # 06/19/2017
More informationSOUTH TEXAS ELECTRIC COOPERATIVE, INC.
SOUTH TEXAS ELECTRIC COOPERATIVE, INC. P.O. Box 119 Nursery, Texas 77976 (361) 575-6491 Fax (361) 576-1433 Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection
More informationPRC Coordination of Protection Systems for Performance During Faults
PRC-027-1 Coordination of Protection Systems for Performance During Faults A. Introduction 1. Title: Coordination of Protection Systems for Performance During Faults 2. Number: PRC-027-1 3. Purpose: To
More informationWestern Spirit Clean Line Project. Non Tariff Interconnection Facilities Study
Western Spirit Clean Line Project Non Tariff Interconnection Facilities Study September 2017 Work Performed by: Public Service Company of New Mexico Foreword This technical report is prepared for Clean
More informationPepco. Reliability Enhancement Plan. For. Montgomery County, Maryland. Including. Distribution System Overview and Reliability Initiatives
l pepco A PHI Company Pepco Reliability Enhancement Plan For Montgomery County, Maryland Including Distribution System Overview and Reliability Initiatives August 2010 TABLE OF CONTENTS 1. Executive Summary.
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft
More informationStandard CIP Cyber Security Critical Cyber As s et Identification
A. Introduction 1. Title: Cyber Security Critical Cyber Asset Identification 2. Number: CIP-002-4 3. Purpose: NERC Standards CIP-002-4 through CIP-009-4 provide a cyber security framework for the identification
More informationPOWER INFRASTRUCTURE PLAN 2016
POWER INFRASTRUCTURE PLAN 2016 Introduction LADWP has built a vast power generation, transmission and distribution system that spans five Western states, and delivers electricity to about 4 million people
More informationRE: Response to the U.S. Army Corps of Engineers s Questions Related to the Proposed Haymarket Transmission Line
Dominion Energy P.O. Box 26666, Richmond, VA 23261 DominionEnergy.com David J. DePippo Senior Counsel Direct: (804) 819-2411 Facsimile: (804) 819-2183 david.j.depippo@dominionenergy.com Via Email Ms. Anna
More informationSouthern Company Smart Grid
Southern Company Smart Grid Smart Grid Investment Grant Update July 25, 2011 Southern Company Southern Company is one of the nations largest generators of electricity Has 4.4 million retail customers across
More informationDUKE ENERGY OHIO SMART GRID / GRID MODERNIZATION. Don Schneider GM, Smart Grid Field Deployment May 24, 2012
DUKE ENERGY OHIO SMART GRID / GRID MODERNIZATION Don Schneider GM, Smart Grid Field Deployment May 24, 2012 FACTS ABOUT DUKE ENERGY 150+ years of service 4 million customers Fortune 500 $50 billion in
More informationDUKE ENERGY FLORIDA 2015 HURRICANE SEASON PREPARATION BRIEFING. Florida PSC Hurricane Preparedness Workshop March 18, 2015
Our hurricane restoration operational plan functioned well in 2004 and 2005. We continue to review it annually in an effort to make improvements. All lessons learned from past major storms and mid-level
More informationDisclaimer Executive Summary Introduction Overall Application of Attachment Generation Transmission...
CIP-002-4 Cyber Security Critical Cyber Asset Identification Rationale and Implementation Reference Document September, 2010 Table of Contents TABLE OF CONTENts Disclaimer... 3 Executive Summary... 4 Introduction...
More informationMinnesota Hosting Capacity Analysis
Minnesota Hosting Capacity Analysis MIPSYCON November 8, 2017 Chris Punt, P.E. Outline What is Hosting Capacity? Background DRIVE Results Visualization Accuracy Timeline Next Steps 2 What is Hosting Capacity?
More informationXXXXX XXXX Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation XXXXX XXXX Wind Generation Project XXXX XXXXX XXXXXXX Co., Inc. Interconnection System Impact Study Final Report Prepared By Arizona Public Service Company
More informationRFP Attachment 13. January 2010
PacifiCorp Transmission Technical Workshop RFP Attachment 13 January 2010 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated t dresource Plan Attachment 13 Point of Receipt
More informationPreliminary 2010 Revenue Requirements. Appendix D. O&M Savings Report
O&M Savings Report 0 0 Implementation of different projects within the capital plan can result in an increase, decrease or have little to no effect on operating costs depending on the nature of the work
More informationQ44 Generation Interconnection
A subsidiary of Pinnacle West Capital Corporation Q44 Generation Interconnection Interconnection Facilities Study APS Contract No. 52129 By Arizona Public Service Company Transmission Planning August 19,
More informationWORKPAPERS TO PREPARED DIRECT TESTIMONY OF RAJAN AGARWAL ON BEHALF OF SOUTHERN CALIFORNIA GAS COMPANY
Application of Southern California Gas Company for authority to update its gas revenue requirement and base rates effective on January 1, 2012. (U904G) Application No. 10-12- Exhibit No.: (SCG-36-WP) WORKPAPERS
More information345kV Transmission Line Thermal Uprating Using Connector Shunts
345kV Transmission Line Thermal Uprating Using Connector Shunts Douglas P. Harms, P.E. Sr. Consulting Engineer Transmission Engineering CenterPoint Energy (Ret.) Presented At The 46 th Annual Transmission
More informationipcgrid 2015 March 26, 2015 David Roop Director Electric Transmission Operations Dominion Virginia Power
Substation Security and Resiliency Update on Accomplishments thus far ipcgrid 2015 March 26, 2015 David Roop Director Electric Transmission Operations Dominion Virginia Power Dominion Profile Leading provider
More informationDecision D ATCO Electric Ltd. Crystal Lake 722S Substation Telecommunications Tower Replacement
Decision 21617-D01-2016 Crystal Lake 722S Substation October 5, 2016 Alberta Utilities Commission Decision 21617-D01-2016 Crystal Lake 722S Substation Proceeding 21617 Application 21617-A001 October 5,
More informationQuébec Interconnection Approach to BES
Québec Interconnection Approach to BES Placer une photo ici s il y a lieu NPCC Governmental/Regulatory Affairs Advisory Group Sylvain Clermont November 27, 2012 Introduction: HQT Our mission HQT operates
More informationGeomagnetic Disturbances
Geomagnetic Disturbances Managing Risk to the North American Power Grid Mark Olson, Reliability Standards Developer Worcester Polytechnic Institute Energy Symposium September 25, 2013 About NERC The North
More informationGeneration Interconnection Feasibility Study Report
Project #169 Generation Interconnection Feasibility Study Report 7/2/2014 Regional Electric Transmission Planning TABLE OF CONTENTS Executive Summary... 3 Generator and Interconnection Data... 5 Study
More informationWashington City. September Capital Facilities Plan- Electrical
Washington City Capital Facilities Plan- Electrical September 2007 Intermountain Consumer Professional Engineers, Inc. 1145 East South Union Avenue Midvale, Utah 84047 (801) 255-1111 TABLE OF CONTENTS
More informationQuarter 3, 2007 (2007Q3) Generation Deliverability Assessment Study Plan
Quarter 3, (Q3) Generation Deliverability Assessment Study Plan Background and Purpose of Study Phases I & II Generation and Import Deliverability Studies were completed that established the deliverability
More informationCollector System Design Considerations for Wind Farms. Sean Carr Ernst Camm S&C Electric Co.
Collector System Design Considerations for Wind Farms Sean Carr Ernst Camm S&C Electric Co. 1 Overview Challenges in wind farm collector systems Design considerations for collector systems Summary The
More informationPacifiCorp Transmission Technical Workshop
PacifiCorp Transmission Technical Workshop RFP Attachment 20 February 22, 2012 Presented by PacifiCorp Transmission PacifiCorp Transmission Update Integrated Resource Plan Attachment 20 Point of Receipt
More informationA Data Approach to Advanced Distribution Management Systems. L. WILKE, B. WALL POWER Engineers USA
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2017 Grid of the Future Symposium A Data Approach to Advanced Distribution Management Systems L. WILKE, B. WALL POWER
More information